The Signature Bridge is a cantilever spar cable-stayed bridge spanning the Yamuna River in Delhi, India, connecting Wazirabad in North Delhi to the East Delhi area to reduce traffic congestion along the Outer Ring Road.
India's first asymmetrical cable-stayed bridge, it features a distinctive inclined steel pylon rising 154 meters, making it the tallest structure in Delhi and incorporating a public viewing gallery at the top for panoramic city views.
Conceptualized in 2004 with an initial budget of approximately ₹670 crore, the project encountered prolonged delays due to construction challenges, design modifications, and contractual disputes, ultimately costing over ₹1,600 crore and opening to vehicular traffic in November 2018 following its inauguration.
Notable for its engineering innovation and role in improving connectivity, the bridge shortens travel times significantly while providing recreational facilities including selfie points and a glass-floor deck, though its development highlighted issues in large-scale infrastructure execution in urban India.

History

Planning and Conception

The Signature Bridge project was conceptualized in 2004 by the Delhi Tourism and Transportation Development Corporation (DTTDC), a body under the Government of Delhi, to address chronic traffic congestion across the Yamuna River amid the city's rapid urbanization and preparations for the 2010 Commonwealth Games. The initiative sought to alleviate pressure on aging crossings like the Wazirabad Bridge, which handled substantial north-to-east Delhi traffic volumes, by providing a direct elevated link from Wazirabad in North Delhi to East Delhi's inner ring road areas. Primary objectives included slashing peak-hour cross-Yamuna commute times from roughly 45 minutes—due to bottlenecks at existing routes—to less than 10 minutes, thereby enhancing connectivity for over 40 residents in northeastern suburbs and supporting economic activity in underserved eastern sectors. The cabinet approved the proposal in 2007, envisioning a cable-stayed structure not merely as but as a symbolic "signature" landmark, incorporating a panoramic viewing gallery at its apex to draw tourists and symbolize modern 's aspirations. Initial cost projections stood at approximately 459 as of March 2006, funded primarily through state budgets and loans, with the DTTDC tasked to oversee design and execution phases aligned to timelines. This planning emphasized multimodal utility, integrating vehicular lanes with pedestrian and recreational elements to balance transport efficiency and urban aesthetics.

Construction Phase

The construction contract for the Signature Bridge was awarded to a comprising Gammon , Consegur Ltda of , and Tensacciai SpA of . The project utilized a spar cable-stayed design engineered by , featuring an asymmetrical configuration to optimize balance across the River. Foundation work commenced on the banks with a mix of deep open foundations using spread footings on rocky strata approximately 20 meters below ground, 16 well foundations with diameters of 8-9 meters, and hybrid foundations incorporating piles for the anchorage to address varying conditions including alluvial deposits. The foundations consisted of two 23-meter-diameter circular open foundations integrated with the structure. These elements supported the 165-meter-high asymmetrical —India's first of its kind—erected via a 1,250-ton crawler crane that lifted pre-assembled segments weighing 40-560 tons, which were rotated into position using ground-based turntables and secured with temporary struts and tie-downs to manage the inclined, eccentrically loaded form. The deck, measuring 675 meters in total length with a 251-meter main span and 35.2-meter width accommodating eight lanes, was built incrementally on temporary trestles using a Goliath gantry crane, incorporating composite construction with precast concrete panels 250-350 millimeters thick (up to 700 millimeters near the pylon). To handle asymmetrical loads, the pylon's self-weight was leveraged through its eccentric center of gravity, minimizing reliance on backstay cables. Stay cables—15 pairs for the main span (55-123 strands each) and 4 backstay pairs (127 strands)—were installed sequentially via tower crane and winch, tensioned in 2-3 stages using the iso-elongation method with 15.7-millimeter-diameter, 1,860 MPa high-strength strands. Pylon modules were bolted on-site rather than welded to adapt to local fabrication practices.

Delays and Overruns

The Signature Bridge project, conceived to alleviate ahead of the , encountered repeated delays that pushed its completion from an initial target of 2013 to inauguration on November 4, 2018. Construction, awarded to the Delhi Tourism and Transportation Development Corporation (DTTDC) in 2012 after earlier planning phases, stalled due to land acquisition disputes, requiring negotiations with local stakeholders and utility relocations. Additionally, the project demanded 21 environmental clearances from various authorities, a process that extended over years amid concerns over River ecology and urban impact assessments. Funding shortfalls and inter-governmental coordination issues compounded the timeline extensions, with the Delhi government releasing funds incrementally amid budgetary constraints and disputes over cost revisions. For instance, work halted in mid-2018 pending resolution of payment arrears to contractors, prompting a third-party audit ordered by the administration to address allegations of mismanagement in fund allocation between state agencies. Bureaucratic delays in approvals, including revisions to design specifications for approach roads, further inflated timelines, as noted in government reports attributing over seven years of slippage to lags. Budget overruns were substantial, with the initial 2006 estimate of ₹459 escalating to a revised total of ₹1,518.37 by , driven by inflationary pressures on materials like , expanded scope for ancillary such as underpasses, and penalties from prolonged contractor idle time. Delhi Cabinet approvals in July cleared the final escalation from ₹1,131 , incorporating costs for unresolved claims and efficiency losses from phased funding. The High Court, in February proceedings, criticized the protracted delays and ordered expedited payments totaling over ₹1,334 already disbursed, underscoring systemic inefficiencies in public and oversight that warranted higher-level review.

Design and Engineering

Structural Design

The Signature Bridge utilizes a spar cable-stayed configuration, characterized by a single inclined asymmetrically to support the main via radiating stay cables. This setup enables efficient load transfer from the to the through in the cables and along the spar, minimizing moments in the pylon and optimizing material efficiency. The single-pylon arrangement reduces the number of substructures required in the River, thereby limiting interference with riverine ecology and compared to multi-pier alternatives. The asymmetrical design addresses the unequal span lengths by tilting the pylon, which balances horizontal forces and enhances overall stability without additional counterweights or piers. This approach leverages principles of cable prestressing to counteract dead loads, distributing compressive stresses effectively while reducing the deck's self-weight contribution to the pylon. Such configuration draws from established cable-stayed to achieve structural economy, as the inclined spar aligns cable forces more directly with the primary load path. The bridge deck accommodates eight lanes in a format, engineered for resilience in IV per Indian Road Congress standards, incorporating ductile detailing and analysis to mitigate earthquake-induced vibrations. The design prioritizes load-bearing integrity under dynamic conditions, ensuring the cable-stayed system maintains tension integrity during seismic events.

