Trans Mountain pipeline

The Trans Mountain Pipeline System is a 1,180-kilometre pipeline transporting crude oil and refined petroleum products from Edmonton, Alberta, to Burnaby, British Columbia, with onward connections to refineries in Washington state. Originally constructed in 1953, it has been owned and operated by the Canadian federal government through Trans Mountain Corporation since 2018, following the acquisition from Kinder Morgan for CA$4.5 billion amid regulatory delays and opposition. The system's expanded capacity, achieved through a parallel pipeline twinning completed in 2024, now totals approximately 890,000 barrels per day, tripling prior throughput to facilitate greater export of Canadian heavy oil to international markets. The expansion project, approved in 2016 after initial regulatory hurdles, encountered protracted legal challenges from environmental groups and certain communities citing risks to ecosystems, like the southern resident killer whales, and potential spills from increased tanker traffic. Despite these, federal courts upheld approvals, emphasizing the project's compliance with environmental assessments and its role in economic diversification. Costs escalated dramatically from an initial CA$7.4 billion estimate to over CA$34 billion by completion, attributed to delays, regulatory requirements, and supply chain issues, underscoring challenges in large-scale infrastructure delivery under government stewardship. Economically, the pipeline enhances Canada's energy sector by providing reliable access, mitigating the discount against global benchmarks and bolstering GDP through job creation and fiscal revenues estimated in billions over decades. It reduces reliance on riskier alternatives like for , which has higher spill and safety incidents per volume moved. Operationally, the system maintains a strong safety record, with modern monitoring and integrity programs minimizing environmental incidents relative to transport volumes. While critics highlight climate emissions from expanded production, the infrastructure supports market-driven efficiency in global energy supply without mandating increased output.

Overview

Route, Capacity, and Current Operations

The Trans Mountain Pipeline system originates in Strathcona County near Edmonton, Alberta, and extends approximately 1,150 kilometers westward to Burnaby, British Columbia, primarily following existing rights-of-way through Alberta and British Columbia. The route traverses diverse terrain, including the Rocky Mountains, with 33 active pump stations located along the path to maintain flow, such as facilities near Hinton, Alberta, and Hope, British Columbia. Key intermediate terminals include those at Kamloops and Sumas, British Columbia, facilitating connections to local distribution and the 111-kilometer Trans Mountain Puget Sound pipeline extension to Washington state refineries. The system terminates at the Westridge Marine Terminal in Burnaby, enabling marine loading for exports. The pipeline transports a mix of crude oil—both and heavy grades—and refined products, including , , and , from Edmonton-area supply sources to destinations. Following the 2024 expansion, which twinned much of the original line and added infrastructure, the system's nominal capacity reached 890,000 barrels per day, a near tripling from pre-expansion levels of around 300,000 barrels per day. This includes capacity on Line 1 for approximately 350,000 barrels per day of lighter crudes and refined products directed mainly to and destinations, and Line 2 handling up to 540,000 barrels per day of heavier crudes. Commercial operations of the expanded system commenced on May 1, 2024, significantly alleviating pipeline bottlenecks for Alberta producers by boosting exports to Pacific markets. As of October 2025, the pipeline operates at approximately 80-85% utilization, with total system nominations unapportioned for that month, reflecting strong demand but not yet full loading due to market dynamics and optimization efforts. Volumes have shifted toward balanced light and heavy crude shipments, supporting increased tanker exports from Westridge and deliveries to regional refineries like Parkland in Burnaby. In the first half of 2025, the system generated substantial cash flows, underscoring its role in enhancing Canada's energy infrastructure connectivity.

