Jammu–Baramulla line

The Jammu–Baramulla line is a 324 km railway connecting Jammu, the winter capital of the Indian union territory of Jammu and Kashmir, to Baramulla in the Kashmir Valley via Udhampur and Srinagar. Constructed through rugged Himalayan terrain marked by tectonic faults, high seismic activity, and extreme weather, the line incorporates the 272 km Udhampur–Srinagar–Baramulla Rail Link (USBRL), which became fully operational on 6 June 2025 after nearly three decades of development at a cost exceeding ₹44,000 crore. The project's defining engineering achievements include 36 tunnels spanning about 119 km—such as the 11.215 km Pir Panjal Railway Tunnel and the 12.775 km USBRL Tunnel 50 (T-50), India's longest transportation tunnel—and 927 bridges, among them the Chenab Rail Bridge, the world's highest railway arch bridge at 359 meters above the riverbed. These feats enable year-round connectivity, supplanting reliance on snow-vulnerable roads like the Jammu–Srinagar National Highway, and facilitate passenger services, freight transport, tourism, and strategic logistics to a region previously rail-isolated from the Indian network. Key sections include the pre-existing Jammu–Udhampur line (53 km, operational since 2005), the challenging Katra–Banihal stretch with steep 1:6 gradients navigated via a 25 km spiral loop and the Reasi region's viaducts, and the electrified Qazigund–Baramulla extension (118 km, serving 20 stations). The completion addresses longstanding infrastructural deficits, enhancing economic integration while overcoming geological hurdles that delayed progress, including landslides and avalanches, through advanced tunneling and bridging techniques.

Overview

Route Description

The Jammu–Baramulla line comprises a 272 km railway alignment from Udhampur to Baramulla, integrating with the existing Jammu–Udhampur section to provide connectivity from Jammu Tawi to the Kashmir Valley. The route navigates through the Himalayan foothills, ascending steeply into the Pir Panjal range before descending into the relatively flat Kashmir Valley. The line is segmented into distinct portions: the initial Udhampur–Katra stretch covering about 25 km in the lower hills, followed by the 111 km Katra–Banihal section that crosses challenging mountainous terrain, and the concluding Banihal–Srinagar–Baramulla segment traversing the valley floor for approximately 136 km. Key stations along the route include Katra, serving as a gateway for pilgrims; Banihal, marking the transition from mountains to valley; Srinagar, the regional capital; and Baramulla, the northern terminus near the Line of Control. Intermediate stops such as Qazigund, Awantipora, and Budgam facilitate local access in the valley. This alignment enhances regional linkage by bridging the geologically active young Himalayas, with the path following river valleys and ridgelines to minimize gradients while spanning tectonic zones. The terrain shifts from subtropical plains near Udhampur to alpine heights in the Pir Panjal, culminating in the alluvial plains of the Jhelum River basin toward Baramulla.

Strategic and Geopolitical Significance

The Jammu–Baramulla line serves as a critical conduit for national integration, forging a reliable all-weather rail connection between the Kashmir Valley and the Indian mainland that supplants the limitations of road networks like National Highway 44, which are frequently impassable due to heavy snowfall and landslides. This linkage realizes a long-standing objective of physical unification, enabling uninterrupted access to remote areas and countering geographic isolation that has historically fueled separatist sentiments in the disputed region. Militarily, the line markedly improves logistics for the Indian armed forces by permitting rapid and secure movement of personnel, equipment, and supplies to forward deployments near the Line of Control with Pakistan and the Line of Actual Control with China. A pivotal demonstration occurred on September 15, 2025, when the Indian Army operated its first exclusive freight train on the Udhampur–Srinagar–Baramulla Rail Link, conveying 753 metric tonnes of advance winter stocking loads from BD Bari to Anantnag for units in Jammu and Kashmir. This operation enhances sustainment capabilities during harsh winters, mitigating vulnerabilities inherent in truck convoys susceptible to ambushes or blockages. Geopolitically, the infrastructure reinforces India's strategic depth in Jammu and Kashmir by diversifying supply routes and accelerating response times in a contested frontier zone, thereby deterring adversarial incursions and supporting post-2019 administrative reforms aimed at tighter territorial cohesion. The line's operationalization also promotes ancillary economic ties, such as expedited goods transport—including the return leg of the September 2025 freight run carrying Kashmiri produce—fostering trade and tourism that undermine claims of systemic disconnection.

Historical Development

Planning and Initial Surveys

The Udhampur-Srinagar-Baramulla Rail Link (USBRL), the critical extension of the Jammu–Baramulla line into the Kashmir Valley, was conceptualized in 1994 as a continuation beyond the planned Jammu-Udhampur segment to provide all-weather rail connectivity amid the region's geopolitical isolation. The Government of India sanctioned the project in 1994-95, recognizing its role in integrating Jammu and Kashmir with the national rail network despite the formidable Himalayan barriers. Initial planning emphasized feasibility assessments in tectonically active thrust zones, where seismic risks and unstable geology posed fundamental challenges to alignment selection. Feasibility surveys began in early 1997, with teams dispatched to map routes from Udhampur through the Pir Panjal range toward Srinagar. These efforts quickly encountered local opposition in Kashmir, as on November 12, 1997, surveyors in Nowgam were mistaken by residents for security personnel amid heightened insurgency-related sensitivities, prompting near-violent confrontations and necessitating diplomatic interventions to proceed. Such incidents underscored early logistical hurdles in data collection, delaying comprehensive topographic and geotechnical evaluations essential for validating the proposed 272 km alignment. Post-2000, governmental resolve intensified with the USBRL's designation as a National Project in 2002, elevating it to priority status for resource allocation and strategic oversight under Northern Railway's construction wing. This commitment facilitated refined planning, including IRCON International's involvement in preliminary engineering studies to address the valley's connectivity deficits, though surveys remained constrained by security protocols and environmental complexities in the young fold mountains.

Construction Phases and Milestones

The Udhampur–Srinagar–Baramulla Rail Link (USBRL), comprising the bulk of the Jammu–Baramulla line's challenging alignment, advanced through phased construction initiated after project sanctioning in 1997, with progress dictated by the need for over 900 bridges and 38 tunnels amid unstable geology and extreme topography. The Kashmir Valley portion from Qazigund to Baramulla (118 km) marked the first major commissioning in October 2009, establishing a functional broad-gauge line through relatively flatter terrain but still requiring 72 km of tunneling. Subsequent efforts targeted connectivity gaps, with the 18 km Banihal–Qazigund section—including the 11.215 km Pir Panjal Railway Tunnel—achieving operational status by early 2013 after tunneling works that navigated fault zones and high water ingress. The Udhampur–Katra leg (25 km), involving 17 tunnels and steep 1:100 gradients, saw construction intensify from the mid-2000s, culminating in service commencement on July 4, 2014, following iterative geotechnical reinforcements to counter landslides. The Katra–Banihal phase (111 km), launched around 2009 as the project's engineering core, encompassed 272 tunnels (totaling 119 km) and 31 major bridges, with incremental milestones including the 2021 arch completion of the Chenab Bridge and multiple tunnel penetrations addressing seismic-prone rock bursts. Progress accelerated post-2020, yielding the February 2024 commissioning of the 48 km Banihal–Sangaldan stretch, which integrated electrified tracks and trial runs up to 100 km/h. By December 2024, 255 km of the overall 272 km USBRL alignment was track-ready, supported by completed electrification across 185.66 km to facilitate consistent operations in sub-zero conditions. These phases, spanning 28 years to near-full linkage, underscored iterative adaptations to empirical subsurface data over initial designs.

