Fact-checked by Grok 2 weeks ago

Msikaba Bridge

The Msikaba Bridge is a under construction in the province of , spanning the Msikaba River near as part of the N2 Wild Coast Toll Road upgrade project. Featuring a main span of 580 metres supported by two 127-metre-high inverted Y-shaped pylons and 34 pairs of stay cables, it is designed to carry a dual two-lane with pedestrian walkways and will stand 192 metres above the gorge floor upon completion. Scheduled for completion by the end of 2025, the bridge represents a significant engineering feat, poised to become Africa's longest cable-stayed main span and the continent's third-highest bridge. Initiated in late 2019 by the , the project addresses longstanding connectivity challenges in the remote Wild Coast region, reducing travel times between and by up to three hours while boosting local through thousands of direct and indirect jobs. The , led by Danish firm Dissing+Weitling in collaboration with South African engineers, incorporates a composite steel-concrete deck 22.8 metres wide, ground-anchored back spans, and advanced features like a system and wind-resistant cable arrangements tested in wind tunnels. Construction has progressed steadily, with anchor blocks completed by late 2023, pylons reaching approximately 104 metres by May 2025, and deck erection commencing in 2025, despite challenges posed by the site's rugged terrain and the need for a temporary for access. Beyond its technical specifications—which include 48,500 cubic metres of , 4,300 tons of reinforcing , and 1,090 tons of stays—the Msikaba Bridge holds broader significance as a symbol of investment in underserved areas, fostering , , and while enhancing on a historically hazardous route. Valued at approximately R1.7 billion as part of the R5.7 billion for the two mega-bridges, it forms one of two mega-bridges in the 560-kilometre initiative, underscoring South Africa's commitment to modernizing its national highway network amid environmental and geological complexities like the Msikaba Gorge's deep valley and rocky foundations.

Location and Significance

Geographical Context

The Msikaba Bridge is located at coordinates 31°17′45.07″S 29°47′35.74″E, approximately 23 km east of in the Ingquza Hill Local Municipality of the province, . This positioning places it within a remote coastal corridor along National Route 2 (N2), connecting key economic hubs like and . The bridge spans the Msikaba River gorge, a dramatic feature plunging approximately 195 meters deep through steep, forested valleys. The surrounding Wild Coast region exemplifies 's rugged coastal terrain, with sheer cliffs, wide sandy beaches, and numerous river mouths carving deep incisions into the landscape, creating a mosaic of inaccessible headlands and estuaries. Ecologically, this area is highly sensitive, forming part of the Centre of Plant Endemism, where sandy, acidic soils support unique , including rare floral species and dense subtropical thickets vulnerable to disturbance. The Msikaba River and its gorge lie within the historical bounds of the former homeland, established under apartheid-era policies from 1976 to 1994 as a semi-autonomous territory for Xhosa-speaking populations. During this period, the region faced severe transportation challenges, including dilapidated gravel roads, limited rail access, and inadequate infrastructure that isolated rural communities and hindered economic activity. These legacy issues of poor connectivity persisted post-reintegration into in 1994, exacerbating travel times across the rugged terrain. The bridge plays a key role in the N2 Wild Coast Toll Highway initiative to address such longstanding barriers.

Project Overview

The N2 Wild Coast Toll Highway represents a major infrastructure upgrade spanning approximately 410 km from the Mtamvuna River near Port Edward in to the Gonubie Interchange near East London in the , aimed at modernizing a critical segment of South Africa's national road network. This ambitious project, managed by the South African National Roads Agency (SANRAL), incorporates two signature mega-bridges—the Msikaba Bridge spanning the Msikaba River near and the Mtentu Bridge near Lundini—to facilitate seamless crossings over deep gorges and rugged terrain that have long impeded efficient travel. By replacing winding, accident-prone sections of the existing N2 and parallel R61 routes with a straighter, more resilient alignment, the initiative addresses longstanding bottlenecks in freight and passenger mobility along the southeastern coastal corridor. The strategic objectives of the N2 Wild Coast Toll Highway emphasize enhanced connectivity, safety, and economic vitality in one of South Africa's most underdeveloped regions. It is designed to shorten the route by about 85 km compared to the current paths, reducing travel times by 1.5 to 3 hours—particularly benefiting heavy freight vehicles between and —while mitigating risks on the notoriously hazardous existing N2, which features steep gradients and frequent accidents. Furthermore, the project is poised to stimulate regional by unlocking access to isolated communities, supporting , , and , and creating thousands of jobs during and beyond, thereby integrating the Wild Coast into broader national supply chains. Initiated in the early as part of SANRAL's broader expansion strategy, the project gained momentum with environmental approvals and feasibility studies around 2010–2011. The Msikaba Bridge segment marked a key milestone when its construction tender was awarded in October 2018, with groundbreaking and construction commencing in January 2019, signaling the onset of on-site works for this engineering centerpiece. The Msikaba River crossing, characterized by its steep gorge and remote location, exemplifies the geographical hurdles the project navigates to achieve these connectivity gains.

