Cold ironing


Cold ironing, also referred to as shore power or alternative maritime power, is a system that supplies electrical power from onshore grids to berthed ships, enabling the shutdown of auxiliary diesel engines to curb fuel use, noise, and exhaust emissions.
The term derives from historical maritime practices where coal-fired ship engines would cool ("cold iron") during port stays without power needs, but modern implementation addresses environmental pressures by substituting ship-generated power with shore-based electricity, particularly effective for reducing localized pollutants in densely populated port areas.
Empirical studies demonstrate substantial emission cuts, such as up to 97.7% for nitrogen oxides (NOx), 96.69% for sulfur oxides (SOx), and notable decreases in particulate matter (PM) and carbon dioxide (CO2) when connected, though net CO2 reductions hinge on the cleanliness of the supplying grid.
Adoption faces barriers including high capital investments for infrastructure, vessel retrofits, and cabling, alongside operational challenges like voltage synchronization and elevated electricity costs, limiting widespread use despite mandates in regions such as California ports and emerging European regulations.
Standardization via the IEC/ISO/IEEE 80005-1 framework governs high-voltage shore connections, ensuring safety and interoperability for systems typically operating at 6.6–11 kV, which has facilitated gradual expansion in major ports like those in Oslo and Trieste.

History

Origins and Etymology

The term "cold ironing" derives from the era, when vessels powered by -fired boilers would shut down their s upon arriving in , allowing the iron engine components to cool while receiving external utilities such as , water, and electricity from shore facilities. This process, often phrased as placing the ship "on cold iron," minimized onboard fuel use and boiler maintenance during berthing periods, a common practice by the late 19th and early 20th centuries when dominated global shipping fleets. The reflects the literal cooling of machinery—contrasting with the "hot iron" state of active operation—and has persisted into modern usage despite the shift to and alternative systems. Early adoption of shore-side power connections, independent of the term's nautical phrasing, traces to naval applications aimed at preserving ship equipment rather than emissions control; for instance, U.S. Navy vessels utilized such systems post-World War II to extend engine life and conserve during extended stays. These origins underscore cold ironing's roots in , predating its contemporary role in reduction.

Early Modern Adoption

The practice of cold ironing evolved from naval applications in the early to mid-20th century, where electrical connections were established to support docked warships without relying on onboard generators. The pioneered routine use of at its bases worldwide, primarily to reduce mechanical wear on shipboard equipment, conserve fuel, and facilitate maintenance during prolonged port visits. This approach allowed vessels to secure their systems—effectively "cold ironing" the engines—while powering lighting, , and other auxiliaries from grid-supplied . By the post-World War II era, infrastructure had become standard at major naval facilities, with ships employing standardized cable-and-plug systems compatible across ports. For instance, during and after the war, converted vessels like turbo-electric destroyer escorts demonstrated the feasibility of interfacing ship electrical systems with shore supplies, though initial implementations focused on rather than emissions reduction. Naval adoption emphasized reliability and cost savings, with connections rated for the high loads of warships, often exceeding 1 MW per vessel. Early commercial trials lagged behind naval precedents, with limited experiments in the late confined to specific regions like , where cruise operators began connecting select vessels to around 2001 to comply with local air quality mandates. However, these were not widespread until regulatory pressures intensified in the , marking a transition from military utility to broader maritime application. Naval systems, by contrast, had already proven scalable, informing later standards like those from the .

Expansion in the 21st Century

![IEC/ISO/IEEE 80005-1 plugs ready to be attached to a ship in the Port of Oslo][float-right] The expansion of cold ironing in the 21st century began with pioneering installations in major ports during the early 2000s, driven by air quality concerns in densely populated coastal areas. The Port of Los Angeles opened the world's first container terminal equipped with shore power infrastructure at Berth 100 in June 2004, enabling vessels to connect to high-voltage shore electricity. Earlier, in January 2000, the first high-voltage shore connection for a commercial vessel was established in Europe, marking the initial shift toward standardized onshore power systems. These developments coincided with feasibility studies, such as California's 2006 assessment identifying 18 ports for potential cold ironing deployment to curb emissions from docked ships. Regulatory mandates accelerated adoption, particularly in regions with stringent environmental policies. California's Air Resources Board introduced the At-Berth Regulation in 2007, requiring ocean-going container vessels to use or equivalent controls during berthing, with full compliance phased in by 2014 for 50% of a carrier's fleet calling at regulated ports. In the , Directive 2014/94/EU mandated that ports provide onshore infrastructure for seagoing ships by December 31, 2025, aiming to reduce auxiliary engine emissions across the bloc. The has supported these efforts through guidelines on energy efficiency, though lacking binding global requirements, leaving expansion reliant on national and regional incentives. Technical standardization further facilitated growth with the publication of IEC/ISO/IEEE 80005-1 in 2012, establishing uniform requirements for high-voltage shore connections to ensure compatibility between ships and ports worldwide. From approximately 12 ports equipped between 2000 and 2010, the number rose to over 25 by 2017, reflecting incremental infrastructure investments. By 2025, despite commitments from numerous large ports to deploy by 2028, adoption remains limited, with fewer than 20% of the world's over 2,000 ports offering standardized facilities, constrained by high upfront costs and inconsistent vessel compatibility. The global shore power market, valued at around USD 2 billion in 2025, is projected to double by 2032, signaling potential for broader implementation amid decarbonization pressures.

Technical Process

Connection and Operation

Cold ironing connection requires specialized high-voltage shore connection (HVSC) systems compliant with the IEC/IEEE 80005-1 standard, which specifies protocols for linking ships to supplies typically at 6.6 kV or 11 kV to match large vessel requirements. Shore-side infrastructure includes transformers to step down grid voltage and frequency converters if needed to align with the ship's electrical system, often 50 Hz or 60 Hz depending on the vessel's origin. Ship-side preparations involve positioning the vessel at a berth equipped with shore power outlets, where flexible high-voltage cables—color-coded for phase identification—are extended from the ship's deck-mounted to the shore terminal. Prior to physical connection, compatibility checks verify voltage levels (e.g., around 440 V initial sync before transfer), frequency, phase rotation, and grounding to prevent mismatches that could . Cables are then plugged into receptacles on both ends, with interlocks and communication links—often via fiber optics or power line carrier ()—ensuring no live energization until confirmation signals are exchanged between ship and shore systems. stop tests are conducted to validate rapid disconnection capabilities. Operation commences with synchronization of the ship's electrical bus to the shore supply, either automatically via the alternative marine power () or manually using a synchroscope and three-bulb method to align voltage, frequency, and phase. Once synchronized, the shore connection (VCB) is closed after shore-side permission, allowing gradual offloading of the ship's auxiliary generators—maintained at minimum load initially—before opening their breakers to fully transfer the hotel load (e.g., , HVAC, ) to . Continuous monitoring of power parameters, fault detection, and automatic disconnection sequences ensure safe operation, with the system designed to handle loads up to several megawatts per vessel. Upon departure, the process reverses: generators are restarted, loads transferred back, and cables disconnected and reeled in.