Ownership, Governance, and Strategic Importance

The Trans Mountain Pipeline is owned by the Government of Canada, which purchased the system from Kinder Morgan Canada Limited in May 2018 for CAD 4.5 billion to prevent its cancellation amid regulatory and opposition challenges. The assets are held through Trans Mountain Corporation (TMC), a wholly owned subsidiary of the Canada Development Investment Corporation (CDEV), functioning as a Crown corporation responsible for operations and maintenance. Although the federal government has stated it does not intend long-term ownership and plans to initiate a divestment process, as of 2025, TMC remains under public control, with the pipeline generating significant returns including an expected CAD 1.25 billion dividend payment to Ottawa in that year due to high utilization and refinancing. Governance of the pipeline falls under TMC's management team, led by President and CEO Dawn Farrell, with oversight from CDEV and compliance with federal regulations. The Canada Energy Regulator (CER) serves as the primary regulatory authority, enforcing 156 binding conditions across the project's lifecycle, covering safety, environmental protection, and Indigenous engagement. These conditions stem from CER's approval processes, including detailed audits and lifecycle transitions from construction to operations, ensuring adherence to standards for pipeline integrity and emergency response. TMC also publishes annual Environmental, Social, and Governance (ESG) reports to detail performance metrics, though critics from organizations like the Institute for Energy Economics and Financial Analysis have questioned the project's financial sustainability despite these frameworks. The pipeline holds strategic importance as Canada's sole oil transport link to the , enabling diversification of export markets beyond the and access to high-demand Asian buyers, which has elevated Western Canadian crude pricing and reduced discount volatility. Post-expansion, it has tripled capacity to approximately 890,000 barrels per day, supporting upstream production growth in Alberta's and contributing over CAD 10 billion in economic value through exports in 2024 alone. By 2025, had become the largest purchaser of its cargoes, underscoring the route's role in global energy trade amid efforts to meet demand for responsibly produced hydrocarbons. This bolsters energy security and fiscal revenues, with proponents arguing it counters geographic constraints on Canadian oil exports that previously limited producer revenues.

Historical Development

Initial Construction and Early Operations (1953–1970s)

The Trans Mountain Pipeline Company was chartered by the on March 21, 1951, authorizing the of a to transport crude oil from to . Ownership was initially divided between Canadian Bechtel Ltd. and of . began in 1952, involving the building of a 1,150-kilometre (718-mile), 24-inch-diameter steel from , , to the Burnaby Terminal near Vancouver, , at a total cost of $93 million. The project required blasting through rocky terrain, draining swamps, and installing initial pumping stations to facilitate flow. Commercial operations commenced on October 17, 1953, with the first shipment of crude oil arriving at the Terminal, marking the initial delivery of oil to the . The pipeline's original capacity was 150,000 barrels per day, supported by four pump stations along the route, enabling transport primarily of light crude for local refineries and marine export via tankers from Vancouver-area facilities. In response to rising demand from Alberta's expanding oil production, the first capacity expansion occurred in 1957, adding a 160-kilometre to boost throughput. Subsequent upgrades through the and included further looping segments, additional pumping capacity, and modifications to handle varying crude qualities, gradually increasing system capacity while maintaining safe operations amid growing regional energy needs. These enhancements reflected the pipeline's role in linking inland oil fields to coastal markets, with annual volumes rising steadily to support economic development in .

Product Shifts, Capacity Adjustments, and Pre-Expansion Era (1980s–2010s)

In the , the Trans Mountain Pipeline underwent modifications to enable batching, allowing the transport of refined products alongside crude in the same line, which improved efficiency and competitiveness compared to single-product operations. This shift diversified the pipeline's product mix from primarily crude to include semi-refined products, , methyl tert-butyl ether (MTBE), and heavy crude derived from Alberta's resources, with regular heavy crude tanker shipments from the Westridge Marine Terminal commencing in 1986. By the late , proposals emerged to expand capacity by approximately 56,000 barrels per day (bpd) to accommodate growing exports of MTBE and heavy crude. Capacity adjustments during this period addressed fluctuating demand and operational needs, building on prior expansions that had reached a historical maximum throughput of 410,000 by 1973. Daily average deliveries averaged around 300,000 barrels in 1980, rising to approximately 350,000 by 1990 amid rebounding throughput after a decline in the and early that had dipped below 200,000 due to export restrictions and reduced demand. From 1992 to 2010, throughput increased further, averaging above 200,000 and reaching about 400,000 by 2010, reflecting stronger heavy crude exports and refined product demand. A notable infrastructure upgrade occurred in 2008 with the completion of the Anchor Loop Project, which added a 158-kilometer pipeline loop between Hinton, Alberta, and Hargreaves, British Columbia, enhancing reliability and supporting higher volumes without altering the nominal system capacity, which stabilized at around 300,000 bpd heading into the pre-expansion era. These adjustments maintained the pipeline's role in supplying crude oil and refined products to British Columbia refineries, Washington state markets, and export terminals, amid periodic operational challenges like variable tanker loadings from Westridge, which were sporadic from 1954 to 1982 but became consistent thereafter.

