Thames Gateway Bridge

The Thames Gateway Bridge was a proposed toll road crossing over the River Thames in , , intended to connect in the London Borough of Newham on the north bank with in the Royal Borough of Greenwich on the south bank. First mooted in the 1970s as part of broader regeneration efforts to stimulate in deprived areas, the project gained momentum in the early 2000s under (TfL), with plans for a 2 km cable-stayed structure featuring a 80-meter and for 72,000 vehicles daily. Aimed at alleviating congestion on downstream bridges like the , the bridge was envisioned to include pedestrian and cycle paths alongside vehicular lanes, supporting housing and commercial growth projected for up to 160,000 new residents in the vicinity. Despite initial backing from and TfL, the proposal faced significant opposition during a protracted concluding in 2006, with objectors citing projected increases in traffic volumes, emissions exceeding EU limits, and adverse impacts on local air quality in boroughs like and Newham. In 2007, the planning inspector recommended rejection, a decision upheld when incoming formally cancelled the project in 2008, deeming it environmentally damaging, financially burdensome at an estimated £500 million cost, and unpopular among residents who prioritized alternatives like public transit enhancements over additional road capacity. The cancellation reflected broader debates on in transport planning, where new road infrastructure often generates equivalent additional traffic rather than reducing overall congestion, as evidenced by empirical studies on similar projects. Safeguarding orders reserving land for the bridge, in place since 1940, were finally lifted by the UK government in July 2025, freeing approximately 40 hectares for housing development potentially accommodating thousands of new homes and extensions to the , marking the definitive end to a scheme stalled for over four decades amid competing priorities for urban regeneration and sustainable mobility. This outcome underscores causal realities in infrastructure decision-making, where local political opposition from affected boroughs like —concerned with spillover traffic—and fiscal constraints outweighed projected benefits, despite endorsements from Council for enhanced connectivity.

Overview

Project Description

The Thames Gateway Bridge was proposed as a crossing over the River Thames in , linking in the London Borough of Newham on the north bank to in the Royal Borough of on the south bank. It was planned to feature six lanes for vehicular traffic, comprising two lanes in each direction for private cars and two dedicated lanes for such as buses, alongside separate paths for pedestrians and cyclists. A tolling system was incorporated to regulate usage and generate revenue, with proposed charges of £1 for residents of Newham and Greenwich boroughs and £2 for other users; heavy goods vehicles were initially excluded from access. The estimated construction cost stood at around £450 million, to be funded primarily through investment recovered via tolls, supplemented by government contributions of approximately £200 million.

Strategic Objectives

The Thames Gateway Bridge was intended to remedy the scarcity of vehicular crossings east of the , the primary route handling substantial traffic but plagued by chronic congestion, thereby lessening pressure on more central Thames spans like and the . This would have provided a dedicated link between on the north bank and on the south, spanning approximately 1.3 kilometers and accommodating cars, lorries, buses, cyclists, and pedestrians without direct motorway connections to minimize induced long-distance travel. A core strategic aim was to bolster the regeneration initiative, a government-led program targeting underdeveloped areas along the for economic revitalization. The bridge was positioned to enable and growth in these deprived locales, supporting plans for up to 160,000 additional homes and 42,000 jobs across the region, which spans from to coastal and . Complementing road capacity, the project emphasized multimodal integration, with two of the six bridge lanes reserved exclusively for to prioritize buses and future rail services over private vehicles. This aligned with broader transport goals, including extensions to the and enhanced networks to serve new developments and reduce in expanding residential and industrial zones.

Historical Background

Early Concepts and Safeguarding

The safeguarding direction for the Thames Gateway Bridge site was established in amid wartime planning efforts to reserve land for potential future transport infrastructure, including a road crossing over the River Thames east of . This measure aimed to prevent conflicting development on corridors identified as strategically important, reflecting planners' anticipation of post-war traffic demands in the expanding metropolitan area, though no immediate construction followed due to the era's priorities. By the 1970s, concepts for an Thames crossing were revived through feasibility studies addressing surging vehicular volumes straining existing routes such as the and . Initially termed the East London River Crossing, the proposal sought to extend the A406 North Circular trunk road southward across the Thames, linking to the A2 toward and providing downstream relief from upstream bottlenecks at and central tunnels. Assessments highlighted the need for enhanced connectivity to support industrial and residential growth in the corridor, with early schemes favoring a tunnel alignment before shifting toward bridge options amid lobbying from local authorities like the London Docklands Development Corporation. Public inquiries in the late 1970s and into the 1980s examined alignments between and but deferred implementation due to funding constraints and competing priorities.

Revival under Livingstone Administration

In the early 2000s, under Ken Livingstone's mayoralty following his election in May 2000, the Thames Gateway Bridge project was actively revived as a key component of 's regeneration strategy. Livingstone's (GLA) positioned the bridge to address transport deficiencies in the , an area designated for substantial urban and economic development stretching from into and . The initiative aligned with the emerging , which Livingstone drafted from 2000 onward and finalized in February , explicitly endorsing the bridge to facilitate regeneration and intensification in the by improving cross-river connectivity. The emphasized the bridge's role in linking underdeveloped eastern boroughs such as Newham and Barking and Dagenham—characterized by higher deprivation levels—with southern areas including and , aiming to promote balanced growth and reduce east-west disparities without relying solely on radial rail links. By March 2004, the submitted a hybrid bill to to secure the necessary powers for , garnering initial support from local authorities like the London Borough of Greenwich and Bexley Council, which viewed it as essential for unlocking development potential in their jurisdictions. This legislative step reflected Livingstone's commitment to the project as part of a broader £10 billion investment program announced in October 2004, which highlighted the bridge's four-lane road capacity plus dedicated routes to spur economic activity.

