Big Dig

The Central Artery/Tunnel Project, commonly known as the Big Dig, was a massive initiative in , , undertaken from 1991 to 2007 to replace the aging elevated —a 1.5-mile (2.4 km) built in the —with an underground highway tunnel through downtown, while extending eastward via the to connect the directly to and constructing the cable-stayed Bunker Hill Memorial Bridge over the . The project encompassed 7.8 miles (12.6 km) of new roadways, including three major harbor tunnels and extensive interchanges, aimed at alleviating chronic congestion in one of the nation's most densely developed urban cores. Despite its engineering innovations—such as tunnel construction and the deployment of advanced techniques in challenging glacial till and fill conditions—the Big Dig delivered measurable improvements in , reducing peak-hour delays on the former by up to 62% and enabling smoother regional mobility that supported economic expansion. The demolition of the elevated structure freed up 300 acres of surface land, fostering the creation of the , a system with public plazas, waterfront access, and green spaces that enhanced urban livability and property values in adjacent neighborhoods. However, the project became emblematic of fiscal and managerial dysfunction in large-scale endeavors, with initial cost projections of $2.8 billion escalating to $14.6 billion due to scope expansions, design revisions, litigation, and contractor disputes, alongside delays that pushed full opening from 1998 to late 2007. Compounding these overruns were persistent defects, including widespread infiltration and, most critically, the July 10, 2006, partial of a 40-ton ceiling panel in the Interstate 90 connector , which killed a when unsecured concrete anchors failed under epoxy that did not meet specifications. Subsequent investigations revealed systemic lapses in and oversight by project managers and contractors, leading to federal probes, criminal charges against a supplier, and multimillion-dollar settlements.

Origins and Rationale

Central Artery Deficiencies and Pre-Project Context

The , an elevated six-lane highway designated as , was constructed in the to route through traffic around as part of the emerging . Designed to handle approximately 75,000 vehicles per day upon its opening in 1959, the structure quickly proved inadequate as vehicular demand surged due to postwar suburbanization and economic growth in the region. By the early , daily traffic volume had exceeded 200,000 vehicles, resulting in chronic congestion that persisted for over 10 hours each day and exacerbated delays across the metropolitan area. Safety deficiencies compounded the traffic issues, with the Central Artery recording an accident rate four times the national average for urban highways, attributed to tight merges, deteriorating , and high speeds amid bottlenecks. The elevated also inflicted broader harms, physically bisecting neighborhoods like the West End and North End, displacing over 20,000 residents during construction, and generating persistent noise, , and shadows that depressed adjacent property values and hindered pedestrian connectivity. These factors contributed to economic losses, including wasted fuel from idling vehicles and reduced productivity from delayed commutes and deliveries. Pre-project assessments in the 1970s and highlighted these escalating problems, prompting Department of studies that identified the Artery's obsolescence and advocated for its replacement to restore urban cohesion and accommodate projected growth. A 1982 engineering evaluation specifically recommended depressing the highway into a to mitigate , improve , and eliminate the barrier effect on the , setting the stage for federal authorization of the /Tunnel Project in the late . By 1985, detailed planning had formalized the need for innovative underground solutions to address the Artery's fundamental design flaws, which had transformed a once-optimistic solution into a symbol of shortcomings.

Conception Amid Urban Renewal Debates

The elevated , constructed between 1953 and 1959 as part of federal interstate highway initiatives intertwined with programs, displaced approximately 20,000 residents, demolished diverse neighborhoods like parts of the West End and South End, and erected a barrier that severed from the North End waterfront and adjacent communities. By the late , this structure—designed for 75,000 vehicles daily—was handling far higher volumes, fostering chronic , elevated accident rates four times the national average, and estimated at $500 million annually in lost productivity. Public backlash against such "bulldozer" renewal tactics peaked in the 1970s, halting projects like the Inner Belt Expressway—a proposed circumferential route that would have further encroached on residential areas—and prompting a 1970 moratorium on new highway construction within Route 128 under Governor . Influenced by environmental litigation, neighborhood advocacy, and the , debates shifted toward preserving urban cohesion over expansive road-building, with critics decrying how elevated highways amplified blight, noise, and visual disruption while failing to resolve underlying traffic issues. Fred Salvucci, an MIT civil engineering alumnus and Massachusetts Secretary of Transportation under Governor Michael Dukakis from 1975 to 1979, originated the core concept of "depressing" the Central Artery into an underground tunnel during this era, drawing from his earlier activism against neighborhood-destroying expressways. Salvucci's proposal envisioned an 8- to 10-lane immersed-tube and cut-and-cover tunnel system to replace the deteriorating viaduct, reconnecting severed urban zones with parks and plazas in the freed surface space, while integrating a third harbor tunnel for Logan Airport access to secure federal funding and business support. This hybrid approach, first sketched in the mid-1970s and refined post-Salvucci's tenure, marked a pivot from 1950s demolition-heavy renewal to mitigation strategies emphasizing minimal displacement and environmental restoration, though it still faced scrutiny for potential construction disruptions. Formal planning advanced with the 1982 initiation of environmental impact studies, culminating in the 1985 Final Environmental Impact Report approved in , which projected without intervention daily congestion extending to 16 hours by 2010. Congressional authorization followed in , embedding the project within evolving urban policy that balanced imperatives against the era's anti-highway ethos.

Planning and Design

Initial Proposals and Alternatives Considered

The Boston Transportation Planning Review (BTPR), initiated in July 1971 and completed in 1973, represented the first systematic examination of alternatives to address congestion on the elevated (I-93), which had opened in 1959 and was already handling over 100,000 vehicles daily by the early . The BTPR evaluated options including a "do-minimum" approach with minor upgrades, widening the existing elevated structure to 10-12 lanes, and depressing portions of the highway underground to reconnect divided neighborhoods and reduce visual blight, while integrating potential transit enhancements like rail upgrades. These proposals emphasized causal links between decay—such as the Artery's rusting and induced spillover—and broader urban mobility failures, prioritizing empirical modeling over indefinite postponement. By 1982, formal planning advanced under the Highway Department, refining the depression alternative as the preferred solution: submerging 3.5 miles of I-93 into an 8-to-10-lane cut-and-cover tunnel from the to , alongside a 1.5-mile immersed-tube tunnel extension of I-90 () under to Logan Airport. Widening the elevated was rejected due to projected air quality violations under Clean Air Act standards, high disruption costs exceeding $1 billion in property impacts, and failure to mitigate community severance, as modeled in environmental assessments showing persistent 20-30% capacity shortfalls. Full surface boulevard conversion was dismissed for inducing even greater , given data from similar urban reconstructions indicating 40-50% traffic diversion to local streets without underground capacity. Proposals also incorporated a North-South rail link beneath the depressed Artery to connect commuter lines, aiming to shift 10-15% of trips from highways based on BTPR ridership forecasts, but this was excised in 1987 after President Reagan vetoed federal authorization, citing diversion of interstate funds to non-highway elements amid a $2.3 billion initial estimate. The final scope, approved by Congress in April 1987, focused on highway-centric depression and tunneling, with later additions like (Silver Line) substituting for heavy rail to comply with mandates. This selection reflected first-principles of throughput gains—projected to add 190,000 vehicles per day—over less scalable alternatives, though critics noted underestimation of from empirical studies of prior urban freeway expansions.

