Fact-checked by Grok 2 weeks ago

Kaleshwaram Lift Irrigation Project

The Kaleshwaram Lift Irrigation Project (KLIP) is the world's largest multi-stage lift irrigation scheme on the Godavari River at Kaleshwaram in Bhupalpally district, Telangana, India, designed to divert water for agricultural, drinking, and industrial purposes across drought-prone regions. It comprises three barrages—at Medigadda, Annaram, and Sundilla—with a combined storage capacity of 33.18 thousand million cubic feet (TMC), 20 pump houses enabling cumulative lifts in stages, 20 reservoirs totaling 147.71 TMC, and an extensive 1,832 km network of gravity canals, tunnels, and pressure mains to distribute water. The project aims to create new irrigation for 1,825,700 acres and stabilize 1,882,970 acres in 13 districts, while supplying 40 TMC for drinking water (including 30 TMC for Hyderabad and Secunderabad) and 16 TMC for industry, drawing primarily from 195 TMC lifted from the Godavari supplemented by other sources, at a designed power demand of 4,627 MW. Despite its ambitious scale and approval by the , KLIP has encountered substantial challenges, including cost overruns far exceeding the initial Rs. 80,190 estimate, with projections indicating totals surpassing Rs. 1.47 lakh amid irregularities such as potential undue contractor benefits of at least Rs. 2,684 as flagged in a and Auditor General (CAG) performance audit. Structural failures, notably sinking piers at the Medigadda barrage attributable to foundation cavities, , and flaws, have raised engineering viability concerns shortly after commissioning, compounded by high annual operational costs estimated at Rs. 18,000 with limited actual water delivery to intended ayacuts. These issues underscore causal factors like rushed execution and inadequate geotechnical assessments, prompting ongoing investigations and debates over the project's long-term sustainability despite its potential to transform Telangana's .

History and Background

Conception and Planning

The Kaleshwaram Lift Irrigation Project (KLIP) evolved from the Pranahita-Chevella Lift Irrigation Project, originally conceived in 2007 by the Congress government of undivided to divert surplus water from the —a Godavari originating in —for in Telangana's arid regions. This earlier scheme aimed to transfer up to 16,000 million cubic feet (TMC) of water annually but faced delays due to interstate disputes over water rights with and environmental concerns. Following Telangana's formation in June 2014, the Telangana Rashtra Samithi (TRS) government under redesigned the project to lift water directly from the at village in , avoiding reliance on Pranahita inflows controlled by upstream states. The revised plan, formalized as KLIP, targeted harnessing 141 TMC of Godavari floodwaters to irrigate 18.25 acres across 13 districts, stabilize drinking water supply for , and enable industrial use, with an emphasis on multi-stage pumping to elevations exceeding 500 meters. This shift was driven by hydrological assessments showing underutilized Godavari flows in Telangana's upper basin, estimated at over 200 TMC during monsoons, amid the state's historical dependence on rain-fed agriculture vulnerable to droughts. Planning commenced in 2015 with feasibility studies by the Irrigation Department, incorporating geological surveys of the Godavari basin and engineering designs for three barrages, reservoirs, and a 500-kilometer distribution network of canals, tunnels, and lifts. Pre-feasibility reports submitted for environmental clearance in June 2017 detailed lifting 4.5 TMC initially from the Godavari near Kannepally to fill local tanks, scaling to full capacity via 19 pump houses with a total installed power of 36,000 MW. The design prioritized gravity flow where possible post-lifting to minimize energy costs, budgeted initially at ₹80,190 crores, though later estimates rose due to scope expansions. Critics, including opposition parties, argued the redesign inflated costs and bypassed rigorous cost-benefit analyses inherited from the original Pranahita-Chevella framework, but proponents cited empirical data on 's 70% rain-dependent farmland yielding low productivity without assured .

Political Context and Approvals

The Kaleshwaram Lift Irrigation Project (KLIP) was conceived as a flagship initiative of the Telangana Rashtra Samithi (TRS, later renamed Bharat Rashtra Samithi or BRS) government following the state's formation in 2014, with Chief Minister K. Chandrashekar Rao (KCR) positioning it as a critical infrastructure project to harness Godavari River waters for irrigation in arid regions. The project drew from earlier proposals like the Pranahita-Chevella Lift Irrigation Scheme under the undivided Andhra Pradesh Congress government, but was substantially expanded and relocated upstream under BRS rule to avoid interstate disputes with Maharashtra and to enable higher water lifts. Approvals proceeded under the BRS administration without formal state cabinet endorsement, as alleged by subsequent investigations; decisions were reportedly centralized under KCR, bypassing standard procedural checks to expedite implementation. The ratified the project in 2016 through a , during which KCR presented technical details via PowerPoint, marking a rare legislative engagement for such infrastructure. Central clearances were secured from the (CWC) and for Agriculture and Rural Development (NABARD), which provided funding support and public endorsements during the BRS tenure, amid the BJP-led Union government's involvement in loan approvals. The project's inauguration on June 21, 2019, by Governor and KCR underscored its political significance, framed as the world's largest multi-stage scheme and funded entirely by state resources exceeding ₹80,000 initially. Post-2023, following the BRS electoral defeat to the Congress-led government under A. , political scrutiny intensified; the Justice P.C. Ghose Commission, appointed in 2024, concluded in August 2025 that KCR bore direct responsibility for procedural lapses, including the absence of cabinet-level approvals and unilateral site changes from the originally planned . This led to calls for a (CBI) probe, highlighting ongoing partisan debates over accountability, with BRS dismissing the findings as politically motivated.

Technical Design and Components

Barrages and Reservoirs

The Kaleshwaram Lift Irrigation Project incorporates three primary barrages along the system—Medigadda, Annaram, and Sundilla—to facilitate water diversion and initial for subsequent lifting and distribution. These barrages collectively provide a capacity of 33.18 TMC at their respective full reservoir levels (FRL), enabling the harnessing of inflow from the Pranhita and upstream reaches. The Medigadda Barrage, situated at Medigadda village in Mahadevpur mandal of the former , operates at an FRL of 100.0 meters with a gross of 16.17 TMC, serving as the project's foremost diversion point for an annual yield of 195 TMC primarily allocated to across 1,825,700 acres, alongside 40 TMC for and 16 TMC for needs. Annaram Barrage, positioned upstream between Medigadda and the existing Sripada Yellampally Project, maintains an FRL of 120.0 meters and 11.9 TMC capacity to support water conveyance to intermediate command areas. Sundilla Barrage, similarly located in the inter-barrage reach, features an FRL of 130.0 meters and 5.11 TMC for augmented flow regulation and pumping intake. An auxiliary barrage, Tummidihetti, at Tummidihetti village in Koutala mandal of , supplements the system with an FRL of 148.0 meters and 1.85 TMC capacity, diverting 20 TMC for the linked Dr. B.R. Ambedkar Pranahita Project to irrigate 200,000 acres. These barrages employ gated spillways to manage flood discharges while minimizing submergence, with designs predicated on riverbed foundations to balance storage against the Godavari's variable monsoon yields.
Barrage NameLocationFRL (meters)Storage Capacity (TMC)Primary Purpose
MedigaddaMedigadda (V), Mahadevpur (M), former Karimnagar district100.016.17Diversion of 195 TMC for irrigation, drinking, and industry
AnnaramBetween Medigadda and Sripada Yellampally120.011.9Water conveyance to command areas
SundillaBetween Medigadda and Sripada Yellampally130.05.11Flow regulation and pumping
TummidihettiTummidihetti (V), Koutala (M), 148.01.85Diversion for Pranahita linkage (20 TMC)
Beyond barrage impoundments, the project integrates 20 downstream reservoirs totaling 147.71 TMC capacity for seasonal storage, stabilization of lifted water, and equitable distribution to ayacuts spanning new irrigation (1,825,700 acres) and stabilization (1,882,970 acres). Prominent among these is the Sri Komaravelly Mallana Sagar with 50 TMC at an FRL of 557 meters, alongside others such as Konda Pochamma Reservoir (15 TMC, FRL 618 meters), Gandhamalla Reservoir (9.87 TMC, FRL 510 meters), and Baswapuram Reservoir (11.39 TMC, FRL 490 meters), which mitigate evaporation losses and enable gravity-fed laterals in elevated terrains. Smaller reservoirs like Ananthagiri (3.5 TMC, FRL 397 meters) and Sri Ranganayaka Sagar (3 TMC, FRL 490 meters) target localized command stabilization.

