Level of effort

Level of effort (LOE) in is a type of support activity that involves ongoing work necessary to sustain the project but does not produce identifiable deliverables or directly tie to measurable outputs, such as administrative tasks or stakeholder management. These activities are typically measured by the passage of time—often in hours or days—rather than by specific accomplishments, distinguishing LOE from discrete effort tasks that have clear end products. LOE plays a critical role in planning by ensuring accurate estimation of timelines, , and overall costs, as it accounts for the continuous effort required to keep the on track without inflating progress metrics. In (EVM), LOE tasks are budgeted and earned based on scheduled time rather than , with budgeted cost of work performed equaling budgeted cost of work scheduled at period ends to avoid misleading variance reports. Properly identifying and limiting LOE—ideally to no more than 20% of a account's when mixed with other efforts—helps prevent overestimation and supports realistic scoping. Common examples of LOE include updating project reports, such as tracking expenses in budget documents; managing stakeholder communications through emails, meetings, or surveys; and performing sustaining activities like equipment maintenance or program liaison duties. These differ from core project tasks, like developing a , which are discrete and output-focused. To calculate LOE, project managers first assess the required accuracy for estimates, then apply techniques such as prioritizing tasks by impact, categorizing them (e.g., low to high effort), or assigning numerical values on a scale like 1-10 to reach team consensus. Historical data, team input, and buffers for unforeseen issues are incorporated, with hours distributed across project phases rather than evenly, accounting for factors like holidays. Tools like project management software can aid in tracking and refining these estimates during the planning phase.

Definition and Fundamentals

Core Definition

In , level of effort (LOE) refers to a category of activities that involve ongoing support work essential for sustaining primary project tasks, but which do not typically yield a discrete end product, , or objectively measurable output. These activities, such as general administration or coordination, are integral to project execution yet lack independent progress indicators beyond the passage of time. LOE is particularly prominent in (EVM) systems, where it ensures that supportive functions are accounted for without distorting performance metrics for core work. LOE is distinguished from other effort types in project planning and measurement. Discrete effort pertains to tasks directly linked to specific deliverables, allowing for assessment based on completion criteria, while apportioned effort is derived proportionally from discrete tasks and scaled accordingly. In contrast, LOE aligns its value with the duration of the activities it supports, rather than tracking autonomous advancement, which prevents it from influencing critical path analysis or earned value calculations independently. This measurement approach emphasizes time-based budgeting to maintain oversight without implying productivity variances. The concept of LOE emerged within frameworks in the 1960s, initially developed by the U.S. Department of Defense to manage complex defense programs. It was later formalized through standards such as ANSI/EIA-748, adopted in 1998 and subsequently revised (most recently as EIA-748-D in 2013, with Revision E anticipated in 2025), which outlines guidelines for incorporating LOE into compliant EVM systems, particularly for government contracts requiring integrated cost and schedule control. As of 2025, the standard is undergoing Revision E, expected to provide updated guidelines for EVMS compliance, including LOE integration. This standardization helped minimize the use of LOE where possible, favoring more measurable effort types to enhance project predictability.

Key Characteristics

Level of effort (LOE) activities are characterized by their tight alignment with the durations and timelines of the primary work they support, functioning as "" activities in project scheduling that stretch or contract automatically to match the start and end dates of the driving tasks. This dependency is typically established through start-to-start () and finish-to-finish () logical relationships, ensuring that LOE durations derive directly from the progress of supported activities rather than milestones. As a result, LOE elements provide continuous, uniform support—such as administrative oversight or resource maintenance—without introducing fixed endpoints of their own, thereby mirroring the ebb and flow of the core work they enable. A defining behavioral trait of LOE activities is their inherent non-critical status within the , as they possess positive total float and cannot generate schedule variances or on the critical path. Unlike tasks, LOE adjusts dynamically to the pace of supported work, remaining neither ahead nor behind in isolation; instead, any perceived variance in LOE simply reflects shifts in the underlying activities it accompanies. This property ensures that LOE does not drive completion dates or add time to the overall timeline, positioning it as a flexible, supportive layer that enhances execution without imposing constraints. Progress tracking for LOE activities emphasizes work performance metrics, such as staff hours expended per reporting period, over traditional completion percentages, given the absence of identifiable, discrete outputs. Status updates are thus tied to the percent complete or advancement of the supported tasks, measuring LOE in terms of sustained effort rather than achievements. This approach avoids resource leveling or constraint applications specific to LOE, focusing instead on its role as an ongoing enabler of momentum. In relation to project phases, LOE activities exhibit a continuous or recurring nature, frequently spanning the entire lifecycle to deliver unbroken support across multiple stages without reliance on discrete phase boundaries. For instance, elements like or customer liaison may persist from initiation through closure, adapting to phase transitions via their linkage to the evolving primary work. This phased continuity underscores LOE's role in maintaining stability over extended periods, independent of interim deliverables.