Completion and Inauguration

The Sangaldan–Katra section, the final 25.8 km stretch of the 272 km Udhampur–Srinagar–Baramulla Rail Link (USBRL) integrating into the broader Jammu–Baramulla line, was completed on June 6, 2025, following track laying, ballastless track installation in key tunnels, and final safety certifications. This completion bridged the remaining gap after the Banihal–Sangaldan portion opened in February 2024, enabling uninterrupted connectivity from Jammu through the Pir Panjal range to Baramulla. Prime Minister Narendra Modi inaugurated the fully operational USBRL on June 6, 2025, in a ceremony highlighting its role as an all-weather rail corridor linking the Kashmir Valley to the Indian rail network for the first time. The event included the flagging off of inaugural Vande Bharat services, with regular passenger operations commencing on June 7, 2025, via two daily train pairs covering Srinagar–Katra routes six days a week. Preceding the inauguration, accelerated trial runs and motor trolley inspections validated track stability amid the region's seismic activity, with no reported structural anomalies in the young Himalayan geology. This milestone realized a vision originating from British-era surveys in the 1890s, spanning over 127 years of intermittent planning and execution, and stands as a pinnacle of post-independence infrastructure amid challenging terrain and security contexts. The line's activation immediately enhanced logistical readiness, integrating with the pre-existing electrified Qazigund–Baramulla valley section for end-to-end Jammu–Baramulla travel.

Engineering Achievements

Major Tunnels

The Jammu–Baramulla line incorporates 38 tunnels aggregating 119 km in length, enabling rail passage through the geologically complex Pir Panjal Range and surrounding Himalayan formations. These structures were predominantly excavated using the New Austrian Tunnelling Method (NATM), adapted for the region's heterogeneous, squeezing rock masses and high water inflow risks, with selective application of tunnel boring machines (TBMs) in stable segments. The Pir Panjal Tunnel (T-80), at 11.215 km, stands as an early engineering benchmark, with breakthrough attained on October 28, 2011, via dual-heading NATM excavation. It features an integrated ventilation system of 25 roof-mounted axial fans grouped in five sets, alongside fire detection and emergency escape provisions to ensure operational safety at depths exceeding 1,000 meters.
TunnelLength (km)Breakthrough/Completion NotesConstruction Highlights
T-50 (Khari-Sumber)12.77Escape tunnel breakthrough December 15, 2022; Operational February 2024India's longest transportation tunnel; parallel 12.895 km escape tunnel for evacuation; NATM for faulted geology; modern safety integrations including semi-transverse ventilation.
These tunnels underscore advancements in Himalayan-specific techniques, such as the Indian Tunnelling Method (I-TM), which optimizes NATM for local seismic and hydrogeological conditions without reliance on full mechanization.

Iconic Bridges

The Jammu–Baramulla line incorporates 927 bridges with a combined length of 13 kilometers, utilizing steel truss and arch designs engineered for resilience in seismic zone IV, capable of withstanding earthquakes up to magnitude 8.0. Among these, the Chenab Bridge stands as the world's highest railway bridge, with a deck height of 359 meters above the river bed—exceeding the Eiffel Tower by 35 meters—and features a steel-concrete arch main span of 467 meters within a total structure length of 1,315 meters. Located between Bakkal and Kauri stations in Reasi district, it employs corrosion-resistant steel and wind-resistant features to endure extreme Himalayan conditions, including winds up to 266 km/h. The bridge's arch was fully erected by August 2022, with trial runs commencing in June 2024 and official commissioning for rail traffic on June 6, 2025. The Anji Khad Bridge, at 331 meters high, represents India's inaugural cable-stayed railway bridge, spanning 725.5 meters overall with a primary cable-stayed section of 473.25 meters across a gorge near Reasi. Its design integrates high-strength steel cables and a composite deck to navigate the challenging topography, contributing to the line's connectivity through the Pir Panjal range.

Gradient, Electrification, and Safety Features

The Jammu–Baramulla line features challenging gradients, with steep inclines up to approximately 3% in sections like Katra-Banihal, demanding robust traction capabilities from locomotives to maintain operational efficiency amid the Himalayan terrain. These gradients, steeper in pre-electrification diesel-era operations where peaks reached 3.5%, now benefit from electric power to reduce dependency on adhesion-limited diesel haulage. Electrification of the full 272 km Udhampur-Srinagar-Baramulla Rail Link (USBRL) segment was completed by mid-2025 using a standard 25 kV AC overhead catenary system, following phased rollout including the 185.66 km Baramulla-Banihal section achieved by 2020 and subsequent Katra-Dharam extensions. This upgrade supports higher power output for gradient navigation, with electrical sectioning points integrated in long tunnels for isolated fault management and operational flexibility. Safety protocols incorporate automatic block signaling via three-aspect colour-light systems across the route, supplemented by electronic interlocking at all 23 stations to prevent signal passing errors and ensure train separation. Anti-collision measures draw from Indian Railways' Kavach system deployment, an indigenous automatic train protection mechanism that enforces speed supervision and emergency braking in high-risk zones, though full rollout on this line aligns with national prioritization for seismic and gradient-prone corridors. Ballastless slab tracks are employed in tunnels for seismic stability, combined with continuous geotechnical monitoring along fault lines to detect slope instability or seismic activity in real-time. Operational speed limits cap at 100 km/h on valley plains, dropping to 60-75 km/h in steeper hill sections to mitigate derailment risks from curvature and gradient interplay.

Construction Challenges

Geological and Environmental Obstacles

The Jammu–Baramulla line traverses the Pir Panjal range, a segment of the tectonically active lower Himalayas characterized by young fold-thrust belts, highly heterogeneous rock masses including quartzites, slates, limestones, and volcanic tuffs, and frequent shear zones with fault gouge. This geology, compounded by thrust faults such as the Main Boundary Thrust and Panjal Thrust, contributes to seismic vulnerability and slope instability, with the region exhibiting dominant thrust faulting and normal faulting mechanisms. Construction encountered frequent landslides and rockfalls, particularly in the Udhampur-Qazigund section, leading to tunnel face slips, excessive overbreak, and delays due to unstable ground conditions like squeezing and water ingress. To address these hazards, engineers employed the New Austrian Tunneling Method (NATM) for stability in fractured rock, with systematic rock classification and support systems to mitigate instabilities and rockfalls at portals. The alignment's design incorporated over 90 kilometers of tunneling in the 111-kilometer Katra-Banihal stretch alone, comprising about 84% underground passage to navigate thrust zones and reduce surface exposure to landslides. Environmental obstacles included managing excavation spoil to prevent sediment runoff into rivers like the Chenab, with muck from tunnel boring repurposed for embankments to limit erosion, though heavy monsoons exacerbated landslide risks during open-cut works. Extensive tunneling minimized deforestation compared to surface routes, preserving forest cover in the fragile Himalayan ecosystem while addressing seismic and geotechnical risks through geotechnical monitoring.

Security and Political Disruptions

The initial planning and survey phases encountered political resistance amid the region's separatist sentiments. On November 12, 1997, a railway survey team consisting of two officers, three junior engineers, and six helpers arrived at Nowgam (later renamed Srinagar railway station) for feasibility assessments, but local residents mistook them for police personnel, prompting confrontations and necessitating de-escalation efforts to avert violence. This incident underscored early political sensitivities that delayed preparatory work in militancy-prone areas. Throughout the 2000s and 2010s, construction faced persistent security threats from ongoing insurgency, including sabotage risks and targeted killings of non-local migrant laborers, who formed a significant portion of the workforce. Militant groups frequently attacked civilian workers across Jammu and Kashmir, with official data recording 29 such targeted civilian incidents in 2022 alone, many aimed at disrupting infrastructure projects by instilling fear and reducing available security cover for sites. These disruptions contributed to prolonged halts, as reduced protective deployments left workers vulnerable, contrasting with claims attributing delays solely to terrain and highlighting militancy as a primary causal factor in timeline extensions from the 1994 sanctioning. The revocation of Article 370 on August 5, 2019, correlated with enhanced governance stability and a relative decline in militant violence, enabling accelerated construction phases. Post-revocation, key segments like the Chenab Bridge and Banihal-Qazigund tunnel advanced without prior levels of interruption, culminating in the 272-km line's full operational status by June 2025. This empirical progression under improved security conditions refutes assertions of inherent project infeasibility, demonstrating that targeted stabilization measures mitigated political and insurgent barriers effectively.

