Fact-checked by Grok 2 weeks ago

North Triangle Common Station

The North Triangle Common Station, officially designated as the Unified Grand Central Station, is an under-construction interchange in , , , , intended to connect the Light Rail Transit Line 1 (LRT-1) extension, Metro Rail Transit Line 3 (MRT-3), terminus, and the future . Located at the North Avenue-Quezon Avenue junction along , the station occupies a site adjacent to the existing North Avenue MRT-3 station and the MRT-7 depot, aiming to streamline passenger transfers in one of the region's busiest transport corridors. Conceptualized in the late as a key component of Metro Manila's rail integration efforts, the project divides into three areas: Area A for LRT-1 and MRT-3 platforms funded by the (DOTr), Area B as a atrium, and Area C integrated with MRT-7 developed by . Construction, awarded to BF Corporation in 2019 for Area A at a cost of ₱2.78 billion, has encountered repeated setbacks, including site acquisition disputes and coordination challenges among stakeholders, resulting in stalled work since August 2024. In May 2025, the DOTr terminated BF Corporation's contract citing persistent delays and failure to meet milestones, shifting to a public-private partnership model to select a new contractor by late 2025 with a targeted completion in 2027 to coincide with MRT-7's partial operations. The delays have drawn criticism for exacerbating and hindering the ' urban mobility improvements, though MRT-7's independent sections advance toward service by early 2026.

Background and Planning

Initial Proposal and Rationale

The concept of the North Triangle Common Station originated in 2006, when the Philippine government initiated discussions with private stakeholders near the EDSA-North Avenue intersection to develop a unified rail hub, initially focused on linking the existing Line 3 with the proposed LRT Line 1 northward extension. This early proposal addressed the inefficiencies of Metro Manila's rail network, where disparate lines operated in isolation, requiring passengers to navigate surface transport or extended pedestrian routes for transfers, exacerbating daily commutes in a region plagued by severe . The core rationale centered on creating a centralized interchange to enable seamless connectivity, reducing reliance on road-based vehicles and optimizing passenger flow across elevated and future underground lines. By consolidating transfers at one facility, the station would serve the northern periphery of —an area with substantial underserved populations commuting to employment hubs in , Ortigas, and —thereby enhancing system capacity and promoting economic mobility without expanding roadway infrastructure. Initial plans envisioned handling peak-hour demands through integrated ticketing and direct platform linkages, drawing from global models of grand central stations to mitigate the capital's chronic transport bottlenecks, where public rail carried over 1 million daily riders across fragmented routes by the mid-2000s. By 2011, the and Communications expanded the proposal to incorporate the , positioning the North Triangle site—spanning the area between and malls, adjacent to the North Avenue bus terminal—as the optimal location for a multi-line terminus rather than a direct overlay, to accommodate depot functions and future expansions like the . This shift emphasized long-term scalability, with the station designed to integrate feeds and vertical development, aiming to capture projected ridership growth from northern suburbs like while minimizing disruptions to existing traffic volumes exceeding 400,000 vehicles daily.

Site Selection Process

The North Triangle Common Station site was initially identified in 2008–2009 as the optimal interchange location at the -North Avenue junction in , where the MRT-3 North Avenue terminus, the planned LRT-1 extension, and the MRT-7 North Avenue station converge, facilitating passenger transfers for an estimated daily ridership of over 800,000. The and Communications (DOTC, now DOTr) prioritized this site for its central position in Metro Manila's northern transport network, minimizing walking distances between lines and integrating with existing bus and routes along . A major dispute emerged over the precise location due to competing interests from adjacent property owners Holdings (operator of SM City North EDSA) and (operator of TriNoma mall), whose facilities flank North Avenue. The original 2009 plan placed the station primarily in front of the SM Annex building, but in 2014, Transportation Secretary Joseph Emilio Abaya proposed relocating it nearer to TriNoma to reduce construction costs by approximately P1 billion and improve commuter access to that mall's facilities. contested the shift, securing a temporary in July 2014 to halt the move, arguing it violated existing rights and agreements tied to MRT-3 operations near their property. Negotiations, spanning roughly eight years from the initial conflicts, involved DOTC/DOTr officials, rail operators like (MRT-7 developer), and mall owners, with interim proposals including dual stations—one near each mall—to bypass the impasse, though this was deemed inefficient for seamless transfers. The deadlock was resolved in September 2016 through a compromise agreement endorsed by DOTC Secretary , positioning the station to straddle North Avenue directly between and , granting both malls direct pedestrian access and shared to balance commercial interests while preserving operational efficiency. This site divides into three areas: Area A (platforms for LRT-1 and MRT-3, near the malls), Area B (MRT-7 integration), and Area C (future expansions), with land acquisition facilitated by right-of-way easements over public and private parcels. The resolution prioritized empirical connectivity needs over individual stakeholder preferences, though it delayed groundbreaking until 2018.

