Apollo 5

Apollo 5 was an uncrewed mission launched on , 1968, from Launch Complex 37B at Cape Kennedy, , aboard a rocket designated AS-204, marking the first of the (LM-1) in to verify its systems and prepare for future manned lunar landings. The primary objectives of Apollo 5 focused on evaluating the performance of the Lunar Module's two main engines: the Descent Propulsion System (DPS) for simulated lunar touchdown and the Ascent Propulsion System (APS) for liftoff and abort scenarios, while also testing LM staging and guidance systems without the need for landing legs on LM-1. This mission followed the tragedy and Apollo 4's test, addressing delays in LM development due to technical challenges with the descent engine and program redesigns after the 1967 fire. During the 10-hour flight, the achieved a about 10 minutes after launch, where ground controllers from Mission Control in commanded two firings of the —first for 4 seconds, then extended to 33 and 28 seconds after an initial shutdown due to guidance computer errors—and two APS burns, including a 60-second "fire-in-the-hole" abort test and a main 445-second burn that ended early after 355 seconds from fuel depletion. Despite these anomalies, the mission demonstrated the LM's restart capability and structural integrity, with the ascent stage later separated and the descent stage deorbited to burn up on reentry after approximately 7 hours and 52 minutes of orbital operations. Apollo 5's success validated the hardware and NASA's ability to adapt to in-flight issues, eliminating the need for a second uncrewed LM test and paving the way for the manned orbital verification on in March 1969, ultimately contributing to the Apollo program's goal of landing humans on the later that year.

Mission Overview

Launch Details

Apollo 5 lifted off on January 22, 1968, at 22:48:09 UTC from Launch Complex 37B at NASA's in . The mission utilized the launch vehicle designated SA-204, marking the fourth flight of this configuration and the first to carry the Lunar Module Test Article (LTA-10R, also known as LM-1). The launch sequence proceeded nominally, with the first stage (S-IB) igniting at liftoff and burning for 2 minutes 26 seconds to propel the vehicle to an altitude of approximately 68 kilometers. Following stage separation, the second stage (S-IVB) ignited and burned for 8 minutes 36 seconds, achieving insertion into a low Earth parking orbit with parameters of 163 by 222 kilometers (101 by 138 miles) altitude and an inclination of 31.6 degrees. The S-IVB stage played a critical role in this orbit insertion phase, settling propellants via ullage motors prior to main engine start. Flight operations were directed from the in , with serving as Flight Director, overseeing the uncrewed mission's early phases without incident. Launch conditions were favorable, featuring clear skies over the and no delays beyond standard countdown procedures.

Primary Objectives

The primary objectives of Apollo 5 centered on validating the () as a critical component of the , marking its inaugural uncrewed flight to ensure readiness for subsequent crewed missions. Specifically, the mission aimed to verify key LM subsystems, including , guidance, , and structural integrity, in the space environment to confirm their performance under orbital conditions. This verification was essential to assess the LM's overall compatibility with the launch vehicle and to gather data for post-mission analysis without attempting a lunar trajectory. A core focus was the demonstration of ascent and descent stage operations, encompassing separation between the stages, attitude control maneuvers, and controlled engine firings to simulate key phases of lunar landing and ascent. The descent stage's propulsion system was to undergo planned burns at varying thrust levels, while the ascent stage would test ignition and sustainment capabilities, including restart operations to prove reliability in vacuum. These tests emphasized the LM's ability to maintain stability and execute precise maneuvers, building confidence in its design features such as the integrated guidance computer for . Particularly critical was the "fire in the hole" test, which simulated an abort scenario during the simulated lunar landing phase by immediately igniting the ascent propulsion system upon shutdown of the descent engine, evaluating and restart under high-stress conditions. The was planned to last approximately 11 hours and 10 minutes in , allowing sufficient time for these engineering evaluations. Success hinged on achieving no structural failures, accurate engine performance during burns, and comprehensive for subsystem analysis, thereby paving the way for manned LM flights.

