The Circle Line (CCL) is a fully automated, underground medium-capacity mass rapid transit line forming an orbital route around Singapore's central districts, spanning approximately 35.5 kilometres with 30 stations that interconnect the North-South, East-West, and North East Lines to enhance circumferential travel efficiency. Operated by SMRT Corporation under oversight from the Land Transport Authority, the line utilises driverless trains equipped with advanced signalling for high-frequency service, serving over 200,000 daily passengers by alleviating congestion on radial routes. Opened in five stages from May 2009 to October 2011, it represents a key expansion of Singapore's rail network, prioritising seamless transfers at 11 interchange stations and integration with bus services for multimodal connectivity. A pending Circle Line 6 extension, adding three stations between HarbourFront and Marina Bay to close the full loop, is slated for completion in 2026, incorporating 23 new trains to handle projected demand growth amid urban densification.

History

Initial Proposals and Planning (1990s–2000s)

Proposals for the Circle Line originated in the 1990s as part of efforts to expand Singapore's Mass Rapid Transit (MRT) network amid rising public transport demand and overcrowding on the North South and East West Lines. The line was envisioned as an orbital route to interconnect existing radial lines, bypass congested city-centre interchanges such as Raffles Place, City Hall, and Dhoby Ghaut, and facilitate faster travel between suburban areas in the north, east, and west of the island. Initially designated the Marina Line, the project focused on linking the emerging Marina Bay district with other growth areas, including provisions for underground sections to serve dense urban zones. By the late , planning had advanced to outline a comprehensive loop that would enhance subregional hubs and reduce reliance on through-city journeys. In 2000, the (LTA) initiated the Marina Line International in collaboration with the Singapore Institute of Architects, targeting innovative designs for stations like Bras Basah and to integrate with surrounding urban landscapes. The line's development was structured into five stages to manage construction complexity, with initial targets setting Stage 1 operations for 2006, though later adjusted due to engineering challenges. This phased approach aimed to progressively distribute commuter loads and improve network resilience.

Construction Phases and Challenges

The MRT3 Circle Line project entered its pre-construction phase with final approval of the railway scheme by the Malaysian Transport Ministry on July 17, 2025, initiating land acquisition processes targeted for completion by the end of 2026. This phase involves detailed finalization, community engagement, and securing approximately 32% fewer land plots than earlier estimates through route optimizations, reducing the scope of acquisitions in urban . Construction proper is projected to commence in 2027, following land handover, with the 51.6 km —comprising a mix of elevated and underground sections—divided into segments to facilitate progressive development and minimize prolonged disruptions. Implementation is structured for phased openings to align with ridership demands and fiscal pacing, with initial segments potentially operational by late and full network completion by 2032. The line's 31 stations and 10 interchanges necessitate coordinated tunneling and elevated works, drawing on lessons from prior lines where elevated sections reduced costs but amplified surface-level interference. Total estimated costs exceed RM45 billion, funding a driverless system integrated with existing networks. Key challenges include protracted land acquisition in densely built environments, where negotiations with private owners and relocations have historically delayed similar projects by years due to compensation disputes and legal appeals. coordination poses further hurdles, as the perimeter alignment traverses hubs, requiring synchronization with agencies like Prasarana and councils to avert during peak —exacerbated by the need for 24 stations amid Kuala Lumpur's congested subsurface utilities. Prior shelving in under fiscal highlighted vulnerability to budgetary shifts, though recent optimizations aim to curb overruns by prioritizing elevated over extensive tunneling. Corp has emphasized proactive consultations to address these, including public inspections initiated in 2024 for alignment feedback.