Development Agreements

Negotiations with Stakeholders

The primary negotiations for the North Triangle Common Station centered on resolving a longstanding dispute over the station's location, which pitted the interests of major mall operators against government priorities for cost efficiency and passenger connectivity. Initially proposed in 2005 near the SM North EDSA mall, the site was shifted toward the adjacent TriNoma mall (owned by Ayala Land) in 2015 by the Department of Transportation and Communications under Secretary Joseph Emilio Abaya, citing potential savings of up to PHP 1.5 billion in construction costs and better alignment with existing rail infrastructure. This move drew opposition from SM Prime Holdings, which secured a Supreme Court temporary restraining order in 2016, arguing it would disadvantage their mall's accessibility and foot traffic; the conflict delayed progress and highlighted tensions between private commercial interests and public transport integration. Under the incoming Duterte administration, Transportation Secretary Arthur Tugade initiated renewed talks in mid-2016, convening key stakeholders including the Department of Transportation (DOTr), Light Rail Transit Authority (LRTA), Metro Rail Transit Corporation (MRTC, operator of MRT-3 under Metro Pacific Investments Corporation), SM Prime Holdings, Ayala Land, and North Triangle Depot Commercial Corporation (a government entity managing depot lands). The discussions, spanning several months, focused on a compromise site on underutilized government-owned land in the North Triangle area, positioned equidistant between SM North EDSA and TriNoma to balance commercial access while incorporating a vehicular underpass along EDSA to mitigate traffic disruptions. On September 28, 2016, the parties formalized this agreement, with MPIC chairman Manuel V. Pangilinan endorsing the location as a pragmatic resolution to avoid further litigation. Building on this consensus, a memorandum of agreement (MOA) was signed on January 18, 2017, by representatives from DOTr, Department of Public Works and Highways (DPWH), SM Prime Holdings Inc., Universal LRT Corporation (LRTA's foreign partner), Light Rail Manila Corporation, North Triangle Depot Commercial Corporation, Ayala Land Inc., and Sumitomo Corporation (involved in MRT-7 development). The MOA delineated responsibilities for land use, infrastructure contributions, and integration of LRT-1, MRT-3, and future MRT-7 lines, with private stakeholders committing to non-interference and support for right-of-way provisions; it also addressed MRT-7 operator San Miguel Corporation's need for adjacent platforms (Areas B and C) to link seamlessly without separate ticketing systems. Securing this pact ended an eight-year impasse, enabling subsequent contract awards, though it required concessions such as shared maintenance costs and pedestrian linkages to malls to align private incentives with public goals.

Contract Awards and Financing

The contract for the construction of Area A of the North Triangle Common Station, valued at 2.8 billion, was awarded in to a consortium comprising BF Corporation and Foresight Development and Surveying Company (BF-FDSC). This agreement was executed under the (DOTr) as a direct arrangement, with completion targeted for 2021. In May 2025, the DOTr terminated the contract with BF-FDSC due to persistent delays in project execution. Following the termination, the DOTr initiated plans to rebid the project through a (PPP) framework to expedite resumption and completion. The DOTr expressed a preference for a solicited PPP mode, citing its efficiency and reduced risk compared to unsolicited proposals, with a target award date in the third quarter of 2025. Under this approach, involvement would handle financing and operations, supplemented by equity where necessary, though specific funding allocations such as loans or subsidies have not been detailed publicly as of the rebidding phase.

Construction Progress

Early Construction Phases

Construction of the North Triangle Common Station, also known as the North Avenue Common Station or Unified Grand Central Station, commenced in December 2017 after site selection agreements were finalized between the Department of Transportation (DOTr), Ayala Land, Inc., and SM Prime Holdings in September 2016. The station was structured into three interconnected areas: Area A for integrating LRT Line 1 and MRT Line 3 platforms, Area B as a commercial concourse, and Area C linking to the MRT Line 7 terminus. Initial activities focused on site preparation, including clearing and excavation at the North Triangle site between SM North EDSA and TriNoma malls along in . The DOTr awarded the contract for Area A to BF Corporation in early 2019, targeting completion by October 2020, with works emphasizing foundation piling and structural framing to accommodate underground and elevated rail connections. Area B development by proceeded concurrently, incorporating retail spaces to fund portions of the project, while Area C advanced in tandem with viaduct construction by , which had begun line-wide earthworks in 2016 but integrated station-specific elements post-2017. By 2020, visible progress included partial erection of steel frameworks in Area A and ongoing extensions in Area C, though the began impacting timelines shortly thereafter. These early phases laid the groundwork for the station's 13,700 square meter footprint, designed to handle interchanges for three rail lines serving an estimated 380,000 daily passengers upon completion.