Pre-TMX Spill Incidents and Safety Responses

The original Trans Mountain Pipeline, operational since 1953, experienced approximately 81 liquid spills from 1961 to 2013, averaging 1.53 incidents per year, according to an analysis of regulatory data. Trans Mountain's own reporting indicates around 85 spills over the same period under Canada Energy Regulator (CER) oversight, with most involving small volumes but highlighting risks from , third-party damage, and equipment failure on the aging . These incidents prompted regulatory notifications, containment efforts, and , though critics have questioned the adequacy of preventive measures given the pipeline's age exceeding 50 years by the . One of the largest pre-expansion spills occurred on January 14, 1985, at an Edmonton-area tank farm, releasing nearly 10,000 barrels of crude oil due to a tank overfill and valve failure. Response involved immediate shutdown, recovery of spilled oil, and soil remediation, with the National Energy Board (NEB, CER predecessor) conducting post-incident audits that led to enhanced tank farm safety protocols, including improved overfill protection systems. In 2005, a spill of 210,000 liters occurred, followed by 250,000 liters in 2007 at the Wahleach pump station from rupture, attributed to internal ; cleanup included monitoring and affected removal, with NEB-mandated hydrostatic testing on segments to verify integrity. By 2011, a detected leak on the 60-year-old line near Merritt, British Columbia, prompted the NEB to order a pressure reduction from 8,850 kPa to 6,550 kPa across 18 pipeline segments to mitigate rupture risk, alongside accelerated inline inspections using smart pigs for defect detection. Kinder Morgan, the operator at the time, responded by implementing a comprehensive integrity management program, including cathodic protection upgrades and regular condition assessments, as required under NEB's Onshore Pipeline Regulations. These measures aimed to address systemic issues like external corrosion and coating degradation, though the NEB's 2012 spill history review emphasized ongoing vigilance due to the pipeline's exposure to geohazards such as landslides. Overall, pre-TMX responses focused on reactive containment and proactive integrity digs, reducing spill frequency in later years but not eliminating risks inherent to unexpanded, high-pressure crude transport.

Trans Mountain Expansion Project (TMX)

Project Rationale, Proposal, and Initial Planning (2012–2016)

The Trans Mountain Expansion Project (TMX) was proposed to address capacity constraints on the existing Trans Mountain Pipeline system, which transported approximately 300,000 barrels per day (bpd) of crude oil and refined products from , , to , . Rapid growth in 's production during the early outpaced the pipeline's ability to deliver volumes to markets, resulting in transportation bottlenecks and persistent price discounts for crude relative to benchmarks like . Canada, the pipeline's owner at the time, identified the need for expansion to enable greater export access to international markets, particularly , where demand for heavy oil could yield higher netbacks for producers. In May 2012, announced the TMX project, planning to construct a parallel loop alongside approximately 980 kilometers of the existing route to nearly triple system capacity to 890,000 . The proposal included adding new pumping stations, tankage at terminals in and , and reactivating a mothballed , with an estimated initial cost of around $5.4 billion. This expansion aimed to secure long-term shipping commitments from oil producers, who had expressed demand for additional westbound capacity through prior open seasons conducted by the company. Initial planning from 2012 to 2013 involved engineering feasibility studies, preliminary environmental and routing assessments, and finalizing shipper agreements, which increased the targeted capacity from an initial 750,000 to 890,000 by January 2013. On December 16, 2013, formally filed a comprehensive application with the National Energy Board (NEB), including detailed project descriptions, economic analyses, and initial environmental impact assessments, marking the transition to formal regulatory review. Throughout 2014 to 2016, early planning phases encompassed stakeholder consultations, indigenous engagement protocols, and data collection for the NEB's environmental assessment, though these efforts began encountering opposition from environmental advocates and some municipalities concerned over potential spill risks and tanker traffic increases. In May 2016, the National Energy Board (NEB) issued a report recommending conditional approval of the Trans Mountain Expansion Project, subject to 157 conditions aimed at mitigating environmental and safety risks, following a review that included public hearings and intervenor submissions. On November 29, 2016, the federal cabinet, under , approved the project via P.C. 2016-1069, directing the NEB to implement the conditions, which encompassed enhanced marine spill response, pipeline integrity measures, and Aboriginal engagement protocols. This approval faced immediate scrutiny from environmental non-governmental organizations (ENGOs) and certain groups, who argued that the NEB process inadequately addressed upstream , marine ecosystem impacts, and consultation duties under section 35 of the Constitution Act, 1982. Legal challenges proliferated post-approval, with 17 judicial reviews filed in the Federal Court of Appeal contesting the NEB's assessment and cabinet's decision. On August 30, 2018, the Court quashed the 2016 approval in Tsleil-Waututh Nation v. , ruling that the Crown's consultation with affected was inadequate and constitutionally deficient, though it did not find flaws in the substantive environmental review; the matter was remitted for reconsideration without overturning the project's certificate outright. Concurrently, regulatory opposition in , including provincial legislation attempting to restrict heavy oil transport, contributed to Kinder Morgan's May 2018 suspension of non-essential expansion activities, citing political and legal uncertainties that threatened investor confidence. In response, the federal government intervened decisively on May 29, 2018, agreeing to acquire Kinder Morgan's Trans Mountain assets—including the existing pipeline, expansion project, and terminals—for C$4.5 billion, forming Trans Mountain Corporation as a Crown entity to oversee completion and mitigate risks of project abandonment. Following the court's directive, the NEB conducted a targeted reconsideration in 2018–2019, incorporating additional evidence on marine shipping impacts and emissions, ultimately recommending re-approval with 156 conditions. The cabinet re-approved the project on June 18, 2019, via Order in Council P.C. 2019-854, affirming its economic necessity for diversifying Canadian oil exports amid constrained market access. Further appeals ensued, but on February 4, 2020, the Federal Court of Appeal dismissed challenges from First Nations, ENGOs, and British Columbia, upholding the re-approval as reasonable and constitutionally compliant after enhanced consultations. This sequence underscored tensions between federal jurisdiction over interprovincial pipelines under section 92(10) of the Constitution Act, 1867, and provincial, Indigenous, and environmental claims, with critics attributing delays to activist litigation often funded by U.S.-based interests opposing fossil fuel development.

