Marble Arch Mound

The Marble Arch Mound was a temporary artificial hill, 25 metres in height, constructed on a traffic island next to Marble Arch at the western end of Oxford Street in London, England. Designed by the Dutch architecture studio MVRDV and commissioned by Westminster City Council, the structure sought to revitalize the area's post-pandemic footfall by offering elevated viewpoints and simulating an extension of Hyde Park's greenery with planned plantings of trees and wildflowers. Announced in February 2021 as part of a broader £150 million regeneration initiative, the mound's construction proceeded rapidly but opened incompletely in July 2021, presenting as a scaffolded mound of with minimal , prompting visitor complaints and refunds. Initially budgeted at £2 million, total expenditures escalated to £6 million, encompassing build, operation, and eventual dismantling costs of £660,000, amid accusations of mismanagement. The project became emblematic of folly, derided in and online for its aesthetic shortcomings—likened to a "slag heap" or unfinished earth pile—and failure to deliver promised scenic allure, ultimately closing to visitors in January 2022 after meager attendance and contributing to political repercussions for the commissioning council. attributed the debacle to inadequate execution by contractors rather than design flaws, highlighting tensions between architectural intent and practical delivery.

Conception and Planning

Project Origins and Stated Goals

The Marble Arch Mound originated as a post-COVID-19 recovery initiative by , which announced plans for the temporary structure on February 16, 2021, amid severe economic impacts from pandemic lockdowns that had drastically reduced footfall in central London's retail districts like . The council commissioned Dutch architecture firm to design the project, drawing on the firm's prior conceptual work for elevated landscape features, with construction beginning in spring 2021 on a site adjacent to the historic . This effort was positioned as part of broader urban regeneration strategies to counteract the closure of shops, restaurants, and attractions that had left the area economically stagnant. Stated goals centered on revitalizing visitor numbers and local commerce by creating an accessible, novel outdoor attraction intended to draw approximately 200,000 people to the West End over its planned lifespan until January 2022. The mound was described as a "temporary landscape installation" to inject excitement into the urban environment, offering elevated panoramic views across Hyde Park and integrating temporary greenery with over 100 planted trees to evoke a natural hill experience amid the concrete surroundings. Council documents emphasized its role in attracting foot traffic to support struggling businesses, positioning it as a low-risk, reversible intervention to test public appetite for innovative public spaces post-restrictions. These objectives aligned with the council's mandate to promote tourism and economic activity in a high-traffic but lockdown-depleted zone.

Initial Budgeting and Political Approvals

The Marble Arch Mound was conceived by in early 2021 as a low-cost, temporary installation to revitalize footfall on following restrictions, with an initial construction budget of approximately £2 million plus £0.8 million in operating costs. The modest estimate reflected expectations of simple earthworks, basic planting, and revenue generation via £4.50 entry fees to offset expenses and support local businesses. Planning permission for the 25-meter structure adjacent to was unanimously approved by the council's planning committee on 30 March 2021, enabling rapid implementation during the summer tourist season. This followed submission of designs by Dutch firm , commissioned for a nominal fee within the overall allocation. On 11 May 2021, the cabinet member for the authorized advancement to site , affirming the architectural approach and provisions for income from tickets alongside potential legacy uses for the soil post-dismantling. Funding derived exclusively from the council's £150 million District initiative, sourced from local reserves and business rates rather than national subsidies. These decisions occurred under Conservative council leadership, prioritizing swift economic stimulus over extended scrutiny.

Design and Construction

Architectural Concept by MVRDV

The Marble Arch Mound was designed by the Rotterdam-based architecture firm as a temporary, 25-meter-high intended to revitalize the area around by extending Hyde Park's greenery westward. The concept sought to homage the park's pre-1851 boundaries, which originally encompassed the Arch's site before its relocation to the current traffic-isolated plaza, thereby visually reconnecting the monument to its natural context. This elevation was envisioned as a sloping, soil-covered hill supported by a reusable metal scaffold framework, accommodating 45 mature trees and undergrowth to create an immersive green ascent. In its initial iteration, proposed enveloping the directly with a protective 25-meter roofscape and internal staircase, enabling visitors to climb atop the structure while preserving the monument beneath a verdant layer. This was later modified to a freestanding mound positioned adjacent to the Arch, prioritizing unobstructed views of the historic structure amid concerns over heritage preservation. Winding paths were incorporated to guide ascent, culminating in a summit platform offering elevated vistas of , , and the London skyline, with the overall form drawing from natural hillocks to blend artificial intervention with landscape typology. The design emphasized through modular, recyclable components— sheeting, , and selected for post-project —positioning the mound as a for greening initiatives amid post-pandemic recovery efforts to draw pedestrians to the West End. described it as a "temporary " fostering experiential access to elevated in a dense setting, contrasting the Arch's isolation with dynamic, accessible topography.