Integration of Rail Lines

The North Triangle Common Station facilitates the convergence of the Light Rail Transit Line 1 (LRT-1) North Extension, Metro Rail Transit Line 3 (MRT-3), and Metro Rail Transit Line 7 (MRT-7), enabling paid-area transfers to streamline passenger movement across these systems. The LRT-1 extension, spanning from Roosevelt Station to North Avenue, incorporates underground linkages to the station, allowing direct connectivity to MRT-3's North EDSA terminus approximately 500 meters away via enclosed walkways and concourses. MRT-7 terminates at the station as its southern endpoint, with elevated platforms integrated into the structure's Area B, designed for efficient cross-platform transfers to LRT-1 and MRT-3 via Area C's central hub. This zonal layout—Area A for LRT-1 and MRT-3 platforms, Area B for MRT-7, and Area C for unified circulation—minimizes transfer times to under five minutes under optimal conditions, supported by escalators, elevators, and fare-integrated ticketing systems. Provisions exist for future expansion, including stub tracks and vertical alignments to link with the Metro Manila Subway's North Avenue portal, ensuring scalability for additional heavy rail capacity projected at over 800,000 daily passengers across integrated lines. As of October 2025, structural integration remains incomplete due to segmented construction by separate operators— for LRT-1, for MRT-7, and the for overall coordination—necessitating phased commissioning starting with MRT-7 in 2027.

Technical Specifications

Station Design and Architecture

The North Triangle Common Station features a multi-level, integrated divided into three primary areas to facilitate seamless interchanges among MRT Line 3, LRT Line 1, , and future connections such as the (Line 9). Area A accommodates the platforms and for MRT-3 and LRT-1, Area B serves as the central atrium for cross-platform transfers, and Area C houses the . This tripartite structure, designed by Visionarch, emphasizes by linking the station to adjacent commercial hubs like mall, incorporating retail, entertainment, and pedestrian pathways. The station spans approximately 13,700 square meters of space, with a daily passenger capacity of 478,000. Architecturally, it employs an airy interior with prominent thick silver columns supporting geometric lines, while indoor and cladding mitigate the visibility of exposed and structural elements. Levels include ground-level to nearby bus and terminals, a second-level equipped with ticketing counters and walkways, and third-level platforms for the primary rail lines; an underground walkway connects to the Line 9 subway platform. The atrium in Area B, completed as of early construction phases, functions as the interchange core, promoting efficient vertical and horizontal passenger flow without extensive escalator reliance. Integration with urban surroundings prioritizes functionality over ornate aesthetics, utilizing steel framing and modular components visible in ongoing MRT-7 extensions, though some observers have critiqued the utilitarian appearance as resembling a due to limited natural light provisions. The design supports public-private partnerships, with contributing to the atrium under agreements, ensuring commercial viability alongside transport efficiency.

Facilities and Amenities

The North Triangle Common Station incorporates a 13,700-square-meter area engineered to serve as an interchange hub for the Transit Line 1 (LRT-1), Metro Rail Transit Line 3 (MRT-3), and Metro Rail Transit Line 7 (MRT-7). This facilitates seamless passenger transfers across the three rail lines through a tripartite structural layout: dedicated platforms and sub-concourses for LRT-1 and MRT-3 integration, separate platforms and facilities for MRT-7, and a central common atrium enabling cross-platform access without requiring passengers to exit the paid zone. The design prioritizes minimal walking distances between platforms to enhance efficiency for high-volume commuter flows in the densely populated area. Passenger amenities emphasize transit-oriented functionality with integrated commercial spaces within the station footprint, allowing for on-site shopping and quick-service dining options to accommodate transfers and waiting periods. Direct linkages to adjacent developments, including ' expansion, extend access to broader retail outlets, entertainment venues, sports facilities, and exhibition halls, effectively augmenting the station's utility as a mixed-use . Intermodal supports onward travel via buses and jeepneys from dedicated areas, reducing reliance on external transfers. Accessibility features are incorporated to accommodate diverse users, including provisions for elevators and escalators across multi-level platforms, though specific counts remain tied to ongoing specifications. The overall aims to mitigate through wide circulation paths in the common atrium, drawing on standard urban rail design principles for elevated and at-grade interchanges. As of 2025, these elements reflect planned configurations amid project delays, with final implementations subject to contractor awards and site adaptations.

Delays and Controversies

Primary Causes of Delays

The North Triangle Common Station project, first proposed in 2009 as part of efforts to interconnect Metro Manila's rail lines, experienced significant initial delays due to protracted disputes over its location. Negotiations between the government and private stakeholders stalled for years, with disagreements centering on land acquisition and optimal site placement amid competing urban development interests, culminating in a compromise location near only in January 2017. Subsequent construction delays arose after the (DOTr) awarded the civil works contract in 2019 to the BF Corporation-Foresight Development and Surveying Company (BFC-FDSC) for approximately ₱873 million, targeting completion of key phases by 2021. Progress halted amid mutual recriminations: the attributed stoppages to DOTr's failure to release payments for verified completed work, which strained suppliers and labor, rendering further operations untenable by mid-2024. In contrast, DOTr cited excessive delays in civil works, exacerbated by the pandemic's disruptions to supply chains and site access, as well as the contractor's cited excuses including government arrears, leading to a of termination issued on , 2025. These payment and performance disputes compounded earlier setbacks, including legal challenges over project splitting into phases to resolve site conflicts, which fragmented oversight and extended timelines. Construction effectively stalled by August 2024, with the project—originally slated for partial operations by 2021—remaining indefinitely postponed as of late , underscoring systemic issues in contract enforcement and fiscal coordination between public and private entities.