Water Lifting and Pumping Infrastructure

The water lifting and pumping infrastructure of the Kaleshwaram Lift Irrigation Project features 20 pumping stations distributed across seven links, designed to elevate approximately 195 thousand million cubic feet (TMC) of from the basin to elevations reaching up to 450 meters over distances of about 110 kilometers. These stations enable multi-stage lifting, with conveyed through a combination of pressure mains, tunnels, and canals totaling 1,832 kilometers in length. The system demands a total designed power rating of 4,627 megawatts (MW) to drive the pumps. Link 1 incorporates three primary pumping facilities tied to the Medigadda, Annaram, and Sundilla barrages, including the Lakshmi Pump House near Medigadda, which commenced operations on August 12, 2019, as the initial lifting point for the project. This station, along with the Saraswathi and Parvathi pump houses, houses 43 pump machines, each with a 40 MW capacity, contributing to a combined power draw of 1,720 MW for Link 1 operations. Subsequent links feature additional stations, such as those in Links 2 through 4 and 7, with Link 7 alone including seven pumping points. Notable among these is the Gayatri Pump House, located near Lakshmipur village in , which employs seven high-capacity pumps totaling 973 MW to lift water to a static height of 118 meters, achieving a daily output of at least 2 TMC (622 cubic meters per second). Another specialized facility, Package 8, is situated 330 meters underground and designed to lift 3 TMC per day, representing one of the project's most challenging engineering feats. The pumping system integrates advanced electrical technologies, including 37 medium-voltage motors rated at 40-43 MW each, paired with 15 load commutated inverter (LCI) drive units, excitation systems, and controls for optimized performance across the 300-kilometer network, supporting an annual delivery of 5.5 billion cubic meters. This underpins the project's to irrigate extensive areas by overcoming the region's topographic constraints through staged . The distribution network of the Kaleshwaram Lift Irrigation Project forms an extensive water conveyance system totaling 1,832 kilometers, comprising 1,531 kilometers of gravity canals for downstream flow, 203 kilometers of tunnels to navigate hilly terrains, and 98 kilometers of and mains for pressurized . Organized into seven spanning 13 districts, this links upstream barrages and reservoirs—such as Medigadda, Annaram, and Sundilla—to downstream command areas, enabling gravity-fed after initial lifts. Tunnels, primarily in , 6, and 7, minimize surface evaporation and land requirements by boring through rock formations, while gravity canals branch into distributaries for field-level . Each link features tailored combinations of canals, tunnels, and mains to adapt to local and demands, as detailed below:
LinkGravity Canal (km)Tunnel (km)Pressure/Delivery Mains (km)Total Length (km)Notes
116.3021.95 (plus 8.1 )46.30Connects three barrages; 33.18 TMC .
212.2049.80 (twin)3.6465.63Tunnel-dominant for inter-reservoir transfer; no direct ayacut.
327.50125.9245.48Serves 86,150 acres.
439441.4010.82446.22Extensive canal network; 589,280 acres.
52071.450208.65Primarily canals; 251,800 acres.
6581430.93625Longest canal segment; 329,042 acres.
72855655395Balanced system; 539,428 acres.
These components integrate with 20 reservoirs holding 147.71 TMC capacity, facilitating phased water release for kharif and rabi seasons across 1,825,700 acres of ayacut. The design prioritizes efficient conveyance, with tunnels engineered for high-velocity flow to maintain hydraulic gradients, though implementation has involved geological assessments to ensure stability in the Deccan Plateau's and sedimentary formations.

Intended Command Area and Water Allocation

The Kaleshwaram Lift Irrigation Project (KLIP) was designed to provide to a new ayacut, or command area, of 1,825,700 acres (approximately 739,000 hectares) spread across 13 districts in , including , , , , and Rangareddy. This new command area targets drought-prone regions previously lacking reliable water supply, with water distributed through a network of reservoirs, canals, and links to enable cultivation of multiple crops per year. In addition to the new ayacut, the project aims to stabilize an existing command area of 1,882,970 acres associated with prior infrastructure such as the Sri Ram Sagar Project (SRSP) stages I and II, the Flood Flow Canal, , and , bringing the total intended irrigated area to 3,708,670 acres. Stabilization involves enhancing water reliability for these areas by lifting and channeling water to offset deficits from upstream abstractions and seasonal variability. The project's water allocation totals 240 thousand million cubic feet (TMC), sourced primarily from 195 TMC lifted at the Medigadda Barrage on the Godavari, supplemented by 20 TMC from the and 25 TMC from groundwater integration. Of this, 169 TMC is designated for across the combined new and stabilized command areas, enabling an estimated annual intensity sufficient for two to three crop cycles in upland regions. Further allocations include 40 TMC for drinking water—30 TMC for and urban supplies and 10 TMC for enroute villages—and 16 TMC for industrial purposes, prioritizing high-demand sectors in the project's service area. These distributions reflect the multi-purpose intent, with comprising the largest share to address Telangana's historical under- relative to its cultivable land.

Construction Execution and Timeline

Key Milestones and Phases

The Kaleshwaram Lift Irrigation Project was executed in phases corresponding to its seven links and 28 packages, with accelerating after project re-engineering between 2015 and 2016, building on initial agreements signed in 2007-2009. Interstate pacts, including the 2012 agreement between and and the 2016 full reservoir level fixation at +148.00 m, paved the way for implementation, culminating in all statutory clearances by June 6, 2018. Phase 1, centered on Link 1, encompassed construction of three barrages—Medigadda (Lakshmi), Annaram (Saraswati), and Sundilla (Parvati)—with a combined storage of 33.18 TMC. The Lakshmi Barrage and initial pumping stations at Medigadda, capable of lifting 2 TMC daily, were completed by Megha Engineering and Infrastructure Limited in record time and inaugurated on June 21, 2019, marking the project's operational launch. Subsequent phases advanced Link 2 infrastructure, including the underground pumphouse, with electro-mechanical works commencing in August 2019. The Barrage followed in 2020, enhancing storage and lifting from higher elevations. Link 1 barrages collectively enabled phased water diversion, though full project stabilization occurred post-2020 floods, with operations resuming by July 2023. Later links progressed variably, targeting completion of distribution networks by the early 2020s to irrigate the intended 18.25 acres.

Contractors, Contracts, and Implementation Challenges

Megha Engineering and Infrastructures Limited (MEIL) executed a substantial share of the project, constructing 15 of the 22 pump houses, including the Lakshmi pumphouse at Medigadda Barrage (12 machines), Saraswati at Annaram (12 machines), and Parvati at Sundilla (14 machines), among others like Annapurna, Ranganayakasagar, and Mallannasagar. Navayuga Engineering Company Limited handled Package 6, encompassing 9.534 km twin tunnels (10 m diameter), India's largest man-made surge pool (375 m x 25 m x 67 m), and an underground pump house with seven 124.5 MW pumps for a 110 m lift and 634 cumecs discharge capacity. (L&T) in with Patel Engineering Services (PES JV) managed key elements of the Medigadda Barrage, including pile foundations for Block 7, under contracts valued at over ₹4,613 via supplemental agreements. The project comprised 28 packages across seven links, with contracts emphasizing rapid execution amid political pressures for early inauguration on June 21, 2019. Excess work worth ₹28,000 was allegedly awarded to MEIL without competitive bidding, raising concerns over irregularities. Implementation encountered severe hurdles, including massive cost overruns documented by the Comptroller and Auditor General (CAG), with expenditures rising from ₹80,190 crore (2015-16 price level) to over ₹1.47 lakh crore, yielding a benefit-cost ratio of 0.75 and deeming the project economically unviable. Progress lagged, with only 12 of 56 works completed and excess payments exceeding ₹7,500 crore to firms like MEIL and L&T due to inflated claims and unverified measurements. Structural failures compounded issues, exemplified by the sinking of piers in Medigadda Barrage's Block 7 on October 21, 2023, triggered by faulty secant pile execution, unrectified defects noted since 2019, inadequate foundation concrete, and excessive water storage inducing soil liquefaction. These lapses stemmed from design delays, reliance on unproven contractor methods without Indian Standards compliance, and rushed approvals bypassing rigorous scrutiny. Allegations of prompted investigations, including CAG-flagged financial mismanagement and a probe ordered in September 2025 into fund siphoning and construction flaws, with recommendations for action against 57 engineers and cost recovery from L&T PES JV. Political haste for milestones overrode engineering protocols, exacerbating risks in geologically challenging terrain.

