Delaware Aqueduct

The Delaware Aqueduct is an 85-mile-long concrete-lined that serves as a vital component of the water supply system, conveying approximately 600 million gallons of per day by gravity from the Rondout Reservoir in Ulster County to the Hillview Reservoir in Yonkers, thereby providing about half of the city's water needs for nearly 10 million residents across the five boroughs and surrounding areas. Constructed between 1937 and 1944 at a depth of up to 1,550 feet below the surface and crossing under the , it connects water from the Basin's upstream reservoirs—including the Pepacton, Neversink, and Cannonsville—to the Rondout Reservoir before distribution to intermediate storage at the West Branch and Kensico Reservoirs en route to the city. With a ranging from 13.5 to 19.5 feet, the aqueduct was engineered as the world's longest continuous of its kind upon completion and remains a cornerstone of the unfiltered water delivery infrastructure that draws from 19 reservoirs and three controlled lakes spanning over 125 miles northwest of the city. Since the 1990s, the aqueduct has faced significant challenges from leaks, particularly in the Rondout-West Branch Tunnel section, resulting in the daily loss of about 35 million gallons of water—equivalent to the needs of a small city—prompting the New York City Department of Environmental Protection (DEP) to initiate extensive monitoring and repair efforts. These leaks, identified near Wawarsing and Roseton, have necessitated a $2 billion bypass tunnel project, including a 2.5-mile parallel bypass tunnel constructed between 2017 and 2021 to divert flow around damaged sections. Final connections and repairs, originally planned for 2024–2025, have been delayed and are now expected after 2027, involving an extended shutdown of the aqueduct to ensure long-term reliability without compromising supply. However, as of May 2025, the final phase was paused, and DEP announced plans for a new contract. The system's design, approved in 1928 as part of broader Delaware River Basin agreements, underscores its historical significance in addressing New York City's growing water demands during the early 20th century, while ongoing optimizations—such as Catskill Aqueduct enhancements and groundwater reactivation—support resilience during maintenance.

History

Planning and Construction

In the early 20th century, New York City's population surged past 3 million residents, straining the existing water supply infrastructure and necessitating expansion beyond the Croton and Catskill systems. The Catskill Aqueduct, initiated in 1907 and completed in stages by 1927, delivered up to 610 million gallons per day but proved insufficient to meet the city's growing demands driven by urbanization and industrial growth. Planning for the Delaware System began in earnest in 1927 when the Board of Water Supply proposed developing reservoirs on the River's tributaries to secure an additional 640 million gallons per day. This initiative faced opposition from downstream states, particularly , over potential reductions in river flow; negotiations led to a proposed in 1927 involving , , , and the federal government to regulate diversions. The dispute culminated in the U.S. Supreme Court case (283 U.S. 336), where the Court in 1931 approved 's right to divert up to 440 million gallons daily from the upper Basin, subject to minimum flow protections for downstream users. City voters and the state legislature subsequently authorized the project in 1937. Construction commenced in March 1937 with the initial phase focused on the Rondout Reservoir and associated shafts, marking the start of a multi-stage effort projected to span over a decade. Boring for the Delaware Aqueduct itself began in 1939, involving drill-and-blast techniques to excavate through challenging including Normanskill , Wappinger , and dolomitic formations, which posed risks of water inflows and structural instability. caused significant delays from 1941 onward due to material shortages and labor reallocations, slowing progress on the 85-mile tunnel despite its overall length establishing it as the world's longest continuous water tunnel. The aqueduct entered partial on April 5, 1944, when Fiorello La Guardia opened the gates at Hillview Reservoir, allowing initial water flow from the Rondout section; full operational completion followed in 1953 after wartime setbacks were overcome. The project, encompassing dams, tunnels, and reservoirs, was estimated at approximately $272 million in 1939 dollars, equivalent to over $4.8 billion when adjusted for inflation to 2025.

Early Operations

Upon its operational handover following construction completion, the Delaware Aqueduct achieved first full flow in 1953, coinciding with the activation of the Rondout Reservoir and Merriman Dam, which enabled consistent delivery from the basin. This initial phase supplied up to 650 million gallons per day (mgd), accounting for approximately 50% of City's total water needs at the time. The aqueduct's gravity-fed design relied on the elevation differential between the upstate reservoirs and the city, ensuring efficient transport without pumps. Key operational milestones in the early years included seamless integration with the existing Croton and Catskill systems through interconnection points at the West Branch and Kensico Reservoirs, allowing for balanced distribution and redundancy during variable demand periods. Monitoring technologies, such as early flow meters installed at access shafts along the route, enabled real-time tracking of water volumes and pressure to optimize delivery. Expansions during this era, including the addition of further shafts for enhanced access and control, supported growing utilization as subsequent reservoirs like Neversink (1953) and Pepacton (1955) came online. Routine maintenance practices emphasized proactive oversight to sustain reliability through the . Periodic inspections were performed via the aqueduct's vertical access shafts, which provided entry points for structural assessments, flow regulation, and chemical dosing to maintain water integrity. management involved targeted flushing operations at diversion points to prevent buildup, while testing protocols, formalized in the 1960s under City's expanding environmental standards, included regular sampling for and contaminants at key junctions like Shaft 18. Early challenges primarily involved minor ground settling around shaft sites and fine-tuning pressure gradients to accommodate fluctuating levels, both addressed through routine adjustments and reinforcements without interrupting . These issues were resolved efficiently, underscoring the aqueduct's robust for long-term performance.

