Project Unigauge

Project Unigauge is an ongoing initiative by , launched on 1 April 1992, to standardize the country's diverse rail network by converting meter gauge (1,000 mm) and narrow gauge (762 mm and 610 mm) lines to the broad gauge of 1,676 mm (5 ft 6 in), enabling uniform operations across the system. The primary objectives of the project include improving connectivity to underdeveloped regions, facilitating faster and more efficient freight and passenger transport, and reducing delays at gauge breaks, thereby supporting national under the principle of "one nation, one gauge." As part of this effort, has progressively converted over 21,000 km of non-broad gauge lines to broad gauge since inception, with no fixed completion timeline; annual targets are set based on resource availability. By March 2025, the broad network had expanded to 69,512 route kilometers, comprising nearly the entire ' total route length of approximately 70,000 km, with ongoing targeting the remaining meter and narrow sections primarily in remote and heritage areas. In the 2024-25, over 259 km of was commissioned, reflecting continued momentum toward near-complete unification. As of November 2025, the project is nearly complete, with only a few hundred kilometers of non-broad lines remaining. This has significantly enhanced the network's capacity, with broad lines now supporting high-speed and heavy-haul operations essential for India's transport infrastructure.

Background and History

Origins and Launch

Project Unigauge was officially launched on 1 April 1992 by as a key initiative under the Eighth Five-Year Plan (1992-1997), marking a strategic shift toward gauge unification. The project aimed to standardize the rail network on the 1,676 mm (5 ft 6 in) broad gauge to streamline operations and boost capacity. The decision to adopt a uni-gauge policy was formalized in 1992 by the , addressing the inefficiencies of the multi-gauge system inherited from British colonial rule, which had resulted in fragmented networks and operational bottlenecks. This eliminated the need for at gauge breaks, promoting seamless connectivity across the country. The initial announcement came in the Railway Budget speech of February 1992, where the Railway Minister outlined the project's launch to prioritize conversions on high-traffic routes. Government backing was secured through increased allocations in the Eighth Five-Year Plan, elevating gauge conversion funding to 52.5% of total development outlays. The Railway Board played a pivotal role in formalizing the project by sanctioning conversions, directing zonal railways to adhere to guidelines in July 1992, and establishing financial criteria such as a minimum 14% for projects. This structured approach ensured the project's alignment with broader objectives of enhancing transport efficiency and .

Pre-Project Gauge Situation

Prior to the launch of Project Unigauge, the Indian railway network was characterized by a fragmented multi-gauge system inherited from the colonial era and perpetuated through post-independence expansions. As of 1948, shortly after independence, the total route length stood at 54,693 kilometers, comprising 25,170 kilometers of broad gauge (1,676 mm), which accounted for approximately 46% of the network; 24,153 kilometers of metre gauge (1,000 mm), representing about 44%; and 5,370 kilometers of narrow gauge (primarily 762 mm and 610 mm), making up roughly 10%. This diversity in gauges stemmed from colonial-era decisions, where the British administration initially adopted the broad gauge for major trunk lines to accommodate heavier loads and provide stability on long-haul routes, influenced by Lord Dalhousie's policy in the 1850s to prioritize a uniform 5 ft 6 in (1,676 mm) standard for economic viability in India's varied terrain. However, regional variations emerged as private companies and princely states constructed lighter metre gauge lines for cost savings in less densely populated or branch areas, while narrow gauge was selected for hilly and remote regions to minimize construction expenses and navigate sharp curves. Post-independence, expansions continued on existing gauge types without a comprehensive standardization policy, exacerbating the patchwork as new lines were built to connect isolated metre and narrow gauge sections rather than converting them. The multi-gauge configuration created significant operational challenges, particularly at points of gauge breaks where trains could not proceed directly, necessitating transshipment of passengers and freight. These breaks, numbering over 200 by the late 1980s, resulted in substantial delays—often several hours per transfer—and increased handling costs due to the labor-intensive reloading of goods onto different rolling stock. Connectivity barriers were acute, as the network's fragmentation limited seamless movement across regions; for instance, key routes linking major economic centers required multiple gauge changes, hindering efficient freight transport of commodities like coal and food grains. Higher maintenance expenses arose from maintaining separate inventories of locomotives, wagons, and infrastructure tailored to each gauge, while safety risks escalated during transshipments, contributing to inefficiencies in overall capacity utilization. From to the , the railway network grew modestly from approximately 54,700 kilometers to around 60,000 kilometers, reflecting incremental additions amid resource constraints and prioritization of over gauge unification. However, this expansion without amplified the pre-existing inefficiencies, as the proliferation of gauge breaks strained and escalated operational costs, underscoring the need for a unified system by the early .