Contract Disputes and Termination

The (DOTr) issued a notice of termination on May 16, 2025, against the BF Corporation and Foresight Development and Surveying Company (BFC-FDSC) consortium, which had been contracted for the of Area A of the North Triangle Common Station, also known as the Unified Grand Central Station. The decision stemmed from excessive delays, with halting in August 2024 despite the project being originally slated for completion by mid-2023. DOTr officials cited the consortium's failure to meet milestones as grounds for invoking termination clauses in the contract, which had been awarded in 2021 under a design-and-build scheme valued at approximately PHP 1.5 billion for the station's foundational works. In response, BFC-FDSC contested the termination as "unjust," asserting that project setbacks were primarily due to DOTr's delays in processing payments and approvals, which disrupted and material procurement. The claimed it had completed about 40% of the assigned scope, including initial piling and structural framing, but argued that the remained valid pending or formal mechanisms outlined in the . BF Corporation, led by former public works secretary , emphasized its prior experience in infrastructure but did not provide independent verification of payment disputes in public statements. Following the termination, DOTr announced plans to rebid the unfinished works through a public-private partnership (PPP) modality, targeting award by the third quarter of 2025 to align with MRT-7's projected operations in 2026. This shift aims to expedite integration of LRT Line 1, MRT Line 3, and MRT-7 at the station, though potential legal challenges from BFC-FDSC could prolong resolution, as the consortium reserved rights to seek redress through the courts or the Construction Industry Arbitration Commission. No prior major contract terminations were recorded for the project, though earlier location disputes in 2016 between rail operators had delayed overall planning without affecting construction contracts directly.

Criticisms from Stakeholders

The (DOTr) has criticized the BFC-FSDC consortium, the project's since 2020, for excessive delays in civil works, leading to a termination notice issued on May 16, 2025, after the project—initially proposed in 2009—remained incomplete despite over 16 years of development. The DOTr highlighted that these delays stemmed from the contractor's failure to meet milestones, including halted progress since early 2024, amid broader challenges like location disputes and the . In rebuttal, the BFC-FSDC accused the DOTr of causing work stoppages through "undue and habitual" payment delays for verified quality outputs, asserting that the termination violated contractual terms and ignored government-directed scope changes that increased complexity without corresponding adjustments. This mutual finger-pointing reflects ongoing tensions between oversight and private execution, with the contractor warning of potential claims against the DOTr. Private stakeholders, particularly Holdings, opposed the station's relocation in 2014 from adjacent to to a site between and malls, arguing it undermined prior agreements valued at ₱200 million and disrupted commercial interests; this led to temporary restraining orders and interventions that stalled construction until a 2017 memorandum of agreement. , owner of , initially contributed to the project but faced similar integration concerns, contributing to years of negotiation deadlocks. Commuter groups and transport officials have voiced frustration over the absence of seamless transfers, which continues to force inefficient walks or bus connections between LRT-1, MRT-3, and MRT-7 lines, prolonging travel times by up to two hours in peak congestion and amplifying Metro Manila's mobility bottlenecks. Legislative figures, including House Speaker in March 2017, criticized judicial interference in site decisions as obstructive, threatening proceedings against justices to expedite progress. Former MRT-3 general manager Al Vitangcol III announced in January 2017 plans to pursue graft charges against multiple stakeholders for alleged irregularities in negotiations and site selections, underscoring perceptions of favoritism and procedural lapses in early project phases. These criticisms highlight systemic challenges in public-private coordination, though no formal convictions have resulted from such allegations as of October 2025.

Current Status and Future Plans

Developments Through 2025

In May 2025, the (DOTr) terminated the original P2.8-billion contract with previous contractors BF Corporation and Foresight Development and Surveying Co. due to persistent delays in construction. Subsequently, in June 2025, DOTr Secretary Vince Dizon announced that the North Triangle Common Station, along with the MRT-7 line, is targeted for operational readiness by 2027, revising earlier projections amid ongoing design adjustments and procurement reforms. On June 4, 2025, MRT-7 train cars were observed stationed at a depot in , signaling preparatory phases for . MRT-7 train testing was scheduled to commence by the end of 2025, with full commercial operations of the line anticipated in 2026, ahead of the common station's complete linkage. By August 2025, DOTr prioritized selecting a new contractor through a solicited public-private partnership (PPP) mode under the New Government Procurement Act, aiming for award within the year to expedite resumption. The station's design encompasses a 13,700-square-meter concourse at the EDSA-North Avenue intersection, facilitating interchanges among LRT-1, MRT-3, MRT-7, and the forthcoming Metro Manila Subway. Construction on Area C, dedicated to MRT-7 platform concourse and atrium connections, progressed incrementally through 2025, though overall site integration remained limited pending contract finalization. As of October 2025, no full-scale advancement on unified facilities had materialized, with efforts focused on procurement to align with the 2027 deadline.