Technical Specifications

The Signature Bridge is an asymmetric cable-stayed structure with a total length of 675 meters, comprising a main span of 251 meters flanked by side spans of 36 meters each. The spans 35.2 meters in width, supporting eight lanes (four in each direction) across a composite with a surface area of approximately 21,000 square meters. The inclined pylon, rigidly connected at its base, rises to a height of 165 meters above ground level and weighs 5,800 tonnes in . incorporates high-strength for substructure elements and corrosion-resistant alloys for the pylon and stay cables to ensure durability in the region's environmental conditions. Foundations feature elevated pile-supported designs adapted for the flood-prone River site, utilizing deep borings and specialized substructure systems to mitigate scour and hydraulic loads.
ParameterSpecification
Total Length675 m
Main 251 m
Deck Width35.2 m
Height165 m
Traffic Lanes8 (4 per direction)
5,800 tonnes (pylon)

Innovations and Challenges

The Signature Bridge introduced India's first asymmetrical cable-stayed configuration, diverging from symmetric global precedents to align with the Yamuna River's narrow 300-meter width at Wazirabad and the skewed urban roadway geometry connecting east Delhi to the outer ring road. This single-pylon design, with the 154-meter inclined steel tower offset from the centerline, optimized span efficiency—featuring a 251-meter main span within a 675-meter total length—while reducing foundation requirements in constrained riparian zones. The asymmetry addressed causal constraints of site geometry, enabling harp-pattern stay cables to transfer loads without symmetric counterweights impractical for the locale. Engineering challenges stemmed from the Yamuna's alluvial soils, prone to settlement, necessitating deep pile foundations up to 50 meters to anchor the substructure against scour and differential movement. Seasonal flooding, peaking during monsoons, complicated ; temporary trestles and props were engineered to endure submersion and hydrodynamic forces, allowing incremental deck segment assembly via balanced method even in wet seasons. Pylon lifting, executed with a 1,250-ton crawler crane, incorporated erection-stage analysis-derived temporary supports to mitigate risks from the slender, inclined profile under progressive self-weight and wind. Innovative integration of dynamic LED lighting along the and enhanced visibility for 24-hour operations, synchronized with the aesthetics, though commissioning tests exposed calibration issues with vibration-induced variances. Planned arrays for and traffic oversight faced early hurdles in routing amid the stays, resolved through redundant fiber-optic embedding to ensure against environmental .

Construction and Completion

Key Milestones

Construction of the Signature Bridge commenced in late 2012, marking the start of on-site and piling activities after years of and tendering. Piling work, essential for supporting the asymmetrical structure over the River, spanned 45 months and reached completion in April 2016, positioning the project as one of India's faster foundational efforts for such a span. Erection of the 165-meter boomerang-shaped pylon advanced following piling, with the structure fully topped out by the end of 2017 despite challenges in aligning its inclined geometry to ensure load distribution. Cable spinning for the stay cables began post-pylon erection, achieving installation of half the cables by late 2017, with the full set of cables tensioned and operational by early the following year to stabilize the main span. The composite steel-concrete deck segments were progressively installed from the pylon anchors, with most erection complete by end-2017 and full linkage across the 251-meter main finalized in early 2018. Mid-2018 saw trial vehicle runs on the linked deck, alongside structural integrity tests and safety certifications by independent engineers, confirming readiness for load-bearing traffic prior to operational handover.

Inauguration and Initial Operations

The Signature Bridge was inaugurated on November 4, 2018, by during a public ceremony that included performances and speeches highlighting its role in decongesting northern traffic. The event proceeded amid minor disruptions, including a scuffle between political supporters, but proceeded to mark the bridge's partial operational readiness. Vehicular traffic was permitted starting November 5, 2018, prioritizing the bridge's core function as a signal-free corridor despite ongoing work on ancillary features like the elevated viewing gallery, which was targeted for completion by early 2019 but faced further delays. Early operations routed vehicles from congested alternatives such as the Bridge, enabling direct connectivity between and urban areas to alleviate peak-hour bottlenecks. Initial feedback reported generally smooth traffic flow on the eight-lane structure, though Delhi Traffic Police raised immediate concerns about inadequate safety provisions, including pedestrian barriers on the helical ramps and entry points, prompting requests for rapid modifications to prevent accidents. These adjustments focused on short-term logistical tweaks, such as signage and enforcement, to stabilize usage during the first months without toll charges imposed by the Department.

Features and Functionality

Transportation Role

The Signature Bridge functions primarily as a vehicular crossing over the River, linking on the eastern bank to on the western bank, thereby providing a direct route that bypasses congested inner-city paths dependent on older structures like the Wazirabad Barrage. This connectivity integrates with the Outer Ring Road on the west and Wazirabad Road on the east, streamlining access between northern suburbs and eastern regions while avoiding bottlenecks in central areas. Comprising an eight-lane , the bridge supports efficient traffic flow for cars, buses, and other vehicles, with design elements including a central verge for cable anchoring and maintenance access to ensure operational reliability. Approach roads feature dedicated connections to adjacent locales such as Timarpur, Nehru Vihar, and , incorporating grade-separated structures to reduce at-grade intersections and enhance routing efficiency.

Tourist Attractions

The Signature Bridge incorporates a dedicated tourist facility in the form of a 154-meter-high viewing gallery perched atop its central , designed to deliver panoramic vistas of the River and surrounding landmarks, positioning it as an iconic "" vantage point for visitors. This steel-and-glass , double the height of the Qutub Minar, was engineered with elevators capable of transporting up to 50 people at a time to facilitate public access and elevate the bridge's appeal beyond mere transportation infrastructure. Supporting amenities were integrated to enhance the visitor experience and drive tourism revenue for the Delhi Tourism and Transportation Development Corporation (DTTDC), the project overseer, including provisions for eateries, areas, and points to accommodate crowds drawn to the elevated perspectives. Evening illuminations, featuring dynamic theme-based lighting systems installed by 2020, further amplify its allure by transforming the structure into a luminous spectacle against the skyline, intended to attract photographers and evening sightseers. Initial plans envisioned a fully enclosed all-glass operational by mid-2020, extending to comprehensive public access by 2022, to capitalize on the structure's height for sustained tourist footfall; however, realization has been hampered by escalating maintenance demands and logistical constraints, limiting the facility's consistent draw compared to its promotional ambitions.