Design and Engineering

Structural Design

The Msikaba Bridge features a cable-stayed configuration with a steel-concrete composite deck supported by steel stay cables anchored to two inverted Y-shaped concrete pylons, each rising 127 meters above the gorge floor. This design allows for a main span of 580 meters, enabling the bridge to cross the deep Msikaba River gorge while integrating a dual two-lane carriageway that is 22.8 meters wide, including pedestrian walkways. The pylons are back-stayed by additional cables anchored into massive concrete blocks, providing stability against the region's high winds and seismic activity. The architectural and conceptual design was led by the Danish firm Dissing+Weitling Architecture, selected by the South African National Roads Agency (SANRAL) for its proven expertise in complex, long-span bridges, such as the in . Dissing+Weitling's approach emphasized a minimalist aesthetic that harmonizes with the Wild Coast's rugged landscape, blending functionality with visual elegance to minimize the structure's intrusion on the natural environment. The firm's involvement covered both concept and detailed design phases, in collaboration with engineering partners like SMEC . This project has been highlighted in National Geographic's "Building Impossible with Daniel Ashville" (Season 1, Episode 2), showcasing the innovative design process. The choice of a cable-stayed design over alternatives like bridges was driven by the need to accommodate the 580-meter span across an approximately 192-meter-deep gorge while reducing environmental disruption in this ecologically sensitive with vegetation. Unlike bridges, which require extensive anchorages and taller towers (potentially up to 60 meters higher), the cable-stayed configuration uses simpler foundations and modular steel strand cables, allowing for less invasive in the steep terrain and lowering the overall material footprint. This selection also supports the broader N2 Wild Coast project goals by facilitating efficient highway integration with reduced transit times for local communities.

Technical Specifications

The Msikaba Bridge is engineered as a with a main span measuring 580 meters, establishing it as Africa's longest by main span length. The overall structure extends approximately 800 meters, encompassing side spans and anchorages. Positioned 192 meters above the valley floor, its deck height positions it as one of the highest bridges on the continent, surpassed by the at 216 meters. Construction materials emphasize durability and efficiency, with 48,500 cubic meters of forming the pylons, blocks, and components. The prefabricated box requires 2,900 tons of to achieve the necessary strength-to-weight ratio for the expansive span. Additionally, 1,090 tons of stay cables support the structure, distributed across 17 pairs of main stay cables per (34 pairs total for the main span), with additional back-stay cables, to evenly distribute loads. Supporting infrastructure includes 1.5 kilometers of approach roads to integrate seamlessly with the N2 . The encompasses 650,000 cubic meters of earthworks, addressing the challenging terrain of the Msikaba River gorge. The bridge's accommodates a configuration with four lanes, each 3.7 meters wide, flanked by 2.5-meter shoulders, ensuring capacity for high-volume traffic while maintaining safety standards.