Types and Classification

Support-Type Activities

Support-type activities within level of effort (LOE) encompass ongoing tasks that enable the execution of primary operational or technical project work by providing essential facilitation, without directly producing measurable deliverables. These efforts are crucial for maintaining the and of core activities, focusing on support that sustains project momentum. Distinct examples of support-type LOE include routine such as oiling machinery during active runs to prevent , regular data backups in IT projects to safeguard amid development cycles, and vendor coordination for continuous provisioning of supplies like raw materials or components. In these cases, the activities run parallel to the main , ensuring operational reliability without advancing the project's tangible outputs. Classification as support-type LOE requires tasks to be inherently ongoing with minimal variability in required effort, directly linked to the rhythm and duration of core project work rather than triggered by discrete events. Unlike one-off interventions, these efforts exhibit consistent demand, often spanning the lifespan of predecessor and successor activities to mirror the project's progress. The resource implications of support-type activities emphasize steady, predictable staffing needs, as they demand reliable personnel allocation to avoid disruptions in primary execution. This allocation supports smooth integration with technical teams, minimizing variability in project velocity.

Management and Sustaining Activities

Management and sustaining activities within level of effort (LOE) encompass administrative tasks that are essential for ensuring continuity and , without producing discrete deliverables or directly influencing the timeline. These include oversight functions such as tracking, reporting, and monitoring, which support the broader ecosystem by maintaining and coordination. Unique to sustaining efforts, these activities involve ongoing overhead, exemplified by monthly status meetings to align team progress, contract administration to manage relationships and amendments, and environmental checks in projects to adhere to regulatory standards throughout the lifecycle. Such tasks ensure long-term viability but operate at a consistent, uniform rate tied to the duration of supported work packages rather than specific milestones. Classification criteria for these activities emphasize their non-value-adding yet necessary role in , distinguishing them from or apportioned efforts by the absence of measurable outputs or direct ties to end products; they are typically scheduled as hammock activities with start-to-start and finish-to-finish relationships to mirror supported tasks. In large-scale projects, and sustaining LOE often represents 15-20% of total effort, serving as indirect overhead that requires regular progress tracking via percentage complete without impacting the critical path. These activities align with the Project Management Institute's (PMI) PMBOK Guide, particularly in treating them as within project time management and budgeting processes, ensuring they are incorporated into the overall schedule model for accurate . Similarly, the U.S. Department of Defense's System Interpretation Guide (DoD EVMSIG) mandates their inclusion in the performance measurement baseline, limited to supportive functions like and to avoid inflating earned value metrics improperly.

Estimation Methods

Calculation Approaches

The calculation of level of effort (LOE) typically begins with a fundamental approach that ties the effort directly to the duration of the supported activities, ensuring alignment with project timelines without influencing critical path durations. The basic formula for determining LOE in hours is given by: \text{LOE (hours)} = \text{(Duration of supported activity in periods)} \times \text{(Effort rate per period, e.g., staff hours per day)} This method spreads the estimated effort uniformly or according to historical profiles over the relevant time frame, accounting for factors like holidays and varying workweeks to avoid simplistic linear division of total hours. Qualitative estimation techniques form the foundation for setting effort rates, drawing on historical from similar projects or expert judgment to assess ongoing support needs. These approaches prioritize contextual understanding, such as team experience and activity uniformity, to derive realistic rates without detailed task breakdowns. Quantitative methods enhance precision through structured aggregation or modeling. Bottom-up techniques involve compiling effort estimates from analogous past projects, summing component rates to total LOE, while modeling applies statistical relationships from historical datasets, expressed as LOE = × project scale factor, where the scale factor adjusts for variables like project size or . These are particularly useful for repetitive support activities, ensuring scalability and data-driven validation. To refine estimates, adjustment factors are incorporated based on project-specific risks and complexities, often derived from risk registers or contingency analyses. For instance, in high-risk environments, an uplift may be added to the baseline LOE to buffer against unforeseen disruptions. Such adjustments prevent underestimation and align LOE with broader controls.