Projected Timeline and Challenges

The (DOTr) has targeted completion of the North Triangle Common Station by 2027, aligning with the projected full operations of the MRT-7 line. This timeline assumes successful re-tendering of the stalled civil works, with a new contractor expected to be selected via public-private partnership (PPP) by the third quarter of 2025. Partial integration with MRT-7 is anticipated earlier, potentially by late 2025 or 2026, once test runs of the MRT-7 trains commence by year-end 2025. However, full interconnectivity with LRT-1, MRT-3, and future lines remains contingent on resolving Area B construction, which links the existing Areas A and C. Key challenges include the May 2025 termination of the contract with the BF Corporation-Ferrovial-DMCI joint venture due to excessive delays and stalled progress since August 2024, prompting DOTr to deem the prior agreement unviable. The former contractor attributed delays to DOTr's administrative hurdles and design changes, though DOTr inspections highlighted unacceptable stagnation in civil works originally slated for 2019 completion. Securing a new contractor faces risks from bidding complexities and cost escalations, with DOTr evaluating proposals such as one from (LRMC) in September 2025 to expedite Area B. Broader obstacles encompass coordination with interdependent projects like , whose full rollout to 2027-2028 is hampered by right-of-way acquisitions, potentially cascading delays to the common station. Historical patterns of slippage— from initial 2021 targets to indefinite postponements—underscore execution risks in Philippine rail infrastructure, exacerbated by procurement disputes and funding dependencies. DOTr Secretary Vince Dizon emphasized urgency in restarting works by January 2026 to meet the 2027 goal, but observers note that repeated contractor changes could further inflate the P2.8 billion project cost.

Significance and Impact

Urban and Economic Benefits

The North Triangle Common Station is designed to serve as a major interchange hub integrating the LRT Line 1 North Extension, MRT Line 3, , and future , enabling seamless passenger transfers without exiting the facility and thereby reducing overall travel times across Metro Manila's network. This connectivity is projected to alleviate road along and North Avenue by shifting commuters from private vehicles to , potentially easing the daily that affects over 800,000 vehicles in the area. Urban development benefits include fostering (TOD) in the surrounding North Triangle area, which encompasses mixed-use zones with commercial, residential, and recreational spaces adjacent to the station. The station's location near existing business districts like Vertis North and is expected to enhance pedestrian accessibility and promote denser, efficient , opening growth corridors northward from Manila's core. Integration with elevated walkways and bus terminals will further support , improving urban mobility and reducing reliance on congested roadways. Economically, the station is anticipated to lower commuter transportation costs by minimizing transfers and wait times, with estimates suggesting annual savings for users through faster linkages compared to bus or car alternatives. By catalyzing infrastructure-led growth, it aligns with broader Philippine plans to boost via improved and access to centers, potentially generating indirect economic multipliers through heightened commercial activity in . Enhanced efficiency is also projected to support regional economic transformation by facilitating commuter flows to key hubs, though realization depends on timely completion amid ongoing delays.

Evaluations of Project Efficacy

The North Triangle Common Station is designed to serve as a major interchange hub integrating , the LRT Line 1 North Extension, MRT Line 3, and future connections to the and other lines, with a projected daily capacity of up to 500,000 passengers to facilitate efficient transfers and alleviate congestion at EDSA-North Avenue. This integration is intended to reduce average transfer times between lines from over 20 minutes via street-level walks or buses to under 5 minutes through paid-area connections, potentially boosting overall rail ridership in by enabling seamless multi-line journeys. However, no publicly available formal cost-benefit analysis or economic has been released specifically for the station, limiting quantitative assessments of long-term efficacy against its initial ₱2.8 billion estimated cost from 2017. Persistent execution challenges have compromised the project's efficacy in delivering timely benefits. Construction, originally slated for completion by early 2020, remains incomplete as of October 2025, with the terminating the contract with BF Corporation in May 2025 due to six to seven years of delays attributed to contractor performance failures. These delays have cascading effects, hindering Line 7's full operationalization and exacerbating traffic in , where daily commuters already face overload at interim transfer points; for instance, MRT-7's partial service since 2023 has seen lower-than-optimal ridership partly due to incomplete integration. The shift to a new contractor via public-private partnership in 2025 aims to resume work, but historical overruns in Philippine rail projects—often exceeding 50% due to design changes and procurement issues—suggest the station's net benefits may be diminished if final costs substantially exceed projections without corresponding ridership gains. Stakeholder evaluations highlight mixed efficacy prospects. Transportation officials, including DOTr Secretary Vince Dizon, have described the delays as "unacceptable" and emphasized the station's critical role in network interconnectivity, yet critics from business and commuter groups argue that the project's location and phased design fail to address peak-hour bottlenecks effectively, potentially leading to overcrowding similar to existing MRT-3 stations. Independent analyses of comparable Asian interchange stations, such as Singapore's Dhoby Ghaut, indicate that efficacy hinges on reliable operations post-opening, with Philippine projects historically underperforming due to gaps; preliminary DOTr reviews in 2025 propose operational protocols to mitigate this, but efficacy remains unproven absent completed and monitoring data. Overall, while the station's aligns with causal needs for modal integration to cut vehicle use by an estimated 10-15% in northern , execution inefficiencies have eroded confidence in achieving projected socioeconomic returns.