Procurement and Construction

Contract Award

The procurement process for the Msikaba Bridge was initiated by the in 2016 as part of the broader N2 Wild Coast Toll Highway project. The initial tender invitation, under contract SANRAL N.002-200-2016/3, sought proposals for the bridge's construction but received no fully responsive bids, prompting to re-advertise the tender in November 2017 with a closing date in March 2018. This re-tendering ensured compliance with 's procurement guidelines, emphasizing technical feasibility and value for money. On September 20, 2018, SANRAL awarded the contract to the Concor Mota-Engil Joint Venture (CMEJV), a partnership between South Africa's Concor Holdings (a majority black-owned construction firm) and Portugal's Mota-Engil (an international specialist in bridge projects). The total contract value was R1.65 billion (approximately US$118 million at the time of award), covering the design, construction, and commissioning of the 580-meter cable-stayed bridge. The selection criteria included a functionality threshold of 70% based on bidders' technical expertise and methodology, alongside price competitiveness (80% weighting) and Broad-Based Black Economic Empowerment (B-BBEE) status (20% weighting) to promote local empowerment and skills transfer. The HVA Joint Venture, led by SMEC South Africa in partnership with and , was appointed by for detailed design oversight, contract administration, and construction supervision to ensure adherence to standards and specifications. This arrangement provided independent verification of the CMEJV's work, focusing on quality control and risk management throughout the pre-construction and implementation phases.

Construction Methods

The construction of the Msikaba Bridge employed innovative techniques to navigate the challenging 195-meter-deep gorge and rugged terrain. A key method for accessing the site during pylon construction was the installation of a temporary system, which facilitated safe and efficient transport of workers, materials, and equipment across the gorge, reducing crossing time to approximately eight minutes compared to longer ground routes. This aerial access was essential for erecting the 127-meter-high inverted Y-shaped , where workers performed , , and pouring in phases, often using hydraulic to separate pylon legs for stability. The bridge deck, comprising a composite structure with steel box girders, utilized extensive prefabrication to minimize on-site risks and assembly time. Steel box girder segments, each measuring about 15 meters long, 22 meters wide, and weighing around 84 to 100 tons, were fabricated off-site in South African facilities using detailed 3D modeling with software like Tekla Structures and analyzed via Straus7 for structural integrity. On-site, these segments were assembled incrementally from both banks of the gorge using two specialized 160-ton bridge deck launch gantries, which lifted, rotated (by 90 degrees for alignment), and positioned the segments via the free cantilever method, starting with a reinforced concrete ladder deck base cast into the first steel segment. This approach allowed for the 580-meter main span to be built symmetrically, with transverse truss-like cross-frames connecting the dual box girders to support the two-lane carriageway. Cable installation for the cable-stayed system involved precise tensioning and procedures to ensure structural equilibrium. The bridge features 17 pairs of stay cables per side (34 pairs total), fabricated from high-strength strands totaling 2,500 tons, which are anchored into the pylons and extend to massive anchor blocks on each . Installation occurs during the erection phase, with cables set into pre-formed deviators and galleries within the anchor blocks, followed by post-tensioning using specialized hydraulic jacks to apply forces up to tons per strand at 17 anchor points per block, incorporating U-shaped tendons for enhanced capacity and for protection in the steep inclines. Earthworks and approach road construction addressed the unstable coastal soils prevalent in the Eastern Cape region through bulk excavation and stabilization measures. Approximately 1.5 kilometers of temporary access roads were developed on both sides of the gorge, involving up to 20 meters of deep excavations for foundations and anchor blocks, with 650,000 cubic meters of material moved, including hard rock blasting where necessary. Geotechnical stabilization techniques included layer-by-layer verification of compacted materials for road bases, interlock designs for anchor blocks with the underlying rock mass to resist lateral forces, and ongoing monitoring via drone surveys to mitigate soil instability and erosion in the coastal environment. These methods ensured durable approach viaducts integrating seamlessly with the main structure while handling the site's variable soil conditions.

Progress and Timeline

Key Milestones

The Msikaba Bridge project originated as part of the N2 Wild Coast Toll Road initiative, with planning commencing in 2011 to enhance freight transport and regional connectivity along South Africa's eastern seaboard. The detailed engineering design for the bridge was finalized by 2017, paving the way for the competitive tender process managed by the . In September 2018, awarded the R1.65 billion construction contract to the Concor-Mota-Engil Joint Venture (CMEJV), marking the transition from planning to execution. Site mobilization followed shortly thereafter in late 2018, with initial groundwork including access roads and preparatory surveys. Construction activities ramped up in early , with pylon foundation work beginning that January amid challenging terrain and weather conditions. The project gained international attention through media coverage, including a feature in National Geographic's "Building Impossible with Daniel Ashville" series, which highlighted the feats involved in spanning the Msikaba Gorge. However, progress was hampered in and 2020 by legal challenges from local communities contesting environmental authorizations and toll implementations, as well as funding constraints amid broader N2 Wild Coast disputes; these issues were largely resolved by early 2021 following favorable court rulings upholding SANRAL's approvals. By 2022, significant advancements included the hydraulic jacking of the south pylon legs, a critical that separated the structure's foundational elements for . Through 2023 and into 2024, the project achieved completion of the four anchor blocks and pylon bases, with pylon progressing to approximately 86 meters by mid-2024, while initial preparations for cable-stayed installations commenced.

