Time and materials

Time and materials (T&M) contracts are a form of procurement agreement under which a buyer reimburses a seller for the direct costs of labor—typically billed at predetermined fixed hourly rates that include wages, fringe benefits, overhead, general and administrative expenses, and profit—and the actual costs of materials used, without a fixed total price. These contracts are distinct from fixed-price or cost-reimbursement models, as they emphasize reimbursement based on verifiable time expended and resources consumed rather than a predefined scope or outcome. T&M arrangements are regulated in frameworks like the U.S. Federal Acquisition Regulation (FAR), where they apply to both supplies and services, with materials encompassing direct items incorporated into the end product, subcontracts, travel, and other allowable costs. T&M contracts are employed when the extent, duration, or costs of the required work cannot be reasonably estimated at the outset, such as in efforts, emergency repairs, or initial prototype development where uncertainties preclude other contract types. In the U.S. context, their use demands a written by the contracting that no more suitable alternative exists, and they must include a not-to-exceed price to limit the buyer's exposure, with the seller assuming risk for any overruns. Extensions beyond three years for base periods and options require higher-level approval, and they are particularly applicable to commercial services under FAR Part 12. Common applications span federal acquisitions, construction projects, consulting services, and implementations where flexibility is paramount. While T&M contracts offer advantages in flexibility for uncertain requirements and reduced administrative compared to negotiating fixed scopes, they place the majority of and on the buyer, as there is no inherent for the seller to labor hours or optimize . This structure necessitates robust government or buyer surveillance to verify hours, materials, and progress, which can increase oversight costs and susceptibility to abuse if not managed rigorously. Protracted reliance on T&M after initial uncertainties resolve is discouraged, as it may lead to higher overall expenses without corresponding benefits in accountability.

Definition and Overview

Definition

A time and materials (T&M) is a type of in which the client reimburses the contractor for the actual labor hours worked at predetermined fixed hourly rates, along with the of materials consumed in the performance of the work. These fixed hourly rates typically incorporate the contractor's wages, overhead, general and administrative expenses, and profit, providing a structured compensation for labor without reimbursing actual labor costs. Unlike fixed-price contracts, T&M arrangements do not establish a total predetermined price, making them suitable for projects where the scope, duration, or extent of work is uncertain at the outset. Billing under a T&M relies on verifiable , such as individual daily job timekeeping records or timesheets for labor hours, and invoices or receipts for costs, ensuring and in reimbursements. The submits periodic invoices detailing the hours worked by specific employees and the materials used, with the government or client reviewing these against supporting records to approve payments. This mechanism allows for flexibility in project execution but requires diligent tracking to prevent disputes over unverifiable claims. T&M contracts differ from cost-reimbursement contracts in that labor compensation uses fixed hourly rates rather than reimbursing the actual costs incurred by the for wages and associated expenses. In cost-reimbursement arrangements, the client covers allowable direct and plus a , whereas T&M structures the labor portion predictably through rates while still basing materials on actual expenditures. A basic billing formula for T&M contracts under U.S. regulations can be expressed as: \text{Total Payment} = (\text{Labor Hours} \times \text{Hourly Rate}) + \text{Material Costs} This formula highlights the additive nature of reimbursements, where material costs include applicable indirect costs per the contract terms.

Key Components

The labor component of a time and materials (T&M) contract consists of fixed hourly rates charged for direct labor hours, differentiated by skill levels or labor categories to reflect varying expertise and responsibilities. These rates typically encompass wages, fringe benefits such as health insurance and retirement contributions, overhead, and a portion of profit, ensuring comprehensive compensation without separate billing for indirect labor expenses. For instance, rates might be set at approximately $50 per hour for technicians performing routine tasks and $100 per hour for engineers handling complex design work, with separate schedules for subcontractors and affiliates to maintain transparency. The materials component covers the actual costs of direct materials, subcontracts for supplies or incidental services, other direct costs (such as travel), and applicable indirect costs essential to the project. These costs include freight, taxes, and handling fees directly tied to , with indirect costs allocated per the contractor's practices and allowable under regulations like FAR Part 31. Verification relies on original receipts or invoices to substantiate purchases and prevent overbilling, with any unused materials returned and credited accordingly. Under U.S. T&M contracts, is included only in the fixed labor hourly rates, with no separate or applied to materials costs; however, in T&M contracts, a markup of 10% to 30% may be added to labor and materials costs to cover and administrative , depending on terms and norms. Documentation requirements form the backbone of T&M contracts, mandating detailed records to validate all charges and facilitate audits. Labor must be substantiated through timesheets or daily logs recording hours worked by each individual, including task descriptions and signatures for approval. Materials claims require corresponding logs or invoices detailing quantities, suppliers, and costs, with periodic reports (e.g., weekly) submitted for client review to ensure ongoing and . All submissions undergo approval processes, often via formal change orders for any deviations, to mitigate disputes and support efficient project surveillance.