Development and Preparation

Program Background

The Apollo program originated from President John F. Kennedy's May 25, 1961, address to Congress, in which he committed the to achieving a manned lunar landing before the end of the decade as a response to the Soviet Union's early successes in space. This ambitious goal necessitated innovative mission architectures, leading to adopt the (LOR) concept on July 11, 1962, which required a separate lightweight spacecraft—the (LM)—to ferry astronauts from to the surface and back. The LOR approach, favored over direct ascent or earth orbit rendezvous due to its efficiency in reducing launch mass, underscored the need for dedicated LM development to enable the overall lunar landing strategy. To realize the LM, NASA issued a request for proposals in July 1962, evaluating submissions from nine companies based on technical feasibility and cost. Grumman Aircraft Engineering Corporation was selected as the prime contractor on November 7, 1962, receiving a fixed-price development contract valued at approximately $375 million to design, build, and test the LM. Under Grumman's leadership, the LM was envisioned as a two-stage vehicle capable of independent flight operations, marking a pivotal step in separating the lunar lander from the command and service module for the Apollo stack. Apollo 5 emerged as a critical uncrewed test following the successful mission on November 9, 1967, which validated the launch vehicle in Earth orbit. The Apollo 1 fire on January 27, 1967, which claimed the lives of astronauts Virgil I. Grissom, Edward H. White, and , prompted significant program restructuring, including the repurposing of the AS-204 booster originally intended for that crewed flight to launch the first LM test article. Key figures overseeing this phase included George M. Low, appointed Apollo Spacecraft Program Manager in April 1967 to lead recovery efforts and ensure spacecraft safety improvements, and Major General Samuel C. Phillips, who served as Apollo Program Director from 1964, coordinating the integration of hardware across contractors. As the inaugural uncrewed LM flight, Apollo 5 held strategic importance in de-risking subsequent crewed missions, such as Apollo 8's lunar orbit test in December 1968 and Apollo 9's Earth-orbital LM demonstration in March 1969, by verifying the LM's propulsion systems and flight performance without endangering human lives. This test was essential to building confidence in the LM's reliability, allowing to accelerate toward the lunar landing objective amid tight timelines.

Delays and Modifications

The preparation of Apollo 5 faced substantial delays stemming from the fire on January 27, 1967, which necessitated widespread program adjustments to prioritize safety and testing. The Test Article (LM-1), built by Aerospace Corporation, was originally scheduled for delivery to in November 1966 but slipped due to persistent engineering challenges, arriving instead on June 23, 1967. These hurdles included welding and plumbing defects leading to propellant leaks that required extensive rework, thermal protection enhancements to address flammability risks post-fire, and difficulties integrating the guidance and navigation systems. The launch vehicle also required repurposing following the Apollo 1 tragedy. The Saturn IB designated SA-204/AS-204, intended for the crewed mission, emerged undamaged from the incident at Launch Complex 34 and was subsequently redesignated for the uncrewed LM test flight on March 20, 1967. This decision allowed to reuse the existing hardware rather than mobilizing the stored AS-206 vehicle, accelerating the overall timeline amid broader post-fire recovery efforts. Schedule pressures further intensified as compressed the Apollo timeline to meet lunar landing goals by 1969. The original target for the LM's first flight had been late 1967 using AS-206, but delays in LM-1 delivery and vehicle reassignments pushed Apollo 5 to January 1968, slipping the mission by several months while aligning it with accelerated testing of subsequent hardware. By September 1967, LM-1 was already 39 days behind the operations plan, contributing to an $81 million cost increase for fiscal years 1967-1968. Key adaptations to the and launch were implemented to suit the uncrewed orbital profile. The was removed entirely, replaced by a nine-foot aerodynamic fairing to protect the LM during ascent, given the Saturn IB's limitations. An Instrument Unit was added to the stage for autonomous control of the LM, independent of a crewed CSM. For LM-1 itself, non-essential components like landing legs and the descent stage radar were omitted to reduce weight and complexity, as no lunar landing was planned; additionally, its windows were plated over with aluminum in December 1967 following a pressurization on a similar unit. modifications addressed the earlier leaks using four-bolt flanges, though single O-rings proved problematic in later reviews. Critical pre-flight testing milestones were achieved in fall 1967 at in . After engine installation at in July, the LM-1 ascent stage underwent ground vibration tests to verify structural integrity under launch loads, followed by static firings of the ascent propulsion system to confirm engine performance. These evaluations, including flammability checks on related mockups, ensured the hardware met safety standards post-redesign and paved the way for integration with the by late 1967.

