Fact-checked by Grok 2 weeks ago

Rogfast

Rogfast, officially the Rogaland Fixed Link, is a subsea road tunnel project under construction in Rogaland County, Norway, comprising the 27-kilometer-long Boknafjord Tunnel that will connect the municipalities of Randaberg near Stavanger and Bokn across the Boknafjord. The tunnel forms a key segment of the European route E39 coastal highway, contributing to Norway's national goal of eliminating ferry dependencies along the route to enhance connectivity and reduce travel times between western Norway and the north. Upon completion, expected in 2033, Rogfast will hold the records for the world's longest and deepest subsea road tunnel, extending 26.7 kilometers with a maximum depth of 392 meters below sea level. The project involves twin tunnels with a of 10.5 meters, driven through approximately 15 meters apart, employing advanced tunneling techniques to navigate challenging geological conditions at extreme depths. , awarded to contractors including for a valued at around NOK 5 billion, began with preparatory works and is advancing through simultaneous operations from multiple access points to meet the ambitious timeline. By replacing ferry services that currently handle significant traffic, Rogfast is projected to substantially cut durations, boosting in the region while demonstrating Norway's prowess in subsea .

Background and Proposal

Initial Planning and Approval (2017)

The Norwegian Ministry of Transport and Communications submitted Proposition No. 105 S (2016–2017) to the on April 5, 2017, outlining plans for the construction and financing of the E39 Rogfast subsea tunnel project across the municipalities of Randaberg, Kvitsøy, and Bokn in county. This proposition detailed the tunnel's role in establishing a ferry-free connection over Boknafjorden and Kvitsøyfjorden, spanning approximately 27 kilometers to link the region with northern . On May 23, 2017, the Storting approved the project, committing to an initial budget of 16.8 billion Norwegian kroner for the development, which included twin tunnels with a design speed of 110 km/h and a maximum depth of 392 meters below sea level. The approval emphasized the tunnel's integration into the broader E39 coastal highway initiative, projected to reduce travel time between Stavanger and Bergen by 40 minutes by eliminating ferry dependencies. At the time of approval, completion was targeted for 2025–2026, with early activities initiated to select contractors for the ambitious subsea engineering feat. The planning phase in 2017 built on prior feasibility studies, focusing on route optimization, geological assessments, and environmental impact evaluations to ensure technical viability and .

Strategic Context within E39 Highway

The constitutes Norway's principal coastal highway, extending roughly 1,330 kilometers along the western seaboard from to and linking major population centers including , , , and . The route currently incorporates seven ferry services within to traverse fjord barriers, resulting in operational delays, limited capacity, and susceptibility to meteorological interruptions that compromise punctuality and safety. Norway's Coastal Highway Route E39 initiative, overseen by the Norwegian Public Roads Administration, seeks to render the corridor ferry-free via subsea tunnels, bridges, and upgraded roadways, targeting a reduction in end-to-end travel duration from approximately 21 hours to 13 hours while elevating efficiency, reliability, and capacity for both passenger and freight movement. This transformation addresses longstanding infrastructural deficiencies in the fjord-dominated terrain, promoting across western Norway's disparate municipalities and bolstering resilience against ferry-dependent vulnerabilities. Rogfast forms an integral segment of this strategy, substituting the Mortavika–Arsvågen ferry with a 26.7-kilometer twin-tube subsea tunnel linking Randaberg municipality adjacent to Stavanger with Bokn, thereby establishing uninterrupted connectivity between southern Rogaland's energy sector hubs and northern coastal extensions of E39. By circumventing this pivotal fjord crossing, Rogfast mitigates a key temporal and logistical chokepoint, facilitating swifter regional linkages essential for industrial logistics, emergency response, and tourism along the E39's southern flank.

Project Timeline and Developments

Early Construction and Halt (2018–2019)

Construction on the subsea tunnel began on January 4, 2018, marking the initial phase of site preparation and rock blasting at the planned entrance near Randaberg. These early activities involved establishing access points and preliminary excavation for the tunnel portals, serving as preparatory steps ahead of the main undersea boring contracts. By mid-2018, contracts for these initial packages had been awarded, with focus on surface-level infrastructure to support subsequent tunnelling. Progress halted in October 2019 when the Norwegian Public Roads Administration (Statens vegvesen) canceled the tender for the primary subsea tunnelling works. The decision stemmed from updated budgetary assessments revealing potential cost overruns, prompting a comprehensive review to reassess contracting strategies and identify savings. Officials indicated that without adjustments, the project's escalating expenses—initially estimated at around 16.8 billion Norwegian kroner in 2017—threatened fiscal viability, leading to an indefinite postponement of major excavation. In November 2019, Statens vegvesen launched a full-scale to scrutinize all aspects of the project, including design, materials, and supplier bids, with the explicit goal of reducing overall expenditures. This halt preserved resources amid concerns over tender competitiveness and economic pressures, though it delayed the transition from preparatory phases to core tunnelling operations. No significant subsea advancement occurred during this period, as contracts for the 27-kilometer underwater segments remained unawarded.