Design and Route

Technical Specifications

The Delaware Aqueduct measures 85 miles (137 ) in length, making it the world's longest continuous tunnel upon its completion in 1944. The tunnel features a circular cross-section with a of 13.5 feet (4.1 m) in its primary sections, though it varies up to 19.5 feet (5.9 m) in certain areas to accommodate flow requirements, with the larger of up to 19.5 feet (5.9 m) in the final 21 (13 miles) to accommodate higher flow requirements. It was excavated through solid , reaching depths of up to 2,000 feet (610 m) below the surface in some locations. Construction utilized a lining throughout the tunnel to ensure structural and watertightness under . In geologically weaker zones, additional supports were incorporated to reinforce the excavation and prevent deformation. The bedrock primarily consists of , , , , and , which provided a stable medium for tunneling while requiring careful management of inflows during . The aqueduct operates as a gravity-fed , relying on the elevation difference between the source reservoirs and the city's distribution points to drive without pumps. Its is 900 million gallons per day (3.4 billion liters per day), sufficient to supply over half of City's average daily demand. Operating pressures reach up to 100 in low-lying sections due to the , while typical velocities range from 5 to 10 feet per second (1.5 to 3 m/s), ensuring efficient conveyance while minimizing on the lining. rates are determined using principles akin to Manning's , which accounts for the tunnel's roughness , hydraulic , and to predict discharge under gravity conditions. Key engineering features address the challenges of the hilly terrain along the route, where the tunnel dips below the hydraulic grade line to create effects that maintain flow across valleys without issues. To manage pressure s from sudden flow changes or operations, the design incorporates eight intermediate vertical shafts serving as surge chambers for and . These shafts, typically 20 to 30 feet in , connect to the surface and allow for operational access and monitoring.

Path and Key Features

The Delaware Aqueduct originates at the Rondout Reservoir in , and extends approximately 85 miles southeast, paralleling the through , , , Putnam, and Westchester counties before terminating at the Hillview Reservoir in . The route navigates a varied landscape of the , utilizing deep rock tunneling to traverse mountains, valleys, and rivers while maintaining a pressurized flow under gravity. The aqueduct comprises three primary segments: the 44-mile Rondout-West Branch tunnel, which conveys water from the Rondout Reservoir southward across the to the West Branch Reservoir in Putnam County; the 27-mile West Branch-Kensico tunnel, linking to the Kensico Reservoir in Westchester County; and the 14-mile Kensico-Hillview tunnel, completing the path to the distribution hub. These segments were constructed using drill-and-blast methods in hard rock formations such as , , , , and , with depths reaching up to 2,300 feet to adapt to the rugged terrain. A notable engineering feature is the crossing near Newburgh in , where the tunnel passes approximately 600 feet below the riverbed via horizontal drilling techniques to avoid surface disruption. The aqueduct includes connections to branch tunnels, such as the Rondout delivery tunnel at the intake and effluent chambers at intermediate points for . Access along the route is provided by 25 vertical shafts, excavated during construction for ventilation, inspection, and maintenance; these vary in depth, with examples including Shaft 6 near in Dutchess County at 675 feet and Shaft 5B near Newburgh at 900 feet. Shaft 18, located on the western shore of Kensico Reservoir, facilitates water intake into the aqueduct from the reservoir.