Execution, Delays, and Cost Escalations

Construction of the Marble Arch Mound began in early 2021 under the oversight of Westminster City Council, following the architectural concept by MVRDV, but was marred by execution shortcomings including inadequate project management and scope changes during building. A post-project review identified failures in maintaining timelines and budgets, with alterations to the design—such as reducing its scale and relocating it slightly due to regulatory investigations—contributing to operational inefficiencies. The mound prematurely opened to ticketed visitors on July 26, 2021, despite ongoing construction and incomplete features like sparse tree planting, leading to its suspension just two days later on July 28, 2021, as it was deemed "not yet ready for visitors." Efforts to rectify issues, including additional landscaping, delayed full accessibility until a free reopening on August 9, 2021. These delays stemmed from rushed timelines to meet summer goals amid post-lockdown recovery, compounded by the decision to open unfinished, which later attributed to "loveless execution" rather than inherent design flaws. Cost escalations were severe, with the project ballooning from an initial of approximately £3.3 million to a total of £6 million, encompassing , operations, and eventual removal. Earlier estimates had pegged costs at £1.25 million to £2 million, but overruns arose primarily from mid- modifications and underestimated complexities in and vegetation integration. Dismantling alone incurred an additional £660,000, completed by mid-2022, highlighting the fiscal burdens of inadequate initial scoping. The council's review described these overruns as "devastating and avoidable," resulting from insufficient and reactive adjustments.

Operation and Public Experience

Opening Event and Entry Policies

The Marble Arch Mound opened to the public on 26 July 2021, operating under a timed-ticket booking system managed by to control visitor numbers and ensure amid ongoing restrictions. Initial entry fees ranged from £4.50 for adults to £8 during peak times, with reduced rates of £5 for children and concessions, and tickets available for purchase online in advance or at the door; operating hours were set at 10:00 a.m. to 8:00 p.m. on weekdays and 9:00 a.m. to 8:00 p.m. on weekends. Within two days of opening, on 28 July 2021, the suspended all bookings and temporarily closed access following complaints from early visitors about incomplete , dying , obstructed views, and structural instability, prompting organizers to prioritize site improvements. Visitors holding paid tickets from the first week were offered full refunds or complimentary return visits after reopening, reflecting an policy adjustment to mitigate dissatisfaction. The mound reopened on 9 August 2021 with revised entry protocols, but by early September, fees were permanently eliminated in response to persistent low turnout and further critiques of its unfinished state, allowing free timed bookings until the attraction's scheduled closure on 9 January 2022. This shift to no-cost access aimed to boost usage, though no capacity limits or additional restrictions beyond standard booking requirements were publicly detailed beyond the initial emphasis on pre-reservation to avoid queues.