References

  1. [1]
    Unified Grand Central Station – Metro Manila - Future Southeast Asia
    Mar 3, 2025 · The Unified Grand Central Station (also called North Triangle Common Station) is an under-construction urban rail transit station in Quezon City, Metro Manila.
  2. [2]
    Much delayed common station | Philstar.com
    Feb 23, 2025 · The Unified Grand Central Station, or Common Station, in North EDSA, Quezon City, was conceptualized over a decade ago to connect LRT-1, MRT-3, MRT-7.
  3. [3]
    Common station contractor picked this year - BusinessWorld Online
    Aug 3, 2025 · The project aims to link Metro Manila's main commuter rail lines, including LRT-1, MRT-3, MRT-7, and eventually the Metro Manila Subway. The ...
  4. [4]
    LRT-1 operator pitches plan to finish long-delayed common station
    Sep 23, 2025 · LRT-1 operator pitches plan to finish long-delayed common station. By Dexter Barro II. Published Sep 23, 2025 02:52 pm. Copy Link X ...
  5. [5]
    DOTr ends contract for MRT's Unified Grand Central Station
    May 16, 2025 · The Department of Transportation (DOTr) formally issued the notice of termination on the contract to build the Unified Grand Central Station due to delays.
  6. [6]
    DOTr eyes finishing the Unified Grand Central Station by 2027
    May 27, 2025 · [Vantage Point] New DOTr chief faces massive problems in common station project. The P2.8-billion project for the common station was awarded ...<|separator|>
  7. [7]
    North Triangle Common Station construction update - Facebook
    Oct 11, 2025 · The North Triangle common station or also known as the Unified Grand Central station. It was a proposed Station where the LRT 1 Line and the ...Original grand central station design in north edsaDevelopment of MRT 7 North Avenue Station and The ...More results from www.facebook.com
  8. [8]
    Why SM is after the MRT-LRT common station - Rappler
    Jun 14, 2014 · The concept of the common station was born in 2006, when the government started to “court” stakeholders in the vicinity of North Avenue and EDSA ...<|separator|>
  9. [9]
    North Triangle Common Station - Visionarch
    Located in the rapidly developing central business district in North Triangle, Quezon City, the North Triangle MRT-LRT Common Station will form part of ...
  10. [10]
    [Vantage Point] New DOTr chief faces massive problems in common ...
    Mar 1, 2025 · In 2011, the government hatched an ambitious plan for the Common Station that will integrate LRT-1, MRT-3, and MRT-7 to provide seamless ...
  11. [11]
    A traffic plan for the common station project - PPP Center
    Jan 30, 2017 · There will be an Area A, the platform and concourse for LRT 1 and MRT 3, to be constructed by the DOTr; an Area C for MRT 7, to be built by San ...Missing: details | Show results with:details
  12. [12]
    Common station dispute finally resolve - PPP Center
    Sep 28, 2016 · In July 2014, SM Prime secured a Supreme Court stay order stopping the transfer of the common station's site to TriNoma. Then-Transportation ...
  13. [13]
    LRT-MRT common station to rise between SM, Trinoma - Philstar.com
    Sep 29, 2016 · Abaya wanted to move the common station near the Trinoma mall, citing savings in construction cost and convenience to passengers. The agreement ...Missing: dispute | Show results with:dispute
  14. [14]
    MPIC backs commons rail station between Trinoma and SM
    The agency's strategy of building two common stations aims to resolve a conflict with the SM Group. SM Prime Holdings Inc. earlier secured a Supreme Court stay ...Missing: dispute | Show results with:dispute
  15. [15]
    North Triangle Common Station - Wikipedia
    It is located in Bagong Pag-asa, Quezon City, Philippines, and is named after its location, which is at the corner of EDSA and North Avenue.History · Negotiations · Construction · Station layout
  16. [16]
    DOTr cites resolution of dispute on LRT-MRT common station as key ...
    Oct 10, 2016 · The agreement stated that the LRT-MRT common station will be located between SM North and Trinoma malls with a vehicular underpass being ...<|separator|>
  17. [17]
    Common Station (SM North, Trinoma) | PDF | Rapid Transit - Scribd
    Metro Pacific Investments Corporation's Manuel V. Pangilinan agreed on the location of the common station. On Wednesday, all stakeholders will formalize this ...
  18. [18]
    MOA inked on common MRT-LRT station - Philstar.com
    Jan 19, 2017 · Construction of the common station to link Light Rail Transit Line 1 (LRT-1) and Metro Rail Transit (MRT) Lines 3 and 7 is expected to start in December this ...<|control11|><|separator|>
  19. [19]
    DOTr inks MOA for construction of LRT-MRT common station
