Mini-shinkansen

The Mini-shinkansen refers to a specialized category of services in where existing narrow-gauge (1,067 mm) conventional railway lines are upgraded and converted to standard gauge (1,435 mm) to enable direct operation of trainsets from regional destinations to , bypassing the need for transfers at junction points. This approach allows for cost-effective extension of the network into less densely populated areas without constructing entirely new dedicated high-speed infrastructure. The two operational mini-shinkansen lines are the , branching from the Tohoku Shinkansen at , and the , branching at . The , operated under the Tsubasa service name, commenced operations on July 1, 1992, initially covering the 87 km route from to Yamagata, and was extended 61 km further to Shinjō in December 1999. Similarly, the , branded as Komachi, began service on March 22, 1997, spanning 127 km from to via the converted Tazawako and Ōu Main Lines. These conversions involved widening tunnels, straightening curves, and installing slab track where necessary to accommodate standards, while preserving dual use for local freight and passenger services on parallel tracks in some sections. The development of mini-shinkansen addressed regional connectivity challenges in Tohoku, significantly reducing travel times—for instance, to Yamagata now takes about 2 hours 45 minutes, down from over 5 hours by conventional trains. Technically, mini-shinkansen trains are narrower than full-sized sets, with a width of 2.945 m to fit the smaller of the converted lines, resulting in seating configurations rather than the standard 2+3 or 3+2. Current includes the E8 series for the Yamagata line (introduced in 2024, with a capacity of 352 passengers per 7-car set) and the E6 series for the line (7-car sets since 2013, accommodating 338 passengers). While these trains can reach up to 300–320 km/h on the dedicated Tohoku portions (often coupled to mainline services like or for efficiency), speeds are restricted to 130 km/h on the mini-shinkansen sections due to tighter curves and infrastructure limitations. All seats are reserved and non-smoking, with features like universal accessibility, LED displays, and snow-resistant designs tailored to Tohoku's harsh winters.

Overview

Concept

The Mini-shinkansen represents a hybrid system initiated by (JR East) after its establishment in 1987 through the privatization of . This concept entails the regauging of existing 1,067 mm narrow- lines to 1,435 mm standard gauge, facilitating direct through-running of trains from regional branches onto the main Tohoku Shinkansen network without requiring passenger transfers. The primary purpose of the Mini-shinkansen is to extend high-speed services to less densely populated regional areas in northern , leveraging upgraded conventional to minimize costs while enhancing to major urban centers like . By converting underutilized narrow-gauge routes rather than building entirely new dedicated lines, JR East addressed financial inefficiencies in parallel conventional services and promoted in remote regions. A critical design adaptation for Mini-shinkansen trains involves a reduced to accommodate the constraints of pre-existing tunnels and structures on converted lines; specifically, the car body width is limited to 2,945 mm, narrower than the 3,380 mm profile of standard . This ensures operational compatibility without extensive modifications. In distinction from full lines, which achieve speeds up to 320 km/h, Mini-shinkansen services on the converted sections are capped at a maximum of 130 km/h to account for tighter track curvatures and infrastructure limitations inherited from the original narrow-gauge alignments.