Measurement Units and Metrics

The primary units for measuring level of effort (LOE) in are staff-days, person-hours, and full-time equivalents (FTEs), with a common baseline of 8 hours per day for one FTE. These units quantify the supportive work over a defined period, such as or , without tying to discrete outputs. In (EVM), LOE performance is tracked using the budgeted cost of work scheduled (BCWS) as the key metric, representing cumulative effort planned over time rather than percentage complete, since LOE lacks measurable accomplishments. For LOE, the budgeted cost of work performed (BCWP) equals BCWS each reporting period, resulting in zero schedule variance and focusing analysis on cost variance alone. Reporting standards for LOE follow ANSI/EIA-748 guidelines, which require baselining LOE separately from discrete efforts to prevent performance inflation in EVM reporting. LOE is typically allocated within control accounts for overarching support like , ensuring clear segregation in control accounts and work packages. Metrics for LOE accommodate variability by prorating FTEs for part-time resources—for instance, a resource working 20 hours per week equals 0.5 FTE based on a 40-hour standard—and excluding non-project time such as holidays, vacations, or training to reflect only dedicated effort. This adjustment maintains accurate time-phased budgets aligned with resource availability.

Applications in Project Management

Integration with Scheduling Techniques

In the Critical Path Method (CPM), Level of Effort (LOE) activities are typically modeled as hammock activities, which span the duration of supporting discrete tasks without driving the overall project timeline. These activities are linked using start-to-start (SS) constraints to the predecessor task's initiation and finish-to-finish (FF) constraints to the successor task's completion, ensuring the LOE duration automatically equals the successor's finish date minus the predecessor's start date. This setup maintains logical ties to the driving path while preventing LOE from influencing or , as LOE lacks discrete deliverables and measurable outputs. LOE activities are incorporated into the performance measurement baseline (PMB) within (EVM) frameworks, where they contribute to the total time-phased budgeted cost for supportive work such as or oversight. As part of the PMB, LOE budgets are allocated separately in accounts to reflect expected resource consumption over the supported period, but they do not generate schedule variances or affect critical path floats due to their non-discrete nature. This inclusion ensures comprehensive cost planning without distorting performance metrics for productive efforts. Project management software facilitates LOE modeling by treating these as resource-loaded activities with fixed effort rates tied to the underlying schedule logic. In tools like , LOE can be implemented by linking task dates via paste special operations or custom flags to simulate behavior, assigning uniform effort across the spanned duration without altering the critical path. Similarly, P6 supports LOE through dedicated activity types that use and relationships for automatic duration adjustment, enabling resource loading at consistent rates for supportive tasks. According to Department of Defense (DoD) EVM guidelines, LOE progress is measured proportionally to the time elapsed within the supported activity's period, with earned value equaling the planned value for each reporting interval to avoid artificial variances. This time-based assumption simplifies tracking for non-measurable support but requires controls in mixed control accounts to isolate LOE from discrete work and prevent performance distortion.