Visitor Feedback During Runtime

Upon opening to the public on July 26, 2021, the Marble Arch Mound received immediate backlash from early visitors who paid up to £8 for entry, describing it as unfinished with exposed scaffolding, patchy grass, and scrawny, dying trees that failed to match promotional renderings of lush greenery. These complaints prompted Westminster City Council to temporarily close the site on July 27, 2021, offer full refunds to ticket holders, and delay reopening until improvements could be made, acknowledging that "it wasn't ready for visitors when it opened." Visitor reviews aggregated on platforms like reflected this dissatisfaction, yielding an average rating of 2.9 out of 5 from 19 reviews as of late 2021, with many citing obstructed views dominated by scaffolding and nearby foliage rather than panoramic cityscapes, alongside criticisms of the "horrible metal stairs" and "poor dead plants." Individual accounts labeled it a "monstrosity" and "the worst thing I've ever done in ," emphasizing its barren appearance and perceived waste of public funds during a period of economic recovery from restrictions. After entry fees were waived in August 2021 to boost attendance, the site attracted crowds intrigued by its notoriety as "so bad it's good," though feedback remained largely negative, with visitors noting mediocre vistas comparable to but inferior to free alternatives like , and an overall aesthetic of a "heap of earth" rather than a verdant viewpoint. A minority of reviews praised incremental improvements, such as growing saplings and basic elevation for observing urban layouts, but these were overshadowed by persistent gripes about its proximity to the historic , which some deemed visually compromised by the structure's industrial scaffolding. By late 2021, into its extended runtime until January 2022, the mound's draw shifted toward ironic tourism, with visitors queuing to experience its infamy firsthand rather than for inherent appeal.

Reception and Controversies

Aesthetic and Practical Criticisms

The Marble Arch Mound drew widespread aesthetic criticism upon its opening on 26 July 2021 for resembling a barren "pile of mud" or "slag heap" rather than the verdant, tree-draped hill shown in architectural renderings by . Early visitors noted the structure's parched, patchy turf, applied hastily by workers days before launch, which contrasted sharply with the lush green landscape promised in planning proposals. Critics and locals labeled it a "hideous " that disrupted the historic vicinity without enhancing its appeal. Practically, the mound's 25-meter height proved inadequate for unobstructed views over central London's tree canopy and buildings, limiting the summit platform to confined sightlines that disappointed ticket holders paying £4.50 to £6.50. Initial operations saw long queues and overcrowding, prompting to suspend bookings and issue refunds on 27 July 2021 after just one day of public access. Vegetation issues compounded functionality, as grass and plants wilted rapidly under summer heat, forcing a temporary closure in late for replanting and leading to free entry from September to mitigate ongoing complaints. Visitors frequently cited the steep, scaffolded paths and hollow interior as uncomfortable and uninviting, with one describing the experience as "the worst thing I've ever done in ."

Fiscal Irresponsibility and Political Accountability

The Marble Arch Mound project, commissioned by , saw its initial budget of £3.3 million escalate to a total cost of £6 million, encompassing , , and eventual removal. This overrun, described in an internal council review as "devastating and avoidable," stemmed from errors in judgment, insufficient oversight, and a deliberate misrepresentation of financial risks to senior decision-makers. Key factors contributing to the included decisions that locked in higher expenses early, such as selecting a specialist contractor without competitive tendering for certain elements, and subsequent changes due to incomplete design execution and site constraints. An additional £190,000 arose from operator costs exceeding targets, while broader mismanagement concealed rising expenditures from cabinet members until mid-project. The council's identified a " of complacency" in , with officers failing to escalate warnings adequately, leading to taxpayer-funded losses without corresponding revenue from low visitor numbers. Politically, the overspend prompted the resignation of Deputy Leader Melvyn Caplan on August 13, 2021, who accepted responsibility for the financial mismanagement under his portfolio. Opposition councillors, representing a minority on the Tory-controlled council, demanded an independent inquiry into the "basic lack of financial control," highlighting it as a symptom of broader Conservative failures in public spending oversight. Council Leader Rachael Robathan issued an apology for the project's shortcomings but defended its intent within the £150 million regeneration framework, resisting calls for her own resignation. Accountability measures were limited to the internal review and Caplan's departure, with no further resignations or external audits mandated, despite criticisms that the process prioritized internal absolution over rigorous external . The episode underscored vulnerabilities in project controls, where accelerated COVID-19 recovery initiatives bypassed standard fiscal safeguards, resulting in unrecouped public expenditure. Dismantling costs alone added £660,000, further amplifying the net fiscal burden on Westminster ratepayers.