Technical specifications

The mini-shinkansen system achieves compatibility with the standard network through the conversion of existing 1,067 mm narrow-gauge lines to 1,435 mm standard gauge, involving the physical uplifting of rails, , and associated , as well as realignment to accommodate the wider . This process allows for direct through-running of high-speed without the need for gauge-changing facilities at junction points. on mini-shinkansen sections operates at 20 kV AC 50 Hz to align with the legacy conventional line standards, contrasting with the 25 kV AC 50/60 Hz used on dedicated standard routes; are therefore equipped with dual-voltage systems to ensure seamless power transition during operations. Due to the retention of original tunnels, bridges, and platforms from the narrow-gauge era, the is strictly limited to a maximum car body width of 2,945 mm and height of 4,080 mm, necessitating the design of trains with compact profiles that differ from the broader 3,380 mm width of conventional . Signaling and control systems integrate (ATC) on the standard Shinkansen portions for precise high-speed operation with continuous speed supervision, while the mini-sections employ (ATS) for compatibility with conventional line safety protocols; automatic switching between these hybrid systems occurs at key junctions such as and stations to maintain operational continuity. Infrastructure upgrades on mini-shinkansen lines prioritize the installation of ballastless slab track where terrain and geometry permit, enhancing stability and maintenance efficiency, though legacy curves from the original narrow-gauge alignment persist in places, capping operational speeds at 130 km/h on these sections. Overall compatibility is facilitated by trains engineered for dual-voltage operation and adherence to the constrained , enabling uninterrupted end-to-end services from major hubs like to regional destinations via the converted lines.

History

Development

The origins of the mini-shinkansen concept lie in the 1971 (JNR) Comprehensive Railway Development Plan, which proposed extensions of the Tohoku Shinkansen to enhance connectivity in northern . Following JNR's in April 1987, which divided the debt-laden organization into regional companies including JR East, the mini-shinkansen was formalized as a pragmatic solution to extend services without the prohibitive costs of entirely new standard-gauge lines, estimated in the billions of yen. This approach was driven by post-privatization economic pressures, including fiscal reconstruction needs and the need to maintain competitiveness amid declining conventional rail usage. Feasibility studies in the , led by East, incorporated cost-benefit analyses highlighting significant savings—through reuse of existing rights-of-way and infrastructure upgrades—compared to full construction, while targeting the Tohoku region's ongoing depopulation and to foster regional revitalization. In , the Transport Policy Council endorsed continued network expansion, reversing a prior Cabinet suspension and supporting the Yamagata and routes as pilot projects for the mini-shinkansen model to balance needs. Development faced key challenges, including political debates over prioritizing regional equity in underserved areas like Tohoku against broader national infrastructure goals, amid JNR's legacy debt and reforms.

Implementation

The implementation of the mini-shinkansen network began with detailed between 1987 and 1990, focusing on the conversion of existing narrow-gauge lines to standard gauge to enable high-speed services while integrating with the Tohoku . Conversions commenced in 1988, emphasizing engineering techniques that preserved ongoing rail operations on conventional lines. For the , construction on the initial 87.1 km branch from to Yamagata involved regauging the Ou Main Line, with work starting in late 1988 and completing in 1992. This section opened on July 1, 1992, marking the debut of mini-shinkansen operations and allowing direct services from via the Tohoku Shinkansen. An extension of 61.5 km from Yamagata to Shinjo followed, with construction from 1997 to 1999 and inauguration on December 4, 1999, further extending connectivity to northern . The project covered 127.3 km from to , utilizing the existing Tazawako Line route, with construction initiating in April 1992 and proceeding in phases through 1997. This included laying parallel standard-gauge tracks alongside the narrow-gauge infrastructure and upgrading alignments, bridges, and electrification to specifications, at a cost of ¥97 billion. Services launched on March 22, 1997, providing the second mini-shinkansen route. Key engineering achievements across both lines involved minimal disruptions to local and freight services during conversion, accomplished by building temporary parallel tracks to reroute conventional trains while the original alignments were widened and elevated to standard . This staged approach ensured continuity of operations, with the parallel trackage later integrated or removed post-conversion. Brief references to technical methods, such as precise track realignment, highlight adaptations from broader standards to fit the narrower mini-shinkansen profile.