Cost Overruns and Logistical Realities

The Udhampur-Srinagar-Baramulla Rail Link (USBRL) project, approved in 1995 with an initial estimated cost of Rs 2,500 crore, experienced substantial budget escalations, reaching over Rs 40,000 crore by completion in 2025. This overrun stemmed primarily from scope expansions and unforeseen site conditions rather than initial underestimation alone; the original budget anticipated a simpler alignment, but detailed surveys revealed extensive tunneling requirements—over 119 km of tunnels, or 38% of the 272 km route—necessitated by Himalayan geology including fault lines and soft rock zones that demanded reinforced linings and advanced stabilization. Inflation compounded this, with construction spanning three decades amid rising material and labor costs, while imported technologies such as tunnel boring machines (TBMs) and high-strength steel for seismic-resistant bridges added premiums due to customization for extreme altitudes and temperatures. Logistical constraints in the rugged Pir Panjal range further drove costs, as conventional road access was infeasible for heavy equipment; materials for structures like the Chenab Bridge were transported using aerial ropeways spanning up to 1 km and helicopter lifts for remote tunnel portals, enabling delivery of 28,000-tonne girders despite elevations exceeding 1,000 meters. Public-sector entities like IRCON International contributed efficiency gains through integrated project management, reducing delays in procurement and execution by coordinating with international partners for specialized imports, though early phases suffered from fragmented planning that amplified overruns. These measures addressed causal realities of the terrain, where supply chains faced seasonal snow blockades and limited helipads, prioritizing long-term asset durability over short-term savings. At approximately Rs 150 crore per km, the USBRL holds one of the highest unit costs among global mountain railways, surpassing lines like Switzerland's Gotthard Base Tunnel (adjusted for inflation and scale) due to the combination of seismic activity, avalanche risks, and minimal prior infrastructure. This premium is attributable to the line's engineered permanence—featuring ballasted tracks resistant to -20°C winters and earthquake magnitudes up to 8—contrasting with regional roads that require annual reconstructions from landslides, yielding a lifecycle cost advantage despite upfront escalation. Comptroller and Auditor General reviews attributed much of the variance to geological variances encountered post-approval, underscoring the limits of pre-construction modeling in tectonically active zones.

Operational Aspects

Passenger Services

The Jammu–Baramulla line facilitates passenger services primarily via the Katra–Srinagar Vande Bharat Express, inaugurated on June 6, 2025, by Prime Minister Narendra Modi, marking the first direct semi-high-speed rail connection between these points. This train operates six days a week, departing Shri Mata Vaishno Devi Katra at 2:55 PM and arriving in Srinagar at 5:53 PM, covering the distance in approximately three hours with intermediate stops at Banihal and, effective October 29, 2025, Reasi for two minutes in both directions. The return service, train number 26402, departs Srinagar at 2:00 PM. Local DEMU passenger trains provide connectivity along segments such as Baramulla to Banihal, supporting daily commuters and short-distance travel within the Kashmir Valley, with the full line's operationalization on June 7, 2025, enabling seamless integration from Jammu Tawi via existing links to Udhampur and Katra. The infrastructure supports up to 10-15 train pairs daily in peak conditions, enhancing accessibility and tourism through panoramic views of the Pir Panjal range and Chenab Valley, though services occasionally face suspensions due to heavy snowfall or floods, as seen in post-monsoon disruptions in September-October 2025 requiring phased resumptions. Initial operations post-June 2025 have demonstrated reliability, with the Vande Bharat achieving consistent runs and contributing to a surge in rail-based tourism despite seasonal challenges.

Freight Operations

Freight operations on the Jammu–Baramulla line, part of the Udhampur-Srinagar-Baramulla Rail Link (USBRL), commenced in August 2025 with the arrival of the first loaded freight train at Anantnag Goods Shed, carrying cement from Punjab and marking the initiation of inward and outward goods movement in the Kashmir Valley. This development enabled the Northern Railway's Jammu Division to handle cargo logistics, reducing dependence on the Srinagar-Jammu National Highway (NH44), which is prone to closures from landslides and heavy snowfall. A significant milestone occurred on September 12–13, 2025, when the Indian Army operated its first exclusive freight train from BD Bari to Anantnag, transporting 753 metric tonnes of advance winter stocking supplies for military units in Jammu and Kashmir. The train's return journey carried Kashmiri apples to Delhi, demonstrating bidirectional cargo potential amid highway disruptions that had caused apple spoilage for growers. This operation highlighted the line's role in strategic logistics, providing a more reliable alternative to road transport vulnerable to seasonal blockages. The fully electrified USBRL supports heavier freight loads through electric locomotives, aligning with India's National Rail Plan for enhanced cargo capacity via electrification. Integration with NH44 facilitates multimodal transport, easing road congestion and enabling exports of Valley produce such as apples—via dedicated parcel trains starting September 2025—and potentially timber, though operations remain nascent post-full commissioning in June 2025. Current single-track sections limit frequency, but the corridor's design supports up to 20–30 trains daily in optimized conditions, prioritizing military and essential goods to mitigate supply vulnerabilities.

Maintenance and Safety Protocols

The Jammu Division of Northern Railway, operational since June 1, 2025, and headquartered at Jammu Tawi, provides dedicated oversight for the maintenance and safety of the Jammu–Baramulla line, facilitating efficient management of its challenging terrain and infrastructure. Maintenance protocols emphasize preventive measures against environmental stresses, including regular track destressing and monitoring in sections prone to thermal expansion, such as between Sadura and Panzgom, particularly ahead of winter snowfall to ensure track stability and reliability. Advanced track maintenance machines are deployed for upkeep, complemented by upgrades to passenger coaches for enhanced safety. Safety measures incorporate comprehensive security arrangements, with routine patrols conducted by Railway Protection Force (RPF), Central Reserve Police Force (CRPF), and Jammu and Kashmir Police to sanitize the route and mitigate risks, including intensified protocols following regional security incidents. Specialized RPF commandos provide additional protection for high-speed services like Vande Bharat trains operating on the line. Ongoing training initiatives, such as fire safety seminars at key stations like Jammu, equip personnel with skills for emergency response in tunnel-heavy sections, where fire risks are elevated due to the predominantly single-track configuration. Since the line's full inauguration in February 2025, no major operational accidents have been reported, reflecting the efficacy of these integrated protocols in a seismically active and high-altitude environment.

Impacts and Controversies

Economic and Developmental Benefits

The completion of the Jammu–Baramulla railway line has generated substantial employment during its construction phase, with over 14,000 jobs created through project executing agencies, 65% of which were allocated to local residents in Jammu and Kashmir. Additionally, the project provided 804 government jobs via the Railways and amassed more than 5 crore man-days of employment overall, contributing to skill development and temporary economic activity in a region historically constrained by limited infrastructure. Freight operations, commencing with the first dedicated train in August 2025, have enabled faster and more cost-effective transport of perishable goods such as apples, dry fruits, and flowers from the Kashmir Valley to national markets, reducing dependency on road haulage vulnerable to seasonal disruptions. This connectivity counters prior isolation by streamlining exports for horticulture and handicrafts sectors, potentially lowering logistics costs and enhancing profitability for local producers. The line's passenger services, including Vande Bharat Express extensions with stops like Reasi from October 2025, are projected to stimulate tourism by improving access to Valley destinations year-round, fostering revenue from spiritual and leisure visits while supporting ancillary local businesses. Enhanced all-weather links are expected to promote self-reliance in regional industries by curbing out-migration through viable local opportunities in trade and services.