Public Inquiry and Initial Approval

The public inquiry into the Thames Gateway Bridge scheme, covering planning permissions and associated compulsory purchase and side road orders, opened on 13 June 2005 at Charlton Athletic Football Club and closed on 3 May 2006 following an 11-month process that included a two-month suspension for Transport for London to prepare supplementary evidence. The inquiry examined proposals for a £500 million cable-stayed road bridge with integrated public transport elements, amid concerns over traffic generation, environmental impacts, and alignment with the London Plan's emphasis on reducing car dependency. Evidence from promoters, including Transport for London, highlighted projected modal shifts toward public transport—such as segregated bus lanes, Docklands Light Railway extensions, and East London Transit enhancements—to cap private vehicle trips at around 40% of bridge demand and mitigate induced traffic, supported by transport modeling forecasts of limited net vehicle kilometers increase. Inspector Michael Ellison's report, delivered to on 17 November 2006, recommended refusal of the applications, citing unreliable modeling (non-compliant with Design Manual for Roads and Bridges standards at multiple validation sites), projected 1.75% rise in total vehicle kilometers, exacerbated congestion, degraded air quality, and an additional 55,000 tonnes of annual CO2 emissions by 2016. The inspector deemed the scheme non-compliant with policy 3C.15 on hierarchy, arguing that promised mitigations, including £70 million in for public realm and improvements, were insufficient to offset car-favoring outcomes or deliver reliable regeneration benefits, with modal shift claims undermined by modeling flaws and policy inconsistencies favoring road-building over . Parliamentary consideration of the Thames Gateway Bridge Bill advanced through initial committee stages in 2006, with debates in the addressing funding contingencies and integration with regeneration, including up to £200 million in government PFI credits for construction. Despite the inspector's stance, the government indicated provisional progression contingent on refined mitigation plans for traffic dispersal and environmental safeguards, though no final decision issued before reopened in July 2007 to assess additional promoter-submitted evidence on these issues.

Design and Engineering

Structural Features

The Thames Gateway Bridge was designed as a cable-stayed structure to span the River Thames between and . This configuration allowed for efficient load distribution via cables anchored to a central support, facilitating a relatively slender deck while supporting vehicular, pedestrian, and cycle traffic. The bridge deck was planned to include six lanes in total: four for general traffic and two dedicated to vehicles, such as buses or future . Separate provisions were incorporated for cyclists and pedestrians, including dedicated paths to promote multi-modal use and enhance connectivity without compromising the main . requirements dictated a vertical clearance of 50 meters above high water to permit passage of large vessels on the tidal Thames. The design emphasized , targeting high environmental standards through minimized ecological disruption and of green features to blend with the surrounding and . Ground investigations informed pier placements to address local conditions, ensuring in the alluvial Thames .

Connectivity and Access Plans

The Thames Gateway Bridge was planned to integrate with regional road networks through dedicated approach roads, connecting the A406 at its junction with the A13 Alfreds Way in on the northern side to the A2016 Western Way spine road in on the southern side. These approaches included provisions for extensions and new alignments to facilitate traffic flow from the A13 corridor eastward and local distributors in , prioritizing bus lanes to support high-capacity over general vehicular traffic. Dedicated public transport lanes—two in each direction—were incorporated into the bridge design to enable seamless integration with systems, particularly the (ELT) network, which was envisioned to extend services across the crossing for multi-modal journeys linking to and beyond. This alignment aimed to prioritize buses and potentially accommodate future rail connections, including exploratory ties to (DLR) extensions in the area, fostering reliance on non-car modes amid regeneration. To fund maintenance and mitigate overuse, the bridge would implement a tolling system patterned on the , with charges set at approximately twice the Dartford rates—around £4 for cars during peak periods—offering a 50% discount for qualifying local residents to balance accessibility and . This electronic tolling approach, similar to Dartford's free-flow model, was intended to generate revenue for operational costs while discouraging non-essential trips, thereby preserving capacity for local and freight movements essential to regional connectivity.

Location and Environmental Setting

Geographic Route

The Thames Gateway Bridge was proposed to cross the River Thames at , linking the area in the London Borough of Newham on the north bank to , spanning the boundary between the Royal Borough of and the London Borough of on the . This alignment positioned the crossing approximately 4 kilometers east (downstream) of the , providing an additional east-west connection beyond existing infrastructure like the . On the northern approach, the route would connect from the A13 Newham Way near its junction with the A406 North Circular, passing through industrial zones including proximity to the and leveraging access to former docklands such as the Royal Victoria Dock vicinity. The bridge deck would span the river's width at this point, which measures about 500 meters, amid a terrain characterized by reclaimed land and wharves. Southern connections would tie into the A2016 Western Way in Thamesmead, routing through post-industrial landscapes while skirting the edges of green spaces like the periphery of Oxleas Woods to the west. The design aimed to align with existing road networks and avoid direct overlap with London City Airport's primary flight paths, positioning the structure clear of key approach and takeoff surfaces. Overall, the path emphasized connectivity across heavily developed, non-residential riverine corridors dominated by utilities and facilities.