Operational Impact

Traffic and Economic Effects

The Signature Bridge has substantially reduced cross-Yamuna travel times between north and northeast , shortening the typical journey from approximately 45 minutes via alternative routes to 10 minutes on the bridge itself. This improvement, equivalent to a roughly 78% decrease in duration, has eased pressure on parallel structures like the Wazirabad Bridge by diverting traffic flows during peak periods. Consequently, commuters experience lower fuel consumption due to minimized idling and detours, with initial projections estimating savings aligned with the reduced travel distance of about 8 kilometers. Economically, the bridge enhances connectivity for North-East Delhi's residential and industrial areas to central business districts, enabling shorter commutes that support workforce mobility and operational efficiency in sectors like and . It has also spurred local appreciation in adjacent neighborhoods by improving , with property values in and nearby zones reflecting heightened demand post-inauguration in November 2018. As a dual-purpose serving vehicular and tourist , the initially attracted significant visitor numbers, fostering ancillary spending on and amenities, though sustained footfall has fluctuated amid broader trends. These effects collectively contribute to incremental in regional and productivity, though comprehensive econometric studies quantifying net GDP impact remain limited.

Environmental Considerations

The National Green Tribunal ordered environmental clearance for the Signature Bridge project in February 2015, extending environmental impact assessment requirements to suspension bridges for the first time and addressing potential disruptions to the Yamuna River's ecosystem. Construction had begun in 2014 without prior clearance, leading to delays in compliance, but approval was ultimately granted by Delhi's State Environment Impact Assessment Authority in March 2017 after submission of an environmental management plan. The clearance stipulated measures to minimize riverbed interference, including provisions for waste prevention via a protective deck beneath the structure to curb direct pollution from litter or runoff. During construction, recommended pollution controls included water sprinkling to suppress dust and roadside tree planting to buffer ambient air quality, as outlined in the State Expert Appraisal Committee's review. However, these were undermined by extensive debris accumulation in the riverbed and , which choked Yamuna's , reduced habitat viability, and persisted into 2019 despite expert warnings of flood risks and ecological harm ahead of the monsoon season. Partial debris removal occurred following media and activist scrutiny, but violations of clearance conditions, such as inadequate , drew criticism from environmental groups for failing to fully protect riverine . In the long term, residual has contributed to ongoing degradation, including sediment buildup and hotspots under the bridge that facilitate easier floodplain crossing and exacerbate seasonal frothing from untreated effluents. While the bridge's role in decongesting north traffic could indirectly lower idling-related emissions, no verified assessments confirm net gains in air quality or restoration, against a backdrop of the 's persistent in the capital stretch. Legacy debris issues highlight incomplete mitigation, with authorities like the Control Committee imposing fines on related entities for non-compliance in cleanup efforts.

Controversies

Cost and Management Issues

The Signature Bridge project, managed by the Delhi Tourism and Transportation Development Corporation (DTTDC), experienced significant cost overruns, with the estimated expenditure rising from an initial Rs 459 in March 2006 to Rs 1,131 by 2009, and ultimately reaching Rs 1,518.37 upon approval in July 2018. The Comptroller and Auditor General (CAG) of attributed much of this escalation—specifically Rs 672 —to administrative lapses, including six revisions to the project estimates between May 2005 and October 2009, delayed contract awards, and failure to effectively manage and execution timelines. Administrative shortcomings under DTTDC oversight were highlighted in CAG audits and vigilance inquiries, which pointed to inflated contracts, inadequate event management during construction phases, and the use of unverified imported materials without proper quality assurance, contributing to unnecessary expenditure. Inter-departmental disputes exacerbated delays and costs, as evidenced by conflicts between DTTDC and the (PWD) over responsibilities, leading to work stoppages and the need for a third-party ordered by the government in May 2018 to resolve payment impasses. Contractor-related challenges, including non-payment disputes that prompted labor walkouts and reliance on firms facing financial strain, further inflated costs without mechanisms for overrun recovery, underscoring systemic inefficiencies in state-led execution. These issues reflect broader accountability gaps in public mega-projects, where repeated delays—from an original target to inauguration in November 2018—amplified expenses through extended overheads and penalty waivers, with no documented reclamation of excess funds from contractors or officials. The criticized such management failures in February 2018, urging high-level scrutiny to prevent recurrence in similar ventures.

Suicide Epidemic

Since its inauguration on November 4, 2018, the Signature Bridge has become a notorious site for suicides by jumping into the Yamuna River below, with reports indicating at least 22 such deaths recorded from 2019 onward. The bridge's 154-meter-high pylon offers accessible vantage points with initial minimal barriers, drawing distressed individuals seeking high visibility and ease of access for fatal leaps. This pattern contrasts with Delhi's overall suicide landscape, where the city recorded 3,131 cases in 2023 alone—12% of national urban totals—but the bridge accounts for a disproportionate concentration of jumping incidents relative to other elevated structures, amplified by its prominence as a landmark. Incidents have escalated over time, with police reporting roughly three attempted jumps per month by early 2023, leading to at least 30 rescues by divers through 2022. A notable recent case involved 19-year-old Delhi University student Sneha Debnath from Tripura, who disappeared on July 7, 2025, after being dropped by cab near the bridge; her body was recovered from the Yamuna on July 13, accompanied by a suicide note citing feelings of failure. Such events highlight causal factors including the structure's elevated, unsecured edges and absence of functional CCTV surveillance, which authorities have failed to implement despite repeated calls. Efforts to mitigate risks, such as proposed mesh barriers discussed by in , have lagged, with earlier retrospective additions like nets or fences between 2020 and 2022 proving inadequate against determined attempts. The bridge's design, prioritizing aesthetic visibility over robust perimeter security, exacerbates its appeal as a site amid 's youth pressures, where suicides constitute a significant portion of deaths in the 15-29 age group.