Economic Analysis

Cost Overruns and Funding Sources

The Kaleshwaram Lift Irrigation Project (KLIP), originally envisioned as the lower-cost Pranahita-Chevella Lift Irrigation Project with an estimated outlay of around ₹25,000 crore, underwent significant re-engineering after 2014, which the Comptroller and Auditor General (CAG) of India described as quadrupling the project cost through altered design parameters and scope expansion without adequate justification or benefit-cost analysis updates. The revised administrative approval in 2016 pegged the cost at approximately ₹80,500 crore, but by 2023, expenditures had surpassed ₹1.03 lakh crore, with CAG audits projecting a potential overrun to ₹1.4 lakh crore due to escalated land acquisition, civil works, and electro-mechanical components, compounded by delays and inefficient contracting. These overruns stemmed from fragmented packaging of works into over 100 contracts, bypassing competitive bidding norms in some cases, and failure to revise cost estimates amid inflation and scope changes, as highlighted in CAG's performance audit for 2016-2022. Funding for KLIP was primarily secured through off-budget loans raised by the Irrigation Project (KIPCL), a special purpose vehicle established in , totaling approximately ₹87,449 from 15 banks and financial institutions by 2023, including major contributions from Rural Electrification Corporation (REC) at ₹30,536 and other public sector lenders like . These loans carried high interest rates averaging 9-10%, serviced from the state , with cumulative interest payments reaching ₹29,956 and principal repayments ₹19,878 by mid-2025, straining Telangana's fiscal resources amid annual outflows exceeding ₹9,500 . No grants or multilateral loans, such as from the , were involved, with funding reliant on domestic borrowings that exposed the project to non-performing asset risks for lenders following construction delays and structural issues reported from 2023 onward. The has sought loan restructuring and transfer to lower-interest entities, citing violations of funding norms like inadequate tie-ups for loan servicing prior to disbursement.

Projected and Realized Benefits

The Kaleshwaram Lift Irrigation Project was projected to create a new ayacut of 18.25 acres (approximately 1.825 million acres) through multi-stage lifting of water, while also stabilizing irrigation for an additional 26.76 acres in existing systems. Proponents anticipated enhanced in drought-prone regions of , alongside allocation of 30 TMC of water for drinking and industrial uses, including supply to and rural households. These projections underpinned claims of economic returns through increased crop yields, , and support for fisheries and , with the overall scheme designed to harness 141 TMC of storage capacity. In practice, realization of these benefits has fallen short, with the Comptroller and Auditor General (CAG) reporting only 40,888 acres of command area created as of March 2022, equating to less than 3% of the targeted new ayacut. Partial water diversion has enabled some drinking water supply to , positioning the project as a supplementary source amid efforts to revive local rivers like the Musi, though full industrial and rural allocations remain unachieved due to incomplete distribution networks. Agricultural outcomes are constrained by limited operational lifts and high costs for pumping, estimated at Rs. 46,666 per acre annually under partial utilization assumptions. Economic assessments by the highlight discrepancies in projected versus realized value, with the benefit-cost ratio overstated through inflated benefit valuations and understated annual expenses, yielding an actual ratio of 0.52—indicating losses exceeding gains even if fully operational from 2024-25. Independent analyses corroborate that re-engineering from the original Pranahita-Chevella design quadrupled costs while expanding ayacut by only 50%, undermining viability without corresponding productivity surges. While modest and urban have materialized in select districts, systemic delays and structural concerns have deferred broader economic uplift, with critics attributing shortfalls to optimistic assumptions ungrounded in hydrological and fiscal realism.

Operational Impacts

Agricultural and Groundwater Outcomes

The Kaleshwaram Lift Irrigation Project (KLIP), operational since , has influenced agricultural patterns in its command area through expanded water availability, leading to an 82.1% increase in cultivation area from 313,929 hectares in the 2018–2019 winter to 571,632 hectares in 2022–2023. This shift coincided with a 30.3% reduction in , from 754,954 hectares to 526,559 hectares over the same period, enabling greater utilization in previously drought-prone districts like , where area rose by 219.7%. analyses further indicate enhanced cropping intensity, particularly double-cropping in the Rabi , transforming underutilized lands into productive zones via improved infrastructure. Statewide, Rabi area grew by 50.75% to 21.45 hectares by 2020 from 12.28 hectares in , with KLIP contributing an ayacut of 7.3 hectares, though this encompasses complementary initiatives like restorations. However, realized irrigation coverage has fallen short of the planned 18.25 acres, with only 44,570 acres irrigated under KLIP during the Kharif of 2025 due to insufficient inflows amid operational constraints. The emphasis on water-intensive has elevated requirements by 54.4%, from 3.22 billion cubic meters to 4.97 billion cubic meters between 2018–2019 and 2022–2023, potentially straining supply in variable years without proportional yield gains documented in geospatial assessments. productivity remained stable but showed minor declines in districts like , suggesting limits to efficiency amid pattern shifts. Regarding groundwater, KLIP aimed to recharge aquifers by diverting to and reducing reliance on wells, yet extraction in the project area reached 88.03 thousand million cubic feet (TMC) against 160.5 TMC availability as of , equating to a 55% development stage indicative of moderate stress. Statewide levels improved post-monsoon in May , with an rise of 4.22 meters, attributed partly to enhancements including KLIP, though overexploited zones expanded by 36% by May 2025 despite overall table elevations from excess rainfall. Complementary efforts like elevated levels from 10.40 meters below ground in 2017–2018 to 6.57 meters in , adding irrigable area, but free policies have spurred deeper pumping, offsetting recharge benefits in some mandals. Risks of waterlogging persist in low-lying command zones due to elevated recharge without adequate drainage.

Drinking and Industrial Water Supply

The Kaleshwaram Lift Irrigation Project allocates 30 TMC of water for municipal drinking supply to and 10 TMC for rural drinking needs under the program, drawn from the project's reservoirs and distribution network. These volumes support piped water delivery to households in enroute villages and augment urban supplies, with Mallanna Sagar reservoir enabling diversion of up to 17.5 TMC annually for 's core demands and 2.5 TMC for replenishing and reservoirs. integrates KLIP water to provide safe, treated to over 24,000 rural habitations statewide, covering approximately 70% of Telangana's through local and . Industrial allocation stands at 16 TMC, primarily for miscellaneous manufacturing and industrial parks in the project's 13 covered districts, lifted via gravity canals and tunnels from intermediate reservoirs like Annaram and Lakshmi. This supports sectors such as pharmaceuticals and food processing by ensuring reliable raw water for cooling, processing, and operations, with Link-2 infrastructure facilitating delivery to mid-Manair areas. Realized supplies have been partial due to operational challenges, including structural distress at Medigadda barrage reported since October 2023, limiting full lifts and prompting reliance on alternative Godavari sources for . Phase II of the Godavari drinking water scheme from Mallanna Sagar, approved in August 2024 at a cost of ₹5,560 , aims to operationalize additional urban flows but remains under implementation as of 2025. Industrial drawdowns have similarly prioritized essential users amid reduced capacity, though the allocation framework persists for future expansion.

Environmental Effects

Mitigation Measures and Positive Outcomes

The Kaleshwaram Lift Irrigation Project incorporated several environmental mitigation measures as part of its Environmental Management Plan (EMP), including compensatory afforestation on 2,653.121 hectares of non-forest land across seven districts: Rajanna-Sircilla, Jagtial, Warangal Urban, Siddipet, Peddapalli, Nagarjunasagar, and Nalgonda. These efforts utilized native species such as neem, teak, nemilinara, rela, marri, raavi, and juvi, with planting initiated prior to the project's 2020 completion target and employing techniques like gunny bag and canister methods for rocky terrains, alongside protective measures including chain-linked fencing, contour trenches, rock-fill dams, and mini-tanks for soil and moisture conservation. Additional safeguards encompassed catchment area treatment plans using remote sensing, GIS, and silt yield indexing to address soil erosion in severe-prone zones through biological and engineering interventions, as well as green belt development along reservoirs, canals, and worker colonies with local species. Pollution control during construction phases targeted air quality via dust suppression, noise via barriers and scheduling restrictions, and water via sediment traps and wastewater treatment, with ongoing monitoring plans for air and water quality post-construction. Biodiversity conservation involved collaboration with the State Forest Department to protect rare, endemic, and , while fisheries management plans addressed river and reservoir impacts, and muck disposal sites were selected beyond high levels with rehabilitation protocols. The EMP allocated approximately ₹36.09 for construction-phase implementation, emphasizing disaster management including break analysis and early warning systems. Positive environmental outcomes include enhanced water availability from lifting 180 TMC annually, supporting local ecosystems through stabilized across 1,825,700 acres and potential for pisciculture in reservoirs. The project's and initiatives have contributed to increased vegetative cover in semi-arid regions, aiding and microclimate improvement, while reliable water diversion reduces scarcity-driven overexploitation of in drought-prone areas. These measures, when realized, promote sustainable by enabling perennial cropping patterns that minimize fallow periods and erosion risks associated with rain-fed agriculture.