Historical Development

Origins

Flexible contracting approaches, such as cost-reimbursement, began to emerge in the for large-scale projects amid the , where unpredictable scopes often made fixed-price agreements challenging. For example, early canal projects in the UK frequently exceeded budgets, with average overruns of 279% due to inadequate planning. Advances in cost-accounting during the late 1800s in British and American industries enabled better tracking of expenditures in manufacturing and . Early labor laws, including the British of the 1830s and 1840s and U.S. efforts for ten-hour workdays, supported documentation of labor inputs. In , cost-plus frameworks became traditional for managing uncertainties in and , particularly as the transitioned to iron and steel vessels in the late 19th and early 20th centuries.

Modern Evolution

Cost-reimbursement contracts, including flexible types for uncertain scopes, saw increased use in U.S. following during the 1940s and 1950s, driven by complex projects in rearmament. These were applied alongside cost-plus arrangements for research, development, test, and evaluation (RDT&E) activities. This evolution was supported by the Armed Services Act of 1947, which unified practices across the and provided groundwork for handling intricate needs through standardized regulations. (T&M) contracts were explicitly recognized as a type—combining elements of cost-reimbursement and fixed-price structures—within the (FAR), implemented in 1984 under Subpart 16.6, to standardize their use across executive agencies. In the , hourly-based compensation became common in consulting during the and , aligning with technological advances and project uncertainties in emerging fields like . In the , concerns over cost overruns in government contracts led to reforms enhancing audit requirements and controls for flexible agreements, particularly in . The (GAO) identified vulnerabilities in , such as overpayments, recommending improved oversight. These efforts, amid defense budget reductions of about 40% from 1991 to 1995, focused on better cost-estimating and surveillance while retaining utility for uncertain projects. Entering the , T&M contracts have adapted to and digitalization, with software tools enabling tracking of labor and materials for greater . This supports use in international outsourcing, as seen in the European Union's Directive 2004/18/EC, which promotes flexible negotiated procedures in public procurement. Integrated platforms for automated invoicing aid management of distributed teams and .

Types and Variations

Standard T&M Contracts

Standard time and materials (T&M) contracts represent the basic form of this agreement type, where billing is based on the actual hours of labor expended at fixed hourly rates and the costs of materials consumed during the project. Unlike fixed-price arrangements, these contracts do not establish a predetermined total cost for the entire scope, allowing flexibility in execution without the need for detailed upfront scoping. They are particularly suitable for projects where the scope is undefined or subject to change, such as emergency repairs or initial exploratory phases, where estimating precise requirements in advance would be impractical. In regulated contexts such as U.S. government acquisitions under the (FAR), standard T&M contracts must include a not-to-exceed (NTE) price to limit the buyer's exposure, with the seller bearing the risk for any costs beyond this limit; commercial contracts may omit such ceilings, emphasizing mutual trust supplemented by periodic progress reviews and invoicing to monitor expenditures. This structure is commonly applied in small-scale or exploratory projects, where the work's extent cannot be reliably forecasted at the outset, enabling adjustments as needs evolve without renegotiating the agreement. For instance, materials are reimbursed at actual cost, while labor is charged at a predefined hourly rate that incorporates the contractor's overhead and . A representative example of a standard T&M contract involves hiring a for undefined tasks, where the agreement specifies an hourly labor rate—such as $100 per hour—along with reimbursement for direct expenses like travel. Invoices are submitted periodically, detailing time logs and material receipts to ensure . This approach allows the project to proceed iteratively based on emerging requirements. Regarding risk allocation, standard T&M contracts shift the majority of to the client up to the ceiling price (if applicable), who bears the burden of costs for extended labor hours due to inefficiencies or unforeseen changes, while the faces lower exposure since compensation directly correlates with actual inputs up to the limit. The must still manage operational risks, such as ensuring timely performance to maintain client trust.