Engineering Challenges and Innovative Solutions

The Central Artery/Tunnel Project encountered formidable engineering challenges stemming from Boston's dense urban fabric and geotechnical conditions. The city's subsurface featured compressible glacial clays and fills overlying bedrock at depths exceeding 100 feet in places, posing risks of settlement and instability during excavation. These soils, combined with high groundwater levels, necessitated advanced stabilization to prevent damage to adjacent structures, including historic buildings, subways, and active rail lines. Construction had to proceed with minimal disruption to ongoing traffic on the elevated Central Artery, which carried over 190,000 vehicles daily, while coordinating around unforeseen utilities and variable soil strata that led to ground movements. To address excavation stability for the I-93 tunnel, engineers deployed technology on an unprecedented scale in the United States. These diaphragm walls, installed via to stabilize trenches before pouring concrete, formed watertight barriers up to 120 feet deep and supported temporary bracing during cut-and-cover operations. walls underpinned the existing elevated structure, allowing sequential and replacement with the 1.5-mile below. For underwater segments, the utilized construction, the first major application of this method in for a project. Prefabricated concrete tube sections, each weighing approximately 35,000 tons, were floated into position, submerged into dredged trenches in , and connected with watertight joints to form a 1.6-mile dual-tube structure at depths up to 100 feet below the surface. This approach minimized disruption and enabled rapid assembly compared to traditional bored tunneling in soft sediments. Overland obstacles, such as active rail tracks, were overcome through tunnel jacking techniques. Precast concrete box sections were hydraulically jacked into place over distances up to 500 feet, using deep soil mixing with to stabilize surrounding and reduce risks. The Bunker Hill Bridge incorporated a cable-stayed with 28 pairs of curved cables from a single , creating the world's widest such span at 10 lanes and 1,800 feet long, which preserved surface space for the Rose Kennedy Greenway park. These methods collectively enabled the project's completion despite the complexities of integrating 7.8 miles of new roadways beneath an operating city.

Approval and Early Obstacles

Political and Regulatory Hurdles

The approval of the Central Artery/Tunnel (CA/T) Project, known as the Big Dig, required navigating extensive federal and state regulatory frameworks, including compliance with the (NEPA) through multiple Environmental Impact Statements (EIS). The Final EIS/Report (FEIS/R) was filed in 1985 and approved in early 1986, followed by a Final Supplemental EIS/Report (FSEIS/R) in 1991, which addressed evolving design elements and secured the Federal Highway Administration's (FHWA) Record of Decision—the formal go-ahead for construction—in the same year. These reviews incorporated mitigation measures for air quality, noise, wetlands, and historic sites, which ultimately comprised over one-fourth of the project's budget to offset urban disruptions. Political support at the state level, driven by figures like Governor in the 1980s, secured initial momentum, but sustaining it demanded intensive lobbying amid community opposition from neighborhoods such as the North End and , where residents feared increased traffic, noise, and displacement. Federal endorsement came via congressional approval of funding and scope in April 1987, with an initial allocation of $755 million in 1990, though this hinged on demonstrating interstate highway benefits under programs like the . Regulatory complexity escalated with over 1,000 permit actions across federal, state, and local agencies, plus more than 500 conditions, making the Big Dig the most heavily permitted infrastructure project of its era and contributing to delays in decision-making. A pivotal regulatory hurdle emerged in the early over the proposed Scheme Z viaduct crossing the , which faced vehement local and environmental opposition for its visual and ecological impacts, prompting regulators to a redesign. This led to a three-year revision process, culminating in approval of the revised Crossing in 1994 and construction start in 1997, at an added cost of $1.4 billion. Politically, managers in 1994–1995 revised cost estimates downward from $13.8 billion to $8 billion through measures like applying a 13% market discount, a tactic critics later attributed to avoiding "sticker shock" and preserving legislative and federal backing, though it masked underlying risks. By 1997, the Legislature established the Metropolitan Highway System to streamline funding via tolls and bonds, signed into law by Governor William Weld on March 20, ensuring continuity despite these pressures.

Environmental and Community Opposition

Environmental groups, including the Conservation Law Foundation (CLF), raised concerns about the project's potential to exacerbate through induced traffic demand and the filling of approximately 40 acres of tidal wetlands for tunnel construction and ventilation structures. CLF advocated for extensive mitigation measures during the (NEPA) review process in the , demanding offsets such as enhanced public transit investments to counteract projected increases in vehicle miles traveled, estimated at up to 20% regionally. These groups successfully pressured planners to commit to over 1,200 specific environmental mitigations, including stormwater management systems and habitat restoration, though enforcement disputes persisted, leading to lawsuits like CLF v. Romney in 2005, which sought compliance with transitway construction promises to reduce emissions. An early legal challenge came in the late when environmental advocates filed suit over inadequate assessment of alternatives and impacts, but the case was dropped in March 1992 after negotiations incorporated additional safeguards, clearing a key hurdle for federal approval. Critics argued that the project's scale would overwhelm urban air quality standards, with initial environmental impact statements projecting non-compliance with Clean Air Act limits without mitigations like high-occupancy vehicle lanes and improved . Community opposition centered on construction disruptions and design elements threatening neighborhood cohesion, particularly in and the North End. In , residents and groups like the Chinese Progressive Association protested the proposed DD (Depressed Downtown) ramp in the late and early , citing risks of heightened truck traffic, noise, and in an already densely populated, low-income area historically divided by highways. Activists organized marches and meetings with project officials, arguing the ramp would encroach on open space and exacerbate issues, leading to design modifications that reduced its footprint and incorporated community input. North End residents expressed apprehensions over temporary noise, dust, and access restrictions during demolition of the elevated , as well as permanent stacks potentially emitting fumes near historic sites, though many supported the project for removing the "" that had shadowed the neighborhood since 1959. Neighborhood coalitions negotiated mitigations like archaeological protections, which uncovered over 7,000 years of artifacts during excavations, but opposition highlighted broader fears of and displacement amid 16 years of phased construction starting in 1991. These concerns contributed to regulatory delays but were largely addressed through community advisory panels and adjusted alignments, reflecting a pattern of localized resistance yielding concessions rather than project cancellation.

Construction Execution

Key Methods and Technical Implementation

The Central Artery/Tunnel (CA/T) Project, known as the Big Dig, relied on innovative engineering methods to depress the elevated into underground tunnels amid Boston's dense urban environment. Cut-and-cover tunneling formed the core technique for the 1.5-mile , involving sequential excavation within temporary retaining structures while traffic was maintained overhead via temporary decks. Deep slurry walls, exceeding 26,000 linear feet of steel-reinforced , provided retention and support, enabling the removal of the existing elevated structure and installation of tunnel segments. For underwater extensions, the beneath employed construction, the first major U.S. application for a vehicle of this scale. Prefabricated or sections—twelve binocular units each roughly the size of a —were manufactured off-site, floated to the site, positioned in a dredged seabed trench, ballasted with water to sink them precisely, and sealed with bulkheads before backfilling. This method minimized on-site assembly risks and environmental disruption compared to traditional or boring. Passages under active rail lines and embankments utilized tunnel jacking, where box segments were hydraulically pushed into position beneath the tracks without halting rail operations, supported by ground improvement like deep soil mixing for stability. The Bunker Hill Bridge incorporated cable-stayed design with hybrid materials: steel girders spanning the 745-foot main crossing and concrete for backspans, anchored to dual 270-foot towers, marking the widest such bridge globally at ten lanes. Soil freezing and sheet piling supplemented slurry walls in sensitive areas to prevent settlement during excavation. These techniques demanded precise geotechnical monitoring, with extensive use of precast elements accelerating assembly and reducing on-site labor exposure in contaminated urban soils.