Strategic Military Advantages

The Jammu–Baramulla railway line, particularly the Udhampur–Srinagar–Baramulla Rail Link (USBRL) segment, provides the Indian Army with an all-weather alternative to vulnerable road networks in Jammu and Kashmir, enabling faster and more secure deployment of troops and equipment to forward areas along the Line of Control (LoC) and international border. Prior to its completion, military logistics depended heavily on convoys traversing narrow, ambush-prone highways like National Highway 44, which are susceptible to landslides, snow blockades, and insurgent attacks; the rail link reduces transit times significantly, allowing rapid mobilization of armored units, artillery, and supplies without exposure to such risks. This logistical edge was demonstrated in September 2025, when the Indian Army operated its first exclusive freight train on the USBRL, transporting 753 metric tonnes of advance winter stocking supplies from Udhampur to Anantnag for units in the Kashmir Valley, marking a shift from road dependency and enhancing preparedness for harsh seasonal conditions. The operation, initiated via an indent to Northern Railway on August 7, 2025, underscores the line's capacity for bulk military freight, bypassing weather-induced disruptions that previously hampered winter resupply efforts. Geostrategically, the line bolsters India's defensive posture by facilitating access to border regions proximate to Pakistan-occupied Kashmir (PoK) terror infrastructure, with planned extensions such as the 40.2 km Baramulla–Uri alignment—approved in September 2025—extending connectivity to key army bases in Uri tehsil, a western flank hotspot near the LoC. This development supports seamless movement of military specials, including personnel and ordnance, while reinforcing national integration in the post-2019 security landscape by curtailing isolation that could foster separatist activities.

Criticisms Regarding Environment and Displacement

The construction of the Udhampur-Srinagar-Baramulla Rail Link (USBRL) has faced criticisms from environmental activists and local communities regarding its potential to displace residents and harm fragile Himalayan ecosystems, including risks of habitat fragmentation, deforestation from tunnel excavation, and disruption to water quality near structures like the Chenab Bridge. Specific concerns include the acquisition of approximately 1,559 hectares of private land, which affected agricultural areas and prompted claims of livelihood threats to farming households, though exact numbers of displaced individuals remain undocumented in official records. In the Baramulla-Uri segment, ongoing surveys as of 2025 have raised fears among locals of further relocations impacting small landholdings, echoing broader apprehensions about cultural and economic disruptions in agrarian communities. These claims have been tempered by the project's design, which minimizes surface-level habitat loss through extensive tunneling—87% of the 111-km Katra-Banihal section consists of tunnels, reducing direct ecological footprint compared to open-cut alternatives. The USBRL complied with Environmental Impact Assessment (EIA) requirements under India's Ministry of Environment, Forest and Climate Change, incorporating compensatory afforestation and net present value payments for diverted forest areas, as mandated by railway construction protocols. Post-commissioning in June 2025, no evidence has emerged of mass extinctions, widespread irreversible damage, or unmitigated biodiversity collapse, with tunnel muck repurposed for site stabilization to offset erosion risks. Critics' assertions often stem from pre-operational modeling of seismic and blasting impacts in a geologically active zone, but operational data indicates that rail transport's lower emissions and reduced reliance on landslide-prone roads provide net environmental benefits over time, outweighing localized displacements where compensation has been disbursed for acquired lands. While some agricultural losses occurred, these were not on a scale causing systemic food insecurity, and afforestation efforts aligned with forest conservation norms have aimed to restore equivalent greenery.

Future Prospects

Planned Extensions

In September 2025, the Indian Ministry of Railways approved the construction of a new 40.2 km railway line from Baramulla to Uri, extending the Jammu–Baramulla network northward toward the Line of Control (LoC). This project, proposed during the 99th meeting of the Network Planning Group under PM GatiShakti on September 3, 2025, will integrate five existing stations and enhance connectivity to Uri, a border town proximate to the Kaman Post along the LoC with Pakistan-occupied Kashmir. The primary rationale centers on strategic military logistics, facilitating rapid troop and supply movements in a geopolitically sensitive region, rather than prioritizing immediate civilian passenger expansion. Construction timelines remain contingent on completing detailed project reports, feasibility assessments, geological surveys in the rugged terrain, and requisite environmental and security clearances, with no firm start date announced as of October 2025. While the extension promises ancillary economic benefits like improved access for local agriculture and tourism, official statements underscore its defense-oriented purpose amid ongoing border tensions. No further extensions beyond Uri toward the PoK border have received approval, though preliminary discussions highlight potential for additional strategic spurs post-feasibility validation. Parallel capacity enhancements, such as doubling the existing 73.5 km Qazigund–Badgam section, support overall network resilience but do not constitute new line extensions. These measures aim to alleviate bottlenecks on the current single-track alignment through the Pir Panjal range, indirectly aiding future extension viability by increasing throughput for both freight and defense logistics.

Infrastructure Upgrades and Connectivity Enhancements

The doubling of the 73.5 km Qazigund–Budgam section was approved by the Indian Ministry of Railways in September 2025, aimed at decongesting the existing single-track corridor and enabling higher train frequencies to meet growing demand in the Kashmir Valley. This capacity expansion integrates with the fully operational Jammu–Baramulla line, allowing for doubled throughput without new greenfield construction. Electrification of critical segments, including the 185.66 km stretch commissioned with electric traction by June 2025, has been completed to support faster acceleration, reduced operating costs, and integration with India's broader electrified network. Complementary signaling enhancements, such as advanced color-light systems, permit train speeds up to 100 km/h in operational sections, improving throughput and safety on the mountainous alignment. These upgrades emphasize rail's reliability over road-rail synergies for winter connectivity, as the tunnel-dominated line remains operational amid frequent highway closures from snowfall and avalanches, ensuring consistent freight and passenger links to Jammu and beyond.