Violations, Risks, and Criticisms

The National Green Tribunal (NGT) ruled in October 2020 that the environmental clearance for the Kaleshwaram Lift Irrigation Project was granted ex post facto, after construction had commenced, constituting a violation of the Environmental Impact Assessment (EIA) Notification, 2006, which mandates prior approval. The tribunal directed the Ministry of Environment, Forest and Climate Change to constitute an expert panel for remedial measures, highlighting the absence of a comprehensive EIA and social impact assessment prior to project initiation. Environmental risks include heightened vulnerability to flooding along the , as evidenced by the submergence of two key pump houses—Pranahita and —in July 2022 due to unprecedented inflows exceeding design capacities, leading to operational disruptions and repair costs. The project's barrages and reservoirs, such as those at Mallannasagar, feature orientations parallel to the river flow, potentially exacerbating waterlogging and artesian pressure buildup in surrounding aquifers. Component structures like the Baswapur reservoir are projected to submerge over 3,400 acres, including 1,600 acres of farmland, raising concerns over downstream flooding in and cross-border impacts in Maharashtra's , where 11 villages reported land inundation and livelihood losses without adequate compensation. Criticisms from environmentalists center on inadequate baseline data in the EIA, with studies relying on secondary information from a limited 10 km radius around sites, potentially underestimating ecological disruptions to the Godavari basin's and riparian habitats. Post-2024 rulings on EIA compliance have amplified calls for scrutiny of KLIP, arguing that rushed clearances bypassed rigorous consultations and failed to address cumulative impacts from multiple barrages on flow and salinization. Independent assessments have flagged the project's for insufficient against events, attributing risks to over-reliance on lift mechanisms without integrated attenuation measures.

Controversies and Structural Failures

Engineering and Design Flaws

The Kaleshwaram Lift Irrigation Project (KLIP) deviated from the original Pranahita-Chevella Lift Irrigation Project design, shifting the primary intake site from Tummidihatti on the Pranahita River—a tributary of the Godavari—to Medigadda on the main Godavari River downstream of the confluence. This relocation, implemented around 2016, increased vulnerability to siltation due to the accumulation of sediments from upstream tributaries, reducing storage capacity in the headworks and necessitating ongoing dredging not adequately accounted for in the initial hydrology studies. Critics, including engineering analyses, argue this choice prioritized political considerations over technical optimality, as the Pranahita site offered clearer water with lower silt loads and potentially more stable long-term reservoir performance, though it involved interstate water-sharing complexities with Maharashtra. The project's barrages—Medigadda, Annaram, and Sundilla—exhibit fundamental deficiencies identified in the National Dam Safety Authority (NDSA) investigation, including inadequate geo-technical investigations that failed to assess weak strata and scour potential beneath . Hydraulic flaws, such as improper Gauge-Discharge curve calibration for flood modeling, compounded risks, leading to uneven stress distribution during high flows. At Medigadda, the raft design overlooked formation and sand piping, resulting in the partial sinking of in Block 7 on October 21, 2023, with displacements up to 30-50 cm and cracks rendering the structure unfit for operations. Similar issues at Sundilla, including damage attributed to defects by contractor Navayuga , highlight systemic underestimation of seismic and hydraulic loads despite the site's proximity to fault lines. Construction deviated from approved parameters, with shallow pile foundations and insufficient scour protection exacerbating vulnerabilities, as confirmed by IIT audits revealing leaks, seepages, and foundation instabilities across all three barrages. The NDSA's April 2025 report classified these as "irreversible" in Medigadda, stemming from flawed redesign without comprehensive model studies, while attributing partial responsibility to contractors like L&T for execution lapses, though the firm contested the findings as overlooking as-built conditions. Overall, the multi-stage pumping design, while enabling lifts up to 151 meters, amplified energy demands without corresponding efficiency gains, underscoring a prioritization of scale over resilient fundamentals.

Allegations of Corruption and Political Motivations

The Kaleshwaram Lift Irrigation Project has faced allegations of systemic corruption, including fund siphoning, inflated costs, and kickbacks during its execution under the (BRS) government led by former (KCR). Critics, including opposition leaders and subsequent investigations, have pointed to the project's from an initial estimate of approximately ₹38,000 crore to over ₹1 lakh crore, attributing it to irregular tendering processes, favoritism toward specific contractors like the L&T-Mecon JV, and deviations from approved designs without due diligence. A judicial inquiry by the Justice P.C. Ghose Commission, constituted in 2023, identified "massive irregularities" such as bypassing expert committee recommendations on project components like the Medigadda barrage, recommending criminal action against 57 engineers and contractors for actions that compromised structural integrity and financial prudence. The government under A. has pursued probes, with the Vigilance Commission approving asset freezes for implicated engineers in October 2025 and handing over the case to the (CBI) for deeper scrutiny into corruption and lapses, following the Ghose report's findings of political interference in administrative decisions. Political motivations underlying the project's initiation and rushed implementation have been central to the discourse, with detractors arguing that KCR prioritized it as a flagship achievement to bolster BRS's electoral image in agrarian post-2014 bifurcation, often overriding technical advisories for expedited completion ahead of polls. The Ghose Commission explicitly held KCR accountable for "bad planning and execution," citing instances where ministerial directives, including from then-Irrigation Minister , compelled engineers to approve substandard work and ignore geological risks, framing these as politically driven overrides rather than merit-based decisions. BRS leaders have countered these claims as vendetta by the incoming administration, denying and portraying the probes as selective politicization to discredit the project's intent of year-round for farmers, while noting that loans totaling ₹85,000 were raised transparently for infrastructure needs. Opposition figures like YSR Telangana Party's have labeled it India's "biggest national scam," emphasizing how political urgency led to opaque funding via off-budget borrowings, evading assembly oversight. As of September 2025, the Anti-Corruption Bureau (ACB) has assumed aspects of the investigation amid delays in involvement, with KCR and Harish Rao seeking protection against , underscoring ongoing tensions where accountability claims intersect with accusations of electoral maneuvering. These allegations persist amid structural failures like barrage , prompting debates on whether the project's scale was a genuine developmental imperative or a vehicle for patronage and legacy-building, with judicial findings lending weight to critiques of governance lapses under BRS rule.

Recent Investigations and Developments

Government Transitions and Inquiries

Following the elections on November 30, 2023, the won 64 seats, defeating the incumbent (BRS) which secured 39, resulting in a government transition with A. sworn in as on December 7, 2023, ending K. Chandrashekar Rao's (KCR) decade-long tenure. The incoming Congress administration prioritized scrutiny of major infrastructure projects executed under the prior BRS regime, including the Kaleshwaram Lift Irrigation Project (KLIP), amid reports of structural distress—such as the sinking of piers at the Medigadda barrage in October 2023—and cost escalations surpassing ₹1.07 lakh crore against an initial estimate of ₹80,000 crore. On March 14, 2024, the government established a one-man judicial commission under retired judge P.C. Ghose to probe alleged irregularities, , and lapses in KLIP's , tendering, , , and , particularly focusing on the barrages at Medigadda, Annaram, and Sundilla. The commission, extended multiple times due to its scope, summoned key figures including former KCR and ex-Irrigation Minister , and submitted its report on July 31, 2025, attributing primary responsibility for project failures and financial overruns to decisions by KCR and Harish Rao, including deviations from technical norms that led to avoidable state liabilities exceeding ₹50,000 crore. The state cabinet approved the report on August 4, 2025, after which BRS leaders petitioned the on August 20, 2025, to quash it, claiming procedural flaws and political bias in its constitution and conduct. In the state assembly debate on August 31, 2025, referenced the Ghose report's evidence of systemic violations to announce transferring the investigation to the () for impartial examination of corruption, fund diversion, and engineering shortcomings. A formal government order followed on September 2, 2025, entrusting the with the probe, prompting BRS accusations of a Congress-BJP to target opposition leaders while shielding contractors. On the same day, the granted interim protection to KCR and Harish Rao against coercive measures pending further hearings, directing the government to refrain from actions based solely on the commission's findings. The () has urged broadening the 's terms of reference to encompass all project phases and potential complicity beyond the BRS era. As of October 2025, the investigation remains in preliminary stages, with no charges filed, amid ongoing legal challenges to the Ghose Commission's validity.