Timeline, Delays, and Milestones

Construction of the /Tunnel Project, known as the Big Dig, commenced in September 1991 following federal approval via the Record of Decision issued by the . The project was initially projected for completion by December 1998, but persistent challenges including incomplete designs at contract outset, water infiltration issues in tunnels, and the intricacies of building in a dense setting led to substantial delays. Substantial completion occurred in January 2006, with final project closeout and ancillary work extending into December 2007. Key milestones in the project's execution are outlined below:
YearMilestone
1991Construction begins on and South Boston Haul Road.
1993South Boston Haul Road opens to traffic; all 12 tube sections of immersed and connected on harbor floor.
1995 opens to commercial traffic on December 15.
1999Construction reaches 50% completion; Broadway Bridge and Leverett Circle Connector Bridge open.
2002 Bunker Hill Bridge completed and opens.
2003I-90 Connector to , I-93 northbound tunnel, and I-93 southbound tunnel segments open to traffic.
2005Full I-93 southbound opens; Dewey Square Tunnel and associated ramps operational.
2006Majority of project completed in January; elevated demolition advances; Spectacle Island Park opens.
2007Final street restorations and Greenway development continue; project officially concludes in December.
Delays accumulated from multiple factors, notably the need for design revisions during construction—such as modifications to the Crossing in 1994—and utility relocations that reached only 80% completion by 1997 despite earlier targets. Peak workforce of nearly 5,000 in 2000 underscored the scale, yet interdependent contracts in Boston's constrained geography amplified schedule slippages, with some phases like I-90 extension hindered by specific installation contract issues. By 2001, progress stood at 70%, reflecting slowed momentum from these cascading effects rather than initial planning optimism. The ultimate nine-year extension beyond the 1998 baseline stemmed from underestimation of technical risks in tunneling 100 feet below surface amid active city infrastructure.

Cost Management and Financing

Budget Estimates Versus Actual Expenditures

The Central Artery/Tunnel Project's initial cost estimate, established around 1985 during early planning, stood at $2.56 billion, with an anticipated completion by 1998. This figure encompassed the replacement of Boston's elevated (Interstate 93) with underground tunnels and related infrastructure improvements. Subsequent revisions reflected expanded scope, design refinements, and inflation adjustments, driving estimates higher: $7.74 billion by 1992, $10.4 billion in 1994, and reaching $14.8 billion by 2007 as the project neared substantial completion. funding was capped at $8.549 billion in 1997 through congressional action, prompting to cover overruns via state bonds and toll revenues. Actual expenditures for the core highway and tunnel construction totaled approximately $14.5 billion upon final accounting in the early 2010s, aligning closely with the 2007 revised estimate but exceeding the original by over fivefold. Including service and on borrowings—projected to continue until 2038—the lifetime cost to taxpayers surpassed $24 billion by 2012.
Year of EstimateProjected Cost (billions USD)
19852.56
19927.74
199410.4
200714.8
These escalations stemmed from annual cost updates that incorporated geotechnical challenges, relocations, and measures, though independent audits later critiqued early underestimation practices for lacking sufficient buffers.

Sources of Funding and Overrun Drivers

The /Tunnel Project received funding primarily from federal highway aid and state bonds. The federal contribution totaled approximately $7 billion, drawn from the through Interstate Substitution and National Highway System programs, reflecting the project's designation as a high-priority interstate improvement. The state of covered the balance of roughly $7.8 billion via general obligation bonds, which were to be repaid through tolls on the Metropolitan Highway System (including the and Zakim Bridge), supplemented by state gas taxes and federal reimbursements where applicable. Although early plans envisioned up to 90% federal funding, escalations prompted to impose an $8.549 billion federal cap in the FY 2001 DOT Appropriations Act, compelling to absorb additional overruns via accelerated bond issuances and revenue pledges. Project costs surged from an initial 1982 estimate of $2.6 billion (in then-year dollars) to $14.8 billion upon substantial completion in 2007, with overruns attributable to systemic underestimation, scope expansions, and execution inefficiencies. Inaccurate baseline estimates failed to incorporate adjustments per or adequately model geological uncertainties, such as variable conditions and relocations, necessitating repeated changes and rework. Delays averaging years beyond schedules—driven by regulatory approvals, (e.g., restoration and archaeological protections), and community-mandated modifications—amplified labor, equipment, and financing costs, with idle periods exacerbating unionized workforce productivity issues. Contractor claims and litigation further inflated expenditures, as disputes over changed conditions led to settlements totaling hundreds of millions, including a $352 million contribution from /Parsons Brinckerhoff in 2008 to resolve liability for overruns and defects. Management shortcomings, including fragmented oversight across nearly 100 contracts and insufficient contingency reserves, compounded these issues, as federal audits highlighted inadequate risk pricing and optimistic phasing that masked emerging variances. Ultimately, these drivers reflected causal failures in upfront probabilistic modeling and adaptive , rather than isolated events, resulting in Massachusetts taxpayers bearing an effective share exceeding initial projections by over 200%.

Completion and Operational Infrastructure

Final Construction Phases and Openings

The final construction phases of the /Tunnel Project, commencing around 2003, focused on integrating the underground tunnels with surface connections, bridges, and ramps while demolishing portions of the elevated . These phases marked the transition from major tunneling to operational handover, with key milestones emphasizing traffic redirection to reduce reliance on the aging . In January 2003, the I-90 Connector Tunnel opened on January 18, extending the eastward to via a 3.5-mile route that bypassed surface streets and saved up to 45 minutes in travel time. This was followed by the northbound lanes of the (carrying I-93) and the on March 29, 2003, allowing four lanes of northbound traffic to utilize the 1.5-mile underground segment and the cable-stayed bridge's asymmetrical design. The southbound portions of both the and opened on December 20, 2003, completing initial bidirectional flow through the core downtown tunnel system. Subsequent openings in 2004 included the tunnel connector from to the Leverett Circle area, enhancing northern access. By March 5, 2005, all southbound lanes of I-93 fully opened, incorporating the Dewey Square Tunnel with new entrance and exit ramps, alongside the Zakim Bridge's remaining two cantilevered lanes. These activations represented three major 2003 milestones and addressed critical bottlenecks in the interstate network. The achieved majority completion on January 13, 2006, finalizing connections for the I-90 extension to the airport despite its initial opening for commercial traffic. Overall project substantial completion occurred in December 2007, enabling full demolition of the elevated and paving the way for surface-level urban redevelopment.