Current Status

As of the latest available data from a June 2025 parliamentary report (based on a March 2025 oversight visit), construction on the Msikaba Bridge has advanced significantly, with the north reaching 92 meters (72% complete) and the south at 100 meters (79% complete), progressing toward their final 127-meter elevation. The first segment was launched in late March 2025. The bridge launch gantry is fully operational, facilitating the assembly of the steel segments, while stay cables have been delivered to the site, with initial installations commencing as the pylons near completion. The project, part of the broader N2 Wild Coast Toll Road initiative, is expected to achieve substantial completion by the 2028/29 financial year, enabling full integration into the national N2 highway network and reducing travel times between and by up to three hours. This timeline reflects adjustments from earlier projections due to factors such as challenges for specialized materials, though no major accelerations have been reported in recent oversight updates. Safety and quality oversight is managed by the HVA , led by SMEC, which supervises activities to ensure compliance with engineering standards and worker protection protocols. Progress in 2025 has been documented through official photos and videos released by and parliamentary oversight visits, highlighting ongoing advancements in pylon erection and deck launching amid the challenging coastal terrain.

Impact and Challenges

Economic and Social Benefits

The Msikaba Bridge, integral to the N2 Wild Coast Toll Road project, is anticipated to substantially reduce travel times along the N2 highway between and the , shortening the journey from to by up to three hours through a more direct, flatter route. This enhancement in connectivity will also decrease road accidents by mitigating the risks associated with the existing route's steep gradients, sharp curves, and poor conditions, thereby improving safety for both passenger and freight vehicles. Economically, the project has generated significant employment during construction, creating approximately 8,000 direct jobs and 21,000 to 28,000 indirect jobs, with 80% of the workforce comprising local residents from the . Completion of the bridge will further stimulate the regional economy by boosting eco-tourism along the Wild Coast, where improved access to pristine coastal areas is expected to attract more visitors and support local businesses. Additionally, it will facilitate efficient , benefiting through faster movement of and produce, as well as activities by reducing costs and enhancing market access for raw materials. On the social front, the bridge will alleviate isolation in rural Wild Coast communities by providing reliable access to , including healthcare facilities and , which are currently hindered by inadequate road infrastructure. This improved mobility will empower residents, particularly in underserved areas, to engage more fully in economic opportunities and social networks beyond their localities. Overall, these benefits position the Msikaba Bridge as a key contributor to South Africa's National Development Plan, advancing infrastructure-led inclusive growth and regional equity.