Use in Different Methodologies

In traditional methodologies such as , level of effort (LOE) activities are typically represented as fixed overhead tasks within Gantt charts, spanning the duration of project phases without discrete deliverables. These include ongoing support functions like project monitoring and control, where effort is allocated consistently over time rather than tied to specific outputs, aligning with the predictive nature of sequential processes outlined in the PMBOK Guide. According to the PMBOK Guide, such LOE tasks, such as vendor liaison or administrative support, are measured by the passage of time and integrated into baseline schedules to account for sustaining activities across the project lifecycle. In Agile and Scrum frameworks, LOE for support tasks is typically managed by reserving a portion of the team's sprint capacity (e.g., 10-20%) for non-development activities such as sprint retrospectives, backlog refinement, and other overhead, rather than estimating them with story points. This ensures focus on delivering value while accounting for sustaining efforts, aligning with Scrum guidelines. Earned Value Management (EVM) treats LOE as level-loaded resources in the budget, where progress is earned strictly based on elapsed time rather than achievement of milestones, preventing artificial inflation of performance metrics. In EVM systems, LOE tasks—such as general management or quality assurance oversight—are planned with consistent resource allocation, and earned value equals planned value each reporting period, resulting in zero schedule variance by design. This time-based earning rule, detailed in EVM guidelines, ensures that LOE does not contribute to cost or schedule performance indices beyond sustaining the project's baseline, making it suitable for integration with traditional or hybrid schedules. Hybrid applications, such as those in environments, blend LOE estimation with throughput metrics to manage ongoing maintenance of / () pipelines, combining predictive budgeting with adaptive . Here, LOE for tasks like pipeline upkeep or automated testing is forecasted using historical throughput rates—such as deployments per week—to allocate resources predictively while adjusting based on flow efficiency. This integration, informed by DevOps Research and Assessment () metrics, allows teams to balance fixed effort assumptions with empirical data from tools like boards, enhancing reliability in environments that merge planning with Agile execution.

Practical Examples and Challenges

Real-World Illustrations

In , level of effort is often estimated for ongoing tasks that do not directly advance deliverables but ensure system stability. For instance, in a hypothetical six-month , database maintenance might require 4 hours per week, resulting in a total LOE of 4 hours/week × 26 weeks = 104 hours (adjusted for a standard project calendar). This calculation highlights how LOE captures recurring administrative work without discrete milestones. NASA frequently employs LOE for oversight in major acquisition projects, where it represents a substantial portion of the overall to manage , , and across complex missions. According to analyses of NASA programs, such LOE activities typically comprise 15-20% of the total , underscoring their role in preventing cost overruns by addressing underestimated engineering demands. In projects, LOE is applied to continuous functions like site security, which persist throughout the build without varying outputs. For a hypothetical 12-month project, ongoing site security could be estimated at 1 (FTE) position, equating to 2,080 staff-hours (based on 40 hours/week × 52 weeks). This LOE estimation aids in budgeting for non-discretionary safety measures that run parallel to core building activities. In IT services, helpdesk during migrations exemplifies LOE for user assistance and issue resolution, forming a predictable overhead amid transitions. Forrester case studies on such migrations highlight the of helpdesk efforts in maintaining operations while deploying new infrastructure.

Advantages and Limitations

Level of effort (LOE) estimation simplifies budgeting for ongoing support tasks by providing a consistent for allocating resources to activities like and , which do not fluctuate significantly with project milestones. In (EVM) systems, LOE allows value to be earned at a predetermined rate over time, enhancing visibility into cost variances and supporting more reliable forecasts for total project costs. This approach also promotes resource stability by evenly distributing workload across the project duration, reducing the risk of overburdening teams during peak discrete task periods. Despite these benefits, LOE can mask inefficiencies when over-allocated, as it earns value based solely on time elapsed rather than output, potentially inflating budgets without corresponding value addition and distorting overall project performance metrics in EVM. Adjusting LOE mid-project proves challenging due to its dependency on fixed durations tied to the project timeline, often requiring revisions that complicate processes. In volatile environments, such as startups, LOE risks underestimation by assuming steady effort levels that may not account for rapid scope changes or emerging requirements. To mitigate these limitations, project managers can implement regular reviews, such as during agile sprints or EVM audits, to monitor LOE allocation and ensure it remains limited—ideally to less than 10% of the total —to avoid skewing measurements. Integrating agile practices with EVM further supports dynamic adjustments by aligning LOE tracking with iterative planning cycles. Comparatively, LOE performs well in stable projects with predictable support needs but underperforms relative to discrete effort estimation in innovative R&D settings, where high uncertainty and evolving scopes demand more flexible, milestone-based approaches to capture true progress.