Objectives and Rationale

Strategic Goals

Project Unigauge, launched in , aims primarily to establish a single broad spanning the entirety of India's railway system, facilitating uninterrupted train operations and embodying the principle of "one country, one gauge." This unification seeks to standardize track widths at 1,676 mm, eliminating the fragmentation caused by the historical mix of metre and narrow lines that comprised approximately 38% and 6.5% of the , respectively, at the project's inception. By prioritizing selective conversions, the initiative targets the development of alternate routes parallel to congested broad trunk lines, thereby enhancing overall capacity and supporting industrial growth in underdeveloped regions. A core policy directive under Project Unigauge mandates the conversion of all and narrow lines to broad gauge, with exceptions made solely for routes or those deemed uneconomical due to low traffic volumes or challenging terrain. This approach aligns with broader national development frameworks by integrating the standardized network with initiatives such as the Dedicated Freight Corridors, which operate exclusively on broad gauge to optimize freight movement without interruptions. The policy underscores a commitment to national integration, enabling efficient connectivity across diverse geographical and administrative boundaries that were previously isolated by gauge disparities. Central to these goals is the emphasis on eliminating gauge breaks—points where track widths change, necessitating costly and time-consuming transshipment of goods and passengers. By enabling direct through-running of trains, the project minimizes logistical bottlenecks and hazards associated with manual handling, thereby streamlining operations and fostering a cohesive rail ecosystem that supports high-speed and freight corridors. This strategic focus on seamlessness positions the unified broad gauge as a foundational element for modernizing India's rail infrastructure in line with long-term national plans.

Economic and Social Benefits

The unification of railway gauges under Project Unigauge has delivered significant economic benefits by eliminating at gauge breaks, thereby reducing costs, time delays, and associated hazards in freight movement. This streamlining has enhanced overall transport efficiency, with meter gauge lines historically operating at a higher cost ratio (164%) compared to broad gauge (80%), allowing for improved financial viability post-conversion. Additionally, the project has increased freight-carrying capacity and provided alternate routes to relieve congestion on major broad gauge trunk lines, fostering industrial growth particularly in underdeveloped regions by improving to markets and resources. On the social front, Project Unigauge has improved access to remote and backward areas, enhancing passenger mobility and through better transport facilities. The initiative supports national integration by linking economically disparate regions, serving as a key instrument in and unifying diverse parts of the country. Construction activities under the project have generated employment opportunities in involved regions, contributing to local economic upliftment. Furthermore, the expanded broad gauge network facilitates by enabling smoother connectivity to scenic and cultural sites, while long-term impacts include accelerated and modernization of the rail infrastructure, promoting .

Implementation and Process

Conversion Methodology

The conversion methodology under Project Unigauge involves a systematic, engineering-driven approach to transform narrow gauge (typically 762 ) and meter gauge (1,000 ) tracks to the standard broad gauge of 1,676 , ensuring compatibility with the national rail network. This process prioritizes minimal disruption to operations while adhering to ' standards for , formation, and safety. The process begins with detailed of the route, including an engineering-cum-traffic survey to evaluate , conditions, and feasibility for broad conversion. Following approval, land acquisition occurs to widen the formation to broad gauge standards of 6.85 m on embankments and 6.25 m in cuttings (excluding side drains). Existing tracks are then dismantled during planned traffic blocks lasting 15 to 90 days, where rails, sleepers, and fittings are removed using manual labor and basic equipment. Realignment follows, adjusting curves and gradients to meet broad specifications, often requiring earthwork for side slopes and cess widening. Bridges and culverts are widened or replaced to support the increased and axle loads; for instance, abutments may be extended, and superstructures rebuilt with minimal interruption to river or road . New track installation employs techniques like rail lifting and relaying, where old rails are lifted and repositioned if reusable, or entirely new 52 kg/m or 60 kg/m rails are laid alongside prestressed concrete (approximately 1,540 per km) using the telescopic method—transporting components to base depots for assembly and on-site placement. Heavy machinery plays a critical role in expediting the work: ballast regulators distribute stone to a depth of 300 mm for high-traffic sections, while tampers—such as light Phooltas for initial packing (up to 50 km/h speeds) and heavy dynamic tampers for final stabilization (up to 100 km/h)—consolidate the . is packed to achieve the required cushion and drainage, with fastening systems securing rails to . Simultaneously, signaling upgrades are coordinated, installing new electro-mechanical or electronic systems, track circuits, and signals compatible with operations. Safety protocols are integral throughout, mandating temporary line closures during peak phases and rerouting via alternative paths to maintain connectivity. Work sites adjacent to live tracks require block protection, with mandatory briefings for laborers on hazards like overhead and moving trains; all activities occur under supervised blocks, and the converted section undergoes inspection by the Commissioner of Railway Safety before reopening.