Ongoing Probes and Future Implications

The (CBI) initiated preliminary scrutiny of documents related to the Kaleshwaram Lift Irrigation Project (KLIP) on September 26, 2025, following a order on September 1, 2025, to probe alleged irregularities, fund siphoning, and construction lapses in the barrages at Medigadda, Annaram, and Sundilla. This directive stemmed from the Justice P.C. Ghose Commission's July 31, 2025, report, which identified lapses in planning, execution, and oversight under the prior (BRS) administration, including suppression of expert advice against the project's design. Concurrently, the Telangana Vigilance and Enforcement Department, through its Anti-Corruption Bureau (ACB), has pursued investigations uncovering unaccounted funds estimated in hundreds of crores, with approvals on October 14, 2025, to freeze assets of implicated engineers. These probes build on the National Dam Safety Authority's (NDSA) April 2025 assessment, which documented structural deficiencies in the barrages, prompting government directives for expert-led rehabilitation starting October 1, 2025. Legal challenges persist, including a September 24, 2025, high court petition by former official contesting the Ghose report's observations for lacking . While the inquiries attribute causation to rushed approvals, substandard materials, and political haste—evident in the project's from an initial ₹71,000 crore to over ₹1 lakh crore—no convictions have resulted as of October 2025, with outcomes hinging on evidentiary thresholds amid partisan critiques of selective enforcement. Future implications include sustained financial strain on Telangana's , with repair costs potentially adding to the load and diverting funds from operational enhancements. Structurally, incomplete restorations risk seasonal failures, as seen in the 2023 Medigadda , undermining ayacut coverage targets of 45.5 lakh acres. Legally, substantiated findings could lead to prosecutions of officials and contractors, reshaping accountability in large-scale infrastructure, though delays in proceedings—due to prior state consent withdrawals—may prolong resolution. Politically, the probes intensify of prior , potentially influencing water policy toward decentralized alternatives like , prioritizing verifiable hydrology over expansive lifts to mitigate flood-drought cycles in the Godavari basin.