Power Requirements and Infrastructure

![IEC/ISO/IEEE 80005-1 plugs for cold ironing connection][float-right] Power requirements for cold ironing vary significantly by vessel type and size, as ships must sustain onboard systems such as , heating, , , , and cargo handling without running auxiliary engines. Container ships typically demand 1 to 4 megawatts (MW), with examples citing up to 4,000 kilowatts (kW) per hour for large vessels during port stays. Cruise ships and ferries require higher loads, often exceeding 5 MW and reaching 10-20 MW for larger passenger vessels to power extensive hotel services. Smaller vessels or those with lower auxiliary needs may require only hundreds of kilowatts, while liquid bulk carriers can necessitate multiple high-voltage feeds. The IEC/IEEE 80005-1 standard governs high-voltage shore connections (HVSC), specifying systems for voltages above 1 to supply ships efficiently from shore grids. It supports typical configurations like 6.6 at 60 Hz, common for vessels built to standards, though frequency converters are often needed for 50 Hz grids to prevent equipment damage. Power delivery occurs via specialized plugs, sockets, and cables rated for high amperage, with safety protocols including interlocks and grounding to mitigate risks like mismatches. Shore-side infrastructure comprises substations equipped with transformers to match ship voltage and , high-capacity for protection, and robust cabling systems—often liquid-cooled for loads over 1 MW—to bridge the berth. panels and boxes ensure synchronized transfer, while cable reels manage the physical linkage, typically spanning 50-100 meters from the substation. Ports must integrate these with the local grid, sometimes requiring dedicated feeders to handle peak demands without straining utility networks, as seen in installations using multiple 6.6 cables for high- vessels. existing berths involves significant to comply with standards, ensuring compatibility and reliability.

Standardization and Compatibility

The IEC/IEEE 80005 series establishes the primary international standards for high-voltage shore connection (HVSC) systems in cold ironing, with IEC/IEEE 80005-1 specifying requirements for power interfaces, safety protocols, and operational procedures to facilitate between ships and ports. This standard, developed jointly by the (IEC), (ISO), and Institute of Electrical and Electronics Engineers (IEEE), addresses connection systems for vessels requiring up to 20 MW, including ships and liners, by defining standardized plugs, cables, and systems. Compliance with IEC/IEEE 80005 enables any equipped ship to connect to any compliant shore facility, promoting global consistency in infrastructure. Despite these standards, compatibility challenges arise from discrepancies in electrical parameters between shipboard systems and shore grids. Ships typically operate on 60 Hz systems with voltages such as 6.6 or 11 , while many shore grids use 50 Hz, necessitating frequency converters or transformers that add and cost. In regions like , early cold ironing implementations adopted 6.6 /60 Hz configurations predating full harmonization, leading to retrofitting needs for vessels interfacing with or Asian ports standardized differently. Varying connector designs and power quality requirements further complicate plug-and-play operations, as non-standardized legacy setups in smaller ports hinder seamless integration. Ongoing efforts focus on broader adoption of IEC/IEEE 80005 to mitigate these issues, including guidelines from societies and authorities for synchronized voltage, , and matching during connections. Technical hurdles like electric shock risks and protocols are explicitly covered in the standards' annexes, yet incomplete global implementation—particularly in developing s—persists as a barrier to compatibility. Peer-reviewed analyses emphasize that while the standards provide a robust framework, regional variations in grid require case-specific adaptations, such as hybrid converters, to achieve reliable shore-to-ship transfer.

Implementation and Adoption

Global Port Deployments

Shore power facilities have been established in approximately 68 ports worldwide as of 2022, encompassing high-voltage systems for various vessel types including , ferries, and container vessels, though adoption remains limited relative to global port numbers. By October 2024, the International Chamber of Shipping estimated that only 3% of global ports provided such capabilities, reflecting slow uptake outside regulated regions despite ongoing expansions. For operations specifically, 33 ports offered as of August 2025, supported by 24 funded projects and 18 planned installations, according to the Cruise Lines International Association. In , deployments originated in U.S. West Coast ports under California's at-berth emission regulations, with the initiating cold ironing for ships in 2004 and expanding to container terminals by 2014. The achieved 70% utilization for calls at Pier 66 in 2023, while the Northwest Seaport Alliance completed installation at Tacoma's Husky Terminal in June 2025 to serve container ships. Canadian ports including , , and also feature operational systems, often used by and traffic. European adoption has accelerated under EU directives mandating infrastructure in major ports by 2025, with in pioneering high-voltage for ships as early as the mid-2000s. Recent completions include Germany's Port of in September 2025, enabling simultaneous supply to up to seven vessels with green electricity, and expansions in with dual plants per quay. and ports such as Copenhagen-Malmö, , , , Antwerp-Bruges, and now provide facilities, primarily for passenger and container vessels, with further containership rollouts planned by 2030 in , , Bremerhaven, and . In , infrastructure lags behind but includes operational systems at South Korea's and China's , where all container terminal berths are equipped, alongside trials in . Ferry-dominant ports in , such as those using IEC/ISO/IEEE 80005-1 standardized plugs, demonstrate practical deployment for short-sea routes.
RegionNotable PortsVessel Types SupportedKey Deployment Year
North America, , Cruise, , 2004–2025
Europe, , , Antwerp-BrugesPassenger, , Mid-2000s–2025
Asia, , , 2010s–present

Shipboard Adaptations

Shipboard adaptations for cold ironing entail installing specialized electrical infrastructure to enable safe reception and utilization of shore-supplied power, allowing vessels to deactivate auxiliary generators during stays. These modifications integrate high-voltage shore (HVSC) systems compliant with standards such as IEC/IEEE 80005-1, which specify requirements for voltages up to 11 kV and frequencies matching the ship's typical 60 Hz system. Core components include shore connection and receiving switchboards equipped with breakers rated for short-circuit currents, transformers for voltage matching, and converters where shore power differs (e.g., 50 Hz in versus ship's 60 Hz). Cable management systems, comprising reels or handling mechanisms for high-voltage flexible cables, facilitate secure connection and disconnection, often positioned in non-hazardous, access-controlled areas. Power receptacles and sockets, designed per IEC 62613 series, provide the points, with equipotential bonding and interlocks ensuring grounding compatibility and preventing hazardous paralleling with onboard generators. Safety adaptations feature protection relays against overloads and short-circuits, emergency shutdown circuits triggered by faults like loss of bonding or , and integration with the ship's alarm management systems. Fire-resistant enclosures and compliance with classification society rules for machinery spaces are mandatory for installations. Low-voltage systems (under 1 kV) serve smaller vessels but demand similar switchboards and plugs per IEC 60309-5. Retrofitting established ships involves altering main switchboards, adding change-over panels, and modifying power distribution, often requiring dry-docking for weeks and incurring costs from $268,500 to $2.1 million for containerships, influenced by factors like switchboard proximity and voltage levels. New constructions permit seamless incorporation, reducing expenses and downtime compared to retrofits.