Dismantling and Aftermath

Closure Process and Demolition Costs

The Marble Arch Mound ceased public operations on 9 January 2022, earlier than its extended schedule through summer 2022, following persistent low attendance and operational challenges. Dismantling commenced shortly thereafter, structured as a phased to remove the , timber framework, and elevated platform components. The removal process spanned approximately four months, with visible progress by late February 2022 when the mound had been reduced to an exposed skeletal frame of and supports. Efforts included salvaging reusable elements, such as parts of the structure later repurposed for a regeneration project. Full site clearance and restoration to the original vicinity were completed by mid-2022, minimizing disruption to surrounding traffic and parkland. Westminster City Council reported the total dismantling expenditure at £660,000, covering labor, equipment, waste disposal, and site remediation. This figure represented an additional financial burden atop the £6 million overall project outlay, with council officials attributing it to the complexities of reversing the earthworks and ensuring environmental compliance. No revenue offsets were noted for the demolition phase, as ticket sales had already proven insufficient during operations.

Broader Impacts and Lessons Learned

The Marble Arch Mound project, which cost approximately £6 million in construction expenses plus £660,000 for dismantling, served as a cautionary example of fiscal mismanagement in initiatives. Initial budgets were projected at around £3 million, but escalations arose from design alterations, site constraints, and execution delays, underscoring the perils of inadequate contingency planning and contract enforcement in taxpayer-funded ventures. The internal council review highlighted circumvented checks, lack of oversight, and avoidable errors, leading to five recommendations aimed at bolstering , rigor, and for future endeavors. In terms, the mound's failure—manifest in wilting , obscured vistas, and sparse attendance of roughly 250,000 visitors against optimistic projections—revealed execution pitfalls in temporary green installations. Rushed timelines prevented proper plant maturation and functionality, transforming a conceptual "green hill" into a barren scaffold that drew public derision rather than revitalizing post-pandemic. This contrasted with successful pop-up parks, such as Liverpool's 2019 initiatives or London's Wild West End, which prioritized , , and modest scales to yield enduring ecological and social benefits without prohibitive costs. The episode emphasized causal necessities like extended lead times for landscape integration and empirical feasibility assessments over render-driven hype, particularly in dense urban settings where green deficits demand pragmatic, not performative, interventions. Politically, the overspend prompted the resignation of the council's deputy leader and calls for auditing a "culture of complacency" in decision-making, amplifying scrutiny on local authorities' allocation of funds amid competing priorities like housing pressures eroding existing parks. It illustrated how top-down, tourism-oriented projects can erode public trust when outcomes diverge from promises, fostering demands for greater transparency and independent oversight in municipal projects. Overall, the mound reinforced that effective public works hinge on rigorous pre-implementation testing, stakeholder alignment, and avoidance of politically expedited approvals, informing a more cautious approach to experimental urban enhancements.

