Project charter

A project charter is a formal document issued by the project initiator or sponsor that authorizes the existence of a project and grants the project manager the authority to apply organizational resources to project activities. In project management, the project charter serves as the foundational artifact during the initiation phase, aligning stakeholders on the project's purpose and ensuring it supports broader organizational goals. It acts as a reference point throughout the project lifecycle, helping to manage scope creep, facilitate communication, and provide a basis for decision-making by documenting high-level requirements and expectations. According to the Project Management Institute (PMI), the charter empowers the project manager to lead the team and secure necessary support, thereby increasing the likelihood of project success. Key components of a project charter typically include the project's purpose or , measurable objectives and success criteria, high-level description, identified stakeholders and their roles, summary schedule, overview, key assumptions and constraints, high-level risks, and approval signatures from the sponsor. These elements ensure clarity and buy-in from the outset, distinguishing the charter from more detailed planning documents like the project management plan. While the charter is concise—often one to a few pages—it must be created before detailed planning begins to establish authority and prevent misalignment.

Overview

Definition

A project charter is a document issued by the project initiator or that formally authorizes the existence of a and provides the with the authority to apply organizational resources to project activities. This high-level document outlines the project's initial requirements, objectives, and key stakeholders, serving as the foundational authorization without delving into detailed execution plans. In the lifecycle, the project charter represents the key output of the phase. In process-oriented frameworks such as the PMBOK Guide editions prior to the seventh and the eighth edition (2025), it specifically aligns with the "Develop Project Charter" process, acting as the first formal project document to align the effort with organizational strategy. It establishes the project's legitimacy and empowers the from the outset, distinguishing it from subsequent planning artifacts. The project charter differs from similar documents like the project initiation document () in methodology, which is more comprehensive and includes detailed project controls, approaches, and quality criteria, whereas the charter remains concise and focused on authorization. Similarly, it contrasts with (), which typically provide broader, detailed definitions for initiatives such as committees or programs, rather than the charter's specific emphasis on project start-up and .

Historical Context

The concept of the project charter emerged in the mid-20th century as part of the formalization of practices, driven by the need to manage complex, large-scale initiatives in the and during the 1950s and 1960s. The U.S. Navy's submarine-launched ballistic missile program in the late 1950s introduced methodologies like the (PERT), while 's in the 1960s applied similar tools to coordinate massive efforts involving thousands of contractors and strict timelines. These programs highlighted the necessity for a formal document to authorize projects, allocate resources, and define authority, laying the groundwork for what would become the project charter. In the 1980s, project management gained further structure through emerging standards, with influences from quality management pioneers and underscoring the value of documented authority and systematic processes to ensure accountability and success. The (PMI) published the inaugural PMBOK Guide in 1987 as a foundational document outlining project initiation artifacts, which evolved into the explicit "project charter" in subsequent editions starting with the 1996 full guide and formalized in the 2000 second edition. The PMBOK Guide's sixth edition (2017) refined the "Develop Project Charter" process within the Project Integration Management knowledge area, incorporating inputs like business documents and enterprise environmental factors to better align with and agile approaches while maintaining its core role in formal authorization. The seventh edition (2021) marked a significant shift toward a principles-based with eight domains, repositioning the project charter as a key strategy artifact focused on value delivery and outcomes rather than prescriptive steps. The eighth edition (2025), released on November 13, 2025, builds on this by reintroducing approximately 40 processes—including "Develop Project Charter"—in a non-prescriptive, blended approach that integrates principles and domains (now seven), with expanded coverage of emerging trends like and offices to enhance adaptability and value alignment. Internationally, the project charter gained recognition through :2012, which included "Develop project charter" as a core process in the integration and initiating process groups to formally authorize and link them to organizational objectives. The standard's 2021 revision (:2021) retained this element, updating it alongside ISO 21502 to emphasize context, concepts, and processes for , , and in diverse organizational settings.