Phased Openings (2009–2011)

The Circle Line's initial passenger services began with the opening of Stage 3 on 28 May 2009, covering the 5.7-kilometre segment from Bartley to Marymount stations. This phase included four stations—Bartley (CC5), (CC14, interchange with North East Line), Lorong Chuan (CC13), and Marymount (CC16)—and marked the first operational use of the fully automated, driverless medium-capacity line equipped with trains. The segment operated as a shuttle service, providing connectivity to residential areas in the Bishan and regions while testing the line's systems ahead of further expansions. Stages 1 and 2 opened simultaneously on 17 April 2010, extending services northward from Dhoby Ghaut to Bartley and forming a continuous route from Dhoby Ghaut (CC1, interchange with North South and North East Lines) through central districts. The 7.6-kilometre addition incorporated six new stations: Bras Basah (CC2), Esplanade (CC3), Promenade (CC4, interchange with Downtown Line), Nicoll Highway (CC5, later renumbered), Little India (CC6, interchange with North South Line), and Farrer Park (CC7). This phase improved access to cultural and commercial hubs like the Civic District and Marina Bay, with peak-hour frequencies reaching every 2.5 minutes to accommodate growing demand. On 8 2011, Stages 4 and 5 commenced operations, linking Marymount to HarbourFront and creating a 21.6-kilometre horseshoe-shaped network spanning 21 stations in total up to that point. The 11.3-kilometre extension featured eight stations: Caldecott (CC17), Botanic Gardens (CC19, interchange with future Thomson-East Coast Line), Stevens (CC20, later added), Farrer Road (CC21), Holland Village (CC23), (CC23), (CC22, interchange with East West Line), and HarbourFront (CC29, interchange with North East Line and Sentosa Express). The opening, officiated by Transport Minister , followed extensive testing and an emergency exercise in September 2011 to ensure safety on the underground and elevated sections. These phases collectively boosted the line's daily ridership to over 200,000 passengers by late 2011, alleviating pressure on parallel North South Line services.

Route Description

Network Overview and Alignment

The MRT Circle Line, designated as MRT3, is a planned orbital mass rapid transit line intended to encircle the perimeter of , serving as the final link to complete the Klang Valley's integrated urban rail network. Spanning 50.8 kilometers in a circular , it aims to enhance circumferential for commuters in suburban and peripheral areas, reducing reliance on radial routes through the center and improving overall mobility for a growing population. The line's design prioritizes integration with existing systems, including the , LRT, , and , through 10 dedicated interchange stations that facilitate seamless transfers. The alignment follows an outer loop around Kuala Lumpur's urban core, traversing key corridors along major highways and residential zones to connect underserved peripheral regions such as the northern, eastern, southern, and western suburbs. It comprises approximately 39 kilometers of elevated track and 12 kilometers of underground sections, with a total of 32 planned stations—22 elevated and 10 underground—to minimize land acquisition impacts while navigating dense built-up areas. This configuration supports efficient orbital travel, enabling shorter paths to employment hubs, commercial districts, and transport nodes without converging on central Kuala Lumpur. Interchanges are strategically located to align with high-traffic points on the existing network, such as connections to the MRT Putrajaya Line, LRT Kelana Jaya and Ampang Lines, and KTM services, promoting multimodal access and load distribution across the system. The final railway scheme, approved in July 2025 following consultations with agencies including the Land Public Transport Agency (APAD), incorporates public feedback on alignment adjustments to optimize coverage and reduce disruptions. This orbital structure addresses longstanding gaps in peripheral connectivity, potentially easing congestion on inner-city lines by diverting orbital demand.

Stations and Interchanges

The MRT Circle Line, designated as MRT3, is planned to include 32 stations along its 51-kilometer orbital alignment, consisting of 22 elevated stations, 7 underground stations, and 3 provisional stations. These stations aim to serve densely populated peripheral areas of Kuala Lumpur, such as , , , Ampang, and , while integrating with the existing network through 10 dedicated interchange and connecting stations. This design facilitates seamless transfers to Lines 1 and 2, LRT Kelana Jaya, Ampang, and Sri Petaling lines, the , and services, reducing reliance on radial routes into the city center. Interchange stations are strategically located to bridge gaps in the current system, with connections verified during public inspections in 2024. For instance, Bukit Kiara Selatan will allow transfers to the Kajang Line at a new station, while provides multi-modal access to the LRT Ampang and Sri Petaling Lines, , and Putrajaya Line. Similarly, Kuchai and Ampang enable switches to and LRT services, respectively, supporting circumferential travel without entering central . The following table summarizes the planned interchange stations and their connections, based on alignments detailed in 2024-2025 project updates:
StationConnected Lines/Services
Bukit Kiara SelatanMRT Kajang Line
LRT Ampang/Sri Petaling Lines, ,
AmpangLRT Ampang Line
Salak SelatanLRT Sri Petaling Line
Kuchai
Pantai DalamKTM Tanjung Malim–Port Klang Line (connecting)
Universiti Malaya (connecting)
MRT Kajang Line (new station)
Non-interchange stations, such as , , and , will primarily serve local access via elevated or underground platforms, with provisional stations like Bukit Kiara subject to final alignment adjustments during land acquisition phases approved in July 2025.