Lines

Yamagata Shinkansen

The branches off from the Tohoku Shinkansen at Fukushima Station and extends 148.6 km northward to Shinjo Station, serving along upgraded sections of the Ou Main Line. This route integrates seamlessly at the Fukushima junction, where trains from transition to the narrower mini-shinkansen tracks designed for compatibility with conventional infrastructure. The line traverses the rugged terrain of the Ou Mountains, including the central Ou Backbone Range, which forms the spine of the Tohoku region and presents challenging geography with steep gradients and heavy snowfall. A proposed 24.9 km base under the Ou Mountains, mostly bypassing the challenging Itaya Toge pass, is under consideration to reduce travel times and improve reliability, with planning ongoing as of 2023. Adapted from the existing Ou Main Line, the route features numerous and bridges to navigate the mountainous landscape, ensuring reliable passage through valleys and ridges. Key stations along the way include Yonezawa, known for its historical sites; Yamagata, the prefectural capital; and the terminus at Shinjo, providing access to northern rural areas. Since its opening in 1992, the has played a vital role in bolstering the regional economy and tourism in , facilitating easier access to natural attractions like the sacred Dewa Sanzan mountains. The 1999 extension from Yamagata to Shinjo, adding 61.5 km of track, further enhanced connectivity to remote northern communities, integrating them more fully into the broader Tohoku rail network. Unique operational features, such as snow management systems, address the line's harsh winter conditions, ensuring year-round reliability despite the mountainous environment's challenges.

Akita Shinkansen

The branches off the at Morioka Station in , extending 127.3 km northward to Akita Station via the upgraded Tazawako Line and Ōu Main Line. This route traverses diverse terrain in the , including the mountainous landscapes around —Japan's deepest caldera lake at 423 meters—and approaches the coastal plains near Akita, where expansive rice fields dominate the scenery. The line's path highlights the area's natural beauty, with views of forested hills and volcanic features, while navigating a seismically active zone prone to earthquakes due to its proximity to tectonic plate boundaries. Key stations along the route include , serving as the northern junction for coupled train operations; Tazawako, near the lake's eastern shore and a gateway to outdoor activities; Kakunodate, a historic town preserved as a cultural ; and , the terminus connecting to local urban and port facilities. The infrastructure incorporates reinforced viaducts and base-isolation systems to mitigate seismic risks, reflecting adaptations to the region's frequent tremors and lessons from the 2011 Great East Japan Earthquake. Integration with existing conventional rail lines was achieved with minimal disruption to local freight traffic, allowing shared use while upgrading for higher speeds up to 130 km/h. Since its opening in 1997, the has significantly enhanced connectivity to rural , facilitating tourism to attractions like Nyuto Onsen's hot springs and the surrounding rice paddies, which produce renowned varieties. This improved access has supported local revitalization efforts by boosting visitor numbers—contributing to in and —and promoting cultural preservation in depopulating areas, as part of JR East's broader initiatives.

Rolling stock

Current fleets

The current fleets of mini-shinkansen consist primarily of the on the and the series on the , both operated by (JR East). These trains feature narrow-body designs adapted for the converted 1,435 mm standard-gauge sections, with a maximum width of 2,945 mm to navigate existing tunnels and structures originally built for 1,067 mm narrow-gauge lines. They are equipped with (ATC) systems compatible with both and conventional signaling on mini-sections. The E8 series, introduced in March 2024 to replace the E3 series on Tsubasa services, operates as 7-car sets with a 5M2T configuration (five motored and two trailer cars). These dual-voltage trains (20 kV and 25 kV AC) have a maximum operating speed of 300 km/h on standard-gauge sections of the Tohoku Shinkansen and 130 km/h on the mini-shinkansen portion. Key features include a 2+2 seating arrangement in standard class for 329 passengers, plus 26 Green Car seats, with improvements to passenger experience such as larger windows, power outlets at each seat, Wi-Fi connectivity, and a stylish interior with gradient coloring from red to yellow. The exterior livery features a yellow gradient inspired by local Yamagata scenery. In June 2025, four E8 sets were temporarily suspended due to auxiliary power unit malfunctions, but operations resumed progressively by August 2025, with all affected units back in service by November. As of late 2025, nine E8 sets are fully operational, with the remaining six in testing or delivery phases toward a total fleet of 15 sets, supporting the phase-out of E3 series trains by fiscal 2026. The series, in service since March 2013 on Komachi services, uses a 7-car articulated mini-shinkansen formation (Z sets) that couples with 10-car E5 series trains for through operation from to . This design allows for a narrower body while maintaining stability on curves, with a maximum speed of 320 km/h on the Tohoku Shinkansen standard sections and 130 km/h on the mini portion. The trains feature a purple livery and provide 315 standard seats plus 23 Green Car seats in a 2+2 layout, emphasizing comfort with and tilting capability up to 1.5 degrees. As of 2025, the fleet comprises 23 sets (161 cars total), with no retirements planned yet, though JR East announced development of the E11 series, a successor, in October 2025 to address aging infrastructure.

