Commercial Crew Program

The Commercial Crew Program (CCP) is a NASA initiative established in 2010 to develop and certify U.S. commercial vehicles for transporting astronauts to and from the International Space Station (ISS), restoring domestic human spaceflight capabilities following the retirement of the Space Shuttle program in 2011. The program employs fixed-price contracts to encourage innovation and cost efficiency, awarding development agreements in 2012 to Boeing and SpaceX for their respective Starliner and Crew Dragon spacecraft systems. Key achievements include SpaceX's successful certification of Crew Dragon as the first human-rated commercial spacecraft in November 2020, enabling operational missions such as Crew-1 later that year and subsequent rotations that have carried over a dozen NASA astronauts and international partners to the ISS. In contrast, Boeing's Starliner program has encountered significant technical challenges, including software failures during its 2019 uncrewed test flight and helium leaks with thruster malfunctions during its 2024 crewed debut, resulting in delays and the safe return of its test astronauts via a SpaceX vehicle in 2025. These issues have led to Boeing incurring over $2 billion in losses on the fixed-price contract, highlighting disparities in execution between the contractors. The program's defining characteristic is its shift toward public-private partnerships, which have reduced NASA's dependency on foreign launch services like Russia's Soyuz—previously costing up to $90 million per seat—and lowered per-seat costs to the ISS to around $55 million via SpaceX flights, demonstrating the viability of commercial approaches in human spaceflight. Despite Boeing's setbacks, CCP has facilitated 10 crewed missions by mid-2025, sustaining U.S. leadership in low-Earth orbit access while paving the way for future expansions involving additional providers.

Historical Context and Rationale

Origins in Post-Shuttle Era

The Space Shuttle program's final mission, STS-135, launched on July 8, 2011, and landed on July 21, 2011, concluding three decades of operations and leaving the United States without a domestic crewed launch capability to the International Space Station (ISS). This retirement, planned since President George W. Bush's 2004 Vision for Space Exploration but delayed due to safety issues following the Columbia disaster, resulted in a multi-year gap in independent U.S. access to the ISS, which NASA had significantly funded and assembled using the Shuttle fleet. In the immediate aftermath, NASA contracted with Roscosmos for Soyuz seats to transport its astronauts, with costs per seat rising from about $51 million under a 2010 agreement to $90 million by 2020, totaling over $4 billion for the period spanning 2011 to 2020. This arrangement exposed strategic risks, including geopolitical tensions and supply chain dependencies on Russia, which controlled the sole reliable crewed transport option during the gap. The escalating prices and limited seat availability—typically four per Soyuz flight—constrained NASA's ISS crew rotation schedules and research operations, underscoring the need for diversified, cost-competitive alternatives. To mitigate these vulnerabilities and reestablish U.S.-based crewed missions, NASA formalized the Commercial Crew Program (CCP) in March 2010, shortly before the Shuttle's full retirement, as a pivot from the canceled Constellation program toward fixed-price contracts with private firms. The program's core objective was to develop safe, reliable commercial systems for transporting NASA astronauts to and from the ISS, reducing long-term costs through competition and innovation rather than in-house development. Initial efforts under Commercial Crew Development Round 1 (CCDev1), funded partly by the American Recovery and Reinvestment Act, awarded non-competitive Space Act Agreements totaling $50 million to five companies in February 2010 for early design and risk-reduction work. This approach aimed to end foreign dependency by 2017, though delays extended the timeline, while fostering a sustainable commercial ecosystem for low Earth orbit access.

Strategic Objectives and Economic Justification

The Commercial Crew Program was initiated in 2010 to restore the United States' independent capability for transporting astronauts to and from the International Space Station following the retirement of the Space Shuttle fleet in 2011, thereby ending reliance on Russian Soyuz spacecraft for crew access. This dependency had arisen due to the absence of a domestic human-rated launch system post-Shuttle, compelling NASA to procure seats on Soyuz at escalating prices that reached approximately $86 million per astronaut by 2019. The program's core strategic objective was to certify commercially developed and operated crew vehicles meeting NASA's safety and reliability standards, enabling routine, on-demand missions from U.S. soil while fostering a competitive private sector ecosystem for low-Earth orbit transportation. Economically, the program was justified as a means to achieve long-term cost reductions compared to foreign procurement, with NASA estimating operational seat prices for certified vehicles at $55–$67 million for SpaceX's Crew Dragon and $91–$99 million for Boeing's Starliner, versus Soyuz's $80–$90 million average per seat across 71 missions from 2006 to 2020. Initial development funding—totaling about $6.8 billion across SpaceX ($2.6 billion) and Boeing ($4.2 billion) contracts for design, testing, and certification—represented an upfront investment to displace recurring Soyuz expenditures, which exceeded $4 billion for NASA alone between 2011 and 2020. By leveraging fixed-price contracts and private innovation, the approach aimed to lower marginal costs through reusability and economies of scale, while generating broader economic multipliers including job creation and supply chain stimulation across 42 states. Although Boeing's overruns increased its effective development costs, SpaceX's delivery enabled NASA to realize per-seat savings relative to Soyuz by 2020, supporting sustained ISS operations without geopolitical vulnerabilities.

Program Development

Commercial Crew Development Phases

The development of the Commercial Crew Program progressed through four primary phases, leveraging competitive Space Act Agreements and fixed-price contracts to mature technologies from subsystem-level innovations to fully certified crew transportation systems. These phases—Commercial Crew Development Rounds 1 and 2 (CCDev1 and CCDev2), Commercial Crew Integrated Capability (CCiCap), and Commercial Crew Transportation Capability (CCtCap)—emphasized milestone-based funding, risk reduction, and iterative testing to enable reliable U.S.-based human spaceflight to the International Space Station (ISS). CCDev1, launched in February 2010 with $50 million from American Recovery and Reinvestment Act funds, awarded Space Act Agreements to five companies for early-stage research and design of critical subsystems, including launch abort systems, environmental controls, and propulsion elements, without mandating full vehicle integration. Boeing received $18 million, Sierra Nevada Corporation $20 million, Blue Origin $3.7 million, Paragon Space Development Corporation $1.4 million, and United Launch Alliance $6.7 million; the focus was on concept validation and technology maturation to inform subsequent efforts. CCDev2, initiated in April 2011 with approximately $269.6 million (plus $46.2 million in additional milestones), expanded to funded agreements with four companies—Boeing ($92.3 million), Sierra Nevada ($80 million), SpaceX ($75 million), and Blue Origin ($22 million)—alongside unfunded partners like ATK, Excalibur Almaz Inc., and United Launch Alliance. Objectives centered on demonstrating integrated capabilities, such as pad abort tests (e.g., SpaceX's successful test on May 24, 2012) and launch vehicle compatibility assessments, to bridge toward operational systems. The CCiCap phase, awarded on August 3, 2012, provided $1.1 billion in milestone-based funding to Boeing ($460 million), SpaceX ($440 million), and Sierra Nevada ($212.5 million) for end-to-end design, assembly, testing, and verification of integrated crew vehicles and launch systems meeting NASA safety standards. Key milestones included critical design reviews (achieved by Boeing in 2015 and SpaceX in 2014) and subscale demonstrations, such as SpaceX's integrated pad abort test in November 2012, advancing vehicles toward flight readiness while allowing NASA oversight on human-rating requirements. CCtCap, selected on September 16, 2014, issued fixed-price contracts totaling $6.8 billion—$4.2 billion to Boeing for Starliner and $2.6 billion to SpaceX for Crew Dragon—to finalize development, execute certification test flights, and deliver operational ISS crew rotations. Excluding Sierra Nevada, which pivoted Dream Chaser to cargo applications, this phase required uncrewed and crewed test missions, software validation, and anomaly resolutions; SpaceX completed certification on November 10, 2020, after Demo-2's success on May 30, 2020, whereas Boeing's process extended beyond initial 2017 targets due to propulsion and software issues in its 2019 uncrewed Orbital Flight Test and 2024 Crew Flight Test.