Spacecraft Configuration

Saturn IB Launch Vehicle

The Saturn IB launch vehicle designated SA-204 served as the dedicated two-stage rocket for Apollo 5, transporting the uncrewed Test Article (LM-1) into to enable propulsion system demonstrations. Originally prepared as the backup vehicle for the mission (AS-204), SA-204 remained undamaged following the January 1967 fire and was repurposed for this LM test flight after modifications to accommodate the payload adapter. The overall vehicle stood approximately 43.2 meters tall, excluding the , and relied on liquid-fueled engines for ascent. The first stage, S-IB, manufactured by Chrysler Corporation, consisted of a cylindrical tankage structure 24.5 meters long and 6.5 meters in diameter, powered by eight engines clustered in a circular pattern. These / engines delivered a combined sea-level of 7,120 (1,600,000 lbf), with the four outboard units gimbaled up to ±8 degrees for , yaw, and roll control during the initial 150 seconds of powered flight. The stage's fueled mass exceeded 448,000 kg, enabling rapid ascent to an altitude of about 59 km before separation. The second stage, , produced by , measured 21.7 meters in length and 3.05 meters in diameter, employing a single engine that generated 1,033 kN (232,000 lbf) of vacuum thrust using and . This stage burned for roughly 475 seconds to achieve orbital velocity, with a fueled of approximately 105,000 . Mounted above the S-IVB was the Instrument Unit, a 4.2-meter-diameter, unpressurized aluminum ring weighing about 2,800 , housing the Launch Vehicle Digital Computer, inertial , and systems for precise guidance, stage separation, and payload deployment. Capable of delivering up to 21,000 kg to , the configuration for Apollo 5 successfully inserted the /LM-1 stack into an initial with an apogee of 222 km and perigee of 163 km, providing the stable environment needed for the mission's objectives.

Lunar Module Test Article

The Test Article (LM-1), also designated as the first flight-ready , was constructed by Aircraft Engineering Corporation in , as the initial production vehicle following several ground-based prototypes and test articles. This uncrewed spacecraft represented a significant in the Apollo program's , optimized specifically for orbital testing of its core subsystems without the complexities of a crewed lunar mission. LM-1's design emphasized reliability in vacuum conditions, incorporating flight-qualified hardware to validate performance under spaceflight stresses. LM-1 had a launch mass of approximately 14,300 kg, configured as Test Article 1 (TA-1) with several weight-saving modifications to fit within the Saturn IB launch constraints. Unlike later crewed Lunar Modules, it lacked landing legs, a descent stage , and a fully equipped crew cabin, as these elements were unnecessary for its Earth-orbit objectives. The forward triangular windows, typically used for pilot visibility, were covered with protective aluminum plating to shield against launch vibrations and acoustic loads, ensuring structural integrity during ascent. The vehicle retained a pressurized structure with a habitable volume of about 4.5 cubic meters, but its was incomplete, prioritizing and guidance validation over . The propulsion systems of LM-1 consisted of two primary hypergolic engines using fuel and nitrogen tetroxide oxidizer for reliable ignition in space. The Descent Propulsion System (DPS) featured a throttleable delivering 44.5 of , intended to simulate lunar descent maneuvers. Complementing this was the Ascent Propulsion System (APS), a fixed-thrust producing 16.0 to demonstrate separation and ascent from the descent stage. Both systems were pressure-fed and restartable, with the (RCS) employing 16 thrusters at 0.44 each for fine attitude adjustments and translation control. Guidance and control for LM-1 relied on an (IMU) for navigation and orientation, integrated with the Abort Guidance System (AGS) as a backup for emergency maneuvers. The RCS thrusters provided precise attitude control, enabling the spacecraft to maintain stability during engine firings. These components operated under preprogrammed sequences from the onboard digital computer, allowing ground controllers to monitor and command via without real-time crew input. Structurally, LM-1 was adapted for uncrewed vacuum testing, with its two-stage assembly stowed horizontally within the atop the upper stage of the . The descent stage served as the base, housing propellant tanks and the , while the ascent stage contained the , guidance equipment, and avionics. This configuration ensured protection during launch and facilitated extraction into orbit for subsystem demonstrations.