Tunnels, Bridges, and Control Systems

The /Tunnel Project constructed three primary tunnels as part of its infrastructure overhaul. The Thomas P. O'Neill Jr. Tunnel, carrying underground through , measures 1.5 miles in length and was built using and cut-and-cover methods, with northbound lanes opening on March 29, 2003, and southbound on December 20, 2003. The tunnel reaches a depth of 120 feet below the Red Line subway at Dewey Square, marking the deepest point of any underground highway in the project. The , an 8-lane structure extending 1.6 miles total (with 0.75 miles underwater), connects to via 12 prefabricated steel tube sections sunk into ; its land-water interface lies 90 feet below the surface, the deepest such connection in , and it opened on December 15, 1995, at a cost of $1.3 billion. The I-90 Extension spans 3.5 miles from the through to the , incorporating cut-and-cover, tunnel jacking, and segments, including the first jacked vehicle tunnels in under Fort Point Channel; it opened on January 18, 2003. Overall, the project delivered approximately 161 lane-miles of highway, with roughly half situated in tunnels. The project's bridges include the Leonard P. Zakim Bunker Hill Memorial Bridge, a cable-stayed structure crossing the Charles River with a total length of 1,432 feet, a main span of 380 feet, back spans of 225 feet, and a width accommodating 10 lanes (eight passing through the towers and two cantilevered). This hybrid steel-and-concrete design, the widest cable-stayed bridge in the world at 183 feet across, utilizes 1,820 miles of steel wire in its support cables and opened in stages between March 2003 and early 2005. The Leverett Circle Connector Bridge, a 830-foot steel box girder structure 76 feet wide carrying four lanes to Storrow Drive, was assembled from barged sections jacked into place and opened in October 1999. Control systems for the tunnels and bridges integrate advanced and across the Metropolitan Highway System, encompassing the , , and to Route 128, with capabilities for radio and cellular signal rebroadcast. The system employs over 35,000 data collection points to oversee , incident response, , lighting, security, and air quality in . is handled by a seven-building , one of the largest highway tunnel systems globally, designed to maintain safe air quality in the extensive underground segments.

Transportation and Urban Impacts

Traffic Flow and Congestion Outcomes

The Central Artery/Tunnel (CA/T) Project, commonly known as the Big Dig, aimed to alleviate severe congestion on Boston's elevated Interstate 93 Central Artery, which by the 1990s carried nearly 200,000 vehicles per day despite being designed for 75,000, resulting in average speeds as low as 10-15 mph during peak hours and over 10 hours of daily gridlock. Post-completion in 2007, the underground O'Neill Tunnel and expanded infrastructure, including the 10-lane Leonard P. Zakim Bunker Hill Bridge, initially improved traffic metrics: total vehicle-hours of delay on project highways decreased by 62% from 1995 levels through 2003, with sustained gains in average speeds and throughput reflecting higher capacity (up to 245,000 vehicles per day on the new I-93 alignment). Specific travel time reductions materialized, such as peak-period trips from the I-90/I-93 interchange to Logan Airport, which shortened by 42-74% due to the and direct connectors, enabling smoother flow for approximately 5,000 daily airport-bound vehicles. Overall —measured by volume times speed—rose 62% compared to pre-project baselines, with accident rates on the replaced corridor falling to below national averages and vehicle-hours of travel dropping substantially amid construction-era disruptions and post-opening efficiencies. These gains translated to annual savings of about $168 million in time and fuel costs for users versus 1995 conditions, per project evaluators. However, long-term congestion outcomes were tempered by , where added capacity attracted more vehicles, filling lanes and shifting bottlenecks to peripheral routes like the Bridge and I-90 approaches. By the mid-2010s, daily volumes on the new I-93 approached design limits, with peak speeds reverting toward pre-Dig lows in some segments despite population and employment growth in ; studies attribute this to elastic driver behavior, where lower costs of travel spurred longer commutes and modal shifts insufficient to offset highway draw. Regional vehicle-miles traveled rose post-2007, underscoring that while core artery flow enhanced reliability, systemic urban congestion persisted without complementary like or expansions.
MetricPre-Big Dig (1990s)Post-Completion (2007+)
Central Artery Daily Volume~190,000-200,000 vehicles~200,000-245,000 vehicles (I-93 tunnel/bridge)
Peak-Hour Delays10+ hours/day 62% reduction in vehicle-hours vs. 1995
Accident Rate4x national averageBelow national average on new corridors
Empirical assessments indicate the project succeeded in boosting throughput and safety but fell short of eliminating , as latent demand from regional growth—Boston's metro population expanded by over 10% since 2000—eroded initial capacity margins without offsetting policies.

and Property Effects

The Central Artery/Tunnel Project spurred economic development by enhancing connectivity and reducing congestion, attracting over $7 billion in private investment that included construction of 7,700 housing units and 10 million square feet of commercial space along the corridor and in the . This development generated more than 43,000 jobs in those areas, contributing to the growth of Boston's innovation economy, particularly in and sectors within the Seaport. The project's 62% improvement in has yielded annual savings of $167 million in time and operating costs, bolstering regional and business efficiency. These transportation gains facilitated urban revitalization, with the Seaport evolving from underutilized waterfront into a hub for commercial and residential expansion post-completion in the early 2000s. Property effects were pronounced in , where the replacement of the elevated with the Rose Kennedy Greenway—a 17-acre public park system—elevated adjacent values by improving , , and access to amenities. Class-A office buildings bordering the Greenway command a 30% average rent premium over comparable properties elsewhere in the city, reflecting heightened demand driven by the enhanced urban environment. Overall, the Greenway has supported increased commercial activity and property appreciation, though initial construction disruptions temporarily depressed values in affected zones during the 1990s and early 2000s.

Controversies and Failures

Material and Construction Defects

The most prominent material defect in the Big Dig involved the anchors securing ceiling panels in the Interstate 90 connector tunnel, which failed catastrophically on July 10, 2006, when a 26-ton panel and associated debris collapsed, killing passenger Milena Del Valle. The (NTSB) investigation determined that the failure stemmed from —a gradual deformation and fracturing of the adhesive over time—exacerbated by the use of an epoxy not suited for long-term loading, insufficient epoxy volume in 19 of 20 failed anchors due to poor installation, and inadequate post-installation testing and inspections. This led to the removal and replacement of over 4,000 suspect anchors across Big Dig tunnels, with Governor announcing in July 2006 that tests identified more than 1,100 unreliable bolt assemblies using the epoxy. Waterproofing and sealing defects caused widespread tunnel leaks, with federal assessments documenting 400 to 700 infiltration points by 2004, allowing millions of gallons of to enter the system annually and incurring over $10 million in initial repair overruns. These leaks arose from construction flaws in slurry wall joints and membrane applications, compounded by unexpected pressures and rushed , resulting in chronic seepage that corroded electrical systems, flooded vents, and required ongoing pumping in violation of some environmental rules. A 2005 FHWA review noted that while low-level leaks are inherent to and cut-and-cover s, Big Dig defects exceeded expectations due to panel misalignments and incomplete grouting in slurry walls. Slurry wall construction, which formed the primary tunnel enclosures using 120-foot-deep panels, revealed additional defects including voids, misalignments, and substandard quality, as identified in detailed inspections of contracts like C17A1. In September 2004, a wall breach in the caused a sudden water influx onto the roadway, attributed to inspection oversights during panel erection. Contractor C. Rana & Associates faced federal charges in 2008 for falsely certifying defective slurry wall panels as compliant with specifications, despite known material inconsistencies that compromised structural integrity. These issues contributed to a 2008 settlement exceeding $450 million from contractors to address leaks, design flaws, and related defects across the project.