Technical Specifications

Infrastructure and Track Details

The MRT Circle Line, designated as MRT3, is planned as a 51-kilometer orbital rail alignment encircling the perimeter of , integrating with existing , LRT, KTM, and networks through 10 interchange stations. The line will comprise 31 stations in total, with 24 elevated and 7 underground, facilitating connectivity to underserved areas and reducing radial travel times across the . Infrastructure will consist of approximately 40 kilometers of elevated track and 11 kilometers of underground sections, employing standard construction techniques for urban mass rapid transit to minimize surface disruption. The alignment avoids penetrating the central business district, prioritizing perimeter coverage to enhance orbital mobility. Depots and maintenance facilities are incorporated into the design, though specific locations remain under finalization as of the project's approval in July 2025. Technical features include full for operations, aligning with the driverless systems of prior lines to optimize and . Trackwork will support high-frequency service, with integration into the broader transit ecosystem via shared standards for .

Rolling Stock and

The Circle Line is planned as a fully automated and driverless rail system, marking it as the fifth such line in the 's urban transit network. This goA-train operations will rely on (CBTC) signaling for precise movement authorization and at all stations to enhance safety in the absence of onboard crew. Specific details, including manufacturer and configuration, remain undetermined pending future tenders after commencement. Trains are expected to consist of four cars each, with a per-train capacity of up to 750 passengers, supporting a peak-hour peak-direction throughput of 25,000 passengers. Operational speeds are targeted at 100 km/h, aligning with standards of comparable Malaysian lines to facilitate efficient orbital circulation. Depots at Kampung Puah and will handle maintenance and stabling for the fleet.

Operations and Service

Daily Operations and Timetables

As of October 2025, the MRT Circle Line remains under development, with land acquisition targeted for completion by the end of 2026, construction commencement in 2027, and full operations projected no earlier than 2032. No daily train services or timetables are in place, as the 51.6 km orbital line has not entered . Planned operations envision a fully automated, driverless system operating in a loop, with a projected end-to-end journey time of 73 minutes for the full circuit. The line is designed for peak-hour capacities of up to 25,000 passengers per hour per direction, using three-car trains accommodating around 750 passengers each. Service frequencies have not been finalized in public planning documents, though they are expected to mirror headways on existing MRT lines such as the , ranging from 3 to 10 minutes during peak periods. Anticipated daily hours align with MRT standards, with stations opening at 6:00 AM and services running until approximately midnight, subject to adjustments for demand and integration with radial lines at 10 interchange points. Feeder bus connections, managed by , will supplement access once operational, similar to current MRT feeder networks. Delays in prior MRT projects, including cost overruns and land issues, suggest potential revisions to these timelines. The MRT Circle Line is engineered to handle a peak capacity of 25,000 passengers per hour per direction, with each train accommodating up to 750 passengers across its 31 stations spanning 50.8 km. This design supports a full loop travel time of approximately 73 minutes, integrating with 10 interchange stations to enhance network-wide throughput. Projections estimate daily ridership at 180,300 passengers upon completion, potentially scaling to 101 million annually by 2060 as increases. These figures assume effective integration with the existing , where the Circle Line's circumferential alignment is intended to redistribute loads from overburdened radial routes like the Kajang and Putrajaya Lines. With construction slated to commence in 2028 and operations by 2032, no empirical ridership data exists as of 2025, precluding observed trends. However, the broader MRT network has consistently underperformed against targets, exemplified by the Kajang Line's average daily load factors ranging from 10.8% to 37.4% between 2017 and 2023, and the achieving only 89,000 daily passengers against a 196,000 target in 2023. Anticipated capacity challenges for the Circle Line stem from systemic issues in the regional transit ecosystem, including insufficient feeder bus connectivity, fragmented that limits last-mile access, and historical underutilization despite infrastructure investments exceeding RM120 billion. Without remedial measures such as enhanced and , the line risks similar shortfalls, potentially straining resources amid rising projections. The project's emphasis on 12 km of underground sections and automated operations aims to mitigate bottlenecks, but realization depends on resolving these extrinsic constraints.

