The Forties Pipeline System (FPS) is a comprehensive integrated network for the transportation and processing of crude oil and liquids from the central , fully owned and operated by . Spanning more than 500 miles of subsea and onshore pipelines, it connects nearly 80 offshore fields in and waters to key processing facilities at Kinneil Terminal and in . With a nominal capacity exceeding 600,000 barrels of oil per day, the system has historically handled approximately 40% of the United Kingdom's production, delivering processed products including the benchmark Forties Blend crude. Established as a cornerstone of North Sea energy infrastructure, the FPS was officially commissioned on 3 November 1975 by Queen Elizabeth II, marking a transformative era for energy following the discovery of the in 1969. Initially developed and operated by , the system enabled the rapid commercialization of multiple fields, transporting over 9.6 billion barrels of oil and gas liquids across its first five decades of operation. In 2017, acquired the FPS from for an undisclosed sum, assuming full control of its assets including the Kinneil processing plant and associated terminals. Since then, has committed £500 million to modernization efforts, such as pipeline upgrades and integrity management, aimed at extending the system's viability into the 2040s. Operationally, the FPS gathers production from connected fields via a web of subsea , including the 36-inch main from the Forties Unity platform to , followed by a to Kinneil, where crude is separated, stabilized, and blended into Forties crude—a medium crude oil with around 41°. The blended crude is then shipped from the Hound Point near , while natural gas liquids are fractionated at for distribution as , , and . Designated as Critical National Infrastructure by the government, the system supports domestic , , and energy exports, contributing significantly to the through taxes exceeding £500 billion over its lifetime. Despite declining flows due to maturing fields—down 40% from 2017 to 2023, with further reductions to approximately 150,000 barrels per day by mid-2025—the FPS remains vital for ongoing production and innovation in offshore energy transport.

Overview

Description and Purpose

The (FPS) is a major integrated oil and gas liquid transportation and processing network in the . It is 100% owned and operated by . The system has a nominal capacity exceeding 600,000 barrels per day and plays a central role in handling a significant portion of oil production, equivalent to approximately 30% based on current flows of around 200,000 to 250,000 barrels per day as of 2024. The primary purpose of the is to transport crude oil and gas liquids from fields to onshore and facilities, enabling the delivery of stabilized products such as the Forties Blend crude oil. This function has supported by facilitating domestic production and reducing reliance on imports since the . The system contributes to fueling homes, transportation, and industries across the , while providing essential feedstocks for manufacturing sectors like plastics and chemicals. The FPS achieves its objectives through an integrated design that combines subsea pipelines, offshore platforms, and onshore infrastructure for comprehensive end-to-end handling of hydrocarbons. This interconnected setup ensures efficient gathering, stabilization, and export of oil and gas liquids from multiple production sources, including contributions from both UK and Norwegian fields.

Route and Key Components

The Forties Pipeline System (FPS) originates from numerous and gas fields in the UK and Norwegian sectors of the Central , where production is gathered through an extensive network of subsea pipelines that converge at the Forties Unity Platform (), an unmanned riser platform located in Block 21/9 approximately 177 km (110 miles) east of , . The FUP serves as the central gathering and export hub, receiving hydrocarbons via six incoming subsea lines from connected fields and facilitating the integration of flows from over 80 production assets, including notable tie-ins from the Forties, Brent, and other nearby fields. From the FUP, crude and associated gas liquids are transported eastward through the primary 36-inch diameter submarine export pipeline, known as the FPS Sealine, which spans approximately 169 km (105 miles) to the landfall point at on the coast. Upon reaching Cruden Bay Terminal, the hydrocarbons transition to the onshore segment of the system, comprising a 36-inch diameter buried , referred to as the FPS Landline, which extends roughly 209 km southward to the Kinneil Oil Terminal near on the . At Kinneil, the system integrates with additional , including pumping stations that manage and , before distributing processed crude —blended as Forties crude—to downstream destinations such as the via a dedicated line or the Hound Point Marine Terminal for export. liquids are separated at Kinneil and routed to for fractionation into , , and . Key infrastructure elements extend the system's reach, encompassing subsea tie-ins and interconnections with adjacent networks, such as the Brent Pipeline System, which enables efficient aggregation from a broad cluster of fields spanning more than 500 miles (800 km) in total pipeline length across the entire network. The , remotely operated from Kinneil, includes facilities for maintenance and supports multiple subsea umbilicals for control and monitoring, while onshore terminals like feature reception and metering stations to handle incoming flows. This layout underscores the 's role as a vital conduit, linking production hubs to Scotland's and export capabilities.