Reservoirs and Water Supply

Delaware System Reservoirs

The Delaware System consists of four reservoirs—Pepacton, Cannonsville, Neversink, and Rondout—that collectively store and regulate water from the upper Delaware River basin for New York City's supply. These reservoirs were constructed as part of the Delaware Project between 1952 and 1964, following legal agreements that authorized New York City to develop the system while limiting diversions to an average of 440 million gallons per day under the 1931 U.S. Supreme Court decree and subsequent amendments. Pepacton Reservoir, the largest in the system, covers 5,740 acres and holds 140.2 billion gallons at full capacity; it was impounded on the East Branch of the Delaware River and placed into service in 1955. Cannonsville Reservoir spans 4,550 acres with a capacity of 95.7 billion gallons and entered service in 1964 on the West Branch. Neversink Reservoir, with 1,820 acres and 34.9 billion gallons of storage, was completed in 1954 on the Neversink River. Rondout Reservoir, encompassing 2,100 acres and 49.6 billion gallons, serves as the downstream collecting point and was operational by 1950. The four reservoirs provide a combined usable storage of approximately 320 billion gallons. The reservoirs draw from a protected watershed spanning approximately 1,012 square miles in the Catskill and Delaware regions of Ulster, Sullivan, and Delaware counties. This area is characterized by forested uplands with minimal development, ensuring high water quality; under the 1997 New York City Watershed Memorandum of Agreement, New York City committed to land acquisition, regulatory protections, and monitoring to avoid the need for filtration of the supply, a status affirmed by the U.S. Environmental Protection Agency's Filtration Avoidance Determination. The watershed's hydrology relies on annual precipitation averaging 40-50 inches, supplemented by snowmelt that contributes 20-30% of the inflow, particularly during spring thaws. Hydrologically, the system yields depend on rainfall and seasonal patterns, with storage levels managed to balance diversions, releases for downstream flows, and flood control. The reservoirs connect to the Delaware Aqueduct at the Rondout intake, facilitating gravity-fed transport southward.
ReservoirSurface Area (acres)Usable Capacity (billion gallons)Year CompletedPrimary Tributary
Pepacton5,740140.21955East Branch Delaware River
Cannonsville4,55095.71964West Branch Delaware River
Neversink1,82034.91954Neversink River
Rondout2,10049.61950Rondout Creek

Integration with NYC Supply

The Delaware Aqueduct forms a vital part of City's expansive system, which encompasses 19 reservoirs and three controlled lakes spanning a 2,000-square-mile , delivering more than 1.1 billion gallons of daily to approximately 9.5 million residents in the city and surrounding upstate counties as of 2025. This aqueduct specifically conveys roughly 50 percent of the total supply, averaging about 600 million gallons per day from the Basin reservoirs to meet urban demands. Water transported through the Delaware Aqueduct discharges into Hillview Reservoir in Yonkers, New York, which acts as the system's primary balancing and distribution hub, blending flows from the Delaware, Catskill, and Croton watersheds before onward transmission. From Hillview, the water enters the city's underground tunnel network, primarily via City Tunnel No. 1 (operational since 1917), City Tunnel No. 2 (since 1936), and the more recent City Tunnel No. 3 (phased into service starting 2013), which together span over 100 miles and convey water under pressure to treatment facilities and distribution mains across the five boroughs. This setup provides built-in redundancy, as the Croton and Catskill aqueducts also feed into Hillview, enabling seamless integration and fallback capacity during varying conditions. The New York City Department of Environmental Protection (DEP) oversees daily operations of the aqueduct through advanced Supervisory Control and Data Acquisition () systems, which monitor flow rates, pressure, and in across the network to optimize delivery and detect anomalies. Seasonal adjustments are routine, with DEP increasing releases from upstream reservoirs during summer months when demand peaks due to higher residential and landscape irrigation needs, potentially rising 10-20 percent above winter averages. Emergency protocols for aqueduct shutdowns or disruptions involve coordinated diversions, such as ramping up flows from the parallel or activating interconnections like the Catskill-Delaware link to maintain supply continuity without interruption to end users. Interconnections throughout the system facilitate load shifting during maintenance or high-demand periods; for instance, valves and bypasses allow excess capacity from the Croton system to supplement Delaware flows at key junctions, ensuring the overall network's and preventing shortages even when one aqueduct is offline. This integrated approach underscores the aqueduct's role in a multi-redundant designed for reliability.