Environmental and Engineering Challenges

The construction of the Msikaba Bridge has encountered significant environmental challenges due to its location in the ecologically sensitive Wild Coast region of South Africa's province. The project area falls within the Centre of , a encompassing approximately 1,885 km² and hosting around 200 endemic plant species, including endangered ones such as the Pondoland Conebush (Leucadendron pondoense) and Pondo Coconut (Jubaeopsis caffra). These species face risks from and loss caused by bridge foundations and access roads encroaching on the Msikaba River gorge ecosystem, which supports unique wetlands, grasslands, and riverine habitats critical for local biodiversity. Additionally, the broader N2 Wild Coast Toll Road development has raised concerns over threats to sacred sites like the Isinuka and Sibhenga pools, used for cultural rituals, potentially impacting cultural and spiritual practices alongside ecological degradation such as and water pollution. To address these issues, comprehensive environmental impact assessments (EIAs) were conducted prior to 2017, with the initial EIA in 2004 rejected for lacking independence and a revised one approved in 2010 by the Department of Environmental Affairs. Mitigation strategies included search-and-rescue operations for rare plants from September 2016 to February 2017, translocation of endangered species to protected nurseries, and habitat rehabilitation plans in collaboration with the South African National Biodiversity Institute and Eastern Cape Parks and Tourism Agency. Offset agreements were also established to conserve equivalent biodiversity areas, ensuring minimal net loss to the region's endemic flora and fauna. Engineering challenges stem from the site's rugged in a seismically active zone with unstable conditions and . The Msikaba Gorge's steep inclines and fractured rock formations posed risks of soil instability, addressed through deep anchor block foundations—each 49 m long, 10 m wide, and 17 m deep, interlocked with in-situ rock for enhanced lateral stability and seismic resistance. Seismic activity in the , including potential for moderate earthquakes, necessitated adaptive structural monitoring via (IoT) sensors to detect and respond to ground movements in real time. High winds, frequently exceeding 80 km/h in the gorge, threatened and operational stability, mitigated by extensive testing to optimize the cable-stayed design's and the use of high-strength, corrosion-resistant in the composite deck to withstand coastal exposure. Project delays from 2019 to 2021 were exacerbated by community protests, funding constraints, and the , halting progress on the broader N2 Wild Coast Toll Road program. unrest, particularly over perceived cultural disruptions and inadequate consultation, led to work stoppages similar to those at the adjacent Mtentu Bridge site in 2018–2021. The lockdown imposed a moratorium in 2020, while funding shortages arose from contractor terminations and tender irregularities, prompting to re-tender and secure government backing. These issues were resolved through legal settlements addressing interdicts, extensive engagements including a 2022 imbizo with traditional leaders, and additional government funding allocations to restart activities by late 2021. However, as of March 2025, the project remains only 40% complete, with completion now projected for the 2028/29 financial year due to ongoing and challenges, further postponing anticipated economic and social benefits.