Flight Execution

Ascent and Orbit Insertion

Following the successful liftoff of the launch vehicle at 5:48 p.m. EST on January 22, 1968, from Kennedy Space Center's Launch Complex 37B, the S-IB first stage provided initial thrust for 2 minutes and 25 seconds before separation. The second stage then ignited its J-2 engine, burning for approximately 7 minutes and 36 seconds to propel the integrated Test Article (LM-1) and into a low Earth parking orbit. A brief ullage burn from the 's auxiliary followed engine cutoff to settle propellants in the tanks, ensuring stability for subsequent operations. This sequence inserted the stack into an elliptical orbit of 163 by 222 kilometers, with an inclination of 31.63 degrees and a period of about 88 minutes. During the orbital coast phase, the mission timeline reached T+31 minutes, when pyrotechnic devices fired to jettison the protective fairing, exposing the spacecraft to space. The four panels of the Spacecraft- Adapter (SLA) then deployed outward via springs and pyrotechnics, allowing access to the . At this point, additional pyrotechnic separation charges detonated between the and , releasing the from its mounting. Spring-ejection mechanisms imparted an initial separation velocity, propelling the to a distance of approximately 30 meters from the within seconds. Post-separation, the LM's () thrusters fired in a controlled sequence to execute maneuvers, rotating the vehicle to a stable solar for optimal thermal management and zero-gravity orientation. Concurrently, ground controllers commanded the to passivate by venting residual and propellants through its relief valves, mitigating risks of structural failure or re-ignition. Real-time from both the LM and relayed data on separation velocities, angular rates, and structural integrity, confirming nominal dynamics with no significant oscillations or instabilities in the LM's free-flight configuration. This ascent and orbit insertion phase spanned from T+0 to roughly T+2 hours, encompassing powered ascent, orbital establishment, extraction, and stabilization maneuvers, thereby verifying the integrated vehicle's performance in the initial orbital environment prior to propulsion demonstrations.

Engine Tests and Anomalies

The primary in-flight experiment of Apollo 5 involved testing the Lunar Module's (DPS) engine, designed to simulate deceleration for a lunar . Approximately four hours after launch, during the fourth , ground controllers initiated the first DPS burn, planned for 39 seconds to achieve a delta-v of about 15.6 m/s—beginning at 10% for 27 seconds and ramping to full for the final 12 seconds. However, the burn terminated prematurely after only four seconds due to an in the LM's guidance computer, which failed to detect the expected velocity change within its programmed four-second window, interpreting this as an engine failure and issuing an abort signal. Mission Control rapidly diagnosed the issue as a software timing mismatch—the actual thrust response took six seconds—and devised an alternate flight plan to bypass the autonomous guidance system. Flight controllers deactivated the LM's inertial guidance and navigation computer, opting instead for direct ground commands to ignite and shut down the engine. On the same orbit, they executed a revised DPS firing: 33 seconds at 10% thrust, followed by 28 seconds at 10% thrust. These maneuvers successfully demonstrated the engine's restart capability in vacuum conditions and verified its throttle control, though the planned long-duration simulation of lunar descent (739 seconds) was skipped to prioritize ascent testing. Transitioning to the Ascent Propulsion System (APS) tests on the fifth orbit, about seven hours and 20 minutes mission elapsed time, controllers performed the critical "fire in the hole" demonstration to simulate an emergency abort during descent. This involved shutting down the DPS engine and igniting the APS just two seconds later—firing for 60 seconds at full thrust—to confirm the ascent stage could separate and propel away from the descent stage without structural damage or performance loss. The test succeeded, with the APS achieving stable ignition and shutdown as planned, validating the restart sequence essential for crew safety in manned missions. Subsequently, the stages were separated, and the APS was fired until propellant depletion, lasting 161 seconds and imparting a delta-v of approximately 38 m/s before a guidance error (stemming from unupdated software assuming the stages remained attached) caused excessive fuel consumption and uncontrolled tumbling of the ascent stage. Throughout the engine firings, monitored extensive parameters, including over 1,000 data points on flow rates, profiles, conditions in the engine nozzles, and structural integrity under firing. Analysis confirmed nominal settling via thrusters, efficient hypergolic ignition without leaks, and performance within design limits, despite the anomalies—providing crucial validation of the LM propulsion systems' reliability for subsequent flights. The descent stage, with remaining , was allowed to remain in orbit and reenter naturally, while the ascent stage was placed in an orbit that decayed on January 24, 1968.