Maintenance and Challenges

Leak Detection and Problems

The major leaks in the Delaware Aqueduct were first suspected in the late through observations of unexplained surface springs along the route, with confirmation occurring in the early via systematic monitoring. In 1991, a significant leak was identified near the Roseton area in by a utility worker at a nearby power plant, initially estimated at around 15 million gallons per day (mgd). By 1992, a second major leak was detected near Wawarsing in Ulster County, close to Shaft 18, contributing to a combined initial loss rate of 15-20 mgd across both sites. In the 2000s, advanced assessments refined the quantification, confirming a total leakage of 30-35 mgd under full operational flow, with approximately 18 mgd originating from the Ulster County (Wawarsing) section and 17 mgd from the (Roseton) section. This escalation was documented through repeated hydraulic testing, revealing that the leaks had worsened due to ongoing structural degradation. The annual water loss from these leaks equates to roughly 11-13 billion gallons, representing a substantial portion of the aqueduct's capacity and straining City's overall efficiency. The primary causes of these leaks trace back to construction-era vulnerabilities in the aqueduct's and materials, exacerbated by the challenging along its path. During the and , a liner was installed within the tunnel, supported by a to seal the surrounding rock; however, over time, this degraded, allowing high internal pressures to exploit cracks in the liner. The route's passage through karst-prone formations—particularly near geological faults in the Wawarsing and Roseton areas—promoted of the rock, widening fissures and accelerating water escape. While nearby quarrying and blasting activities have induced minor seismic stresses that may have contributed to crack propagation, the dominant factors remain the initial limitations and long-term geological interactions. Detection efforts relied on a combination of non-invasive and exploratory techniques to pinpoint and quantify the leaks without major disruption to operations. Flow imbalance monitoring, comparing input at the Rondout Reservoir with output at the Hillview Reservoir, provided the initial alert in the early 1990s by revealing discrepancies of up to 20 mgd. using fluorescein, conducted as early as 1993, confirmed pathways by injecting the tracer into the aqueduct and tracking its emergence in surface features like springs near Wawarsing. Later, acoustic and seismic surveys—deployed via autonomous underwater vehicles (AUVs) and remotely operated vehicles (ROVs) in the —mapped crack locations and leak points through sound wave analysis of water flow and structural vibrations, enabling precise localization within the 45-mile Rondout-West Branch Tunnel segment. The leaks pose ongoing operational and environmental challenges, including the loss of potable water equivalent to the daily needs of a mid-sized city and heightened risks of contamination if internal pressures drop sufficiently to allow reverse flow. In the Wawarsing area, leaked water has surfaced in local wells and streams, raising concerns about unintended connections to surface water bodies along the aqueduct route, such as those near Schoharie Creek, potentially introducing pathogens or pollutants into the supply during low-flow conditions. Although the outward leakage direction currently minimizes inbound contamination, the cumulative annual volume—exceeding 10 billion gallons—underscores the need for vigilant monitoring to prevent broader ecological disruptions in the Hudson Valley groundwater systems.

Repair Projects

In the early 1990s, the Department of Environmental Protection (NYC DEP) identified significant leaks in the Delaware Aqueduct's Rondout-West Branch Tunnel section, particularly near the crossings at Roseton and Wawarsing, with daily losses estimated at 20 to 35 million gallons. Initial mitigation efforts focused on monitoring and structural reinforcements, including the installation of inter-lining in faulted sections to provide temporary support and reduce leakage rates, though these measures did not achieve a permanent fix. The primary repair initiative, launched in 2013 and ongoing as of 2025, is the $2 billion Rondout-West Bypass project, aimed at isolating the leaking Roseton section through a new 2.5-mile-long tunnel segment located approximately 600 feet beneath the . This bypass features an excavated of about 22 feet, reduced to a finished 14-foot with a two-pass pressure tunnel liner system comprising composite steel and , along with gasketed segmental lining during tunneling. The project includes of two vertical s—a 270-meter-deep launch shaft in Newburgh, , and a 197-meter-deep retrieval shaft in Wappinger, —for tunnel access and connections to the existing aqueduct. Construction phases encompassed shaft excavation from 2013 to 2016, followed by tunnel boring using a 22-foot-diameter shielded from 2017 to 2019, which navigated challenging folded and faulted limestone geology. Lining and testing occurred subsequently, including dewatering trials in March and October 2023 to evaluate groundwater infiltration, with final connections and repairs to the Wawarsing leaks planned during an 8-month aqueduct shutdown. Originally slated for 2023, the shutdown has been delayed multiple times, including a pause in November 2024 due to drought conditions, with a new contract procurement announced in May 2025 pushing completion to after 2027. Additional repairs include sealing work at the Newburgh shaft in , completed as part of the bypass infrastructure by 2018, and the deployment of robotic inspection technologies, such as the $14 million underwater remotely operated vehicle delivered in 2018 for internal aqueduct assessments, though full utilization has been deferred pending the shutdown. Throughout the bypass construction, challenges included managing high inflows—addressed via pre-excavation grouting up to 100 meters ahead using high-pressure hammers—and cost escalations from an initial $1 billion estimate due to geological complexities and project delays.

Significance

Environmental and Economic Impact

The Delaware Aqueduct plays a pivotal role in by facilitating the delivery of unfiltered from the Basin reservoirs, thanks to rigorous efforts that have averted the need for costly filtration facilities. These protections, including land acquisition and regulatory measures, have saved an estimated $8-10 billion in construction and operational costs for treatment , while maintaining compliant with federal standards. The Department of Environmental Protection (DEP) has invested over $2.7 billion in such programs since the , emphasizing to preserve the natural provided by forested uplands and wetlands. However, chronic leaks in the aqueduct, totaling up to 35 million gallons per day, pose risks such as localized alterations and potential pathways for contaminants to infiltrate the through structural fissures, though ongoing repairs aim to mitigate these issues. The associated reservoirs—Pepacton, Neversink, and Cannonsville—harbor diverse aquatic and terrestrial ecosystems, with protected buffer zones supporting fish populations, bird habitats, and vegetation that enhance overall watershed resilience against and climate stressors. Economically, the construction of the Delaware System, including the aqueduct, from 1937 to 1965 generated thousands of jobs in engineering, tunneling, and support roles across and northern , injecting millions into regional economies during a period of post-Depression recovery and wartime mobilization. Today, its reliable conveyance of approximately half of the city's bolsters City's $1.1 trillion by ensuring uninterrupted access for over 9 million residents and myriad industries, from to , where water reliability underpins operational continuity. Maintenance and repair initiatives, including the multi-billion-dollar bypass tunnel project, are financed through water and sewer rates, with annual expenditures on protection averaging $100 million, distributed across ratepayers to sustain long-term system integrity. The project's community impacts began with land acquisitions in the for reservoir construction, which displaced over 500 families from farms and small settlements in the Neversink and East Branch valleys, reshaping agricultural communities and prompting relocations that altered local demographics and patterns. In response to these historical effects, the ongoing NYC Watershed Program enforces development restrictions upstream, such as 100-foot buffers from watercourses for septic systems and prohibitions on new impervious surfaces near , to prevent while fostering sustainable economic activities like eco-tourism. This approach has broader significance, positioning the Delaware Aqueduct as a exemplar for watershed-based policy, influencing federal guidelines under the by proving that proactive land stewardship can obviate filtration mandates for large-scale supplies.