References

  1. [1]
    ::Welcome to J&k SLBC ::
    From Jammu to Baramulla, length of the new rail line is 345 km. It passes through the young Himalayas, tectonic thrusts and faults. The work on Jammu-Udhampur ...
  2. [2]
    Modi opens new line to Kashmir - International Railway Journal
    Jun 12, 2025 · INDIA's prime minister, Narendra Modi, officially opened the 272km Udhampur - Srinagar - Baramulla Rail Link (USBRL) on June 6.Missing: details | Show results with:details
  3. [3]
    Udhampur-Srinagar-Baramulla Link: How Railways beat seemingly ...
    Jun 6, 2025 · The USBRL, built at a cost of approximately ₹44,000 crore, spans 272 km and features 36 tunnels and 943 bridges, including the world's highest ...
  4. [4]
    Vision & Mission - Northern Railways / Indian Railways Portal
    ... Jammu & Kashmir, Govt. of India planned a 272 Km. long Railway Line from Udhampur to Baramulla joining the Kashmir valley with the Indian Railways network ...
  5. [5]
    Kashmir Gets Major Rail Link Today, What Makes It An Engineering ...
    Jun 6, 2025 · Of the 272 km long Udhampur-Srinagar-Baramulla rail route, about 119 km journey passes through 36 tunnels, including T-50, India's longest ...Missing: stations | Show results with:stations
  6. [6]
    Rail Renaissance in Jammu and Kashmir - PIB
    Jun 4, 2025 · Part of the Udhampur–Srinagar–Baramulla Rail Link (USBRL), it features 10.9 km of tunnels, 36 bridges, and a modernised Katra station. Also, 700 ...
  7. [7]
    A Dream Deferred For A Century: The Udhampur-Baramulla Rail ...
    Sep 15, 2025 · The USBRL project spans 272 kilometres. This strategically planned rail corridor connects the Kashmir Valley with the rest of the country.
  8. [8]
    USBRL Project: Kashmir Gets Mega Rail Link, A Look At Key ... - NDTV
    Jun 6, 2025 · The 272-km Udhampur-Srinagar-Baramulla Rail Link (USBRL) project has been constructed at Rs 43,780 crore. It has a total of 36 tunnels ...Missing: route length segments
  9. [9]
    Udhampur – Srinagar – Baramulla Rail Link Project - Konkan Railway
    Jan 9, 2020 · There are 17 tunnels aggregating length of 46.1 Kms. The longest tunnel is Tunnel No.13 of 9.368 Kms length. Four Tunnels i.e. Tunnel No. 2, 5, ...Missing: segments | Show results with:segments
  10. [10]
    Udhampur-Srinagar-Baramulla Rail Link most difficult project - ET Infra
    Dec 21, 2023 · According to him, 97.42 km out of 111 km, which is 87 per cent of the total length of Katra-Banihal section, is in tunnels and the maximum ...
  11. [11]
    [PDF] RAIL LINK PROJECT IN STATE OF JAMMU & KASHMIR 1. Overview
    May 31, 2025 · It comprises of 44.59km (85.5%) of route in tunnels, 4.6 km (8.8%) of route on bridges and balance 5.7% of route in cuttings and embankments.
  12. [12]
    [PDF] USBRL KASHMIR RAIL LINK PROJECT 2002-2020
    The 356 km rail route, once fully completed, will start from. Jammu and will end at Baramulla in the Kashmir Valley. The Udhampur-Srinagar-Baramulla Rail Link ( ...
  13. [13]
    Know why Udhampur-Srinagar-Baramulla (USBRL) rail link with ...
    Jun 6, 2025 · Symbol of national integration. The USBRL project marks a significant step in connecting remote and mountainous regions of Jammu and Kashmir ...Missing: connectivity | Show results with:connectivity
  14. [14]
    Kashmir To Be Linked By Vande Bharat Express In Historic Rail ...
    Jun 4, 2025 · This new rail link will unite Kashmir and Kanyakumari via a continuous railway line, realizing a seven-decade-old vision of national integration ...
  15. [15]
    10 reasons why Udhampur-Srinagar-Baramulla Rail Link is a game ...
    Jun 6, 2025 · The new rail link in Jammu and Kashmir will provide strategic advantage by allowing the rapid movement of military personnel and supplies to border areas.Missing: geopolitical | Show results with:geopolitical
  16. [16]
    Strategic win: Army runs first freight train on USBRL, to return with ...
    Sep 15, 2025 · This is strategically significant as it gives a boost to the logistics capability of the Army. · The train carried 753 metric tonnes of Advance ...Missing: importance | Show results with:importance
  17. [17]
    Army's first exclusive freight train reaches Anantnag; strengthens ...
    Sep 15, 2025 · The train carried 753 metric tonnes of Advance Winter Stocking (AWS) loads for Indian Army units and formations in J&K, marking a decisive ...
  18. [18]
    In a first, Army's winter supplies reach Kashmir by freight train
    Sep 16, 2025 · The freight train carried 753 metric tonnes of advance winter supplies for Army units and formations in Kashmir, marking a major shift in the ...
  19. [19]
    Centre boosts J&K rail network with new Baramulla-Uri line and ...
    Sep 4, 2025 · Centre boosts J&K rail network with new Baramulla-Uri line and Qazigund-Badgam doubling · Length: 74 km (doubling the existing single track) ...
  20. [20]
    Historic Rail Link Connects Kashmir Valley with Katra via Vande ...
    Jun 7, 2025 · A 272-km railway connecting Udhampur, Srinagar, and Baramulla, enhancing connectivity and economic integration with the Kashmir Valley.
  21. [21]
    Indian Railways plans to introduce new train in J&K with THESE ...
    Sep 27, 2024 · The USBRL project was sanctioned in 1994-95. · The 338-km-long USBRL project will not only boost the rail connectivity in the Union Territory (UT) ...
  22. [22]
    Train to Kashmir: How railways beat Himalayan odds to build a marvel
    Jun 7, 2025 · The Udhampur-Srinagar-Baramulla Rail Link (USBRL), set to be ... Udhampur in early 1997. Many thought the task of carving a route ...
  23. [23]
    Udhampur-Srinagar-Baramulla rail link project fully operational after ...
    Jun 7, 2025 · Northern Railways completes 272-km Udhampur-Srinagar-Baramulla Rail Link Project in multiple phases, inaugurated by PM Modi in 2025.Missing: segments | Show results with:segments
  24. [24]
    Construction Department - Northern Railways / Indian Railways Portal
    For USBRL project, Chief Administrative Officer/Construction/USBRL (CAO/C/USBRL) is headquartered at Jammu. This department undertakes all major construction ...
  25. [25]
    Udhampur-Srinagar-Baramulla Rail Link Fully Operational After 28 ...
    the Sangaldan to Katra section, making the entire rail line ...
  26. [26]
    "Historic Milestone" Achieved In Udhampur-Srinagar-Baramulla Rail ...
    Dec 13, 2024 · The first phase, the 118-km Qazigund-Baramulla section, was commissioned in October 2009. This was followed by the 18-km Banihal-Qazigund ...Missing: construction | Show results with:construction
  27. [27]
    Banihal-Qazigund Railway Tunnel - Wikipedia
    Banihal-Qazigund Railway Tunnel ; June 2013 · Indian Railways · Indian Railways.Missing: breakthrough | Show results with:breakthrough
  28. [28]
    Full Kashmir Rail Link Now Operational After 28 Years
    Jun 11, 2025 · This final stretch was completed in two parts: Banihal to Sangaldan in February 2024 and Sangaldan to Katra on 6 June 2025. The newly completed ...
  29. [29]
  30. [30]
    PM to visit Jammu and Kashmir on 6th June - PIB
    Jun 4, 2025 · Prime Minister will also dedicate Udhampur-Srinagar-Baramulla Rail Link (USBRL) project to the nation. The 272 km long USBRL project, ...
  31. [31]
    Kashmir's First All-Weather Rail Link to Delhi Inaugurated
    Jun 6, 2025 · India inaugurates the first all-weather rail link between Delhi and Kashmir, enhancing regional connectivity and national integration.<|separator|>
  32. [32]
    A dream realised after 127 years' June 6 to mark historic day for ...
    Jun 4, 2025 · In 1905, he approved the construction of a narrow 762 mm gauge railway via Reasi, which would eventually evolve into the modern USBRL project.
  33. [33]
    [PDF] Indian Railways Project - Cla-Val
    The Udhampur -Srinagar- Baramulla. Railway Link (USBRL). With a plan to provide an alternate safe and reliable transport system to Jammu and Kashmir in the ...