Reliability and Incidents

Major Disruptions and Breakdowns

The MRT Circle Line (MRT3) in has not experienced any major disruptions or breakdowns, as passenger services are not yet operational. The line received final approval from the Ministry of Transport in July 2025, following a public inspection period from September to December 2024, but construction has not commenced, with land acquisition planned for 2026 and full operations targeted for 2032. Prior to approval, the project underwent revisions to address cost overruns and alignment concerns, but no incidents related to infrastructure failures or service interruptions have been reported during planning or preliminary works. The 51.6 km loop, designed to integrate with 10 interchange stations across existing MRT, LRT, and KTM lines, aims to enhance network reliability once built, drawing lessons from disruptions on operational lines like the Kajang and Putrajaya MRT lines, which have faced signalling and power issues unrelated to the Circle Line.

Criticisms of Maintenance and Signaling

Criticisms of practices within the system, which the forthcoming will join, center on recurrent infrastructure failures and inadequate upkeep. A 2020 audit of Line 1 () identified frequent malfunctions and breakdowns that remained unresolved despite ongoing defects liability periods, attributing these to weaknesses in system reliability and operational readiness. Station facilities have also drawn complaints for poor condition, including water leaks from ceilings and non-functional escalators, elevators, and toilets, which undermine passenger experience and suggest lapses in routine preventive . Signaling systems have faced scrutiny for vulnerabilities exposed in operational disruptions. On October 25, 2025, the MRT Putrajaya Line (part of the network) experienced a signaling fault leading to service interruptions, later traced to suspected cable theft that damaged and communication , requiring manual operations and extended repairs. Such incidents highlight gaps in and rapid fault detection for signaling equipment, with critics arguing that inadequate perimeter protection and delayed response exacerbate downtime. Broader concerns about MRT Corp and Prasarana's maintenance regime point to historical crises, including multiple system failures and prolonged station closures—such as 16 stations shuttered for five days—stemming from underinvestment in predictive maintenance and spare parts inventory. While operators have reported improvements, such as reduced breakdowns on integrated lines from 36 incidents in 2023 to fewer in 2024 through targeted upgrades, skeptics contend that these measures fall short of international benchmarks, potentially foreshadowing similar challenges for the Circle Line upon commissioning. These issues are often linked to procurement delays and cost pressures rather than inherent design flaws, though empirical data on post-handover performance remains limited.

Impact and Developments

Economic and Urban Effects

The MRT Circle Line, with an estimated cost of RM31 billion excluding acquisition of RM8.4 billion, is projected to catalyze socio-economic growth in the by enhancing national competitiveness and integrating with existing rail networks. Official assessments from Corp indicate that the project will drive infrastructure-led economic value, including job creation during the multi-year phase starting post-2026 acquisition completion, similar to prior lines that generated thousands of direct and indirect opportunities in , , and operations. Urban rejuvenation is anticipated along the 51.6 km route, particularly through improved orbital connectivity that reduces reliance on radial lines converging at Kuala Lumpur's , thereby alleviating transfer bottlenecks and shortening commutes. The line's 31 stations are expected to spur mixed-use developments and multi-modal hubs, such as in northern , fostering accessibility to underserved peripheral areas and promoting transit-oriented urban expansion. Property market dynamics mirror effects observed from the Sungai Buloh-Kajang (SBK) Line, where proximity to stations within 1.5 km correlated with higher residential prices and transaction volumes, with premiums ranging from 5-15% based on hedonic pricing models using transaction data. For the Circle Line, analysts project analogous uplifts in areas like commercial corridors, enhancing spillover benefits for employment accessibility without entering the core , though actual gains depend on execution and ridership uptake projected at over 20 million annually post-2032 completion. Traffic congestion relief is forecasted through modal shifts, with orbital routing enabling circumferential travel that bypasses city-center chokepoints, potentially reducing vehicle kilometers traveled in line with integrated system enhancements.