Surrounding Infrastructure

The Thames Gateway Bridge was planned to integrate with existing road networks by connecting to the A406 North Circular at its junction with the A13 Alfreds Way in Beckton on the northern side, facilitating access to London's primary orbital route. On the southern bank, it would link to the A2016 Western Way in Thamesmead, a dual carriageway extending toward Erith and connecting to radial routes like the A206, which leads to the Dartford Crossing. This configuration aimed to bridge connectivity gaps in east London's urban fabric, where southern approaches lack robust circumferential infrastructure comparable to the northern North Circular. The proposed location spans a void in fixed Thames crossings, situated approximately 10 km east of and 20 km west of the , with no intervening road bridges or tunnels prior to recent developments like the . This expanse exacerbates east-west travel imbalances, as traffic relies heavily on distant western tunnels or ferries, straining radial routes without direct orbital relief south of the river. Proximity to London City Airport, located about 2 km northeast, required stringent aviation coordination, including height limitations on the bridge structure to preserve the airport's steep flight approach paths. Adjacent public transport includes the (DLR), with safeguarded land overlapping planned extensions to Beckton Riverside and , underscoring multi-modal integration potential amid pre-existing rail gaps in the zone.

Economic and Regenerative Rationale

Projected Job Creation and Growth

Proponents of the Thames Gateway Bridge forecasted that it would enable the creation of approximately 25,000 new jobs in the surrounding region by improving road access to underdeveloped industrial sites and supporting housing-led regeneration on both banks of the Thames. emphasized that the crossing would stimulate economic activity in and the through better linkages to employment hubs, potentially generating up to 42,000 jobs overall via enhanced worker mobility and development viability. The bridge's design was projected to particularly benefit and sectors by providing direct vehicular connections between and , areas with significant port-related and industrial potential, thereby reducing freight and commuter journey times. This improved accessibility was anticipated to contribute to GDP growth in the through agglomeration effects, where shorter travel distances facilitate labor market integration and business expansion without reliance on congested existing crossings. Official appraisals from the mid-2000s, including those tied to the , modeled net economic advantages in the range of £2-3 billion over the project's lifespan, driven primarily by these connectivity gains.

Support for Thames Gateway Development

The regeneration initiative, outlined in the UK government's Sustainable Communities Plan of 2003, targeted the construction of 160,000 homes and the creation of 180,000 jobs across deprived areas spanning , south , and north by addressing concentrations of economic deprivation and underutilized land. This policy emphasized transforming post-industrial brownfield sites into viable residential and commercial zones to stimulate sustainable growth in regions marked by high unemployment and low housing density. The Thames Gateway Bridge was positioned as a component to support this development by bridging on the north bank with on the south, thereby unlocking access to regeneration zones south of the river that lacked sufficient east-west crossings. Proponents argued that the bridge would enable the efficient mobilization of labor from lower-income communities in and boroughs—areas with persistent deprivation indices—to expanding job centers in the Docklands and beyond, potentially mitigating regional inequalities through improved daily commutes without reliance on congested central tunnels. Business organizations, including those advocating for Thames Gateway projects, highlighted the bridge's role in facilitating the redevelopment of derelict industrial land for housing and enterprise, estimating that enhanced connectivity could accelerate the delivery of planned homes by integrating isolated southern sites into the broader . This alignment with national housing targets was seen as essential for reducing deprivation by fostering mixed-use developments that combine affordable residences with local employment opportunities, thereby promoting self-sustaining community revitalization.

Controversies and Opposition

Environmental and Ecological Criticisms

Opponents of the Thames Gateway Bridge, including environmental groups and the public inquiry inspector, highlighted risks to local habitats from construction and increased human activity. The Environment Agency expressed concerns over the loss of wild habitats in the Thames corridor, where the bridge's eastern crossing near Thamesmead and associated road links would encroach on ecologically sensitive floodplains and estuarine zones vital for wetland species. These areas support diverse flora and fauna, including bird populations reliant on the Thames for migration and breeding, with critics arguing that fragmentation of habitats could lead to irreversible biodiversity declines without adequate compensation measures. Air quality assessments during the 2005-2006 public inquiry revealed that the bridge would exacerbate pollution in an already deficient region. The inspector concluded that local air quality, including nitrogen oxides (NOx) and nitrogen dioxide (NO2) levels, would be worse in 2016 with the scheme than without it, despite proponent mitigations like emissions standards for vehicles. This projected deterioration conflicted with obligations under the EU Air Quality Directive (2008/50/EC), as the area east of London struggled to meet legal limits for roadside pollutants, potentially harming sensitive ecosystems and human health in proximity to the river. Additionally, the scheme's net environmental footprint included an estimated 55,000 additional tonnes of emissions annually by 2016, undermining commitments to reductions under the Climate Change Act 2008. The inspector deemed this unacceptable, noting the bridge's failure to align with sustainability goals in a prone to tidal surges, where elevated infrastructure could alter natural water flows and heighten flood risks to adjacent wetlands.