Revisions and Restart (2020–2021)

In response to the October 2019 halt prompted by projected cost overruns exceeding initial estimates, the Norwegian Public Roads Administration initiated a thorough of the throughout 2020. This assessment focused on challenges, budgetary inaccuracies, and contracting inefficiencies that had inflated anticipated expenses. Key revisions included restructuring the main tunnelling phase into three distinct contracts—covering northern, central, and southern sections—alongside a separate agreement for the 3.5 km Kvitsøy spur , aiming to foster greater competition, reduce reliance on large consortia, and enable bids from smaller specialized firms. The updated plan also incorporated an enhanced cost estimate, raising the total project budget (encompassing the main tunnel and Kvitsøy link) to NOK 24.8 billion, reflecting adjusted forecasts for materials, labor, and risk contingencies. These modifications received governmental approval in late 2020, addressing prior underestimations in geological complexities and supply chain demands for the 26.7 km twin-bore subsea alignment. The revisions prioritized value engineering without altering core design specifications, such as the tunnel's 10.5 m diameter bores and maximum depth of 392 m below sea level. With the restructured framework in place, recommenced in autumn 2021, marking the start of the first major contract for the southern section from Randaberg. This restart aligned with the broader E39 coastal goals, extending the projected completion to 2033 while incorporating phased operations from multiple portals to mitigate risks in the challenging Boknafjord . Subsequent contracts for the remaining sections followed in 2022–2024, validating the 2020 adjustments' effectiveness in stabilizing the timeline.

Ongoing Construction (2022–Present)

Following the revisions and restart in prior phases, major construction contracts for the Rogfast tunnel's primary sections were awarded starting in late 2022. On December 12, 2022, secured a valued at approximately 5 billion (about 5.2 billion) for a significant subsea portion, with work commencing in the first quarter of 2023 and targeted completion by the third quarter of 2029. This was followed by the signing of the second major on January 6, 2023, worth 4 billion, awarded to Norge for additional tunneling works. The third and largest contract, valued at NOK 6.238 billion, was signed on June 11, 2024, with the Implenia Norge AS and Stangeland Maskin AS for the E02 Kvitsøy section—the most complex part of the project, encompassing an 8.8 km two-way with a 10.5 m cross-section. Tunneling operations on this section began with the first blasting () in November 2024, marking the initiation of excavation at this critical midpoint junction site. By late 2023, blasting and excavation were advancing at multiple access points along the 26.7 km route, enabling simultaneous operations across sections to accelerate progress. In September 2025, deployed advanced tunneling intelligence systems, including automated drilling and real-time data analytics, to enhance efficiency and safety in the joint venture's operations. As of October 2025, construction continues without reported major interruptions, with the project on track for opening in 2033, though subject to ongoing monitoring for geological challenges at depths up to 392 m below .

Design and Engineering

Route and Physical Specifications

The Rogfast project centers on the Boknafjord Tunnel, a subsea road connection spanning 26.7 kilometers under the Boknafjord in County, . It links Harestad in Randaberg municipality—near —to Laupland in Bokn municipality, forming a key segment of the E39 coastal . This route bypasses existing services across the fjord, integrating with surface roads and shorter tunnels at each end to create a continuous link. The tunnel comprises twin parallel tubes, each with a 10.5-meter excavated and separated by approximately 15 meters of rock, designed for bidirectional two-lane . Its maximum reaches 392 meters below at the deepest point, surpassing previous subsea road tunnels in depth. The overall underwater portion totals about 27 kilometers across two main sections, with an additional 4-kilometer branch tunnel serving Kvitsøy island.