Reentry and End of Mission

Following the completion of the primary engine tests and anomaly resolutions, the Apollo 5 mission proceeded to its final orbital adjustments to ensure safe disposal of the components. The descent stage remained in a after separation and reentered the atmosphere on February 12, 1968, disintegrating over the as planned. Subsequently, the ascent stage was separated from the descent stage via pyrotechnic devices after the APS depletion burn. The separation left the ascent stage in an elliptical orbit that decayed naturally, leading to uncontrolled reentry and burn-up over the on January 24, 1968. The Saturn IVB upper stage underwent passivation procedures, including additional venting of residual propellants and a spin-up maneuver using auxiliary thrusters to stabilize it in a "disposal orbit" and minimize explosion risks from residual pressure. This placed the S-IVB in a of about 180 by 1,900 kilometers, from which it naturally decayed and reentered over the approximately two weeks later. The overall duration was 11 hours and 10 minutes, with the final data received at T+10 hours 58 minutes on January 23, 1968, after which contact was lost as the components dispersed. As an uncrewed test flight, no recovery operations were required or conducted; the mission was officially declared a success by at the in shortly after loss of signal, confirming all objectives met despite minor anomalies. during these final phases was monitored by 's global Manned Space Flight Network, utilizing ground stations in locations such as , the , and to track orbital parameters and ensure proper stage disposal.

Results and Significance

Mission Outcomes

The Apollo 5 mission achieved its primary engineering objectives, confirming the reliable performance of the Lunar Module's (LM) key subsystems in Earth orbit. All , guidance, and systems operated within design parameters, with the ascent system demonstrating successful ignition and sustained burn for 5 minutes and 47 seconds, validating engine restart capability essential for future lunar operations. No structural anomalies or significant deviations in loads and vibrations were detected during ascent, staging, or reentry phases, underscoring the LM's structural integrity under vacuum conditions. A notable anomaly occurred during the descent test, where the shut down prematurely after only 4 seconds instead of the planned 38 seconds, triggering a computer indicative of a guidance misalignment. Post-flight traced this to a software error in the LM's guidance computer, specifically an incorrect modeling of buildup during ignition, which caused the to interpret the 's as outside acceptable limits. This issue was resolved through a targeted software implemented for subsequent missions, ensuring enhanced reliability without hardware modifications. Additionally, excessive activity in the (RCS) following staging led to accelerated depletion due to a mass property miscalculation, resulting in temporary tumbling of the LM ascent stage; however, minor RCS leaks observed were deemed non-critical and did not compromise overall certification. The mission yielded approximately 8 hours of high-fidelity data, captured by ground stations worldwide and subjected to detailed post-flight review, which comprehensively validated the LM's readiness for crewed operations. This confirmed that the systems, including abort sequences, met or exceeded performance thresholds, with no impacts to or orbital insertion. Ground-based simulations replicating conditions further corroborated the flight results, verifying subsystem interactions without the need for additional uncrewed tests. As a direct outcome, the LM was officially certified for its first manned flight on , scheduled for early 1969, allowing the program to proceed without a redundant uncrewed LM mission; , launched in April 1968, instead prioritized vehicle qualification. The Manned Spacecraft Center's Apollo 5 Mission Report (MSC-PA-R-68-7), released in March 1968, documented these findings and provided the technical basis for advancing to crewed LM evaluations.

Legacy in Apollo Program

The success of Apollo 5 in January 1968 played a pivotal role in accelerating the Apollo program's timeline toward the goal of a crewed lunar landing by the end of the decade. By verifying the Lunar Module's (LM) propulsion systems and operational reliability despite minor anomalies, the mission provided NASA with the confidence to proceed without further delays, enabling the bold decision to send Apollo 8 on its historic crewed lunar orbit mission just 11 months later in December 1968. This advancement kept the program on track amid tight deadlines set by President Kennedy, avoiding potential setbacks that could have jeopardized the 1969 landing objective. As a direct precursor to crewed LM operations, Apollo 5's test data informed the design refinements and flight procedures for , the first crewed Earth-orbit demonstration of the LM in March 1969, where astronauts , , and successfully separated, maneuvered, and rendezvoused the LM with the Command and Service Module. Lessons from the uncrewed firing sequences and guidance system performance were directly applied to Apollo 10's lunar orbit rehearsal in May 1969 and ultimately to Apollo 11's historic landing in , ensuring the LM's ascent stage could reliably lift astronauts from the lunar surface. The mission's outcomes also led to the cancellation of a planned second uncrewed LM test flight with LM-2 on March 15, 1968, deemed redundant after Apollo 5's achievements, thereby conserving significant resources and streamlining the path to crewed flights. Apollo 5 holds historical significance as the first U.S. mission to successfully restart a spacecraft's system in space, with the LM's ascent system firing twice—once for 60 seconds and again for over six minutes—demonstrating critical restart capability essential for lunar mission aborts. This milestone was honored in NASA's retrospectives during the Apollo program's 50th anniversary celebrations from 2018 to 2019, including dedicated articles and exhibits highlighting uncrewed tests as foundational to the Moon landings. Recent analyses, such as NASA's 2023 commemorative overview of the mission's 55th anniversary, emphasize Apollo 5's role in showcasing the diversity of Apollo engineering challenges, from restarts to guidance adaptations, while underscoring how uncrewed contributions like this one are often overlooked in narratives focused on crewed spectaculars. No major updates to the mission's legacy have emerged since, but these reflections reinforce its enduring impact on reliable spaceflight hardware development.