References

  1. [1]
    [PDF] Kaleshwaram project
    Jun 14, 2018 · ❖ Further, after careful planning, the proposed capacity of reservoirs is increased from 11.43 TMC to 147.71 TMC by enhancing the capacities of ...
  2. [2]
    CAG says Kaleshwaram project cost likely to exceed ₹1.47 lakh ...
    Feb 15, 2024 · CAG says Kaleshwaram project cost likely to exceed ₹1.47 lakh crore as against ₹81,911 crore projected - The Hindu.Missing: specifications | Show results with:specifications
  3. [3]
    Kaleshwaram cost to exceed Rs 1.4 lakh cr, likely corruption of Rs ...
    Feb 15, 2024 · The CAG report on Kaleshwaram stated that the possibility of undue benefit of at least ₹2,684.73 crore to contractors working on the project ...Missing: structural | Show results with:structural
  4. [4]
    Kaleshwaram Project: What went wrong with Telangana's mega ...
    May 5, 2025 · Similar issues like sand piping, cavity formation beneath the raft design deficiencies were found in other blocks and at the Annaram and ...
  5. [5]
    No water from Kaleshwaram, but project costs Telangana Rs 18K cr
    Feb 9, 2024 · No water from Kaleshwaram, but project costs Telangana around Rs 18,000 cr annually. State had set up a Special Purpose Vehicle for the Rs 1 ...Missing: specifications | Show results with:specifications
  6. [6]
    Kaleshwaram Irrigation Project: A Blunder or Solution For ... - The Wire
    Jun 3, 2024 · The report categorically warned about all the issues which had surfaced, including the cost of water delivery and safety of major structures.
  7. [7]
    Telangana's Kaleshwaram Lift Irrigation Project - The Hindu
    Jan 15, 2024 · B.R. Ambedkar Pranahitha-Chevella Sujala Sravanthi (PCSS) project, conceived by the Congress in 2007 and meant to harness water from the ...
  8. [8]
    Kaleshwaram Lift Irrigation Project (KLIP) - PMF IAS
    It is a multi-purpose lift irrigation project constructed on Godavari river in Telangana is redesigned from the Pranahita-Chevella project of erstwhile AP.Missing: conception | Show results with:conception
  9. [9]
    Detailed Article on the Kaleshwaram Lift Irrigation Project - LinkedIn
    Oct 26, 2024 · The Kaleshwaram Project evolved from the original Dr. B.R. Ambedkar Pranahita-Chevella Sujala Sravanthi project, redesigned after resolving ...
  10. [10]
    [PDF] KALESHWARAM PROJECT – A GROWTH ENGINE FOR ...
    Kaleshwaram Project is a multi-stage lift irrigation scheme with 141TMC storage, lifting Godavari waters, and is considered a growth engine for Telangana.Missing: conception | Show results with:conception
  11. [11]
    [PDF] kaleshwaram lift irrigation scheme - environmental clearance
    Jun 20, 2017 · Kaleshwaram LIS envisages lifting of 4.5 TMC of water from Godavari River to fill 14. Minor irrigation tanks in Mahadevpur Mandal, ...Missing: specifications | Show results with:specifications
  12. [12]
    [PDF] KALESHWARAM LIFT IRRIGATION SCHEME - TG PCB
    Jul 24, 2018 · Kaleshwaram LIS envisages lifting of 4.5 TMC of water from Godavari River to fill 14 Minor irrigation tanks in Mahadevpur Mandal, Jayashankar ...
  13. [13]
    (PDF) KALESHWARAM PROJECT -A REVIEW - ResearchGate
    The Cost of Kaleshwaram Project is Rs 80,000 crores. Proposed another Rs. 25,000 Crore on Dec, 2019. ... acres in another 7 districts. ... Hyderabad and ...Missing: specifications | Show results with:specifications
  14. [14]
    MEGA Kaleshwaram Project: Conception to Construction
    Dec 3, 2023 · Kaleshwaram Lift Irrigation Project which now is familiar to the entire universe is a multiple entity, comprising construction of three barrages ...
  15. [15]
    Decode Politics: A 'Telangana lifeline' project row that refuses to die ...
    Aug 12, 2025 · The Kaleshwaram Lift Irrigation Project is seen to be the brainchild of former Telangana CM K Chandrashekar Rao. Nikhila Henry. HyderabadAugust ...Missing: history | Show results with:history
  16. [16]
    What is Telangana's Kaleshwaram project? What is the controversy ...
    Aug 6, 2025 · The project was conceived by the BRS government, headed by K. Chandrasekhar Rao, to provide irrigation facilities to over 16 lakh acres in 13 ...
  17. [17]
    Why the Union Govt Cannot Pretend to Be Shocked by ... - The Wire
    Sep 13, 2022 · These two ministers and the Union government, should also be aware that the CWC and NABARD gave approvals and funded the project and praised it ...
  18. [18]
    Revanth rebuffs KCR, says KLIP did not get state cabinet approval
    Jun 19, 2025 · Chief Minister A Revanth Reddy has said that the Kaleshwaram project has not got the approval of the state cabinet during the BRS government.Missing: TRS | Show results with:TRS
  19. [19]
    Kaleshwaram Project: Leaked Report Holds KCR Accountable for ...
    Aug 4, 2025 · The Commission reportedly found that the project was initiated without Cabinet approval and concluded that KCR had taken unilateral decisions ...Missing: TRS | Show results with:TRS
  20. [20]
    Who is responsible for Kaleshwaram project debacle - Facebook
    Sep 14, 2022 · The loans were approved with the blessings of BJP central government. The author Biksham Gujja, the water management expert recommends the ...
  21. [21]
    World's largest multi-stage lift irrigation project ready for launch in ...
    Jun 21, 2019 · The project will be inaugurated with three Chief Ministers and the Governor participating in a series of programmes at the project site in ...
  22. [22]
    Kaleshwaram Lift Irrigation Project - Wikipedia
    Assuming the project irrigates about 15 lakh acres, the electricity cost for irrigation is about Rs. 46,666 per acre per year. The chief minister has said ...Project details · New reservoirs · Gravity Canals & Tunnels for... · Project EconomicsMissing: specifications | Show results with:specifications
  23. [23]
    'KCR to blame for Kaleshwaram project lapses': Panel finds ...
    Sep 1, 2025 · A commission led by Justice (retd) PC Ghose has criticized former Telangana CM KCR for alleged irregularities in the Kaleshwaram Lift IrrigationMissing: KLIP TRS
  24. [24]
    Ghose Commission holds KCR directly responsible for irregularities ...
    Aug 4, 2025 · Ghose Commission holds KCR directly responsible for irregularities in Kaleshwaram lift irrigation project ... RSS ban row: Karnataka Cabinet ...<|separator|>
  25. [25]
    Kaleshwaram under CBI lens: Why Revanth Reddy's stand matters ...
    Sep 1, 2025 · Revanth Reddy rose in the Assembly past midnight on September 1 and declared a CBI probe into the Kaleshwaram Lift Irrigation Project (KLIS), ...
  26. [26]
    Kaleshwaram Lift Irrigation Project: Legal, Political Storm Engulfs ...
    Aug 20, 2025 · With structural flaws, massive debt, and political turbulence converging, the project threatens not just the state's finances, but also public ...
  27. [27]
    Details of Kaleshwaram Lift Irrigation Project - ResearchGate
    Project is aimed at lifting 195TMC of water to an altitude of 450m over a distance of about 110km, with 20 pumping stations located at varying altitudes.
  28. [28]
    World's largest water pump house begins operation in Telangana
    Aug 12, 2019 · Lakshmipur pump house, a key component of Kaleshwaram Lift Irrigation Project (KLIP) and claimed to be the world's largest pump house, has successfully ...
  29. [29]
    A Historical Accomplishment in Kaleshwaram Project - PR Newswire
    Mar 16, 2021 · The Laxmi, Saraswathi and Parvathi pump houses have 43 machines with a capacity of 40 MW each. These Link-1 pump houses established with 1720 MW ...Missing: Lakshmi details
  30. [30]
    Gayatri Pumphouse Kaleshwaram - Meil
    The machines pump the water to a static height of 118 metres. The power consumed by this pump house is much higher than the power generated in the Srisailam or ...
  31. [31]
    MEIL constructs the largest lift irrigation marvel
    Jun 20, 2019 · The Package-8 pumping station can lift 3 TMCs of water per day. It is constructed 330 meters below the ground and is the only one consisting of ...<|separator|>
  32. [32]
    World's largest multi-stage water pumping stations get ABB's support ...
    Dec 31, 2023 · The Kaleshwaram Lift Irrigation System, which is the world's largest multi-stage lift irrigation project, is designed to end the water woes by ...
  33. [33]
    [PDF] Engineering Geological Investigations and Assessments of Support ...
    Dec 17, 2022 · Kaleshwaram lift irrigation scheme is divided into seven links and 28 packages to complete the project as per the given schedule. Package-6 of ...
  34. [34]
    KCR inaugurates mega Kaleshwaram multi-purpose irrigation project
    Jun 21, 2019 · The first phase of Telangana's Kaleshwaram Lift Irrigation Project was inaugurated on Friday by Chief Minister K Chandrasekhar Rao.
  35. [35]
    MEIL completes work on mega Kaleshwaram lift irrigation project in ...
    Jun 20, 2019 · All the civil and electro-mechanical works in Medigadda to Mid-Maneru link-1 and link-2 have been completed. The company, an industry leader ...
  36. [36]
    A historical accomplishment in Kaleshwaram Project
    Mar 16, 2021 · The world's biggest underground pump house, the Gayatri, is in Link-2, package-8. MEIL commenced this gigantic pump house on 11th August 2019 ...
  37. [37]
    Telangana: Kaleshwaram project is operational again
    Jul 14, 2023 · The project was completed in phases – the Lakshmi barrage was completed in 2019, followed by Saraswati in 2020 and Paravati (Sundilla) in the ...Missing: milestones timeline
  38. [38]
    Medigadda Pumphouse (KLIP) - Meil
    The company installed 12 machines in Medigadda barrage's Lakshmi pump house, 12 machines in the Annaram ... Sundilla's Parvati pump house, and seven machines ...
  39. [39]
    Package - 6 - Navayuga Engineering Company
    The Package-6 of the 'Kaleshwaram Project' is a lift irrigation project that envisages the lifting of 146.24 tmc of water with a total discharge capacity of ...
  40. [40]
    Kaleshwaram scam: Action advised against 57 engineers, L&T JV
    Jun 3, 2025 · It has also recommended action against the contractor, L&T-PES JV, including recovery of the cost of replacing Block-7 of the Medigadda barrage.
  41. [41]
    Medigadda Collapse: KCR's Hands-On Decisions Likely Cause
    Mar 3, 2024 · Apparent plans to inaugurate the barrage in June by Chandrashekar Rao. It was inaugurated on June 21, 2019 by the then Chief Minister who also ...
  42. [42]
    Bigger KLIS aided contractors - Deccan Chronicle