Case Studies of Major Ports

The Port of Los Angeles pioneered cold ironing through its Alternative Maritime Power (AMP) program, initiating infrastructure development in the early 2000s to enable container ships and other vessels to connect to shore-side electricity rather than running auxiliary diesel engines. By 2010, the port had equipped multiple terminals with AMP capabilities, achieving widespread adoption among carriers; as of 2024, compliance with California's at-berth shore power requirements exceeded 95%, significantly curbing diesel particulate matter, nitrogen oxides, and greenhouse gas emissions from idling ships. The program has expanded to include refrigerated cargo and auto carriers, with terminal operators investing in vessel-side modifications to meet mandates effective by 2027. In the Port of Gothenburg, Sweden, the world's first high-voltage shore power system for ships was operationalized in 2000 at the Älvsborg RoRo terminal, supplying electricity to ferries and roll-on/roll-off vessels to displace auxiliary engine use. The port has since extended cold ironing to tanker berths, unveiling a specialized concept in 2023 as the first globally for such vessels, while offering free electricity as an incentive to boost uptake; a 2025 pilot integrated hydrogen generators for supplementary power, aiming to further decarbonize operations amid EU emission directives. These efforts have reduced local air pollutants, with the port reporting consistent use by Stena Line ferries since early adoption. The Port of Oslo, , advanced through a policy-driven transition starting in the , culminating in a full-scale system test in February 2022 that successfully loaded vessels with shore electricity compliant with IEC/IEEE 80005-1 standards. This infrastructure supports the port's zero-emission ambitions, enabling battery-electric cruise ships and to charge while integrating with urban grids for electric buses; emissions measurements indicate substantial cuts in CO2, , and from ocean-going vessels at berth, driven by municipal mandates and incentives like those in the 2016 electric strategy. The complemented California's regulatory framework by investing over $185 million in dockside hookups since the mid-2000s, facilitating for container, cruise, and tanker traffic with high compliance rates under the 2020 At Berth Regulation. This has yielded measurable emission reductions, aligning with statewide goals to minimize health-impacting pollutants from berthed ships.

Benefits

Environmental Reductions

Cold ironing substantially mitigates from ships at berth by replacing onboard auxiliary engines with shore-supplied , eliminating direct stack emissions of criteria pollutants during hotelling periods that often account for 65-98% of a vessel's total emissions depending on ship type and dwell time. This shift primarily curbs nitrogen oxides (NOx), sulfur oxides (SOx), and (PM), which arise from combusting high-sulfur bunker fuels in inefficient engines, while (CO2) reductions hinge on the shore grid's carbon intensity relative to marine . Local air quality benefits accrue regardless of grid composition, as emissions are displaced from densely populated vicinities to potentially remote power plants with advanced controls. Quantified assessments in European ports, using 2023 vessel tracking data from major hubs like and , project 97% reductions in , 96% in , 94% in , and 95% in volatile organic compounds (VOCs) under full cold ironing adoption, assuming average ship power demands of 7-11 MW for and vessels. CO2 emissions could decline by 53%, based on the EU-25 electricity mix's emission factors (e.g., 0.35 g/kWh for ). In U.S. contexts, such as ports under at-berth regulations, yields over 99% cuts in and from auxiliary engines, alongside 96-98% for , with empirical ship-side data showing 97.7% , 96.7% , 92.1% , and 38% CO2 reductions compared to operation. These reductions enhance port-adjacent by lowering exposure to respiratory irritants like and , which contribute to and premature mortality, though net CO2 benefits diminish in coal-reliant grids where may exceed ship diesel's intensity—necessitating renewable integration for maximal mitigation. Empirical port studies confirm near-total elimination (up to 100%) of hotelling-phase emissions for all pollutants when vessels comply, underscoring cold ironing's efficacy for localized improvements but limited by partial adoption and grid decarbonization pace.

Operational and Economic Gains

Cold ironing enables vessels to draw electrical power from shore infrastructure, allowing auxiliary engines to remain idle during berthing. This curtailment of engine runtime substantially diminishes mechanical degradation, extending component lifespan and reducing maintenance expenditures for ship operators. By supplanting onboard fuel with grid-supplied , cold ironing yields direct savings on marine fuels, which constitute a major variable cost in port operations. In the , implementation has been shown to cut auxiliary fuel use by 80-90% per berthing event. At the , cruise operators achieve up to 26% financial savings per port call through avoided fuel and related expenses. Cost-effectiveness models affirm that these gains—primarily from lower procurement and upkeep—can amortize ship-side adaptations within 5-7 years, provided electricity tariffs remain competitive against fuel equivalents. Such outcomes hold particularly under medium-to-high price regimes, as evidenced in route-specific assessments for Ro-Ro vessels.

Criticisms and Challenges

High Capital and Infrastructure Costs

Implementing cold ironing requires substantial upfront investments in port infrastructure, including high-voltage substations, frequency converters, transformers, control systems, and specialized cabling to deliver power safely to vessels. These installations can cost millions to tens of millions of dollars per berth for container ships, depending on power demand and grid integration complexity. For instance, the has invested over $185 million in dockside power hookups and related infrastructure as of 2014 to support widespread shore power use. A study on medium-sized ports estimated total capital costs at approximately £6.6 million (€7.4 million), highlighting the scale needed even for smaller facilities. Vessel-side adaptations add further expense, as ships must be retrofitted with onboard transformers, switchboards, systems, and compatible connectors to interface with shore supplies, often requiring dry-dock time. Retrofit costs typically range from €400,000 to €1.5 million per vessel, varying by ship size, age, and electrical system modifications. Newbuild vessels can incorporate these features at lower relative cost, but the majority of the global fleet requires upgrades, exacerbating the financial burden on shipping operators. These high capital outlays create economic hurdles, as costs must be apportioned among authorities, operators, utilities, and shipping lines, with periods extending to 7 years without subsidies or 3.5 years with partial funding like the TEN-T program's 20% support. Limited and infrequent port calls for many vessels further diminish , contributing to slow adoption despite environmental mandates.