Retired fleets

The 400 series trains were the inaugural rolling stock for the Mini-shinkansen, specifically designed for the Yamagata Shinkansen line with 6-car formations capable of a maximum speed of 240 km/h on dedicated high-speed sections. These steel-bodied sets, built between 1992 and 1995, entered service on July 1, 1992, and operated until their full withdrawal on April 18, 2010, after 18 years of service. Their retirement was driven by advancing age, operational inefficiencies compared to newer designs, and the need to replace them with more capable E3 series trains to meet growing demand. The E3 series, introduced in 1997 for the Akita Shinkansen and expanded to the Yamagata line in 1999, featured 7-car mini configurations with a top speed of 275 km/h, enabling coupled operation with standard Tohoku Shinkansen sets for through services to . These aluminum-bodied trains served both lines until a gradual phase-out began in March 2024, with all units scheduled for retirement by the end of 2025, except two sets repurposed for other uses. The replacement by E8 and E9 series trains addresses limitations in passenger comfort, such as outdated interiors and seating, as well as improved through modern and propulsion systems. Both the and series pioneered Mini-shinkansen operations by allowing to extend onto converted narrow-gauge lines, but their retirements highlight the evolution toward fleets with enhanced accessibility features, like elements, and amenities such as onboard , which were absent in these earlier models.

Operations and services

Services

The Mini-shinkansen lines feature specialized passenger services that enhance regional access from . The Tsubasa service on the operates 16 daily trains (weekdays) between and Shinjo as of November 2025, following a September 2025 timetable revision that slightly adjusted some departure times, with an end-to-end journey of approximately 4 hours and reserved seating required for all cars. On the , the Komachi service runs 15 daily trains from to as of November 2025, covering the route in about 3.5 hours end-to-end, with sets coupled to trains for the Tohoku Shinkansen portion. Schedules incorporate frequencies of approximately one train per hour during peak periods, alongside seasonal adjustments to support increased during holidays and festivals. These services are included in the for standard seating, but ordinary pass holders pay a supplement for Green Car access; e-ticket reservations via mobile have been integrated since for seamless boarding. Accessibility provisions encompass dedicated spaces in each trainset and multilingual announcements in , English, , and Chinese.

Performance

The Mini-shinkansen services achieve maximum operating speeds of 320 km/h on the Tohoku Shinkansen tracks between and , transitioning to 130 km/h on the upgraded mini-shinkansen sections of the Ou Main Line. This dual-speed profile balances high-velocity travel on dedicated infrastructure with compatibility on narrower conventional tracks, enabling seamless integration into the broader network. Key travel times include approximately 2 hours and 22 minutes from to Yamagata and 3 hours and 37 minutes from to as of November 2025, reflecting operational efficiencies from infrastructure upgrades and advancements. The 2014 introduction of the series on the enhanced speeds to 320 km/h on the Tohoku section, shortening end-to-end journeys compared to prior E3 series operations limited to 275 km/h. These services provide about 20% faster connections than pre-mini-shinkansen conventional rail options on the Ou Main Line, prioritizing regional accessibility while leveraging high-speed segments for overall time savings. Efficiency metrics highlight the system's reliability, with on-time performance exceeding 99% across operations, including mini-shinkansen lines, supported by rigorous maintenance and scheduling protocols that average delays under one minute annually. Recent enhancements include the March 2024 debut of the E8 series on Tsubasa services, which raised maximum speeds to 300 km/h between and —up from 275 km/h—and trimmed select Tokyo-Yamagata runs by up to 4 minutes through optimized acceleration and route adjustments.