Current Status and Future Outlook

As of November 2025, the Delaware Aqueduct continues to operate despite ongoing leaks estimated at up to 35 million gallons per day, primarily from the Roseton and Wawarsing sections under the Hudson River. The excavation of the 2.5-mile bypass tunnel, designed to reroute flow around the leaking portions, was completed in prior phases, but the final connection remains paused following a May 2025 announcement by the New York City Department of Environmental Protection (DEP). This pause stems from procurement challenges, below-average precipitation concerns, and the need for pump upgrades, with an eight-month shutdown now deferred to avoid straining alternative supplies during potential droughts. Partial operational adjustments, including flow testing, have been conducted periodically to assess integrity without full disruption. Monitoring efforts have been enhanced with advanced real-time sensors installed at key aqueduct locations as part of DEP's 2023 watershed program, enabling continuous data collection on flow, pressure, and contaminants. Additionally, pilot trials of AI-driven predictive maintenance, supported by NASA-funded tools at , integrate and hydraulic modeling to forecast potential failures and optimize supply management across the system. Looking ahead, DEP targets full repair completion and activation after 2027, incorporating pump enhancements to boost capacity toward 990 million gallons per day from the current operational average of around 600 million gallons per day. These upgrades align with broader strategies, including measures like optimizations and contingency planning for extended low-precipitation periods, as outlined in DEP's ongoing impact assessments. The aqueduct's heavy reliance on the Delaware River Basin—supplying roughly half of City's water—poses risks amid accelerating , with recent droughts prompting repeated project delays and highlighting vulnerabilities to prolonged dry spells. Contingency protocols emphasize diversified sourcing from the Catskill and Croton systems during potential longer shutdowns, ensuring supply stability through 2030 and beyond. Ongoing repair delays, including the latest procurement shift, underscore the need for robust adaptive infrastructure to mitigate these evolving threats.