Reliability and Technical Hurdles

A primary technical hurdle in cold ironing systems arises from electrical incompatibilities between shipboard and shore power supplies, particularly differences in and voltage. Ship electrical systems commonly operate at 60 Hz and voltages around 440-690 V, while many shore grids use 50 Hz and higher voltages such as 6.6 kV or 11 kV, necessitating frequency converters and transformers that add complexity and potential points of failure. These mismatches require precise of and voltage to prevent equipment damage during connection, with power quality issues like harmonics further complicating integration. Standardization efforts, such as the IEC/ISO/IEEE 80005-1 for high-voltage shore , aim to address but face uneven global adoption, leading to variations in connectors and protocols that hinder seamless implementation. Low-voltage systems lack equivalent uniformity, exacerbating challenges for , where space constraints and high costs—often requiring specialized —limit feasibility, particularly for older ships or tankers with dependencies. Mechanical aspects, including the handling of heavy, high-power cables via reels or manual attachment, are vulnerable to environmental factors like , , and movements, which can disrupt or cause wear. Reliability concerns stem from dependence on shore grid stability, where local outages or interruptions—such as those at the , allowable with 30 minutes' notice during peak demand—can leave ships without power, potentially requiring fallback to auxiliary engines. The single-point nature of connections introduces risks of total system failure without redundancy, compounded by from stray AC and DC currents between ship hulls and piers, which can degrade by up to 10% in tensile strength after prolonged exposure. Mitigation strategies, including active compensation for stray currents and impressed current , are essential but increase operational complexity and maintenance demands.

Limited Scope and Unintended Consequences

Cold ironing addresses only a fraction of a 's total emissions, as it applies exclusively during berthing periods, which typically constitute less than 10% of a ship's operational time for many vessel types, leaving the majority of emissions from at-sea activities unaffected. For instance, ships in ports like spend approximately 8-10 hours per call docked, limiting the technology's impact to short intervals amid longer voyages. Globally, remains constrained, with available at only about 3% of ports as of 2024, primarily concentrated in regions like , , and coastal , while most and carriers operate without compatible . This scarcity perpetuates a "chicken-and-egg" , where shipping lines hesitate to retrofit vessels—requiring investments in the millions per ship—absent widespread port availability, and ports delay infrastructure development without sufficient equipped vessels calling. Unintended consequences arise from the displacement of emissions to onshore electricity generation, where net reductions depend heavily on the carbon intensity of local grids; in regions reliant on fossil fuels like , shifting power demand can result in comparable or higher outputs than onboard generators, potentially negating local air quality benefits. High-voltage systems for large vessels often exceed the capacity of existing grids, necessitating costly upgrades that strain public utilities and may indirectly increase electricity costs for surrounding communities. Additionally, the focus on berthing overlooks broader emissions, as unelectrified segments—such as inland transport or non-equipped ports—may see compensatory increases in activity, diluting overall decarbonization efforts without complementary measures like or alternative . These factors underscore that cold ironing's efficacy varies by locale, with empirical assessments required to verify benefits beyond idealized low-carbon grid scenarios.

Regulatory Framework

Key International and Regional Mandates

Internationally, the (IMO) has developed non-binding guidelines rather than enforceable mandates for onshore power supply (OPS), also termed cold ironing or alternative maritime power. In June 2023, the IMO issued MSC.1/Circ.1675, providing interim guidelines on the safe operation of OPS systems, covering aspects such as electrical compatibility, safety protocols, and emergency procedures to standardize connections between ships and shore grids. These guidelines, stemming from work by the Sub-Committee on Ship Systems and Equipment, aim to facilitate voluntary adoption but do not impose usage requirements, reflecting the absence of global compulsion amid varying national infrastructures. In the , binding regional mandates under the FuelEU Maritime Regulation (Regulation (EU) 2023/1805) require ships and ships exceeding 5,000 to connect to —or deploy equivalent zero-emission technologies—during calls at Trans-European Transport Network (TEN-T) ports where such infrastructure is available, effective from January 1, 2030, with phased intensification thereafter to curb intensity. Complementing this, the Alternative Fuels Infrastructure Regulation (AFIR, Regulation (EU) 2023/1804) mandates that all TEN-T ports provide capability for and ships by 2030, targeting 90% uptake in relevant calls to align with decarbonization goals under the . Some EU ports, such as , have accelerated implementation, requiring shore power use for capable cruise ships from 2027, preceding broader EU timelines. In , the Air Resources Board (CARB) enforces the At-Berth Ocean-Going Vessels Regulation, mandating that ocean-going commercial vessels at major ports like , Long Beach, Oakland, and reduce auxiliary engine emissions by at least 80% via or approved alternatives during berthing exceeding specified hours; compliance phases include container ships since 2014, passenger ships since 2010, and tankers from January 1, 2027. This state-level rule, upheld despite industry challenges, prioritizes local air quality in high-traffic areas and influences voluntary programs elsewhere in the U.S., such as , though federal mandates remain absent.

Incentives and Enforcement Mechanisms

Incentives for adopting cold ironing primarily involve financial mechanisms to offset infrastructure and retrofit costs, including government subsidies, grants, and reduced port charges. In , the (CARB) administers incentive funding programs to support deployment at ports, helping to cover electrification expenses despite high upfront investments. In , ports offer targeted reductions in docking fees and tariffs for vessels using onshore ; for instance, the Port of provides harbor dues discounts alongside grants of up to 1 million (approximately €90,000 as of 2021 exchange rates) for Ro-Pax vessel retrofits to enable cold ironing compatibility. These measures, often coupled with tax exemptions on shore-supplied , aim to improve economic viability, though their effectiveness depends on local grid capacity and vessel participation rates. Enforcement relies on regional mandates with compliance monitoring and escalating penalties, rather than uniform international standards. California's 2020 At-Berth Regulation requires ocean-going such as container ships, refrigerated cargo carriers, and passenger to achieve at least 80% emissions reductions during berthing periods exceeding two hours by using , exhaust capture systems, or approved alternatives, applicable at major like and Long Beach since January 1, 2023, with expansions to tankers by 2027. CARB enforces through reporting, port inspections, and third-party , imposing civil penalties up to $37,500 per violation per day under California Health and Safety Code Section 43016; notable cases include a $680,750 settlement with in 2023 for multiple non-compliance instances and a $630,625 fine against in 2018 for over 2,500 violations. In the , the FuelEU Maritime Regulation (EU 2023/1805), effective from January 1, 2025, mandates that container ships and passenger vessels over 400 gross tons use onshore or equivalent zero-emission technologies while berthed or moored in core (TEN-T) ports for more than two hours, starting January 1, 2030, where such infrastructure is available. Non-compliance triggers penalties calculated as €2,400 per ton of excess intensity beyond mandated reductions, applied annually to shipping companies based on pooled fleet performance, with the overseeing enforcement via member state authorities and potential audits. The (IMO) issues interim guidelines on safe onshore power operations (MSC.1/Circ.1675, adopted 2023) to standardize procedures but lacks binding enforcement powers, deferring to flag states and ports for implementation. These mechanisms prioritize emissions accountability, though challenges persist in verifying availability and equivalence of alternatives.