References

  1. [1]
    JR East's new E8 Shinkansen impresses with speed and interior ...
    Oct 10, 2024 · One side-effect of the mini-Shinkansen conversion, as opposed to a fully new Shinkansen line, is that the loading gauge (essentially the height ...
  2. [2]
    History of the Shinkansen: The Japanese Bullet Trains | JRailPass
    Oct 3, 2024 · Planning began before WWII, the first line opened in 1964, the Sanyo line in 1975, and the Nozomi trains in 1992. The Hokkaido line opened in ...
  3. [3]
    Yamagata Shinkansen | Route Maps | JR-EAST
    The Yamagata Shinkansen runs between Tokyo and Yamagata/Shinjo. Operation began in 1992 after the section between Fukushima and Yamagata on the Ōu Main Line ...
  4. [4]
    Akita Shinkansen | Route Maps | JR-EAST
    The Akita Shinkansen runs between Tokyo and Akita. Operation began in 1997 after the section between Morioka and Akita on the Tazawako Line and Ōu Main Line ...Missing: Mini- | Show results with:Mini-
  5. [5]
    The Akita Shinkansen line between Tokyo and Akita - Japan Rail Pass
    Known as a mini-Shinkansen, the Akita Shinkansen is basically a branch line of the Tohoku Shinkansen. Train formations depart together from Tokyo station, at ...
  6. [6]
    Series E8 enters service on Yamagata mini-Shinkansen
    Mar 20, 2024 · The Series E8s are designed to run at up to 300 km/h on the Tohoku Shinkansen, whereas the Series E3s they will replace are limited to 275 km/h, ...
  7. [7]
    Tohoku Shinkansen - Japan Guide
    Mar 16, 2025 · For these reasons, they are also known as mini-shinkansen. Six train ... The Komachi is the only train category of the Akita Shinkansen.
  8. [8]
    2. High-speed rail development in Japan - ElgarOnline
    and Akita, JR East introduced services on conventional lines known as the Mini-Shinkansen, which is not classified as a Shinkansen system by definition. JR ...
  9. [9]
    Narrow gauge legacy
    **Summary of Mini-shinkansen Concept (Railway Gazette International, 2002):**
  10. [10]
    [PDF] 16.8 million/day No. of Trains
    3,380mm. Double Decker. Series E4. Through service. Series E6. Standard. Series E2. 17,500mm. 25,000mm. 2,500mm. 20,000mm. 14,150mm. Width of car body ... small ...
  11. [11]
    The Shinkansen: Japan's Bullet Train | Nippon.com
    Sep 16, 2022 · The maximum speed on these routes is only 130 kilometers per hour, but they are directly connected with the Tōhoku Shinkansen. Later, new ...
  12. [12]
    Fastech 360 twins herald speed-up to the north - Railway Gazette
    May 1, 2006 · JR East's six-car small-profile Fastech 360 Z began ... converted from 1067mm to 1435mm gauge - commonly known as mini-Shinkansen lines.
  13. [13]
    JR East presents first Series E8 high speed train - Railway Gazette
    Feb 28, 2023 · ... mini-Shinkansen ... Designed to take power at 20 kV and 25 kV 50 Hz, the dual-voltage Series E8 ...
  14. [14]
    [PDF] JR-East Shinkansen Technology - Schienenfahrzeugtagung Graz
    Mar 11, 2011 · Body width. 3380mm. 2945mm. 3380mm. 3350mm. 2945mm. Motor power ... car body, ride quality is further enhanced in our high-speed operations.
  15. [15]
    JR East unveils Super Komachi high speed train - Railway Gazette
    Nov 27, 2012 · The first of 23 production Series E6 trainsets being supplied to East Japan Railway for Akita mini-Shinkansen services was officially unveiled.
  16. [16]
    [PDF] Organizing the Development of the High-Speed Railway Network ...