Future Extensions and Upgrades

The MRT3 received final railway scheme approval from the Transport Ministry on July 17, 2025, enabling land acquisition to commence immediately, with a target completion by the end of 2026. The project incorporates optimizations such as reduced land requirements, from an initial 1,012 lots to 690, alongside refined station locations and alignments to minimize disruptions. Construction tenders are anticipated to restart by mid-2026 following the lapse of prior extensions. The 51.6 km orbital line will comprise 31 stations—22 elevated and 9 underground—along 40 km of elevated track and 11 km underground, integrating with existing , LRT, KTM, and networks at 10 interchange points to enhance connectivity across densely populated areas. Development is planned in phases, with Phase 1 targeted for operational readiness in 2028 and Phase 2 in 2030, culminating in full service by 2032. No further extensions beyond the approved alignment have been announced, though the design prioritizes orbital relief for radial lines like and . Upgrades to signaling, , and capacity are integrated into the baseline design to align with prior lines, but specific enhancements remain subject to outcomes and reviews post-land acquisition. The estimated is projected to mirror the RM40-50 billion range of previous phases, funded via allocations and potential private partnerships, though fiscal constraints noted in earlier cancellations (2018) underscore risks of delays.

References

  1. [1]
    Circle Line - Singapore - Land Transport Authority (LTA)
    Jun 17, 2025 · The 30-station CCL is a circular rail line linking the North-South, East-West and North East Lines to the city.
  2. [2]
    Circle Line - SGTrains.com
    Spanning 35.7km across 30 stations, the CCL connects major MRT lines ... Stations / Length: 30 stations / 35.7km (currently operational) Dhoby Ghaut ...
  3. [3]
    Circle Line | Land Transport Guru
    The line is currently 35.5 km long with 30 stations, running from Dhoby Ghaut (CC1) to HarbourFront (CC29) via Serangoon. A separate branch line known as the ...Missing: facts | Show results with:facts
  4. [4]
    Rail Network - Land Transport Authority (LTA)
    Jul 4, 2025 · MRT Maps and latest information of our rail network - Circle Line, Downtown Line, North-South and East-West Lines, North East Line and ...Circle Line · Downtown Line · East-West Line · North-South Line
  5. [5]
    [PDF] The Circle Line - Land Transport Authority (LTA)
    The Circle Line (CCL) has added some 33km to our MRT network. As an orbital line, it will shorten journeys by allowing commuters to transfer to other radial ...
  6. [6]
    Circle Line 6 - Singapore - Land Transport Authority (LTA)
    May 5, 2025 · The Circle Line 6 (CCL6) extension will add three stations between HarbourFront and Marina Bay MRT stations, closing the loop for CCL.
  7. [7]
    Mass Rapid Transit (MRT) system - Singapore - Article Detail
    The idea for Singapore's MRT system originated from a concept plan that was based on a 1967 study conducted by the United Nations Development Programme (UNDP) ...
  8. [8]
    MRT3 gets final approval: Land acquisition for 51.6km Circle Line ...
    Jul 17, 2025 · “With today's approval, the land acquisition process can now commence and is targeted for completion by the end of 2026. MRT Corp will be ...Missing: challenges | Show results with:challenges
  9. [9]
    MRT3 Circle Line tenders likely to restart by mid-2026
    Jul 18, 2025 · The re-tender is anticipated due to changes in project alignment and station placements, following a 32% reduction in land plots required for ...<|separator|>
  10. [10]
    MRT 3 may start in 2027, links to petrol subsidy reform