Safety Incidents and Liability Issues

The most prominent safety incident occurred on July 10, 2006, when a ceiling panel weighing approximately 26 short tons collapsed in the Interstate 90 connector tunnel, crushing a passing and killing passenger Milena Del Valle while injuring her husband, the driver. Investigations by the identified the primary cause as the failure of anchor bolts securing the panels, attributed to ""—a gradual movement and loosening exacerbated by the use of an inappropriate formulation that did not meet performance specifications for long-term under load. Additional factors included inadequate for potential and insufficient monitoring protocols during and after installation. Post-collapse inspections revealed at least 60 similar vulnerability points in the tunnel ceiling, prompting immediate shutdowns and reinforcements across affected sections. Other documented safety issues included pervasive water leaks throughout the tunnel system, with thousands reported stemming from faulty joints, seals, and mixes that allowed infiltration, sometimes at rates of hundreds of gallons per hour in isolated voids. These leaks contributed to structural concerns, including soil voids beneath roadways and corrosion risks to reinforcements, though officials maintained that ongoing pumping mitigated immediate hazards to traffic. Construction-phase incidents involved worker injuries, such as a case where a New Bedford laborer suffered severe harm from a falling steel beam dislodged by a crane, leading to documented violations. Earlier warnings, including a 1999 internal from a , highlighted potential ceiling instability in tunnels due to anchoring deficiencies, though these were not fully addressed prior to the 2006 event. lapses were also noted, with multiple doors in tunnels found blocked, boarded, or missing during audits, impeding emergency egress. Liability disputes centered on contractor accountability for design, material, and oversight failures. The Massachusetts Turnpike Authority pursued claims against primary contractors Bechtel/Parsons Brinckerhoff (B/PB), culminating in a January 2008 settlement exceeding $450 million to address the ceiling collapse, leaks, and defective concrete issues, with B/PB contributing $407 million specifically for these deficiencies. Del Valle's family secured over $28 million in a September 2008 wrongful death settlement from involved parties, including a $6 million portion from fastener supplier Powers Fasteners, while ongoing suits against other subcontractors persisted. The agreements included provisions holding contractors liable for future catastrophic failures exceeding $50 million in damages, reflecting admissions of systemic quality control shortcomings without fully resolving disputes over management practices. Overall, the state filed more than 200 formal complaints encompassing safety violations, though many were settled out of court amid protracted litigation spanning over a decade.

Long-Term Evaluation

Documented Achievements

The Central Artery/Tunnel (CA/T) Project, commonly known as the Big Dig, achieved measurable improvements in regional , with post-completion data indicating a 62% enhancement in overall traffic movement on interstate highways and tunnels compared to baseline conditions. This included higher vehicle speeds and volumes, contributing to annual transportation cost savings estimated at $167 million. Travel times through decreased by up to 62% on key routes, aligning with pre-project projections for relief in one of the nation's most gridlocked urban areas. Safety outcomes were notably positive, with the recording one of the lowest incident rates for a of its scale, far below initial estimates that anticipated one worker fatality per $1 billion in costs. The underground configuration reduced surface-level accident exposure, and citywide levels dropped by 12% following completion, aiding air quality compliance. Urban regeneration via the Rose Kennedy Greenway transformed 300 acres of former highway land into public parks, promenades, and plazas, reconnecting divided neighborhoods such as the North End and while attracting millions of annual visitors for recreation and events. This linear green space spurred $7 billion in adjacent private investment and supported 43,000 jobs through induced development, fostering long-term economic expansion in .

Criticisms, Waste Analysis, and Policy Lessons

The Central Artery/Tunnel Project, commonly known as the Big Dig, drew widespread criticism for its extreme cost overruns, chronic delays, and systemic mismanagement, which exemplified broader challenges in large-scale endeavors. Initially projected at $2.6 billion in 1985 with a completion target of 1998, the project's construction costs alone reached $14.6 billion by its substantial completion in December 2007, a more than fivefold escalation driven by scope expansions, design changes, and underestimated complexities in urban tunneling. When factoring in financing costs and interest on debt, the total expenditure surpassed $24 billion as of 2012 assessments by officials. Delays extended the timeline by nearly a , with full not achieved until 2012, exacerbating disruptions and costs estimated at $500 million annually in pre-project alone. Detractors, including auditors and overseers, highlighted opaque , such as the of 1994 cost estimates from an internal $13.8 billion figure to a public $8 billion projection for political and bonding purposes, which eroded public trust and invited accusations of deliberate deception. Waste analysis reveals inefficiencies rooted in flawed accounting, inadequate oversight, and unrecovered expenditures. Project managers employed optimistic assumptions, including a 13% market discount rate and insufficient contingencies for change orders (initially budgeted at 7%), which masked emerging overruns totaling $2.5 billion by late 2000 and contributed to a final exposure exceeding initial forecasts by over $6 billion. The cost recovery program, intended to recoup funds from contractors for deficiencies, yielded negligible results, recovering just $30,000 from $83.5 million in related change orders over six years, hampered by procedural neglect such as lost files, average case closure times of 394 days, and elimination of mandatory legal reviews. Conflicts of interest further compounded waste, as the primary management consultant, Bechtel/Parsons Brinckerhoff, assessed its own liability through subcontractors, undermining impartiality and full accountability for design flaws that inflated downstream construction expenses. These issues stemmed from over-reliance on a single integrated team without sufficient independent checks, leading to unquantified but substantial leakage in claims processing and scope adjustments, with post-1994 contract awards alone surpassing prior estimates by billions due to unmitigated design growth. Policy lessons from the Big Dig underscore the necessity of rigorous, independent cost estimation incorporating historical data, projections, and realistic buffers to counteract prevalent in megaprojects. Effective management requires delinking oversight from primary contractors to eliminate conflicts, mandating standardized procedures for claims and with dedicated , and enforcing transparent of overruns to legislatures and markets to prevent breaches. Balancing collaborative team structures with external audits can mitigate , while prioritizing federal-state coordination early ensures funding alignments without deferred liabilities; ultimately, these elements highlight that underestimating urban geotechnical and logistical variables in dense environments demands phased piloting over all-encompassing designs to contain fiscal drift.