    Mar 31, 2023 · Shinkansen lines that were in operation in 1987 were taken over by JR Central for ... via the Tōhoku Shinkansen operated by JR East. These are the ...
  17. [17]
    [PDF] Shinkansen investment before and after JNR Reform | OECD
    Dec 27, 2013 · Before JNR reform, Shinkansen was operated by JNR. After, JNR was separated, and public funds were used to extend lines, modifying financial ...
  18. [18]
    Privatization and Beyond: The JR Case
    JNR was privatized due to financial issues, loss of competitiveness, and the need for fiscal reconstruction, as it was not allowed to set its own budget or ...
  19. [19]
    [PDF] Le 13 1" - DSpace@MIT
    only on the narrow-gauge tracks. So the widening tracks for Mini Shinkansen means basi- cally no freight rail transportation is possible on the route. The ...<|control11|><|separator|>
  20. [20]
    Dark Skies Ahead for Shinkansen Network Expansion | Nippon.com
    Oct 3, 2024 · In 1971, the government approved plans and construction started on the Tōhoku, Jōetsu, and Narita lines—although the Narita line was ...
  21. [21]
    Japan Railway & Transport Review No. 48 (pp.6–21)
    The 1987 railway reforms transferred responsibility for operations of the Tohoku and Joetsu shinkansen ... In a bid to operate shinkansen at 360 km/h, JR East is ...
  22. [22]
    JR East launches Akita Shinkansen | News | Railway Gazette ...
    Replacing a service requiring passengers to change between standard gauge Tohoku Shinkansen and 1067mm gauge trains at Morioka, the five-car Series E3 trains ...
  23. [23]
    Yamagata mini-Shinkansen base tunnel proposal makes progress
    Nov 6, 2022 · JAPAN: Construction of a base tunnel below the Ou mountain range on the Yamagata mini-Shinkansen has moved a step closer.
  24. [24]
    JR Yamagata Shinkansen Guide: Routes, Tickets, and Travel Tips
    Sep 22, 2025 · The Yamagata Shinkansen is one of Japan's two Mini Shinkansen lines, linking Tokyo with Yamagata and Shinjo through the mountains of Tohoku.
  25. [25]
    Yamagata bullet train stoppage cause remains unidentified
    Jul 16, 2025 · The ongoing disruptions have dealt a significant blow to Yamagata's tourism industry, particularly during the popular cherry-picking season.Missing: economy | Show results with:economy
  26. [26]
    Why does Shinkansen train track in Japan have sprinklers installed ...
    Nov 16, 2016 · The sprinklers spray warm water to melt snow to eliminate build up on the rails and switches. ... Yamagata Shinkansen and Akita Shinkansen.
  27. [27]
    Heavy Snow Continues to Affect Shinkansen Services
    Feb 8, 2025 · Heavy snow continued to affect Shinkansen bullet train services on Saturday, causing suspensions or delays starting in the morning.Missing: heated | Show results with:heated
  28. [28]
    Shinkansen Route Map | Nippon.com
    Mar 16, 2024 · Originally launched in 1964 between Tokyo and Osaka, it has grown in the decades since, and today it spans much of the country, with plans ...Missing: timeline | Show results with:timeline
  29. [29]
    Kakunodate & Around | Akita | Tohoku | Destinations | Travel Japan
    Kakunodate has Edo-period architecture, samurai and merchant quarters, preserved samurai homes, cherry blossom viewing, and cherry-bark crafts.Missing: impact Lake
  30. [30]
    [PDF] JR East Group CSR Report 2015
    ○ Disaster prevention measures for Yamagata and Akita Shinkansen lines in mountainous areas ... We are also pursuing regional revitalization by deepening ...<|control11|><|separator|>
  31. [31]