    Nov 27, 2024 · After finalising the alignment, the land acquisition phase will take up to two years, pushing the timeline for construction back to 2027.
  11. [11]
    The MRT3 Circle Line is coming: Here's where you can find out ...
    Sep 1, 2024 · However in 2022, MRT Corp CEO Datuk Mohd Zarif Hashim was reportedsaying the project is set to begin operations in phases starting in 2028, with ...Missing: construction timeline
  12. [12]
    MRT 3 Circle Line: Everything You Should Know, and Best Nearby ...
    Oct 18, 2024 · Malaysia's first circular rail line. MRT 3 Circle Line is a route that helps commuters reach different areas of the Klang Valley more easily.<|separator|>
  13. [13]
    MRT3 project updates and land acquisition challenges - Facebook
    Apr 15, 2025 · The construction of the MRT3 Circle Line has not yet commenced, and its full commencement is scheduled for 2030. While we currently lack ...The MRT 3 Circle Line is currently undergoing a comprehensive ...Is it possible to complete the MRT Circle line in 6 years? - FacebookMore results from www.facebook.com
  14. [14]
    MRT3 Circle Line Project Timeline and Future Scenarios - LinkedIn
    Jul 18, 2025 · 2028 (Earliest Phase Operation): The first phase of the line could be running as early as December 2028, subject to land acquisition. 2030 (Full ...
  15. [15]
    MRT Corp: Home
    The MRT3 Circle Line is the critical final piece to complete Kuala Lumpur's urban rail network. Its 50.8km alignment will run along the perimeter of the city of ...Travel With MRT · Circle Line MRT3 · Corporate profile · LRT Mutiara LineMissing: length | Show results with:length
  16. [16]
    Circle Line MRT3 - MRT Corp
    1. Go to underserved areas and prepare for Kuala Lumpur Local Plan 2040 (PTKL 2040) · 2. Spur urban rejuvenation along the alignment · 3. Establish new multi- ...Missing: timeline phases
  17. [17]
    MRT 3 Circle Line: New Stations and Alignment - SoyaCincau
    Sep 3, 2024 · The new MRT line includes 12km of underground alignment and 39km of elevated sections. A total of 32 stations have been planned which includes 22 elevated ...Missing: length | Show results with:length
  18. [18]
    MRT3 Final Approval - MRT KL
    Jul 17, 2025 · MRT Corp stated that land acquisition can now proceed and that the company will begin engaging with affected communities to provide updates on ...Missing: challenges | Show results with:challenges
  19. [19]
    MRT Circle Line Details: Proposed Stops To Completion Date
    Sep 5, 2024 · Bukit Kiara Selatan (Interchange station with MRT Kajang Line); Bukit Kiara; Sri Hartamas; Bukit Segambut; Taman Sri Sinar; Dutamas; Kompleks ...
  20. [20]
    MRT 3: Here is the list of stations for Klang Valley's upcoming Circle ...
    Mar 20, 2022 · Dutamas; Jalan Kuching (Interchange with Port Klang Line); Titiwangsa (Interchange with Ampang & Sri Petaling Line, KL Monorail and Putrajaya ...<|separator|>
  21. [21]
    MRT3 is a go - 51.6 km Circle Line approved by transport ministry ...
    Jul 18, 2025 · With 10 interchange stations, the 51.6 km MRT3 Circle Line (was previously quoted as 50.8 km) will integrate with existing MRT, LRT, KTM and ...
  22. [22]
    Final railway scheme for MRT3 approved, paving way for next phase
    Jul 18, 2025 · The MRT3 Circle Line is a 51km orbital alignment that will serve the perimeter of Kuala Lumpur. It is designed for full integration with the ...<|separator|>
  23. [23]
    Malaysia's MRT3 project to become fully operational by 2030
    Mar 16, 2022 · It will include 40km of elevated tracks and 11km of underground tunnels. Malaysia Transport Minister Datuk Seri Dr Wee Ka Siong stated that the ...
  24. [24]
    MRT 3 Circle Line: All the latest details - kopiandproperty.com