Key Components

Core Elements

The core elements of a project charter form its foundational structure, ensuring it serves as a clear document that aligns the project with organizational goals while defining essential boundaries. These mandatory components, as outlined in standard practices, provide a high-level overview without delving into detailed . The purpose and justification articulate the fundamental reason for undertaking the , including a summary of the that explains expected benefits, alignment with strategic objectives, and high-level goals. This section typically summarizes how the addresses organizational needs, such as improving or entering new markets, supported by a concise rationale derived from business documents. High-level objectives are measurable and specific, serving as criteria to evaluate outcomes, such as achieving a 20% or launching a product by a target date. Key deliverables outline the major outputs expected from the , while scope boundaries define what is included and excluded to prevent . Success criteria, often tied to objectives, specify conditions for completion, such as meeting standards or satisfaction thresholds. High-level requirements may also be noted here to highlight critical functional or technical needs without exhaustive detail. Identified stakeholders include a list of key individuals or groups, such as the project sponsor, manager, and primary affected parties, along with their roles. High-level risks identify potential threats or opportunities at a broad level, assumptions detail preconditions taken as true (e.g., resource availability), and constraints specify limitations like budget caps or timelines. These elements ensure early awareness of external factors influencing the project. The assigned project manager's authority is formally granted, empowering them to allocate resources and make decisions within the defined . A resources summary provides an overview of allocated , personnel, and assets, often including a high-level schedule and preapproved financials. Approval signatures from the or authorizing body, such as a , validate the and signify commitment. This authorization establishes the project manager's role in leading execution. Typically spanning 1 to 5 pages, the project charter adopts a concise, formal document format, such as a or standalone , to facilitate quick and endorsement without overwhelming detail.

Optional Additions

In project charters, optional additions provide flexibility to address specific project complexities or organizational contexts, building upon the foundational core elements to offer greater clarity and control without mandating their inclusion in every case. These enhancements can include preliminary planning details that help anticipate challenges early, particularly in larger or more regulated initiatives. High-level schedule milestones offer a preliminary timeline overview, such as key phases or deliverables, to set expectations for project duration and progress checkpoints. Similarly, budget estimates provide rough financial projections, encompassing costs for labor, materials, and contingencies, while resource requirements outline anticipated personnel, , or tools needed across phases. These are particularly useful for securing initial approvals and aligning expectations, as seen in construction projects where a $15 million estimate and phased milestones (e.g., site preparation completion in three months) guide . An outline of the communication plan can specify preferred methods, frequency, and escalation paths for updates, ensuring efficient . The governance structure may detail hierarchies, approval processes for changes, and roles of oversight bodies, such as a steering committee reviewing milestones. For instance, in governance-focused charters, the project sponsor monitors progress against defined KPIs, facilitating accountability in distributed teams. Notes on alignment with organizational emphasize how the supports broader goals, such as revenue growth or , while sections highlight adherence to standards like data privacy laws (e.g., GDPR). This ensures the fits within enterprise priorities and mitigates legal risks from the outset. Tailoring optional additions varies by project scale; for small projects, a simplified might omit detailed budgets in favor of basic milestones to expedite initiation, whereas large-scale efforts benefit from expanded sections like a to evaluate internal strengths (e.g., skilled team) against external threats (e.g., market volatility). This approach, recommended by , allows methodologies to fit project size, with abbreviated charters for minor initiatives focusing only on essential alignments. In post-2020 remote work environments, considerations for digital versus traditional formats have gained prominence, with charters increasingly created using collaborative tools like or for real-time editing and version control, contrasting paper-based or static documents that hinder distributed access. Digital formats enable embedded links to shared resources and automated approvals, enhancing accessibility for global teams amid hybrid work trends.

Purpose and Benefits

Establishing Authority

The project charter serves as the primary mechanism through which the project sponsor or initiator formally approves and authorizes the project, thereby empowering the with explicit decision-making authority over key aspects such as , , and . This approval process typically involves the sponsor reviewing and signing the charter, which designates the and outlines their rights to allocate organizational resources without needing further external permissions for routine project activities. By establishing this authority at the project's inception, the charter prevents by creating a clear boundary for changes, requiring any deviations to follow formal approval procedures. Within organizations, the project charter carries significant implications as a formal internal that binds stakeholders to the defined project parameters, though it is generally not a legally enforceable like a agreement. In some contexts, particularly in structured corporate environments, it functions similarly to an internal , providing a documented from the that can influence and accountability, but it lacks the legal weight of external binding agreements unless explicitly incorporated into contractual terms. The charter plays a crucial role in resolving conflicts by establishing a documented of objectives, assumptions, and constraints that all parties can reference to mediate disputes over , priorities, or use. This acts as an impartial record, enabling objective discussions and reducing ambiguity during execution, thereby facilitating quicker resolutions without escalating to higher organizational levels. Historically, the (PMBOK) has emphasized the project charter as the essential "authorization" tool since its early editions, defining it consistently as a document that formally initiates the project and grants managerial authority—a role that remains unchanged in the 7th edition, which retains the core concept amid its shift toward principle-based guidance.