    The Akita Shinkansen Line connecting Tokyo and Akita | JRailPass
    The Akita Shinkansen line. Last Update: August 23, ... The Akita Line is sometimes referred to as a “mini-shinkansen” because its smaller trains are able to ...
  32. [32]
    [PDF] Great East Japan Earthquake, JR East Mitigation Successes, and ...
    Researchers in California are developing an earthquake early warning system for the state, and the private sector has seismic sensors in place. These ...
  33. [33]
    [PDF] JR East Group Report INTEGRATED REPORT 2024
    Regional Revitalization. Goals. • Growth in the number of people engaging with eastern Japan. • Promotion of regional economic revitalization. Policy. In ...
  34. [34]
    [PDF] List of JR East's Railway Vehicles
    Series E8. 300. 7. 1.0. Series E7. 275. 468. 4.4. Series E6. 320. 161. 10.3. Series E5. 320. 460. 9.2. Series E3. 275. 105. 15.3. Series E2. 275. 170. 17.2.
  35. [35]
    E8 Series Yamagata Shinkansen Bullet Train Unveiled to Media
    Feb 25, 2023 · East Japan Railway Co. (JR East) unveiled a new Shinkansen bullet train, the E8 Series, to be introduced on the Yamagata Shinkansen line in the spring of 2024.
  36. [36]
    JR East to suspend E8 shinkansen trains for time being
    Jun 19, 2025 · The E8 series entered service last March. Nine trains are in operation, while two are undergoing test runs. The four trains that malfunctioned ...
  37. [37]
    JR East to Resume E8 Shinkansen Train Operations - JIJI PRESS
    Tokyo, July 22 (Jiji Press)--East Japan Railway Co., or JR East, said Tuesday that it will gradually resume individual operations of E8 series Shinkansen ...
  38. [38]
    Reading between lines , JR East also going to replace E6 series ...
    Oct 8, 2025 · Maximum speed on the mini-Shinkansen will be limited to 130 km/h. The new trains are decked in a three-colour livery, combining the purple of a ...
  39. [39]
    [PDF] Overview of New Shinkansen (E6 Series) Mass-Production Prototype
    Full active suspension on lead cars (No. 11 and 16). Semi-active suspension on intermediate cars (No. 12 – 15). Train tilting system (up to 1.5° tilt on ...
  40. [40]
    Series E6 mini-Shinkansen trainset unveiled | News - Railway Gazette
    Jul 14, 2010 · The prototype Series E6 mini-Shinkansen trainset for East Japan Railway's Akita route was unveiled to the public at Sendai depot on July 9.Missing: construction | Show results with:construction
  41. [41]
    400 Series Shinkansen - Locomotive Wiki - Fandom
    Withdrawals began in February 2009 with set L9, with the trains being replaced with E3 Series sets; the last service for a 400 Series Shinkansen set was a ...Missing: details | Show results with:details
  42. [42]
    400 Series Shinkansen Last Run - Japan Rail - JNS Forum
    Apr 18, 2010 · The first generation "Mini-Shinkansen" train was retired on Apr. 18, 2010 ... Mini-Shinkansen 400 Series sets were built between 1992 and 1995.No clue what it can be and why it's open - Japan Rail - JNS ForumE3系0番台 To Be Retired From Akita Shinkansen [15/3/2014]More results from jnsforum.comMissing: details | Show results with:details
  43. [43]
    Shinkansen series guide: Shinkansen train models | JRailPass
    Sep 19, 2025 · E3 series Shinkansen were built to coincide with the opening of the new Akita Shinkansen “mini-shinkansen” line between Morioka and Akita.
  44. [44]
    E3 series Bullet Train - The Red List of Trains in Japan