History

Discovery and Development

The was discovered in October 1970 by British Petroleum (BP) when exploratory well 21/10-1 encountered oil in sands at a depth of approximately 7,000 feet, marking it as one of the largest discoveries in the UK sector of the to date. Located about 110 miles east of in water depths of 300-430 feet, the field spans a broad anticlinal structure covering roughly 35 square miles with an oil column of 509 feet. Initial estimates pegged recoverable reserves at around 1.8 billion barrels from a total of 4.4 billion barrels, underscoring its potential to transform the UK's energy landscape. In the early , initiated detailed development planning following an appraisal program of five wells between and , opting for a of fixed platforms to exploit the rather than relying solely on subsea completions at that stage. The plan centered on a main processing platform (Forties 'A') linked to three wellhead platforms, enabling and from over 100 wells while incorporating peripheral injection to maintain pressure in the . Given the field's projected peak output of approximately 500,000 barrels per day, determined that a dedicated to shore was essential to handle the substantial volumes, avoiding reliance on tanker loading which would be inefficient for such scale. BP formally announced its £160 million development program on December 16, 1971, with UK government approval granted the same month, clearing the way for engineering and procurement activities. This timing proved fortuitous amid the , as the Forties project accelerated the 's push toward self-sufficiency, reducing dependence on imported crude and bolstering national during a period of global supply disruptions and price surges.

Construction and Commissioning

The construction of the Forties pipeline system commenced in 1974, following the discovery of the four years earlier, with efforts focused on rapidly developing infrastructure to capitalize on the UK's emerging resources. The project involved the fabrication and installation of four production platforms (, and ), the laying of a 32-inch-diameter subsea spanning approximately 170 kilometers from the field to the Kinneil terminal near , and the establishment of onshore connections including a landfall at . These works were completed in under two years, driven by the urgency of the 1970s global oil crisis and advancements in engineering that enabled accelerated timelines. Key milestones during construction included the fabrication of platform jackets and topsides at Scottish yards such as Nigg Bay and , with the Forties Charlie platform's jacket completed in August 1974 and subsequent installations progressing through 1975. The subsea was installed using specialized vessels in water depths of around 100 , followed by hydrotesting and commissioning phases in mid-1975 to verify integrity and flow capabilities. The total project cost reached approximately £750 million, more than double the initial £360 million estimate, due to technical challenges in the harsh environment. Commissioning began with first oil from in September 1975, marking the initial flow through the platforms at a rate of about 10,000 barrels per day. The first oil reached the onshore terminal via the on November 3, 1975, coinciding with the official at BP's Dyce control center near , where Queen Elizabeth II pressed a ceremonial button to inaugurate operations in the presence of officials. Throughput ramped up steadily thereafter, achieving peak design capacity of around 500,000 barrels per day by 1976 as additional wells came online and system efficiencies were optimized.

Technical Specifications

Pipeline Network

The Forties Pipeline System's main is constructed from 36-inch , extending 169 km subsea from the Forties Charlie platform via the Forties Unity platform to the landfall. The features corrosion-resistant coatings applied during to mitigate degradation in the marine environment, complemented by ongoing integrity management practices. The network configuration incorporates feeder lines from connected fields and facilities, including 20-inch lines associated with and gas lift operations linking to the Unity platform, as well as smaller diameter spurs such as 12-inch lines from gas processing sites like St. Fergus. stations are strategically positioned at the Forties platform, Unity platform, and to enable regular maintenance, cleaning, and inspection runs using intelligent pigs for internal assessment. The system is engineered to accommodate , transporting a of crude oil, liquids, , and associated gases from multiple fields. Safety features integrated during the original construction include via sacrificial anodes to prevent external corrosion on the subsea sections, with regular surveys to monitor anode depletion and effectiveness. Leak detection is supported through operational protocols, including pressure monitoring and intelligent pigging inspections to identify potential integrity issues.