Safety and Maintenance Failures

Shortly after its inauguration on November 4, 2018, the Signature Bridge experienced multiple attributed to its steep ramps, absence of speed breakers, and inadequate . On November 23, 2018, a collision involving three vehicles resulted in two fatalities due to high speeds on the ramps merging with the Outer Ring Road, where drivers struggled to control vehicles without rumble strips or . The following day, another crash killed one person and injured others, prompting to request immediate installation of signboards for speed limits and merging points, which had been flagged days earlier but not implemented. These incidents highlighted lapses in ramp design and , turning the bridge into an early hotspot despite its role in decongesting . Maintenance shortcomings exacerbated operational hazards, with the bridge rapidly accumulating litter and becoming an unauthorized picnic site, leading to wrong-side driving and encroachments that impeded . Within a week of opening, reports documented piles of garbage without waste bins, alongside violations like vehicles parked illegally and crowds climbing on motorcycles for photos, creating secondary risks without enforcement mechanisms. The absence of functional CCTV cameras across the structure, noted in incident investigations, further compromised monitoring and response to such hazards, with no cameras operational as of mid-2025 despite repeated calls for following early mishaps. The viewing gallery at the bridge's pylon head faced operational disruptions, including a 2022 proposal by the government to scrap public access due to unresolved regulatory hurdles with elevators, halting the intended tourist feature and underscoring upkeep deficiencies. In response to persistent issues, authorities implemented partial measures like a 2022 tactical urbanism trial involving redesigned signage, narrowed merging angles, and approach lanes to mitigate ramp-related conflicts, though reports indicated ongoing neglect. By 2025, cleanup initiatives addressed visible deterioration, including volunteer and civic drives targeting litter near the bridge amid broader efforts, yet documentation of unaddressed structural vulnerabilities and surveillance gaps persisted, reflecting chronic underfunding in preventive maintenance.

Reception and Legacy

Public and Media Response

The inauguration of Signature Bridge on November 4, 2018, by the (AAP)-led government elicited initial praise from supporters for symbolizing infrastructural ambition and reducing travel times across the River, with Chief Minister dubbing it "'s ." AAP leaders highlighted its role in easing congestion on the , crediting the project to their administration's oversight despite pre-existing delays. However, opposition (BJP) figures, including BJP chief , critiqued the AAP for politicizing the event amid long-standing delays—originally conceived in 2000 and facing multiple missed deadlines—and accused the government of populist overreach in claiming sole credit for a centrally funded initiative. Clashes between AAP and BJP workers at the opening underscored partisan divides, with FIRs naming both Kejriwal and Tiwari in violence-related complaints. Media coverage reflected a split, with early reports lauding the bridge's aesthetic and functional promise as India's first asymmetric cable-stayed structure, yet quickly shifting to scandals involving cost escalations from an initial ₹459 to over ₹1,500 due to delays and revisions, alongside maintenance lapses. Outlets like and noted rapid littering, traffic violations, and unsafe selfie-taking within days of opening, portraying it as a "sorry picture" despite ambitions for . Foreign media, including , highlighted risks of "dangerous s" from its 154-meter height, prompting government plans for designated selfie points and a viewing deck. Coverage intensified on suicides, with over 25 attempts rescued in 2022 alone, and public outcry following incidents like the July 2025 death of student Sneha Debnath, where her family blamed absent CCTV surveillance on the "suicide-prone" bridge. Public sentiment, as reflected in tourist reviews and social media, showed mixed satisfaction: appreciation for panoramic views of and the , earning average ratings around 4.5/5 on platforms like for its modern appeal, contrasted with complaints over poor upkeep, garbage accumulation, and safety gaps. Visitors often amplified failures online, decrying it as a "picnic spot" overrun by crowds violating rules for photos, while demands grew for barriers and monitoring to curb suicides and reckless behavior. Stakeholder calls, including from , urged tourism authorities for mesh barriers and better oversight, underscoring persistent concerns over performance despite symbolic value.

Long-Term Assessment

The Signature Bridge has sustained partial traffic benefits by shortening routes between North and Northeast , yet connecting corridors like the Outer Ring Road remain , prompting new six-lane flyovers estimated at ₹183 to alleviate bottlenecks as of 2025. This relief is undermined by dynamics, where infrastructure expansions attract more vehicles, restoring pre-bridge levels over time. Persistent suicides—totaling at least 22 deaths since 2019, alongside roughly three monthly rescue attempts—have entrenched a that curtails , despite the bridge's intended viewing gallery and asymmetric cable-stayed as an engineering landmark. Lacking barriers, CCTV, or akin to those on bridges like Japan's Mapo (which cut attempts by 30%), 's site exhibits elevated incident rates relative to global peers with proactive safeguards. Construction costs surpassing ₹1,500 , plus handover from to for maintenance, question amid forgone visitor revenue and unresolved safety liabilities. The structure's legacy underscores public project pitfalls, including delays and oversight gaps that amplify risks in high-exposure , with fiscal strains delaying upgrades like anti-suicide meshes despite repeated police requests. While persists, administrative inefficiencies—evident in the 2025 transition—fuel broader discourse on privatizing upkeep to enforce accountability, though no formal proposals have advanced.