Future Prospects

Technological Innovations

The IEC/IEEE 80005-1 standard, initially published in 2007 and revised in 2012 and 2019, establishes protocols for high-voltage shore connection (HVSC) systems operating at 1 to 15 kV AC, enabling electrical power transfer up to 12 MVA or higher from shore to ships while ensuring safety through interlocks, grounding, and protection relays. This standardization addresses compatibility issues between diverse ship electrical systems and port grids, facilitating broader adoption by specifying cable reels, plugs, and control interfaces. HVSC innovations reduce the need for bulky low-voltage cabling by transmitting power at higher voltages, minimizing transmission losses and infrastructure demands for large vessels like cruise ships and container carriers requiring 5-10 MW. Developments include enhanced short-circuit management and device protection, with classification societies such as ABS issuing guides in recent years for shipboard design and operation to mitigate risks like arcing or insulation failure. Frequency converters represent a critical advancement, installed onshore or onboard to reconcile discrepancies between shore grid frequencies (typically 50 Hz in ) and ship systems (often 60 Hz), incorporating step-down transformers, rectifiers, inverters, and filters for seamless . Recent modular designs improve and , supporting up to 44 MVA in integrated onshore systems. Power electronics innovations enable integration with port microgrids incorporating sources, such as and , alongside storage for stable, low-carbon supply during berthing. These systems employ advanced control for voltage and frequency matching, reducing reliance on fossil-fuel backups and aligning with decarbonization goals, though challenges persist in handling variable renewable inputs.

Market Growth and Barriers

The global shore power market, encompassing cold ironing infrastructure and equipment, was valued at approximately USD 1.5 billion in 2022 and is projected to grow to USD 2.4 billion by 2032, reflecting a (CAGR) of 11.9% driven by regulatory pressures and emission reduction mandates. Alternative estimates place the market at USD 2.49 billion in , expanding to USD 5.04 billion by 2032, with onshore installations comprising a significant segment expected to reach USD 1.6 billion by 2030 at a 5.6% CAGR. Adoption has accelerated in specific sectors, such as shipping, where over 210 vessels—representing 72% of Cruise Lines International Association (CLIA) member ships—will be shore power-compatible by 2028. In container shipping, uptake has surged dramatically in recent years, supported by compliance with regulations like California's At-Berth Regulation, which achieved over 95% adherence in 2024. However, global port availability remains limited, with only about 35 ports—less than 3% of worldwide facilities—offering shore power connections as of 2023. Despite growth potential, high pose a primary barrier, with implementation expenses for cold ironing systems often ranging from USD 2 million to USD 6 million or more per berth, depending on scale and location. These upfront investments, split between ports, shipowners, and utilities, deter widespread adoption, particularly in smaller or developing ports lacking financial incentives or public funding. Technical challenges, including non-standardized electrical systems (e.g., varying voltages and frequencies across regions), complicate and require costly retrofits for vessels and . Regulatory fragmentation further hinders progress, as inconsistent mandates and enforcement—such as the absence of uniform EU-wide requirements—limit , while the division of costs among stakeholders often leads to delays or abandonment of projects. Economic analyses indicate that without subsidies or penalties, the payback period for can exceed a decade in low-utilization scenarios, exacerbating reluctance among operators prioritizing short-term viability over long-term environmental benefits.