Processing and Storage Facilities

The Forties Unity Platform (FUP), located in the North Sea, functions as a central offshore gathering hub for the Forties Pipeline System, receiving crude oil and associated gas from multiple incoming pipelines. It includes modules for initial processing, such as separation to isolate oil and gas streams, metering to measure flow rates, and compression to maintain pipeline pressure, before combining the fluids for export via the main 36-inch subsea pipeline to shore. As a not permanently attended installation, the platform is operated remotely from onshore control centers. Onshore processing primarily occurs at the Kinneil Terminal near , , where unstabilized crude oil arriving via the undergoes key treatments including to remove , desalting to eliminate salts and impurities, and further separation of oil, gas, and condensates. The terminal operates three processing trains with a capacity to handle up to 775,000 barrels per day of unstabilized crude and approximately 6,700 tonnes per day of raw gas, producing stabilized products through and . Gas outputs, including dry gas, , and , are directed to the adjacent Complex for feedstock or LPG export, while heavier condensates (C5+) are shipped via Grangemouth Docks; the stabilized oil connects directly to the for final refining. Storage facilities support the system's operations at multiple points, with tanks at providing initial onshore buffering for hydrocarbons received from the subsea , complemented by booster compression to sustain flow. The Kinneil Terminal incorporates elements integral to its processing workflow, while the primary bulk occurs at the Dalmeny terminal near , featuring six floating-roof tanks with a total capacity of about 3 million barrels for the blended crude. Blending capabilities at Kinneil enable the creation of the standardized Forties crude blend by mixing inputs from various fields to meet quality specifications before distribution to or .

Ownership and Operations

Ownership History

The Forties Pipeline System () was constructed and initially owned entirely by British Petroleum (), which operated it from its commissioning in 1975 to transport crude oil from the in the UK to onshore processing facilities. As production from the Forties field declined and additional fields connected to the system, maintained 100% ownership of the , which became a critical artery for approximately 30-40% of the UK's offshore oil output. sold its interests in the Forties field itself to Apache Corporation in 2003, but retained full control of the pipeline infrastructure to support broader regional production. In 2016, explored options to divest a minority stake in the amid efforts to streamline its portfolio, engaging in discussions with potential buyers, but ultimately pursued a full . On April 3, 2017, announced the agreement to sell the entire , including associated onshore pipelines and the Kinneil Terminal, to FPS Limited—a subsidiary of the chemicals company —for up to $250 million, comprising $125 million in cash at closing and potential contingent payments tied to future throughput volumes. The transaction was completed on October 31, 2017, transferring 100% ownership to , which committed to investing in the system's maintenance and upgrades to ensure continued reliability for producers. Since then, has held sole ownership, with no further changes reported as of 2025, solidifying its role as a key independent operator of oil infrastructure.

Current Operations and Maintenance

INEOS FPS Ltd, a wholly owned subsidiary of , manages the day-to-day operations of the Forties Pipeline System, providing 24/7 remote monitoring and control primarily from the Kinneil Terminal in . The operational structure involves approximately 460 personnel distributed across onshore facilities at Kinneil, Dalmeny, and , as well as offshore support roles, ensuring continuous oversight of hydrocarbon transportation from over 80 fields. Since the 2017 acquisition, has invested more than £500 million in maintenance and upgrades to extend the system's operational life into the 2040s. Maintenance practices emphasize routine assessments and preventive measures to sustain system reliability. Key activities include regular visits to not permanently attended installations like the Platform for operational checks, alongside periodic intensive campaigns using walk-to-work vessels to address equipment such as emergency shutdown valves and import systems. Inline inspections are conducted to detect potential issues, with pig reception facilities at key points like supporting pipeline cleaning and anomaly identification. Annual inspections cover the entire network, focusing on structural , while control involves ongoing monitoring and strategies to prevent in the subsea and landline segments. All activities comply with () regulations, including the Offshore Activities ( Pollution Prevention and Control) Regulations, targeting zero environmental incidents and non-compliances. Current challenges in operations and maintenance center on the system's aging , which requires vigilant management to avoid disruptions like those from hairline cracks identified in past inspections. Integration with declining production from connected fields adds complexity, necessitating adaptive flow management and efficiency optimizations to maintain throughput amid reduced inputs. , conducted daily, weekly, and monthly, tracks emissions and discharges to ensure minimal impact, with recent data showing reductions in flaring and CO2 emissions through targeted upkeep.

Capacity and Throughput

Design Capacity

The Forties Pipeline System was originally designed in the mid-1970s with a nominal capacity exceeding 600,000 barrels per day (b/d) of crude oil and natural gas liquids (NGLs) from the Forties field and associated installations to onshore terminals. This capacity supported the field's peak production, utilizing a primary 36-inch diameter spanning approximately 169 kilometers from the to . Historical sources indicate the system's nominal capacity reached over 1 million b/d with the integration of NGLs from connected fields, allowing for multiphase handling including stabilized crude and NGLs. Connections to additional fields broadened the system's intake network over time. The design capacity is defined by hydraulic factors, including drops across the length—managed at key points—and maximum flow rates determined by the pipe's , viscosity, and operational limits. These parameters ensure stable transport while preventing issues like or , with the operational limit around 600,000 b/d as of 2025 following optimizations.