    Mar 17, 2022 · MRT 3 will consist of 40.1km of elevated tracks and 10.7km of underground tunnels with 31 stations, of which 10 will be interchange stations with existing rail ...
  25. [25]
    [PDF] politicise tender timeline - MRT Corp
    MRT3, also referred to as the. Circle Line, is set to be the 13th urban rail transit line and the fifth fully automated and driverless line in the Klang Valley.
  26. [26]
    Malaysia's MRT Line 3 gets final approval, will be driverless - LinkedIn
    Jul 18, 2025 · The MRT Line 3 Circle Line is a 51km orbital route with 32 stations that will serve the perimeter of Kuala Lumpur gets final scheme approval to proceed.
  27. [27]
    Technical Information - MRT Corp
    The Putrajaya Line has 36 stations, 24 elevated and 8 underground. Trains have 1204 passenger capacity, 4 cars, and a max speed of 100 km/h. Driverless trains ...
  28. [28]
    What would MRT 3 circle line rolling stock look like? - Facebook
    Sep 22, 2024 · 🇲🇾 MRT3 or MRT Circle Line is a 50.8km circular alignment that consists of 31 stations covering the perimeter of Kuala Lumpur.MRT3 circle line alignment and stations - FacebookMRT3 Route Map Changes and Reduced Capacity in MalaysiaMore results from www.facebook.comMissing: signaling | Show results with:signaling
  29. [29]
    MRT3 Circle Line construction only starting in 2027 - paultan.org
    Nov 19, 2024 · Construction at the Mass Rapid Transit Circle Line (MRT3) project site is only expected to start in 2027 after MRT Corp completes the land acquisition process.
  30. [30]
    KL MRT Guide: Route Map, Stations & Timetable
    Timetable & Operating Hours ; Monday to Friday · 0900 – 1700 Hrs, 10 mins ; Monday to Friday · 1700 – 1930 Hrs, 5 mins ; Monday to Friday · 1930 – 2400 Hrs, 10 mins.<|separator|>
  31. [31]
    MRT Operation Hours - Malaysia Rail Transportation | mrt.com.my
    Stations will be opened for services at 6:00 am daily except if there is approved event that need specific station (s) to be opened earlier than normal. Station ...MRT Putrajaya Line · MRT Feeder Bus · Kwasa Damansara MRT Station
  32. [32]
    Travel With MRT - MRT Corp
    MRT Fares and Schedules. For the fares and schedules of the MRT Kajang (KG) Line and MRT Putrajaya (PY) Line, please go to www.myrapid.com.my.
  33. [33]
    MRT3 Circle Line Is Coming! - Landserve Malaysia
    Sep 2, 2024 · The alignment map and other details of the MRT3 Circle Line will be displayed at 8 MRT Info Kiosks and 27 MRT Info Trucks stationed at 35 ...
  34. [34]
    MRT3 seen to carry 180,300 passengers per day upon completion ...
    KUALA LUMPUR (Aug 4): The Mass Rapid Transit 3 (MRT3), also known as the Circle Line, is expected to carry 180,300 passengers per day when it is completed, ...
  35. [35]
    A Case Study on the Alignment of Mass Rapid Transit 3 (Circle Line)
    It is proposed to have three lines, arranged in the wheel and spoke pattern, encompassing two north-south radial lines as well as one circle line (also known as ...
  36. [36]
  37. [37]
    What is a 'circle line', and how can this new MRT route solve Klang ...
    Jul 14, 2024 · The planned line has a 51km alignment and will run along the perimeter of the capital city, connecting to existing MRT, LRT, KTM, and Monorail lines through 10 ...
  38. [38]
    MRT Lines 1 and 2 Ridership Targets Not Met in Malaysia - Facebook
    Jul 4, 2024 · MRT 2 2023 TARGET RIDERSHIP: 196K ACTUAL RIDERSHIP: 89K During peak hours, MRT2 increased the number of trains from 14 in 2022 to 37 in 2023.MRT3 Route Map Changes and Reduced Capacity in MalaysiaWhy Kuala Lumpur's mass rapid transit ridership is not as high as ...More results from www.facebook.com
  39. [39]
    Why Malaysians Shy Away from their RM120 Billion MRT System
    Jan 20, 2025 · During the construction phase, cost-saving measures like the avoidance of extensive tunneling work often led to the placement of MRT stations ...