References

  1. [1]
    Cold Ironing Ports - Everything You Want To Know - Marine Insight
    Sep 5, 2023 · Cold ironing is a term in the shipping industry that came into vogue when all the vessels had coal-fired engines. Once a ship was at port, there ...
  2. [2]
    Coldironing: On-shore Power Supply for Vessels
    Cold ironing means a ship at berth uses shore power for auxiliary engines instead of bunker fuel, reducing emissions when stationary.
  3. [3]
    Cold ironing - Wärtsilä
    Connecting ships to the onshore power supply and shutt down the gensets in order to decrease exhaust emissions and noise.
  4. [4]
    Shore Power, Cold Ironing or Shore Side Electricity - Tratos Group
    The process is called cold ironing because, back in the old days when the ship's mainframe engines used to be rested, they used to get cold while the power was ...
  5. [5]
    Two-stage energy management framework of the cold ironing ...
    Jul 1, 2024 · The result shows significant improvement in emission reduction where the CO2, NOX, SO2, and PM have been reduced to 38.44 %, 97.7 %, 96.69 %, ...
  6. [6]
    Emphasizing the importance of using cold-ironing technology by ...
    Jun 7, 2022 · Studies have shown that cold-ironing technology is extremely effective in reducing emissions that contribute to air pollution and climate change ...
  7. [7]
    [PDF] Prospects of cold ironing as an emissions reduction option - DTU Orbit
    This technological solution can eliminate the emissions of auxiliary engines at berth, resulting in a global reduction of emissions if the grid powering the ...
  8. [8]
    Research on Drivers and Barriers to the Implementation of Cold ...
    Jul 24, 2024 · Cold ironing is frequently viewed as one method for cleaner and more ecologically friendly marine transport. This is one of the techniques to ...
  9. [9]
    Identifying the unique challenges of installing cold ironing at small ...
    Challenges result from several small berths needing individual OPS units, long cables and cable reel storage, as well as the need for several vessels to install ...
  10. [10]
    ISO/IEC/IEEE 80005-1:2012(en), Utility connections in port — Part 1
    This part of IEC 80005 describes high voltage shore connection (HVSC) systems, on board the ship and on shore, to supply the ship with electrical power from ...
  11. [11]
    A Comprehensive Exploration of IEC/IEEE 80005-1 Standards and ...
    In 2012, IEEE, IEC, and ISO jointly issued the High Voltage Shore Connection (HVSC) standard called IEC/ISO/IEEE 80005-1 to ensure the reliability of vessel ...
  12. [12]
    IEC/IEEE 80005 - Tratos Group
    IEC/IEEE 80005 describes high-voltage shore connection (HVSC) systems, onboard the ship and on shore, to supply the ship with electrical power from shore.
  13. [13]
    COLD IRONING. - languagehat.com
    Aug 14, 2009 · That's the beauty part: “Cold ironing is a shipping industry term that first came into use when all ships had coal fired iron clad engines.
  14. [14]
    Cold Ironing: The role of ports in reducing shipping emissions
    Mar 18, 2019 · Cold ironing is the way that ports can contribute to reducing shipping's emissions. By simply turning off their engines and plugging in to an electrical supply ...
  15. [15]
    Cold Ironing - The Islander Magazine
    The technology is called 'cold ironing' or 'cooling the irons'. The origin of the name comes from when ships were propelled with steam engines and boilers.Missing: etymology | Show results with:etymology
  16. [16]
    Cold ironing - power system grounding and safety analysis
    Aug 7, 2025 · ... The etymology of cold ironing rose from the era when coal-fired engines would stop burning while the ship was tied to the port, and the iron ...
  17. [17]
    Cold ironing: An approach to ship’s power whose time has come
    Apr 10, 2008 · The Navy originally instituted shore power not to cut pollution, but to reduce wear and tear on ship equipment. It also saves fuel.Missing: history | Show results with:history
  18. [18]
    [PDF] DRAFT USE OF SHORE-SIDE POWER FOR OCEAN-GOING ...
    May 1, 2007 · The U.S. Naval ships have been using shore-power at their bases worldwide for several decades. Naval ships are also connected to water, sewer,.
  19. [19]
    [PDF] ship to shore power: us navy humanitarian relief?
    History. During World War II, there were seven destroyer escorts converted into Turbo-Electric. Generators (TEG) specifically for the purpose of providing ...
  20. [20]
    Shore Power Technology Assessment at U.S. Ports - EPA
    In addition to the deployment of shore power technology in the commercial sector, shore power has been successfully used by the U.S. Navy for decades and is ...Missing: first | Show results with:first
  21. [21]
    [PDF] standardisation of ship and shore-based power supply (cold ironing)
    The Navy, which traditionally spends a long time at sea followed by long periods in port, has used shore power for decades at ports.
  22. [22]
    Standardization of Utility Connections in Ports - Nxtbook Media
    A standard for monitoring and control communication was issued in 2016 as 80005-2. About Standardization of Utility Connections Within IEC, IEEE, and ISO and ...
  23. [23]
    Alternative Maritime Power (AMP) | Air Quality - Port of Los Angeles
    ... cold ironing, or High Voltage Shore Connection (HVSC) Systems ... On June 21, 2004, the Port of Los Angeles announced the opening of the West Basin Container ...Missing: date | Show results with:date
  24. [24]
    [PDF] Cold ironing = hot topic - World Port Sustainability Program
    The first ship was connected to the new high-voltage supply in January 2000 and it has become a major success. There have been hardly any problems and key ...
  25. [25]
    [PDF] Cold Ironing Report - World Port Sustainability Program
    Mar 6, 2006 · The Navy uses a pigtail-and-plug cable-connection system to ensure shore power can be used at ports worldwide. In order for cold-ironing to be ...
  26. [26]
    A maritime first: APL 'cold-irons' ships in Oakland to clear the air
    May 27, 2011 · The state of California has mandated cold-ironing for container ships by 2014. At that time, half of a carrier's fleet must rely on shore power ...Missing: Los Angeles date
  27. [27]
    CARB Emissions Regulations for at-berth Vessels—everything You ...
    Jun 14, 2024 · CARB first introduced at-berth regulations in 2007 and has since progressively implemented stricter rules, which will continue to expand through ...<|separator|>
  28. [28]
    Specific environmental charges to boost Cold Ironing use in the ...
    Through Directive 2014/94/EU, European Union (EU) has required European ports to provide facilities to enable Cold Ironing (CI) use by 2025.
  29. [29]
    [PDF] An Action Plan for Maritime Energy and Emissions Innovation
    Dec 1, 2024 · maneuvering speeds, at berth (cold ironing), or with auxiliary loads ... seeking compliance with IMO regulations such as the Energy ...<|separator|>
  30. [30]
    ISO/IEC/IEEE 80005-1:2012 - Utility connections in port — Part 1
    IEC/ISO/IEEE 80005-1:2012(E) describes high voltage shore connection (HVSC) systems, on board the ship and on shore, to supply the ship with electrical power ...
  31. [31]
    Port energy demand model for implementing onshore power supply ...
    Between 2000 and 2010, only 12 ports implemented OPS (WPCI (World Ports ... Identifying the unique challenges of installing cold ironing at small and medium ports ...
  32. [32]
    Development, features and prospects of application of AMP / cold ...
    Aug 6, 2025 · shipowner. As of 2017, the AMP technology has already been used in more than twenty-five ports whose list is ; presented in Table 1, and in 2020 ...
  33. [33]
    SHORE POWER CONNECTION- COLD IRONING - DieselShip
    Sep 19, 2025 · Many of the world's largest ports have signed declarations committing to deploy shore-side electricity by 2028 where possible. Below is a list ...Missing: century history
  34. [34]
    Cold Ironing Made Simple: 2025 Update - Ship Universe
    Jul 24, 2025 · Gaps Still Exist: While growing fast, less than 20% of global ports offer standardized cold ironing. Compatibility and voltage-frequency ...