References

  1. [1]
    Signature Bridge | District North East, Government of Delhi | India
    The Signature Bridge is a cantilever spar cable-stayed bridge which spans the Yamuna river at Wazirabad section, connecting Wazirabad to East Delhi.
  2. [2]
    Photos: Delhi's iconic Signature Bridge opens Sunday - Times of India
    Nov 2, 2018 · Conceptualised in 2004, the project witnessed several missed deadlines and a major cost escalation and took almost eight years to complete.Missing: length | Show results with:length
  3. [3]
    Grand opening of Delhi's Signature Bridge - sbp
    Delhi Chief Minister Arvind Kejriwal and his deputy Manish Sisodia inaugurated the bridge on Sunday in a festive ceremony. The Signature Bridge is India's first ...Missing: facts length controversies
  4. [4]
    [PDF] TOURISM - Planning Department
    A steel pylon which is 154 meter high has been built at Signature bridge which has a viewing gallery at the top. In order that tourists coming to Viewing ...<|control11|><|separator|>
  5. [5]
    Delhi Signature bridge: All you need to know - The Indian Express
    Nov 4, 2018 · The bridge will be opened to the public on Monday, November 5. A laser show is also expected to take place after the inauguration ceremony.
  6. [6]
    Delhi's iconic Signature Bridge opens today: 5 interesting facts to know
    Nov 4, 2018 · Delhi's Signature Bridge was inaugurated today after a gap of 14 years. Announced in 2004, the bridge was finally inaugurated by Delhi chief ...
  7. [7]
    Delhi's Signature Bridge Has Selfie Spots, Glass Viewing Deck
    Nov 3, 2018 · The much-awaited bridge was inaugurated by Chief Minister Arvind Kejriwal on November 4, and thrown open to public on November 5. The grand ...<|separator|>
  8. [8]
    Delhi's Signature Bridge needs environmental clearance
    Feb 15, 2015 · Proposed in 2004 by DTTDC, the bridge was meant to be inaugurated before the 2010 Delhi Commonwealth Games. According to sources in DTTDC ...Missing: planning 2000s
  9. [9]
    Signature Bridge Feature Photo An aerial view of the De...
    The project was conceptualised in 2004 and got the nod from Delhi cabinet in 2007. The first deadline was fixed ahead of the 2010 Commonwealth Games but it was ...
  10. [10]
    Signature Bridge project: Govt sets January 2015 as deadline
    Oct 13, 2014 · The project was initially to be completed before 2010 Commonwealth Games. The DTTDC has also faced the ire of Lieutenant-Governor Najeeb Jung ...Missing: conception | Show results with:conception
  11. [11]
    Signature Bridge Delhi: A new tourist destination, double the height ...
    Nov 5, 2018 · The bridge will reduce the commuting time between northeast areas and the inner city from 45 minutes to just 10 minutes, saving the pollution ...
  12. [12]
    Signature bridge, double Qutub Minar's height, to cut travel time in ...
    Nov 4, 2018 · The bridge will reduce the commuting time between northeast areas and the inner city from 45 minutes to just 10 minutes, saving the pollution ...
  13. [13]
    Signature Bridge- Delhi - TNPSC Current Affairs
    This Bridge is connecting Wazirabad across the Yamuna river to the inner city of Delhi. · It will cut down the present travelling time from 45 minutes to 10 ...Missing: reduce | Show results with:reduce
  14. [14]
    DTTDC pulled up over Signature Bridge project - Delhi - The Hindu
    Apr 3, 2013 · ... estimated cost of the project from Rs.459 crore in March 2006 to Rs.1,131 crore in February 2010 (an increase of Rs. 672 crore),” stated the ...Missing: 670 | Show results with:670
  15. [15]
    Design & Construction of Iconic Signature Bridge in Delhi
    Aug 9, 2025 · The presently under construction at Delhi over river Yamuna Signature Bridge is an iconic bridge of its kind which is languid in perpetual ...
  16. [16]
    Signature bridge - Crane & Transport Briefing
    Dec 11, 2014 · Work for the main bridge is by joint venture of Gammon India, Cidade Brazil and Tensacciai of Italy. The client for the project is Delhi Tourism ...<|control11|><|separator|>
  17. [17]
    Yamuna Bridge at Wazirabad - sbp
    The “Signature Bridge” as the new landmark of New Delhi connects the city Wazirabad across the river Yamuna to the inner city. The dynamically shaped pylon ...Missing: banks balanced cantilever
  18. [18]
    [PDF] YAMUNA SIGNATURE BRIDGE - e-mosty
    The Yamuna Signature Bridge is India's first 'Signature Bridge', an asymmetric cable-stayed bridge with a 251m main span and 675m total length, connecting ...
  19. [19]
    Signature Bridge hits a rocky patch | Delhi News - Times of India
    Sep 16, 2014 · The project has been marred by delays over the years for various reasons. These range from 21 environmental clearances to financial constraints ...Missing: overruns | Show results with:overruns
  20. [20]
    14 years in the making, Delhi's Signature Bridge is still a project ...
    Jun 6, 2018 · More than a decade after the idea for India's first asymmetrical bridge was proposed, repeated delays have stalled what was meant to be a new ...<|separator|>
  21. [21]
    To resolve dispute over Signature Bridge funding, Delhi govt orders ...
    May 1, 2018 · The Delhi government has ordered a third party audit of funding of the Signature Bridge project, construction of which has come to a halt due ...Missing: intervention | Show results with:intervention
  22. [22]
    Signature Bridge proving to be costly affair for Delhi govt - India Today
    Aug 24, 2015 · The project is already delayed by 7 years and almost one-fourth of the work remains to be done, officials said. Signature Bridge is a pet ...
  23. [23]
    Cabinet nod for revised Signature Bridge estimate - Delhi - The Hindu
    Jul 13, 2018 · Cabinet nod for revised Signature Bridge estimate. ₹1,518.37 cr will be used to complete construction and build an approach road. Published - ...Missing: initial | Show results with:initial
  24. [24]
    Delay in Signature bridge deserves scrutiny at highest level: HC
    Feb 20, 2018 · The court noted that Rs 1,334.10 crore had already been paid to DTTDC by the Delhi government but the bridge was still nowhere near completion.Missing: overruns | Show results with:overruns
  25. [25]
    [PDF] SIGNATURE BRIDGE - ijtre
    Construction:- Gammon(c.cidadeTensacciai JV). Characteristics of the ... Very important information. When the Construction was starts in 2004 our delhi chief.
  26. [26]
    General arrangement of Signature Bridge - ResearchGate
    Bridge is an elaborated cantilever spar cable-stayed bridge (Fig.3 The Steel Pylon of around 154 meters from top of the bearings consists of two legs made ...
  27. [27]
    [PDF] CASE STUDY OF SIGNATURE BRIDGE - ijtre
    Project was divided into two phases with Phase I including Approaches to the Bridge and Main Bridge to be completed before Commonwealth Games and Phase II of.Missing: early | Show results with:early