Construction Timeline, Delays, and Cost Escalations (2020–2024)

Construction of the Trans Mountain (TMX) proceeded amid significant challenges from 2020 onward, following the resumption of work in late 2019 after regulatory approvals. In December 2020, Trans Mountain suspended non-essential construction activities until January 4, 2021, primarily due to restrictions and public health measures in , which disrupted workforce mobilization and logistics. This pause contributed to broader schedule slippage, as the project had already been delayed from earlier targets, with ongoing work focusing on segments, pump stations, and tank farms across and . By mid-2021, construction ramped up again, but persistent pandemic-related supply chain disruptions, labor shortages, and enhanced safety protocols—implemented in response to regulatory demands—further impeded progress. Cost estimates for TMX escalated sharply during this period, reflecting the cumulative impact of delays and scope changes under federal government ownership. In 2020, the projected stood at $12.6 billion, incorporating prior expenditures and anticipated overruns from initial private-sector estimates of around $7.4 billion. By February 2022, Trans Mountain revised this to $21.4 billion, attributing the $8.8 billion increase to factors including regulatory-mandated design modifications for safety and , consultations, and inflation-driven material costs, though critics pointed to inefficiencies in government-managed execution as a primary driver. The Parliamentary Budget Officer noted that these hikes included contingency buffers exhausted by unforeseen issues, with the federal acquisition price of $4.5 billion in 2018 serving as a baseline that masked escalating capital outlays. Further delays emerged in 2022–2023 from environmental and regulatory hurdles, including British Columbia's 2021 floods that damaged segments in the and required rerouting, as well as disputes over horizontal routes to minimize ecological disruption. In August 2023, the project reached 80% completion, but the Energy Regulator's December 2023 denial of a variance for pipeline routing threatened additional months of delay, prompting Trans Mountain to pursue alternative paths amid pressure from shippers facing constrained . Technical challenges, such as installing pipeline in geotechnically complex areas like the , compounded these issues, with labor shortages and global bottlenecks—exacerbated by the —adding to timeline pressures. Despite these, construction advanced, achieving key progress in reactivating existing line segments and building new facilities. By early 2024, TMX neared completion, with the "Golden Weld"—connecting the final pipeline segment—performed on April 11 near the Mountain 3 Horizontal Directional Drill site in British Columbia's . First oil was loaded into Line 2 from the Terminal on April 16, followed by mechanical completion on April 30 after the final Energy Regulator approval confirming operational readiness. Cost estimates culminated at $34.2 billion by late 2024, a $12.8 billion rise from the 2020 figure, driven by the prolonged construction phase, additional compliance measures, and economic factors like interest expenses on government loans, though official analyses emphasized the necessity of these expenditures to meet stringent safety standards amid opposition-fueled scrutiny. The overruns highlighted systemic risks in large-scale under , where regulatory and legal frictions—often rooted in environmental —prolonged timelines without proportionally mitigating hazards, as evidenced by the project's adherence to enhanced monitoring protocols throughout.