Contract Selection and Funding Allocation

The Commercial Crew Program's contract selection process began with early competitive funding rounds under the Commercial Crew Development (CCDev) initiative to foster partial spacecraft and launch system technologies. In February 2010, NASA awarded $50 million in CCDev1 grants to five companies—Boeing, Sierra Nevada Corporation, SpaceDev (later acquired by Sierra Nevada), United Launch Alliance, and Blue Origin—for concept studies and component demonstrations, selected via unsolicited proposals emphasizing innovation and risk reduction without full peer review competition. This was followed by CCDev2 in April 2011, where $269.3 million was allocated through competitive bids to four firms: Boeing ($92.3 million for CST-100 capsule work), Sierra Nevada ($80 million for Dream Chaser spaceplane), SpaceX ($75 million for launch abort and crew systems), and Blue Origin ($22 million for propulsion and life support), prioritizing milestones tied to technical feasibility and cost control. Progressing to integrated system development, NASA launched the Commercial Crew Integrated Capability (CCiCap) phase in August 2012, awarding $1.1025 billion in Space Act Agreements to three competitors selected from seven proposals: Boeing ($460 million), SpaceX ($440 million), and Sierra Nevada ($212.5 million). Selection criteria included proposal maturity, integrated design coherence, risk mitigation plans, and alignment with NASA safety standards, with evaluations conducted by expert panels assessing technical, management, and cost elements; Sierra Nevada's lower funding reflected its novel lifting-body design's higher perceived integration risks compared to capsule architectures. These fixed-price milestones funded end-to-end system designs aimed at International Space Station transport, with additional $55 million in optional extensions awarded in 2013 to the same trio for further risk reduction. The pivotal Commercial Crew Transportation Capability (CCtCap) contracts, announced on September 16, 2014, marked the program's shift to certification and operational funding, with NASA selecting Boeing and SpaceX from CCiCap survivors (Sierra Nevada's proposal was disqualified for failing to demonstrate full operational capability under revised requirements). These firm-fixed-price contracts totaled $6.8 billion—Boeing receiving $4.2 billion and SpaceX $2.6 billion—for developing, certifying, and flying up to two crewed test flights plus six operational missions each to the International Space Station, including spacecraft, launch vehicles, and ground systems. The source selection process, detailed in NASA's public statement, weighted non-cost factors (technical approach, management, and past performance) at 70% and most probable cost at 30%, rating Boeing "excellent" in crew module design due to its heritage systems while noting SpaceX's advantages in lower cost and Falcon 9 reusability potential, though with risks in novel abort mechanisms; this led to Boeing's higher allocation to account for its diversified supplier base and established aerospace experience, ensuring program redundancy against single-provider failure. Subsequent modifications, such as 2022 additions for SpaceX extending through 2030, raised its total to approximately $4.9 billion to accommodate increased mission demand, reflecting performance-based adjustments rather than initial selection criteria.

Technical and Regulatory Milestones

The Commercial Crew Program (CCP) initiated its technical development with Commercial Crew Development Round 1 (CCDev1) on February 1, 2010, awarding approximately $50 million in Space Act Agreements to five companies—Boeing, Sierra Nevada Corporation, SpaceX, Paragon Space Development, and United Launch Alliance—for preliminary concept studies, component testing, and risk reduction activities aimed at human spaceflight capabilities. This phase focused on early engineering milestones such as launch vehicle assessments and life support prototypes, without full vehicle integration. CCDev2 followed on April 18, 2011, distributing $269.3 million to four recipients—Boeing ($92.3 million), Sierra Nevada ($80 million), SpaceX ($75 million), and Blue Origin ($22 million)—to advance subsystem demonstrations, including abort systems and crew interfaces. Subsequent phases emphasized integrated system maturation. On August 3, 2012, NASA selected Boeing ($460 million), SpaceX ($440 million), and Sierra Nevada ($212.5 million) for Commercial Crew Integrated Capability (CCiCap) agreements, requiring milestones like full-scale mockups, propulsion testing, and environmental simulations to validate end-to-end architectures. The program transitioned to certification-oriented efforts with Commercial Crew Transportation Capability (CCtCap) contracts awarded on September 16, 2014, to Boeing ($4.2 billion) and SpaceX ($2.6 billion), funding final development, verification testing, and up to six operational International Space Station missions each, contingent on achieving NASA-defined safety and performance criteria. Key technical milestones included abort system validations essential for crew safety. SpaceX conducted its Crew Dragon pad abort test on May 6, 2015, demonstrating SuperDraco engine ignition and capsule separation from the launch mount under nominal conditions. Boeing achieved a similar pad abort for Starliner on November 4, 2019, confirming service module jettison and main engine performance. SpaceX's in-flight abort test on January 19, 2020, verified Crew Dragon separation from a Falcon 9 during max-Q ascent, using the third-stage simulator at Cape Canaveral. Uncrewed orbital demonstrations followed: SpaceX's Demo-1 on March 2, 2019, successfully docked to the ISS and returned after 24 orbits, while Boeing's Orbital Flight Test-1 (OFT-1) on December 20, 2019, reached orbit but aborted docking due to software faults. Boeing's OFT-2 on May 22, 2022, completed autonomous docking and a week-long ISS stay, addressing prior anomalies. Crewed test flights marked advanced technical achievements. SpaceX's Demo-2 launched on May 30, 2020, with NASA astronauts Douglas Hurley and Robert Behnken, docking to the ISS the next day and splashing down on August 2 after 64 days, validating human-rating elements like life support and reentry dynamics. Boeing's Crew Flight Test (CFT) lifted off on June 5, 2024, aboard an Atlas V, docking to the ISS on June 6 despite helium leaks and thruster degradation, with astronauts Butch Wilmore and Suni Williams conducting extended evaluations; return was delayed for anomaly resolution, with the crew repatriated via SpaceX Crew-9 in February 2025. Regulatory milestones involved NASA certification for human spaceflight and Federal Aviation Administration (FAA) licensing for launch safety. NASA certified SpaceX's Crew Dragon, Falcon 9, and ground systems on November 10, 2020, following integrated reviews of Demo-2 data, abort tests, and risk assessments, enabling operational missions. Boeing's Starliner certification remains pending as of October 2025, hinging on CFT propulsion forensics and software validations. The FAA's role encompasses public safety oversight, issuing launch licenses under 14 CFR Part 450 for CCP vehicles from U.S. sites, requiring hazard analyses, flight termination systems, and continuity-of-operations demonstrations, while deferring vehicle airworthiness to NASA for government astronauts.

Crew Vehicles and Capabilities

SpaceX Crew Dragon Development and Features

SpaceX developed the Crew Dragon spacecraft under NASA's Commercial Crew Program to provide crew transportation to the International Space Station. On September 16, 2014, NASA awarded SpaceX a $2.6 billion fixed-price contract as part of the Commercial Crew Transportation Capability initiative, funding final design, testing, certification, and up to six operational missions. The program built on prior Commercial Crew Development phases, leveraging SpaceX's existing Dragon cargo vehicle experience. Key development milestones included the pad abort test on May 6, 2015, which successfully demonstrated the launch escape system from Launch Complex 40 at Cape Canaveral. This was followed by the uncrewed Demo-1 mission, launched March 2, 2019, which docked autonomously to the ISS and splashed down on March 8 after verifying systems. The in-flight abort test occurred January 19, 2020, using a Falcon 9 to simulate a launch anomaly, confirming the spacecraft's ability to separate mid-flight. The crewed Demo-2 mission launched May 30, 2020, marking the first U.S. crewed orbital flight from American soil since 2011, followed by NASA certification for operational use on November 10, 2020. Crew Dragon measures 8.1 meters in height and 4 meters in diameter, with a pressurized volume of 9.3 cubic meters accommodating up to seven passengers and a trunk providing 37 cubic meters of unpressurized storage. Propulsion consists of 16 Draco thrusters (90 lbf each) for orbital maneuvers, attitude control, and deorbit burns, plus eight SuperDraco engines (16,000 lbf each) enabling integrated abort capability from pad to orbit. The spacecraft features autonomous docking via the International Docking Adapter, solar arrays on the trunk for power generation, and a PICA-X heat shield for reentry. Life support systems include a closed-loop environmental control and a touchscreen-based interface for crew operations. Reentry culminates in parachute deployment for splashdown in the Atlantic or Gulf of Mexico, with the capsule designed for reusability up to 10 flights following refurbishment.

Boeing CST-100 Starliner Development and Features

Boeing initiated development of the CST-100 Starliner in 2010 as its entry for NASA's Commercial Crew Program, aiming to provide crew transportation to low-Earth orbit, including the International Space Station (ISS). The program built on earlier Commercial Crew Development (CCDev) phases starting in 2006, with Boeing receiving initial funding of $18 million in CCDev-2 to advance capsule concepts. In September 2014, NASA selected Boeing for the Commercial Crew Transportation Capability (CCtCap) contract, awarding $4.2 billion to complete design, development, testing, and certification of the Starliner system, including up to six operational missions following certification. This fixed-price contract emphasized reusability and integration with United Launch Alliance's Atlas V rocket for initial flights. Development progressed through milestones such as pad abort tests in November 2019 and the first Orbital Flight Test (OFT) on December 20, 2019, which launched successfully but failed to rendezvous with the ISS due to a software timing error that misloaded the flight software, causing excessive thruster firings and propellant depletion. A second uncrewed Orbital Flight Test-2 (OFT-2) in May 2022 successfully docked with the ISS after 4 days in orbit, validating autonomous docking and return capabilities, though minor helium leaks were noted post-mission. The Crew Flight Test (CFT), launched June 5, 2024, carried NASA astronauts Barry "Butch" Wilmore and Sunita "Suni" Williams aboard Starliner atop an Atlas V from Cape Canaveral, achieving docking with the ISS on June 6 despite pre-launch delays from thruster valve concerns. However, in-flight issues emerged, including five helium leaks in the propulsion system and degradation of 28 of 28 reaction control system thrusters, prompting extensive ground testing and raising concerns over safe return reliability. On August 24, 2024, NASA opted to return Starliner uncrewed on September 7, 2024, landing successfully in New Mexico, while the crew remained on the ISS and returned via SpaceX Crew-9 in February 2025. As of October 2025, certification for operational flights remains pending resolution of propulsion anomalies, with the first post-certification mission (Starliner-1) delayed to no earlier than early 2026, potentially starting uncrewed. The Starliner spacecraft features a crew module with capacity for up to seven astronauts or a mix of four crew and cargo for NASA missions, designed for reusability up to 10 times with a six-month refurbishment turnaround. Its conical structure, approximately 5 meters tall and 4.6 meters in diameter with a dry mass of 13,000 kg, employs a weldless aluminum-lithium alloy pressure vessel for enhanced manufacturability and strength. Key systems include a service module providing propulsion via Aerojet Rocketdyne OMAC thrusters for orbital maneuvers and attitude control, with hypergolic propellants and non-toxic abort motors in the launch escape system using hydroxyl-terminated polybutadiene fuel. Autonomous docking is enabled by a NASA Docking System compatible with the ISS, supported by a laser-vision-based star tracker for precise navigation. Entry and landing occur via parachutes and airbags on land in designated U.S. sites like White Sands, New Mexico, allowing rapid recovery compared to ocean splashdowns. Additional features encompass environmental control systems for up to 210 days docked to the ISS, wireless connectivity for crew tablets, and capacity to return up to 600 pounds of cargo. Despite these capabilities, recurrent propulsion challenges, particularly helium leaks tied to seal degradation under thermal stresses, have highlighted design vulnerabilities requiring iterative fixes.