Planning and Prioritization

The planning and prioritization of route conversions under Project Unigauge were guided by a set of strategic criteria aimed at maximizing and economic impact. High-traffic volume lines were prioritized to alleviate on existing broad gauge networks and enhance , as these routes offered the greatest potential for immediate relief and revenue generation. Economic potential played a central role, with selections favoring connections to ports, industrial centers, and areas with growth prospects to facilitate trade and while ensuring projects yielded a minimum 14% return under the method. Connectivity to major hubs was emphasized through the of alternative broad gauge routes and new links between stations already on the broad gauge network, reducing the need for costly doublings and minimizing delays. Additionally, linkage to backward areas was incorporated to address social and strategic needs, promoting balanced . A phased approach structured the implementation, beginning with trunk lines carrying substantial freight and loads before progressing to lines, ensuring a logical build-up of the unified network. This sequencing was determined through collaborative input from zonal railways, which provided operational insights, and the Railway Ministry, which aligned selections with national priorities. Projects were categorized into priorities such as for near-complete works, A2 for viable high-impact routes, and B/C for strategic or socially desirable lines, allowing for targeted execution within defined timelines. Budget allocation for conversions was integrated into ' Five-Year Plans, with the Eighth Plan (1992–1997) targeting approximately 6,000 km of conversion to establish foundational connectivity. Subsequent plans, including the Ninth (1997–2002), maintained similar annual outlays to sustain momentum, funded primarily through the Railways' internal resources supplemented by external support for socially oriented projects. Coordination with state governments was essential for securing land acquisition and environmental clearances, particularly for routes traversing diverse terrains or populated regions, ensuring timely project approvals without compromising regulatory standards. Once prioritized, selected routes proceeded to technical conversion steps, such as track laying and signaling upgrades, to integrate seamlessly into the .

Progress and Milestones

Historical Progress

Project Unigauge was officially launched by on April 1, 1992, with the aim of systematically converting and narrow gauge lines to the 1,676 mm to create a unified national network. In its initial phase from 1992 to 2000, the project achieved the conversion of approximately 5,000 km of track, marking a significant departure from the slower pace of prior decades where only about 3,100 km had been converted between 1980 and 1992. The period from 2000 to 2010 saw accelerated momentum, with cumulative conversions under the project surpassing 13,000 km by the early 2000s, reflecting intensified efforts to integrate key routes and reduce bottlenecks. Annual targets during the Ninth Five-Year Plan (1997–2002) aimed for 3,710 km of conversions, though achievements reached 1,740 km in the first three years, prompting adjustments to prioritize strategic lines. By 2010, the project's progress had expanded the broad gauge network substantially, supporting broader economic connectivity. From 2010 to 2024, conversions advanced further with approximately 12,000 km added to the , driven by policy accelerations in the under Project Unigauge initiatives. This phase emphasized high-impact routes, with annual achievements such as 837 km in 2010–11 and ongoing targets averaging 800–1,000 km yearly to complete the network integration. The statistical evolution underscores the project's impact: route length grew from 25,170 km in (46% of the total 54,693 km network) to 66,820 km by March 2024 (96.59% of the 69,181 km total), while metre gauge declined from 24,153 km to 1,159 km and narrow gauge from 5,370 km to 1,202 km. These shifts, primarily through Unigauge efforts, enhanced and capacity across the system. Since its inception, the project has resulted in approximately 25,000 km of conversions to .