Construction Techniques and Innovations

The Rogfast tunnels are primarily excavated using the drill and blast method, a standard technique in Norwegian subsea tunneling due to the favorable conditions. Jumbo rigs drill blast holes, followed by controlled blasting, with excavated material loaded by conventional machines and transported by trucks for disposal. This method is preferred over tunnel boring machines for its flexibility in navigating geological variations, though it requires rigorous safety protocols under high hydrostatic pressures reaching 392 meters below . A key innovation involves simultaneous advancement from both tunnel portals, with separate teams toward a central breakthrough point, optimizing progress on the 26.7-kilometer main bores. Extensive pre-drilling and pre-grouting extend 25 meters ahead of the faces to seal fractures and control water ingress, maintaining a minimum 50-meter rock cover above the tunnel to the . Probe up to 50 meters in various configurations further assesses and mitigates risks from weakness zones. Advanced digital tools enhance efficiency and safety, including Epiroc's Tunneling Intelligence system, which provides real-time 3D visualization, machine tracking, and operational reporting to support proactive adjustments at the faces. Construction of deep infrastructure elements, such as 250-meter ventilation shafts with 10-meter diameters, employs mine shaft sinking technology adapted for road tunnels. The project's underground at Kvitsøy, featuring a spiral ramp and at 250 meters depth, represents a engineering feat, integrated via drill and blast with elements for the inner lining. Cross passages spaced every 250 meters facilitate and ventilation. Overall, these techniques incorporate BIM modeling for precise and execution, minimizing environmental impact through targeted grouting and sustainable spoil disposal at sea.

Safety and Risk Mitigation Features

The Rogfast tunnel incorporates a twin-tube design, consisting of two parallel tubes—one for each direction of traffic—connected by safety galleries at regular intervals to facilitate and cross-ventilation in the event of incidents such as fires or accidents. This configuration allows traffic in one tube to continue while the other is isolated for response, mitigating risks associated with the tunnel's extreme length of 26.7 km and maximum depth of 392 meters below . Risk assessments have been integral to the project's design, addressing uncertainties in geotechnical stability, fire propagation, and user safety through and modeling, including probabilistic evaluations of like structural failures or evacuation challenges. The maximum longitudinal has been limited to 5% to reduce braking distances for heavy vehicles during descent and ascent, a revision from initial proposals to enhance and prevent runaway incidents informed by lessons from prior tunnel projects. Technical safety features include advanced tunnel ventilation systems designed for smoke extraction and air quality maintenance during emergencies, alongside emergency preparedness protocols that integrate real-time monitoring for seismic activity, water ingress, and traffic anomalies. risk mitigation draws from broader road tunnel standards, emphasizing compartmentation via the twin tubes and cross passages to contain hazards and enable rapid response, with non-acceptable risks addressed through supplemental measures beyond baseline regulations. These elements collectively aim to achieve levels comparable to or exceeding those of existing subsea tunnels, despite the unprecedented scale.

Economic and Regional Impacts

Transportation and Time Savings

The Rogfast tunnel will establish a direct subsea road link across the Boknafjord as part of the E39 coastal highway, replacing the Mortavika–Arsvågen and enabling continuous vehicular travel without interruptions. This eliminates ferry crossing times, typically 25–30 minutes plus waiting periods, and reduces route detours, thereby streamlining transportation along Norway's western coast. For regional journeys, Rogfast is projected to shorten travel time between and by up to 40 minutes, enhancing connectivity between and counties. In the context of the full E39 upgrades, which include multiple tunnel and bridge projects to remove all ferries, Rogfast contributes to reducing the end-to-end route time from to from approximately 21 hours to 10.5–11 hours. These time savings apply to both passenger vehicles and , fostering more efficient by minimizing delays from schedules and weather disruptions. The all-weather reliability of the tunnel route supports increased road-based , potentially diverting traffic from air and alternatives and promoting across fjord-divided regions.