    Jan 18, 2017 · This comes after the Department of Transportation (DOTr) led Wednesday morning the signing of the memorandum of agreement that would pave the ...<|separator|>
  20. [20]
    Construction of LRT-MRT common station starts Dec. 2017
    Jan 19, 2017 · ... 2017. This after a memorandum of agreement (MOA) was signed Wednesday by the Deartment of Transportation, SM Prime Holdings Inc., Universal ...
  21. [21]
    Common train station contract finally signed - News - Inquirer.net
    Jan 19, 2017 · Common train station contract finally signed ... The railway common station project, stuck in limbo for nearly eight years as mall titans SM North ...Missing: Triangle | Show results with:Triangle
  22. [22]
    DOTr ends deal with LRT, MRT common station contractor over delays
    May 16, 2025 · The Department of Transportation (DOTr) has terminated its contract with the construction and engineering consulting firms responsible for building the Unified ...Missing: selection | Show results with:selection
  23. [23]
    Common station contractor blames project delays on DOTr - News
    May 21, 2025 · Embattled contractor of the Unified Grand Central Station defended itself after the DOTr formally terminated its contract for the project.Missing: details | Show results with:details
  24. [24]
    Unified Grand Central Station contractor blames DOTr payment delays
    May 21, 2025 · The contract for the construction of the common station was awarded in 2019 to BFC-FSDC, a firm of the late former Metropolitan Manila ...Missing: details | Show results with:details
  25. [25]
    DOTr seeks new contractor for Unified Grand Central Station via PPP
    May 23, 2025 · Once completed, the common station will provide seamless access between Light Rail Transit Line 1 (LRT-1) and MRT Lines 3 and 7. Originally ...Missing: details | Show results with:details
  26. [26]
    DOTr eyes new builder for common station by Q3 | ABS-CBN News
    May 20, 2025 · Dizon said the DOTr is still studying how they will bid out the project but said he is leaning towards a Public Private Partnership (PPP). “ ...<|separator|>
  27. [27]
    Common Station reboots via PPP - Daily Tribune
    May 16, 2025 · The Department of Transportation (DoTr) is seeking a swift restart of the long-delayed P2.8-billion Common Station project.Missing: agreement | Show results with:agreement
  28. [28]
    Deal reached: LRT-MRT common station between SM North, TriNoma
    Sep 28, 2016 · The proposed Light Rail Transit (LRT) and Metro Rail Transit (MRT) common station will be constructed between SM North EDSA and TriNoma malls.Missing: rationale | Show results with:rationale
  29. [29]
    DOTr inks deal on common station construction
    Feb 13, 2019 · The Department of Transportation (DOTr) on Wednesday signed a contract with a private consortium for the construction of Area A of the Unified Grand Central ...
  30. [30]
    Knock-on delay - Manila Standard
    Mar 5, 2025 · THE ground-breaking ceremony of the North Triangle Common Station in Metro Manila was held nearly eight years ago – on Sept. 29, 2017–which ...
  31. [31]
    DOTr plans to revoke contract for Unified Central Station connecting ...
    Mar 6, 2025 · The DOTr plans to revoke the government's contract with the builder of the Unified Grand Central Station in Metro Manila.Missing: selection | Show results with:selection
  32. [32]
    Railway Operations | Light Rail Transit Authority
    ... Line 1 to North Avenue of Line 3, with 3 additional stations namely: Balintawak, Roosevelt and a Common Station. The opening of Balintawak Station and Roosevelt ...
  33. [33]
    MRT-7, common station set to be operational by 2027, says DOTR
    Jun 5, 2025 · The Department of Transportation is aiming to complete the long-delayed MRT-7 project by 2027, according to agency chief Vince Dizon.Missing: rationale integration
  34. [34]
    Take a look at the North Avenue Common Station project - Philkotse
    Mar 29, 2021 · Take a look at the North Avenue Common Station project. Updated Mar 29, 2021. Same topic: Latest Traffic Updates. At least one component of the ...
  35. [35]
    Opening of common station for train lines postponed anew - ABS-CBN
    Located in North Edsa, Quezon City, the Unified Grand Central Station will feature a 13,700-square meter concourse area and will interconnect the Light Rail ...
  36. [36]
    Edsa Common Station construction done by March this year
    Mar 5, 2022 · ... North Triangle Common Station, along Edsa in Quezon City March 1, 2022. ... DOTr to improve mobility and connectivity. “So, in the near ...Missing: proposal | Show results with:proposal
  37. [37]
    A Sneak Peek on The Unified Grand Central Station | Bria Homes
    The Unified Grand Central Station is built between the two previously mentioned malls, SM North EDSA and Trinoma mall, which guarantees equality and fair ...