    Jan 10, 2024 · ( Source : Deccan Chronicle. ) Pranahita river KLIS central water commission Megha Engineering and Infrastructure Limited Kaleshwaram lift ...
  43. [43]
    Auditor Report Says Telangana's Kaleshwaram Project ... - NDTV
    Feb 16, 2024 · The Comptroller and Auditor General has come out with a damning report on Telangana's Kaleshwaram project, which says it was economically unviable from the ...Missing: implementation issues
  44. [44]
    'It's unviable, will bleed Telangana': CAG damns Kaleshwaram
    Feb 16, 2024 · The report disproved of the project benefits as claimed by the previous BRS govt and said the cost was likely to exceed ₹1.47 lakh crore. “For ...Missing: implementation | Show results with:implementation
  45. [45]
    Telangana's Kaleshwaram Irrigation Project Economically Unviable
    Feb 17, 2024 · Even with the understated project cost of Rs 81,911.01 crore, benefit-cost ratio works out to be 0.75. Considering the latest likely project ...
  46. [46]
    Sinking of Medigadda piers forces Irrigation department to examine ...
    Oct 28, 2023 · The official explained that the design of barrages would be such that all blocks would act independently and any damage to a block would not ...
  47. [47]
    Defects detected in 2019, non-correction led to sinking of ...
    Jan 25, 2025 · Not rectifying the defects, which were found back in 2019, resulted in the sinking of Medigadda piers in 2023, said Larsen and Toubro (L&T) Project Director MV ...
  48. [48]
    Medigadda dam of Kaleshwaram project in Telangana damaged in ...
    Oct 24, 2023 · The Medigadda barrage, which is the first barrage of the KLIP, was designed to withstand 28.25 lakh cusecs (cubic feet per second) of flow and ...Missing: specifications | Show results with:specifications
  49. [49]
    CAG Report on Kaleshwaram Nails Previous BRS Govt on Every ...
    Feb 15, 2024 · Kaleshwaram Lift Irrigation Scheme: CAG report reveals financial mismanagement, design flaws, and unanswered queries by the BRS government.Missing: implementation | Show results with:implementation
  50. [50]
    Telangana Hands Over Kaleshwaram Project Irregularities Probe to ...
    Sep 2, 2025 · The Telangana government has ordered a CBI probe into alleged corruption, fund siphoning, and construction lapses in the Kaleshwaram ...Missing: implementation challenges
  51. [51]
    KLIS: Re-engineering Quadrupled Project Cost, Says CAG
    Jan 11, 2024 · ( Source : Deccan Chronicle. ) Kaleshwaram Lift Irrigation Project (KLIP) pranahita-chevella project Kaleshwaram project Megha Engineering and ...
  52. [52]
    CAG flags soaring costs, planning flaws in Telangana's ...
    Feb 15, 2024 · A file photo of the Kaleshwaram lift irrigation project (Express) ... Even with the estimated project cost of Rs 81 thousand crore, BCR works out ...
  53. [53]
  54. [54]
    Kaleshwaram loans at risk of becoming NPAs
    Jun 27, 2025 · Kaleshwaram loans at risk of becoming NPAs ... The REC had sanctioned Rs 30,536.08 crore to KIPCL. In October 2024, the state government had ...
  55. [55]
    Revanth-led Telangana govt to hand over Kaleshwaram project ...
    Sep 1, 2025 · “We have paid Rs 19,878 crore as principal amount for the loans they took so far. Rs 29,956 crore was paid as interest to various banks.
  56. [56]
    Govt seeks loan restructuring for KLIS amid interest burden
    Feb 7, 2025 · The govt is paying about Rs 950 crore towards interest and principal amount for approximately Rs 61,000 crore from the Kaleshwaram corporation ...
  57. [57]
    No, Telangana government did not raise any loans from the World ...
    Mar 2, 2022 · Further, the post alludes that loans for the construction of the Kaleshwaram Lift Irrigation project were also raised from the World Bank.<|control11|><|separator|>
  58. [58]
    Funding rules broken, designs delayed, KLIS probe told
    Feb 27, 2025 · During the cross examination on Thursday, it emerged that there were likely serious omissions right from the design stage ending with the ...Missing: overruns | Show results with:overruns
  59. [59]
    [PDF] GOVERNMENT OF INDIA MINISTRY OF FINANCE DEPARTMENT ...
    Mar 17, 2025 · restructuring of loans raised by the Special Purpose Vehicles (SPVs) that are serviced from the State Consolidated Fund under Kaleshwaram Lift ...
  60. [60]
    Before Deciding on Next Steps for the Kaleshwaram Project, a ...
    Jan 17, 2024 · This mega project is reported to have cost Rs 1,20,000 crores, most of it on commercial loans from banks. Though the project is supposed to have ...Missing: specifications | Show results with:specifications<|separator|>
  61. [61]
    Kaleshwaram Lift Irrigation Project set to emerge as Hyderabad's ...
    Sep 7, 2025 · Inaugurated in February 2022, the Mallanna Sagar reservoir, built at a cost of Rs.6,805 crore between Thoguta and Kondapak in Siddipet district, ...
  62. [62]
    Telangana's troubled Kaleshwaram project | A barrage of woes
    Feb 23, 2024 · Sources in L&T, the construction agency for Medigadda barrage, say its engineers had noticed damage to the cement 'wearing coat' and concrete ...
  63. [63]
    CAG calls Kaleshwaram project economically unviable - ThePrint
    Feb 16, 2024 · CAG report tabled in Telangana assembly says cost of lift irrigation project likely to exceed Rs 1,47,427 crore, as against Rs 81,911 crore ...Missing: achieved | Show results with:achieved
  64. [64]
    Geospatial assessment of cropping pattern shifts and their impact on ...
    Oct 10, 2024 · Efficient monitoring of crop water requirements is crucial for assessing the impacts of major irrigation projects, such as the Kaleshwaram ...<|separator|>
  65. [65]
    Satellite-based monitoring of crop intensity changes in kaleshwaram ...
    The primary objective of this ambitious project is to provide irrigation to around 18.75 lakh hectares of land in drought-prone areas of Telangana State, ...
  66. [66]
    [PDF] Study on the impact of major irrigation projects on rice cultivation in ...
    The Kaleshwaram Lift Irrigation Project, which became operational in 2019, significantly increased the availability of water for agriculture in Telangana, ...
  67. [67]
    Only 44,570 acres to be irrigated under Kaleshwaram Lift Irrigation ...
    Jul 17, 2025 · Only 44,570 acres will be irrigated under the Kaleshwaram Lift Irrigation Scheme (KLIS) this Kharif season, all due to lack of sufficient water.
  68. [68]
    Average groundwater table up in Telangana, but red zone of ...
    May 9, 2025 · Telangana's water table rises due to 22% excess rainfall, but number of areas where water levels dropped below 20 metres has increased.
  69. [69]
    [PDF] EXECUTIVE SUMMARY FOR THE PROPOSED KALESHWARAM ...
    2.5 Drainage​​ Due to the proposed project, there will be recharging to the groundwater that may create water logging and drainage problem in the command area. ...
  70. [70]
    How Telangana's Age-Old Thirst Was Quenched - The Wire
    Mar 3, 2023 · The heart of water security in Telangana is Project Bhagiratha for drinking water, and the Kaleshwaram lift irrigation project.
  71. [71]
    Kaleshwaram Lift Irrigation Project: Telangana's Feat
    The Kaleshwaram Lift Irrigation Project, the world's largest of its kind, providing water for irrigation, drinking, and industrial use across Telangana.
  72. [72]
    Industry banking on Kaleshwaram project - Deccan Chronicle
    Jun 28, 2018 · “The government has allocated 16 tmc ft water for industrial requirements. Link-2 will ensure lifting Yellampally water to mid-Manair reservoir, ...
  73. [73]
    Crisis at Kaleshwaram — why Telangana's massive irrigation project ...
    May 5, 2025 · Thirty TMC is for the Hyderabad municipal area, 16 TMC for miscellaneous industrial uses, and 10 TMC is meant to provide drinking water to ...
  74. [74]
    Hyderabad to get additional drinking water as government clears ...
    Aug 7, 2024 · The project will entail an investment of ₹5,560 crore. It proposes diverting water to Hyderabad from Mallanna Sagar in Siddipet district, part ...
  75. [75]
    Kaleshwaram project afforestation in full swing - The Hindu
    Jul 21, 2018 · Kaleshwaram project afforestation in full swing. Plantation drive in 7 districts to cover 2,653.121 hectares of non-forest lands. Published - ...
  76. [76]
    [PDF] proposed terms of reference - environmental clearance
    ... Project are being constructed, one at Annaram (v) and the other at. Sundilla (V) and convey water by pumping towards upstream side from Medigadda barrage to ...<|separator|>
  77. [77]
    Kaleshwaram Lift Irrigation Project (KLIP) for UPSC Aspirant
    Location: Telangana, utilizing Godavari River water. · Key Features: Lift irrigation, barrages, pump houses, reservoirs, pipeline network. · Objectives: ...Missing: specifications | Show results with:specifications
  78. [78]
    NGT red-flags Kaleshwaram project: Green clearance was in ...
    Oct 21, 2020 · Reddit. NGT red-flags Kaleshwaram project: Green clearance was in violation of law, halt Kaleshwaram Lift Irrigation project. (File).
  79. [79]
    Kaleshwaram irrigation project got environmental clearance 'ex post ...
    Oct 20, 2020 · Kaleshwaram irrigation project got environmental clearance 'ex post facto' in violation of law: NGT ... The green panel directed the Ministry of ...Missing: criticisms | Show results with:criticisms
  80. [80]
    Environmental clearance to Kaleshwaram given in violation of law
    Oct 20, 2020 · Environmental clearance to Kaleshwaram given in violation of law: NGT. Tribunal directs Centre to appoint expert panel on remedial measures.
  81. [81]
    Environmental Clearance to Kaleshwaram Project Invalid - Drishti IAS
    Oct 21, 2020 · Issues in the Project: ... Thus, the EC was ex post facto, in violation of the Environmental Impact Assessment (EIA) Notification, 2006.
  82. [82]
    Unprecedented flood in Godavari damages Kaleshwaram pump ...
    Jul 15, 2022 · Unprecedented flood in Godavari damages Kaleshwaram pump houses. Two key pump houses of the project submerged; Uncertainty over lifting water ...Missing: risks | Show results with:risks
  83. [83]
    ExpertSpeak: Here are four points you should know about ...
    Jul 20, 2022 · The unprecedented rains in Telangana last week led to flooding of two pump houses of the Kaleshwaram Lift Irrigation Scheme (KLIS). · Bad design ...Missing: environmental risks
  84. [84]
    Fearing Flooding, Telangana Farmers Demand Reduced Capacity ...