Key Converted Lines

One of the flagship achievements of Project Unigauge in the was the conversion of the Lumding-Silchar metre line, spanning 210 km through challenging including tunnels and bridges, completed in March 2015 at a cost of approximately Rs 3,500 crore. This project integrated the with the national broad network, enabling direct connectivity from to over a total route length of about 375 km and supporting new express trains for improved and . In Southern , the conversion of the Mysore-Chamarajanagar metre gauge , covering 61 km and linking to forested hill regions near , began in 2007 with metre gauge services suspended to facilitate the work, and was fully commissioned for passenger traffic in November 2008 at a cost of Rs 150 crore. This upgrade enhanced access to eco-tourism areas and agricultural belts in , allowing for faster and more reliable broad gauge services while preserving connections to sensitive hill ecosystems. Western India's arid regions saw extensive metre-to-broad conversions under Project Unigauge, particularly in and , to bolster freight and passenger movement across desert corridors. Notable among these was the phased conversion of routes like Ahmedabad-Mahesana and extensions toward , which improved logistics for mineral transport and interstate in the North Western and Railway zones. Across all zones, Project Unigauge has resulted in approximately 25,000 km of flagship conversions to broad gauge, enabling the introduction of high-speed express trains and significantly enhancing .

Exceptions and Challenges

Scrapped Lines

Under Project Unigauge, 9 lines totaling 382.2 km were scrapped rather than converted to broad gauge, consisting mostly of short or branches with insufficient economic justification for continued operation. These routes were abandoned primarily due to low passenger and freight traffic, high maintenance costs relative to usage, from more efficient , and occasional environmental considerations that made rehabilitation impractical. A key example is the Road–Pani Mines line, a 49 km metre gauge route originally constructed in the early to transport from local mines. Operations ceased in the late , and the line was fully dismantled in the after assessments deemed conversion unviable given its declining industrial relevance and sparse traffic. Other scrapped lines included short hauls such as industrial branches in and , where reduced activity and alternative logistics options led to their decommissioning without replacement. By scrapping these low-viability lines, Project Unigauge freed up financial and engineering resources for prioritizing high-impact conversions elsewhere, resulting in negligible overall loss to the network's and capacity.

Preserved Heritage Lines

Under Project Unigauge, a select number of railway lines have been exempted from gauge conversion to safeguard their significant cultural, historical, and touristic importance. These preserved lines total five routes spanning 415.6 km as of 2024, predominantly narrow , allowing them to retain their original configurations as living museums of India's colonial-era rail engineering. Key examples among these preserved lines include the (DHR), a 88 km narrow-gauge (610 mm) line operational since 1881 that ascends the Himalayas from New Jalpaiguri to , recognized as a in 1999 for its innovative zig-zag and loop engineering. The (NMR), a 46 km metre-gauge connecting Mettupalayam to since 1908, was designated a in 2005 due to its unique Abt rack system navigating steep gradients. Other preserved lines are the (96.6 km, 762 mm narrow gauge, 2008), (164 km, 762 mm narrow gauge, preserved for scenic and historical value), and (21 km, 610 mm narrow gauge, retained for tourism). The criteria for exemption include World Heritage status where applicable, exceptional engineering feats like helical loops or rack mechanisms, and substantial revenue that surpasses the operational advantages of unification under broad . These factors ensure that the cultural and economic benefits of preservation outweigh the goals of Project Unigauge, particularly for routes serving as global tourist icons with minimal into the main network. Maintenance of these heritage lines involves dedicated funding to sustain steam locomotive operations and limit modernization to essential safety upgrades, preserving authenticity while ensuring operational viability. For instance, Indian Railways allocates specific budgets for steam engine overhauls and track upkeep on the DHR and NMR, enabling regular heritage steam runs that draw international visitors. This approach includes investments in historic rolling stock restoration, as highlighted in UNESCO conservation reports, to maintain the lines' original charm without compromising their exemption status.

Current Status and Future Outlook

Network Coverage as of 2025

As of March 2025, Project Unigauge has extended broad gauge (1,676 mm) tracks to 69,512 km, encompassing over 99% of ' total route network of approximately 70,000 km. This near-universal standardization has streamlined operations across the country, minimizing delays and enabling seamless connectivity for freight and passenger services. The project's success is evident in the conversion of key arterial routes, leaving only marginal segments on alternative gauges. The remaining non-broad gauge infrastructure, comprising metre gauge (1,000 mm) and narrow gauge (762 mm or 610 mm) lines, totals under 1,000 km and consists mostly of isolated branches in remote or ecologically sensitive areas, including metre gauge segments like the 162 km Mavli-Marwar in . These pockets are often retained for specialized uses, such as tourist heritage operations, rather than integration into the main network. Recent advancements under the project include the completion of final Northeast links, notably the broad gauge extension connecting to the national grid in September 2025, enhancing regional accessibility. Similarly, in island territories like the Andamans, partial retention of narrow gauge lines has preserved historical segments while allowing selective conversions for . Complementing these gauge unification efforts, has reached 99% of the broad gauge network by 2025, with over 68,700 km now powered by electric traction, significantly boosting and reducing operational costs. This synergy between gauge conversion and electrification has amplified Project Unigauge's impact, supporting higher train speeds and capacities across the unified network.