References

  1. [1]
    Msikaba Bridge - SMEC
    The Msikaba bridge is a cable-stayed bridge, currently under construction, spanning the Msikaba River, near Lusikisiki in the Eastern Cape Province of South ...Missing: facts | Show results with:facts
  2. [2]
    Iconic Msikaba Bridge Makes Steady Progress - Concor
    “At 580 m in length, it will the longest cable-stayed bridge – in terms of main span – in Africa and it will have the second longest main span of any bridge on ...Missing: facts | Show results with:facts
  3. [3]
    Msikaba Bridge - HighestBridges.com
    Feb 5, 2024 · The beautiful Msikaba Bridge is scheduled to become the second longest span crossing ever constructed on the African Continent with a tower to tower distance ...Missing: facts | Show results with:facts
  4. [4]
    South Africa's R5.7 billion mega-bridges coming soon - BusinessTech
    Aug 30, 2024 · The Msikaba Bridge is currently under construction, and will span ... Started in 2019 and expected to be completed in 2025, it has a project value ...
  5. [5]
    Msikaba Bridge | Projects - Surbana Jurong
    Part of South Africa's N2 Wild Coast Toll Road project, the Msikaba River Bridge is set to become one of the highest bridges in the country.Missing: facts | Show results with:facts
  6. [6]
    [PDF] msikaba river bridge - SAICE
    The site is 425 km north of East London and 325 km South of Durban. • The closest towns to the South and North bank are Lusikisiki and Flagstaff respectively.
  7. [7]
    [PDF] N2 WILD COAST - Sanral
    The Msikaba Bridge will cross the 195m deep Msikaba River gorge, and once completed will be the longest-span cable-stayed bridge in South Africa, standing at ...Missing: depth | Show results with:depth<|separator|>
  8. [8]
    Msikaba Bridge - SMEC
    The Msikaba bridge is a cable-stayed bridge, currently under construction, spanning the Msikaba River, near Lusikisiki in the Eastern Cape Province of South ...
  9. [9]
    A guide to the Wild Coast South Africa - Exclusive Travel
    Terrain: The Wild Coast is characterized by its rugged cliffs, deep gorges, wide sandy beaches, dense coastal forests, and numerous rivers and waterfalls that ...Missing: depth | Show results with:depth
  10. [10]
    [PDF] The Pondoland Centre of Endemism, Species Richness and Threats
    Jul 13, 2007 · Species rich estuarine forest –Msikaba river gorge. In the PCE the natural environment is still relatively intact and population densities ...Missing: depth | Show results with:depth
  11. [11]
  12. [12]
    Transkei transport: the twentieth century transition - Academia.edu
    Transport improvements were limited due to poor infrastructure and limited market demand for services.Missing: Msikaba | Show results with:Msikaba
  13. [13]
    A gentler time on the 'Wild Coast' - Los Angeles Times
    Oct 24, 2004 · The Eastern Cape province, including the former independent Transkei homeland, has known a wicked history of violence and political turmoil.
  14. [14]
    N2 Wild Coast Toll Road – Package 4, South Africa
    Oct 4, 2024 · The project entails a 410 km stretch of road, from East London to the Mtamvuna river, on the border of the Eastern Cape and the KwaZulu-Natal ...Missing: length | Show results with:length
  15. [15]
    Taking the high road to development | SAnews
    Oct 22, 2025 · The project includes two mega-bridges: the Msikaba Bridge, which spans the Msikaba Gorge near Lusikisiki, and the Mtentu Bridge near Lundini. At ...Missing: Highway | Show results with:Highway
  16. [16]
    [PDF] N2 WILD COAST ROAD UPDATE 18 November 2021
    Nov 18, 2021 · Once complete the route will be approx. 69km and 85 km shorter than the current N2 and R61 routes and be 1.5 to 3 hours faster, particularly for ...
  17. [17]
    [PDF] provincial presentation to the ncop - Parliament of South Africa
    Aug 28, 2024 · Shorter, flatter, faster and safer route than either. R61 or current N2. • 85 km shorter. • 1.5 to 3 hours faster. Page 10. N2 WILD COAST MEGA ...Missing: Highway | Show results with:Highway
  18. [18]
    N2 Wild Coast Road project to support development along key trade ...
    Apr 29, 2021 · The N2 Wild Coast road project will contribute to economic growth and open a trade corridor along the south-eastern coast of South Africa.
  19. [19]
    N2 Wild Coast route projects will benefit the economy
    Mar 19, 2019 · The new route will bring: Regional economic development. Significantly faster delivery times and lower transportation costs between KZN and EC; ...
  20. [20]
    [PDF] ANNUAL REPORT 2010/11 12 –– 13 October 2011
    ➢ Toll Road development: Gauteng Freeways, N1/N2. Winelands. N2 Wild Coast. ➢ Community Development Projects (rural areas). ➢ Using appropriate technology.
  21. [21]
    SANRAL awards N2 Wild Coast Bridge tender