Hybrid T&M Contracts

Hybrid time and materials (T&M) contracts incorporate elements from other contract types, such as fixed-price or cost-reimbursement provisions, to mitigate risks associated with the flexibility of standard T&M agreements, allowing for better cost control while preserving adaptability for uncertain scopes of work. These variations are particularly useful in scenarios where requirements may evolve but require safeguards for defined portions of the work. One common hybrid form is the labor-hour only contract, a subset of T&M that compensates exclusively for direct labor hours at fixed rates, excluding any reimbursement for materials supplied by the , making it suitable for service-intensive engagements like professional training or consulting without . Under FAR 16.602, this type differs from full T&M solely in the absence of costs, applying the same rules for labor billing, oversight, and ceiling price requirements. Hybrid T&M contracts often combine elements of fixed-price structures with T&M provisions, where a base fixed fee covers well-defined tasks and T&M rates apply to variable or unforeseen elements. For instance, in projects, a fixed-price component might fund the initial design phase, while T&M handles iterative testing and adjustments based on actual hours and materials used, providing predictability for core deliverables alongside flexibility for changes. Upon approaching or reaching the ceiling price in a T&M component, the is not obligated to pay additional amounts, and any continuation of work may require modification, potentially converting relevant portions to a fixed-price arrangement to shift excess costs to the . This was emphasized in updates to the (FAR) following 2000, including revisions in 2006 and 2011 that clarified payment procedures and reinforced the ceiling price to prevent overruns in noncommercial T&M contracts. Milestone-based hybrid T&M contracts integrate progress-triggered payments with T&M billing, where compensation is released upon achieving specific milestones, such as of phases, to blend the flexibility of hourly and material reimbursements with accountability for timely advancement. This approach ensures that while labor and materials are paid as incurred up to the ceiling, overall progress is monitored through defined checkpoints, reducing the risk of indefinite extensions.

Advantages and Disadvantages

Advantages

Time and materials (T&M) contracts provide significant flexibility in handling scope changes, making them particularly suitable for projects with uncertain or evolving requirements, such as initiatives where initial estimates may prove inaccurate. Unlike fixed-price agreements that require formal renegotiation for modifications, T&M structures allow adjustments to the project scope based on actual needs without disrupting the overall , enabling seamless adaptation as new emerges or priorities shift. This adaptability is especially valuable in dynamic fields like or prototypes, where iterative changes are common, reducing the risk of delays associated with re-bidding or amendments. A key benefit of T&M contracts is the enhanced in billing practices, as clients receive detailed logs of hours worked and materials used, which fosters and minimizes disputes over costs. This visibility is amplified by modern time-tracking tools, such as platforms that enable of labor and expenses, allowing stakeholders to and expenditures as they occur rather than at project completion. For instance, software like Knowify or Rhumbix provides automated approvals and dashboards that ensure accurate, verifiable records, helping to prevent overbilling and promoting accountability on both sides. T&M contracts are well-suited for short-term or work, offering a rapid setup process that bypasses the need for comprehensive upfront estimates, which can be time-consuming in urgent scenarios like or maintenance repairs. In such cases, the ability to commence work immediately without detailed scoping ensures timely response, as seen in where T&M is authorized for situations demanding quick mobilization. This expedited approach is particularly advantageous in or IT support, where unforeseen issues require prompt intervention without the overhead of fixed-scope negotiations. Regarding incentives, while T&M contracts tie payment directly to actual time expended, they can motivate contractors to maintain through mechanisms like not-to-exceed clauses or the desire to secure future , as prolonged work may strain client relationships; however, this is often supplemented by performance monitoring to align interests. In practice, tools integrated with T&M billing encourage timely completion by providing shared visibility into progress, indirectly promoting streamlined workflows to meet deadlines and budgets.

Disadvantages

One significant drawback of time and materials (T&M) contracts is the of overruns for clients, as these agreements typically include a not-to-exceed price to limit financial exposure, but the buyer still bears the primary up to that if expenditures escalate due to changes or inefficiencies. Unlike fixed-price contracts, where the assumes the of exceeding estimates, T&M arrangements reimburse actual hours worked and materials used up to the , which can be reached if the expands or inefficiencies arise. This structure shifts the burden of control primarily to the client, potentially resulting in budgets that approach or hit the beyond initial projections, particularly in volatile sectors like and . T&M contracts also diminish contractors' incentives to complete work efficiently, as compensation is directly tied to billable hours rather than overall performance or speed. Without built-in rewards for minimizing time or resources, contractors may lack motivation to optimize processes, leading to prolonged project timelines and opportunities for inflating hours—commonly referred to as "padding"—to maximize revenue. Clients must therefore implement vigilant oversight, such as regular progress reviews and time-tracking audits, to mitigate these risks, which further complicates project management. Budgeting poses another challenge under T&M contracts, as clients face difficulty in accurately forecasting total costs due to the open-ended nature of reimbursements. This unpredictability hampers financial planning, , and stakeholder approvals, especially for organizations with strict fiscal constraints or multi-year funding cycles. In practice, clients often resort to conservative estimates or reserves, but these measures can still lead to reallocations or delays if actual expenditures deviate significantly. Finally, the administrative demands of T&M contracts impose substantial audit burdens on clients, requiring detailed of invoices, timesheets, and receipts to prevent overbilling. This ongoing scrutiny increases overhead costs, with the need for dedicated personnel or third-party ors adding to the project's total expense and diverting resources from core activities. Such processes can elevate administrative efforts considerably, straining smaller clients or those without robust internal controls. To address some of these issues, hybrid T&M models incorporating caps or milestones may be employed, though they introduce their own complexities.