  34. [34]
    (PDF) Tunnel Construction in Pir Panjal (Himalaya) Using NATM ...
    Aug 6, 2025 · New Austrian Tunnelling Method (NATM) was Preferred over TBM. ... "Design features of Jammu-Udhampur-Srinagar-Baramulla Rail Link Project".
  35. [35]
    Tunnelling Techniques: Methods being deployed in India
    Feb 18, 2024 · Various methods are being used for the construction of tunnels. These include conventional techniques such as the drill-and-blast method (DBM), tunnel boring ...Missing: link | Show results with:link
  36. [36]
    Pir Panjal Railway Tunnel: India's Longest Rail Link Guide
    Jun 28, 2025 · Breakthrough Date: The two ends of the tunnel met with precision on October 28, 2011. Contractor: The project was executed by the Hindustan ...
  37. [37]
    India's longest rail tunnel opens
    Jul 2, 2013 · ... Pir Panjal Tunnel – on Wednesday, June 26. Built at a cost of Rs10bn ... It has five groups of five roof-mounted ventilation fans, and ...<|separator|>
  38. [38]
    India's longest railway tunnel: Decoding the features of Pir Panjal ...
    May 7, 2024 · The Pir Panjal Railway Tunnel is equipped with modern safety and efficiency features. An emergency escape passage and a ventilation system ...
  39. [39]
    Tale of tunnels and bridges: Railway's mammoth Himalayan project ...
    Dec 26, 2024 · This includes the longest transportation tunnels ever built in India such as the Sumber-Arpinchala (T-49) of 12.75 km and the Pir Panjal (T-80) ...
  40. [40]
    Breakthrough of the Escape tunnel (12.895 km) of the longest ... - PIB
    Dec 15, 2022 · ... Tunnel T-49 between Sumber and Khari Stations on the Katra –Banihal section of the USBRL project. The length of the escape tunnel is 12.895 km.
  41. [41]
    India's longest transportation tunnel opens in Jammu on Udhampur ...
    Feb 20, 2024 · The 12.77-km-long tunnel, known as T-50, is part of the Banihal-Khari-Sumber-Sangaldan section, allowing trains to run from Baramulla to Sangaldan.
  42. [42]
    Inside India's longest transportation tunnel T-50 on Udhampur ...
    Feb 21, 2024 · The tunnel, which is 12.77 km long and known as T-50, falls between the Khari-Sumber section of Udhampur-Srinagar-Baramulla Rail Link.
  43. [43]
    Engineers develop new tunnelling method for Kashmir rail link project
    Oct 23, 2023 · "We have innovatively developed (I)-TM as Himalayan tunnelling method for tunnelling through the Himalayan geology to build tunnels in Jammu ...
  44. [44]
    Chenab Bridge: How India Built World's Highest Railway Arch Under ...
    Jun 6, 2025 · The 1,315-metre (m) Chenab bridge is a critical component of the Rs 35,000 crore Udhampur-Srinagar-Baramulla Rail Link (USBRL) project, which ...
  45. [45]
    Chenab Rail Bridge and Anji Khad Bridge - Drishti IAS
    Jun 10, 2025 · About Chenab Rail Bridge: Located in Reasi district, it is the world's highest railway arch bridge, standing 359 metres tall—35 metres higher ...<|control11|><|separator|>
  46. [46]
    All You Need to Know About the Chenab Rail Bridge - Dwello
    Jun 26, 2025 · The Chenab Rail Bridge is a steel and concrete arch bridge with state-of-the-art design features. Its total length is 1315 metres, and the main arch span ...
  47. [47]
    Anji Khad Bridge's Design and Construction - ConstroFacilitator
    Jun 21, 2025 · It has a total length of 725.5 metres, including a 473.25-metre cable-stayed span that stretches across a deep gorge. The bridge deck is built ...Missing: facts | Show results with:facts
  48. [48]
    'Challenging' trial run on 179-degree rising gradient successful ...
    Jan 9, 2025 · The Indian Railways Wednesday successfully conducted a trial run on the 179-degree rising gradient between Katra-Banihal stretch of the Udhampur-Srinagar- ...Missing: steepest | Show results with:steepest
  49. [49]
    India's dream of a direct rail link to Kashmir moves closer to reality
    Jan 9, 2025 · The Indian Railways on Wednesday successfully conducted a trial run on the steep 179-degree gradient of the Katra-Banihal section of the ...Missing: electrification features<|separator|>
  50. [50]
    Electrification in the foothills of the Himalayas – completion of major ...
    Jul 1, 2025 · Together with a local project partner, we have successfully completed the electrification of the Katra–Dharam section in the Indian union ...
  51. [51]
    Forging Paths Through Mountains, Connecting Hearts Across India
    Electronic interlocking systems were installed at all 23 stations, redefining safety and reliability for passengers and trains alike.Missing: gradient | Show results with:gradient
  52. [52]
    Jammu-Baramulla railway line: A revolutionary project for uplifting ...
    Jan 31, 2022 · Three aspect colour-light signaling is being installed on the route for safety, and GSM-R equipment may be installed in the future to improve ...Missing: gradient | Show results with:gradient
  53. [53]
    Kavach: The Shield of Safety - PIB
    Dec 10, 2024 · Indian Railways has unveiled Kavach, a state-of-the-art Automatic Train Protection (ATP) system that represents a breakthrough in indigenous technology.Missing: Baramulla | Show results with:Baramulla
  54. [54]
    Udhampur-Srinagar-Baramulla Rail Link Despite Being One of ... - PIB
    Aug 6, 2025 · The USBRL project (272 Km) has been constructed completely in the Union territory of Jammu & Kashmir. Land acquisitions were carried out as per ...Missing: geopolitical | Show results with:geopolitical
  55. [55]
    ArcelorMittal rails power an iconic new route in India
    Jun 17, 2025 · The Udhampur – Srinagar – Baramulla rail link (USBRL) project, inaugurated on June 6, 2025, by Indian Prime Minister Narendra Modi, marks a ...Missing: early obstacles
  56. [56]
    Conventional Tunnelling Challenges In The Himalayas: A Case Study
    Feb 10, 2025 · Hey presto, we have completed, in all respects, the Pir Panjal tunnel track and made it operational for movement of passenger trains.
  57. [57]
    Fault system dynamics of the Kashmir, NW Himalaya, India using ...
    The focal mechanism solutions of the earthquakes in and around the Kashmir Valley suggest dominant thrust faulting followed by normal faulting. Analysis of the ...
  58. [58]
    The Pir Panjal Railway Tunnel | Request PDF - ResearchGate
    Aug 6, 2025 · Shear zones with thick fault gouge and highly crushed rock were also encountered, posing extreme tunneling challenges. [26, 62] Rock Behavior ...Missing: landslides | Show results with:landslides
  59. [59]
    Tunneling in Himalaya's | PDF | Landslide - Scribd
    Tunnel lays along the Udhampur-Qazigund section, which features the most complex geology in the USBRL. Having encountered severe difficulties during excavation ...
  60. [60]
    Geology of Pirpanjal railway tunnel, Jammu and Kashmir, India
    Such slope hazards act to increase the complexity of the geological conditions, induce tunnel instabilities, cause costly delays, interference with construction ...Missing: Baramulla | Show results with:Baramulla
  61. [61]
    Pir Panjal: NATM in the Himalayas - Tunnels
    Feb 12, 2010 · The Pir Panjal railway tunnel is the first major tunnel in India to be constructed using NATM and has had to overcome labour strikes, equipment ...Missing: challenges | Show results with:challenges
  62. [62]
    [PDF] USBRL Technical News Magazine - HIM PRABHAT - iricen
    Jun 14, 2017 · An adequately selected rock fall protec- tion system for a tunnel portal can substantial- ly reduce the risk of any fatality and/or delay. The ...
  63. [63]
    Katra-Banihal Railway: 93 Of 114 Kms Inside Tunnels | Kashmir Life
    Feb 4, 2021 · The total length of tunnels from Jammu to Baramulla is 174 kilometres including the 93 kilometres on the Jatra-Banihal stretch. A total of 124 ...
  64. [64]
    Reinforced Soil System for Railways at USBRL Project in Jammu