  28. [28]
    [PDF] Signature Bridge Project
    Equipped with two four-lanes, this engineering masterpiece will have 2.0 meter wide side verges, space for anchoring cables, maintenance walkway and crash ...
  29. [29]
    [PDF] government of india - Ministry of Earth Sciences
    Jul 28, 2016 · As per Bureau of Indian Standards [IS-1893 (Part- 1): 2002], based on the past seismic history, Delhi lies in Zone-IV that has fairly high ...
  30. [30]
    [PDF] GUIDELINES FOR SEISMIC DESIGN OF ROAD BRIDGES
    It is preferable to design bridges in zones IV and V in such a way that ... For the purpose of determining the seismic forces, the Country is classified into four ...
  31. [31]
    Signature Bridge Project in India - SARENS
    The bridge is expected to open to the public around July 2018. Our team has worked together to accomplish the engineering feat in a safe manner, always being ...
  32. [32]
    Foundations and Substructure challenges of Signature Bridge at Delhi
    It has deep open foundations, well foundations and hybrid foundations. As the pylons were integrated with the deck and supported on bearings required very large ...Missing: techniques | Show results with:techniques
  33. [33]
    [PDF] The Signature Cable-Stayed Bridge in New Delhi | Structurae
    Summary. The Yamuna crossing in New Delhi, a single-pylon cable-stayed bridge with a main span of about. 250m length will be India´s longest-span bridge of ...
  34. [34]
    Foundations and Substructure challenges of Signature Bridge at Delhi
    Signature Bridge features complex foundation systems including deep open, well, and hybrid foundations. · Pylon foundations involve unique design elements like ...
  35. [35]
    [PDF] Signature Bridge Project - Gammon India
    India's first 'Signature Bridge' is a customized, unsymmetric cable-stayed bridge with a 251m main span, 675m total length, 8 lanes, and a 150m steel tower, ...
  36. [36]
    Signature Bridge - Traxon e:cue North America
    Double the height of Qutub Minar with a 157-meter high viewing pylon, the bridge becomes the tallest modern structure in the skyline, offering a panoramic view ...Missing: engineering width daily capacity<|separator|>
  37. [37]
    Iconic Structure: India's first asymmetric cable-stayed bridge ...
    Dec 20, 2018 · With the inauguration of the much-awaited Signature Bridge on November 4, 2018, India completed its first asymmetric cable-stayed bridge.
  38. [38]
    [PDF] THE YAMUNA BRIDGE IN NEW DELHI, INDIA - Bruggenstichting
    The 'Signature Bridge' as the new landmark of New Delhi connects the city Ghaziabad and its surroundings across the river Yamuna to. Delhi's the inner city. The ...
  39. [39]
    Delhi's Signature Bridge To Open In October - NDTV
    Jul 12, 2018 · Ninety-six per cent of the work is already complete, the bridge is expected to be opened by October 31. New Delhi: India''s first asymmetrical ...
  40. [40]
    Delhi CM Arvind Kejriwal opens Signature Bridge for public
    Nov 4, 2018 · Delhi's long-awaited Signature Bridge - the first asymmetrical cable-stayed bridge in India - was opened for the public on Sunday.Missing: groundbreaking construction
  41. [41]
    Chaos marks inauguration of much-awaited Signature Bridge
    Nov 5, 2018 · Chaos marks inauguration of much-awaited Signature Bridge. State BJP chief gets into brawl with AAP workers, police; CM urges L-G to take action.Missing: gallery delay
  42. [42]
    On Day 1, Signature Bridge doubles as tourist spot, viewing gallery ...
    Nov 6, 2018 · Even as the bridge was inaugurated by Delhi Chief Minister Arvind Kejriwal on Sunday, work on the viewing gallery is pending. “We hope to ...Missing: delay | Show results with:delay
  43. [43]
    Delhi's Signature Bridge, twice the size of Qutub Minar, opens for ...
    Nov 5, 2018 · After a delay of eight years, Delhi's much-awaited Signature Bridge was finally inaugurated on Sunday by chief minister Arvind Kejriwal and ...
  44. [44]
    Signature Bridge: 'requests on safety measures ignored' - The Hindu
    Nov 27, 2018 · The city government ignored requests by the traffic police on safety measures to be implemented on the recently opened Signature Bridge, ...Missing: operations pedestrian ramps<|control11|><|separator|>
  45. [45]
    Public Works Department, Govt. of NCT of Delhi - PWD
    Helpline : 1908 (Toll Free) हेल्पलाइन : 1908 (नि: शुल्क) ... Eastern Approach Road of Signature Bridge. Category of Road: Other Roads. Zone ...Missing: operations | Show results with:operations
  46. [46]
    Delhi gets Signature Bridge, after fracas at site - National Herald
    The 575-metre-long suspension bridge, proposed in 2004 and approved by the Delhi cabinet in 2007, will reduce the travel time between North and North-East Delhi ...
  47. [47]
    construction of an iconic signature bridge in delhi - ResearchGate
    Oct 30, 2021 · The bridge has a dual carriage way of 4 lanes each with 1.2 m, central verge for anchoring cables and accommodating maintenance walk way, crash ...Missing: facts controversies
  48. [48]
    Eight years later,Signature Bridge not too far - The Indian Express
    covering four intersections at Timarpur,Nehru Vihar,Wazirabad and Mukherjee ...
  49. [49]
    154-metre high viewing box, selfie points: Delhi's Signature Bridge ...
    Nov 4, 2018 · *The bridge will have a 154-metre-high glass viewing box, which is double the height of Qutub Minar. * The people will be taken to the top of ...
  50. [50]
    Delhi Signature Bridge | AITS Hyderabad
    The Signature Bridge is India's first asymmetrical cable-stayed bridge, 575 meters long, with a glass facade, four inclined lifts, and a 154m high pillar with ...
  51. [51]
    Signature Bridge Is All Set To Become A Tourist Spot | So Delhi
    Oct 22, 2019 · Delhi's Signature Bridge will soon start hosting tourists inside a viewing gallery made of glass by the middle of the next year.Missing: attractions | Show results with:attractions<|separator|>
  52. [52]
    Government To Develop Safe Selfie Points, Parking Lot On ... - NDTV
    Nov 16, 2018 · Delhi's Deputy Chief Minister Manish Sisodia has directed authorities to develop safe selfie points and install special lighting equipment.Missing: amenities | Show results with:amenities
  53. [53]
    Iconic bridge gets signature lighting | Delhi News - Times of India
    Aug 3, 2020 · The Signature Bridge will now appear with a new look every evening, thanks to a theme-based lighting system that can showcase thousands of different patterns.Missing: amenities | Show results with:amenities
  54. [54]
    Delhi govt to permanently illuminate Signature Bridge - Times of India