Applications

Construction Industry

In the construction industry, time and materials (T&M) contracts are frequently employed for projects involving uncertain or evolving scopes, such as renovations, site preparations, and change orders during ongoing builds. These contracts allow flexibility when initial designs or conditions change, enabling contractors to bill based on actual hours and material expenditures rather than a predetermined fixed . For instance, in residential additions, contractors typically charge around $50 per hour—covering wages, overhead, and profit—plus the direct cost of materials like and fixtures, making T&M suitable for customized extensions where exact requirements emerge during work. T&M contracts are among the most popular options in for handling variability, often incorporating safeguards like daily rate caps or not-to-exceed clauses to limit total exposure while preserving adaptability. Average project sizes under these agreements range from $50,000 to $500,000, aligning with mid-scale renovations or repairs where precise cost estimation is challenging upfront. This structure proves advantageous in scenarios with uncertain scopes, as it aligns payments with progress without requiring extensive pre-bidding. However, T&M contracts in face specific challenges, including delays that extend labor hours and fluctuations that inflate material prices, both of which can lead to higher-than-expected billing for owners. These issues require meticulous tracking and documentation to ensure and prevent disputes over allowable costs. For example, unexpected or storms can halt site work, adding unpredicted time charges, while volatile markets for or —exacerbated by global disruptions—directly impact reimbursements. Federal agencies like FEMA have utilized T&M contracts for post-hurricane emergency responses and recovery efforts along the U.S. Gulf Coast, enabling rapid of contractors to address unpredictable damage without fixed bids that might delay critical rebuilding. This approach facilitates quicker assessments and adjustments for varying removal, structural reinforcements, and infrastructure fixes in affected areas.

Software and IT Services

In software and IT services, time and materials (T&M) contracts are particularly suited to scenarios involving iterative and evolving requirements, such as agile development, bug fixes, and consulting engagements. These contracts allow clients to pay for actual hours worked by developers, typically at rates ranging from $100 to $150 per hour, plus costs for materials like software licenses or resources. For instance, in agile development, teams can adapt to changing priorities without renegotiating fixed scopes, making T&M the most common model for such projects, with approximately 70% of agile initiatives using this approach. The flexibility of T&M contracts provides key benefits in the tech sector, especially for prototyping and developing minimum viable products (MVPs). This model supports rapid iteration based on user feedback, enabling startups to build custom applications without committing to a rigid upfront. For example, a startup commissioning a custom might engage a firm under T&M terms, with billing occurring weekly to maintain and control over evolving features. Hours are typically tracked using integrated tools like , which log time against tasks and generate reports for billing accuracy. A notable metric underscores T&M's prevalence: it accounts for a substantial share of IT outsourcing, aligning with the iterative of software work where fixed-price models may falter. However, unique risks arise in these environments, including from ongoing feature requests that can inflate costs. This is often mitigated through sprint-based billing in agile frameworks, where work is scoped and approved in fixed-duration cycles to prevent uncontrolled expansions.

Government Regulations

In the United States, the 16.601 governs the use of time and materials (T&M) contracts in procurement. These contracts are permitted only when it is not possible to accurately estimate the extent or duration of the work required, and no other contract type—such as fixed-price or cost-reimbursement—is suitable. A written determination and findings (D&F) must justify their use, documenting why alternative contract types are inappropriate and confirming that the work involves uncertainties that preclude fixed . Additionally, T&M contracts must incorporate fixed hourly rates for labor categories, which include direct wages, fringe benefits, overhead, general and administrative expenses, and or ; these rates must be based on where applicable, and the requires ongoing audits to verify and actual costs. To mitigate risks of cost overruns and , T&M contracts mandate a not-to-exceed (NTE) ceiling price that the cannot surpass without approval, with the bearing any excess costs. surveillance is essential throughout performance, as T&M arrangements provide no inherent for the to control costs or improve labor ; this includes monitoring labor hours, material usage, and progress to ensure value for taxpayer funds. Furthermore, under the Defense Federal Acquisition Regulation Supplement (DFARS) 252.204-7023, contractors must submit annual reports on services performed under T&M and similar contracts via the (SAM.gov), detailing direct labor hours to identify potential , , or and inform future strategies. As of October 1, 2025, the simplified acquisition threshold has been adjusted to $350,000 due to , affecting certain procedures that may intersect with T&M use. Internationally, parallels exist in the 's public procurement framework under Directive 2014/24/, which permits innovation partnerships for innovative projects (Article 31). These allow contracting authorities to engage partners for followed by production, where payments are made in installments based on the successful completion of phases and intermediate milestones, rather than solely fixed prices, provided the arrangement addresses market gaps for innovative solutions. Transparency is mandated, including clear criteria for partner selection, phased payments tied to milestones, and limits on duration (typically up to five years) to prevent open-ended commitments, ensuring and . Enforcement of T&M regulations emphasizes audits, compliance reviews, and civil penalties under the (FCA) for violations such as overstated labor hours or unallowable costs. For instance, in defense contracts, the (DoD) has pursued significant fines; a notable case involved Inc., which in 2025 agreed to pay $62 million to resolve FCA allegations of submitting defective cost or pricing data related to labor and materials on multiple DoD contracts, including elements akin to T&M billing practices. Such actions underscore the government's commitment to deterring abuse through , civil penalties, and potential debarment.