References

  1. [1]
    55 Years Ago: The First Test Flight of the Apollo Lunar Module - NASA
    Jan 23, 2023 · During the Jan. 22, 1968, flight of Apollo 5, LM-1 simulated the steps of a lunar landing mission, testing the engines of the descent stage, ...
  2. [2]
    Apollo 5 | National Air and Space Museum
    The Apollo 5 mission's primary objective was to test the Apollo lunar module, which was a two-stage vehicle designed to ferry two astronauts from lunar orbit to ...Missing: NASA | Show results with:NASA
  3. [3]
    Apollo 5 - NASA
    Oct 31, 2024 · The Apollo 5 (LM-1/Saturn 204) uncrewed space mission was launched from Kennedy Space Center's Launch Complex 37 at 5:48:09 pm (EST), Jan. 22, 1968.Missing: UTC times parameters
  4. [4]
    [PDF] Apollo Program Summary Report JSC-09423 - NASA
    Jan 2, 2010 · The Apollo 5 mission was the first flight of a lunar module and the ... Postlaunch Report for Mission AS-201. NASA Johnson Space Center ...
  5. [5]
    President John F. Kennedy's May 25, 1961 Speech before a ... - NASA
    Sep 22, 1998 · Kennedy announced before a special joint session of Congress the dramatic and ambitious goal of sending an American safely to the Moon before ...Missing: LOR | Show results with:LOR
  6. [6]
    NASA Decides on Lunar Orbit Rendezvous for Moon Landing
    Jul 11, 2022 · On July 11, 1962, senior NASA managers announced the decision to use the lunar orbit rendezvous method for the Apollo Moon landing program.Missing: origins | Show results with:origins
  7. [7]
    Project Apollo Annotated Bibliography, Ch4 - NASA
    The bulk of the volume recounts the actual history of the Apollo spacecraft themselves through 7 November 1962 when NASA selected Grumman to develop the lunar ...
  8. [8]
    Apollo's Lunar Module Bridged Technological Leap to the Moon
    Jan 28, 2019 · The contract for designing and building the LM was awarded to Grumman Aerospace in November 1962. A year earlier, North American Aviation ...
  9. [9]
    55 Years Ago: Apollo 4, the First Flight of the Saturn V - NASA
    Nov 9, 2022 · After arriving at Launch Pad 39A on Aug. 26, 1967, engineers put the Apollo 4 Saturn V stack through several months of integrated tests. On ...
  10. [10]
    55 Years Ago: The Apollo 1 Fire and its Aftermath - NASA
    Feb 3, 2022 · Following the fire, NASA decided that all subsequent Apollo crews would fly aboard the more advanced Block II version of the spacecraft, not ...
  11. [11]
    50 Years Ago: Low Named Acting NASA Administrator
    Sep 16, 2020 · In April 1967, following the Apollo 1 fire, Low was named as the manager of the Apollo Spacecraft Program Office responsible for implementing ...
  12. [12]
    50 Years Ago: Management Changes at NASA
    Dec 3, 2019 · Low who, in that position since April 1967, led the agency's efforts to recover from the Apollo 1 fire and originated the idea to send Apollo 8 ...
  13. [13]
    The Apollo Program - NASA
    Oct 31, 2024 · Apollo 5. The primary goal of the uncrewed Apollo 5 mission was to complete the first test flight of the Lunar Module. About Apollo 5.Apollo 5 · Apollo 1 · Apollo 11 · Apollo 13
  14. [14]
    55 Years Ago: Final Preparations for the Planned Launch of Apollo 1
    Jan 19, 2022 · Although LM-1 missed its November 1966 delivery date, NASA pressed ahead with assembly of its Saturn IB rocket, designated AS-206, to be ready ...
  15. [15]
    [PDF] The Apollo Spacecraft: A Chronology Volume IV - NASA