Traffic Congestion and Pollution Concerns

Opponents highlighted projections that the Thames Gateway Bridge would generate induced traffic demand, exacerbating on roads in southern . Modeling submitted during the indicated that the scheme would increase vehicle flows through by up to 20-30% on key routes like the A206, drawing additional trips rather than solely diverting existing ones. Skepticism was expressed regarding assumptions of significant modal shifts to , with critics arguing that the bridge's design as a six-lane would primarily attract car users, potentially raising overall vehicle miles traveled across southeast . Transport for London's traffic forecasts anticipated up to 100,000 additional daily vehicle crossings by 2016, but independent analysis suggested underestimation of long-distance rat-running through residential areas south of the Thamesmead landing point. Air quality concerns centered on breaches of and limits in already non-compliant zones along approach roads in and . The scheme's environmental statement conceded that nitrogen dioxide levels would exceed targets in 2016 with the bridge operational, affecting up to 5,000 residents within 200 meters of impacted roads, despite baseline already violating directives. Conservatives challenged these projections in assembly scrutiny, citing TfL's own data showing dramatic pollution increases on Bexley streets and questioning the adequacy of mitigation in high-risk areas.

Local Community and Airport Safety Issues

Residents in the London Borough of voiced strong opposition to the Thames Gateway Bridge, citing anticipated increases in and volumes that would intrude upon suburban residential areas. During the 2005 public inquiry, local resident Mr. Ruddell highlighted risks of heightened noise leading to elevated incidence, criticizing Transport for London's modeling as inadequate. Bexley Council, while initially supportive in principle, objected to the inquiry process in 2006 over projected adverse impacts on borough roads, fearing spillover congestion from the bridge's southern approaches near . These concerns reflected broader "not-in-my-backyard" sentiments among communities wary of disrupting quiet locales with heavy vehicle routes and commuter flows. In the London Borough of Greenwich, community attitudes were more mixed despite council endorsement, with some residents expressing neutrality or reluctance toward added infrastructure in an already dense area. Critics, including local councillors, warned of exacerbated noise and from the bridge's eastern placement, potentially affecting Thamesmead's residential zones without sufficient . London City Airport authorities raised safety objections related to the bridge's proximity to active flight paths, particularly concerning potential interference during and operation. The airport highlighted risks to low-level approaches, with the proposed structure's height constrained by safeguards, limiting crane usage and complicating build logistics. These issues stemmed from the site's location just east of the airport's , where even temporary elements could disrupt instrument approaches or pose collision hazards. Equity critiques focused on disproportionate burdens falling on south bank locales like Bexley and Greenwich, which anticipated traffic influxes—estimated to add thousands of daily vehicles—without equivalent economic uplift compared to north bank sites like . Opponents argued the project favored regeneration on the northern side, connected to major employment hubs, while southern suburbs faced unmitigated disruptions like heightened accident risks from intensified road use, as noted in the 2006 inquiry inspector's findings on reduced overall safety. This imbalance was seen as exacerbating deprivation in Thames Gateway's southern reaches, where benefits skewed toward cross-river access for northern commuters rather than localized gains.

Political and Decision-Making Process

Advocacy from Proponents

Proponents, led by and the (GLA), advocated for the Thames Gateway Bridge as a vital component of regional regeneration, arguing it would connect residential areas in southeast London—predominantly working-class communities—with fast-growing employment hubs in the northeast, thereby fostering economic prosperity and job access. , a figure, emphasized the need for such infrastructure to support development in deprived zones, aligning with New Labour's strategy to stimulate growth through improved transport links in underinvested eastern boroughs. Traffic modeling presented by supporters indicated the bridge would alleviate congestion at existing crossings like the by diverting local east-west journeys away from routes, providing net relief to residents in east and southeast areas. assessments highlighted that the structure, planned as a toll-free with dedicated lanes, would encourage modal shifts toward buses and cycles over time, drawing parallels to the Queen Elizabeth II Bridge at , which proponents claimed had similarly underestimated long-term demand redistribution despite initial induced traffic concerns. In November 2002, Livingstone cast the decisive vote in the London Assembly to approve the project, expressing confidence in its role for balanced growth without reliance on upstream crossings overburdened by orbital traffic. Supporters countered environmental critiques by stressing integrated sustainable features, such as integration, positioning the bridge as essential for equitable development in areas lagging behind west London's .

Rejection by Boris Johnson

Upon taking office as in May 2008, initiated a review of major transport projects, leading to the formal cancellation of the Thames Gateway Bridge on 6 November 2008. The decision was announced as part of a £3.5 billion reallocation of funds away from road-building schemes toward investments in cycling, walking, and rail infrastructure, aligning with Johnson's policy shift to reduce reliance on private vehicles and emphasize lower-carbon alternatives. Johnson justified the rejection by highlighting concerns from the preceding , arguing that the bridge would induce unsustainable traffic growth across and impose environmental costs— including increased emissions and pressure on local ecosystems—that exceeded projected benefits. The scheme's estimated completion cost of over £500 million was thereby avoided, with funds redirected to alternative priorities such as expansions, though critics contended this overlooked the inquiry inspector's prior recommendation for approval based on evidence of regional economic regeneration needs.