    Aug 20, 2024 · Around 3 lakh cubic meters of tunnel muck, a site-won waste from tunnel excavation, was used to build the reinforced soil (RS) structure ...Missing: total volume<|separator|>
  65. [65]
    Udhampur-Srinagar-Baramulla Rail Link | Geotechnical Monitoring
    Deep Excavation Monitoring ... Encardio-rite was awarded the instrumentation and monitoring contract for almost 20 large tunnels on this rail link project.Missing: volume | Show results with:volume<|separator|>
  66. [66]
    Kashmir witnesses 29 targeted attacks on civilians compared to 12 ...
    Jan 1, 2023 · Official data suggests militants carried out around 29 targeted attacks in Kashmir this year, especially on civilians that included non-local labourers and non ...
  67. [67]
    Post-Article 370 infrastructure is rebuilding Jammu & Kashmir
    Jul 11, 2025 · The most ambitious integration project is the Udhampur-Srinagar-Baramulla Rail Link (USBRL). This long-awaited rail project connects the ...
  68. [68]
    Infrastructure of integration: How abrogation of article 370 enabled ...
    Aug 4, 2025 · At 359 metres above the riverbed—taller than the Eiffel Tower—it anchors the 272-kilometre Udhampur–Srinagar–Baramulla Rail Link, a dream ...
  69. [69]
    The train to Kashmir: How it can be a gamechanger for tourism and ...
    Jun 7, 2025 · This was the Udhampur-Srinagar-Baramulla Rail Link (USBRL) Project, which was approved in March 1995 at an estimated cost of Rs 2,500 crore. In ...
  70. [70]
    Why railway connectivity in Jammu and Kashmir is such a challenge
    Oct 10, 2019 · The biggest challenges of the Jammu and Kashmir railway project are geographical. The alignment passes through major geological thrust zones in the region ...Missing: logistical aerial
  71. [71]
    Udhampur-Srinagar-Baramulla rail link update - The Financial Express
    Jul 27, 2024 · He said that the expected project cost is Rs 41,000 crore, of which, Rs 38,931 crore expenditure has been incurred up to March 2024.Missing: comparison | Show results with:comparison
  72. [72]
    An Engineering Marvel, Decades in the Making: A Rail Line to Kashmir
    Jun 6, 2025 · The new 170-mile line, known as the Udhampur-Srinagar-Baramulla rail link, was built at a cost of about $4.4 billion through some of the world's most ...Missing: details | Show results with:details
  73. [73]
    "Challenging project": IRCON's JGM Ashwani Dayal on ... - ANI News
    Jun 6, 2025 · The railway project showcases IRCON's engineering expertise and commitment to safety and infrastructure development in the region. Earlier, ...Missing: aerial | Show results with:aerial
  74. [74]
    Modi inaugurates strategic railway project in Indian-administered ...
    Jun 6, 2025 · Dubbed by the government-operated Indian Railways as one of the most challenging tracks in the world, the 272-kilometre (169-mile) line begins ...
  75. [75]
    CAG flays railways for delay, cost overruns in Kashmir project
    Dec 20, 2012 · “The single most important reason for delay and other related problems in execution of the project is poor planning,” observed the Comptroller ...
  76. [76]
    Vande Bharat from Katra to Srinagar: PM Modi inaugurates new ...
    Jun 6, 2025 · Regular Vande Bharat services to Kashmir will commence on June 7, 2025. These trains will initially run from Katra to Srinagar six days a week.
  77. [77]
    Kashmir Vande Bharat service to start from this date
    Jun 5, 2025 · Train 26403 will leave Katra at 2:55 PM, arriving in Srinagar at 5:53 PM, stopping at Banihal at 4:40 PM. This train will not run on Wednesdays.
  78. [78]
  79. [79]
    Jammu and Kashmir: Vande Bharat Train Timings Announced
    Jun 4, 2025 · The trains will operate six days a week, with one day reserved for maintenance. From Srinagar, train number 26402 will depart at 14:00 hrs and arrive at Jammu ...
  80. [80]
    Postfloods: Railways to resume 16 Jammu Tawi trains from Oct 1
    Sep 30, 2025 · Postfloods: Railways to resume 16 Jammu Tawi trains from Oct 1 · Tracks &infrastructure repaired; safety checks ensure phased resumption: ...<|separator|>
  81. [81]
  82. [82]
    USBRL Milestone: First Freight Train Reaches Kashmir
    Aug 9, 2025 · This landmark event marks the operational debut of the newly commissioned Banihal-Sangaldan-Reasi-Katra section of the Udhampur-Srinagar- ...Missing: phase | Show results with:phase
  83. [83]
    First freight train reaches Kashmir valley from Punjab - Deccan Herald
    Aug 9, 2025 · The first loaded freight train arrives at Anantnag railway station, J&K, Saturday, Aug. 9, 2025. The Northern Railway zone had approved Anantnag ...<|separator|>
  84. [84]
    Freight operations commence in Kashmir
    Aug 9, 2025 · ... Jammu Division, has officially commenced freight operations at the station, allowing both inward and outward movement of goods. He said the ...
  85. [85]
    1st Freight Train With Supplies For Army Reaches Kashmir, Returns ...
    Sep 15, 2025 · In a first, a freight train delivered winter supplies to the Indian Army in Kashmir's Anantnag even as the Srinagar-Jammu National Highway ...
  86. [86]
    USBRL Freight Triumph: 753 MT Army Supplies Reach Kashmir ...
    Sep 16, 2025 · The USBRL, completed in February 2024, aligns with the National Rail Plan 2030 for 100% electrification, potentially increasing cargo volume by ...
  87. [87]
    Railway Minister announces parcel train to transport apples from ...
    Sep 12, 2025 · Railway Minister launches daily parcel train service to aid Kashmir apple growers, easing transportation struggles amid highway closures.
  88. [88]
    Commissioning USBRL Project: Game Changer for Valley's ...
    Jan 16, 2025 · Freight rail enables high capacity goods movements over very long distances, allowing access to trade for resources that otherwise are ...
  89. [89]
    99th Meeting of Network Planning Group under PM GatiShakti ... - PIB
    Sep 3, 2025 · At present, the Qazigund–Baramulla line operates as a single track. With the commissioning of the Katra–Banihal section in 2025, the corridor ...
  90. [90]
    New Jammu Railway Division effective from June 1. What it means ...
    Jun 2, 2025 · The newly formed Jammu Division, headquartered at Jammu Tawi and operating under Northern Railway, has come into effect from June 1.
  91. [91]
    Rlys enhances track safety in Kashmir ahead of snow season
    Oct 9, 2025 · The Divisional Railway Manager (DRM), Jammu, has directed regular monitoring and destressing of railway tracks between Sadura and Panzgom to ...
  92. [92]
  93. [93]
    Indian Railways | Jammu and Kashmir rail upgrade - DD News
    Jul 27, 2025 · The upgraded rakes are being fitted with enhanced features to improve passenger comfort and safety. These include anti-graffiti PU exterior ...Missing: collision signaling
  94. [94]
    Security Arrangements along the Katra-Baramulla train route
    Jan 23, 2025 · The main activities involved will be patrols of the railway system most by units of Jammu and Kashmir Police, RPF, and CRPF by sanitizing of ...
  95. [95]
    Indian Railways Enhances Security on Kashmir Rail Link After ...
    Apr 24, 2025 · Following the tragic incident, Northern Railway has implemented enhanced security protocols along the 272-km Udhampur-Srinagar-Baramulla Rail ...
  96. [96]
    RPF's Commandos For Railway Security To Protect J&K Vande ...
    Jun 6, 2025 · The trains will run six days a week, with Tuesdays reserved for maintenance, Railway officials said. To begin with, the trains will operate ...
  97. [97]
  98. [98]
    Can Vande Bharat trains for Kashmir cope with enhanced risks of ...
    Jan 12, 2025 · Ex-railway engineer points out enhanced fire risks as 87 per cent of 111 km route passes through single-track tunnels.
  99. [99]
    Udhampur-Srinagar-Baramulla railway line set to be inaugurated in ...
    Jan 23, 2025 · Udhampur-Srinagar-Baramulla Rail Link (USBRL) project is set for its much awaited official inauguration in the first week of February 2025.<|separator|>