Strategic Alignment and Stakeholder Engagement

The project charter serves as a foundational document that explicitly links objectives to the broader organizational , ensuring that the initiative supports key priorities such as , , or . By outlining how the project contributes to these goals, the charter typically includes a high-level that identifies measurable benefits, including (ROI), key performance indicators (KPIs) like cost savings or , and alignment with strategic objectives defined in the organization's or . This integration helps prevent to misaligned efforts and promotes a unified direction from the outset. A critical aspect of the project charter is the early identification and mapping of , which involves listing individuals or groups affected by or influencing the , such as sponsors, team members, customers, and external partners, along with their defined roles, responsibilities, and expectations. This mapping often employs tools like stakeholder registers or influence grids to assess power, interest, and potential impact, fostering proactive engagement strategies tailored to each group's needs. By documenting these elements, the charter creates a shared reference point that clarifies communication channels and , reducing ambiguities that could derail progress. The facilitates buy-in by articulating a shared of the project's and outcomes, which encourages and minimizes through transparent discussions of benefits and trade-offs. This collaborative approach builds and , as stakeholders contribute input during charter development, aligning their interests with project goals and creating a sense of that sustains throughout the project lifecycle. Furthermore, by addressing concerns and expectations upfront in the , the document aids in , enabling the identification of potential issues like changes or conflicts before they escalate. Studies indicate that strong strategic , reinforced by such early engagement, significantly enhances project outcomes.

Development Process

Steps to Create

The process of creating a project charter is a foundational step in project initiation, ensuring formal authorization and clear direction from the outset. It typically involves collaboration among the project sponsor, key stakeholders, and the to align the document with organizational objectives. According to the PMBOK Guide (7th Edition), project initiation activities, including charter development, are tailored to the project's context and emphasize principles such as , team collaboration, and to produce a document that empowers the to utilize resources effectively. Initiation begins with gathering essential inputs from the project sponsor, key stakeholders, and supporting documentation such as the , which outlines the 's justification, expected benefits, and alignment with strategic goals. This phase also incorporates enterprise environmental factors (like and market conditions) and organizational process assets (including policies, templates, and historical data). Data gathering techniques, such as interviews, brainstorming sessions, and focus groups with stakeholders, help identify high-level requirements, risks, and assumptions early on. Expert judgment from subject matter experts further refines these inputs to ensure the reflects realistic project needs and supports value delivery across performance domains like and stakeholders. Drafting the charter follows, where the assembles the core elements—such as project purpose, objectives, high-level , milestones, summary, and assigned authority—primarily using input from the . The is involved early in this stage to provide insights on feasibility and resource requirements, often facilitated through meetings and interpersonal skills like facilitation to resolve any initial conflicts. This step results in a concise , typically 1-3 pages, that serves as the project's guiding baseline without delving into detailed planning. The draft then undergoes review and iteration, circulated among the sponsor and key stakeholders for feedback to refine assumptions, identify additional risks, and confirm alignment with business needs. This collaborative refinement may involve multiple rounds of revisions, leveraging tools like conflict management and meeting facilitation to address discrepancies and ensure buy-in. The process emphasizes iterative improvements to avoid downstream issues, drawing on stakeholder input to validate the charter's completeness. Approval is obtained through formal sign-off from the sponsor and relevant key stakeholders, authorizing the project's existence and granting the project manager the authority to proceed. This step typically occurs within several weeks of initiation, depending on project complexity and organizational processes. Once approved, the charter becomes the official baseline document. Post-approval, the charter is distributed to all members and stakeholders to communicate expectations and levels, while being archived in organizational repositories for and auditing purposes. This ensures the remains accessible as a throughout the project lifecycle, supporting governance and .