References

  1. [1]
    Marble Arch Mound - MVRDV
    With its sloping landscape supporting 45 trees, Marble Arch Mound extended the green environment of Hyde Park back to its original boundary, which once included ...
  2. [2]
    MVRDV's artificial hill rises at Marble Arch in London - Dezeen
    Jul 20, 2021 · The Marble Arch Mound, a viewpoint disguised as a hill designed by Dutch studio MVRDV, has been photographed rising alongside Hyde Park in London.
  3. [3]
    What went wrong with the Marble Arch Mound - The B1M
    this is the city that built a giant glass walkie ...
  4. [4]
    Marble Arch Mound: Pulling down the tourist attraction cost ... - BBC
    Mar 28, 2022 · The cost of dismantling the Marble Arch Mound was £660,000, Westminster Council has confirmed. The £6m artificial hill opened incomplete, ...
  5. [5]
    London's Marble Arch Mound attraction to close this weekend
    Jan 7, 2022 · Marble Arch Mound, the scaffolding-and-turf urban peak that stood 25m tall, came with a £6m price tag and claimed the scalp of Westminster council's deputy ...<|separator|>
  6. [6]
    Westminster Council spent £660000 tearing down Marble Arch Mound
    Mar 29, 2022 · Westminster Council has spent £660,000 tearing down the Marble Arch Mound. The tourist attraction closed in January after it sparked ...
  7. [7]
    MVRDV blames "loveless execution" for Marble Arch Mound fiasco
    Feb 7, 2022 · Dutch studio MVRDV has blamed Westminster City Council's "nonchalance and laxity" for the disastrous Marble Arch Mound project.
  8. [8]
    Architect behind Marble Arch Mound slams Westminster Council for ...
    Feb 10, 2022 · The architect behind the Marble Arch Mound has slammed Westminster Council for its “loveless execution” of the project and said it should've ...
  9. [9]
    Marble Arch Mound timeline: Why the infamous landmark opened ...
    Jan 9, 2022 · The council apologises as it is revealed the mound will cost £6million - three times its budget. The mound is reopened as a free attraction for ...Missing: construction | Show results with:construction
  10. [10]
    Mound zero: what is Marble Arch's new landmark all about?
    Jul 23, 2021 · Rearing up at the western end of Oxford Street as a faceted green shell, looking like a landscape from a low-fi video game, the 25-metre high ...
  11. [11]
    [PDF] Cabinet Member Report
    Oct 19, 2021 · This report provides a final update on the Marble Arch Mound (“the Mound”) ... Mound's main purpose of attracting visitors back to the City.<|separator|>
  12. [12]
    Marble Arch | Westminster City Council
    Apr 29, 2022 · Marble Arch is a 19th-century white marble-faced triumphal arch, designed by John Nash in 1827 to be the state entrance to the cour d'honneur of Buckingham ...Missing: origins | Show results with:origins
  13. [13]
    Council Still Has Questions To Answer on Marble Arch Mound
    Oct 20, 2021 · The Chief Executive announced the Mound would be free to climb in August, a decision subsequently extended for the Mound's duration. On 13 ...
  14. [14]
    Council deputy leader resigns due to Marble Arch Mound costs
    Aug 13, 2021 · The City of Westminster's deputy leader Melvyn Caplan has resigned after costs for the Marble Arch Mound spiralled from £3.3 million to £6 ...
  15. [15]
    Marble Arch Mound costs have nearly doubled - ianVisits
    and later removing — the now notorious Marble Arch Mound has nearly doubled from the original £3.3 million to £6 million.Missing: timeline | Show results with:timeline
  16. [16]
    Marble Arch Mound Given Green Light
    Mar 31, 2021 · Westminster City Council's plans to build Marble Arch Mound, a 24m landscaped hill, were approved on 30 March 2021.Missing: permission date
  17. [17]
    Marble Arch Mound - Update on Design, commission and ... - Decision
    May 11, 2021 · a) Approved the Mound to progress to site construction to enable its delivery according to the required timeframes. b) Approved the overall ...Missing: political funding
  18. [18]
    Decisions for issue Marble Arch Mound - Update on Design ...
    May 11, 2021 · b) Approved the overall design development approach and means to reduce overall net costs through legacy planning and income generation ...Missing: political funding
  19. [19]
    None
    Nothing is retrieved...<|control11|><|separator|>
  20. [20]
    Marble Arch Mound's finances 'mismanaged and misrepresented'
    Oct 21, 2021 · A part of the council's wider £150m investment in the Oxford Street District, the Mound was designed to encourage more visitors to the area.Missing: initial | Show results with:initial
  21. [21]
    Marble Arch Mound: Soaring costs were 'devastating and avoidable'
    Oct 20, 2021 · A report found senior council staff were told repeatedly that the project would be overbudget.