  40. [40]
    Klang Valley's low MRT ridership and how to fix it | FMT : r/malaysia
    Jul 8, 2024 · As weird as it sounds, the MRT itself is not the problem. The issue is property development, city planning, walkways and feeder buses. Our ...Missing: Circle trends capacity
  41. [41]
    [PDF] Mass Rapid Transit (MRT) Demand and Capacity Assessment for ...
    Jun 8, 2024 · Kuala Lumpur having issues such as long waiting time, punctuality, ticketing systems, delay at transit station as well as train frequencies.
  42. [42]
    Real Estate Opportunities in the MRT3 Circle Line
    Sep 6, 2024 · The MRT3 Circle Line represents a significant milestone in the development of the Klang Valley. It offers a wealth of real estate investment opportunities.
  43. [43]
  44. [44]
    60% drop in rail line failures last year, says Loke | FMT
    Jan 9, 2024 · From 2022 to 2023, Loke said the Kajang MRT line saw a reduction from 46 to 38 failures while the Ampang MRT line dropped from 79 to 19 failures ...
  45. [45]
    Frequent malfunctions, breakdowns among MRT Line 1 concerns ...
    Jul 14, 2020 · The report highlighted a few weaknesses, such as the repeated malfunctions and breakdowns which have yet to be resolved, although the Defects ...
  46. [46]
  47. [47]
  48. [48]
    How Malaysia boosts reliability of urban rail | The Straits Times
    Oct 13, 2025 · SUBANG, Selangor – Multiple system failures, 16 station closures for five consecutive days, frustrated passengers – these were the challenges ...
  49. [49]
    Fewer breakdowns, shorter waits: How Klang Valley's rapid rail got ...
    Jan 15, 2025 · In 2023, the Kelana Jaya LRT line broke down up to five times a month. In total, there were 36 breakdowns in 2023. In 2024, the Transport Ministry aimed to ...
  50. [50]
    No mismanagement in MRT Corp, says Loke - Free Malaysia Today
    Jul 10, 2024 · Earlier today, transport consultant Wan Agyl Wan Hassan questioned the A-G's classification of MRT Corp as “lacking in financial stability”, ...
  51. [51]
    [PDF] MEDIA RELEASE - MRT Corp
    Mar 4, 2022 · Mohd Zarif said this Project is envisaged to catalyse socio-economic growth throughout the country, increase the nation's competitiveness in the ...
  52. [52]
    The new MRT 3 Circle Line and its positive impacts - Propnex
    Sep 11, 2025 · It aims to spur urban rejuvenation along its route, create a new multi-modal hub in the north of Kuala Lumpur City Centre, and open up greater ...
  53. [53]
    What is a 'circle line', and how can this new MRT route solve Klang ...
    Jul 13, 2024 · Singapore Transport Critic, a blog on transport systems, the main benefit of an orbital line is easing congestion at central transfer points by ...
  54. [54]
    [PDF] Estimating the Impact of Mass Rapid Transit (MRT) on Residential ...
    Sep 21, 2022 · This study used a hedonic pricing model with transaction-based data to estimate the impacts of the SBK MRT Line on residential property prices ...
  55. [55]
    Does proximity to MRT train stations boost property values and ...
    Jun 7, 2024 · For properties within 1.5-3km, prices were falling from RM425 in 2020 to RM350 psf in 2021 (17.6%) before it climbed back up to RM369 psf in ...
  56. [56]
    MRT3 Impact Zones: Where Smart Investors Are Looking Now
    Aug 20, 2025 · The MRT3 Circle Line is poised to reshape Kuala Lumpur's property market landscape. For the forward-thinking property agent in KL, the ...
  57. [57]
    MRT Corp: Circle Line to require fewer land lots, acquisition target ...
    Jul 17, 2025 · The line will include 31 stations, with 40km of elevated track and 11km of underground track. The MRT3 project was originally shelved in 2018 by ...