    Jun 12, 2019 · The illumination work will be carried out by the Delhi Transport and Tourism Development Corporation. From static to dynamic lighting, the DTTDC ...Missing: amenities | Show results with:amenities
  55. [55]
    Signature bridge: Delhi government may scrap bird's eye view project
    Apr 10, 2022 · The Signature bridge, built at a cost of Rs 1,518.37 crore, was thrown open to commuters in November 2018. The bridge connects Outer Ring Road ...<|control11|><|separator|>
  56. [56]
    High-strung! Plan For 360 View From Atop Signature Bridge Comes ...
    Feb 8, 2024 · It took more than 11 years for Delhi govt to open the road of the bridge in Nov 2018. The construction of the deck and the glass façade took ...
  57. [57]
    Delhi's iconic Signature Bridge to ease traffic congestion and reduce ...
    Nov 8, 2018 · Standing at 165m, twice the height of the Qutub Minar, it is India's first asymmetrical cable-stayed bridge. It is built over Yamuna river, at a ...Missing: lane capacity per
  58. [58]
    Signature Bridge Delhi: Facts, significance, impact on real estate
    May 29, 2023 · Delhi's Signature Bridge in Wazirabad has cut the travel time between northeastern areas and the inner city from 45 minutes to 10 minutes.
  59. [59]
    The Signature Bridge :- The 1st Asymmetrical Bridge In India - Indiator
    Dec 14, 2018 · Delhi's Signature Bridge is all set to launch its Observatory Deck by June 30, 2019. It will be placed on the top of the signature bridge at ...<|control11|><|separator|>
  60. [60]
    Signature Bridge over Yamuna in Delhi inaugurated on 4th Nov
    Nov 2, 2018 · “This bridge will not only showcase India's technological prowess but will also serve as a catalyst for economic growth, boosting tourism, trade ...
  61. [61]
    Delhi´s Signature Bridge gets environmental approval
    Mar 1, 2017 · Delhi´s Rs 1,575-crore Signature Bridge has obtained environmental clearance. The unique cable-suspended bridge, located in Wazirabad and ...Missing: minimal piers
  62. [62]
    Signature Bridge: No iron mesh, but deck to protect river from waste
    Nov 6, 2018 · Bansal said the iconic bridge was the only such facility in the country for which the Delhi government had taken an environmental clearance. ...Missing: minimal piers
  63. [63]
    [PDF] seac - Delhi Pollution Control Committee
    Dec 30, 2016 · Ambient Air Quality may be impacted during construction; hence control measures like water sprinkling, road side plantation should be adopted.
  64. [64]
    Signature Bridge construction debris choking Yamuna's flow
    Apr 17, 2019 · The experts said that the obstruction under the bridge was seriously affecting the river's flow, and if it was not removed before the 2019 ...
  65. [65]
    Signature Bridge debris partly cleared, new allegations emerge
    May 1, 2019 · The Delhi Tourism and Transportation Development Corporation Ltd, has removed much of the debris that obstructing the river's flow below the Signature bridge.<|separator|>
  66. [66]
    Signature Bridge violated green norms: Experts | Latest News Delhi
    Apr 19, 2019 · The Signature Bridge was constructed allegedly violating at least two “specific conditions” stated in the environment clearance (EC), experts and activists ...
  67. [67]
    Signature Bridge - SANDRP
    On February 16, 2020[i], SANDRP had raised the issue of large scale construction debris left and dumped in the riverbed of Yamuna along the bridges on NH 24 in ...<|separator|>
  68. [68]
    Urgent appeal over rampant encroachment of Yamuna floodplain ...
    Jul 23, 2025 · Locals also report the river section under the Signature Bridge is easily crossable due to construction debris, warranting immediate ...Missing: challenges | Show results with:challenges
  69. [69]
    Some respite for India's dirtiest river? Examining the Yamuna's water ...
    The Yamuna's stretch within Delhi is considered as the dirtiest river reach in India and despite numerous restoration plans, pollution levels have risen ...
  70. [70]
    DDA fined Rs 40 lakh for not clearing Yamuna debris | Delhi News
    Aug 12, 2020 · Delhi Pollution Control Committee (DPCC) has imposed a fine of Rs 40 lakh on Delhi Development Authority (DDA) for failing to remove debris ...
  71. [71]
    Signature Bridge: Delhi government approves revised estimate Rs ...
    Jul 13, 2018 · After several delays and cost escalations, the Delhi government has approved a revised estimate of Rs 1518.37 crores for the construction of ...Missing: 670 | Show results with:670<|separator|>
  72. [72]
    CAG questions use of Chinese material in 'Signature' bridge
    Mar 31, 2013 · The CAG has also slammed Delhi Government for escalation of the cost of the project by Rs 672 crore against the initial estimate.
  73. [73]
    CAG questions use of Chinese material in 'Signature' bridge
    Mar 31, 2013 · On cost escalation, the CAG said "The DTTDC revised the estimates six times between May 2005 and October 2009 and took almost six years to award ...Missing: overruns | Show results with:overruns
  74. [74]
    Irregularities in Delhi's Signature Bridge flagged by Vigilance
    Jul 24, 2018 · The Delhi Cabinet recently cleared a revision of cost from Rs 1,131 crore to Rs 1,518.37 crore for construction of the 67-metre-long cable ...Missing: overruns | Show results with:overruns
  75. [75]
    High Court frowns over PWD & DTTDC sparring over Signature ...
    Apr 26, 2018 · "The PWD and DTTDC are quibbling over the amount to be paid for the Signature Bridge which is long overdue. One last opportunity is given to ...
  76. [76]
    Case Study of Signature Bridge on the Yamuna, New Delhi - LinkedIn
    Oct 10, 2020 · It has 8 lanes with 1.2 meters of central verge(which is used as a ... The Deck of the bridge was constructed with an M50 grade of ...
  77. [77]
    Delay in Signature bridge deserves scrutiny at highest level: HC
    Feb 20, 2018 · The Delhi High Court today expressed concern over the delay in the completion of the Signature Bridge across the river Yamuna and said it ...Missing: contractor | Show results with:contractor
  78. [78]
    Delhi: Political divide widens further at Signature Bridge's opening
    Nov 5, 2018 · “The cost of the bridge was estimated at Rs 1,131 crore in February 2010. The estimate had to be increased by Rs 350 crore when the ...
  79. [79]
    Why DU Student Sneha Debnath's Death Raises Safety Concerns At ...
    Jul 14, 2025 · Signature Bridge's 22 deaths since 2019 reflect a national crisis. India's youth, driving its $283 billion tech sector, face mental health ...
  80. [80]
    Delhi's Signature Bridge, once a symbol of progress, has now ...
    Jul 16, 2025 · Delhi's Signature Bridge, once a symbol of progress, has now witnessed 22 suicides since 2019, including the recent tragic case of DU student ...Missing: total | Show results with:total
  81. [81]