Broader Economic Benefits and Costs

The Rogfast project is projected to enhance regional by expanding effective labor and markets between the Nord-Jæren and Haugalandet regions, enabling greater and residential options that could alleviate pressures in areas while supporting rural economies. Improved goods transport along the is anticipated to lower expenses for key industries, including production and oil-related activities, which dominate the surrounding and rely on efficient coastal to access domestic and markets. These factors contribute to a positive socio-economic of 9,338 million Norwegian kroner (in 2016 prices), as determined by external analyses, indicating overall profitability over a 75-year lifespan despite to volumes. Additional benefits include boosted through shorter, more reliable access to regions and islands like Kvitsøy, potentially increasing visitor numbers and local service sector revenues by making the area more attractive for day trips and extended stays. Construction activities have generated temporary employment in engineering, tunneling, and support services, though long-term job gains are expected primarily from induced economic activity in connected industries rather than direct operational roles. On the cost side, the project demands substantial upfront capital, with recent estimates reaching 25 billion Norwegian kroner (approximately €2.3 billion), financed via allocations and tolls that necessitate elevated rates—potentially up to 330 per light vehicle crossing—to cover financing over 20 years, which could burden users and industries if traffic projections underperform. Opportunity costs arise from diverting public funds from alternative , and while socio-economic analyses affirm net gains, they incorporate assumptions on rates and benefit attribution that external reviewers have scrutinized for optimism in non-time-saving effects.

Controversies and Criticisms

Financial Overruns and Funding Debates

The Rogfast project, approved by the Norwegian in May 2017 for construction and financing as part of the E39 coastal highway upgrades, initially faced budgetary challenges that halted progress. In December 2019, a major contract worth billions was canceled after costs exceeded estimates by 1 billion , prompting Statens vegvesen to reject the bids and delay tendering. By April 2020, updated projections revealed overruns surpassing the original 18.6 billion framework by over 6 billion , pushing the total toward 24.6 billion or more, which led Samferdselsminister Arild Hareide to suspend the project for parliamentary review. Funding for Rogfast relies on a combination of national government allocations, regional guarantees, and anticipated toll revenues, sparking debates over fiscal responsibility and inter-regional equity. Rogaland fylkeskommune provided a 16 billion guarantee in 2018 under state pressure to avert stalling, despite initial resistance, as the central government conditioned progress on such commitments. The greenlit revised financing in November 2020 at 24.8 billion , with state contributions covering a significant portion alongside tolls projected at approximately 350 per crossing to recoup costs over decades. Critics, including opinion leaders, questioned the savings—estimated at 40 minutes for key routes—against the ballooning expense, labeling it a potential "money pit" amid competing national priorities. Political contention intensified around perceived disparities in project handling, with Senterpartiet's Geir Pollestad decrying the 2020 halt as a "" and arguing that equivalent overruns in Oslo-area initiatives would not trigger similar scrutiny or delays. FrP's Roy Steffensen highlighted further escalations in June 2024, noting a four-year delay and additional 2 billion in costs, warning of rising tolls and urging faster execution to mitigate inflation-driven overruns. Despite these, a parliamentary majority, including cross-party support in the Transport Committee, reaffirmed commitment to rapid advancement in June 2020, prioritizing regional connectivity over immediate fiscal tightening, though Miljøpartiet De Grønne advocated stricter oversight to curb unchecked spending. By 2025, estimates stabilized around 25 billion , reflecting adjustments for construction complexities but underscoring persistent risks in mega-infrastructure budgeting.

Safety, Environmental, and Operational Concerns

Safety concerns for the Rogfast tunnel stem primarily from its unprecedented length of approximately 27 kilometers and maximum depth of 392 meters below , which introduce uncertainties in , particularly for incidents and structural integrity under high hydrostatic pressure. Risk assessments conducted during the design phase have emphasized the need to quantify and mitigate these uncertainties, as deviations from standard European fire safety requirements could render certain scenarios unacceptable without compensatory measures. Norwegian emergency response personnel have demonstrated gaps in tunnel competencies, including pre- and post-incident handling, which could exacerbate risks in a subsea environment where external access is limited. Evacuation poses specific challenges due to the self-rescue principle relied upon in tunnel design, with large uncertainties in smoke propagation, visibility impairment, and tenability limits over extended distances. The twin-tube configuration, with tubes 15 meters apart, enables redundancy by allowing traffic diversion during incidents in one tube, while advanced systems aim to isolate affected areas through directional airflow and smoke extraction. Construction-phase fire risks, such as those from battery-electric dump trucks involving lithium-ion , have been modeled using tools like Fire Dynamics Simulator, indicating potential hazards near ignition sources but mitigable through zoning and suppression protocols. Environmental concerns during construction include temporary marine sediment disturbance from tunneling and blasting, though the enclosed design minimizes long-term ecological disruption compared to ongoing ferry operations it replaces. Approximately 20 million cubic meters of excavated rock will be repurposed for coastal , reducing waste disposal impacts and aligning with Norwegian sustainability practices in tunneling. The project incorporates recycled materials, such as steel fibers for concrete reinforcement, to lower the of construction elements. Operationally, maintaining ventilation and air quality over the full length presents ongoing challenges, requiring robust systems for both routine emissions and , with the tunnel's scale demanding and automated adjustments. The inclusion of a at the island of Kvitøy offers potential for enhanced maintenance access and , but the extreme depth complicates routine inspections and repairs, necessitating specialized subsea intervention techniques. Twin-tube supports continuous operation during closures for upkeep in one tube, though high volumes post-completion—projected to exceed 10,000 vehicles daily—could strain capacity without adaptive controls.