  38. [38]
    DOTr Ends Common Station Contract Over Delays - OneNews.PH
    May 17, 2025 · Due to excessive delays in civil works, the Department of Transportation (DOTr) has terminated its deal with the joint venture tasked to build ...Missing: causes | Show results with:causes
  39. [39]
    DOTr ends deal with common station project contractor - GMA Network
    May 16, 2025 · The Department of Transportation (DOTr) on Friday announced the termination of agreement with the contractor tapped to build the common station for LRT1, MRT3, ...
  40. [40]
    Commuters' wait continues: DOTr ends common station contract ...
    May 16, 2025 · The Department of Transportation (DOTr) has terminated its contract with the consortium tapped to build the Unified Grand Central Station due to “excessive ...
  41. [41]
    The DOTr has officially issued a notice of termination against BF ...
    May 15, 2025 · The DOTr has officially issued a notice of termination against BF Corporation and Foresight Development and Surveying Company (BFC-FDSC) ...
  42. [42]
    DOTr terminates Common Station contractor over excessive delays
    May 16, 2025 · The Department of Transportation (DOTr) has issued a notice of termination against the contractor for the Common Station project, citing excessive delays.
  43. [43]
    DOTr ends common station contract over delays - Philstar.com
    May 17, 2025 · The Department of Transportation (DOTr) has terminated its deal with the joint venture tasked to build the common station for Metro Manila railways.<|separator|>
  44. [44]
    After a year, LRT-MRT common station problem still unsolved
    Nov 25, 2015 · A compromise agreement between all stakeholders has yet to be signed.Missing: criticisms | Show results with:criticisms
  45. [45]
    DOTr inks MOA for construction of LRT-MRT common station - News
    Jan 18, 2017 · In September last year, Transportation Secretary Arthur Tugade gathered the stakeholders of the common station to end the impasse by signing a ...Missing: negotiations | Show results with:negotiations
  46. [46]
    Speaker warns SC justices on common station project | Inquirer News
    Mar 9, 2017 · Speaker Pantaleon Alvarez on Wednesday threatened to impeach Supreme Court justices who would insist on blocking the construction of a ...
  47. [47]
    Vitangcol eyes filing graft case vs. MRT-LRT common station ...
    Jan 19, 2017 · Former MRT-3 General Manager Al Vitangcol III on Thursday said he is in talks with several groups about filing a graft case against ...
  48. [48]
    DoTr reviews LRMC proposal to finish Unified Grand Central Station
    Sep 26, 2025 · In May, the DoTr issued a notice of termination to the contractors of the Unified Grand Central Station, also known as the common station for ...
  49. [49]
    Full operation of MRT-7 delayed until 2027 or 2028 - Easy Rock
    While 12 out of the 14 planned stations are expected to open by the end of 2025, the entire line won't be fully operational until 2027 or 2028 due to right-of- ...
  50. [50]
    Philippines aims to restart EDSA central train station project in Jan
    Jun 23, 2025 · The common station is designed to have an intermodal integrated system underneath it, allowing commuters to transfer and travel by buses, ...
  51. [51]
    [PDF] full speed ahead: revitalizing the philippine rail transport system
    Feb 6, 2025 · Station and the MRT 3 North Avenue Station at the common station will help reduce travel time, lower transportation cost for commuters ...
  52. [52]
    Vertis North - Wikipedia
    Vertis North is a 29-hectare (72-acre) transit oriented mixed-use development in Quezon City, Metro Manila, Philippines. ... North Triangle Common Station, which ...
  53. [53]
    [PDF] Accelerating Infrastructure - - Philippine Development Plan
    Line 1 North Extension Project – Common Station. / Unified Grand Central ... These approaches will yield economic gains. 871 through lower transport cost ...
  54. [54]
    'Let's move on': DOTr to scrap common train station deal - Rappler
    around six to seven years so far — are already “unacceptable,” Transportation Secretary Vince Dizon said in a media ...Missing: criticisms | Show results with:criticisms<|separator|>
  55. [55]
    DOTr to terminate contractors over delays in Duterte-era ... - InsiderPH
    The Department of Transportation (DOTr) is preparing to take action against the contractors of the Unified Grand Central Station, a critical hub linking Light ...
  56. [56]
    DOTr reviews LRMC proposal to finish long-delayed Common Station
    Sep 25, 2025 · The Department of Transportation reviews LRMC's proposal to complete the long-delayed Unified Grand Central Station, aiming for seamless ...