References

  1. [1]
    What Is Level of Effort (LOE)? Plus, 5 Tips for Effort Estimation
    Jul 21, 2021 · Level of effort (LOE) is a project management term that refers to a specific type of project activity called support activities.
  2. [2]
    What is the Level of Effort (LOE)? - KnowledgeHut
    Jul 4, 2023 · Level of effort refers to the amount of time, resources, and effort required to complete a task or activity. To learn more about tips, ...<|control11|><|separator|>
  3. [3]
    Level of Effort (LOE) - Humphreys & Associates
    Level of effort (LOE) tasks consist of management or sustaining type activities that have no identifiable end products or an established relationship to.
  4. [4]
    EVM Definitions - OUSD A&S
    Level of Effort (LOE): Work defined as supportive in nature that lacks measurable output or as a product that cannot be discretely planned and objectively ...
  5. [5]
    PP&C Glossary - NASA
    Feb 18, 2025 · Level of Effort (LOE) – Work that does not result in a final deliverable (i.e., liaison, coordination, management, or other support ...
  6. [6]
    [PDF] Earned Value Management Tutorial Module 5: EVMS Concepts and ...
    The Level of Effort (LOE) method is based on the passage of time. A monthly budget value is earned with the passage of time and is always equal to the monthly.
  7. [7]
    [PDF] GAO-12-120G, GAO Schedule Assessment Guide
    May 30, 2012 · be associated with a physical product or defined deliverable. These level of effort (LOE) activities are typically related to management and ...
  8. [8]
    [PDF] Earned Value Management Best Practices Report - CMS
    LEVEL OF EFFORT (LOE) – A method (the use of which should be minimized) of measuring EARNED VALUE for activities of a general or supportive nature that do not ...
  9. [9]
    Earned Value Consulting - Humphreys & Associates
    Earned Value Management emerged as a financial analysis specialty in United States Government programs in the 1960s, with the government specifying rules for ...
  10. [10]
    [PDF] NDIA IPMD EIA-748 EVMS Intent Guide
    Aug 28, 2018 · January. 2015. C. Changed all instances of ANSI/EIA-748 to EIA-748 and updated the ... Level of effort work packages contain tasks of a general or ...
  11. [11]
    ANSI standard on EVMS - PMI
    The ANSI standard gives a full definition of each of the earned value techniques and how items such as level of effort and apportioned effort should be handled.
  12. [12]
    None
    Below is a merged summary of the Level of Effort (LOE) from the *Practice Standard for Scheduling* (PMI, 2nd Edition and 2011 editions), consolidating all information from the provided segments into a single, comprehensive response. To maximize detail and clarity, I’ve organized the information into a table format, followed by a narrative summary that integrates key points not easily captured in the table. The table is presented in CSV-style text for density and structure, which can be easily imported or read.
  13. [13]
    A Guide to Level of Effort (LOE) - Ten Six Consulting
    Here are some tasks that would be classified as LOE activities: Project management; Program management; Portfolio management; Departmental liaison e.g. being ...
  14. [14]
    9 Examples of Level Of Effort - Simplicable Guide
    Jan 28, 2018 · Level of effort is a project management term for ongoing work that ... Maintenance. Maintenance such as a software developer who spends ...
  15. [15]
    What is a Level of Effort Activity in Primavera P6? FAQs
    What are Level of Effort Activities for? · Customer Meetings · Project Management tasks · Maintenance of equipment · Clerical work.
  16. [16]
    What is LOE? How Used in Project Management? - Complete Guide ...
    Vendor coordination: 4 hours per week × 17 weeks = 68 hours ... In project management, estimating the level of effort ... project success and failure. As a ...
  17. [17]
    Level of effort activity - Oracle Help Center
    Oct 9, 2025 · Use level of effort activities for on-going tasks that depend on other activities. For example, you could assign level of effort activities for ...
  18. [18]
    Project Management: How Much Is Enough? - Appropriate Amount
    The project manager's charges will typically amount to about 10 percent of the engineering budget, or about 1.5 percent of the TIC. John P. Byrne, PMP, has ...
  19. [19]
    [PDF] DoD EVMSIG
    Level of Effort (LOE) is defined as being of a general or supportive nature, with no measurable output, product, or activities; for which the attempt to ...
  20. [20]
    [PDF] Project Planning with Level-of-Effort Tasks
    These are efforts like: • Test Facility Operation. • Laboratory/Equipment Operations and Maintenance. • Project Management. • Technical Management. • Support ...