Nomenclature

Origin and Meaning of "Rogfast"

"Rogfast" derives from the Norwegian term Rogaland fastforbindelse, where "" denotes the southwestern county encompassing the project's endpoints, and fastforbindelse signifies a permanent infrastructural linkage. This emerged during early planning phases in the as part of Norway's broader initiative to eliminate dependencies on the E39 , emphasizing durable subsea alternatives over seasonal routes. The term fastforbindelse literally translates to "fixed connection" or "fixed link" in English, highlighting the tunnel's role in providing a reliable, weather-independent crossing beneath the Boknafjord and Kvitsøyfjorden, in contrast to existing ferry operations that connect Randaberg near to the island of Bokn. This fixed-link concept underscores causal engineering priorities: reducing transit vulnerabilities to fjord conditions while integrating regional economies through consistent vehicular access. Similar abbreviations appear in proximate Norwegian projects, such as (Ryfylke fastforbindelse), a completed subsea system operational since 2019, reflecting a standardized terminological for fixed coastal in fjord-dominated terrains. The adoption of "Rogfast" thus encapsulates both geographic specificity and functional intent, with formal approval tied to the Norwegian Public Roads Administration's (Statens vegvesen) project designation in national transport plans post-2010.

References

  1. [1]
    E39 Rogfast | World's Longest Underwater Road Tunnel - Norconsult
    E39 Rogfast will become the world's longest underwater road tunnel, approximately 27 km long, and is part of the national initiative for a ferry-free E39 ...
  2. [2]
    Skanska builds subsea tunnel in Rogaland County, Norway, for ...
    Dec 12, 2022 · The E39 Rogfast project is a 27 km long subsea road tunnel – the Boknafjord tunnel – between the municipalities Randaberg and Bokn in Rogaland County, Norway.
  3. [3]
    World's Deepest Underwater Tunnel to Have Cars Drive 16 Miles ...
    Jun 29, 2025 · The Rogfast project, measuring 26.7 kilometers (about 16.5 miles) and descending to 392 meters (nearly 1,300 feet) below sea level, is scheduled ...Missing: details depth
  4. [4]
    Going deep to build the world's longest road tunnel
    Jun 24, 2019 · The Rogast Tunnel will be built as deep as up to 392 meters below sea level. Using new bridge and tunnel building techniques and set to cut travel times in ...
  5. [5]
    Work on world's longest subsea road tunnel advances with ...
    Nov 28, 2024 · Rogfast will carry E39 road traffic north of Stavanger in twin tunnels of 10.5m diameter and 15m apart, driven through the rock below ...
  6. [6]
    [PDF] Prop. 105 S (2016–2017) - Regjeringen.no
    Apr 5, 2017 · Samferdselsdepartementet legg i denne proposi- sjonen fram forslag om utbygging og finansiering av prosjektet E39 Rogfast i Randaberg, ...
  7. [7]
    E39 Rogfast - Statens vegvesen
    Mer om prosjektet. Stortinget vedtok utbygging og finansiering av prosjektet E39 Rogfast i Randaberg, Kvitsøy og Bokn kommunar i Rogaland den 23. mai 2017.Missing: godkjennelse | Show results with:godkjennelse
  8. [8]
    Norway to build the world's longest floating bridge - We Build Value
    Oct 23, 2019 · Norwegian parliament approved the Rogfast works on May 23, 2017 and construction started at the end of that year.Missing: details | Show results with:details
  9. [9]
    Rogfast procurement update - TunnelTalk.com
    Jun 22, 2017 · Subsequently, the project gained Parliamentary approval in mid-2017, but, with some approvals still needed, the procurement schedule for the ...Missing: initial | Show results with:initial
  10. [10]
    Norway's E39 Road: The Coastal Highway Route
    Jun 30, 2025 · The E39 is a European route along Norway's west coast, connecting fjords, from Aalborg in Denmark to south of Trondheim, and is 1330 km long.Driving Norway's E39 Road · E39 Road Highlights · Stord Island: A Key Fjord...
  11. [11]
    This Is The World's Deepest Underwater Tunnel You'll Be Able To ...