  22. [22]
    Learning from Marble Arch Mound - MVRDV
    Jan 28, 2022 · The Marble Arch Mound's costs escalated to £6 million, an inexplicable budget increase of almost £5 million for which we never received an ...Missing: origins | Show results with:origins
  23. [23]
    Marble Arch Hill, temporary installation in London - MVRDV
    A 25-meter-tall metal scaffold will be covered with plywood, soil, and plants, all to be reused when the structure is dismantled. A winding path will lead ...
  24. [24]
    Marble Arch Mound: report slams 'devastating' failure of MVRDV ...
    Oct 21, 2021 · The same month the council also admitted that the costs associated with the project had ballooned – from an original budget of £3.3 million to ...
  25. [25]
    Damning report into the failures of the Marble Arch Mound - ianVisits
    plus £0.5 million for permanent improvements in the area, but those ...Missing: original | Show results with:original
  26. [26]
    Marble Arch Mound is SHUT after two days amid storm of criticism
    Jul 29, 2021 · City of Westminster Council admitted it was 'clear that it is not ready' but failed to explain why it opened on Monday when it was not finished.<|control11|><|separator|>
  27. [27]
    Why has the Marble Arch Mound closed and what happens if I have ...
    Jul 29, 2021 · In a statement posted on its website, Westminster City Council said it closed the installation because it is 'not yet ready for visitors'.
  28. [28]
    London's Marble Arch Mound closes after a turbulent six-month run
    Jan 10, 2022 · Marble Arch Mound was originally slated to cost just under $3 million. ... date,” reads the #SaveTheMound petition. “This icon of modern ...Missing: origins | Show results with:origins
  29. [29]
    82ft tall 'Marble Arch Mound' takes shape ahead of July 26 opening
    Jun 22, 2021 · The 82ft artificial hill opens on July 26 costing up to £8 for adults and £5 for children who will enjoy breathtaking views of the famed ...
  30. [30]
    Council suspends bookings to MVDRV's Marble Arch Mound - Dezeen
    Jul 29, 2021 · MVRDV's £2 million fake hill in central London has been ridiculed by critics and forced to temporarily close, with refunds issued to ...
  31. [31]
    The Marble Arch Mound Dates and Times - See Tickets
    Opening times are 10am-8pm weekdays and 9am-8pm weekends - we cant wait to see you. Tickets are available on the door or can be booked in advance.Missing: entry policies<|separator|>
  32. [32]
    Marble Arch mound to reopen next month after council said it 'wasn't ...
    Jul 29, 2021 · Tourists hoping to visit the Marble Arch mound won't have long to wait – as ticket sales have already restarted for August 9 onwards.
  33. [33]
    How The Marble Arch Mound Turned Into 'London's Worst Tourist ...
    Aug 2, 2021 · A centerpiece of the plans was construction of an 82-foot hill overlooking Marble Arch, for visitors to climb.
  34. [34]
    Marble Arch Mound: Attraction to stay permanently free - BBC
    Sep 1, 2021 · A viewing platform described as "London's worst tourist attraction" will remain free to climb until it closes in January 2022.Missing: origins | Show results with:origins
  35. [35]
    Marble Arch Mound to open as free attraction after 'spectacular flop'
    Aug 6, 2021 · Westminster council has dropped the £4.50 entrance fee after a flurry of complaints from the first visitors to man-made hill, which temporarily ...Missing: policies | Show results with:policies
  36. [36]
    Scrawny trees, patchy grass, terrible view: why £6m Marble Arch ...
    Aug 28, 2021 · Two complaints stand out: its scrawny trees and patchy brown grass look nothing like the luxuriant foliage promised in computer visualisations ...
  37. [37]
    Londoners Were Promised a Hill With a View. They Got a Pile of ...
    Jul 28, 2021 · They Got a Pile of Scaffolding. The $2.7 million Marble Arch Mound was meant to create a new attraction for visitors in the middle of London.Missing: operation | Show results with:operation<|separator|>
  38. [38]
    I Visited $8M Fake Hill Described As London's Worst Attraction: Photos
    Aug 22, 2021 · The local council said that it "wasn't ready for visitors when it opened" and offered refunds. See more stories on Insider's business page. The ...
  39. [39]
    Marble Arch Mound (2025) - All You Need to Know BEFORE You Go ...
    Rating 2.9 (19) Climb a geometric structure covered in wildflowers and green living walls, where art installations and vibrant light displays await inside.
  40. [40]
    'The worst thing I've ever done in London': Is Marble Arch Mound the ...
    Aug 2, 2021 · “It's a monstrosity,” says Carol Orr (55), a tourist from Glasgow visiting the mound on Wednesday, who has decided not to even attempt a climb.
  41. [41]