Mission Operations

Test and Demonstration Flights

The Commercial Crew Program required contractors to conduct uncrewed and crewed test flights to verify spacecraft safety, autonomy, and integration with the International Space Station (ISS) prior to operational certification. SpaceX's Crew Dragon completed its demonstration flights successfully, enabling NASA certification for crewed operations, while Boeing's Starliner encountered technical setbacks across multiple tests, delaying its certification. SpaceX's first uncrewed demonstration flight, Crew Dragon Demo-1, launched on March 2, 2019, aboard a Falcon 9 rocket from Kennedy Space Center's Launch Complex 39A. The spacecraft autonomously docked to the ISS Harmony module's forward port on March 3, 2019, after a 24-hour rendezvous, and remained attached for five days to conduct systems checks, including environmental control and life support validation. Demo-1 undocked on March 8, 2019, and splashed down in the Atlantic Ocean off Florida's coast, marking the first U.S. commercial spacecraft docking to the ISS and confirming Crew Dragon's orbital maneuvering, reentry, and recovery capabilities without anomalies. The subsequent crewed test, Crew Dragon Demo-2, launched on May 30, 2020, carrying NASA astronauts Douglas Hurley and Robert Behnken—the first Americans to launch from U.S. soil since the Space Shuttle retirement in 2011. The mission achieved autonomous docking to the ISS on May 31, 2020, after 19 hours in orbit, with the crew performing hatch operations, in-flight tests of manual piloting via touchscreen interfaces, and emergency procedure simulations over a 31-day stay. Demo-2 concluded with a parachute-assisted splashdown in the Gulf of Mexico on August 2, 2020, 324 days after the prior U.S. crewed splashdown, validating human-rated systems including propulsion, avionics, and the SuperDraco abort mechanism (not triggered in flight). These successes led to NASA's approval of Crew Dragon for operational missions in October 2020. Boeing's initial uncrewed Orbital Flight Test-1 (OFT-1) of the CST-100 Starliner launched on December 20, 2019, via an Atlas V rocket from Cape Canaveral's Space Launch Complex 41. Software errors caused excessive thruster firings, depleting propellant and preventing rendezvous with the ISS; the mission was aborted after two orbits, with Starliner landing safely at White Sands Space Harbor, New Mexico, on December 22, 2019. Ground analysis identified clock desynchronization and guidance issues, necessitating design changes but confirming the spacecraft's structural integrity and abort systems. OFT-2, the remedial uncrewed test, lifted off on May 19, 2022, and successfully docked autonomously to the ISS's forward port on May 20, 2022, after a 24-hour pursuit. Over four days, the mission tested propulsion, solar arrays, and docking mechanisms, with Starliner carrying over 500 pounds of cargo; it undocked on May 25, 2022, and landed in the White Sands desert, validating fixes from OFT-1 and paving the way for crewed attempts despite minor helium leak observations later deemed non-critical. The crewed Crew Flight Test (CFT) launched on June 5, 2024, with NASA astronauts Barry "Butch" Wilmore and Sunita Williams aboard an Atlas V from Cape Canaveral. En route, five of 28 reaction control system thrusters failed due to overheating, compounded by helium leaks in the propulsion manifold, though the spacecraft docked manually to the ISS on June 6, 2024, after a backup thruster demonstration. Extensive ground testing recovered 27 thrusters, but unresolved risks to safe reentry prompted NASA on August 24, 2024, to return Starliner uncrewed, which splashed down off San Diego on September 6, 2024. Wilmore and Williams remained on the ISS, returning via SpaceX's Crew-9 in February 2025, as Boeing's certification remains pending further validation, with the next flight targeted no earlier than 2026 potentially uncrewed.
ContractorMissionLaunch DateCrewed/UncrewedKey Outcome
SpaceXCrew Dragon Demo-1March 2, 2019UncrewedSuccessful docking, systems validation, splashdown
SpaceXCrew Dragon Demo-2May 30, 2020Crewed (2 astronauts)Full mission success, human-rating achieved
BoeingStarliner OFT-1December 20, 2019UncrewedPartial failure (no ISS rendezvous), safe landing
BoeingStarliner OFT-2May 19, 2022UncrewedSuccessful docking and return
BoeingStarliner CFTJune 5, 2024Crewed (2 astronauts)Docking achieved; thruster/helium issues led to uncrewed return, crew evacuated

Operational Crew Rotation Missions

The operational crew rotation missions of NASA's Commercial Crew Program involve the routine transportation of astronaut crews to and from the International Space Station (ISS) using certified U.S. commercial spacecraft, restoring independent U.S. access to low Earth orbit after the retirement of the Space Shuttle in 2011. These missions primarily utilize SpaceX's Crew Dragon, which achieved operational status following Demo-2 in 2020, while Boeing's CST-100 Starliner has yet to complete certification for operational flights due to technical setbacks including propulsion anomalies during its June 2024 Crew Flight Test, resulting in its uncrewed return and delays pushing subsequent flights to no earlier than early 2026. SpaceX's Crew-1, launched on November 16, 2020, aboard a Falcon 9 rocket from Kennedy Space Center, marked the inaugural operational rotation, carrying NASA astronauts Michael S. Hopkins as commander, Victor J. Glover as pilot, Shannon Walker as mission specialist, and JAXA astronaut Soichi Noguchi; the crew docked to the ISS on November 17 and conducted a 167-day mission focused on scientific experiments and station operations before splashing down on May 2, 2021. Subsequent missions adhered to a similar profile, deploying four-person crews—including NASA astronauts, Roscosmos cosmonauts, and partners from JAXA, ESA, and others—for approximately six-month expeditions, with Crew Dragon's autonomous docking enabling efficient rotations and reusability reducing costs compared to prior Soyuz dependencies. By October 2025, SpaceX completed 11 operational missions (Crew-1 through Crew-11), with launches spanning November 2020 to August 1, 2025, when Crew-11 lifted off carrying NASA astronauts Zena Cardman and Michael Fincke, Roscosmos cosmonaut Oleg Platonov, and JAXA astronaut Takuya Onishi for Dragon's sixth reuse on a crewed flight. NASA contracted up to 14 total rotations across providers, but Boeing's six allocated slots remain unflown, prompting NASA to rely exclusively on SpaceX for 2025 rotations including Crew-10 on March 14, 2025. All SpaceX missions achieved 100% success in launch, docking, and return, supporting over 1,000 hours of crew time for microgravity research annually.
MissionLaunch DateKey Crew MembersMission Duration (approx.)
Crew-1November 16, 2020Michael Hopkins (NASA), Victor Glover (NASA)167 days
Crew-10March 14, 2025Anne McClain (NASA), Nichole Ayers (NASA)180 days
Crew-11August 1, 2025Zena Cardman (NASA), Michael Fincke (NASA)180 days

Mission Performance Data and Reliability Metrics

SpaceX's Crew Dragon has demonstrated high reliability in the Commercial Crew Program, completing 11 crewed missions to the International Space Station (ISS) from Crew-1 in November 2020 to Crew-11 in August 2025, with all achieving successful launches, autonomous dockings, extended stays averaging six months, and safe splashdown returns via parachutes off Florida's coast. No mission has experienced critical failures compromising crew safety, yielding a 100% success rate for primary objectives including crew transport and vehicle reusability, where capsules have flown multiple times post-refurbishment. Boeing's CST-100 Starliner, in contrast, has recorded limited performance data from its Crew Flight Test launched June 5, 2024, which reached the ISS but encountered multiple helium leaks in the propulsion system and five of 28 reaction control thrusters failing to perform nominally during flight, leading NASA to return the vehicle uncrewed on September 7, 2024, while the two astronauts remained aboard the ISS and returned via SpaceX Crew-9 in February 2025. The uncrewed Orbital Flight Test-2 in May 2022 succeeded in docking and return, but prior Orbital Flight Test in December 2019 aborted due to software errors preventing docking. As of October 2025, Starliner lacks certification for operational missions, with no crew rotation flights completed and ongoing reviews of propulsion reliability delaying future tests potentially to 2026.
ProviderCrewed Missions CompletedSuccess Rate (Primary Objectives)Notable AnomaliesCrew Transports (One-Way)
SpaceX Crew Dragon11 (plus Demo-2 certification)100%Minor, non-critical (e.g., occasional sensor alerts resolved in-flight)44+ astronauts to/from ISS
Boeing Starliner1 (Crew Flight Test)Partial (docking achieved; return uncrewed)Propulsion leaks, thruster failures2 astronauts (outbound only; return via alternate vehicle)
Overall program metrics highlight Crew Dragon's role in enabling reliable U.S. crew access, transporting over 40 astronauts without loss of life or mission, contrasting with Starliner's developmental hurdles that have not yet yielded operational reliability equivalent to SpaceX's demonstrated track record. NASA reports no performance anomalies in SpaceX missions rising to the level of crew risk, affirming certification standards met for continued operations, while Boeing's data informs iterative fixes but underscores higher anomaly rates in testing phases.