  21. [21]
  22. [22]
    Five keys to estimating - PMI
    First, the terms in the equation are defined as: LOEe means Level-of-Effort Estimate and is defined as the work required to finish a specified project ...
  23. [23]
    Parametric Estimating in Project Management - ProjectManager
    Sep 8, 2022 · Parametric estimating is a project estimation technique to estimate cost, duration and effort on a project. It uses a set of algorithms, statistics or models ...
  24. [24]
    Project Estimation - Go Parametric to Reduce "Hectic" - PMI
    Oct 22, 2012 · This paper discusses the approach taken by Deloitte to take the estimation model beyond just generating the initial estimate to also providing outputs.
  25. [25]
    10 guidelines for estimating project effort - Susanne Madsen's
    9. Add a contingency factor to your estimate to cater for events which you cannot foresee, such as unexpected problems with the proposed solution or vendor or ...
  26. [26]
    Effort tracking - Control Team Effort and Project Progress - PMI
    Effort tracking is primarily a management tool for schedule control. Specifically, it is the process of measuring the hours expended on both planned and ...
  27. [27]
    [PDF] Level of Effort Planning and Execution on Earned Value Projects
    Aug 13, 2020 · This document provides further explanation of the intent and application of LOE that is not contained in the EIA-748 standard and the. National ...
  28. [28]
    [PDF] Earned Value Management (EVM) System Description
    Nov 1, 2019 · 1 Incorporate IPMR, ANSI/EIA-748 reference change ... ◦ CAs that have Level of Effort (LOE) WPs and discrete effort WPs normally do not.
  29. [29]
    None
    Summary of each segment:
  30. [30]
  31. [31]
    [PDF] Level of Effort (LOE) Support Tasks | Barbecana
    there are specialized task/activity types to model supporting work, sometimes known as 'Level or Effort' or 'Hammock' tasks/activities. Unfortunately, Microsoft ...<|control11|><|separator|>
  32. [32]
    [PDF] Earned Value Management Best Practices Report - CMS
    Level of Effort. Trivial to implement and is appropriate for sustaining tasks such as Program. Management. Offers no benefit over simple planned vs. actual ...
  33. [33]
    Calculating Level of Effort: How Do We Approach It?
    May 28, 2013 · LOE, in project management terms, means the Level of Effort to perform the identified tasks in a project.
  34. [34]
    What are story points in Agile and how do you estimate them?
    Story points are units of measure for expressing an estimate of the overall effort required to fully implement a product backlog item or any other piece of ...
  35. [35]
    Earned Value Management - Beneficial Methods -Achieve Benefits
    Earned Value or Budgeted Cost of Work Performed (EV or BCWP) for Level of Effort work by definition is equal to the Scheduled or Planned Value Budgeted Cost of ...
  36. [36]
    A Discussion on the Level of Effort (LOE) Earned Value Method
    The LOE earned value method sets budgeted cost for work performed (BCWP) equal to budgeted cost for work scheduled (BCWS) each period, acknowledging time ...
  37. [37]
    4 Key DevOps Metrics to Know | Atlassian
    The four key DevOps metrics are: lead time for changes, change failure rate, deployment frequency, and mean time to recovery.
  38. [38]
    Measure CI/CD Performance With DevOps Metrics - JetBrains
    Measuring and monitoring your CI/CD performance is crucial to the efficiency of CI/CD pipelines. Learn about crucial performance metrics today.
  39. [39]
    [PDF] Technical Report Value of Systems Engineering - DSpace@MIT
    Sep 15, 2004 · ... systems engineering budget ... Survey results were likely influenced by different perceptions of systems engineering in the NASA and INCOSE groups ...
  40. [40]
    The Total Economic Impact™ Of A Migration To Microsoft Dynamics ...
    The cost to extend the life of these on-premises solutions and grow with the business also swelled as infrastructure costs, support costs, and partner fees ...Missing: breakdown helpdesk
  41. [41]
    How to make earned value work on your project - PMI
    used when it's very difficult to measure what work was accomplished for the budget spent. My preferred approach with LOE assumes the ...
  42. [42]
    [PDF] AGILE AND EARNED VALUE MANAGEMENT - OUSD A&S
    Nov 17, 2020 · Example Agile and EVM Scenario. This appendix describes a simple Agile and EVM scenario showing one method of how Agile can underpin. EVM ...
  43. [43]
    3 Ways to Successfully Manage Large-Scale R&D Projects
    especially those centered on research and development — extend over time.