Tools and Templates

The () offers resources and templates for project charters aligned with the PMBOK Guide, including examples in their educational materials and free downloads for members, covering sections for project objectives, scope, stakeholders, and high-level risks to ensure consistency in documentation. Software tools facilitate the creation of digital project charters by integrating structured templates with collaboration features, such as real-time editing and notifications. For instance, provides customizable forms for charter elements that sync with task boards for team input. Similarly, supports charter development through issue templates and plugins that incorporate agile workflows, enabling attachment of epics and user stories directly within the document. tools like Word and Copilot can be used to draft charters, with integration to for subsequent planning. Customization of project charter templates varies by industry to address specific regulatory or operational needs; in projects, templates often emphasize technical specifications, risks, and metrics, whereas construction charters prioritize site , safety protocols, and material checklists. Free resources include open-source templates hosted on repositories, such as those in curated collections that offer editable or Excel files for basic charters, and downloadable formats from , which provide versatile options like one-page summaries or detailed variants without cost. As of 2025, advancements incorporate AI-assisted drafting, with for generating initial charter sections based on user prompts, suggesting content for objectives and risks while integrating with tools for automated refinements.

Applications

In Traditional Project Management

In traditional project management methodologies, such as and predictive approaches, the project charter serves as a foundational document that emphasizes comprehensive upfront to define project boundaries and objectives before execution begins. It is particularly integral to the (PMBOK) Guide, where it is the primary output of the Develop Project Charter process within the Initiating . This process involves creating a document that formally authorizes the project's existence, grants the authority to allocate organizational resources, and establishes high-level requirements to meet expectations. The charter then feeds directly into the Planning , providing the basis for detailed , , and development by linking initial business needs to subsequent planning activities. In large-scale projects within industries like and , the project charter ensures early and detailed definition to mitigate risks associated with complex, sequential workflows. For projects, it outlines key elements such as objectives, deliverables, stakeholders, and constraints, enabling teams to align on feasibility and resource needs from the outset, which is critical for linear phases like , , and building. Similarly, in , charters support predictive planning by specifying production goals, quality standards, and timelines, helping to prevent in environments requiring precise material and process controls. The project charter also aligns closely with the methodology, as outlined in its 7th edition (), where it parallels the "Project Mandate"—an initial high-level document provided by the sponsoring organization to trigger project initiation. In , the Mandate outlines objectives, scope, and constraints to justify starting up the project, much like the charter's role in authorizing and directing traditional efforts, though emphasizes controlled stages over rigid processes. This equivalence allows practitioners to adapt charter-like elements for predictive planning while maintaining focus on business justification throughout.

In Agile and Hybrid Methodologies

In Agile methodologies, the project charter adapts into a lightweight, flexible artifact that emphasizes value delivery and iterative refinement over rigid upfront planning. In , for instance, the Product Goal functions as a core directional element, describing a of the product that guides the Scrum Team's efforts and ensures alignment with organizational objectives. This serves as a high-level commitment similar to a traditional charter but remains emergent, evolving through Sprint Reviews to accommodate changing priorities without detailed scope definitions. The focus shifts to the "why" and "what value," as outlined in the official Scrum Guide, promoting adaptability in dynamic environments like where requirements frequently evolve. In hybrid methodologies, such as the (SAFe) 6.0, project charters integrate with strategic roadmaps to support enterprise-scale initiatives that blend predictive and iterative elements. SAFe employs a Vision Statement and Program Increment (PI) Roadmaps to initiate projects, providing a high-level overview of objectives, key milestones, and value streams while allowing for agile adjustments across Agile Release Trains (ARTs). This hybrid approach combines charter-like authorization for large initiatives with ongoing refinement during PI Planning events, ensuring alignment in complex, multi-team settings. For example, in software or product development projects, these elements enable teams to balance fixed strategic goals with sprint-based flexibility, reducing risks in volatile markets. The benefits of such adapted charters are particularly evident in volatile environments, where they foster rapid pivots and sustained without the overhead of exhaustive documentation. In , for instance, evolving charters tied to sprints help maintain focus on delivering incremental value, mitigating while supporting and feedback loops. This iterative evolution enhances responsiveness, as teams can update the charter based on real-time insights from retrospectives and reviews. Post-2021 trends reflect increased emphasis on charters within agile and hybrid practices, particularly for DevOps integrations, as highlighted in PMI's resources on hybrid project management. The Agile Practice Guide underscores tailoring charters for agile contexts, advocating lightweight versions that align with DevOps principles like continuous delivery and automation. In updated PMI frameworks, such as those incorporating PMBOK Guide 7th Edition influences, charters now routinely support hybrid models by linking initial authorization to ongoing value streams in DevOps pipelines, enabling seamless transitions from planning to deployment in fast-paced industries.