    Suicide fears at Signature Bridge, police to write to Delhi tourism ...
    Feb 28, 2023 · With roughly three persons being rescued every month after suicide attempts from the 154-metre-high Signature Bridge in North Delhi, ...
  82. [82]
    Delhi logged over 3k suicide cases, followed by Bengaluru and ...
    3,131 — among 53 major Indian cities, accounting for 12% of the total suicides, ...
  83. [83]
    Delhi Police devises mechanism to prevent suicides at Signature ...
    Jul 3, 2022 · The city police, along with a team of private divers, has saved the lives of 30 people who tried to end their lives by jumping into the Yamuna river from the ...
  84. [84]
    Delhi University Student Found Dead In Yamuna Was Overachiever
    Jul 14, 2025 · Sneha Debnath, the 19-year-old Delhi University student whose body was recovered from the Yamuna last evening, was an overachiever pursuing two courses ...
  85. [85]
    Body of 19-year-old Tripura girl Sneha Debnath, missing for 6 days ...
    Jul 13, 2025 · Delhi University student Sneha Debnath, 19, was found dead in the Yamuna River after going missing on July 7. A suicide note and messages ...
  86. [86]
    DU student death: Delhi's Signature Bridge has no CCTV - ThePrint
    Jul 15, 2025 · Delhi's Rs 1,500 crore Signature Bridge has no CCTV. DU student's death sparks safety alarm. One of Sneha's friends present at her Saket ...Missing: glitches | Show results with:glitches
  87. [87]
    Breaking Down Quickly? - The New Indian Express
    Jul 17, 2025 · I chose to end my life by jumping from the Signature Bridge, Delhi, early morning of 7th July. ... of total deaths in the 15-29 age group are ...
  88. [88]
    Days before accidents, traffic police asked DTTDC to install ...
    Nov 26, 2018 · Motorists are finding it difficult to control their vehicles at high speed at the merging points of Signature Bridge to Ring Road or other roads ...Missing: poor ramps
  89. [89]
    Why has Delhi's Signature Bridge become an accident spot?
    Nov 25, 2018 · Firstly, there isn't proper signage for vehicles on the entire bridge. The bridge neither has a 'no-parking sign' nor does it carry a ...
  90. [90]
    Signature Bridge presents a sorry picture in a week - The Hindu
    Nov 12, 2018 · Revelry on the bridge has turned into a traffic hazard, with motorists driving vehicles on the wrong side of the road, climbing on top of bikes ...
  91. [91]
    Signature Bridge: Delhi govt may scrap bird's eye view project - Mint
    Apr 11, 2022 · In September last year, the labour department had denied permission to operate inclined lifts to carry tourists. The Delhi government had set a ...
  92. [92]
    Delhi govt launches 'tactical urbanism' road safety trial at Signature ...
    Oct 15, 2022 · Between 2018 and 2021, the Signature Bridge witnessed 53 road crashes and 17 fatalities. Inaugurated in November 2018, this cantilever spar ...Missing: initial operations
  93. [93]
    Delhi's Signature Bridge: Unsafe, Unwatched, and Deadly - Vygr News
    Jul 16, 2025 · In the span of just one week, Delhi's Signature Bridge witnessed two devastating incidents, Sneha Debnath, a 19-year-old Delhi University ...
  94. [94]
    Mission Delhi Clean-Up 2025: Signature Bridge Reality - YouTube
    Aug 31, 2025 · Mission Delhi Clean-Up 2025: Signature Bridge Reality | Shocking Truth Revealed | Brothers Enfield #delhicleanup #drainclean-up ...Missing: response | Show results with:response
  95. [95]
    'Delhi's Eiffel Tower': Signature Bridge inaugurated amid AAP-BJP ...
    Nov 4, 2018 · Delhi BJP President Manoj Tiwari accused AAP legislator Amanatullah Khan and his party workers of manhandling him at the Signature Bridge ...Missing: criticism | Show results with:criticism<|separator|>
  96. [96]
    Who gets credit for Signature Bridge? - The Hindu
    Nov 3, 2018 · The construction of this 675-metre-long bridge took 15 years and generated a cost of ₹1500 crore which is a matter of shame..it is a very ...
  97. [97]
    Tug-of-war between BJP and AAP over Delhi's iconic Signature Bridge
    Nov 5, 2018 · For the past few days, the Delhi BJP chief Manoj Tiwari had been criticising the Arvind Kejriwal government for not inviting him to the ...Missing: criticism | Show results with:criticism
  98. [98]
    Among names in Signature bridge violence FIR: Kejriwal and Tiwari
    Nov 11, 2018 · The inauguration of the bridge by the Delhi government on November 4 was marred by violence, with Tiwari turning up with supporters and trying ...Missing: criticism | Show results with:criticism
  99. [99]
    Delhi's newest bridge gets deck to deter risky selfie takers
    Nov 12, 2018 · A 154m-high viewing deck is being built and several “selfie points” will be designated to dissuade people from risking their lives for pictures.
  100. [100]
    3405 Reviews for Signature Bridge in Majnu Ka Tilla, Delhi - Justdial
    Rating 4.5 (3,405) Signature Bridge offers a stunning view of the city and is equipped with clean facilities. It`sa budget-friendly option for those looking toMissing: maintenance | Show results with:maintenance
  101. [101]
    Boomerangs, live videos, stripping, hands-free selfies: Delhi's going ...
    Nov 16, 2018 · The Signature Bridge has turned into a fair ground, with people clicking photos and playing music. And if you feel hungry, there's arrangement ...
  102. [102]
    PWD approves six-lane flyover to decongest Outer Ring Road
    Apr 11, 2025 · Officials said that the new 680-metre-long flyover will significantly address congestion and make smooth traffic flow along the Outer Ring ...
  103. [103]
    New flyover coming up to decongest area between Civil Lines and ...
    Apr 12, 2025 · It will help decongest one of North Delhi's busiest intersections. Our goal is to improve travel time, reduce stress on arterial roads, and ...
  104. [104]
    Why Building Bridges May Do More Harm Than Good | Delhi News
    Oct 4, 2025 · "No study has shown that flyovers actually reduce congestion. At best, they shift traffic from one point to another. Simply elevating a ...
  105. [105]
    Take over Signature Bridge: Delhi Tourism dept writes to PWD
    Mar 10, 2025 · “Currently, the flyover is not in a poor condition, it is not filled with potholes or broken surfaces. But it needs daily maintenance like ...
  106. [106]
    PWD now responsible for Signature Bridge's upkeep | Delhi News
    Jun 25, 2025 · The elevated bridge, which was opened for public use in 2018, was constructed by the DTTDC for Rs 1518.37 crore. Citing a lack of funds, the ...
  107. [107]
    River of grief: Suicides in Yamuna highlight gaps in public safety
    Jul 21, 2025 · Signature Bridge: A suicide hotspot​​ On September 24, 2024, the body of Ansh Chaudhary, a 12th-standard student, was recovered near Okhla ...Missing: statistics | Show results with:statistics