Subsequent Reviews and 2025 Cancellation

Following the 2008 cancellation by Mayor Boris Johnson, discussions on additional Thames river crossings emerged in 2012–2013 through Transport for London consultations, which examined options like a Gallions Reach bridge to address east London connectivity without directly reviving the Thames Gateway Bridge scheme. These inquiries, prompted by ongoing traffic pressures, reopened debate on lower Thames crossings but faced opposition from Johnson, who reiterated in responses to London Assembly queries that the original Thames Gateway Bridge proposal remained unviable and would not be resuscitated due to its environmental impacts, high costs exceeding £500 million, and incompatibility with austerity measures post-2008 financial crisis. No formal revival occurred, as fiscal constraints limited major infrastructure commitments, shifting focus to alternatives like the Silvertown Tunnel. The project remained dormant until July 17, 2025, when Transport Minister announced the lifting of the safeguarding direction originally imposed in 1940 to reserve land for the bridge. This decision formally ended protections on approximately 100 hectares of land in and , enabling redevelopment for over 15,000 homes, extensions of the to and Riverside, and other growth-oriented uses. The rationale cited economic unviability amid post-Brexit trade shifts and stagnant regeneration in the area, which had failed to materialize anticipated growth since the 2000s plans. Prioritizing housing delivery over a stalled road project aligned with goals to address London's supply shortages, as the bridge's original justifications—such as supporting Thames Gateway development—were deemed outdated given alternative crossings like the completed and Dartford options. Lightwood emphasized that lifting safeguards would accelerate local development without compromising transport capacity, reflecting a pragmatic reassessment of 85-year-old reservations that had constrained .

Legacy and Aftermath

Foregone Benefits and Opportunity Costs

The cancellation of the Thames Gateway Bridge deprived the region of projected economic uplift, including an estimated 42,000 new jobs from enhanced cross-river connectivity between and , two of London's most deprived locales. These areas, characterized by long-term economic decline since the and pockets of severe deprivation, have seen regeneration efforts hampered by inadequate transport links, perpetuating high rates above 10% despite targeted initiatives. Persistent reliance on overburdened crossings like the has exacerbated traffic bottlenecks, with frequent closures prompting detours that elevate fuel consumption and emissions through extended mileage and stop-start driving. Without the bridge, commuters between north and south banks face journeys prolonged by up to 40 minutes on average during peak hours, amplifying regional vehicle kilometers traveled and associated . Proponents critique the prevailing environmental objections as yielding pyrrhic gains, insofar as forestalling the bridge curtailed vital for integrating deprived zones into broader labor markets and supply chains, thereby forgoing causal pathways to alleviation via in connectivity-starved locales. This stance holds that unbuilt crossings constrain Thames Gateway's potential to deliver national economic dividends, as evidenced by subdued productivity in the estuary corridor relative to infrastructure-enabled elsewhere.

Land Reallocation for Housing and Transit

On 17 July 2025, the UK government lifted the safeguarding direction on land reserved for the Thames Gateway Bridge, which had been in place since 1940, enabling its repurposing for housing and transit projects. This decision freed approximately 100 hectares of brownfield sites in Thamesmead and Beckton for development, addressing long-standing constraints on urban regeneration in east London. The Thamesmead Waterfront site, spanning 100 hectares, is now targeted for up to 15,000 new homes as part of the government's New Towns programme, with shortlisting announced on 1 2025. This masterplan includes a new town center, enhanced natural assets, and integration with riverside communities, building on Peabody's regeneration efforts for the area. In parallel, Riverside developments aim to deliver around 10,000 homes, with recent approvals for 2,900 units by St William on former land, incorporating commercial spaces and public realms. To support these housing expansions, initiated consultations on 23 June 2025 for a (DLR) extension branching from , serving Beckton Riverside and terminating in . The approximately 3-mile route would provide rail connectivity to an estimated 25,000 new residents and jobs, partially fulfilling original aims for improved east-west links without road infrastructure. Government announcements emphasized that reallocating safeguarded land accelerates brownfield and delivery, prioritizing vertical and proximity to existing over expansive linear projects. The New Towns Taskforce report, published 28 September 2025, reinforced this by advocating strategic sites like for exceeding minimum targets through integrated .