    They were also introduced to Tsubasa (Tokyo - Shinjo) in 1999, when Yamagata Shinkansen was extended from Yamagata to Shinjo. In most cases, they formed 16 or ...
  45. [45]
    Yamagata Shinkansen Timetable - Snow Monkey Resorts
    May 26, 2025 · Regular services run from Fukushima Station to Shinjo, with all services stopping at Yamagata and other stations. The 'Tsubasa' is the only ...Missing: key | Show results with:key
  46. [46]
    Tsubasa Shinkansen Timetable - Tokyo - Japan Travel by NAVITIME
    This is a timetable using the JR Tohoku ShinkansenTsubasa from Tokyo for Sendai/Shin-Aomori/Shin-Hakodate-Hokuto . You can check the list of departure time, ...
  47. [47]
    Complete Guide to the Akita Shinkansen | Tokyo Cheapo
    Jun 18, 2024 · The Akita Shinkansen is a branch line of the Tōhoku Shinkansen. It runs from Tokyo Station to Akita Station via Morioka.Rail Passes And Other... · Stations Of Interest On The... · Akita Shinkansen FaqsMissing: geography | Show results with:geography
  48. [48]
    Tokyo to Akita Komachi&nbsp;Timetable (JR Tohoku Shinkansen)
    Find the complete JR Tohoku Shinkansen(Komachi) timetable from Tokyo to Akita. Check departure times, journey duration, fares, and ticket prices.
  49. [49]
    Shinkansen: Japanese Bullet Trains - Japan Rail Pass
    These high-speed trains allow visitors to quickly and easily discover Japan, by cutting down the travel time between destinations.
  50. [50]
    Train accommodations | JAPAN RAIL PASS
    You cannot use reserved seats (including Green Car) and non-reserved seats on "NOZOMI" and "MIZUHO" Shinkansen trains (☆). There are no Green Cars on most “ ...Missing: Mini- supplement
  51. [51]
    Shinkansen e-ticket / Express train e-ticket | JR-EAST
    This service allows you to reserve an e-ticket in advance and board the Shinkansen or limited express trains without the need to use a ticket counter or ticket ...Missing: Mini- 2020
  52. [52]
    Shinkansen Wheelchair Accessibility - Accessible Japan
    The Shinkansen, or Bullet Train, is practically a symbol of Japan. With great wheelchair accessibility, persons with disabilities can travel with ease.
  53. [53]
    Shinkansen (Japanese Bullet Train) - Japan Guide
    Feb 28, 2025 · Shinkansen are Japan's high-speed bullet trains, known for punctuality, comfort, safety, and efficiency, running up to 320 km/h.
  54. [54]
    Akita Shinkansen | Dovetail Games Forums
    Sep 11, 2020 · Introduced in 2013 these narrow bodied 7 car trains operate all Shinkansen services on this route. They run at speeds of up to 320km/h between ...
  55. [55]
    [PDF] JR East Group CSR Report 2014
    In March 2014, we enhanced the speed of the Akita Shinkansen by having all trains replaced with the new E6 series and began operating at 320 km/h. We also ...
  56. [56]
    Socioeconomic Benefits of the Shinkansen Network - MDPI
    Apr 30, 2021 · The results for the Shinkansen network represent time saving of at least 25% compared with conventional trains on the same routes. Table 2.Missing: mini- cost<|control11|><|separator|>
  57. [57]
    [PDF] How the punctuality of the Shinkansen has been achieved - WIT Press
    The Shinkansen's punctuality is achieved through hardware, software, and humanware, with an average delay of less than one minute per year.
  58. [58]
    Test ride of new E8 Series Tsubasa bullet train held in Japan ahead ...
    Mar 7, 2024 · The Yamagata Shinkansen will have a new train model for the first time since 1999, when the service was extended to Shinjo Station. Yamagata ...