Historical and Current Throughput

The Forties pipeline system reached peak throughput in the late 1970s and 1980s, approaching its nominal capacity of over 600,000 b/d, reflecting rapid development of connected fields. Over its operational history, the system has handled more than 9.6 billion barrels of oil and gas liquids by 2025. Throughput has declined since the 1980s peak due to field depletion. In 2021, volumes dropped 21% year-over-year amid maintenance and reduced output. The average daily throughput was approximately 216,000 b/d in 2024, projected to reach 224,000 b/d by year-end. As of 2025, the Forties pipeline system transports approximately 35-40% of the United Kingdom's production (around 200,000 b/d based on total UK output of ~530,000 b/d), underscoring its ongoing importance despite field depletion challenges.

Upgrades and Future Plans

Major Upgrades

Since acquiring the Forties Pipeline System in 2017, has committed over £500 million to a comprehensive program aimed at modernizing and ensuring long-term viability. As of 2025, has invested more than £500 million in these upgrades. This investment encompasses system-wide enhancements to maintain operational integrity and support ongoing production. A of these efforts was the £75 million integrity project completed in June 2021 during a three-week shutdown, which focused on critical repairs including internal applications and reinforcements to bolster durability against and structural wear. Between 2019 and 2021, additional key initiatives involved subsea tie-ins that connected new fields to the network, incorporating advanced oil-handling systems for more efficient processing and reduced operational disruptions. These upgrades were executed amid challenges like delays, prioritizing safety and minimal environmental impact during implementation. Environmental retrofits formed a significant component of the program, with investments in improved monitoring systems and preparations for low-emission gas compressors designed to cut annual CO2 equivalent emissions by up to 100,000 tonnes once fully operational. These measures align with INEOS's broader goals, including a 45% reduction in overall emissions since acquisition. The upgrades have collectively extended the system's operational life into the 2040s, enhanced protocols to prevent leaks and failures, and improved throughput efficiency, thereby sustaining hundreds of jobs in Scotland's energy sector.

Long-term Outlook

INEOS has committed significant investments to extend the operational life of the Forties Pipeline System () beyond 2040, including a £500 million reconfiguration program initiated in 2018 that enhances through inhibition and regular lifetime reviews. This strategy supports continued production into the 2040s and potentially further, aligning with 's broader goals at connected facilities like , where net-zero operations are targeted by 2045. However, recent UK government policies on energy taxes and net-zero targets, as criticized by in 2025, may accelerate decommissioning and limit new investments. Decommissioning of the FPS will occur after the cessation of economic operations, potentially extending to the 2050s, though recent policy changes pose risks of earlier decommissioning around 2040 or sooner, with costs shared proportionally among historical and future throughput volumes to ensure equitable burden distribution. While the OSPAR Convention governs the full removal of offshore installations in the North-East Atlantic, pipelines like the FPS fall under UK national regulations via the Petroleum Act 1998, requiring operators to submit detailed decommissioning programs that prioritize and clearance. The FPS faces challenges from the accelerating decline in North Sea oil production, which fell to 34 million tonnes in 2023—its lowest since the —and further to 28 million tonnes in 2024, alongside the UK's target by 2050, potentially limiting new upstream investments. However, opportunities exist for repurposing the infrastructure in the , such as integrating with (CCS) projects like 's involvement in the initiative, which aims to store up to 1 million tonnes of CO2 annually by 2027 using existing networks, with the project scaling to 5-10 million tonnes by 2030, or adapting for transport to support low-carbon fuels.