Challenges and Best Practices

Common Pitfalls

One common pitfall in developing project charters is the inclusion of vague objectives, which often results in scope ambiguity and misaligned team efforts. For instance, stating a like "improve " without specifying measurable metrics, such as a targeted in process time by 20%, can lead to confusion over project boundaries and expectations, ultimately contributing to . According to research, 37% of projects fail due to a lack of clearly defined objectives and milestones, underscoring how ambiguity in the charter's statements hampers overall success. Another frequent error involves incomplete stakeholder identification, where key individuals or groups with influence over the are overlooked, leading to unanticipated resistance or lack of support during execution. This omission can manifest as unaddressed concerns from end-users or external partners, causing delays or rework that could have been anticipated through thorough mapping in the . Incomplete identification often stems from rushed during the chartering , where assumptions about involvement prove incorrect, resulting in overlooked impacts on outcomes. Project charters can also suffer from being overly detailed, bloating the document with granular specifications that exceed its primary role of authorization and high-level direction. Instead of focusing on essential elements like objectives and scope, excessive inclusion of tactical details—such as minute resource allocations or step-by-step plans—transforms the charter into a pseudo-project plan, complicating approval and reducing its effectiveness as a concise authorizing tool. This overreach dilutes the charter's strategic focus and burdens stakeholders with unnecessary information, often leading to delays in sign-off. A critical issue arises from insufficient sponsor commitment, where the executive signatory fails to actively endorse or resource the , resulting in mid-project changes, resource shortfalls, or deprioritization. Without visible involvement from the outset, teams encounter shifting priorities or inadequate escalation paths, exacerbating risks during . According to a 2018 PMI report, an average of 38% of projects lack active executive sponsorship, which undermines the 's authority and contributes to project failures. In remote and hybrid work environments, a notable pitfall is the failure to keep project documentation, including charters, updated in collaborative digital tools, leading to miscommunications in distributed teams. For example, relying on unrefreshed contacts or assumptions can result in alignment gaps amid evolving collaboration needs.

Mitigation Strategies

To mitigate issues arising from unclear or overly detailed project objectives, project managers should apply the —ensuring goals are Specific, Measurable, Achievable, Relevant, and Time-bound—when defining objectives in the project charter. This approach provides clarity and alignment, reducing the risk of misinterpretation by making objectives precise and actionable from the outset. Engaging stakeholders through facilitated workshops during the drafting phase ensures comprehensive input and fosters buy-in, helping to capture diverse perspectives early and avoid oversights in scope or expectations. These sessions, led by the , promote collaborative discussion and consensus on key elements like boundaries and success measures. Project charters should remain focused on high-level , such as , high-level , and , while deferring operational details—like schedules, budgets, and risk responses—to the subsequent plan. This distinction prevents the charter from becoming unwieldy and maintains its role as a concise document, as outlined in the PMBOK Guide. In agile and hybrid environments, implementing regular reviews and for the project is essential to adapt to evolving needs; this includes incorporating loops at boundaries to refine the document iteratively. These mechanisms enhance adaptability by treating the charter as a living guide rather than a static artifact, aligning with PMI's emphasis on in distributed teams as of the 2025 Pulse of the Profession report. Project managers benefit from targeted on charter facilitation to build skills in leading workshops, aligning stakeholders, and applying frameworks like effectively. PMI-recommended programs, such as those focused on processes, equip professionals with techniques to create robust that support project success.