References

  1. [1]
    Thames Gateway Bridge - marksbarfield.com
    Status: Project cancelled. Marks Barfield Architects were appointed by TfL and the GLA to lead design proposals for the Thames Gateway Bridge in 2003 as an ...Missing: history facts<|separator|>
  2. [2]
    Thames Gateway Bridge - Adams Hendry
    Sep 19, 2014 · The Thames Gateway Bridge was proposed to improve access to regeneration sites, but the project was not progressed in 2008, though support for ...Missing: history facts
  3. [3]
    Thames Gateway Bridge: The proposed answer to east London's ...
    Sep 18, 2023 · The Thames Gateway Bridge was backed by Ken Livingstone, before being scrapped by Boris Johnson in 2008.
  4. [4]
    [PDF] Extracts from the Inspector's Conclusions in the Thames Gateway ...
    The Public Inquiry into the proposed Thames Gateway Bridge ended in May 2006 after 11 months including a two-month break when Transport for London, ...Missing: history | Show results with:history
  5. [5]
    East London Thames bridge plan 'a mistake' - BBC News
    May 12, 2013 · Mr Johnson originally cancelled the project after a public consultation received hundreds of objections from residents and environmentalists.Missing: controversies | Show results with:controversies
  6. [6]
    The 14-mile Thames crossing delayed by 66 miles of paperwork
    Apr 8, 2025 · It was cancelled in 2008 by then Mayor of London Boris Johnson – too expensive, too environmentally damaging, too unpopular locally.
  7. [7]
    The Saga of the Thames Gateway Bridge at Thamesmead
    Apr 11, 2011 · Boris cancelled the bridge after pressure from the former leader of Bexley Council, Ian Clement. Boris had been helped by Ian Clement during ...
  8. [8]
    Government lifts 85-year safeguarding on London Gateway Bridge ...
    Jul 18, 2025 · The UK government has formally lifted the safeguarding direction on land earmarked for the long-proposed London Gateway Bridge.Missing: facts | Show results with:facts
  9. [9]
    Thames Gateway Bridge axed for good as land freed up for housing
    Jul 17, 2025 · The removal of development barriers will make it possible for housing to be built on either side of the Thames, where the access roads to the ...
  10. [10]
    Thames Gateway Bridge finally killed off to boost new homes and DLR
    Jul 17, 2025 · It was strongly supported by Greenwich Council, but equally strongly opposed by neighbouring Bexley, which feared increased traffic congestion.
  11. [11]
    Thames Gateway Bridge | Road Projects - Lost story
    A toll will be charged on the bridge to fund its costs; it will be £1 for local residents (Newham and Greenwich boroughs) and £2 for everyone else. The ...Missing: types | Show results with:types
  12. [12]
    Thames Gateway Bridge and cost of tolls - Greater London Authority
    The average annual cost of £5m for the bridge includes the cost of major maintenance as well as the cost of operating and maintaining the tolling system. The ...Missing: types | Show results with:types
  13. [13]
    England | London | Application for new Thames bridge - BBC NEWS
    Jul 22, 2004 · The initial costs of the Thames Gateway Bridge will be put up by a private company. It will recoup the funds through tolls and £200m of ...Missing: types | Show results with:types<|separator|>
  14. [14]
    [PDF] The Thames Gateway - The Delivery Plan - Medway Council
    Improved economic and business performance throughout the Gateway, through enhanced education and lifelong learning opportunities for residents, and the ...
  15. [15]
    Blears reopens Thames Gateway bridge inquiry - The Guardian
    Jul 26, 2007 · This new crossing is crucial to supporting plans for an extra 160,000 houses in the Thames Gateway region and up to 42,000 additional jobs in ...
  16. [16]
    Thames Gateway transport infrastructure (1)
    Between now and 2024 there will be significant investment in enhancing current transport infrastructure and building new infrastructure to deal with ...Missing: objectives | Show results with:objectives
  17. [17]
    Lifting of the Thames Gateway Bridge safeguarding direction
    Jul 17, 2025 · It was intended to protect land for a road crossing that has not been delivered. Since then, London's transport priorities have evolved, and ...Missing: objectives | Show results with:objectives
  18. [18]
    East London River Crossing (Hansard, 27 July 1982)
    Jul 27, 1982 · ... East London river crossing scheme will extend the existing dual carriageway A406 trunk road across the Thames to connect with the A2 and Dover.<|separator|>
  19. [19]
    Thames Crossing Proposals - Sabre Roads
    Dec 11, 2017 · There has been talk of an east London River Crossing since the 1970's but the only serious proposal I am aware of was the Thames Gateway Bridge ...Missing: studies | Show results with:studies
  20. [20]
    Thames Gateway Bridge - Greater London Authority
    The Hybrid Bill is the preferred route to obtain these powers because it ... Date. Thames Gateway Bridge, 2004/0366, 31 March 2004. Thames Gateway Bridge ...
  21. [21]
    [PDF] London Plan
    Feb 1, 2004 · Thames Gateway bridge will support regeneration and intensification. ... London: Outer Thames Gateway, West London, Upper Lea Valley and.
  22. [22]
    10bn investment programme to transform London's transport network
    Oct 12, 2004 · the proposed Thames Gateway Bridge, connecting Beckton and Thamesmead. This will carry four lanes of traffic as well as separate lanes for ...
  23. [23]
    [PDF] TRANSPORT FOR LONDON BOARD MEETING - TfL
    May 24, 2006 · 3.27 Thames Gateway Bridge – The public inquiry re-commenced on 21 February 2006 and completed on 3 May. TfL have positively rebutted all ...
  24. [24]
    Thames Gateway Bridge - Hansard - UK Parliament
    The Secretary of State received the Inspector's report following the public inquiry into the proposed Thames Gateway Bridge on 17 November.
  25. [25]
    BBC NEWS | England | London | Review ordered into Thames bridge
    Jul 26, 2007 · After the first public inquiry, which ended in May 2006, government inspector Michael Ellison recommended that the scheme be turned down.
  26. [26]
    [PDF] Business Plan 2006/7 - 2009/10 - TfL
    The Government has granted up to £200 million of PFI credits towards development and construction costs. The Thames Gateway Bridge received Planning Permission ...