Economic and Environmental Impact

Economic Significance

The Forties Pipeline System was instrumental in bolstering the United Kingdom's oil self-sufficiency during the 1970s and 1980s, as it enabled the efficient transport of crude from early North Sea discoveries, including the flagship Forties field that began production in 1975. This infrastructure supported a surge in domestic output that peaked in the early 1980s, reducing reliance on imported oil amid global energy crises and contributing to economic stability through enhanced energy security. Over its 50-year history, the system has transported more than 9.6 billion barrels of oil, underpinning the North Sea sector's generation of approximately £500 billion in tax revenues for the UK Treasury. Forties crude, a light sweet grade, serves as a core component in the Dated Brent benchmark, with pricing differentials like the Brent-Forties spread influencing global oil markets and export values. In its contemporary role, the pipeline sustains hundreds of direct jobs, with around 500 personnel involved in its operations and maintenance, while indirectly supporting thousands more in the across and the . It historically fed the , which had a processing capacity of 150,000 barrels per day and integrated the pipeline's output into production before halting crude in April 2025. To ensure longevity, invested £500 million in upgrades since 2017, modernizing pipelines and terminals to extend service into the 2040s and stimulating local economic activity through construction and technology enhancements. However, in September 2024, INEOS warned that proposed government tax increases on the oil and gas sector could force the early closure of the FPS as soon as 2030, potentially leading to the loss of direct and indirect jobs, reduced export revenues, and threats to energy security. Beyond direct operations, the Forties Pipeline System has facilitated the development of over 80 offshore fields, creating a interconnected value chain that amplifies the North Sea's role as a hub for oil extraction, processing, and export. By linking these assets to onshore facilities, it has driven billions in export revenues, with Forties blend crude shipped to international markets and contributing to the position as a net oil exporter. This network effect has cemented the system's status as a cornerstone of the energy economics, fostering industrial clusters and sustained fiscal benefits.

Environmental Considerations

The Forties Pipeline System has experienced limited environmental incidents since its inception, with one notable example being a minor leak discovered in December 2017 at a landfall section in , , where a hairline crack allowed a few drops of oil to seep per minute without causing or broader ecological harm. Operational emissions have shown a positive trajectory, with Scope 1 CO₂ emissions reduced by 46.5% from a 2019 baseline, flaring decreased by 63%, and effluent discharges to the cut by 78.2% as of 2023, through targeted measures. These reductions reflect a broader trend of minimizing air, water, and land emissions since 2018, as reported in annual environmental statements. Since acquiring the system in 2017, INEOS has invested over £500 million in upgrades that include environmental enhancements, such as infrastructure improvements to prevent pollution and optimize resource use, integrated into an Environmental Management System (EMS) that sets targets for zero offsite incidents and permit compliance. This EMS aligns with UK regulations, including the Offshore Petroleum Activities (Oil Pollution Prevention and Control) Regulations 2005 and Offshore Chemicals Regulations 2002, ensuring discharges remain below limits like 40 mg oil per liter and reporting any incidents via the Environmental Emissions Monitoring System (EEMS). Biodiversity monitoring around the pipeline route forms part of routine environmental assessments under the EMS, focusing on minimizing habitat disruption along the onshore and offshore paths, though specific programs emphasize overall ecological impact prevention rather than targeted species tracking. Looking ahead, INEOS is aligning the Forties system with UK net-zero goals by 2050 through ongoing emissions cuts targeting 2030 and 2045 milestones, including a 2022 tender for a carbon capture-enabled hydrogen plant to repurpose infrastructure for low-carbon applications. Potential integration with carbon capture and storage (CCS) pipelines is under exploration as part of broader North Sea decarbonization efforts, which could utilize the system's network for CO₂ transport. Decommissioning plans, anticipated in the 2040s barring policy changes, incorporate environmental safeguards via the EMS to ensure safe removal, waste minimization, and habitat restoration in compliance with UK guidelines.