    Marble Arch Mound: London's most divisive attraction finally closes ...
    Jan 10, 2022 · “Horrible metal stairs and the poor dead plants”, wrote Christine and Thomas from Gloucestershire on TripAdvisor. If the claimed figure of ...<|separator|>
  42. [42]
    Marble Arch Mound draws crowds keen to see how bad it is
    Aug 23, 2021 · The Marble Arch Mound was strikingly busy when the Guardian paid a visit. But, then again, it is now free – and many people were only there to see if it was as ...
  43. [43]
    London's Marble Arch Mound is a heap of earth | CNN
    Jul 28, 2021 · The Marble Arch Mound in London has opened to a fanfare of publicity – but visitors say it is an unfinished, hollow mound of earth.
  44. [44]
    Visitors head to Marble Arch mound as London attraction 'so bad it ...
    Jan 9, 2022 · A London attraction described as 'so bad it was good' after it was beset by criticism has seen a rush of visitors just hours before it permanently closes.
  45. [45]
    Marble Arch Mound: London's £2m 's**t hill' roundly ridiculed
    Jul 28, 2021 · The 25-metre-tall Marble Arch Mound is a temporary installation commissioned by Westminster City Council and designed by the Rotterdam-based ...Missing: origins | Show results with:origins
  46. [46]
    Why the Marble Arch Mound is a slippery slope to nowhere
    Jul 25, 2021 · Last week, abseiling operatives were still frantically sticking slabs of turf to its sloping sides. The result looked parched and patchy, more ...Missing: aesthetic | Show results with:aesthetic
  47. [47]
    Tourists atop London's £2m Marble Arch Mound call it 'hideous ...
    Aug 2, 2021 · Londoners who paid £6.50 to scale the notorious Marble Arch mound have shared their disappointment at the experience - speaking just hours before Westminster ...Missing: reviews dirt
  48. [48]
    Marble Arch Mound: Much-mocked tourist attraction to close - BBC
    Jan 8, 2022 · The Marble Arch Mound, which was supposed to attract people back into the heart of the city, charged visitors up to £8 when it opened in July.Missing: runtime | Show results with:runtime
  49. [49]
    Marble Arch Mound: deputy council leader resigns over £6m cost
    Aug 13, 2021 · “Total costs are now £6m, covering every aspect of the project: construction, operation and eventual removal. With regret, I have accepted the ...Missing: overrun responsibility
  50. [50]
    Marble Arch Mound: call to review 'culture of complacency' at council
    Oct 28, 2021 · Councillors have called for an independent review of a “culture of complacency” at a flagship Tory-run council that ran up a £3m overspend on a much-derided ...Missing: approvals decisions<|separator|>
  51. [51]
    Call for answers on 'flopped' Marble Arch Mound attraction - BBC
    Aug 4, 2021 · Labour councillors have called for an investigation into the Marble Arch Mound after London's new tourist attraction "spectacularly flopped". ...Missing: criticism accountability<|separator|>
  52. [52]
    City leader stands firm in 'mound' row | Westminster Extra
    Sep 24, 2021 · The leader of the city council has apologised for the Marble Arch Mound failures while insisting it has become a “cult classic” as she faced calls for it to be ...
  53. [53]
    Marble Arch Mound now just a skeleton - The Architects' Journal
    Feb 28, 2022 · Marble Arch Mound now just a skeleton. 28 February 2022 · By will ... original budget. According to a blog post on MVRDV's website, the ...
  54. [54]
    Marble Arch Mound: Parts of attraction to be used in estate ... - BBC
    Sep 20, 2022 · Mocked Marble Arch Mound set to close · Dismantling the Marble Arch Mound cost £660,000. Westminster Council's deputy leader Melvyn Caplan, who ...Missing: expenses | Show results with:expenses
  55. [55]
    The Marble Arch Mound cost £660000 to dismantle - Time Out
    Mar 29, 2022 · Now it's been revealed by Westminster Council that dismantling the mound cost taxpayers in the region of £660,000. That's a spicy demolition ...Missing: process | Show results with:process
  56. [56]
    Oxford Street: Marble Arch Mound overspend prompts review - BBC
    Oct 7, 2022 · Dismantling the Marble Arch Mound cost £660,000 · Mocked Marble Arch Mound set to close. Westminster City Council leader Adam Hug said: "Upon ...
  57. [57]
    Scathing Marble Arch Mound report finds 'unacceptable' failings
    A damning report into the Marble Arch Mound has found a slew of management failures and a deliberate attempt by managers to hide the project's rising costs ...
  58. [58]
    London's Marble Arch Mound was a fiasco in a city losing so many ...
    Aug 17, 2021 · Built to tempt shoppers back to Oxford Street, the Mound has ended up costing Westminster council £6 million. This is double the forecasted cost ...Missing: fiscal accountability