References

  1. [1]
    [PDF] PMI Lexicon of Project Management Terms - Colorado College
    See also program charter and project charter. portfolio management. The centralized management of one or more portfolios to achieve strategic objectives ...<|control11|><|separator|>
  2. [2]
    The Charter - Selling your Project - PMI
    The PMBOK® Guide, 3dEdition defines a project charter as “a document issued by the project initiator or sponsor that formally authorizes the existence of a ...
  3. [3]
    The Power of a Project Charter: Purpose, Creation, and Best Practice
    A project charter is a document that formally authorizes a project, outlining its purpose, objectives, scope, and high-level requirements.
  4. [4]
    How to Write a Project Charter: Examples & Template Included
    Sep 24, 2024 · A project charter is a project planning document that sells the project to stakeholders and sponsors. If you're able to show its viability and return on ...Missing: 7th edition
  5. [5]
  6. [6]
  7. [7]
    Project Brief (PRINCE2) vs Project Charter (PMBOK)
    Sep 1, 2014 · The project charter is the document issued by the project initiator or sponsor that formally authorizes the existence of a project.
  8. [8]
  9. [9]
    Project management research trends of allied disciplines - PMI
    During the 1960s and 1970s, the U.S. Department of Defense, NASA, and large engineering and construction companies used project management principles and tools ...
  10. [10]
    1.3. In-depth Look: History and Evolution of Project Management
    1958: The Apollo Project​​ NASA established the Apollo programme office in 1960 to monitor and schedule Apollo flights using PERT, acquire and contract with ...Missing: origins | Show results with:origins
  11. [11]
    Deming vs Juran vs Crosby: Pioneers of Project Management
    Jun 9, 2025 · Juran emphasized the importance of continuous improvement, while Crosby focused on the need for organizations to meet customer expectations.
  12. [12]
    What is PMBOK Guide? Project Management Body of Knowledge
    Aug 2, 2025 · In 1987, PMI published the first PMBOK whitepaper, and the first draft of PMBOK followed in 1994. The first edition of PMBOK was published in ...
  13. [13]
    A Short History of the PMBOK Guide Published by PMI
    Jun 7, 2017 · The first ever PMBOK® Guide was published in 1996. Each subsequent edition was introduced to supersede the previous version as new best ...
  14. [14]
    6th Edition PMBOK® Guide–Process 4.1 Develop Project Charter ...
    Nov 5, 2017 · This post starts a series of posts on the first project management process, process 4.1 Develop Project Charter.
  15. [15]
    An Overview of the PMBOK® Guide - SEBoK
    May 23, 2025 · The Initiating process group contains two processes: develop the project charter and identify stakeholders. Planning Process Group. The ...
  16. [16]
    [PDF] INTERNATIONAL STANDARD ISO 21500 - isopm.ru
    Project charter. 4.3.3 Develop project plans. The purpose of ...
  17. [17]
    ISO 21500:2021 - Project, programme and portfolio management
    In stockThis document specifies the organizational context and underlying concepts for undertaking project, programme and portfolio management.Missing: charter | Show results with:charter
  18. [18]
    Project Charter Template (PMBOK ® Guide Aligned)
    This sample Project Charter, aligned to A Guide to the Project Management Body of Knowledge (PMBOK®Guide), includes sections for project goals, success criteria ...
  19. [19]
    3.1 Project Charter – Project Management - Pressbooks@MSL
    A project charter provides the project manager with the authority to apply organizational resources to project activities.Missing: 7th | Show results with:7th
  20. [20]
    Managing multiple small projects - Three Steps - PMI
    Oct 18, 2008 · The project charter “lite” consists of project objectives, stakeholders, project scope, major deliverables, assumptions, constraints, risk ...Project Management Process... · Step 1: Develop A Single... · Leadership Skills For...
  21. [21]
    Project Charter Elements | Smartsheet
    ### Summary of Optional Additions to Project Charters
  22. [22]
    How to Use a Project Charter for Project Governance - PM Majik
    What governance elements are part of a project charter? · The project timeline · The project budget · What success looks like · How the project fits with the ...
  23. [23]
    Elements of a Project Charter in Project Management - SixSigma.us
    Aug 7, 2024 · A well-crafted project charter serves as a foundational document that aligns the project team and stakeholders on the objectives, scope, timelines, and ...
  24. [24]
    Managing and Leading Small Projects - PMI
    The project charter includes the following: project roles and responsibilities (project sponsor, project manager, other project stakeholders, core team members) ...
  25. [25]
    Art of Tailoring - Making Project Methodology Fit - PMI