Remaining Conversions and Plans

As of November 2025, Project Unigauge has a few pending conversions totaling approximately 500 km, focused on challenging remote hill sections in the Himalayan regions, such as ongoing work in the Northeast Frontier Railway's network linking areas like and . Select metre gauge lines in , including stretches like Marwar-Mavli and Udaipur-Himmatnagar, also remain targeted for conversion to address isolated segments. The project continues with no fixed completion date, setting annual targets based on resource availability. Integration with mega-projects forms a key part of the strategy, with remaining lines planned to link seamlessly into corridors, such as the Mumbai-Ahmedabad high-speed route, and dedicated freight corridors to support enhanced passenger and cargo movement. Despite potential hurdles like rugged Himalayan terrain requiring specialized engineering and occasional funding delays amid competing infrastructure priorities, has reaffirmed its commitment to 100% broad gauge adoption across the operational network, preserving only select sections. This approach ensures sustained progress toward a unified, modern rail system.

References

  1. [1]
    Indian Railways: Glorious History - English Releases
    The Project Unigauge was launched on April 1, 1992 to develop the backward regions and to connect important places with broad gauge network. So far over 13000 ...
  2. [2]
    [PDF] Conversion of rail track to broad gauge
    No specific time for completion of Project Unigauge has been laid down. Targets are fixed every year depending upon the availability of adequate resources, ...
  3. [3]
    Welcome to Official Website of CORE - Indian Railway
    Indian Railways electrified 62,119 Route Kilometers (RKMs) till March 01, 2024 which is about 94% of the total broad-gauge network (65,775 RKMs) of Indian ...
  4. [4]
    None
    Nothing is retrieved...<|control11|><|separator|>
  5. [5]
    Ministry of Railways: Year End Review 2024 - PIB
    Dec 29, 2024 · Indian Railways have achieved total commissioning of 3433 Km from 01.04. 2024 to till date, which includes 1158 Km New Line, 259 Km Gauge ...
  6. [6]
    [PDF] Has the project been managed so as to achieve its objectives in a ...
    'Project Unigauge' was launched by Indian Railways on 1 April 1992 with the objective of selective conversion of meter gauge and narrow gauge to broad gauge ...
  7. [7]
    [PDF] The “Evil” of Railway Gauge Breaks: A Study of Causes in Britain ...
    Feb 25, 2022 · Following an analysis of gauge breaks in Britain, India, Japan and Manchuria, the thesis concludes that whether a gauge break problem arose and ...
  8. [8]
    [PDF] THIRD REPORT
    Budget for 1992-93 the Railway Minister in his budget speech in February. 1992 announced the launching of project Unigauge wherein he declared the.
  9. [9]
    [PDF] Answer
    As on 31st March, 1948, the total railway lines in terms of route kilometres was 54,693 kilometres comprising 25,170 kilometres broad gauge, 24,153 kilometres ...
  10. [10]
  11. [11]
    Gauge Policy of the Colonial Government: A Reappraisal
    In India, the question of gauge had been allowed to drift, and as the gauge had grown, the difficulties of solving the problem increased gradually relatively ...Missing: multiple era
  12. [12]
    [PDF] Riding the Tracks of Time: Indian Railways – An Unfinished Revolution
    Ultimately, the decision was made for the metre gauge to be 3 feet 3 and 3/8 inch wide, and narrow gauge to be 2 feet. It would have been more cost-effi- cient ...
  13. [13]
    [PDF] VOLUME – I - NAIR - Indian Railway
    gauges. Considerable delay to movement of traffic and additional expense occur due to a break in gauge. This problem is of such importance that serious ...
  14. [14]
    Factors; Distribution and Improvement of Indian Railways
    As on 15 August 1947, Indian Railways consisted of 65,217 km out of which 10,523 km went to Pakistan, leaving India with 54,694 km. Phenomenal growth of Indian ...
  15. [15]
    [PDF] The Indian Railways Report - Dr. Rakesh Mohan
    The mission of IDFC is to: • lead private capital to commercially viable infrastructure projects in India;. • provide a strong policy advisory role to the ...<|control11|><|separator|>