  35. [35]
    Shore Power Market Size and YoY Growth Rate, 2025-2032
    Sep 8, 2025 · The global shore power market is estimated to be valued at USD 2.13 Bn in 2025 and is expected to reach USD 4.86 Bn by 2032, exhibiting a ...Missing: 2000-2025 | Show results with:2000-2025
  36. [36]
    IEEE/IEC 80005-1-2019
    Mar 18, 2019 · This part of IEC/IEEE 80005 describes high-voltage shore connection (HVSC) systems, onboard the ship and on shore, to supply the ship with electrical power ...Working Group Details · Other Activities From This... · Iec/ieee Draft International...
  37. [37]
    What is Alternate Marine Power (AMP) or Cold Ironing?
    Mar 23, 2021 · Alternate marine power or cold ironing is a method of providing power to the ship from an external source. AMP is getting recognition around ...<|separator|>
  38. [38]
    Ship to shore power: 5 exciting reasons why it's time to invest
    Apr 25, 2024 · Cold ironing is the process of using shoreside electrical power – or shore power – for the hotel load of a ship in port, meaning it can keep ...
  39. [39]
    SHORE POWER CONNECTION- COLD IRONING
    No readable text found in the HTML.<|separator|>
  40. [40]
    [PDF] March 29, 2023 Hon. Steven S. Cliff Executive Officer California Air ...
    Mar 29, 2023 · For “cold ironing” purposes, the IEC/IEEE 80005-1 standard, identifies the electrical service voltage per vessel type. For tanker vessels that ...<|separator|>
  41. [41]
  42. [42]
    Electrification of onshore power systems in maritime transportation ...
    Cold ironing is a remarkable electrification innovation in the maritime industry for ship transportation, in which diesel engines driving ship generators ...
  43. [43]
    [PDF] Shore Power Technology Assessment at US Ports 2022 Update
    Dec 16, 2022 · Cold ironing cost effectiveness study: Volume I report. Los Angeles, 2004. 7. Yorke Engineering. Port of San Diego: Cold ironing study. Prepared ...
  44. [44]
    Only 3% of Global Ports Equipped for Shore Power - Ship & Bunker
    Oct 30, 2024 · The International Chamber of Shipping (ICS) this week reported that just 3% of global ports currently offer shore power facilities for ships.
  45. [45]
    Plugging Cruise Ships Into Shore Power Is No Small Feat
    Aug 15, 2025 · The Cruise Lines International Association reports 33 ports worldwide now have shore power, with 24 funded projects and 18 more planned. The ...
  46. [46]
    Cruise Ship Shore Power Facts | Port of Seattle
    In 2023, 70% of calls at Pier 66 were equipped with shore power. Once complete, shore power at Pier 66 is expected eliminate an estimated additional 3,000 ...Missing: worldwide | Show results with:worldwide
  47. [47]
    The Northwest Seaport Alliance Announces Completion of Shore ...
    Jun 17, 2025 · The Northwest Seaport Alliance (NWSA) is excited to announce the completion of shore power at Husky Terminal in Tacoma.Missing: worldwide | Show results with:worldwide<|separator|>
  48. [48]
    [PDF] Shore Power-FY2023 - Carnival Corporation
    Our ships have connected to shore power in: Southampton, UK;. Hamburg, Kiel and Rostock in Germany; Vancouver, Halifax and. Montreal in Canada; Seattle, ...
  49. [49]
    PORT OF KIEL finalises shore power infrastructure as one of the first ...
    Sep 9, 2025 · The Port of Kiel has completed its shore power infrastructure and can now supply up to seven vessels at the same time with green ...
  50. [50]
    New shore power plants and sustainable initiatives in N. Europe
    In 2025, they will also offer shore power at the Filipstad Pier for vessels up to 340 m. In Stockholm, they have installed two shore power plants on each quay ...Missing: worldwide | Show results with:worldwide
  51. [51]
    European and North American Ports Preparing for Cold Ironing
    Dec 10, 2020 · The Ports of Stockholm, together with the Baltic Sea ports of Copenhagen/Malmö, Aarhus, and Helsinki, will all invest in providing onshore power ...Missing: list | Show results with:list
  52. [52]
    [PDF] SHORE CONNECTION SYSTEMS ON SHIPS REVISION 1 - IR Class
    Jul 1, 2025 · 1.2 These Guidelines are applicable to vessels equipped with a High Voltage Shore Connection System (HVSCS) or a Low Voltage Shore Connection ...
  53. [53]
    [PDF] High Voltage Shore Connection Systems for Ships 2020 - IR Class
    1 Cable Management System: the cable management system comprises all equipment designed to control, monitor and handle the HV-flexible and control cables and ...
  54. [54]
    [PDF] Guide for High Voltage Shore Connection 2011
    The shore connection switchboard is provided with a shore power connecting circuit breaker with circuit protection devices. Onboard Receiving Switchboard: The ...
  55. [55]
    [PDF] High Voltage Shore Power Installations on U.S. Flag Ships
    May 6, 2011 · b) The vessel should have a shore power operations manual that defines each step and requires a sign off verification of the connection, power ...
  56. [56]
    Shore Power vs. Capture Control for Ship Emissions Reduction
    Aug 16, 2024 · Ships equipped for shore power can connect to a land-based electrical power source, allowing them to shut down their auxiliary engines while ...
  57. [57]
    Shore power deployment strategies and policies including ...
    This work provides real-world results on an existing shipping network, and delivers policy recommendations and pathways toward shore power deployment.
  58. [58]
    2024 Shore Power Enforcement - California Air Resources Board
    Apr 18, 2025 · The updated emissions control requirements of the 2020 At Berth Regulation began in 2023 for container, cruise, and refrigerated cargo vessels.
  59. [59]
    PORT OF LOS ANGELES READY TO MEET CALIFORNIA'S SHORE ...
    The Port of Los Angeles is fully ready for its terminal operators and ocean carriers to meet California's new clean air requirements.
  60. [60]
    Onshore Power Supply. - Port of Gothenburg
    ... Cold Ironing. Shoreside connections in the Port of Gothenburg. The RoRo terminal at the Älvsborg Harbour is the first onshore power supply to be established ...
  61. [61]
    Port of Gothenburg unveils 'world first' cold ironing concept for tankers
    The Port of Gothenburg is aiming to become the first port in the world to provide shoreside power for tankers. The Swedish port authority says it has ...
  62. [62]
    Cold ironing in Gothenburg's Energy Port - Baltic Transport Journal
    Apr 7, 2025 · The Swedish seaport became the third in the world and the second in the Baltic to enable tankers to draw electricity from the shore.
  63. [63]
    Stena Line cold irons in home port - Riviera Maritime Media
    ABB delivered the world's first shore-to-ship power supply system to the Port of Gothenburg in 2000. The port received a Clean Marine Award for environmental ...
  64. [64]
    Successful full-test load on new shore power system took place at ...
    Feb 22, 2022 · Shore power company Blueday Technology has announced the successful full-test load on a new shore power system at the Port of Oslo.Missing: case study
  65. [65]
    Policy and politics in energy transitions. A case study on shore ...
    This paper dives into one such transition process and investigates the role of policy and politics in the transition to shore power in the Port of Oslo, Norway.
  66. [66]
    [PDF] port of oslo as a zero-emission port - KlimaOslo
    On 28 September 2016, case 260, Oslo City Council adopted a ten-point strategy for the use of electric ferries in the Oslofjord and arrangement of shore power.<|separator|>
  67. [67]
    Shore Power - Port of Long Beach
    Using electrical power for ships at berth rather than diesel-burning engines, a practice called shore power or “cold ironing,” greatly reduces air pollution ...
  68. [68]
    Reduction Potential of Gaseous Emissions in European Ports Using ...
    Aug 5, 2024 · This study identifies and assesses ship and port emissions and analyzes the potential for emission reduction achievable by cold ironing in European ports.
  69. [69]
    California port shore power regulation for different years.