    Aug 25, 2017 · Construction of the bridge is set to start in early November 2017, and is scheduled to last approximately 40 months. "The tender, valued at ...Missing: inaugurated | Show results with:inaugurated
  22. [22]
    N2 Wild Coast Highway - Knight Piésold
    The section of the road extends from the Msikaba River at km 35.3, to the Mtentu River at km 52.8 in the Transkei towards the east of the Eastern Cape province.
  23. [23]
    [PDF] msikaba river bridge | saice
    Aug 4, 2021 · The project forms part of a mega project to upgrade existing sections of the N2 and the R61 between East London in the Eastern Cape and.
  24. [24]
    Msikaba and Mtentu Bridges - Dissing+Weitling
    The Msikaba Bridge is a 580-meter long cable-stayed road bridge spanning across a spectacular steep green gorge created by the beautiful Msikaba River.<|separator|>
  25. [25]
    SANRAL's Msikaba Mega Bridge features on National Geographic's ...
    Oct 5, 2023 · This bridge across the Msikaba Gorge is one of the longest cable-stayed bridges in Africa, and is an engineering marvel.
  26. [26]
    Msikaba Bridge - Arc Innovations
    Tahle, Eastern Cape, South Africa; 636 feet high / 194 meters high; 1,903 foot ... The new cable-stayed bridge will also become the third highest bridge in Africa ...
  27. [27]
    Work resumes on N2 Msikaba bridge project - SARF
    May 25, 2020 · The Msikaba bridge will require 43 000 m3 of concrete, 2 700 t of structural steel, 1 090 t of cables and 3 100 t of steel reinforcing.
  28. [28]
    Msikaba Span Contract Let By South Africa Road Agency | 2018-10-17
    Oct 17, 2018 · The bridge, with a span of 580 meters, is being built by state-owned South African National Roads Agency SOC Ltd. (Sanral) over the 195-m-deep ...Missing: depth exact
  29. [29]
    Sanral: Building South Africa through better roads: SanralTenders
    ... MSIKABA BRIDGE (KM 33.02) CONTRACT SANRAL N.002-200-2016/1. Tender Notice: Awarded To: WBHO - EDWIN CONSTRUCTION JV. BBBEE Points: 10. Full Points Awarded: ...Missing: Concor Mota- Engil
  30. [30]
    Sanral reopens Msikaba bridge tender - Engineering News
    Nov 3, 2017 · The South African National Roads Agency Limited (Sanral) has reopened the tender process for the construction of the R1.7-billion Msikaba bridge ...
  31. [31]
    Sanral awards R1.65bn Msikaba megabridge contract to Concor ...
    Sep 20, 2018 · Sanral has awarded the Concor Mota-Engil joint venture (JV) the second of two megabridge construction contracts as part of the N2 Wild Coast project.
  32. [32]
    Tender Notice - Sanral
    The tenderers will be evaluated on functionality (quality) criteria with a threshold of 70%. Joint Ventures (JV) shall be required with the Lead Partner being a ...
  33. [33]
    Here is who got Sanral's R1.65bn bridge tender
    Artist's impression of the Msikaba Bridge. Picture supplied by Meropa ... total length and 680m main span Maputo-Catembe suspension bridge in Mozambique.
  34. [34]
    Mtentu and Msikaba Bridges: reaching new heights
    Msikaba Bridge was designed by the. HVA Joint Venture (of which SMEC. South Africa is the main partner) and is being constructed by the Concor Mota-. Engil ...
  35. [35]
    Msikaba Bridge - Launching Gantry | LMSteel Projects - LM Steel
    Designed by the Danish studio Dissing+Weitling, the “Msikaba Bridge” is a steel cable-stayed bridge which, once completed, will cross the Msikaba River, ...Missing: Architecture | Show results with:Architecture
  36. [36]
    'Highly technical' phases started at Msikaba - Engineering News
    Jun 14, 2024 · The locally procured post-tensioning strand cables at each of the 17 anchor points in each block are stressed up to around 500 t by a specialist ...
  37. [37]
    Grouting steep inclined tendons: Lessons from the Msikaba Bridge ...
    The anchor structures feature U-shaped post-tension tendons extending to the full depth of the anchor block. These tendons provide structural capacity, ...
  38. [38]
    Msikaba River Bridge | Wild Coast - GeoAfrika
    The Msikaba bridge is a cable-stayed steel deck bridge currently under construction, spanning the Msikaba River near Lusisiki in the Eastern Cape of South ...Missing: facts | Show results with:facts<|control11|><|separator|>
  39. [39]
    Wild Coast N2 Highway Project Taking Shape - Knight Piésold
    It is being constructed in the form of a single carriageway road between the two new major bridges – Msikaba Bridge and Mtentu Bridge – which are both also ...
  40. [40]
    N2 Wild Coast Toll Road megabridge projects – update
    Aug 20, 2021 · 5-billion. Planned Start/End Date The N2WCTR project started in 2011; however, the major greenfield portion of the route between Port St Johns ...
  41. [41]
    Court turns down N2 Wild Coast Road appeal - News24
    Apr 30, 2019 · The court denied an appeal against an earlier judgment, where Judge Cynthia Pretorius found in Sanral's favour and confirmed the validity of the ...<|control11|><|separator|>