References

  1. [1]
    Mayor Adams Launches Final Phase of Historic Project to ... - NYC.gov
    Sep 30, 2024 · The water is delivered from a watershed that extends more than 125 miles from the city, comprising 19 reservoirs and three controlled lakes.
  2. [2]
    Aqueducts - Public Water
    The Delaware Aqueduct, a circular, concrete-lined tunnel 13.5 to 19.5 in diameter, stretches 83.8 miles connecting the Rondout and Hillview Reservoirs.
  3. [3]
    New York City (NYC) Delaware System - NYCdata | Infrastructure
    The Delaware Aqueduct, which was the last water supply system to be built in New York State, provides between 50 and 80 percent of New York City's water.
  4. [4]
    Delaware Aqueduct Rondout-West Branch Tunnel Repair - DEP
    Since the 1990s, DEP has been monitoring leaks in a portion of the aqueduct that connects the Rondout Reservoir in Ulster County to the West Branch Reservoir in ...
  5. [5]
    New York City's Water Supply System: Past, Present, and Future
    From Rondout Reservoir, the Delaware Aqueduct flows 85 miles under the Hudson River via a deep inverted siphon to the West Branch and Kensico reservoirs, where ...
  6. [6]
    History of NYC's Drinking Water
    By the late 1800s, a new aqueduct was under construction to get yet more water from Croton to the City.
  7. [7]
    A History of the NYC Water Supply System - Hofstra Sites
    In 1883, the Croton Aqueduct Commission was enacted and construction of the New Croton System began in 1885. The New Croton Dam was begun in 1892 at a site ( ...
  8. [8]
    [PDF] History and Practice of Flow Management in the Delaware River Basin
    Oct 16, 2017 · 1905: NEW YORK CITY LOOKS WEST FOR. MORE WATER. 1915: CATSKILL SYSTEM completed but not enough. 1927: DELAWARE BASIN Reservoirs approved by NYC ...
  9. [9]
    New Jersey v. New York | 283 U.S. 336 (1931)
    Hearing on exceptions to the report of the Special Master, in a suit by New Jersey to enjoin diversion of water, in New York, from tributaries of the Delaware ...Missing: Aqueduct | Show results with:Aqueduct
  10. [10]
    Delaware River Project Begins | Research Starters - EBSCO
    The Catskill water-supply system was initiated in 1907 and was completed in 1927. This system transported water from Esopus Creek and the Ashokan Reservoir, ...
  11. [11]
    Repair of Delaware Aqueduct, World's Longest Tunnel
    Feb 24, 2024 · The Delaware Aqueduct was begun in 1939 and put into service in 1944 when NYC Mayor La Guardia opened the gates.Missing: groundbreaking | Show results with:groundbreaking
  12. [12]
    Delaware Aqueduct Bypass Tunnel Boring Now Complete
    Oct 11, 2019 · A Specialized TBM​​ The TBM design had to account for challenges presented by the aqueduct repair, such as difficult geology and considerable ...Missing: workforce | Show results with:workforce
  13. [13]
    [PDF] Delaware Aqueduct Rondout-West Branch Tunnel Repair - NYC.gov
    Dec 16, 2011 · The Schoharie Reservoir delivers up to 615 mgd to the Catskill system via the Shandaken Tunnel, which releases into Esopus Creek and flows into ...
  14. [14]
    Out of the Archives: 75 Years of Delaware System Water - Medium
    Cannonsville, Pepacton, Neversink and Rondout — and 160 miles of aqueduct.
  15. [15]
    Delaware Aqueduct Repair Project - Flickr
    On April 5, 1944, Mayor LaGuardia turns open the gate that will release water into the Delaware Aqueduct for the first time. Construction of western shaft ...Missing: 1945 partial WWII
  16. [16]
    [PDF] Delaware Aqueduct Repair Project - Catskill Watershed Corporation
    May 5, 2015 · The groundwater reactivation project would cost roughly $240 million. Reactivation of the Queens Groundwater System. 23. Page 24. • Construction ...
  17. [17]
    NYCDEP Rehabilitation of Delaware Aqueduct Shafts 9, 10 & 17 ...
    The Facility was built between 1939 and 1945, the 85-mile long Delaware Aqueduct supplies up to 1.2 billion gal/day of drinking water from upstate reservoirs to ...
  18. [18]
    DEP Announces Final Steel Segment Lowered Into ... - NYC.gov
    May 14, 2020 · The Delaware Aqueduct Bypass Tunnel is the largest repair project in the 178-year history of New York City's water supply system. Its ...
  19. [19]
    DEP Unveils Design to Repair Leaks In the 85-Mile Delaware ...
    Nov 19, 2010 · The 85-mile Delaware Aqueduct conveys drinking water from these reservoirs to the city's distribution system. It is designed to provide up ...
  20. [20]
    [PDF] ES-1 Executive Summary - NYC.gov
    Dec 19, 2011 · At the Rondout Reservoir, the water is conveyed approximately 45 miles via the. RWBT portion of the Delaware Aqueduct to the West Branch ...
  21. [21]
    [PDF] Probable Impacts of Project 2A, Water Supply System Augmentation ...
    Dec 16, 2011 · As discussed in Chapter 1, “Program Description,” the Delaware Aqueduct is critical to the New. York City water supply system. Shutting down the ...
  22. [22]
    Dam and Tunnel Construction · Lost Hamlets of the Rondout Reservoir
    The main Delaware Aqueduct tunnel construction began with a fanfare of opening ceremonies held in Gardiner, New York, on March 24, 1937. This artist's ...Missing: phases | Show results with:phases