  27. [27]
    [PDF] TfL River Crossings - Ground Investigation Desk Study - index.doc
    May 22, 2013 · Thames Gateway Bridge. Contaminated Land Desk Study. P1-P-R005 ... proved at the locations of the piers for the original cable stayed design in ...
  28. [28]
    [PDF] East London River Crossings: Assessment of Need - TfL
    This report details the need for additional river crossings in East London, to improve infrastructure and deliver growth, as part of a package of crossings.
  29. [29]
    A Bridge too Far - Greater London Authority
    The Thames Gateway Bridge is primarily a local link between Beckton and Thamesmead. Given at both ends of the bridge demand may feed in from more than one road ...
  30. [30]
    Thames Gateway - Greater London Authority
    Yes it does and for this reason the draft transport strategy lays great emphasis on public transport projects such as DLR ... Thames Gateway Bridge, both ...
  31. [31]
    Thames Gateway Bridge tolling system - Greater London Authority
    Analysis completed to date is based on a toll at twice the rates of the Dartford crossing with a 50% discount for local residents.
  32. [32]
    London's First Highway: The East London River Crossings
    Jun 8, 2016 · The most productive new crossing would be the Thames Gateway Bridge, the one that Boris Johnson cancelled, between Beckton and Thamesmead. It ...Missing: 1940s | Show results with:1940s
  33. [33]
    [PDF] A new generation of river crossings to revitalise the east Thames
    The East London River Crossing (the precursor proposal to the Thames Gateway Bridge) was planned to be a strategic link, with three lanes in each direction ...
  34. [34]
    [PDF] New Thames River Crossing Initial Engineering Review - TfL
    This report is a high level assessment of the engineering feasibility of options for river crossings in East London including road tunnels, road bridges and ...Missing: pylon | Show results with:pylon
  35. [35]
    A2016 - Roader's Digest: The SABRE Wiki
    Mar 14, 2025 · The A2016 is a dual carriageway from Plumstead to Erith, linking areas south of the River Thames, and is 5.1 miles long.
  36. [36]
    The trouble with the Thames | Roads.org.uk
    Aug 1, 2018 · The Silvertown Tunnel, a new road link across the Thames between North Greenwich and Silvertown, close to the existing Blackwall Tunnel.
  37. [37]
    Extending the DLR to Beckton Riverside and Thamesmead
    Jun 23, 2025 · We are proposing that the proposed DLR extension would branch off from the existing DLR line after Gallions Reach, travelling through the Beckton Riverside ...
  38. [38]
    Department for Transport offers financial support for Thames ...
    Jan 9, 2004 · It would help create around 25,000 new jobs in the region. London Transport Minister Tony McNulty said: "Effective regeneration goes hand in ...
  39. [39]
  40. [40]
    Statement from Transport for London on Thames Gateway Bridge ...
    "The Bridge would provide an essential and overdue transport link for east London creating better access to employment opportunities and stimulating economic ...
  41. [41]
    [PDF] Finance Committee Agenda Papers October 2006 - TfL
    Oct 12, 2006 · 2.64 The overall aim of the TGB scheme is to improve accessibility to, and within, the. Thames Gateway area and support the regeneration of east ...<|separator|>
  42. [42]
    [PDF] The Thames Gateway: Laying the Foundations - Parliament UK
    Nov 15, 2007 · The Sheppey bridge for example was in the original 1995 Thames Gateway Planning Framework, but did not receive direct support from the ...
  43. [43]
    [PDF] Thames Gateway Economic Development Investment Plan - SEEDA
    The Plan sets out priority strategic investments that will improve the economic performance of the Gateway. It builds on the joint RDA Economic Statement for ...
  44. [44]
    [PDF] The Thames Gateway: Laying the Foundations - National Audit Office
    May 17, 2007 · Thames Gateway Bridge planning application is called in by the Secretary of State for public inquiry. 2006 Appointment of Judith Armitt as ...
  45. [45]
    London Plan - Thames Gateway Bridge
    Improving access for people, goods and services between the north and south of the Thames is a key priority in the regeneration and development of the Thames ...Missing: objectives | Show results with:objectives
  46. [46]
    House of Commons - Transport - Written Evidence - Parliament UK
    As we recognised that there would be concerns about the impact of increased traffic across any road connections such as Thames Gateway Bridge, we proposed tolls ...
  47. [47]
  48. [48]
    Urban myth | Society - The Guardian
    Mar 11, 2003 · The environment agency, the government watchdog, is concerned that the Thames Gateway developments are in Kent and Essex, two of the UK's ...
  49. [49]
    [PDF] Evidence on Strategic river crossings - UK Parliament Committees
    3.3 For the East London River Crossing /Thames Gateway bridge proposals specifically, a crossing has been on various plans at this exact location since 1944 ...
  50. [50]
    [PDF] Local Plan Transport Assessment - London Borough of Bexley
    Thames Gateway Bridge project for a new six-lane two-way highway bridge ... Bexley raises concerns about traffic impacts, highlighting predicted increased ...
  51. [51]
    Thames Gateway Bridge and air quality in Bexley
    ... roads in Bexley that the proposed road bridge, according to TfL's own study, will dramatically increase the likely traffic and pollution outside their front ...Missing: induced southern
  52. [52]
    Troubled waters | Society - The Guardian
    Oct 19, 2004 · The Thames Gateway bridge promises to plug a gap between two of London's poorest areas, but are its regenerative claims being overplayed?Missing: studies | Show results with:studies
  53. [53]
    Bridge opinions drawn at inquiry - News Shopper
    Oct 18, 2005 · All of them, even a supporter of the bridge, expressed major concerns about the potential for serious traffic congestion and the lack of ...
  54. [54]
    Worried about bridge pollution | News Shopper
    Apr 11, 2006 · Bexley Council currently supports the bridge in principle, but objects to the inquiry due to concerns about the effects of traffic on Bexley, ...
  55. [55]