References

  1. [1]
    The Big Dig: project background - Mass.gov
    The Central Artery/Tunnel Project was the largest, most challenging highway project in the history of the United States. It reduced traffic and improved ...Introduction · The Problem · The Solution · The Challenges
  2. [2]
    Project Profile: Boston Central Artery/Tunnel Project, Massachusetts
    The Central Artery/Tunnel Project opened three major highway tunnels and an innovative river crossing. The reconstruction of I-93 through downtown Boston.
  3. [3]
    The Big Dig: tunnels and bridges - Mass.gov
    The Central Artery/Tunnel Project opened three major highway tunnels and an innovative river crossing. Descriptions of the major underground features of the ...The Ted Williams Tunnel · The Thomas P. O'Neill, Jr... · The Charles River Bridges
  4. [4]
    Issues Concerning the Boston Central Artery/Tunnel (CA/T) Project
    Apr 22, 2005 · This $14.6 billion project has been the largest, most expensive, and most complex highway project in U. S. history. With the opening of the full ...
  5. [5]
    [PDF] 2007-0510-3C1 Central Artery / Tunnel Project (CA/T) - Mass.gov
    Jul 30, 2007 · In 1989, CA/T Project management estimated that the Project, as then configured, would cost $4.4 billion and would be completed in 1998. The ...
  6. [6]
    [PDF] Ceiling Collapse in the Interstate 90 Connector Tunnel Boston ...
    Jul 10, 2006 · Ceiling Collapse in the Interstate 90 Connector. Tunnel, Boston, Massachusetts, July 10, 2006. Highway Accident Report NTSB/HAR-07/02.
  7. [7]
    State of Massachusetts Settles Ceiling Collapse for $26 million with ...
    Nov 21, 2008 · The State of Massachusetts $21 million for damages resulting from the I–90 connector tunnel ceiling collapse on July 10, 2006.
  8. [8]
    Powers Fasteners, Inc. Charged with False Statement in Connection ...
    Sep 18, 2009 · Powers Fasteners, Inc. Charged with False Statement in Connection with I-90 Ceiling Collapse on Big Dig Project. U.S. Attorney's Office ...
  9. [9]
    Destruction and Disappointment: The Legacy of Boston's Central ...
    The Central Artery caused demolition, displacement, and disappointment. It failed to improve traffic, displaced 20,000 people, and had high accident rates.
  10. [10]
    Big Lessons from the Big Dig - July 2001 - FHWA-RD-01-065 - Focus
    The 14-year endeavor, scheduled for completion in 2004, will replace an existing 6-lane elevated viaduct structure with a 10-lane underground expressway.
  11. [11]
    The Big Dig: Learning from a Mega Project - nasa appel
    Jul 15, 2010 · Boston's Central Artery/Tunnel Project, commonly known as the Big Dig, was the largest, most complex, and most technically challenging highway project in ...
  12. [12]
    Project: Central Artery Tunnel - View Case Study | AASHTO
    The official cost is still quoted at $14.8 billion (2002$). There is ... day in 2004, when the project was largely complete. Meanwhile, total daily ...
  13. [13]
    The Changing Politics of Urban Mega-Projects
    Oct 1, 2003 · Illustratively, Boston's Big Dig was conceived by Fred Salvucci, a transportation engineer who had become active in battles against planned ...
  14. [14]
    [PDF] THE BOSTON TRANSPORTATION PLANNING REVIEW
    The Boston Transportation Planning Review (BTPR) was initiated in July 1971 and ... The key technical act in the BTPR was to generate alternatives and ...Missing: Central Artery
  15. [15]
    Full text of "Boston transportation planning review - Internet Archive
    Nov 19, 2024 · ... CENTRAL ARTERY REPORT 86 Pages November, 1972 53 Figures CONTENTS A. ... Central Artery Improvement Alternatives Summary Evaluation B.
  16. [16]
    Rise And Fall Of Highways - North South Rail Link
    In March 1987 President Reagan vetoed funding for the Central Artery Project, specifically citing the inclusion of a rail connection. In the battle to overturn ...Missing: 1980s | Show results with:1980s
  17. [17]
    The Big Dig: Learning from a Mega Project - nasa appel
    Jul 23, 2020 · The Big Dig is also famous for cost increases. Its initial estimated cost was $2.56 billion. Estimates increased to $7.74 billion in 1992 ...
  18. [18]
    Lessons Learned for Ground Movements and Soil Stabilization from ...
    The reduction in unit weight from DSM-treated soil was also observed at the Boston Central Artery/Tunnel Project, as reported by O'Rourke and McGinn [36, 37] ...<|separator|>
  19. [19]
    [PDF] Design for Construction Mitigation on the Central Artery/Tunnel Project
    The Central Artery/Tunnel Project in Boston, Massachusetts, has focused on ... Existing structures and utilities can be damaged by soil movement from tunneling ...
  20. [20]
    [PDF] Managing the Central Artery/Tunnel Project
    This Research Report is brought to you for free and open access by the McCormack Graduate School of Policy and. Global Studies at ScholarWorks at UMass ...
  21. [21]
    [PDF] engineering - A Better City
    But all that began to change in 1991 when con- struction crews broke ground on the Central Artery/. Tunnel Project, commonly known as the Big Dig. The surgery ...<|control11|><|separator|>
  22. [22]
    An innovative solution for Boston's Big Dig | Mott MacDonald
    The elevated section of the Central Artery, which had cut off downtown Boston from the city's North End and waterfront, was replaced with a new 8- to 10-lane ...Missing: renewal debates
  23. [23]
    TOUGH CONDITIONS, INNOVATIVE SOLUTIONS - TRID
    ... Central Artery/Tunnel project. Deep soil mixing (DSM) and tunnel jacking, both extensions of technologies used overseas, are helping engineers and ...
  24. [24]
    Boston Begins Reaping Benefits Of Big Dig | 2015-02-18 | ENR
    Feb 18, 2015 · "The Big Dig pushed civil engineering into the future by deploying the biggest, first and most innovative uses of slurry-wall technology, ...<|control11|><|separator|>
  25. [25]
    Permitting uncontrolled costs - Government Executive
    Apr 1, 2001 · In the early 1990s, permitting and mitigation challenges combined to nearly derail the Big Dig as result of a controversy over a proposed bridge ...<|separator|>
  26. [26]
    [PDF] Boston's Big Dig Project: A Cautionary Tale
    The CA/T Project provides a rich laboratory for studying the inner workings of these mammoth and costly undertakings. My 13-year stint in the Massachusetts ...
  27. [27]
    A Victory 32 Years in the Making - Conservation Law Foundation
    CLF sued Massachusetts over the Big Dig, a massive project that made Greater Boston more accessible by car but brought the burden of higher air pollution to ...
  28. [28]
    [PDF] MATTERS - Conservation Law Foundation
    Apr 27, 2023 · Offsetting the Big Dig's increased pollution was not good enough. ... THE JOURNAL OF CONSERVATION LAW FOUNDATION. VOLUME XXXVIII, NO.1 ...
  29. [29]
    Case Study - PlanWorks | Federal Highway Administration
    Planning for the Big Dig began in 1982 to deal with severe traffic congestion on the existing elevated highway built in 1959. The project included a new tunnel ...
  30. [30]
    Conservation Law Foundation v. Romney
    To offset the environmental impact of the Central Artery/Third Harbor Tunnel Project (Big Dig) in Boston, Massachusetts, the defendants agreed to complete.Missing: opposition | Show results with:opposition
  31. [31]
    Boston's 'Big Dig' project clears important legal hurdle - UPI Archives
    Mar 13, 1992 · An environmental group Friday dropped its suit against a $5.4 billion project to rebuild the city's Central Artery and construct a third ...Missing: concerns | Show results with:concerns