Contract Best Practices

Effective drafting of time and materials (T&M) contracts begins with including essential clauses that provide clarity and protect both parties. A detailed scope description should outline the 's objectives, key deliverables, tasks to be performed, and any explicit exclusions to prevent , such as specifying that certain ancillary services like are not covered in a . Rate schedules must specify fixed hourly labor rates for each category (e.g., $75 per hour for skilled crew members) and material markups (e.g., 15% on costs), ensuring and including provisions for subcontractors if applicable. Invoicing timelines should be clearly defined, such as bi-weekly submissions supported by timesheets, receipts, and progress reports, to facilitate timely payments and verification. Dispute resolution clauses are crucial, outlining processes like or in a specific jurisdiction (e.g., ) to resolve conflicts efficiently without litigation. Monitoring the execution of T&M contracts requires robust tools and processes to track time and materials accurately. , such as cloud-based platforms like Construction Cloud or , enables real-time tracking of labor hours, material usage, and expenses through features like digital timesheets, dashboards, and mobile apps, reducing errors from manual entry. Regular audits should be conducted to verify 100% of claims, involving reviews of such as timestamped photos and invoices to ensure and detect discrepancies early. To mitigate risks in T&M contracts, incorporate mechanisms for ongoing oversight and safeguards against cost overruns. Progress reviews should occur at regular intervals, such as every 30 days, allowing stakeholders to assess advancements, adjust scopes if needed, and confirm alignment with the original objectives through collaborative meetings. Termination rights provisions enable either party to end the if costs exceed predefined thresholds (e.g., a not-to-exceed ) or if issues arise, with requirements for periods and final settlements to minimize financial exposure. For government contracts, adherence to (FAR) 16.601 surveillance requirements further ensures cost controls and efficient methods. Negotiation of T&M contracts should emphasize competitive and sustainable terms to foster long-term success. Start by establishing competitive hourly rates and material costs based on market benchmarks, ensuring they include all components like overhead and profit without hidden fees. For extended projects, build in clauses to account for or market changes, such as a 3% annual increase in rates, subject to mutual agreement and documentation of justifying factors. Additionally, negotiate processes upfront to handle unforeseen adjustments transparently, maintaining trust and preventing disputes.