    The supporters of new roads across the Thames are stuck in the ...
    Dec 4, 2014 · A second bore at Blackwall with new feeder motorways were built in the early 1970s but the lower Thames crossing was repeatedly deferred from ...
  56. [56]
    Gateway bridge given green light | This Is Local London
    Dec 21, 2004 · But critics of the scheme fear the bridge will bring extra traffic, pollution and noise. Councillor John Kelly, who voted against the plans, ...
  57. [57]
    Bridge Going Nowhere - London - a spark in your veins
    Jan 21, 2013 · It's a section of road over in Beckton that was built in preparation for the Thames Gateway Bridge, but currently leads to nowhere apart from a dangerous drop.<|control11|><|separator|>
  58. [58]
    Thames Gateway Bridge - Greater London Authority
    I remain committed to the Thames Gateway Bridge as it would improve accessibility and support regeneration and economic development in the London Thames Gateway ...
  59. [59]
    Mayor's vote gives bridge go-ahead | News Shopper
    Nov 28, 2002 · Ken Livingstone says he has no doubts about going ahead with the new bridge at Thamesmead, a decision slammed by environmental campaigners ...
  60. [60]
    Strategies for Sustainable Growth in the Thames Gateway
    Aug 7, 2025 · The Thames Gateway was a central element of the New Labour Government's strategy to regenerate and stimulate economic growth in these areas ...
  61. [61]
    Thames Gateway Bridge - Greater London Authority
    By focussing on the existing problems in the Blackwall area, we will be providing greater relief from the impacts of congestion for the residents of east and ...Missing: studies | Show results with:studies
  62. [62]
    Livingstone backs £350m road bridge over Thames - The Guardian
    Mr Livingstone announced yesterday that he would recommend construction of the £350m bridge at a board meeting of Transport for London on Tuesday, as part of a ...Missing: endorsement | Show results with:endorsement
  63. [63]
    Transport for London scraps plans for six-lane road bridge
    Nov 6, 2008 · The Thames gateway bridge was first proposed in 1996 by Steven Norris when he was transport minister in the last Conservative government. In ...Missing: endorsement | Show results with:endorsement
  64. [64]
    Mayor shelves £3.5bn London transport plans - The Guardian
    Nov 6, 2008 · The decision by TfL follows a year-long public inquiry, which rejected the £450m bridge for environmental, social and economic reasons. The ...
  65. [65]
    New east London Thames bridge to be reconsidered - BBC News
    May 7, 2013 · But a planning inspector rejected the proposal in 2007 after an inquiry received hundreds of objections from residents and environmentalists.Missing: controversies | Show results with:controversies
  66. [66]
    Gallions Reach - Greater London Authority
    As I said in my manifesto both in 2008 and in 2012 the Thames Gateway Bridge, so conceived and proposed, is dead. It will not be resuscitated. We are going ...
  67. [67]
    New Thames road crossings 'would increase air pollution'
    Proposals for two Thames road crossings in east London would increase traffic, congestion and air pollution, according to environmental campaigners.Missing: concerns | Show results with:concerns
  68. [68]
    Thames Gateway Bridge: Safeguarding Direction - Hansard
    Jul 17, 2025 · Today I am informing the House of my decision to lift the safeguarding direction for the Thames gateway bridge.
  69. [69]
    Thames Gateway Bridge plans ditched for housing
    Jul 21, 2025 · Plans dating back more than 85 years to build the £500m Thames Gateway Bridge have finally been axed to free up land for development.
  70. [70]
    TfL scraps projects and cuts jobs - London - Home - BBC News
    Nov 6, 2008 · ... Thames Gateway Bridge had the potential to create 42,000 jobs. ... regeneration of the city." Both the Green Party and Friends of the Earth ...
  71. [71]
    [PDF] The Case for Social Infrastructure Planning
    The area today has a population that is diverse and, in parts, deprived. Unemployment rates across the London Thames Gateway are in excess of 10 per cent and ...
  72. [72]
    London Blackwall Tunnel closures linked to increased congestion ...
    Jan 16, 2025 · Dangerous driving incidents on Tower Bridge have increased by 231% during Blackwall Tunnel closures, with lorries experiencing a 341% rise ...Missing: detours | Show results with:detours
  73. [73]
    London Blackwall Tunnel closures linked to increased congestion ...
    Jan 23, 2025 · New telematics data from Geotab has revealed significant disruptions to traffic patterns, fuel usage, and road safety caused by the closures of ...
  74. [74]
    [PDF] Evidence on Strategic river crossings - UK Parliament Committees
    Additional wider network route improvements above that of the Option C variant will also deliver economic benefits from an enhanced strategic route from the ...
  75. [75]
    Thamesmead shortlisted for Government's 'New Towns' programme
    Oct 1, 2025 · The proposals would see the 100-hectare site developed into a modern, vibrant riverside community. Final designation is subject to further ...
  76. [76]
    15,000-home Thamesmead Waterfront project given welcome boost ...
    Sep 29, 2025 · A 100-hectare brownfield site in Thamesmead with capacity for 15000 new homes has been named by the Government as one of 12 potential ...
  77. [77]
    [PDF] BECKTON RIVERSIDE REGENERATION - Newham Co-Create
    As the largest strategic opportunity site in the bor- ough it has the potential to provide up to 10,000 new homes as well as local jobs and leisure facilities ...
  78. [78]
    Beckton Riverside 2,900-home scheme approved - Estates Gazette
    The approved application from St William consists of 2,900 homes, up to 54,000 sq ft of commercial and community uses and five public spaces. It sits within the ...
  79. [79]
    Potential DLR extension - Transport for London
    We're considering extending the DLR to Beckton Riverside and Thamesmead to improve transport connections and enable growth in housing and jobs.
  80. [80]
    New Towns Taskforce: Report to government - GOV.UK
    Sep 28, 2025 · The government's July 2024 policy statement on new towns launched the work of the Taskforce and made clear that boosting housing supply requires ...