  32. [32]
    Activists speak at a protest against construction in Chinatown - DRS
    Chinatown residents formed a community coalition to stop the proposed Central Artery DD Ramp; the off-ramp would cause increased traffic and air pollution in ...
  33. [33]
    Protestors and officials meet to discuss the Central Artery/Tunnel ...
    Chinese Progressive Association members and Chinatown activists seated in a meeting with Central Artery/Tunnel Project officials to discuss the DD Ramp. In this ...Missing: groups | Show results with:groups
  34. [34]
    Demonstrators assemble to begin marching against the proposed ...
    Chinese Progressive Association members and other Chinatown activists prepare to oppose the Central Artery/Tunnel Project DD Ramp.
  35. [35]
    Boston's Big Dig - Secretary of the Commonwealth of Massachusetts
    As archaeologists removed the layers of soil, they revealed more than 7,000 years of Boston's prehistory and history. The sites in Charlestown, the North End, ...Missing: opposition | Show results with:opposition
  36. [36]
    The Big Dig: facts and figures - Mass.gov
    Traffic. The elevated Central Artery had six lanes. · Dirt. The project excavated a total of 16 million cubic yards of dirt, enough to fill a stadium to the rim ...
  37. [37]
    [PDF] Central Artery/Tunnel Project: A Precast Bonanza - PCI.org
    The Big Dig has been instrumental in bringing new techniques and tech nology to the field of precast concrete construction; however, the project has not ...Missing: key | Show results with:key
  38. [38]
    – LEONARD P. ZAKIM/BUNKER HILL BRIDGE
    The bridge design comprises the hybrid composition of steel in the 745-foot main span and concrete in the bridge back spans, supported by the two, 270-foot ...
  39. [39]
    Central Artery Project "The Big Dig" | www.usa.skanska.com
    The construction of the tunnel and boat sections required a combination of slurry walls, sheet piling and soil stabilization using a freezing technique.
  40. [40]
    INSPECTING THE BIG DIG AND THE PERFORMANCE OF ... - GovInfo
    This ambitious project will provide countless benefits to the city of Boston in the way of enhancing safety, easing traffic congestion, providing acres of open ...
  41. [41]
    BIG DIG UPDATE - Roads and Bridges
    Inaccurate designs. Globe finding: Construction on many of the Big Dig's major contracts began with incomplete and inaccurate designs, causing costly delays.
  42. [42]
    Big Dig, Central Artery/Tunnel Project (CA/T) - DEITABASE
    Jun 16, 2023 · The main purpose of the big dig is to alleviate the pressure of highway traffic. In late 20 century, the traffic congestion rate of Boston ...
  43. [43]
    2. Cost and Schedule Procedures | Completing the "Big Dig"
    The IPO reported to the committee that the continued delays in opening the I-90 extension were primarily caused by one contract that involved the installation ...
  44. [44]
    Best Practices for Mega-Project Cost Estimating - Big Dig - PMI
    The Big Dig was conceived in 1985 as a way to alleviate the continuous traffic gridlock in the center of Boston. The original cost estimate was US$2.56 billion.Missing: facts | Show results with:facts
  45. [45]
    Digger Deeper Into the Big Dig Boondoggle
    May 10, 2006 · In 1997, POGO proposed that federal spending on the project should be cappedand Congress listened, imposing an $8.549 billion funding cap. The ...
  46. [46]
    True cost of Big Dig exceeds $24 billion with interest, officials ...
    Jul 10, 2012 · The highway-tunnel work cost $14.5 billion, with the state using $7 billion in federal aid and borrowing the rest. Add interest and the total ...Missing: initial | Show results with:initial
  47. [47]
    [PDF] T-RCED-96-218 Central Artery/Tunnel Project: Cost and Financing
    Jul 11, 1996 · Artery/Tunnel project might not be sufficient to complete ... state officials told us that a plan has not been selected to date, pending.
  48. [48]
    Black hole - Government Executive
    Apr 1, 2001 · The most important of those steps was the signing of an 11-point agreement with FHWA that caps the federal contribution at the $8.549 billion ...
  49. [49]
    Central Artery/Tunnel Project: Cost and Financing | U.S. GAO
    GAO noted that: (1) there may not be sufficient state and federal funding to complete the project by 2004; (2) Massachusetts faces challenges in maintaining its ...Missing: Big Dig
  50. [50]
    [PDF] A History of Central Artery/Tunnel Project Finances 1994 – 2001
    Mar 20, 2001 · It also shows exactly how Big Dig managers decreased the $13.8 billion estimate to $8 billion for public relations purposes in 1994-1995 by ...
  51. [51]
    Bechtel and Parsons Brinckerhoff Reach Settlement on Big Dig
    Jan 23, 2008 · Under the terms of the agreement, Bechtel Infrastructure Corporation (BINFRA) will contribute $352 million toward the settlement, with Parsons ...
  52. [52]
    [PDF] RCED-96-131 Transportation Infrastructure
    May 10, 1996 · As of March 1, 1996, $4.7 billion had been obligated for the Central. Artery/Tunnel project—$4.1 billion in federal funds (86 percent) and about.Missing: cap | Show results with:cap
  53. [53]
    [PDF] Cost Overruns in Infrastructure Projects - Krieger Web Services
    Jun 18, 2020 · The study discussed Boston's Central Artery project, the complex underground highway project known as the “Big Dig,” which had cost overrun ...
  54. [54]
    Transportation And Economic Impacts Of The Central Artery/Tunnel ...
    The study concludes that it will take years before the full impact of the project on travelers, access and the economy will be fully measurable.Missing: neighborhood division
  55. [55]
    Boston's central Artery - About Tunnelling - ITA-AITES
    Traffic crawled for more than 10 hours each day. The accident rate on the deteriorating elevated highway was four times the national average for urban ...The Problem · The Challenges · Achievements<|separator|>
  56. [56]
    Boston Central Artery - Bechtel
    As part of our work on the Central Artery Tunnel, we reconnected these neighborhoods, improving the quality of life in the city beyond the limited confines of ...Missing: division | Show results with:division
  57. [57]
    10 years later, did the Big Dig deliver? - The Boston Globe
    Dec 29, 2015 · The Ted Williams Tunnel became the necessary appendage in the Central Artery and Tunnel project, appealing to the feds because it would complete ...Missing: alternatives | Show results with:alternatives<|control11|><|separator|>
  58. [58]
    Induced Demand in Action: Boston's Big Dig Increases Traffic
    Nov 24, 2008 · While the Big Dig achieved its goal of freeing up highway traffic downtown, the bottlenecks were only pushed outward, as more drivers jockey for ...Missing: study | Show results with:study
  59. [59]
    [PDF] Assessing the Potential Income Equity Impacts of Congestion ...
    The city's investment in the Big Dig—then the nation's largest highway construction project—helped ease road congestion after opening in 2006. Yet the ...
  60. [60]
    Boston's Big Dig: The Lost Files - DGT Associates
    Sep 27, 2021 · The Big Dig, as we came to call it, was an automobile transportation improvement project originally called the Central Artery Third Harbor Tunnel project.Missing: origins | Show results with:origins
  61. [61]
    Managing Traffic in Massachusetts: Assessing the Potential Income ...