    Oct 22, 2012 · An easy way to do this is simply to divide projects into small, medium, and large projects and have a different set of processes, tools, and ...Making Your Project... · Origins Of The Problem · The Process Of Tailoring
  26. [26]
    A closer look - PMI
    This article explains what a SWOT analysis is, shows how to plot and rank projects within a SWOT matrix, and describes how the tool can be used to evaluate the ...
  27. [27]
    Standardize Your Project Charter with Templates for Microsoft 365
    Jan 29, 2025 · Learn the key elements of how to standardize project charters using templates Power Apps and Microsoft 365. Learn about key elements ...Missing: digital remote 2020 onwards
  28. [28]
  29. [29]
    What is a Project Charter? Complete Guide & Examples
    A project charter is a document that outlines the objectives, scope, stakeholders, and key deliverables of a project to align the team and sponsors.Missing: 2024 | Show results with:2024
  30. [30]
  31. [31]
    Write a Project Charter - OpenClassrooms
    #What Are the Elements of a Project Charter? · Background · Objectives · Scope · Constraints · Assumptions · Risks · Deliverables.
  32. [32]
    Do More in Less - PMI
    The project charter authorizes the project and contains initial requirements to satisfy stakeholder expectations. With the charter, the project begins with a ...
  33. [33]
    Ensuring sponsorship and stakeholder alignment for a project - PMI
    Clearly identifying project stakeholders early in the process allows the sponsor and project manager to see the "landscape" of the organizations and individuals ...
  34. [34]
    Stakeholder analysis - PMI
    Definition of Project Management: Project management is the “application of knowledge, skills, tools, and techniques to project activities in order to meet ...Missing: 7th | Show results with:7th
  35. [35]
    Engaging Stakeholders for Project Success - PMI
    Project teams should be speaking with all stakeholders, obtaining viewpoints, and creating a set of actions as parts of the project plan that are informed by ...
  36. [36]
    How to secure 360 stakeholder buy-in and sustain it? - PMI
    In this paper, the author addresses battle-tested techniques for securing and sustaining buy-in from all stakeholders on your project or program.
  37. [37]
    [PDF] Pulse of the Profession ® 2023: Power Skills, Redefining ... - PMI
    The results reveal some compelling links. For example, 92% of respondents agree that power skills help them work smarter.
  38. [38]
    Project Charter Template - Improving Planning Process - PMI
    A project charter transforms agreements into a documented approach, organizing a project's need and outcomes, and providing a foundation for decisions.
  39. [39]
    Free Project Management Templates and Insights - PMI
    A curated selection of industry-vetted PMI templates, guides, and more to help you grow and maximize project success.Personal Branding · Top Four Power Skills Every... · The Power of the Prompt
  40. [40]
    How AI project management tools streamline workflows - Microsoft
    AI can even help write a project plan by suggesting timelines, resources, and task dependencies based on similar past projects. Enhancing productivity with ...Missing: drafting | Show results with:drafting
  41. [41]
    11 Best Project Management Tools & Software [2025] - Asana
    Feb 21, 2025 · 1. Asana: Best for enterprise companies · 2. Trello: Best for simple project management · 3. Smartsheet: Best for spreadsheet lovers · 4. Jira: ...
  42. [42]
    7 Project Management Tools: Use Cases and the Best One for Your ...
    Sep 17, 2025 · Project management tools—software ... If you're managing software development projects or using agile methodologies, Jira is an excellent choice.
  43. [43]
    Best project charter templates every team needs in 2025
    Oct 13, 2025 · Follow a proven five-step process: define the vision, map stakeholders, establish scope, set timelines, and identify risks to build alignment ...<|separator|>
  44. [44]
    shahedbd/awesome-project-management - GitHub
    The Ultimate List of 42 Free Project Management Templates · Work Breakdown ... Project Start to End Generic Checklist · Project Charter Template · Minutes of ...
  45. [45]
    Create a project plan (Copilot Scenario Library) - Microsoft Adoption
    Copilot can help IT professionals manage their projects from collaboration, to ideation, and content updates.
  46. [46]
    Best Practices of Microsoft Copilot for Project Management
    Sep 11, 2024 · ✓ Drafting Content: Copilot assists in creating content for project documentation, meeting agendas, and reports, ensuring consistent tone ...Project Status Reporting And... · Copilot Success Kit · Start Your Ai Journey With...
  47. [47]
    [PDF] PMBOK Guide 6th Edition Errata | PMI
    Develop Project Charter is the process of developing a document that formally authorizes the existence of a project and provides the project manager with the ...