References

  1. [1]
    About INEOS FPS
    The Forties Pipeline System (FPS) is a 100% INEOS-owned integrated oil and gas liquid transportation and processing system with a nominal capacity of over six ...
  2. [2]
    [PDF] INEOS FORTIES PIPELINE SYSTEM (FPS) LTD. PUBLIC ... - GOV.UK
    The Forties Pipeline System (FPS) is an integrated oil and gas transportation and processing system. It is owned and operated by INEOS and utilises more.
  3. [3]
    Forties Pipeline System oil flows have declined by 40% over six years
    INEOS' Forties Pipeline System moves 40% of the UK's oil from the North Sea through Grangemouth where it is processed for distribution throughout the UK.
  4. [4]
  5. [5]
    INEOS celebrates 50 years of the Forties Pipeline System and warns ...
    Nov 4, 2025 · Officially opened by Her Majesty Queen Elizabeth II on 3 November 1975, the Forties Pipeline transformed the UK's energy landscape. It took ...
  6. [6]
    INEOS completes the acquisition of the North Sea Forties Pipeline ...
    Oct 31, 2017 · The system has a capacity of 610,000 barrels of oil a day. BP sold its interests in the Forties field to Apache in 2003 and sold its ...
  7. [7]
    £500 million in pipeline to modernise FPS - INEOS Group
    Work on The Forties Pipeline System, which can carry up to 600,000 barrels ... INEOS Oxide also plans to make a significant investment in ethylidene norbornene ( ...
  8. [8]
    Technical - INEOS Group
    Pipeline capacity is 610 mbd. A 12 inch diameter buried landline running 25 ... The Brae Pipeline System; The GAEL Pipeline System; The Everest Lomond ...
  9. [9]
    Forties System Report - Wood Mackenzie
    $$2,580.00Jul 17, 2025 · The Forties Pipeline System (FPS) is an integrated oil and gas liquid transportation and processing system with a nominal capacity of over one million b/d.
  10. [10]
    Forties Oil Pipeline System - Global Energy Monitor - GEM.wiki
    Dec 4, 2024 · Forties pipeline system (FPS) is a pre-eminent pipeline network in the North Sea carrying a substantial portion of the UK's oil, ...<|control11|><|separator|>
  11. [11]
    INEOS celebrates 50 years of the Forties Pipeline System and warns ...
    Nov 3, 2025 · At its peak, it carried around 40% of all UK oil production, providing the feedstocks for fuels, plastics, and essential materials that underpin ...
  12. [12]
    [PDF] uk energy in brief 2025 - gov.uk
    Jul 31, 2025 · ... Forties Pipeline System which serves a significant proportion of UK oil and gas production. In 2024, oil and gas production decreased by 8.8 ...
  13. [13]
    bp to sell Forties Pipeline System to INEOS | News | Home
    The FPS system primarily comprises a 169 kilometre (105 mile), 36” pipeline from the unmanned offshore Forties Unity platform to the onshore terminal at Cruden ...
  14. [14]
    North Sea Oil Fields Map: The Pipelines - Identec Solutions
    Aug 26, 2024 · This was developed in line with the Forties field. The system runs some 169 km to the Cruden Bay terminal located on the east coast of Scotland.Missing: route components -
  15. [15]
    Forties Field, North Sea1 | AAPG Bulletin - GeoScienceWorld
    Sep 21, 2019 · HISTORY OF DISCOVERY. The Forties field was discovered in October 1970, when BP's well 21/10–1 found oil in Paleocene sands at a depth of about ...Missing: details | Show results with:details
  16. [16]
    The First UK Giant Oil Field - GeoExpro
    Jul 3, 2010 · The giant Forties Field was discovered in 1970, only the second oil field to be found in the UK North Sea. Originally predicted to run dry ...Missing: details | Show results with:details
  17. [17]
    Partnering on the Forties Field - OnePetro
    Sep 7, 1993 · The Forties Oil Field was discovered in 1970, 110 miles ENE of ... Recoverable reserves were then estimated at 1.8 billion barrels.
  18. [18]
    Forties Oilfield – a timeline - Offshore Technology
    Oct 23, 2014 · ... discovered by British Petroleum (BP) in October 1970. Distinctions. Second-largest producing field in the North Sea and the first major ...Missing: 1969 | Show results with:1969
  19. [19]
    The Forties Field - 20 Years Young | Journal of Petroleum Technology
    Apr 1, 1996 · The development plan evolved during 1972-75. The first major oil field development in the North Sea, it comprised four fixed steel drilling/ ...Missing: initial | Show results with:initial
  20. [20]
    Forties at 50 | News and insights | Home - BP
    Oct 8, 2020 · The Queen famously initiated the flow of oil from the field in November 1975, commenting at the time: “What has been achieved in the North Sea ...
  21. [21]
    Britain Pushes North Sea Oil - The New York Times
    Oct 15, 1973 · The first commercial oil deposits in the North Sea were discovered by British Petroleum three years ago this month in the Forties Field.Missing: UK | Show results with:UK
  22. [22]
    Britain's energy transition in the shadow of the 1970s