References

  1. [1]
    16.601 Time-and-materials contracts. - Acquisition.GOV
    Feb 7, 2023 · A time-and-materials contract provides for acquiring supplies or services on the basis of- (1) Direct labor hours at specified fixed hourly rates.
  2. [2]
    labor and materials (time and materials)
    ### Definition and Explanation of Time and Materials Contracts
  3. [3]
    Contract Types | www.dau.edu
    Time-and-material and labor-hours contracts are among the least preferred contract types because the contractor is not incentivized to establish limitations ...Missing: disadvantages | Show results with:disadvantages
  4. [4]
    [PDF] Justification for Use of Time-And-Materials Contracts - DoD
    Jan 8, 1991 · However, disadvantages to using time-and-materials contracts are that the Government assumes all the cost risks and the monitoring of ...
  5. [5]
    Part 16 - Types of Contracts | Acquisition.GOV
    Apr 24, 2023 · In particular, contracting officers should avoid protracted use of a cost-reimbursement or time-and-materials contract after experience provides ...Missing: disadvantages | Show results with:disadvantages
  6. [6]
    48 CFR § 16.601 - Time-and-materials contracts. - Law.Cornell.Edu
    A time-and-materials contract acquires supplies/services based on direct labor hours at fixed rates and actual material costs, used when work extent/duration ...
  7. [7]
    Time and Materials Contracts | www.dau.edu
    A Time-and-Materials contract is based on direct labor hours at fixed hourly rates and actual material costs, used when work extent or duration is hard to ...
  8. [8]
    48 CFR § 52.232-7 - Payments under Time-and-Materials and Labor ...
    (i) Individual daily job timekeeping records;. (ii) Records that verify the ... (FAR) 2.101, the price to be paid for such materials shall not exceed the ...
  9. [9]
    52.232-7 Payments under Time-and-Materials and Labor-Hour ...
    Oct 9, 2025 · FAR · 52.232-7 Payments under Time-and-Materials and Labor-Hour Contracts.
  10. [10]
    Subpart 16.3 - Cost-Reimbursement Contracts - Acquisition.GOV
    Cost-reimbursement types of contracts provide for payment of allowable incurred costs, to the extent prescribed in the contract.
  11. [11]
    14 FAH-2 H-230 CONTRACT TYPES
    The labor-hour contract is a variant of the time-and-materials contract, differing only in that the contractor does not supply materials. (Reference 48 CFR ...
  12. [12]
    labor and materials (time and materials) | Wex - Law.Cornell.Edu
    A time and materials contract is where the customer pays the cost of labor and materials plus a markup, useful when work extent is hard to estimate.
  13. [13]
    Time and Materials Contracts: Comprehensive Guide - Southron Firm
    Mar 3, 2025 · What are the key components of a time and material contract? · Scope of Work: A clear and detailed description of the work to be performed.
  14. [14]
    Time and Materials (T&M) Contracts in Construction - Procore
    Aug 7, 2025 · Essentially, the basis of the contractor's bid includes the unit costs of materials, an hourly or daily rate, and contractor markup.
  15. [15]
    Time and Materials Contract (T&M): When to Use One & Best Practices
    May 13, 2025 · This section breaks down how the contractor will be paid: hourly labor rates, materials markup, equipment charges and subcontractor costs. It ...
  16. [16]
    Time and Materials (T&M) Contracts: How They Work and ... - NetSuite
    usually between 15% and 35%. Where appropriate, the contract should also ...
  17. [17]
    Time and Materials (T&M) Contract: Key Clauses, Pros & Cons - Mastt
    Feb 12, 2025 · It typically includes key elements such as scope of work, labor rates, material costs, payment terms, and a not-to-exceed (NTE) clause to ...
  18. [18]
    Understanding Time and Material Contracts: A Comprehensive Guide
    Dec 3, 2024 · Provide Supporting Documentation: Timesheets: Attach employee time logs. Receipts: Include copies of material purchase receipts. Clearly ...
  19. [19]
    [PDF] The Origins and History of Cost Engineering Introduction Fixed Price ...
    Mar 8, 2022 · Cost engineering evolved from accounting, with early recognition of time and money in 1573. Romans used public contracting with specific cost ...
  20. [20]
    Understanding the Past - Federal Government Contracting
    One important note, in the last decade of the 19th century was the Dockery Commission or the the Dockery-Cockrell Commission of 1893-1895.
  21. [21]
    The US Army Corps of Engineers in the American Civil War
    Here we have gathered resources highlighting the role of Army Engineers in that conflict, including biographies of engineers who played vital roles in the war.Missing: materials | Show results with:materials
  22. [22]
    How the UK Lost Its Shipbuilding Industry - Construction Physics
    Oct 28, 2025 · By the 1850s, the UK was building iron ships more cheaply than wood ships, and while it took decades for iron, steel and steam to displace wood ...Missing: materials | Show results with:materials
  23. [23]
    [PDF] REARMING FOR THE COLD WAR 1945-1960 - OSD Historical Office
    Converse, Elliott Vanveltner. Rearming for the Cold War, 1945-1960 / Elliott V. Converse III. p. cm. -- (History of acquisition in the Department of Defense ...
  24. [24]
    The History and Future of U.S. Defense Acquisition - NSTXL
    May 21, 2025 · A Brief History of Military Procurement​​ After World War II, the Armed Services Procurement Act of 1947 laid the foundation for a unified ...
  25. [25]
    Subpart 16.6 - Time-and-Materials, Labor-Hour, and Letter Contracts
    A time-and-materials contract provides for acquiring supplies or services on the basis of- (1) Direct labor hours at specified fixed hourly rates.