Achievements and Broader Impacts

Operational Successes and Cost Efficiencies

SpaceX's Crew Dragon has enabled the Commercial Crew Program's core operational successes, with the vehicle completing eight NASA-contracted rotational missions from Crew-1 in November 2020 to Crew-8 in March 2024, safely transporting 32 astronauts to the International Space Station (ISS) and returning them without mission failures. These flights achieved 100% success in primary objectives, including rendezvous, docking, and safe reentry, leveraging Falcon 9's overall launch reliability exceeding 99% across hundreds of missions. By October 2025, additional missions like Crew-9 have further demonstrated the system's maturity, delivering consistent crew rotations and reducing ISS crew gaps previously filled by Russian Soyuz spacecraft. Boeing's CST-100 Starliner has contributed partial operational milestones, including a successful uncrewed Orbital Flight Test-2 in May 2022 that verified autonomous docking and propulsion systems, paving the way for crewed attempts. The June 2024 Crew Flight Test achieved launch and initial ISS docking but faced thruster malfunctions and helium leaks, resulting in an uncrewed return and crew repatriation via Crew Dragon; however, it validated key systems like the crew interface and landing capabilities. These efforts, combined with SpaceX's track record, have certified U.S. domestic crew transport, ending reliance on foreign providers for routine ISS access. The program has yielded significant cost efficiencies, with Crew Dragon seats priced at $55-67 million each under NASA's contracts, compared to $80-90 million per Soyuz seat prior to 2020. This equates to approximately $22 million in savings per astronaut or $88 million per four-person mission, amortizing the program's $6.8 billion development investment over dozens of flights. By avoiding over $4 billion in projected Soyuz payments from 2011-2020 alone, the initiative has delivered lower lifecycle costs than the Space Shuttle's $170 million per seat, marking NASA's most economical human spaceflight effort in decades.
Transportation SystemApproximate Cost per Seat (USD millions)
Soyuz (pre-2020)80-90
Crew Dragon55-67
Starliner (projected)91-99

Contributions to Private Sector Innovation

The Commercial Crew Program advanced private sector innovation by employing competitive fixed-price contracts that shifted development risks to industry partners, compelling efficient engineering and novel solutions to meet stringent safety and performance requirements. In September 2014, NASA awarded $6.8 billion in firm-fixed-price contracts—$4.2 billion to Boeing for the CST-100 Starliner and $2.6 billion to SpaceX for the Crew Dragon—to fund certification of commercially owned and operated crew vehicles capable of transporting astronauts to the International Space Station. This model, building on prior Commercial Orbital Transportation Services successes, reduced NASA's direct oversight while leveraging private expertise for cost containment and technological breakthroughs. SpaceX's Crew Dragon exemplified these incentives through the integration of SuperDraco engines for launch-escape capability from the pad or orbit, Draco thrusters for precise maneuvering, and a heat shield design enabling reusability across multiple missions. The vehicle's autonomous docking system and touchscreen avionics further innovated human-spacecraft interfaces, facilitating the first U.S. commercial crewed launch on May 30, 2020, and subsequent operational flights that demonstrated high reliability with over a dozen missions by 2025. These developments extended beyond NASA needs, supporting private ventures like the Inspiration4 all-civilian orbital flight in September 2021. Boeing's Starliner contributed advancements in reusable capsule construction, including a weldless structure from aluminum-lithium alloy for up to 10 flights and a service module with non-toxic propulsion for simplified ground handling. Innovations such as automated flight software and unified avionics aimed to enhance crew autonomy, though realization was delayed until the crewed test flight on June 5, 2024. By fostering these proprietary technologies, the program generated estimated savings of $20 billion to $30 billion for NASA relative to sustaining Space Shuttle operations or Soyuz dependencies, while catalyzing a commercial ecosystem that has drawn billions in private capital and enabled independent human spaceflight operations. The fixed-price framework proved instrumental in prioritizing verifiable performance over traditional cost-plus inefficiencies, yielding a scalable U.S. crew transport capability independent of government procurement cycles.

Reduction in Foreign Dependencies

Following the retirement of the Space Shuttle program in 2011, the United States lacked independent human spaceflight capability to the International Space Station (ISS), necessitating reliance on the Russian Soyuz spacecraft for transporting NASA astronauts. From 2011 to 2020, NASA procured Soyuz seats from Roscosmos at costs escalating from approximately $76 million per seat in 2015 to over $90 million per seat by 2020, with the final purchase in May 2020 totaling $90.25 million for a seat on the Soyuz MS-17 mission launched in October 2020. This arrangement exposed the U.S. to supply chain vulnerabilities and geopolitical risks, as Soyuz operations were controlled by a single foreign provider amid strained U.S.-Russia relations following events such as the 2014 annexation of Crimea. The Commercial Crew Program mitigated this dependency by certifying U.S.-developed vehicles for operational ISS crew transport, with SpaceX's Crew Dragon achieving NASA certification on November 10, 2020, enabling its inaugural operational mission, Crew-1, which launched on November 16, 2020, from Kennedy Space Center. This certification allowed NASA to forgo additional Soyuz seat purchases beyond pre-existing contracts, effectively ending routine reliance on Russian crew vehicles by late 2020 and restoring domestic launch sovereignty for the first time since 2011. Boeing's Starliner, though delayed, further diversified options upon its eventual crewed certification, but Crew Dragon's reliability—evidenced by multiple successful rotations—primarily fulfilled the program's goal of redundancy without foreign intermediation. This shift enhanced U.S. strategic autonomy, reducing exposure to potential disruptions in Russian launch manifests or international sanctions, while enabling more flexible mission scheduling aligned with ISS needs rather than foreign timetables. By 2025, all NASA crew rotations to the ISS have utilized Commercial Crew vehicles, with over a dozen Crew Dragon missions completing the transition and obviating Soyuz dependency for American personnel.

Criticisms and Challenges

Development Delays and Technical Failures

The Commercial Crew Program, initiated in 2010 with awards to Boeing and SpaceX under the Commercial Crew Development rounds, targeted operational crewed missions to the International Space Station by 2017 but encountered persistent delays due to technical hurdles and certification requirements. By 2018, both contractors had slipped schedules, prompting NASA to extend purchases of Soyuz seats through at least Soyuz MS-17 in 2020 to maintain U.S. presence on the station. A 2016 NASA Inspector General report highlighted ongoing challenges, including integration issues and testing shortfalls, that risked further postponing first routine flights. These setbacks extended U.S. reliance on Russian vehicles for astronaut transport until SpaceX's Crew Dragon Demo-2 in May 2020. SpaceX's Crew Dragon development included a critical anomaly on April 20, 2019, during a static fire test of the integrated SuperDraco abort system, where an explosion destroyed the capsule due to a leaky check valve permitting nitrogen tetroxide oxidizer into the helium-pressurized thruster lines, causing hypergolic ignition. This incident, occurring ahead of planned crewed certification, necessitated redesigns to the abort propulsion architecture, including removal of the composite overwrapped pressure vessels and enhanced ground testing protocols, which delayed NASA's human-rating process by months. Despite this, SpaceX progressed to an uncrewed Demo-1 mission in November 2019 and achieved crewed flight certification post-Demo-2 in 2020, demonstrating resilience through rapid iteration. Earlier concerns, such as parachute drop test failures in 2015-2016, were also resolved via material upgrades without derailing the overall timeline significantly. Boeing's CST-100 Starliner program suffered more extensive delays and failures, starting with the uncrewed Orbital Flight Test-1 (OFT-1) on December 20, 2019, which aborted rendezvous with the ISS due to a mission elapsed time clock desynchronization—caused by a ground software upload error—leading to erroneous thruster firings that depleted propellant and triggered safe mode. Subsequent analysis identified 13 software defects, including uninitialized variables and inadequate mission time management, stemming from flawed Boeing software engineering practices lacking rigorous end-to-end integration testing. A remedial uncrewed OFT-2 flew successfully on May 22, 2022, but the Crew Flight Test (CFT), originally slated for 2023, faced repeated postponements from parachute load issues, valve malfunctions, and wiring harness concerns, launching only on June 5, 2024. During CFT, five of 28 reaction control thrusters failed on ascent due to degradation from propellant exposure, compounded by helium leaks in the service module's propulsion tanks, which eroded seals and prompted thruster overheating; these issues extended the mission beyond eight months, with NASA opting to return astronauts Wilmore and Williams via SpaceX Crew-9 in February 2025 rather than risk deorbit uncertainties. As of mid-2025, Starliner's certification remains pending, with the next operational flight (Starliner-1) delayed to at least late 2025 or beyond pending propulsion system fixes and independent reviews, underscoring systemic challenges in Boeing's approach compared to SpaceX's iterative successes. These failures have amplified program risks, including potential gaps in ISS crew rotation capacity if unresolved.