    Feb 8, 2024 · North Sea oil would, it became clear, protect the UK's political economy by enabling energy self-sufficiency and trade balance stability. It ...
  23. [23]
    Long History of Forties Field North Sea‎
    Jan 2, 2016 · On 7 October 1970, BP the operator and owner of Forties field officially announced that it had found oil that was commercially viable, about 180 ...
  24. [24]
    [PDF] bp 60 YEARS IN THE NORTH SEA
    Sep 2, 2024 · First North Sea oil comes ashore: The first oil from the Forties field flows through bp's newly built Forties Pipeline. System on November 3.
  25. [25]
    North Sea oil begins to flow – archive, 1975 - The Guardian
    Nov 3, 2017 · The Forties Field, inaugurated by the Queen today, is the largest oilfield so far discovered in the British sector of the North Sea.
  26. [26]
    [PDF] Erosion-Corrosion of Carbon Steel Pipework on an Offshore Oil and ...
    Erosion-corrosion is a destructive process which can be encountered in the oil and gas industry when carbon steel pipelines transport sand particles in CO2- ...<|separator|>
  27. [27]
    Corrosion Management for Aging Pipelines—Experience From the ...
    Mar 5, 2009 · The high levels of corrosion inhibition are caused by these pipelines acting as the corrosion inhibitor feed source for the BP Forties pipeline ...Pipeline Corrosion Risk... · Multiphase Pipelines · Intelligent Pigging (in-Line...
  28. [28]
    [PDF] Forties Field Layout
    The Forties Field layout includes platforms like Unity, Bravo, Charlie, Alpha, Delta, and Echo, plus pipelines, cables, and a disused oil pipeline.
  29. [29]
    Corrosion Management For Aging Pipelines — Experience From the ...
    In 2003, Apache became the operator of the Forties Field. The field has now been in operation for 33 years and much of the infield pipeline system has ...
  30. [30]
    BP to sell Forties Pipeline System to INEOS | News and insights
    BP today announced it has agreed to sell its Forties Pipeline System (FPS) business, with assets including the main Forties offshore and onshore pipelines.
  31. [31]
    INEOS to acquire the North Sea Forties Pipeline System and Kinneil ...
    Apr 3, 2017 · The system has a capacity of 575,000 barrels of oil a day. BP sold its interests in the Forties field to Apache in 2003 and sold Grangemouth ...
  32. [32]
    BP Said to Plan Sale of Stake in Key North Sea Oil Pipeline
    May 19, 2016 · BP owns all of the Forties pipeline system, which can transport and process as many as 1 million barrels a day of oil, including liquids ...
  33. [33]
    BP confirms Forties pipeline sale to Ineos - Offshore-Energy.biz
    Apr 3, 2017 · Built, owned and operated by BP, the Forties pipeline was opened in 1975 to transport oil from the Forties field, the UK's first major offshore ...
  34. [34]
    Home | INEOS FPS
    The Forties Pipeline System (FPS) is a 100% INEOS-owned integrated oil and gas-liquid transportation and processing system.About Us · Technical · Forties Blend Quality · Contact
  35. [35]
    Ineos completes Forties Pipeline System acquisition - BBC
    Oct 31, 2017 · Ineos said it has now taken on ownership and operation of FPS, the Kinneil gas processing plant and oil terminal, the Dalmeny storage and export ...
  36. [36]
    INEOS completes the acquisition of the North Sea Forties Pipeline ...
    Oct 31, 2017 · INEOS acquired the Forties Pipeline System, Kinneil terminal, 300 personnel, and assets including the Forties Unity platform and Dalmeny ...
  37. [37]
    [PDF] ineos fps limited 2021 public statement - GOV.UK
    FPS is an integrated oil and gas transportation and processing system. It is owned and operated by INEOS and utilises more than 500 miles of pipeline to.Missing: components | Show results with:components
  38. [38]
    INEOS Forties Pipeline System
    Dec 11, 2017 · This will allow for a suitable repair method to be worked up based on the latest inspection data, while reducing the risk of injury to staff and ...
  39. [39]
    Oil Briefs - Gulf News
    Jul 23, 2019 · BP, the operator of the 800,000 barrel per day (bpd) Forties pipeline that transport oil and gas liquids from more than 25 offshore fields ...
  40. [40]
    Up and running: inside INEOS's decision to keep the Forties pipeline ...
    May 28, 2020 · The Forties pipeline system exports around 40% of the UK's oil and gas, and links up more than 80 North Sea assets. Julian Turner assesses ...
  41. [41]
    Interview: Ineos investing for North Sea Forties operations to '2040 ...
    Jun 16, 2022 · London-based Ineos is continuing its overhaul of the UK's largest crude supply route, the Forties pipeline, aiming to support North Sea ...
  42. [42]
    Forties crude output seen at 10-month high in November
    Jul 31, 2024 · Production of North Sea crude grade Forties is forecast to reach a 10-month high of almost 224000 b/d in November, up from 216000 b/d in ...Missing: average | Show results with:average
  43. [43]