    Boston has long grappled with traffic. The city's investment in the Big Dig--then the nation's largest highway construction project--helped ease road congestion ...Missing: study | Show results with:study
  62. [62]
    [PDF] Park Investment and Economic Vitality - Trust for Public Land
    Sep 24, 2024 · Rose Kennedy Greenway in Boston, MA. +30%. Average rent premium for class-A office buildings adjacent to the Greenway compared to those in.
  63. [63]
    Epoxy and Inspections Cited For Fatal Boston Big Dig Tunnel Accident
    Jul 11, 2007 · Using the wrong epoxy led to long-term deformation and failure in the I-90 tunnel plenum that killed a 38-year-old local woman. NTSB also ...Missing: defects | Show results with:defects
  64. [64]
    Romney: 1,100 Big Dig tunnel bolts unreliable - NBC News
    Jul 17, 2006 · Gov. Mitt Romney said Monday that tests show more than 1,100 bolt assemblies that used epoxy and more than 300 other areas in a Big Dig ...
  65. [65]
    $$14.6 billion Boston Big Dig project is leaking - NBC News
    Nov 10, 2004 · The Big Dig highway project in downtown Boston is riddled with leaks dumping millions of gallons of water into the $14.6 billion tunnel system.
  66. [66]
    Big Dig tunnels riddled with leaks, officials deny design flaw
    Nov 28, 2004 · Boston's Big Dig project has developed between 400 and 700 leaks, which have cost $10 million in overruns to repair.
  67. [67]
    FHWA Tunnel Leak Assessment, Boston Central Artery
    Mar 23, 2005 · Field reports indicate that Panel EO-45 contained defects and inclusions that were caused by poor quality control and quality assurance during ...Missing: context | Show results with:context
  68. [68]
    Big Dig violating rules with pumping | News | rutlandherald.com
    Almost all the water is ground water leaking into the tunnels because of defects in walls and waterproofing, according the MWRA. The MWRA is investigating, ...Missing: infiltration | Show results with:infiltration
  69. [69]
    [PDF] The Breach Problems in the Tunnels of the Boston Central Artery ...
    In September 2004, after the tunnel had been opened to traffic for nearly a year, a breach occurred in one of the tunnels walls. Water gushed onto the roadway, ...
  70. [70]
    Big Dig Contractor Charged With Lying - CBS News
    Jun 20, 2008 · The company also allegedly certified that defective concrete panels in slurry walls in O'Neill tunnel were built to specifications, when it knew ...
  71. [71]
    $$450 million settlement covers Big Dig tragedy - NBC News
    Jan 23, 2008 · Contractors will pay more than $450 million to settle the state's lawsuit over a fatal tunnel collapse and to cover the costs of leaks and design flaws in the ...
  72. [72]
    Bechtel shares blame in Big Dig tragedy / Federal safety panel faults ...
    Jul 11, 2007 · Milena Del Valle, a 39-year-old mother of three, was crushed to death a year ago when concrete ceiling panels weighing a total of 26 tons fell ...
  73. [73]
    'Epoxy Creep' Main Factor in Big Dig Ceiling Panel Collapse
    Jul 11, 2007 · The biggest factor in the collapse of Boston's Big Dig ceiling panel which killed a woman a year ago was "epoxy creep." While National ...Missing: incidents | Show results with:incidents
  74. [74]
    The “Big Dig” Tunnel Collapse - Recognizing the impact of PEs
    May 26, 2022 · The collapse was caused by wrong epoxy material, design not accounting for anchor creep, and failure to monitor for anchor creep, leading to  ...
  75. [75]
    Wide Flaws Found in Boston Tunnel After Death - The New York Times
    Jul 13, 2006 · Inspectors found at least 60 more trouble spots in the Big Dig tunnel where a woman was crushed to death on Monday by three-ton ceiling tiles.
  76. [76]
    Big Dig contractors agree to pay $458 million - Phillips & Cohen LLP
    Jan 24, 2008 · B/PB will pay $407 million for mistakes that resulted in the use of defective concrete, thousands of leaks in Big Dig tunnels and a ceiling ...
  77. [77]
    Despite Leak Problem, Void In Soil, State Insists Big Dig Tunnels ...
    Aug 11, 2011 · Officials say drivers are safe because all of that water is being pumped out, but it can be up to hundreds of gallons an hour.Missing: accidents fires<|separator|>
  78. [78]
    Big Dig worker settles for $8M | Massachusetts Lawyers Weekly
    Oct 10, 2005 · A New Bedford laborer will receive at least $8 million and potentially nearly twice that for injuries suffered when a piece of steel fell from a crane and ...Missing: issues | Show results with:issues
  79. [79]
    In '99 memo, safety officer warned about Big Dig tunnel
    Jul 27, 2006 · BOSTON - Seven years before falling concrete crushed a motorist to death inside one of Boston's Big Dig tunnels, a safety officer warned ...
  80. [80]
    Many Fire Doors in Big Dig Blocked or Boarded Up in Massachusetts
    Apr 7, 2005 · A number of fire doors in the Big Dig tunnels are either boarded up or missing and many others are blocked as a result of work to find and ...Missing: accidents | Show results with:accidents
  81. [81]
    Settlement Reached In Big Dig Death Suit - CBS News
    Sep 30, 2008 · The family of a woman who was crushed to death when a Big Dig tunnel ceiling collapsed has settled a wrongful death lawsuit for more than $28 million.Missing: issues | Show results with:issues
  82. [82]
    Anger Over $500M 'Big Dig' Settlement - ABA Journal
    Jan 23, 2008 · Powers Fasteners has settled a lawsuit brought by the victim's family for $6 million, but it continues against other contractors involved in the ...
  83. [83]
    Big Dig Suit Settled for More Than $400 Million - The New York Times
    Jan 24, 2008 · The companies that designed and managed the costly Big Dig project will pay Massachusetts more than $400 million to settle litigation over leaky tunnels and a ...Missing: environmental | Show results with:environmental
  84. [84]
    State, Contractors Settle Suit Over Big Dig Failures - NPR
    Jan 23, 2008 · A group of companies that designed and managed Boston's Big Dig highway project have agreed to a $450 million settlement. State and federal ...Missing: issues | Show results with:issues
  85. [85]
    “Big Dig” producing big benefits - Roads and Bridges
    The report also touted improved traffic conditions prompted by the project. In 1980 it was projected that the project would improve traffic flow through Boston ...
  86. [86]
    Learning from the Big Dig - CommonWealth Beacon
    Aug 2, 2014 · The Big Dig, despite its problems and costs, represents an unprecedented physical improvement for the city and region, and an extraordinary feat of engineering ...
  87. [87]
    The Big Dig and Spectacle Island's Environmental Restoration
    The project had two main goals: to alleviate traffic on an overburdened, elevated highway that had begun deteriorating, and to extend I-90 from south of ...
  88. [88]
    Project Profile: The Rose Kennedy Greenway, Freeway Cap Park ...
    The greenway attracts millions of visitors who want to gather, play, unwind, and explore in its landscaped gardens, promenades, plazas, fountains, art, and ...
  89. [89]
  90. [90]
    [PDF] A Review of the Central Artery/Tunnel Project Cost Recovery Program
    Dec 19, 2000 · This report identifies systemic vulnerabilities to waste and abuse, points out opportunities for increased cost control and accountability,.<|separator|>
  91. [91]
    Boston's lessons learned - PMI
    Boston's lessons learned. with a new wave of infrastructure projects underway, the U.S. city is determined to avoid the problems that cursed the "Big Dig".Missing: opposition | Show results with:opposition