    From the shipside, emissions reductions of 38.44 % for CO 2 , 97.7 % for NO X , 96.69 % for SO 2 , and 92.1 % for PM were achieved. From the shoreside, the ...
  70. [70]
    [PDF] Air Pollution and Greenhouse Gas Emissions from Ocean-going Ships:
    Pollutants such as NOx, SOx, and PM have been linked to a vari- ety of adverse public health outcomes, including increased risk of premature death ...
  71. [71]
    Cold-Ironing as a Cost-Effective Tool for Improving Sustainability in ...
    The results demonstrated that cold-ironing could deliver substantial savings, dependent on the relative magnitudes of fuel and electricity prices. Overall, ...
  72. [72]
    Shore Power | The Northwest Seaport Alliance
    All together, these infrastructure elements are expensive, costing from millions to tens of millions of dollars to install shore power at a container ship ...
  73. [73]
    [PDF] Examining the Commercial Viability of Cold Ironing
    • Shore-to-ship • Cold ironing • Alternative Maritime Power (AMP) • ... Cost to retrofit the vessel. 400 000 €. Number of ships. 1. Total investment ...
  74. [74]
    Shore Power Retrofits: The Key to Sustainable Shipping and ...
    Sep 27, 2024 · The cost of retrofitting, which can range from €800,000 to €1.5 million, depends on factors like the ship's age, route, and remaining active ...
  75. [75]
    Ditching Diesel in Seaports in Favor of Electrification - IEEE Spectrum
    Aug 24, 2024 · The technical challenges include matching the ship's voltage and frequency with that of the local grid, which, in general, varies globally, ...
  76. [76]
    Cold Ironing Galvanic Corrosion Issues with Regard to a Shore-to ...
    This paper presents the numerical simulation results of a medium voltage cold-ironing system with regard to the currents flowing between the ship's hull and ...
  77. [77]
    Questions about Cruise Ship Emissions at Berth | Port of Seattle
    Jul 12, 2021 · ... ships only spend 8-10 hours at a Port of Seattle berth, during which they disembark passengers, load supplies, and embark new passengers ...
  78. [78]
    The race for shore power | International Chamber of Shipping
    Oct 29, 2024 · Shore power will play an increasing role in maritime energy transformation. However, despite its potential, adoption has been sluggish.
  79. [79]
    [PDF] MSC.1/Circ.1675 27 June 2023 INTERIM GUIDELINES ON SAFE ...
    Jun 27, 2023 · 1. Onshore power supply (OPS) system is the equipment that supplies onshore power to ships berthing in port, including ship-side installations ...
  80. [80]
    Safe operation of on-shore power supply to ships
    Mar 2, 2020 · Draft guidelines on safe operation of on-shore power supply to ships are set to be finalized by the Sub-Committee on Ship Systems and Equipment (SSE).
  81. [81]
    FuelEU Maritime's Onshore Power Supply Requirements - ZeroNorth
    Oct 28, 2024 · From 2030, container ships above 5,000 gross tonnage and passenger ships must connect to OPS or use an equivalent zero-emission technology when ...
  82. [82]
    Shore power electricity demand in EU ports from 2030 onwards
    May 17, 2025 · AFIR mandates that by 2030, 90% of all port calls by container and passenger ships at TEN-T ports must use shore-side electricity.
  83. [83]
    Hamburg Mandates Shore Power for Cruise Ships by 2027
    Oct 4, 2025 · Hamburg will require all shore power-capable cruise ships to use onshore electricity at its terminals starting in 2027, ahead of EU regulations.Missing: directives | Show results with:directives
  84. [84]
    The Regulatory Landscape for Maritime Emissions
    Aug 22, 2025 · The 2020 At-Berth regulation requires ocean-going vessels docked at California's busiest ports to plug into shore power or use emissions control ...
  85. [85]
    California: cold ironing for tankers in 2027 - Riviera Maritime Media
    California already has some of the strictest regulations on tanker activities, including the release of fumes, and introducing cold ironing will be a challenge.
  86. [86]
    Shoreside Electricity Capability - CLIA Europe
    Ships can connect directly to power sources on shore. It allows ship engines to be switched off, reducing emissions by up to 98%, depending on the mix of ...
  87. [87]
    [PDF] At Berth Frequently Asked Questions - California Air Resources Board
    Sep 26, 2024 · CARB follows its Enforcement Penalty Policy to resolve violations of any CARB regulation.7. CARB's Enforcement Division will conduct an ...
  88. [88]
    CARB Fines Shipping Company for Violation of Ocean-Going ...
    The California Air Resources Board reached a settlement agreement with Wan Hai Lines for $680,750 for violations of the Ocean-Going Vessels At-Berth Regulation.
  89. [89]
    MSC penalized for 2500+ air quality violations in California
    Dec 5, 2018 · MSC Mediterranean Shipping Company S.A. has been forced to pay a penalty of $630,625 for violating California's Ocean-Going Vessel At-Berth ...
  90. [90]
    Decarbonising maritime transport – FuelEU Maritime
    To reduce air pollution in ports, passenger and container ships at berth or moored at the quayside must use on-shore power supply (OPS) or alternative zero- ...
  91. [91]
    [PDF] Shore power needs and CO emissions reductions of ships in ...
    Oct 1, 2023 · This study explores the role of shore power in decarbonizing maritime transportation in the European Union (EU) based on two recently ...
  92. [92]
  93. [93]
    ABS Releases Guide for Design & Operation of High Voltage Shore ...
    ABS has released a Guide for High Voltage Shore Connection to address key safety concerns as well as design considerations for shipboard installations.<|separator|>
  94. [94]
    High-Voltage Shore Connection Systems: Powering Sustainable Ports
    A high-voltage shore connection system enables large vessels, like container ships or cruise liners, to draw power from the shore grid. This replaces the need ...
  95. [95]
    OPS Solution - ONSHORE POWER SUPPLY / COLD IRONING
    These are the systems known as OPS (Onshore Power Supply) or Cold Ironing, in naval terminology. It encompasses modular solutions, ranging from 1 MVA to 44 MVA ...Missing: advancements | Show results with:advancements
  96. [96]
    Shore-to-ship: Enabling the electrification sustainability of maritime ...
    Jun 15, 2024 · This study demonstrates the synergy between S2S and RES in the IES to address challenges of the wider electrification of berthed ships at ports.
  97. [97]
    Shore Power Market Projected to Reach USD 2.4 Billion, at a
    Jun 22, 2023 · The market size will be reaching around USD 2.4 Billion by the end of the year 2032. Shore power, also known as cold ironing or alternative ...
  98. [98]
    Shore Power Market Size, Trends YoY Growth Rate 2025-2032
    Shore Power Market holds a forecasted revenue of USD 2.49 Bn in 2025 and is likely to cross USD 5.04 Bn by 2032 with a steady annual growth rate of 10.60%
  99. [99]
    Shore power surge in container ship sector - Riviera Maritime Media
    Apr 8, 2025 · Why the shore power adoption rate has increased 'dramatically' in the box ship sector – and what more needs to be done.
  100. [100]
    Onshore Power Supply (OPS) - Cruise Lines International Association
    Today, only 35 cruise ports—comprising less than 3% of the world's cruise ports—currently offer onshore power (with at least one berth for cruise ships). The ...
  101. [101]
    Research on Drivers and Barriers to the Implementation of Cold ...
    The findings indicate that economic incentives and regulation have a positive impact on the adoption of cold ironing at ports.
  102. [102]
    Key factors and barriers to the adoption of cold ironing in europe
    The present paper investigates the innovative process of cold ironing at European level. Firstly, its recent development in Europe is documented as well as the ...Missing: controversies challenges
  103. [103]
    Policy implementation barriers and economic analysis of shore ...
    This paper takes China as an example to explore the barriers to SP policy implementation by conducting in-depth interviews and builds cost-benefit models.