    Scottish Oil and Gas Production - State of The Coast
    Forties pipeline which passes under the beach at Cruden Bay carries around 30% of UK oil production. The gas terminal at St Fergus is one of three main ...
  44. [44]
    Building Back Better – The Forties Pipeline System Upgrade 2021
    Jul 28, 2021 · Completed in June 2021, this £75m project, as part of a £500m investment in a system-wide upgrade, improves pipeline integrity, brings oil and ...Missing: construction commissioning<|control11|><|separator|>
  45. [45]
    Environmental Performance Update - INEOS Group
    Feb 18, 2022 · Since acquiring the Forties Pipeline System (FPS) in November 2017 ... INEOS FPS rolls out AI optimisation technology for lower emissions.
  46. [46]
    INEOS Marks 50 Years of Forties Pipeline, Warns UK Risks Losing ...
    Nov 3, 2025 · ... oil and gas liquids from over 80 North Sea fields, at times handling as much as 40% of total UK oil production. It remains designated as ...
  47. [47]
    Strategy - INEOS Group
    The forecast operational lifetime of the FPS pipelines is reviewed by us regularly and we expect the system to be available to at least 2040. The pipeline ...<|separator|>
  48. [48]
    Commercial - INEOS Group
    The Components of the Tariff. The tariff has been built up from 4 key components that fully reflect the cost of developing and operating the Forties System:.
  49. [49]
    Oil & Gas: decommissioning of offshore installations & pipelines
    Owners of oil and gas installations and pipelines are required to decommission their offshore infrastructure at the end of a field's economic life.
  50. [50]
    [PDF] Decommissioning of disused offshore oil and gas installations in the ...
    The dumping, and leaving wholly or partly in place, of disused offshore installations within the OSPAR. Maritime Area is prohibited under OSPAR Decision 98/3 on ...
  51. [51]
    North Sea oil decline: 'We can't have a repeat of what happened to ...
    Jul 1, 2024 · The oil and gas fields in the North Sea are in terminal decline. Last year, the oil basin produced 34m tonnes of oil, its lowest since production in the North ...Missing: Forties pipeline
  52. [52]
    [PDF] Feasibility study on repurpose of oil and gas infrastructure for ...
    Jun 30, 2021 · Existing oil and gas pipelines which may be considered as repurposing candidates for the export or storage of hydrogen product, disposal of CO2 ...
  53. [53]
    The UK North Sea: a history of oil and gas - GeoScienceWorld
    BP soon set about planning the first major oil field development in the UK, approval of which was granted in December 1971. The Forties success was one that was ...
  54. [54]
    Two Late Imperial Oil Booms: A comparison of the constrained ...
    Grangemouth is a crucial node in the Forties Pipeline System, processing both North Sea and imported crude. Workers interviewed by Gibbs and Shibe (2024) ...
  55. [55]
    Brent oil structure, physical markets reflect fears of supply glut
    Oct 20, 2025 · The price differential of North Sea Forties crude to dated Brent lost almost $1.30 per barrel last week and on Monday slipped to a 10-cent ...
  56. [56]
    Grangemouth refinery stops processing crude oil - BBC
    Apr 29, 2025 · Another 1,500 people are employed elsewhere at Grangemouth, with 500 working on the Forties pipeline, transporting 300,000 barrels of crude oil ...
  57. [57]
    Scotland's Only Oil Refinery Set to Close in 2025 | OilPrice.com
    Sep 12, 2024 · The Grangemouth refinery, Scotland's only crude processing facility, is set to close in the second quarter of 2025, its owners confirmed on Thursday.<|separator|>
  58. [58]
    INEOS to invest in Forties Pipeline System
    Feb 27, 2019 · This £500 million investment will transform the asset and extend the life of the pipeline by at least twenty years, into the 2040s. INEOS ...
  59. [59]
    [PDF] Country Analysis Brief: United Kingdom - EIA
    Jun 10, 2024 · In. 2023, the UK produced 27% of what it produced in 1999 at its production peak of 3.0 million b/d. Crude oil consumption in 2023 was 78% of ...
  60. [60]
    INEOS Marks 50 Years of Forties Pipeline, Criticizes UK Energy ...
    Nov 3, 2025 · Forties Pipeline System Overview​​ At its peak, it carried around 40% of all UK oil production, providing essential feedstocks for fuels, ...Missing: percentage | Show results with:percentage
  61. [61]
    Forties Pipeline And Nearby Terminal Disrupted After Oil Leak
    Dec 7, 2017 · The spill is not severe, with just a few drops leaking from the pipeline every minute. This is no “contamination issue” at this point due to its ...
  62. [62]
    None
    ### Summary of Forties Pipeline System Data
  63. [63]
    [PDF] emissions reduction report 2024 - Offshore Energies UK (OEUK)
    This positions the UK to achieve the North Sea Transition Deal's (NSTD) emissions reduction target of 25% by 2027, four years ahead of schedule, and the 50% ...