    It is estimated to submerge more than 3,400 acres of land, of which 1,600 acres belong to farmers. The reservoir was proposed in 2016 as part of the Kaleshwaram ...
  85. [85]
    Kaleshwaram lift irrigation project opens a barrage of woes in border ...
    Jan 31, 2023 · Lands submerged and livelihood lost, farmers in 11 villages in Gadchiroli district fight for better compensation.
  86. [86]
    [PDF] minutes of the environmental public hearing for
    EIA and EMP study that was carried out for Kaleshwaram project shows that environmental secondary data collected within 10 kms radius of the project site of ...
  87. [87]
    Telangana projects under lens after SC verdict: Environmentalists
    May 21, 2025 · Environmentalists warn that major irrigation and mining projects in Telangana, including the multi-crore Kaleshwaram Lift Irrigation Scheme, could come under ...Missing: criticisms | Show results with:criticisms
  88. [88]
    Appearing Before Probe Panel, KCR Says Engineers Responsible ...
    Jun 11, 2025 · K. Chandrashekar Rao on Wednesday (June 11) appeared before a judicial inquiry commission here probing allegations of corruption and poor quality of ...Missing: overruns | Show results with:overruns
  89. [89]
    Dumping Pranahitha plan for KLIS KCR blunder | Hyderabad News
    Mar 1, 2024 · Re-engineering of Pranahitha-Chevella project and taking up Kaleshwaram Lift Irrigation Scheme (KLIS) was a blunder by former CM K Chandrasekhar Rao-led BRS ...
  90. [90]
    Design Flaws Exposed in Kaleshwaram Barrages: IIT Report
    Jan 29, 2025 · All developed problems including leaks, seepages, forming of cavities under their foundations, and in the case of Medigadda, partial sinking of Block 7 of the ...
  91. [91]
  92. [92]
    NDSA report describes Medigadda debacle as the worst man-made ...
    Apr 30, 2025 · On 21 October 2023, the Kaleshwaram project faced a serious setback. Pillar No. 20 in Block 7 of the Medigadda Barrage sank, sending alarm bells ...
  93. [93]
    NDSA Flags Irreversible Damage to KLIS Medigadda Barrage
    May 7, 2025 · Block 7 of the Medigadda barrage has suffered irreversible damage, with cracked and displaced piers and rafts, rendering it unfit for further gate operations.
  94. [94]
    Defects in design may have damaged Sundilla barrage
    Jan 24, 2025 · NEC director Y Ramesh said defects in the designs might have caused damage to the piers of the Sundilla barrage.
  95. [95]
    KLIS design flaws led to problems: Barrage contractor
    Jan 24, 2025 · Sundilla completed in Dec 2021, launched for use in 2019. KLIS design flaws led to problems: Barrage contractor. x. Work on the Sundilla barrage ...
  96. [96]
    Kaleshwaram Project Barrages to Undergo Major Repairs After ...
    Oct 6, 2025 · Its final report, submitted in April 2025, identified major flaws in both the design and construction of all three barrages. Findings Of ...<|separator|>
  97. [97]
    Explainer: How Telangana's dream irrigation project turned into a Rs ...
    Sep 1, 2025 · The Commission concluded that Kaleshwaram was marred by irregularities, illegalities, and misuse of public funds. It called the project a “ ...<|separator|>
  98. [98]
    KCR responsible for 'irregularities, bad planning and execution' of ...
    Aug 5, 2025 · KCR responsible for 'irregularities, bad planning and execution' of Kaleshwaram project: Inquiry commission. The one-man Justice P C Ghose ...Missing: motivations | Show results with:motivations
  99. [99]
    Why Kaleshwaram judicial probe blames KCR, Harish Rao, Eatala ...
    Aug 5, 2025 · The judicial commission formed to probe irregularities in the Kaleshwaram project recommended action against several bureaucrats and ...<|separator|>
  100. [100]
    Telangana Vigilance Commission approves proposal to attach ...
    Oct 14, 2025 · The move is a part of the ongoing probe into alleged irregularities and corruption in the execution of the multi crore Kaleshwaram project.
  101. [101]
    Telangana government orders CBI probe into Kaleshwaram project ...
    Sep 1, 2025 · Telangana CM Revanth Reddy hands over Kaleshwaram project irregularities to CBI after Ghose Commission report, alleging corruption and ...
  102. [102]
    PC Ghose Commission holds KCR responsible for irregularities in ...
    Aug 4, 2025 · The BRS denied allegations of corruption in the Kaleshwaram project and termed the summons to KCR an act of political vendetta by the government ...
  103. [103]
    Kaleshwaram report raises questions, critics respond with facts
    Aug 5, 2025 · BRS sees political motives in Congress govt's SIT, selective use of Justice Ghose report ... The KCR government raised loans to construct projects ...
  104. [104]
    Kaleshwaram, biggest national scam - Telangana - The Hindu
    Oct 22, 2022 · YSR Telangana Party president YS Sharmila alleged that Kaleshwaram Lift Irrigation Scheme (KILS) was the biggest scam in India that took place in recent times.Missing: details | Show results with:details
  105. [105]
    Telangana government orders CBI probe into Kaleshwaram project ...
    Sep 1, 2025 · Reddy accused the previous BRS regime of swindling public money through the project. He said the Kaleshwaram Corporation borrowed 85 thousand ...Missing: scam | Show results with:scam
  106. [106]
    Kaleshwaram: ACB takes up probe, as CBI dodges - Great Andhra
    Sep 30, 2025 · ... project, the state government is learnt to have handed over the case to Anti-Corruption Bureau to look into the corruption angle in the case.
  107. [107]
    Kaleshwaram project probe: KCR, ex-minister Harish Rao seek ...
    Sep 1, 2025 · KCR Kaleshwaram notice, Telangana irrigation project probe, Kaleshwaram lift irrigation scam, K Chandrashekar Former Telangana chief minister K ...Missing: details | Show results with:details
  108. [108]
    Kaleshwaram probe: Less about dams, more about political games?
    Sep 3, 2025 · Kaleshwaram probe: Less about dams, more about political games? Political circles are abuzz with theories about Revanth Reddy's motivations.
  109. [109]
    Ghose Commission Timeline - The Hans India
    May 21, 2025 · The one-man commission headed by Justice PC Ghose was constituted on March 14, 2024, to probe alleged corruption into Kaleshwaram project.
  110. [110]
    Ghose Commission finds former Chief Minister KCR accountable for ...
    Aug 31, 2025 · The 2022 CAG report had indicated that project cost would cross ₹1.27 lakh crore and later it was ₹1.47 lakh crore. The Minister stated that ...
  111. [111]
    Telangana govt to hand over Kaleshwaram project irregularities ...
    Sep 1, 2025 · The Ghose Commission of Inquiry submitted its report to the government on July 31, 2025. The state cabinet approved it on August 4, 2025. The ...
  112. [112]
    K Chandrasekhar Rao, Harish ask Telangana HC to suspend report ...
    Aug 20, 2025 · K Chandrasekhar Rao, Harish ask Telangana HC to suspend report on KLIS. They further alleged that the government had repeatedly publicised the ...
  113. [113]
    Telangana CM announces CBI inquiry into Kaleshwaram project ...
    Aug 31, 2025 · Hyderabad: Congress government in Telangana has decided to order a CBI investigation into the Kaleshwaram project controversy.<|control11|><|separator|>
  114. [114]
    Telangana Govt. Issues G.O. Entrusting Kaleshwaram Project Probe ...
    Sep 2, 2025 · Hyderabad: The State government entrusted the investigation of Kaleshwaram Lift Irrigation Project to the Central Bureau of Investigation (CBI).
  115. [115]
    Telangana HC grants interim relief to KCR, ex-minister Harish Rao ...
    Sep 2, 2025 · Telangana HC grants interim relief to KCR, ex-minister Harish Rao in Kaleshwaram project probe. The CBI probe into the execution of the ...
  116. [116]
    BJP demands expansion of CBI probe into KLIP, seeks changes in ...
    Sep 9, 2025 · BJP MLA accuses Congress government of limiting CBI probe into Kaleshwaram project, demands comprehensive investigation or move to Supreme Court<|separator|>
  117. [117]
    Telangana government orders CBI probe into Kaleshwaram project ...
    Sep 1, 2025 · Telangana Chief Minister Revanth Reddy told the Assembly that the Kaleshwaram Lift Irrigation Project ... alleged corruption, would now be handed
  118. [118]
    CBI begins scrutiny of Kaleshwaram project documents after ...
    Sep 26, 2025 · On September 1, the state government had requested the Union government to order a CBI probe into the alleged irregularities.
  119. [119]
    Ghose Commission of Inquiry on Kaleshwaram row submits report
    Jul 31, 2025 · Justice P.C. Ghose hands over report to Principal Secy. Irrigation Rahul Bojja, who in turn, submits report to CS. Updated - July 31, 2025 ...
  120. [120]
    Telangana govt initiates move for restoration of Kaleshwaram ...
    Oct 1, 2025 · The Commission headed by the former judge of the Supreme Court was constituted on March 14, 2024 to probe the irregularities in planning, ...Missing: ongoing | Show results with:ongoing<|separator|>
  121. [121]
    Smita Sabharwal Alleges 'Defamatory Remarks', Moves High Court ...
    Sep 24, 2025 · ... Ghose Commission's report on the Kaleshwaram Lift Irrigation Project made damaging observations against her without granting a fair hearing.
  122. [122]
    Kaleshwaram Lift Irrigation Project 2025 - ExamGuru
    Rating 4.9 (9,673) Aug 12, 2025 · Utilizes a canal network spanning over 1,800 km (KLIP canal network length). · Aims to irrigate around 16 lakh acres across 13 districts in ...Missing: specifications | Show results with:specifications
  123. [123]
    Govt. selectively allowing CBI probe into KLIP irregularities: BJP
    Sep 4, 2025 · Ramchander Rao accused the Congress government of selectively permitting a CBI probe into the “irregularities and corruption” in the ...<|separator|>
  124. [124]
    Kaleshwaram: 'World's Largest' Irrigation Dream Turns into Ruin
    Sep 12, 2025 · Once hailed as Telangana's pride, the Kaleshwaram Lift Irrigation Project now faces collapsed structures, spiraling debt, and a CBI probe ...
  125. [125]
    Telangana relaxes withdrawal of general consent to CBI for ...
    Sep 2, 2025 · Telangana relaxes withdrawal of general consent to CBI for Kaleshwaram probe. BY India News Newsdesk; September 2, 2025; 0 COMMENTS. Hyderabad, ...
  126. [126]
    Kaleshwaram probe: Revanth Reddy's ride to replace KCR's legacy
    Sep 6, 2025 · For Revanth, the probe serves a dual purpose: Exposing corruption and undermining the very foundation of KCR's claim to have transformed ...