Cost Overruns and Contractor Accountability

The Commercial Crew Program's fixed-price contracts were designed to shift financial risk to contractors, incentivizing efficiency and innovation, yet Boeing's development of the CST-100 Starliner resulted in substantial overruns exceeding $2 billion in company-absorbed losses by early 2025, while SpaceX delivered the Crew Dragon within its allocated budget. In 2014, NASA awarded Boeing $4.2 billion for Starliner development and certification under the CCtCap phase, compared to $2.6 billion for SpaceX's Crew Dragon; Boeing's escalating costs stemmed from repeated technical setbacks, including software anomalies, propulsion system failures during uncrewed tests, and parachute redesigns, leading to a $523 million loss in 2024 alone and an additional $250 million charge in October 2024. These overruns forced Boeing to cover approximately $1.5 billion out-of-pocket beyond NASA's contributions, highlighting inefficiencies in its traditional engineering processes amid fixed-price constraints. In contrast, SpaceX's total expenditures for equivalent development and initial operational scopes remained aligned with NASA's roughly $3.1 billion in contracts, enabling Crew Dragon's certification and first crewed flight in 2020 without reported overruns, as the company's iterative design and in-house manufacturing reduced costs through reusable technologies and rapid prototyping. NASA's Office of Inspector General (OIG) audits from 2018 onward identified systemic risks in contractor management, noting that Boeing's delays—pushing Starliner's crewed debut from 2017 to 2024—amplified program-wide expenses, including over $3 billion in Soyuz seat purchases to sustain ISS access, though SpaceX's reliability mitigated some impacts post-2020. Contractor accountability under CCP emphasized milestone-based payments and penalties for delays, with Boeing facing withheld funds and self-funded fixes, yet OIG reports critiqued NASA's oversight for insufficient early enforcement of requirements, potentially allowing Boeing's overruns to persist without mid-course restructuring; GAO assessments of broader NASA projects echoed this, documenting cumulative human spaceflight cost growth exceeding $500 million annually in recent years, though CCP-specific fixed-price mechanisms ultimately protected taxpayer funds from direct supplementation. Boeing's accountability culminated in internal restructuring efforts by 2025 to curb further Starliner losses, signaling partial success of the model's risk-transfer principle despite uneven outcomes between incumbents and disruptors.

Political and Bureaucratic Influences

The Commercial Crew Program originated from policy shifts under the Obama administration, which in 2010 canceled NASA's Constellation program following recommendations from the Augustine Committee review, redirecting resources toward commercially developed crew transportation to the International Space Station as a more cost-effective alternative to government-led development. This approach aimed to leverage private sector innovation but encountered immediate resistance from Congress, where bipartisan concerns over job losses in traditional aerospace hubs and skepticism toward unproven commercial entities led to funding battles; for instance, appropriations for fiscal years 2011-2013 fell short of requested levels, delaying program milestones. Congressional influence prominently shaped contractor selections and allocations, with lawmakers prioritizing geographic and industrial base considerations over pure cost efficiency. In September 2014, NASA awarded fixed-price contracts despite Boeing's bid exceeding SpaceX's by approximately 60% ($4.2 billion versus $2.6 billion), a decision internal documents reveal was nearly singular to Boeing before intervention ensured dual providers to mitigate perceived risks of reliance on a single upstart firm and to sustain employment in Boeing's operational states like Florida and Alabama. This reflected broader political dynamics favoring legacy contractors, whose lobbying efforts—Boeing spent millions annually on advocacy—helped secure support amid congressional directives to maintain competition and avoid "monopolies," even as evidence from cargo programs demonstrated commercial viability. Bureaucratic hurdles within NASA compounded these influences, as entrenched procurement cultures resistant to fixed-price models and rapid iteration imposed stringent certification requirements that extended development timelines. NASA's Inspector General reports from 2011 and 2016 highlighted ongoing challenges in transitioning oversight from traditional cost-plus paradigms, with program offices overburdened by dual-certification processes for Boeing's Starliner and SpaceX's Crew Dragon, leading to delays attributed to internal risk aversion rather than inherent technical infeasibility. Initial agency-wide opposition to commercial paradigms, documented in contemporaneous accounts, stemmed from institutional inertia favoring proven government-industry partnerships, though eventual successes validated the model's efficiency in reducing per-seat costs compared to prior shuttle operations.

Future Directions

Program Extensions and Certifications

NASA certified SpaceX's Crew Dragon spacecraft, along with its Falcon 9 launch vehicle and associated ground systems, for operational astronaut flights to the International Space Station on November 10, 2020, marking the first commercial human spaceflight system to achieve this status since the Space Shuttle program ended in 2011. This certification followed successful demonstration missions, including Demo-2 in May 2020, and encompassed rigorous reviews of design, testing, and safety data under the Commercial Crew Transportation Capability (CCtCap) contract. Initially approved for up to five reentries per capsule, SpaceX has been collaborating with NASA to extend certification to 15 reentries, with progress noted as of March 2024. Additionally, NASA and SpaceX are implementing program updates, such as shifting post-landing recovery operations for Crew Dragon missions from the East Coast to the West Coast to enhance efficiency and reduce logistical dependencies on weather patterns. Boeing's CST-100 Starliner has not yet achieved full operational certification as of October 2025, despite receiving a $4.2 billion CCtCap contract in 2014 parallel to SpaceX's award. The Crew Flight Test (CFT) mission launched on June 5, 2024, but encountered helium leaks and thruster malfunctions, leading NASA to return its astronauts via a SpaceX Crew Dragon on September 25, 2024, while the Starliner returned uncrewed on September 7, 2024. Post-CFT data reviews, ongoing as of March 2025, are assessing propulsion system reliability and software issues to determine certification viability, with NASA considering an additional uncrewed test flight before approving crewed operations. Boeing's capsules are designed for up to 10 reuses, but certification hinges on resolving these anomalies to meet NASA's safety standards. Program extensions include NASA's award of operational contracts under the Commercial Crew Crew Transportation Services (CCCTS) framework, with SpaceX receiving modifications for additional missions beyond initial certification flights; for instance, the agency planned Crew-10 for no earlier than March 2025 and Crew-11 for July 2025, reflecting sustained reliance on certified systems amid Boeing delays. In parallel, the Collaborations for Commercial Space Capabilities 2 (CCSC-2) Space Act Agreements, signed in 2023, extend partnerships with SpaceX to integrate Crew Dragon with emerging architectures like Starship for low-Earth orbit sustainability post-International Space Station deorbit in 2030. These agreements facilitate data sharing and capability enhancements without fixed-price commitments, aiming to transition commercial crew transport toward private space stations while maintaining NASA oversight for reliability.

Integration with Emerging Space Architectures

NASA's Commercial Crew Program (CCP) vehicles are positioned to serve as primary crew transporters to emerging commercial low Earth orbit (LEO) destinations following the planned deorbit of the International Space Station (ISS) in 2030. The agency's Commercial LEO Development (CLD) program supports the development of private space stations, including Axiom Space's planned free-flying Axiom Station, Sierra Space and Blue Origin's Orbital Reef, and Voyager Space and Airbus's Starlab, to sustain U.S. government and commercial activities in LEO without NASA-owned infrastructure. These architectures emphasize modular, commercially operated habitats compatible with the NASA Docking System (NDS), enabling seamless integration with CCP spacecraft like SpaceX's Crew Dragon and Boeing's Starliner, which incorporate NDS ports for automated docking. Under CLD guidelines, all spacecraft transporting NASA crew to or from commercial LEO destinations (CLDs) must utilize vehicles certified through the CCP, ensuring safety standards equivalent to ISS operations. SpaceX's Crew Dragon has already demonstrated this interoperability through private missions, such as Axiom Mission 4 (Ax-4) on June 26, 2025, which docked autonomously to the ISS's Harmony module after a 28-hour flight, carrying a four-person international crew for research and technology demonstrations. This capability positions Crew Dragon to ferry crews to Axiom's standalone station, initially planned as ISS-attached modules transitioning to independent operations by the mid-2020s, with NASA procuring up to two astronaut slots per CLD increment. Boeing's Starliner, despite certification delays from its June 2024 crew flight test—where thruster issues led to an uncrewed return on September 6, 2024—remains architected for similar NDS-compatible missions to commercial stations, supporting NASA's goal of redundant U.S. crew transport options. Integration extends to operational efficiencies, with CLD stations required to demonstrate crewed capability before 2030 via NASA-funded Space Act Agreements, including 30-day missions for four-person crews to validate life support, docking, and research payloads. This model mirrors CCP's fixed-price service contracts, allowing NASA to buy transportation and habitation as services rather than hardware, potentially reducing costs below the $3.1 billion annual ISS operations figure while fostering a competitive LEO economy. Challenges include aligning station readiness with CCP vehicle availability, as Boeing's operational debut lags SpaceX's nine successful ISS crew rotations by October 2025, but NDS standardization minimizes adapter needs across architectures. Future extensions may incorporate hybrid missions, such as using CCP vehicles for CLD cargo precursors or international partnerships, ensuring continuous human presence amid China's Tiangong station expansion.