  16. [16]
    [PDF] SURVEY & CONSTRUCTION OF RAILWAY LINES CHAPTER 3 ...
    Indian Railways, therefore, took up project uni-gauge in 1992 to do the large scale gauge conversion of selected MG/NG lines to BG for developing alternative ...
  17. [17]
    Gauge Conversion - BrainKart
    Aug 8, 2016 · A number of projects have recently been taken up by Indian Railways for converting railway lines from meter gauge to broad gauge.
  18. [18]
    [PDF] Railway Convention Committee (1999) - IRFCA.org
    The IX Plan Working Group on Railways in their Report have stated that project unigauge was conceived with the objective of generating transport capacity by ...
  19. [19]
    [PDF] Answer
    (ii) The policy followed for selection of routes for gauge conversion under Project Unigauge has been as under: -. To take up conversion of lines to develop ...
  20. [20]
    Indian Railways Civil Engineering Portal
    As on 31.03.2020, the route length of Indian Railways covered 67,956 kms with running track length of 99,235 kms. The total trackage including yards, sidings ...
  21. [21]
    Gauge Conversion on Railways - English Releases
    Aug 26, 2011 · 1516 kilometres and 837 kilometres of Metre Gauge//Narrow Gauge lines were converted into Board Gauge lines during 20009-10 and 2010-11 ...Missing: 2000-2010 | Show results with:2000-2010
  22. [22]
    Suresh Prabhu Inaugurates Landmark Lumding-Silchar (Assam ...
    Mar 27, 2015 · The phase-II consists of gauge conversion of three sections namely; Badarpur – Kumarghat, Baraigram - Dullabcherra and Silchar-Jiribam, which ...
  23. [23]
    Suresh Prabhu Flags Off First Passenger Carrying Train Between ...
    Nov 21, 2015 · Today we are introducing a new train between Guwahati and Silchar after conversion of Lumding-Silchar Metre Gauge line into Broad Gauge.
  24. [24]
    Chamarajanagar-Mysore train flagged off - Business Standard
    Jan 29, 2013 · ... gauge trains were suspended in January 2007 and conversion of the track was taken up at a cost of Rs. 150 crore. It received a sizeable ...
  25. [25]
    Mysore-Nanjangud all set to be upgraded to broad gauge - Oneindia
    Jan 2, 2007 · The gauge conversion work, approved by the Railway Board, would be taken up in two phases. The project was approved in 2001 and funds were ...
  26. [26]
    [IRFCA] Indian Railways FAQ - Gauges in India
    In early 2000, about 17,000 route km was metre gauge with a steady decline over the years as they were converted to broad gauge.
  27. [27]
    The Great Indian Railway Part 1-Project Unigauge - Pradyota
    Sep 2, 2016 · Project Unigauge was first officially started in 1990-91 with a vision to convert all the tracks in the country to Broad Gauge standard.
  28. [28]
    Running since 19th Century, five narrow gauge rail lines to stay
    Jun 10, 2018 · The Indian Railways has decided to preserve the five oldest, working narrow gauge lines dating back to its colonial era.
  29. [29]
    Mountain Railways of India - UNESCO World Heritage Centre
    This site includes three railways. The Darjeeling Himalayan Railway was the first, and is still the most outstanding, example of a hill passenger railway.
  30. [30]
    None
    Nothing is retrieved...<|control11|><|separator|>
  31. [31]
    Mountain Railways of India - UNESCO World Heritage Centre
    The State Party's investment in the maintenance of steam engines and historic rolling stock, and in one case the construction of new engines, is to be ...
  32. [32]
    Tracks of Transformation: Railways Redefining the Northeast - PIB
    Sep 13, 2025 · The 152 km Badarpur–Agartala line was converted to broad gauge in April 2016. The Agartala–Sabroom line (112 km) extended railways till the ...Missing: length | Show results with:length
  33. [33]
    North Western Railway / Indian Railways Portal
    Tuesday, November 4, 2025 16:00:05 IST ... Way materials over Udaipur-Dungarpur section in connection with Udaipur-Himmatnagar Gauge conversion project.
  34. [34]
    Indian Railways Industry | Network, Growth & Insights - IBEF
    As of March 2025, Indian Railways had electrified 68,701 km (98.83%) of its 69,512 km broad-gauge network, with the remaining 811 km expected to be completed ...