  26. [26]
    [PDF] 12954 Federal Register / Vol. 49, No. 63 / Friday, March 30, 1984 ...
    Mar 30, 1984 · Federal Acquisition Regulation (FAR) and other directive material contained in this Federal Acquisition Circular is effective April 1,1984.
  27. [27]
    Development and Structure of the International Software Industry ...
    This paper is an attempt to develop a model of the software industry based on historical principles in order to complement a number of studies of the ...
  28. [28]
    [PDF] Software in the 1960s as Concept, Service, and Product
    In the 1960s, software was hardware's complement, often systems software, and included tools/services from outside vendors, not just programs.
  29. [29]
    [PDF] HR-97-4 High-Risk Series: Defense Contract Management - GAO
    In 1990, the General Accounting Office began a special effort to review and report on the federal program areas its work identified as high risk because of ...Missing: overruns | Show results with:overruns
  30. [30]
    [PDF] 2014 EU Directives - OECD
    Utilities: Article 51 also includes transparency requirements and provides that framework agreements are generally not to exceed eight years. Under the 2004.
  31. [31]
    Time and Material (T&M) Contract in Construction - PowerPlay
    Jun 28, 2024 · A Time and Materials (T&M) contract provides flexibility and is ideal for projects with undefined scopes, as it charges based on actual labour ...
  32. [32]
    Time & Materials Contracts: Structure, Use Cases, & Best Practices
    May 5, 2025 · Labor rates remain unchanged throughout the duration of the contract period. Clients need to pay based on weekdays that contractors stay to work ...
  33. [33]
    How to Create Time and Materials Billing for Construction Projects
    Key Components of a Time and Materials Agreement · Labour rates and categories · Material costs and markup · Not-to-exceed clauses · Billing frequency and ...
  34. [34]
    Time and Materials Contracts Explained: A Full Guide for 2025
    Jan 29, 2025 · For example, a time and materials contract may charge $100 per hour, while a cost-plus contract charges $80 per hour with a 20% markup.Missing: typical | Show results with:typical
  35. [35]
    Time and Materials (T&M) Contract: Simple Overview - AcqNotes
    Mar 4, 2024 · Risk Allocation: Be aware that the government bears a large percentage of the risk associated with T&M contracts because the final cost will be ...
  36. [36]
    Time and Materials Contracts: A Breakdown - HyperStart CLM
    Oct 1, 2025 · Successful T&M contracts specify detailed labor rate structures that account for different skill levels, seniority, and specialized expertise.<|control11|><|separator|>
  37. [37]
    Demystifying Time & Materials Contracts: A Comprehensive Guide
    Jan 25, 2024 · Risk Allocation: – Clients bear the risk in T&M contracts, covering additional costs if the project takes longer or requires more materials. – ...
  38. [38]
    Federal Acquisition Regulation; FAR Case 2004-015, Payments ...
    Dec 12, 2006 · T&M contracts are only used when it is not possible at the time of award to estimate accurately the extent or duration of the work. It may be ...
  39. [39]
    Federal Acquisition Regulation; Payments Under Time-and ...
    Jul 27, 2011 · The noncommercial T&M clause provides that the price to be paid for commercial-item materials “shall not exceed” the contractor's established ...
  40. [40]
    16.602 Labor-hour contracts. - Acquisition.GOV
    A labor-hour contract is a variation of the time-and-materials contract, differing only in that materials are not supplied by the contractor.
  41. [41]
    Types of Government Contracts and the Basics of How They Work
    Mar 6, 2023 · A hybrid example might be fixed price contract for items with T&M provisions for support or installation of the items after acceptance.
  42. [42]
    The special challenges of project management under fixed-price ...
    May 10, 2015 · Hybrid Contract—Under this approach, a fixed-price contract is executed to perform specific tasks or phases with clear requirements and less ...
  43. [43]
    [PDF] Time-and-materials and labor-hour (T&M/LH) contracts
    T&M/LH contracts are used when the extent or duration of work cannot be estimated, and no other contract type is suitable. A D&F is required.
  44. [44]
    Contract Types for Agile Development Contracts - TechFAR Hub
    Firm Fixed Price and/or Time & Materials/Labor Hour can be used on Agile software development contracts. ... IDIQ contracts can be structured as hybrid contracts ...
  45. [45]
    Construction time tracking software for trade contractors - Knowify
    Track and approve your team's time, see how labor hours impact project costs in real time, sync time with QuickBooks for accurate payroll.Track Every Hour For Payroll... · Real-Time Labor Costing · Payroll Integration
  46. [46]
    The Ultimate Guide to Digital Time & Materials Tracking - Rhumbix
    Jun 24, 2021 · Digital time & materials tracking software provides real-time visibility of field activities and approvals before the project ends.Missing: century history
  47. [47]
    T&M Contract vs. Fixed-Price Contract: The Pros and Cons | H+M EPC
    May 4, 2023 · Risk transference: For fixed-price contracts, the bulk of the financial risk is on the contractor as opposed to the project owner. Contractors ...
  48. [48]
    Time & Materials Contract vs. Cost-Plus Contract: Choosing the Best ...
    Dec 12, 2024 · When to Use a T&M Contract: A T&M contract is best suited for extended projects with uncertain scopes or durations that are difficult to ...Missing: emergency repairs
  49. [49]