References

  1. [1]
    [PDF] THE EVOLUTION OF THE NASA COMMERCIAL CREW PROGRAM ...
    The National Aeronautics and Space Administration. (NASA) established the Commercial Crew Program. (CCP) in March 2010 to facilitate the development of a United ...
  2. [2]
    Commercial Crew Program - Essentials - NASA
    NASA's Commercial Crew Program (CCP) was formed to facilitate the development of a US commercial crew space transportation capability.
  3. [3]
    NASA and SpaceX Complete Certification of First Human-Rated ...
    Nov 10, 2020 · NASA officially certifying the first commercial spacecraft system in history capable of transporting humans to and from the International Space Station.<|separator|>
  4. [4]
    NASA delays Crew-9 launch as it grapples with Starliner problems
    Aug 7, 2024 · NASA has delayed the launch of the next crew rotation mission to the ISS by a month as reviews when, or if, Boeing's Starliner can complete ...
  5. [5]
    Boeing has now lost $2B on Starliner, but still silent on future plans
    Feb 4, 2025 · Boeing announced Monday it lost $523 million on the Starliner crew capsule program last year, putting the aerospace company $2 billion in the red on its NASA ...
  6. [6]
    Commercial Crew Program Overview - NASA
    NASA's Commercial Crew Program is delivering on its goal of safe, reliable, and cost-effective human transportation to and from the International Space Station.
  7. [7]
    Commercial Crew Program - NASA
    NASA's Commercial Crew Program is delivering on its goal of safe, reliable, and cost-effective human transportation to and from the International Space Station.Learn More about Commercial... · Meet Our Team · Essentials · SpaceX Crew-10
  8. [8]
    10 Years Ago: STS-135, the Space Shuttle's Grand Finale - NASA
    Jul 8, 2021 · The successful completion of the 12-day mission to the station brought an end to the 30-year space shuttle program. sts_135_1_crew_patch ...
  9. [9]
    [PDF] NASA's Management of the International Space Station and Efforts ...
    Nov 30, 2021 · NASA used the Space Shuttle in conjunction with the Russian Soyuz for crew transportation until the Shuttle's retirement in 2011, then began ...
  10. [10]
    NASA to pay Russia $90 million for a Soyuz seat on a crew launch ...
    May 13, 2020 · NASA to pay Russia $90 million for a Soyuz seat on a crew launch this fall · Russia&#039;s Progress 93 cargo spacecraft approaches the ...
  11. [11]
    The Last Soyuz - NASA Ends Reliance On Russia With Final Launch ...
    Apr 9, 2020 · Since the Space Shuttle was retired in July 2011, NASA has bought flights for its astronauts on Soyuz at a cost of $86 million per seat. In ...
  12. [12]
    NASA's Commercial Crew Program Progressing for Future of U.S. ...
    Aug 3, 2012 · NASA's Commercial Crew Development Round 1 (CCDev1) began in 2010 using American Recovery and Reinvestment funds. During that phase, NASA ...Missing: establishment | Show results with:establishment
  13. [13]
    [PDF] IG-20-005 - NASA's Management of Crew Transportation to the ...
    Nov 14, 2019 · 2 In response to the Act, NASA created the. Commercial Crew and Cargo Program Office in 2005 and then later created a separate Commercial Crew.
  14. [14]
    [PDF] NASA Commercial Crew Program: Continued Delays Pose Risks for ...
    Jan 17, 2018 · NASA's Commercial Crew Program is intended to end this dependency by facilitating the commercial development of a crew transportation system ...Missing: rationale | Show results with:rationale
  15. [15]
    NASA cost to fly astronauts with SpaceX, Boeing and Russian Soyuz
    Nov 19, 2019 · In the meantime, the cost per astronaut for flying with the Russians has steadily climbed, with the most recent contracts coming out to $86 ...
  16. [16]
    Commercial Crew Program - Performance.gov
    The Commercial Crew Program facilitates the development of safe, reliable, and cost-effective human space transportation by the US commercial industry.
  17. [17]
    NASA's Commercial Crew Program is a Fantastic Deal
    May 19, 2020 · NASA's commercial crew program is the agency's lowest-cost human spacecraft development effort in nearly 60 years.
  18. [18]
    Here's How Much NASA Is Paying Per Seat on SpaceX's Crew ...
    Nov 16, 2019 · To put those costs into perspective: NASA currently pays about $86 million for each seat aboard Russia's three-person Soyuz spacecraft, which ...<|separator|>
  19. [19]
    [PDF] Commercial Crew Program - NASA
    NASA's Commercial Crew Program is delivering on its goal of safe, reliable, and cost- effective human transportation to and from the International Space ...
  20. [20]
    [PDF] Final Report - IG-16-028 - NASA's Commercial Crew Program
    Sep 1, 2016 · In response to the Act, NASA created the Commercial Crew and Cargo Program Office in 2005. The Agency created a separate Commercial Crew ...
  21. [21]
    NASA, Commercial Crew Partners Fund Additional Development ...
    Aug 15, 2013 · In their respective CCiCap SAAs, which were awarded in August 2012, NASA's partners listed optional milestones that could be exercised to ...
  22. [22]
    [PDF] GAO-17-137, NASA COMMERCIAL CREW PROGRAM
    Feb 16, 2017 · In 2014, NASA awarded two firm-fixed-price contracts to Boeing and. SpaceX with a combined total value up to $6.8 billion for the development of.
  23. [23]
    [PDF] Commercial Crew Integrated Capability (Announcement ... - NASA
    CCiCap will consist of a base period from award to no later than May 31, 2014, which will include detailed integrated system design and significant risk ...
  24. [24]
    NASA, Commercial Crew Partners Fund Additional Development ...
    Aug 15, 2013 · NASA plans to use fiscal year 2014 funding for the total government investment of $55 million. Funding these optional milestones does not alter ...
  25. [25]
    NASA Selects Boeing and SpaceX for Commercial Crew Contracts
    Sep 16, 2014 · NASA awarded contracts worth $6.8 billion to Boeing and SpaceX on Sept. 16 to develop commercial crew transportation systems.
  26. [26]
    [PDF] Source Selection Statement | NASA
    Phase 1 is completed. Phase 2, the Commercial Crew Transportation Capability Contract (CCtCap), was conducted as a full and open competition. Participation in ...
  27. [27]
    NASA Awards SpaceX More Crew Flights to Space Station
    Aug 31, 2022 · The period of performance runs through 2030 and brings the total CCtCap contract value with SpaceX to $4,927,306,350. The award follows the ...
  28. [28]
    NASA's CCiCAP Partners Have Diverse Design Approaches
    Aug 3, 2012 · NASA announced the three winners today: Boeing, $460 million; SpaceX, $440 million;and Sierra Nevada, $212.5 million. The awards are milestone- ...
  29. [29]
    NASA's Boeing Crew Flight Test Launch Milestones
    Jun 5, 2024 · Starliner will autonomously dock to the station on Thursday, June 6, and remain at the orbiting laboratory for about a week. Although Starliner ...
  30. [30]
    [PDF] faa licensing and the nasa commercial crew program
    Oct 5, 2018 · This paper will describe the challenges and successes to date of the FAA's role in the Commercial Crew Program as a regulator of public safety ...
  31. [31]
    Boeing And SpaceX Win $6.8 Billion In NASA Contracts - NPR
    Sep 16, 2014 · The total potential contract value is $4.2 billion for Boeing and $2.6 billion for SpaceX. The spacecraft will launch from Kennedy Space Center ...
  32. [32]
    SpaceX Targets May 6 for Pad Abort Test of New Crew Spacecraft
    Apr 30, 2015 · SpaceX now is targeting Wednesday, May 6, for a pad abort test of its Crew Dragon, a spacecraft under final development and certificationMissing: date | Show results with:date<|separator|>
  33. [33]
    SpaceX Crew Dragon Splashdown Marks Success of First NASA ...
    Mar 8, 2019 · SpaceX's Crew Dragon departed the International Space Station at 2:32 am EST Friday, March 8, 2019, and splashed down at 8:45 am in the Atlantic Ocean.
  34. [34]
    NASA Coverage of SpaceX Crew Dragon Launch Escape Test
    Jan 19, 2020 · SpaceX executes its in-flight abort test Jan. 19, 2020, with the Crew Dragon spacecraft launched atop a Falcon 9 rocket from KSC's Launch Pad 39 ...
  35. [35]
    SpaceX Successfully Launches NASA Astronauts Into Space
    May 31, 2020 · Elon Musk's rocket company, SpaceX, made history on Saturday, May 30, when its Crew Dragon capsule safely reached space carrying two NASA astronauts.
  36. [36]
    NASA formally certifies SpaceX's Crew Dragon for “operational ...
    Nov 10, 2020 · Stich said Tuesday that the Crew-1 astronauts are scheduled to return to Earth in April to cap a six-month expedition on the space station.
  37. [37]
    Dragon - SpaceX
    In addition to flying astronauts to space for NASA, SpaceX's Dragon spacecraft can also carry commercial astronauts to Earth orbit, the ISS or beyond. Learn ...Missing: development | Show results with:development