    Jul 2, 2025 · For years, Norway has envisioned a project that would make travel on the E39 easier. It eventually came up with the "E39 Ferry Free plan ...
  12. [12]
    Norway moves toward more E39 coastal road improvements
    Norway is working on plans to make more of the major north-south E39 coastal route a ferry-free highway, coasting €35.3 billion, according to media.
  13. [13]
    Building the World's Longest Undersea Tunnel - The B1M
    Jul 1, 2019 · Above: The new E39 will replace the ferries that currently operate along Norway's west coast (image courtesy of Volvo CE). The E39 project ...
  14. [14]
    NORWAY – A ROAD TO A BRIGHTER FUTURE
    Norway's plan to develop a continuous Coastal Highway between Kristiansand in the south and Trondheim in the north is a massive undertaking.
  15. [15]
    Coastal Highway Route E39 – Extreme Crossings - ResearchGate
    Aug 7, 2025 · The E39 is envisaged as a ferry-free highway connecting the major cities on the west coast of Norway (Trondheim, Ålesund, Bergen, Stavanger, and ...<|separator|>
  16. [16]
    Rogfast: The World's Longest & Deepest Undersea Road Tunnel
    Apr 18, 2025 · The Rogfast tunnel, currently under construction in western Norway, will become both the world's longest and deepest subsea road tunnel once complete.
  17. [17]
    Norway's massive Rogfast project - Global Highways
    Jan 31, 2025 · The massive Rogfast Tunnel project for Norway will boost transport for the nation, providing new road links.Missing: strategic context
  18. [18]
    Rogfast Tunnel Highlights Norway's Ambitious Leap into Subsea ...
    Dec 11, 2024 · Learn about Rogfast Tunnel, the world's longest and deepest subsea road tunnel, poised to set new benchmarks in engineering excellence.Missing: godkjennelse 2017
  19. [19]
    Going deep to build the world´s longest road tunnel - Volvo Group
    Jun 27, 2019 · Reconstruction of the Coastal Highway Route E39 is not only Norway's biggest ever infrastructure project – but the Rogfast Tunnel, of which it ...
  20. [20]
    Works begin on the Rogfast Project - tunnelbuilder.com News
    Jan 8, 2018 · On the 4th January 2018 the first works started on the Rogfast project . This will be the first tunnel built to replace the ferry service.
  21. [21]
    Rogfast tender call on first tunnel package - TunnelTalk.com
    Sep 14, 2017 · All three lots are expected to be awarded by mid-2018 with construction starting on the package also in 2018. The Rogfast project is part of ...
  22. [22]
    Norway's floating bridges and subsea tunnels - The Off Site by Aphex
    Feb 19, 2025 · Originally approved by the Norwegian Parliament in 2017 with a budget of NOK 16.8 billion (USD $1.5 billion) and planned for completion in 2025- ...
  23. [23]
    Full gjennomgang av Rogfast – NRK Rogaland
    Nov 8, 2019 · Rogfast utsettes på ubestemt tid. Statens vegvesen skal nå snu alle steiner for å finne løsninger som kutter kostnader i Rogfast-prosjektet, ...Missing: stopp | Show results with:stopp
  24. [24]
    Second Contract announced on world's longest subsea tunnel
    Mar 8, 2022 · Rogfast is due to be completed in 2033. Construction began in 2018 but the project was halted in 2019 because of predicted cost overruns.Missing: early | Show results with:early
  25. [25]
    Signerte Rogfast-kontrakt på 4 milliarder - Anlegg&Transport
    Jan 9, 2023 · Fredag ble den andre av tre store Rogfast-kontrakter signert av veidirektør Ingrid Dahl Hovland og direktør Audun Aaland i Implenia Norge.
  26. [26]
    Den største kontrakten på Rogfast er signert - Statens vegvesen
    Den største kontrakten på Rogfast er signert. Publisert 11. juni 2024. Det er JV IMPLENIA STANGELAND E39 E02 ANS som skal bygge E02 kontrakten fra Kvitsøy.
  27. [27]
    Rogfast: Signerte rekordstor kontrakt på hele 6.238.016.052 kroner
    Jun 11, 2024 · Kontrakten er på 6 milliarder 238 millioner, pluss noe lommerusk av i alt 16 tusenlapper – og 52 skinnende kronestykker helt til slutt i ...
  28. [28]
    E02 Kvitsøy (E39 Rogfast) - Implenia