    Hourly Billing: Strategies for Profitability and Trust - ITM Platform
    Nov 14, 2024 · Time and Materials (T&M): Clients are billed based on the time spent ... Efficiency Incentive: Teams are motivated to complete tasks promptly.3. Billing Methods And... · Estimated Hours Vs. Actual... · Actual Hours
  50. [50]
    Why Hourly Contracts Are Great for Building New Apps - Twin Sun
    Feb 20, 2023 · Hourly contracts, also known as time and materials (T&M) ... The development team would be motivated to complete the contractual ...
  51. [51]
    Time and Materials Contract: Items, Uses, Pros and Cons | Indeed.com
    Jun 6, 2025 · Pros of T&M contracts · Billing flexibility · Increased transparency · Improved client relationships · Adjustable deadlines. While a T&M ...
  52. [52]
    The Pros And Cons Of Fixed-Price Vs. Time And Materials Contracts
    T&M Contracts emphasize transparency, as clients are billed for the actual time worked and the materials used. Itemized invoices provide a clear view of labor ...
  53. [53]
    Time and Materials vs. Fixed Fee Contracts: Pros, Cons & Choosing ...
    A time and materials contract involves more complex recordkeeping than a fixed fee contract, but offers more security to a general contractor, as they can ...Fixed Fee Contracts · Time and Materials Contracts · Advantages for Contractors
  54. [54]
    Labor Rate for Construction - How Much to Charge?
    By default, I would price most jobs for a 3-person crew using $50/HR/MAN as the BASE RATE. Using this BASE RATE will allow for the proper margin with any ...Labor Rate For Construction... · Labor Rate Calculation... · Using Base Rates To...
  55. [55]
    What You Need to Know About Time and Materials Contracts
    May 9, 2022 · A time and materials contract ensures work is completed at a fixed hourly rate not to exceed conditions at a set ceiling price as defined by ...Missing: percentage | Show results with:percentage<|control11|><|separator|>
  56. [56]
    How Much Does a Home Addition Cost? - The Spruce
    Sep 17, 2024 · Average Cost, $50,000. Low-end, $4,000. High-end, $155,000. Average Cost. The average national cost of a home addition is around $50,000. Adding ...Costs · Increasing Price · Decreasing Price
  57. [57]
    Time and Materials (T&M) Contracts Explained - Drawer AI
    Sep 3, 2025 · Labor Rates: Detailed breakdown of hourly or daily rates for various roles (e.g., project manager, skilled tradespeople, general laborers).
  58. [58]
    Tariff and supply chain considerations for Construction - RSM US
    Jun 17, 2025 · RSM provides construction management considerations for navigating tariff and supply chain challenges, including material price uncertainty.
  59. [59]
    How Extreme Weather is Impacting the Construction Industry - CMiC
    Extreme weather causes labor shortages, disrupts projects, disrupts equipment, and causes material scarcity and price increases in the construction industry.1. Labor Shortage · 2. Unusual Weather... · Cmic Financials
  60. [60]
    FEMA Contracting | Hurricanes & Flooding
    Time-and-material contracts: involve payment based on time spent and materials used, suitable for projects where the scope is not clearly defined. These ...
  61. [61]
    NAVFAC Southeast Awards Three Contracts for Hurricane Sally ...
    Apr 23, 2025 · NAVFAC Southeast has awarded three contracts to support ongoing recovery efforts for infrastructure damaged by Hurricane Sally in 2020.
  62. [62]
    Software Contracts: Time and Materials (T&M) vs. Fixed Price Devlane
    Fixed price contracts agree on one price for a defined project, while T&M contracts bill hourly for work within a scope, often for long-term projects.
  63. [63]
    [PDF] Contracting for Agile: finding a better way. - KPMG International
    Time and Materials (T&M) seems the most straightforward approach. We estimate that around 70% of Agile projects are contracted for in this way. However, this ...
  64. [64]
    Fixed Price vs Time & Materials Contracts - EliteCoders
    Compare fixed price vs time & materials contracts with real cost analysis, risk assessment, flexibility metrics, and payment structures.
  65. [65]
    Software Development Contracts: Fixed-Price vs. Time-and-Materials
    Apr 10, 2025 · Under a time-and-materials contract, you pay for the work and the expertise of the development team, which you can direct in any way you desire.
  66. [66]
    Time Tracking [Tips & Best Practices] - Project management - Atlassian
    Upgrade your time tracking with Jira​​ Jira facilitates time tracking by allowing teams to assign tasks, track progress, and log work hours against specific ...Benefits Of Effective Time... · Tips For Successful Time... · Best Practices For Time...
  67. [67]
    T&M Contract Management in Agile Projects: A Practical Guide
    Dec 8, 2024 · Common risks include scope creep, budget overruns, misalignment of expectations, and inadequate resource allocation. How can you mitigate risks ...
  68. [68]
    252.204-7023 Reporting Requirements for Contracted Services.
    The contractor shall report annually, by October 31, at https://www.sam.gov , on the services performed under this contract or order, including any first-tier ...Missing: T&M | Show results with:T&M
  69. [69]
    L3 Technologies Inc agrees to pay $62 million to resolve False ...
    Aug 7, 2025 · The settlement also resolved claims that L3 failed to disclose accurate, complete, and current cost or pricing data related to labor, materials, ...
  70. [70]
    A Guide to Time and Materials (T&M) Contracts - Autodesk
    Jun 6, 2025 · When using a time and materials contract, contractors must ensure they have agreement from the owner in terms of payment milestones. Labor rates ...