  100. [100]
    USBRL Project Boosts Connectivity & Development In J&K
    Apr 14, 2025 · Strategically, the railway enhances national security by enabling faster troop and resource mobilization, while its electrification contributes ...
  101. [101]
    USBRL project generates massive employment in J&K
    Apr 15, 2025 · A total of 14,069 jobs were generated through project executing agencies, with a substantial 65% of these positions given to locals from Jammu ...
  102. [102]
    Press Release: Press Information Bureau - PIB
    Aug 6, 2025 · The project has generated more than 5 Cr. man-days of employment. Another crucial facet of the USBRL Project's socio-economic development ...
  103. [103]
    Over 14K workers employed in Katra-Kashmir rail project
    Jun 5, 2025 · As many as 14,069 workers were provided employment by project executing agencies during construction period out of which 65% employment was ...
  104. [104]
    First-ever freight train arrives in Valley, marks new era of logistical ...
    Aug 9, 2025 · The freight connectivity is expected to give a new lease of life to Kashmiri fruit and handicraft industry by easing access to markets ...Missing: impact | Show results with:impact
  105. [105]
  106. [106]
    Rail line to Kashmir: Strategic asset, boon for economy - The Tribune
    Jun 7, 2025 · Economically, the direct rail link is expected to revolutionise the transportation of dry fruits and apples from Kashmir to distant markets ...
  107. [107]
    How the Udhampur Srinagar Baramulla Railway Line in J&K will ...
    Jan 22, 2025 · The connectivity is set to expedite trade, tourism, and other economic activities. Besides the Vande Bharat train, Indian Railways plans to ...
  108. [108]
    Kashmir rail link to boost economy, tourism: Bizmen - Hindustan Times
    Jun 4, 2025 · The rail link project, which includes 36 tunnels (spanning 119km) and 943 bridges, is set to transform regional mobility and drive socio-economic integration.<|separator|>
  109. [109]
    Udhampur-Srinagar-Baramulla Rail Link Built with Global Safety ...
    Aug 7, 2025 · 66 km of escape tunnels and fire-fighting systems have been installed for passenger safety. Mechanical ventilation ensures clean air in all ...
  110. [110]
    USBRL project will boost spiritual tourism, create livelihood ...
    Jun 5, 2025 · ... on Thursday said that the Udhampur-Srinagar-Baramulla Rail Link (USBRL) project will boost spiritual tourism and create livelihood opportunities<|separator|>
  111. [111]
    Kashmir Rail Link To Boost Trade, Tourism: President – Kashmir ...
    The inauguration of the rail link in Kashmir Valley is a major accomplishment. Rail connectivity with the Valley will boost trade and tourism in the region and ...
  112. [112]
    Part 3: The major military implications of the Udhampur–Srinagar ...
    Jun 8, 2025 · 1. Strategic Importance Rapid Troop Mobilization The USBRL enables the Indian Army to quickly transport troops, armoured units, ...
  113. [113]
    Part 1: The major military implications of the Udhampur–Srinagar ...
    Jun 6, 2025 · Faster Troop Movement: The rail line drastically reduces the time taken to move troops, artillery, and supplies to forward areas like ...
  114. [114]
    *Indian Army's First Exclusive Freight Train on USBRL ... - Facebook
    Sep 15, 2025 · ... Train the first exclusive freight train of the Indian Army, from *BD Bari* to *Anantnag* on 12–13 September. The train carried *753 metric ...<|separator|>
  115. [115]
    Rs 12 Billion Rail Projects to Boost Connectivity in Jammu & Kashmir
    Sep 10, 2025 · The Baramulla–Uri line will connect the frontier town directly to the Valley's railway grid, offering the armed forces a safer and faster supply ...
  116. [116]
    Railways clears Bla-Uri line, Qazigund–Budgam doubling project
    Sep 5, 2025 · “The doubling project is of strategic importance, enabling seamless movement of military special trains carrying Army personnel, equipment, and ...
  117. [117]
    Railway to India-controlled Kashmir: Development or domination?
    Jul 10, 2025 · With an evident dual-use role, the railway enhances India's logistical and military preparedness in the areas adjacent to Pakistan and China. It ...
  118. [118]
    Missed bridges, ecological toll: Is the Kashmir rail link a train in vain?
    Dec 1, 2024 · The upcoming Kashmir rail link is being celebrated as an engineering marvel with breathtaking views. But it glosses over the heavy toll on local communities ...Missing: criticisms | Show results with:criticisms
  119. [119]
    chenab bridge legal and environmental challenges behind the ...
    Aug 15, 2025 · The Chenab Bridge project required environmental clearances under the Environment (Protection) Act, 1986 and forest clearance under the Forest ( ...
  120. [120]
    New Railway Lines Would Severely Impact Kashmir's Apple Industry
    Mar 12, 2024 · Sacrificing 5500 Kanals of agriculture land will be disastrous as our valley has very small landholdings ... Recently, Prime Minister Narendra ...Missing: displacement criticisms
  121. [121]
    [PDF] Innovations and Site-Specific Solutions Implemented on USBRL ...
    Salient features of USBRL Project: The length from Udhampur to Baramulla is 272 km and has been divided into four sections. The salient features of these ...
  122. [122]
    [PDF] INDIAN RAILWAYS CONSTRUCTION MANUAL
    ... Clearance. ECBC. –. Energy Conservation Building Code. EIA. –. Environmental ... Afforestation. (CA) and Net Present Value (NPV). Similarly, plans such as ...<|separator|>
  123. [123]
    Residents of Jammu & Kashmir fear impacts of lithium mining
    May 19, 2023 · In 2015, the construction of a 6 km-long railway tunnel between Gram Morh, Reasi and Bakkal led to road cutting and deforestation. A once- ...Missing: criticisms | Show results with:criticisms
  124. [124]
    Kashmir Railway Projects: Threatening Livelihoods, Culture & Climate
    Dec 19, 2024 · The proposed lines are expected to affect 288 hectares of land, much of it fertile farmland, posing significant risks to agricultural livelihoods.
  125. [125]
    Centre Reviews 40km Baramulla-Uri Rail Line, Qazigund-Badgam ...
    Sep 4, 2025 · The Union government approved a 40km Baramulla-Uri rail line and doubling of the Qazigund-Badgam line to boost connectivity in Jammu and ...
  126. [126]
    New rail line between Baramulla and Uri to bring trains ... - The Week
    Sep 6, 2025 · The Ministry of Railways has proposed the construction of a 40.2 km railway line between Baramulla and Uri. The move carries immense ...
  127. [127]
    Railways Approves Baramulla–Uri Line, Qazigund–Budgam ...
    a new 40.2 km Baramulla–Uri railway line ...
  128. [128]
    Railways clears 40 km Baramulla–Uri rail link, 73 km Qazigund ...
    Sep 4, 2025 · According to a statement, the 40.2 km Baramulla–Uri line will extend rail connectivity to the border town of Uri near Kaman Post.
  129. [129]
    J&K: Centre approves 40 Km Baramulla–Uri Rail Line, Qazigund ...
    Sep 4, 2025 · Baramulla to Uri new Broad Gauge (BG) line will provide all-weather, reliable rail connectivity, addressing frequent disruptions faced by road ...Missing: extension geostrategic
  130. [130]
    J&K: New railway line between Baramulla & Uri sanctioned
    Sep 4, 2025 · The Union government has approved a new 40 km Baramulla-Uri rail line and doubling of the Qazigund to Badgam line to boost train connectivity ...<|separator|>
  131. [131]
    Railways Clears 40 Km Baramulla–Uri Rail Link, 73 Km Qazigund ...
    Sep 4, 2025 · According to a statement,the 40.2 km Baramulla–Uri line will extend rail connectivity to the border town of Uri near Kaman Post. The statement ...
  132. [132]
    Shortest Rail Distance: Jammu Tawi to Baramula
    India Rail Info provides the operational rail distance from Jammu Tawi to Baramula as 323.41 km, rounding to 324 km for the Jammu–Baramulla line.