    Kontrakten omfatter blant annet bygging av 8,8 km tunnel og har en verdi på drøyt 6,3 mrd. Prosjektet. Entreprise E02 Kvitsøy regnes som den mest komplekse i ...
  29. [29]
    Epiroc delivers Tunneling Intelligence at world's longest and ...
    Sep 30, 2025 · Epiroc delivers Tunneling Intelligence at world's longest and deepest undersea tunnel project. September 30, 2025. The Rogfast tunnel, set to be ...
  30. [30]
  31. [31]
    Europe approves the construction of the world's longest and deepest ...
    Oct 9, 2025 · The Rogfast project will dramatically reduce this travel time to just 10 hours, eliminating the need for ferry services across major fjords.
  32. [32]
    Skanska awarded major E39 Rogfast tunnel contract
    Dec 13, 2022 · Skanska will build the northern part of the Boknafjord tunnel. It is a twin tunnel, each 10.5m in diameter, and Skanska will construct 18.5km of ...<|control11|><|separator|>
  33. [33]
    Implenia JV wins second contract on Norway's major subsea road ...
    Jun 4, 2024 · The full project involves a 26.7km long, 10.5m diameter tunnel, with a maximum depth of 392m below sea level. It will cross the Boknafjord ...Missing: specifications | Show results with:specifications
  34. [34]
    Norway's massive Rogfast Tunnel project - Global Highways
    Dec 11, 2018 · This 1,100km route will link the major city of Trondheim in the mid-north to Kristiansand on the south coast and aims to develop industry, ...
  35. [35]
    Feasibility of tunnel boring through weakness zones in deep ...
    Norwegian subsea tunnels have all been excavated with the drill and blast method. The prevailing rock mass quality is generally favorable for tunneling, ...Missing: undersea | Show results with:undersea
  36. [36]
    Epiroc delivers Tunneling Intelligence at world's longest and ...
    Sep 30, 2025 · Rogfast, one of the flagship projects of this venture, commenced in 2018 and is expected to open in 2033. The joint venture between Implenia ...Missing: tunnelling | Show results with:tunnelling
  37. [37]
    Inside Norway's project to build the world's deepest subsea highway
    Apr 9, 2025 · The Rogaland fixed link, or simply Rogfast, will be about 26.7km long and 390m at the deepest point under the sea when completed.Missing: context | Show results with:context
  38. [38]
    Norway's Rogfast Tunnel: Redefining Subsea Infrastructure - Smoothx
    Jul 15, 2025 · Upon completion, it will stretch 26.7 kilometers (16.5 miles) and reach a depth of 390 meters (1,280 feet) below sea level. The tunnel will ...
  39. [39]
    Treatment of uncertainty in risk assessments in the Rogfast road ...
    In this paper we review and discuss the use of risk assessments in the design of the world's longest and deepest subsea road tunnel, the Rogfast.
  40. [40]
    Treatment of uncertainty in risk assessments in the Rogfast road ...
    Aug 6, 2025 · In this paper we review and discuss the use of risk assessments in the design of the world's longest and deepest subsea road tunnel, ...
  41. [41]
    Evaluating the role of risk assessment for road tunnel fire safety
    Risk treatment: this step aims at mitigating or eliminating, if possible, non-acceptable risks by imposing additional to standard fire safety measures and ...
  42. [42]
    Green light for the world's longest and deepest road tunnel - AS USA
    Jul 28, 2025 · Construction began in January 2018 but faced delays due to budget overruns, leading to a temporary halt in 2019. Work resumed in 2021, with ...
  43. [43]
    Norway to have world's longest underwater tunnel by 2033 - Inspenet
    Jan 11, 2025 · The world's longest underwater tunnel in Norway will reduce travel times and improve regional connectivity between the south and north of ...
  44. [44]
    [PDF] Kvalitetssikring (KS 2) av E39 Rogfast - regjeringen.no
    Nov 11, 2016 · Vår kvalitetssikring av styringsunderlag og kostnadsoverslag viser at E39 Rogfast har en anslått kostnad P50 på 16 600 millioner kroner og ...Missing: stopp | Show results with:stopp<|separator|>
  45. [45]
    Prop. 54 S (2020–2021) - Regjeringen.no