Commissioning, 2024 Startup, and Post-Operational Developments (2024–2025)

The Canada Energy Regulator issued final authorization for the Trans Mountain Expansion Project to commence operations on April 30, 2024, following completion of construction and verification of compliance with regulatory conditions. Commercial operations of the expanded system, increasing capacity from approximately 300,000 barrels per day (bpd) to 890,000 bpd, began on , 2024, marking the end of over a decade of planning, legal challenges, and construction delays. Initial oil flows ramped up gradually, with the pipeline facilitating increased exports via the Westridge Marine Terminal in , , where an average of 23 vessels departed monthly from June 2024 to July 2025. Post-startup, the pipeline has operated below initial utilization forecasts, reaching about 84% capacity by mid-2025 amid disputes over shipping tolls, which have deterred some shippers and prompted negotiations between Trans Mountain Corporation and producers. Trans Mountain lowered shipment projections for 2025–2027, citing slower-than-expected volume growth, though the has contributed to higher overall Canadian crude production and pipeline movements, with March 2025 volumes reaching 2,797,999 cubic meters. In October 2025, the Environmental Assessment Office proposed fines totaling $292,000 against Trans Mountain for alleged violations during a 2024 rainstorm, including inadequate responses at watercourse crossings, damaged fencing, and a minor spill, though no major operational disruptions or large-scale incidents have been reported since startup. Regarding ownership, the Canadian federal government, which acquired the pipeline for $4.7 billion in 2018 and funded the $34 billion , has reiterated plans to divest the asset but faces challenges including the toll dispute and financial pressures from cost overruns. Trans Mountain's CEO advised against a rushed sale in June , arguing for time to stabilize operations and maximize value recovery, potentially through further optimizations like the Salmon River Replacement Project slated for construction in Q2 and broader capacity enhancements targeting 200,000–300,000 additional bpd via existing corridor modifications. An "open season" for additional capacity commitments was planned for late , reflecting expectations of rising production despite critiques of ongoing subsidies and fiscal risks.

Technical Specifications

Pipeline Infrastructure and Capacity Enhancements

The Trans Mountain pipeline system comprises approximately 1,180 kilometres of pipeline transporting crude oil and refined petroleum products from , , to , . The original pipeline, constructed in 1953, primarily utilized 24-inch and supported a nominal of around 300,000 barrels per day (). Capacity enhancements under the Trans Mountain Expansion (TMX) project, completed in 2024, involved constructing a parallel pipeline segment of 980 kilometres using 36-inch and 42-inch , alongside reactivating 193 kilometres of existing . This upgrade tripled the system's overall to 890,000 by accommodating higher flow rates through increased and enhanced propulsion. To achieve the expanded throughput, TMX incorporated 12 new pump stations along the route, with 11 dedicated to the new pipeline and one added to the existing line, boosting hydraulic capacity via additional electrically powered pumps. These stations, spaced according to terrain and pipe specifications, maintain product flow against elevation changes and friction losses, with the total system now featuring over 30 pump stations. Terminal facilities at Edmonton, Sumas, and Burnaby were also upgraded, including the addition of 19 new storage tanks at the Burnaby terminal and expanded tanker loading infrastructure at the Westridge Marine Terminal to handle increased volumes for export via Pacific Coast tankers. The infrastructure enhancements prioritize steel pipe sourced to 5L standards, with wall thicknesses designed for operating pressures up to 9,930 kPa at select stations, ensuring integrity across varied terrains including the . These modifications not only elevate capacity but also integrate advanced monitoring for and flow optimization, though actual throughput remains subject to market demand and contractual commitments, currently operating below full levels.