  48. [48]
    [PDF] Developing the Project Charter
    Although it contains the usual suspects, such as schedule milestones, budget, project description, and its requirements, the charter also provides objectives of ...
  49. [49]
    Plan of Attack - Boeing utilizing PM | PMI
    To realize its projects, it applies a project and program management approach that the company has internally developed and continuously refined. This article ...
  50. [50]
    [PDF] Boeing Dreamliner:A Project Management Study - PDXScholar
    The 787 Dreamliner aircraft project required not only the application and integration of new construction materials, it also required new project management ...Missing: compliance | Show results with:compliance
  51. [51]
    What is a Project Charter? [aka a Project Mandate] - OnlinePMCourses
    Feb 20, 2025 · A Project Charter is a formal document that authorizes the start of a project. It provides the project manager with the authority to allocate resources and ...
  52. [52]
    The 2020 Scrum Guide TM
    The Product Goal describes a future state of the product which can serve as a target for the Scrum Team to plan against. The Product Goal is in the Product ...Scrum Team · Scrum Events · Scrum Artifacts
  53. [53]
    Top Five Causes of Scope Creep - PMI
    Oct 12, 2009 · Scope creep is a dreaded thing that can happen on any project, wasting money, decreasing satisfaction, and causing the expected project value to not be met.
  54. [54]
    100+ Project Management Statistics & Facts (Updated 2025)
    Mar 27, 2025 · “Reasons for Project Failure” Statistics. 1. 37% of projects fail due to the lack of defined project objectives and milestones. (Source: PMI) ...
  55. [55]
    Top 5 Pitfalls in Crafting a Six Sigma Project Charter | Quality Gurus
    Vague or ambiguous objectives can mire the project in confusion and misdirection. 2. Ill-Defined Scope: An accurately defined scope sets the boundaries for ...<|separator|>
  56. [56]
    We're All in This Together: How to Identify Stakeholders and Achieve ...
    Aug 28, 2017 · These types of issues happen in the final stages of a project, often as a result of incorrect or incomplete stakeholder identification.
  57. [57]
    7 Common Mistakes in Project Charters - 6Sigma.com
    Mar 28, 2018 · This kind of balance is difficult to attain in some cases, but as a good rule of thumb, you should address issues related to the smaller details ...
  58. [58]
    Essential Guidelines for Building Strong Project Charters: 8 Do's and ...
    Oct 29, 2024 · The Don'ts: Avoiding Common Pitfalls · 5. Don't Confuse Charters with Requirements · 6. Don't File and Forget · 7. Don't Over complicate ...
  59. [59]
    Project sponsorship - PMI
    In initiation, the sponsor needs to make sure that the project charter sells and promotes the projects sufficiently and realistically. During planning, the ...Senior Management's Role In... · Introduction · Learning About The Sponsor
  60. [60]
    Project Management Statistics: 45 Stats You Can't Ignore - Workamajig
    Another study found that 33% of projects fail because of a lack of involvement from senior management. ... Among IT projects, failure rate corresponds heavily to ...
  61. [61]
    The Future of Project Work: Pulse of the Profession® 2024 | PMI
    Uncover valuable insight into what drives project performance and the impact of implementing flexibility for project teams in our 2024 Pulse of the Profession ...Missing: poor charter
  62. [62]
    7 Challenges and Solutions in Managing Large Scale IT Projects
    Nov 7, 2022 · The most prominent challenge project managers face today is working in a distributed work environment with stakeholders in different geographic locations and ...
  63. [63]
    Get SMART for better management - PMI
    SMART is a holistic view relying on four factors: 1) keeping projects in tune with the organization; 2) minimizing wasted effort; 3) having teams that are ...
  64. [64]
    Accelerating your Project using Facilitated Work Sessions - PMI
    Incorporating facilitated work sessions into the project lifecycle to produce specific deliverables accelerates creation of the deliverable.
  65. [65]
    The project meeting facilitator - More Effective Project Meetings - PMI
    Meeting facilitation is a structured way to help people reach common understandings and solve problems. It's a skill, a process and an art.
  66. [66]
    PMBOK Guide | Project Management Institute - PMI
    30-day returnsThe go-to source for Project Managers, the PMBOK Guide (7th Edition) is structured around eight Project Management domains and identifies twelve key principles ...Missing: charter | Show results with:charter
  67. [67]
    Developing a Team Charter | PMI
    A charter is defined as “a document issued by a (body) outlining the conditions under which a (body) is organized, and defining its rights and privileges” or ...