  42. [42]
    Milestone at Msikaba project with jacking of south pylon legs - Concor
    The Msikaba Bridge Project on the new N2 toll road between Port Edward and Umtata achieved an engineering milestone this month, as the legs of the bridge's.Missing: timeline | Show results with:timeline
  43. [43]
    Msikaba Mega Bridge - Construction Progress - May 2025 - YouTube
    May 28, 2025 · It's coming along nicely. The towers are currently at 104m and will be completed at 127m. Bridge deck launch gantry components are in place.
  44. [44]
    Report of the Portfolio Committee on Transport on Its Oversight Visit ...
    The envisaged design completion date for this project is November 2025. The envisaged construction tender date is June 2026, followed by the construction start ...
  45. [45]
    A guide to business and investment in the Eastern Cape
    Sep 29, 2025 · The impressive Msikaba Bridge, pictured above, will cut travel times between East London and Durban by three hours and open up the economy ...Missing: benefits | Show results with:benefits
  46. [46]
    Strabag-led JV Wins South Africa Bridge Contract | 2017-10-26 | ENR
    Oct 19, 2017 · The 50:50 JV will build the 1,130-m-long bridge over the Mtentu River near the town of Flagstaff in eastern South Africa as part of the 410- ...
  47. [47]
    Revived infrastructure spending will make for safer roads | Economy
    Sep 1, 2023 · The 1.5-hour to three-hour reduction in travel time for light-to-heavy vehicles using the current N2 and R61 routes between KZN and the Eastern ...
  48. [48]
    Msikaba - a bridge to a better life for the people of the Eastern Cape
    May 16, 2024 · Thousands of jobs have been created as locals in Lusikisiki, recruited to work on the project, make up 80% of the bridge-building workforce.
  49. [49]
    President Cyril Ramaphosa: N2 Wild Coast and Msikaba Bridge ...
    Sep 23, 2021 · There is the job creation benefit. Work on the N2 Wild Coast Project will lead to the creation of 8,000 direct full-time jobs and between ...
  50. [50]
    #DidYouKnow, that so far, the Msikaba Bridge project has benefitted ...
    Jan 27, 2025 · DidYouKnow, that so far, the Msikaba Bridge project has benefitted 44 local suppliers, 48 service providers and 61 subcontractors with over ...
  51. [51]
    N2 Wild Coast Toll Road development | South Africa - Zutari
    The N2 Wild Coast Toll Road development project falls within the Ingquza Hill Local Municipal area of the OR Tambo Municipal District in the Eastern Cape.
  52. [52]
    Infrastructure development and environmental risk perceptions in ...
    The Wild Coast region is located in the Eastern Cape province of South Africa. The area lies between the Great Kei River in the South and the Mthamvuna River in ...Missing: gorge | Show results with:gorge
  53. [53]
    Controversial Wild Coast Toll Road: Environment will be first priority
    Sep 29, 2016 · A second EIA assessment was conducted and in 2010 the Department of ... The project also includes two mega-bridges across the Msikaba and Mtentu ...
  54. [54]
    IoT at Msikaba Bridge - SMEC
    To read more about the Msikaba Bridge project, click here. View the full schedule of sensor types deployed at Msikaba Bridge. Download our technical paper ...
  55. [55]
    Iconic Msikaba Bridge makes steady progress - Crown Publications
    Feb 10, 2023 · The first 24 m of the deck on either side of the gorge is a reinforced concrete ladder deck that is cast into the first steel deck segment, ...
  56. [56]
    Msikaba project harnesses local steel - Engineering News
    Jul 7, 2023 · Among other products, the bridge is being fabricated using “world-class” heavy gauge structural steel sections from the ArcelorMittal Rail and ...
  57. [57]
    CROSSING BOUNDARIES - Engineering News
    Jan 19, 2024 · There were also delays in the construction of the Msikaba bridge because of Covid-19, and the contract was also impacted on by delays caused by ...
  58. [58]
    Communities, SMMEs main beneficiaries of Msikaba Bridge ...
    Sep 23, 2021 · This as work at the project's Mtentu Bridge construction site was halted due to community unrest. President Ramaphosa said although ...Missing: 2019-2021 funding
  59. [59]
    Work Begins on South Africa's 'Mega-bridge' Project
    Sep 9, 2020 · The agency said that the Covid-19 pandemic has caused some delays to the project but activities have now resumed following the easing of ...Missing: 2019-2021 | Show results with:2019-2021
  60. [60]
    Almost inconceivable' cancellation of Sanral projects to lead to ...
    The cancellation of R17.47-billion in tenders by the South African National Roads Agency Limited (Sanral), will lead to major delays in the execution of these ...Missing: legal | Show results with:legal