  38. [38]
    CST-100 Starliner - Boeing
    Paced for success. May 1, 2024. Meet Starliner's safety-focused Pad Team members who keep the spacecraft's liftoff from the launch pad on schedule.
  39. [39]
    Starliner CST-100 (Crew Space Transportation-100) - eoPortal
    Dec 23, 2019 · NASA's Commercial Crew Development(CCDev) program started in 2006 with the goal of establishing a US commercial crew space transportation ...
  40. [40]
    Boeing Starliner - National Space Centre
    Jun 6, 2024 · NASA and Boeing have a long and exciting history, and in 2014 NASA awarded Boeing $4.2 billion to develop the CST-100 Starliner, a reusable ...
  41. [41]
    NASA, Boeing Complete Starliner Uncrewed Flight Test to Space ...
    May 25, 2022 · Boeing's Orbital Flight Test-2 (OFT-2) is Starliner's second uncrewed flight test to the International Space Station as part of NASA's Commercial Crew Program.<|separator|>
  42. [42]
    NASA Decides to Bring Starliner Spacecraft Back to Earth Without ...
    Aug 24, 2024 · NASA will return Boeing's Starliner to Earth without astronauts Butch Wilmore and Suni Williams aboard the spacecraft, the agency announced Saturday.
  43. [43]
    'Doghouse' days of summer — Boeing's Starliner won't fly again until ...
    Jul 17, 2025 · NASA officials say they are now working toward the goal of launching Starliner again no sooner than early 2026.
  44. [44]
    NASA working to 'correct and rectify' Boeing Starliner issues after 1st ...
    Oct 26, 2024 · Boeing's Starliner had propulsion issues after launching on its first test mission with astronauts. Six weeks after the mission concluded, ...
  45. [45]
    CST-100 Starliner - Orbital Velocity
    Specifications. Dry mass: 13,000 kg. Height: 5.0 m. Width: 4.6 m. Max. crew size: 7. Orbital life: 210 days docked. Flight history. First flight: Orbital Flight ...
  46. [46]
    Boeing's Starliner – Advancing Innovative Technology - SpaceNews
    Oct 20, 2022 · Laser-vision star tracker, docking system, and desert landing proven as practical space applications of the future.
  47. [47]
    NASA's Boeing Starliner Mission Landing Criteria, Timeline
    Sep 5, 2024 · NASA and Boeing will use potential landing locations in the White Sands Missile Range, New Mexico; Willcox, Arizona; and Dugway Proving Ground, Utah.
  48. [48]
    NASA Astronauts Launch from America in Historic Test Flight of ...
    May 30, 2020 · The SpaceX Crew Dragon spacecraft is scheduled to dock to the space station at 10:29 a.m. Sunday, May 31. NASA Television and the agency's ...Missing: details | Show results with:details
  49. [49]
    NASA's Boeing Crew Flight Test
    Crew Flight Test Undocking and Return Timeline​​ View the planned mission events from undocking to landing for Boeing's Starliner spacecraft.
  50. [50]
    FAQ: NASA's Boeing Crew Flight Test Return Status
    Aug 20, 2024 · This flight test's goal is to demonstrate Starliner's ability to execute a six-month rotational mission to the space station. The test ...Missing: milestones | Show results with:milestones
  51. [51]
    What You Need to Know About NASA's SpaceX Crew-11 Mission
    Jul 18, 2025 · Overall, the Crew-11 mission is the 16th crewed Dragon flight to the space station, including Demo-2 in 2020 and 11 operational crew rotations ...
  52. [52]
    NASA's SpaceX Crew-1 Astronauts Headed to International Space ...
    Nov 16, 2020 · NASA's SpaceX Crew-1 mission is the first crew rotation mission of the SpaceX Crew Dragon spacecraft and Falcon 9 rocket to the International Space Station.
  53. [53]
    Crew-1 Astronauts Safely Splash Down After Space Station Mission
    May 2, 2021 · NASA's SpaceX Crew-1 mission launched Nov. 15, 2020, on a Falcon 9 rocket from the agency's Kennedy Space Center in Florida.Missing: details | Show results with:details
  54. [54]
    NASA's SpaceX Crew-11 Launches to International Space Station
    Aug 1, 2025 · During Dragon's flight, SpaceX will monitor a series of automatic spacecraft maneuvers from its mission control center in Hawthorne, California.
  55. [55]
    NASA's SpaceX Crew-10 Launches to International Space Station
    Mar 14, 2025 · During Dragon's flight, SpaceX will monitor a series of automatic spacecraft maneuvers from its mission control center in Hawthorne, California.
  56. [56]
    List of all SpaceX crewed flights to space
    Jun 27, 2025 · SpaceX crewed launches at a glance ; Number of crewed launches: 18 (NASA: 11, Commercial: 7) ; Number of crew: 68 (Government: 48, Commercial: 20).
  57. [57]
    NASA's Commercial Crew Program Press Kit
    May 6, 2015 · NASA's Commercial Crew Program is delivering on its goal of safe, reliable, and cost-effective human transportation on International Space Station missions.
  58. [58]
    NASA switches Starliner crew to SpaceX Dragon as testing ...
    Mar 28, 2025 · NASA's decision on August 24, 2024, that the Boeing Starliner Crew Flight Test mission would conclude with the spacecraft returning uncrewed.
  59. [59]
    Starliner future plans still in limbo - SpaceNews
    Jun 8, 2025 · The problems with the thrusters, along with helium leaks detected in flight, led NASA to decide in August 2024 to return Starliner uncrewed, ...
  60. [60]
    Updates - SpaceX
    In March of 2025, the astronauts of the Fram2 mission watched the launch of a Falcon 9 rocket while on the way to their own rocket launch.
  61. [61]
    NASA, SpaceX Launch First Flight Test of Space System Designed ...
    Mar 2, 2019 · NASA's Commercial Crew Program is working with Boeing and SpaceX to design, build, test and operate safe, reliable and cost-effective human ...
  62. [62]
    Boeing's Starliner spacecraft lands in New Mexico after successful ...
    May 25, 2022 · “The test flight was extremely successful,” said Steve Stich, NASA's commercial crew program manager. “We met all the mission objectives. Of ...<|separator|>
  63. [63]
    NASA, Boeing Complete Successful Landing of Starliner Flight Test
    Dec 22, 2019 · The Starliner that landed today will be refurbished for Boeing's first operational crewed mission, following the Crew Flight Test. NASA ...
  64. [64]
    How SpaceX Saves NASA $100 Million Per Flight | The Motley Fool
    Mar 20, 2022 · In hiring SpaceX to carry its astronauts for only $75 million a pop, NASA is saving taxpayers about $22 million per ticket -- or $88 million per flight.
  65. [65]
    [PDF] An Assessment of Cost Improvements in the NASA COTS/CRS ...
    Jun 28, 2017 · The COTS program significantly reduced costs; for example, the Falcon 9 development cost was estimated at $300 million, compared to $1.7 to $4 ...
  66. [66]
    Your Guide to Crew Dragon's First Astronaut Flight
    May 20, 2020 · Former NASA associate administrator Lori Garver joined our 6 May episode to look back at the origins of the commercial crew program. As NASA's ...Missing: post | Show results with:post<|separator|>
  67. [67]
    NASA: SpaceX, Boeing building spacecraft for astronauts saved up ...
    May 13, 2020 · NASA estimates having SpaceX and Boeing build spacecraft for astronauts saved $20 billion to $30 billion. Under the Commercial Crew program, ...
  68. [68]
    NASA Commercial Crew Program Kicks off Spaceflight Renaissance
    Nov 12, 2020 · “It makes spaceflight more affordable in the sense that it's less disposable and that's something people are very conscious of,” Donnenwirth ...Missing: savings | Show results with:savings
  69. [69]
    NASA buys Soyuz seats as agency presses for commercial crew ...
    Aug 5, 2015 · NASA has signed a $490 million agreement with the Russian government to ferry US astronauts to and from the International Space Station in 2018 and 2019.Missing: dependency | Show results with:dependency
  70. [70]
    Soyuz launch marks end of an era for NASA - SpaceNews
    Oct 14, 2020 · Rubins was added to the crew in May when NASA announced it was purchasing a final Soyuz seat from Roscosmos for $90.25 million. NASA ...
  71. [71]
    NASA confirms delays in Boeing and SpaceX commercial crew flights
    Aug 2, 2018 · NASA released an updated schedule of commercial crew test flights Aug. 2 that confirms Boeing's revised plans as well as delays for SpaceX's ...
  72. [72]
    Leaky Valve Blamed for Explosion of SpaceX Crew Dragon during ...
    A check valve leaking toxic oxidizer propellant inside the critical SuperDraco abort thruster propulsion system apparently caused the devastating explosion.
  73. [73]
    SpaceX found the problem that blew up its Crew Dragon spacecraft
    A propellant leak caused the destruction of a SpaceX vehicle during an April test as it prepared to carry astronauts to the International Space Station.
  74. [74]