Safety Features, Monitoring, and Associated Facilities

The Trans Mountain system incorporates multiple safety features designed to mitigate risks of leaks and spills, including enhanced specifications for the Expansion Project (TMX). The TMX utilizes thicker wall thicknesses compared to the original Line 1, ranging from 0.625 to 1.000 inches for new segments, which improves structural integrity and resistance to external damage. Additionally, the system features an increased number of remotely operable valves—approximately doubling from the original—to enable faster sectional shutdowns, thereby reducing potential spill volumes in the event of a rupture. These valves are strategically placed along the route, with automatic and manual activation capabilities integrated into control systems. Monitoring relies on a combination of real-time supervisory control and data acquisition () systems and advanced technologies. The network continuously tracks key parameters such as flow rates, pressure, temperature, and product density across the 1,150-kilometer system, allowing operators at the 24/7 Control Centre to remotely adjust pumps and valves. algorithms compare actual data against theoretical models, flagging anomalies that could indicate a , with two independent systems deployed on both Line 1 and TMX for . In October 2024, Trans Mountain implemented a high-fidelity distributed sensing (HDS) system using fiber-optic cables, which detects leaks, ground movements, and third-party encroachments with sub-kilometer precision, complementing through continuous acoustic and thermal monitoring. This 10-year agreement with Hifi Engineering enhances early warning capabilities, particularly in high-risk areas like river crossings. Associated facilities support operational safety through strategic infrastructure for pressure management and product handling. The system includes 12 new pump stations added via TMX—11 along the new Line 2 and one upgraded on Line 1—to maintain flow without excessive pressures that could strain the pipeline. Pump stations are equipped with automated shutdown features tied to SCADA alarms for overpressure or leak events. Terminals at Edmonton (origin with main control centre), Sumas, and Burnaby's Westridge Marine Terminal include 19 new storage tanks and three expanded berths for tanker loading, each with secondary containment, fire suppression, and spill response equipment to contain any releases at endpoints. These facilities undergo regular integrity assessments under Canada Energy Regulator oversight, integrating with the overall monitoring framework to ensure compliance with federal safety standards.

Economic Impacts

Enhancements to Energy Security, Exports, and Market Access

The Trans Mountain Expansion Project (TMX), operational since May 2024, triples the pipeline's capacity from 300,000 barrels per day (bpd) to approximately 890,000 bpd, adding 590,000 bpd of export capacity to the Pacific Coast. This expansion eases longstanding pipeline constraints in Western Canada, enabling greater volumes of crude oil from Alberta's oil sands to reach tidewater for international shipment. By providing direct access to global markets via the Westridge Marine Terminal in Burnaby, British Columbia, TMX boosts Canada's ability to export to high-demand regions in Asia and beyond, reducing the historical discount of Western Canadian Select (WCS) crude relative to benchmark prices like West Texas Intermediate (WTI). TMX has markedly increased marine exports, with approximately 75% of the post-startup rise in Canadian crude exports transported by tanker rather than or other means. This shift has diversified destination markets, elevating the share of non-U.S. exports and positioning as the pipeline's largest buyer by mid-2025, surpassing the . The enhanced export capacity—representing a roughly 700% increase to tidewater—has generated an estimated $12.6 billion in additional revenue for through higher volumes and improved pricing since May 2024. In terms of , TMX mitigates risks from over-reliance on U.S.-bound pipelines by offering alternative export routes amid geopolitical uncertainties or market volatility. The project's completion strengthens national resilience by enabling to respond flexibly to global demand shifts, supporting stable energy supplies and economic returns without depending solely on continental markets. This diversification has also spurred upstream production expansions in the , ensuring sustained resource development aligned with opportunities.