  23. [23]
    [PDF] delaware-aqueduct-repair-project-presentation.pdf - NYC.gov
    Dec 15, 2017 · 180-year history of NYC's municipal water supply. ➢ Tunnel program cost $1+ billion. ➢ Fixing or eliminating leaks in the Delaware. Aqueduct.
  24. [24]
    DEP Completes Renovation of Critical Delaware Aqueduct Control ...
    Apr 13, 2011 · ... Delaware Aqueduct. A shaft is a vertical pipe that connects a tunnel ... The aqueduct is a concrete-lined tunnel that varies in diameter from 13.5 ...<|separator|>
  25. [25]
    Way Down in the Hole: New York City's water system gets ... - Upstater
    A few years from now, the Delaware Aqueduct will be pumped dry for the first time since 1957, touched up, and rerouted. Then water will flow below us again, and ...
  26. [26]
    [PDF] Chapter 1: Project Description 1.1 INTRODUCTION - NYC.gov
    The existing DEL Shaft 18, located on the western shore of Kensico Reservoir, serves as the intake for the Delaware Aqueduct. Reservoir water enters the shaft, ...
  27. [27]
  28. [28]
    Delaware River Basin Commission|Flow Management - NJ.gov
    May 25, 2021 · On May 4, 1931, the United States Supreme Court issued a decree authorizing New York City to divert an average of up to 440 million gallons of ...Missing: limit | Show results with:limit
  29. [29]
    Pepacton Reservoir - DEP - NYC.gov
    It consists of one basin, approximately 15 miles in length and holds 140.2 billion gallons at full capacity, making it the largest reservoir in the City system ...
  30. [30]
    Cannonsville Reservoir - DEP - NYC.gov
    It was placed into service in 1964 and holds 95.7 billion gallons at full capacity. Cannonsville Reservoir is one of four reservoirs in the City's Delaware ...
  31. [31]
    Neversink Reservoir - DEP - NYC.gov
    It holds 34.9 billion gallons at full capacity and was placed into service in 1954. Neversink Reservoir is one of four reservoirs in the Delaware Water Supply ...
  32. [32]
    Rondout Reservoir - DEP - NYC.gov
    It consists of one basin, almost 6.5 miles long and holds 49.6 billion gallons at full capacity. It was placed into service in 1950. Rondout Reservoir is one of ...
  33. [33]
    [PDF] New York City Watershed Memorandum of Agreement
    Jan 21, 1997 · In the Catskill and Delaware. Watershed, the 1997 Filtration Avoidance Determination issued as described in paragraph 159 ("1997 FAD") will ...
  34. [34]
    Reservoir Operations & Watershed Monitoring - DEP - NYC.gov
    Reservoir levels are primarily determined by the balance between streamflow into the reservoirs, diversions (withdrawals) for water supply, and releases to ...
  35. [35]
    Drinking Water - DEP
    - **Number of people served**: 9 million customers throughout New York state.
  36. [36]
    [PDF] Thematic Unit 2: - Drinking Water and You - NYC.gov
    Because the Delaware Aqueduct carries about 50% of our water each day, we need to take a number of steps to ensure all New Yorkers have an adequate, reliable ...<|control11|><|separator|>
  37. [37]
    [PDF] ONE WATER NYC:
    Jun 1, 2025 · The repair of the Delaware Aqueduct, which delivers half of the city's water supply from the Catskill Mountains, is one of DEP's largest.
  38. [38]
    [PDF] nyc-water-supply-system.pdf
    City Tunnel No. 3. Silver Lake Park. (Underground Storage Tanks). Manhattan. City Tunnel No. 1. City Tunnel No. 2. Richmond Tunnel. Brooklyn. Staten. Island.
  39. [39]
    [PDF] OVERVIEW OF WATER FOR THE FUTURE 1.1 - NYC.gov
    Feb 8, 2019 · The Delaware Aqueduct has been in operation since the 1940s and transports water a distance of approximately 85 miles from the Delaware water ...Missing: facts | Show results with:facts
  40. [40]
    New York City Water Supply Reservoir – Canary Systems
    In addition it must be fed directly into the NYC Department of Environmental Protection (DEP) state-wide SCADA system for monitoring by DEP personnel. We ...
  41. [41]
    [PDF] WATER DEMAND MANAGEMENT PLAN - NYC.gov
    In 2011 DEP launched the Water for the Future program, a comprehensive long-term planning effort to repair leaks in sections of the Delaware Aqueduct by 2021.
  42. [42]
    Catskill-Delaware Interconnection - Mott MacDonald
    The Interconnection includes a major underground structure, designed as an expansion of the existing Delaware Aqueduct Shaft 4. The new structure features large ...Missing: crossings | Show results with:crossings
  43. [43]
    [PDF] Delaware Aqueduct Repair Update - NJ.gov
    Mar 23, 2022 · • Leak identified in 1992 in Town of Wawarsing. • Total leakage rate estimated at approx. 20 MGD on typical day. • Approximately 95 percent is ...
  44. [44]
    The Big Fix: Repairing the Delaware Aqueduct - Times Herald-Record
    Mar 11, 2017 · Today, the Delaware Aqueduct provides upwards of 50 percent of the 1 billion gallons that 9.5 million people use every day – 1 million of them ...
  45. [45]
    [PDF] Delaware Aqueduct System: Water Leak Detection and Repair ...
    Aug 15, 2007 · The Delaware Aqueduct System provides approximately 55 percent of New York City's water supply. DEP has known since 1988.
  46. [46]
    Opinion | New York City's Leaky Water Supply