    Statens vegvesen har sommaren 2020 gjennomført ein ny berekning av kostnader for prosjektet E39 Rogfast. Det er gjennomført nokon mindre endringar i ...Missing: stopp | Show results with:stopp
  46. [46]
    E39 Rogfast er samfunnsøkonomisk lønnsom, men krever høye ...
    Dec 21, 2016 · Finansieringen av prosjektet krever uvanlig høye bomsatser. Det er lav sannsynlighet for å få finansiert prosjektet i løpet av en 20 års ...
  47. [47]
    Milliard Rogfast-kontrakt er avlyst - Samferdsel & Infrastruktur
    Dec 2, 2019 · Rogfast-prosjektet koster èn milliard mer enn det Statens vegvesen regnet med. Vegdirektøren har derfor sagt nei til Rogfast-kontrakten og ...Missing: budsjett overskridelser finansiering
  48. [48]
    Sprekk på 6 mrd. utsetter Rogfast: – Skandale, mener Senterpartiet
    Apr 29, 2020 · Pollestad fra Sp mener tilsvarende overskridelser i prosjekter nærmere hovedstaden aldri hadde ført til stans i arbeidet og ny ...Missing: budsjett finansiering
  49. [49]
    Bøyer seg for staten: Gir milliardgaranti til Rogfast – NRK Rogaland
    Apr 17, 2018 · Byggingen av verdens lengste undersjøiske tunnel sto i fare for å stoppe opp, da staten ikke ville garantere 16 milliarder til prosjektet.Missing: budsjett overskridelser finansiering
  50. [50]
    Trenger vi å spare et kvarter gjennom pengesluket Rogfast? Nei
    Dec 9, 2020 · Med Rogfast snakkes det om en investering på rundt 25 tusen millioner. Da må det være legitimt å stille spørsmålet: Bilistene får svi.Missing: finansiering | Show results with:finansiering
  51. [51]
    Veien blir 4 år forsinket og 2 milliarder dyrere: – Helt uforståelig
    Jun 24, 2024 · Etter over fire års ventetid er prosjektet endelig i gang igjen. Det skal koste 6,2 milliarder - over to 2 milliarder mer enn vegvesenet først ...Missing: stopp | Show results with:stopp
  52. [52]
    Ingen Rogfast-avklaring før sommeren - men stortingsflertallet vil ...
    Jun 5, 2020 · Rogfast kan kuttes med fire milliarder kroner - prosjektet må allikevel opp i Stortinget på nytt. Forsvarlig finansiering. I en pressemelding ...Missing: budsjett | Show results with:budsjett
  53. [53]
    A review of competencies in tunnel fire response seen from the first ...
    This study has revealed tunnel fire safety concerns related to the Norwegian emergency response personnel's state of competence both in the pre- and post- ...<|separator|>
  54. [54]
    Communicating Efforts in Emergencies and Tunnel Users' Learning
    Current expectations to evacuation is based on the self-rescue principle. For many tunnel designs, there are large uncertainties related to evacuation in the ...
  55. [55]
    Fire risk and process impact study of battery-electric dump trucks at
    Analyses at Rogfast E02 by means of the Fire Dynamics Simulator (FDS) have indicated that, tenability limits for persons located in proximity of battery- ...
  56. [56]
    [PDF] Sustainability in Norwegian Tunnelling
    During early planning of new infrastructure projects and, renewal of older infrastructure, a careful evalu- ation of route is vital. The route affects not ...
  57. [57]
    Rogfast - Case studies - Fibres | KrampeHarex - krampe harex
    The Rogaland Fixed Link, commonly known as Rogfast, is one of Norway's most extensive infrastructure projects, involving the construction of a subsea road ...
  58. [58]
    UiS Brage: Maintenance Concept Study for Deep Subsea Tunnels
    Rogfast will be the deepest and longest underwater tunnel in the whole world and it is currently in the middle of the project phase. The case study has focused ...Missing: concerns | Show results with:concerns
  59. [59]
    Norwegian nous - Tunnels
    Sep 19, 2016 · The name Rogfast is an abbreviation for the Norwegian name “Rogaland fastforbindelse”, translated in English as the “Rogaland fixed link”.
  60. [60]
    400 feet underground, here is the world's deepest new tunnel ...
    Sep 18, 2025 · This is the Rogfast project, for Rogaland fastforbindelse, or “Rogaland fixed link”. It involves the construction of a 26.7-kilometre-long ...