    Jul 13, 1974 · ... Postlaunch Report for Mission AS-202 (Apollo Spacecraft Oil)," MSC ... Apollo 5, etc., and (2) the Apollo Applications missions would ...
  16. [16]
    Apollo/Saturn Schedule - NASA
    Oct 22, 2004 · The National Aeronautics and Space Administration today announced an Apollo mission of six flights in 1968 and five in 1969.Missing: compression late
  17. [17]
    'Fire in the Hole': 50 Years Since Apollo 5, First Lunar Module Test ...
    Jan 21, 2018 · Without further ado, at 5:48 p.m. EST on 22 January 1968, the eight H-1 engines of the S-IB first stage roared to life, turning night into day ...
  18. [18]
    22 January 1968, 22:48:08.86 UTC, T + 00:00:00.86
    Jan 22, 2025 · The Saturn IB AS-204 was a two-stage, liquid-fueled, heavy launch vehicle. It consisted of a S-IB first stage and S-IVB second stage.
  19. [19]
    SATURN IB FACT SHEET - Spaceline
    The eight Rocketdyne H-1 first stage engines were improved to produce a combined 1,640,000 pounds of thrust at liftoff. The Saturn IB first stage was designated ...<|control11|><|separator|>
  20. [20]
    [PDF] Saturn IB Stage Launch Operations - Scholarly Commons
    The S-IVB stage, with a single 200,000 pound thrust J-2 engine, burns 64,000 gallons of liquid hydrogen and 20,000 gallons of liquid oxygen in about 7.5 minutes ...
  21. [21]
    Rocket Propulsion Evolution: 7 - Saturn I, IB
    Mar 1, 2021 · Saturn IB SA-201 first took flight on 26 Feb 1966. After two more test flights, the uncrewed Apollo 5 (SA-204) was launched on 22 Jan 1968 ...
  22. [22]
  23. [23]
    [PDF] APOLLO/SATURN CONSOLIDATED INSTRUMENTATION PLAN ...
    SATURN LAUNCH VEHICLE, SA-204L. The SA-204L launch vehicle consists of the S-IB stage, and S-IVB stage, and an unpressurized Instrument Unit (IU). 2.4.1.1. S ...
  24. [24]
    Saturn IB
    Empty Mass: 41,594 kg (91,699 lb). Thrust (vac): 8,241.763 kN (1,852,822 lbf). Isp: 296 sec. Burn time: 155 sec. Isp(sl): 262 sec ...
  25. [25]
    Apollo 5: The First Flight of the Lunar Module | Drew Ex Machina
    Jan 22, 2018 · The first unmanned test flight of the Lunar Module (LM) which would make the actual landing on the Moon possible.
  26. [26]
    LM 1 (LEM 1) - Gunter's Space Page
    Jun 2, 2025 · The LM consists of an ascent stage and a descent stage. Both stages function as a single unit during separation from the CM, lunar descent, and ...
  27. [27]
    [PDF] APOLLO EXPERIENCE REPORT - ASCENT PROPULSION SYSTEM
    burn time was increased to 460 seconds because of increased vehicle weights. Combustion- stability tests on the unbaffled injector were delayed because of ...
  28. [28]
    Apollo experience report: Lunar module reaction control system
    The design, development and qualification of the reaction control system for the Apollo lunar module are described.
  29. [29]
    Guidance and control systems; lunar module mission programer
    Apr 1, 1975 · The system was further proved on the unmanned Apollo 5 mission. Several anomalies were detected, and satisfactory solutions were found. These ...
  30. [30]
    Apollo 5 mission - Final flight evaluation report
    Flight evaluation of Apollo 5 mission with planned mission events and details of mission as flown. Document ID 19700024869.Missing: note | Show results with:note
  31. [31]
    50th anniversary of NASA's decision to cancel the LM-2 mission.
    Mar 9, 2018 · ... Apollo 5 in January. The decision to not fly LM-2 resulted in a significant cost and schedule savings to achieve the goal of landing a man ...