    Dec 4, 2000 · About 35 million gallons of water are leaking every day from cracks in the Delaware Aqueduct, a vital underground thoroughfare for New York ...Missing: confirmation | Show results with:confirmation
  47. [47]
    For Leaky New York Aqueduct, Bypass Tunnel Is Planned
    Nov 19, 2010 · The shutdown will require lining up other sources for the 500 million gallons of water that the Delaware Aqueduct carries each day from the ...Missing: maximum | Show results with:maximum
  48. [48]
    Bypass tunnel confronts the leaks of the Delaware Aqueduct (video)
    ... shale, gneiss and granite, rocks mostly present in the part of the tunnel. DEP will construct a 3-mile bypass tunnel under the Hudson River in order to ...<|separator|>
  49. [49]
    Fixing the Delaware Aqueduct Leaks - North Eastern Fly Fishing
    Mar 4, 2008 · Since then, DEP has continuously monitored, studied and tested the leaks and their effects, using dye tests, backflow tests, hydrostatic tests, ...
  50. [50]
    DEP Will Use Remotely Operated Submarine to Examine ... - NYC.gov
    Nov 29, 2022 · A second aqueduct from the Catskills, the Delaware Aqueduct, was completed in 1945 and together with the Catskill Aqueduct provides between 90 ...Missing: depth | Show results with:depth
  51. [51]
    Hydrogeologic and Geochemical Assessment of the ... - USGS.gov
    The NYCDEP is planning to grout the smaller tunnel leaks in Wawarsing, and build a bypass tunnel in the areas of the larger leaks along the Delaware Aqueduct.Missing: specifications details
  52. [52]
    It's not just leaks being bypassed in the Delaware Aqueduct
    Dec 30, 2024 · In a guest editorial, a a diving scientist and technologist asks whether the Delaware Aqueduct is stable enough to safely dewater.Missing: challenges adjustments 1950s
  53. [53]
    Water for NYC - Kiewit Newsroom
    Sep 25, 2023 · The longest tunnel in the world, the 85-mile-long aqueduct branches into other supply tunnels to the city and surrounding counties. In the early ...
  54. [54]
    Delaware River Basin Commission|Delaware Aqueduct Repair Project
    The 85-mile-long Delaware Aqueduct is the world's longest tunnel. It transfers water from the three NYC Delaware River Basin Reservoirs (Cannonsville, Pepacton ...Missing: length capacity
  55. [55]
    NYC DEP to Develop New Contract for Final Connection of ...
    May 5, 2025 · The final bypass connection requires an eight-month shutdown and draining of the Delaware Aqueduct that would start in October of any given year ...
  56. [56]
    Rondout-West Branch Bypass Tunnel - Delve Underground
    The Rondout-West Branch Bypass Tunnel is a 2.5-mile-long tunnel built to address leakage in the original 45-mile-long tunnel, which supplies 50% of NYC's water.
  57. [57]
    Delaware Aqueduct Repair - The Robbins Company
    Machine Type Single Shield ; Diameters 6.8 m (22.3 ft) ; Tunnel Type Water Transfer ; Tunnel Lengths 3.8 km (2.5 mi) ; Owner New York City Department of ...Missing: NYC | Show results with:NYC
  58. [58]
    Ecosystem Services in the New York City Watershed
    Feb 10, 2006 · A filtration plant large enough to clean the City's water supply would cost between $8-$10 billion in today's dollars, approximately $6 ...Missing: avoidance $5-10
  59. [59]
    Filtration Decision Near for NYC's Drinking Water Supply - NRDC
    Jul 10, 2017 · That could leave city officials with no choice but to construct massive drinking water filtration facilities at a price tag of over 10 billion ...Missing: Aqueduct $5-10
  60. [60]
    [PDF] NEW YORK CITY DRINKING WATER SUPPLY AND QUALITY ...
    The. 100-year-old reservoir continues to play an essential role as the balancing reservoir that ensures drinking water is continuously available to all parts ...
  61. [61]
    Invasive Species Spell Trouble for New York's Beloved Tap Water
    Nov 4, 2024 · Without a change in policy, it is possible that more invasive species will make their way to the city's reservoirs, impacting the ecosystems ...
  62. [62]
    An Account of Human Costs - Places Journal
    Ashokan, Schoharie, Rondout, Neversink, Pepacton, and Cannonsville — that were put in ...<|separator|>
  63. [63]
    Regulations - DEP - NYC.gov
    A comprehensive regulatory program that strives to minimize the risk of water quality impacts from specific watershed activities and associated development ...Missing: restrictions upstream
  64. [64]
    How can we deliver clean, safe water to NYC? - Cornell CALS
    Nov 27, 2018 · The Delaware watershed is part of the largest municipal water supply in the United States, and because it requires no filtration, it saves New ...Missing: savings | Show results with:savings
  65. [65]
    [PDF] New York City Department of Environmental Protection 2023 ...
    extreme scenarios for NYC Water Supply System resiliency studies. The motivation for this work has two parts. First, the need for realistic potential ...
  66. [66]
  67. [67]
    [PDF] Fiscal Year 2025 - CO-CONSULTING ENGINEERING REPORT
    Mar 7, 2025 · leaking section of the Delaware Aqueduct in the area of Roseton, NY, and NYCDEP will perform repairs of the concrete liner in upstream areas ...