    After redesigns, the finish line is in sight for SpaceX's Crew Dragon ...
    Dec 7, 2019 · SpaceX has redesigned elements of the ship's abort propulsion system after an explosion destroyed a test capsule in April, and engineers beefed ...<|separator|>
  75. [75]
    NASA completes investigation on flawed Boeing Starliner capsule ...
    Jul 8, 2020 · NASA has completed its investigation into Boeing's problematic first test flight of a Starliner crew capsule as the company and agency look toward a second ...
  76. [76]
    Starliner investigation finds numerous problems in Boeing software ...
    Feb 7, 2020 · One issue, found immediately after separating from its upper stage, was a timer offset that prevented the spacecraft from firing its thrusters ...
  77. [77]
    Fresh details on Boeing Starliner's mission underscore systemic ...
    Apr 4, 2025 · Starliner's first uncrewed test mission (OFT-1) in 2019 failed to reach the ISS due to critical software errors, revealing inadequate end-to-end ...
  78. [78]
    Further delays of Starliner's next flight mark anniversary of its first ...
    Jun 7, 2025 · The agency said the timing of the next launch is “pending system certification and resolution of Starliner's technical issues.” Repeating what ...
  79. [79]
    Boeing sending first astronaut crew to space after years of delay
    May 3, 2024 · The CST-100 Starliner test mission, a years-delayed milestone after more than $1 billion in cost overruns, will ferry two NASA astronauts to the ...
  80. [80]
    Boeing Starliner Losses Top $2B—And Counting - Payload Space
    Feb 5, 2025 · Boeing said it lost $523M on Starliner in 2024—the largest single-year loss the aerospace titan has recorded in developing the commercial crew ...
  81. [81]
    Boeing Takes Another $250 Million Charge for Starliner
    Oct 23, 2024 · Boeing is taking another $250 million charge against earnings to pay for cost overruns on the Starliner commercial crew program.<|separator|>
  82. [82]
    Boeing's Starliner has cost at least twice as much as SpaceX's Crew ...
    Jul 31, 2024 · All of NASA's contracts with SpaceX for a similar scope of work on the Crew Dragon program totaled more than $3.1 billion, but any expenses paid ...
  83. [83]
    Starliner by the Numbers: Payload Research
    May 8, 2024 · In recent years, the cost per seat on Soyuz has risen to as high as $86M. Dragon and Starliner seat cost: In 2019, NASA's inspector general ...<|separator|>
  84. [84]
    [PDF] NASACOST AND SCHEDULE OVERRUNS - NASA OIG
    Jun 14, 2018 · Since 2011, we have issued eight reports examining acquisition strategies used by. NASA for commercial cargo and crew transportation services to ...
  85. [85]
    Delays, cost overruns by Boeing and SpaceX could ice out NASA ...
    Nov 16, 2019 · OIG estimates SpaceX's Crew Dragon will cost NASA about $55 million per seat for the first six missions. NASA and Boeing both pushed back on ...
  86. [86]
    [PDF] GAO-25-107591, NASA: Assessments of Major Projects
    Jul 1, 2025 · The four projects that experienced annual cost growth collectively reported over $500 million in overruns. NASA's human spaceflight crew capsule ...Missing: CST- | Show results with:CST-
  87. [87]
    Boeing reports progress on containing Starliner costs - SpaceNews
    Apr 24, 2025 · Boeing executives said the company is making progress on containing the costs of its CST-100 Starliner commercial crew vehicle.
  88. [88]
    Space in transition: How Obama's White House…
    Aug 22, 2016 · The report also endorsed extending the life of the ISS to 2020, as opposed to 2016, and using commercial crew providers as a taxi service.
  89. [89]
    Reflections on Commercial Crew and Cargo Missions
    Nov 16, 2020 · In 2005 NASA administrator Mike Griffin had allocated $500M to establish the Commercial Orbital Transportation Services program. This led to the ...
  90. [90]
    In the room where it happened: When NASA nearly gave Boeing all ...
    Sep 24, 2024 · Boeing asked for $4.2 billion, 60 percent more than SpaceX's bid of $2.6 billion. The second category, mission suitability, assessed whether a ...
  91. [91]
    Boeing, Lockheed, ULA corner the government-funded space ...
    Apr 22, 2018 · The US government invested $83 billion in space platforms and hypersonic technologies between fiscal years 2011 and 2017, according to Govini's new report.
  92. [92]
    [PDF] NASA'S CHALLENGES CERTIFYING AND ACQUIRING ...
    Jun 30, 2011 · The Agency would be both stimulating a commercial crew industry and assisting the commercial partners to develop safe, reliable, and cost- ...
  93. [93]
    How Much Did NASA Hate Commercial Crew Initially? (Spoiler Alert
    Jun 9, 2023 · Basically, everybody who was anybody at NASA hated the plan. The comments were even more sobering. Most of them specifically repudiated the most fundamental ...Missing: influences | Show results with:influences
  94. [94]
    [PDF] Commercial Crew Program (CCP) Status - NASA
    NASA is working with SpaceX to shift future Dragon recovery operations for crew and cargo to the West Coast. - Dragon recovery operations to occur in the ...
  95. [95]
    NASA, Boeing Prepare for Starliner Testing
    Mar 27, 2025 · The major in-flight propulsion system anomalies Starliner experienced in orbit are expected to remain open further into 2025, pending the ...Missing: milestones | Show results with:milestones
  96. [96]
    NASA examining options for another Starliner test flight - SpaceNews
    Mar 20, 2025 · NASA is evaluating options for another test flight of Boeing's CST-100 Starliner commercial crew vehicle before having the vehicle begin regular missions to ...
  97. [97]
    SpaceX Makes Adjustments For Crew Dragon's Future - Space Scout
    Sep 23, 2024 · SpaceX's fleet of Crew Dragons are currently rated for five flights each, while each of Boeing's Starliners could fly up to ten times.
  98. [98]
    NASA Updates 2025 Commercial Crew Plan
    Oct 15, 2024 · NASA's SpaceX Crew-11 will be the second crew rotation flight of 2025 and is targeted for no earlier than July to benefit the space station ...Missing: strategic objectives
  99. [99]
    NASA targets multiple Commercial Crew missions in 2025
    Oct 16, 2024 · The next flight of Boeing's Starliner will be scheduled based on the progress toward system certification, which involves reviewing Crew Flight ...<|separator|>
  100. [100]
    [PDF] collaborations for commercial space capabilities 2 (ccsc2) - NASA
    May 31, 2023 · This agreement between NASA and SpaceX aims to facilitate SpaceX's Integrated LEO Architecture, including Starship, and capabilities like human ...
  101. [101]
    NASA agreements to support work on commercial spacecraft and ...
    Jun 16, 2023 · SpaceX received a CCSC-2 agreement to work on an “integrated low Earth orbit architecture” involving both its Dragon and Starship vehicles.
  102. [102]
    NASA Announces Second Collaborations for Commercial Space ...
    Nov 2, 2022 · The first CCSC agreements resulted in four collaborations associated with development of commercial launch vehicles, spacecraft, and space suits ...
  103. [103]
    Commercial Space Stations in Low Earth Orbit - NASA
    May 18, 2023 · NASA plans to transition to a new low Earth orbit model featuring commercial space stations to continue leveraging the unique environment and ...<|separator|>
  104. [104]
    NASA Seeks Industry Input on Next Phase of Commercial Space ...
    Sep 5, 2025 · In Phase 2, NASA intends to support industry's design and demonstration of commercial stations through multiple funded Space Act Agreements, ...
  105. [105]
    [PDF] Commercial Low-Earth Orbit Destination (CLD) Concept of Operations
    All spacecraft transporting Government crewmembers to or from the. CLD must be certified by NASA Commercial Crew Program (CCP) or another Government ...
  106. [106]
    Axiom Mission 4 Astronauts Dock to Station Inside Dragon - NASA
    Jun 26, 2025 · The SpaceX Dragon spacecraft carrying Axiom Mission 4 nears the International Space Station's space-facing docking port on the Harmony module.
  107. [107]
    [PDF] Commercial Low Earth Orbit (LEO) Development | NASA
    NASA aims to transition to a commercial LEO economy, managed by the Commercial LEO Development Program Office, to stimulate production and trade in LEO.
  108. [108]
    NASA Seeks Partners to Demo Commercial Stations Before 2030
    Sep 11, 2025 · Draft AFPP invites proposals for commercial LEO stations with a four-person, 30-day crewed demo before 2030, and a path to later services ...
  109. [109]
    [PDF] Commercial Space Division Programs - NASA
    NASA has a multi-pronged strategy to address this schedule risk: 1. NASA is engaged with multiple CLD providers (3 funded partners and 4 unfunded partners).<|control11|><|separator|>