Job Creation, GDP Contributions, and Fiscal Returns

The phase of the Trans Mountain Expansion Project (TMX), spanning 2018 to 2023, generated 67,423 person-year (FTE) jobs across , including 37,756 in and 8,554 in . These figures encompass direct employment, indirect roles, and induced effects from worker spending, based on an economic impact assessment using input-output modeling. Peak on-site employment reached approximately 5,500 workers in and combined. This activity contributed $26.3 billion to 's (GDP) during the period, with associated government revenues of $2.9 billion from federal, provincial, and municipal taxes. Post-commissioning operations, beginning in May , are projected to sustain 36,066 person-year FTE jobs over the 2024–2043 period, with 20,203 in and 8,959 in . Direct operational roles for the pipeline itself remain limited, estimated at around 90 permanent positions across and . The expanded system's ongoing contributions include $9.2 billion in GDP and $2.8 billion in tax revenues over the same 20-year horizon, derived from pipeline operations and related economic multipliers. In its first year of full operations through mid-2025, the TMX facilitated $13.6 billion in additional economic revenue, including $2.0 billion in heightened fiscal gains, primarily through increased export values and narrowed price differentials for Canadian producers. Fiscal returns extend beyond direct taxes to include repayments to the federal government as owner of Trans Mountain Corporation. In 2025, the corporation anticipates returning $1.25 billion to federal coffers via dividends, supported by elevated crude shipments averaging 600,000 barrels per day. Broader induced effects, such as enhanced producer revenues from improved , have generated an estimated $12.6 billion in new oilpatch income since startup, amplifying provincial royalties—particularly in —and federal corporate taxes. These outcomes reflect causal links from expanded capacity to higher throughput, though projections assume stable global demand and no major disruptions; actual realizations depend on oil prices and volumes, with early data showing GDP uplift in the sector averaging 8.5% year-over-year post-May 2024.

Financial Costs, Overruns, and Critiques of Government Involvement

The Trans Mountain Expansion (TMX) project, initially estimated by at $5.4 billion CAD in 2013, saw costs rise to $6.8 billion by 2015 and $7.4 billion by 2017 due to updated and regulatory requirements. In May 2018, following 's withdrawal amid legal and activist opposition, the purchased the existing pipeline assets and the expansion project for $4.5 billion CAD to prevent cancellation and facilitate construction. Under federal ownership via Trans Mountain Corporation, total capital expenditures escalated dramatically, reaching approximately $34 billion CAD by completion in 2024, representing over sixfold the initial private-sector estimate.
YearCost Estimate (CAD billions)Notes
20135.4 initial proposal.
20156.8Revised due to scope changes.
20177.4Final pre-purchase update.
20184.5 (purchase) + expansionGovernment acquisition.
202434.0Total upon mechanical completion.
Primary drivers of overruns included construction delays from terrain challenges in , labor shortages, supply chain disruptions exacerbated by the , and additional regulatory conditions imposed post-approval, such as enhanced environmental mitigation measures. The Parliamentary Budget Officer estimated in November 2024 that the pipeline's value stands at $29.6 billion to $33.4 billion CAD, depending on tolling models, implying potential taxpayer losses upon divestiture if market conditions do not support full recovery. Critiques of government involvement center on the substitution of private-sector discipline with public-sector inefficiencies, leading to unchecked spending without equivalent commercial incentives for cost control. The has argued that the $34 billion total exemplifies broader patterns of government-led infrastructure projects suffering from overruns and delays, as political priorities—such as navigating consultations and environmental litigation—prioritize compliance over efficiency, ultimately burdening taxpayers with a project that private entities deemed unviable under prevailing risks. Economists and policy analysts, including those from the Taxpayers Federation, have highlighted that the federal purchase and subsequent funding commitments, totaling over $30 billion in public outlays by 2024, represent an implicit to oil producers via below-market tolls, distorting markets and exposing fiscal resources to commercial uncertainties like fluctuating global oil prices. While proponents cite in export diversification, detractors contend the intervention amplified pre-existing risks from regulatory uncertainty, with empirical evidence from the cost trajectory underscoring the challenges of state-directed megaprojects in competitive sectors.

Environmental and Safety Record

Comprehensive Spill History and Incident Analysis

The Trans Mountain pipeline system has recorded approximately 85 spills since mandatory reporting to the Canada Energy Regulator (CER) commenced in 1961, with volumes ranging from minor releases below the 1.5 cubic metre threshold to larger incidents exceeding it. Of these, roughly 70% occurred at pump stations or terminals, where containment measures typically limited environmental spread, while 30%—about 25 incidents—took place along the pipeline right-of-way, including 21 crude oil releases. Only 13 pipeline spills surpassed 1.5 m³ in volume, with four recorded in the three decades prior to 2012; subsequent years have seen primarily small facility leaks rather than significant line ruptures. Major pipeline spills have predominantly resulted from external factors such as third-party or , rather than internal or material defects, reflecting the system's exposure to urban and construction-adjacent routing. The 1966 Alberta rupture released 1,110 m³ of crude due to , marking one of the earliest large-volume events. In 1977, a similar incident spilled 1,031.7 m³. The 1985 event, though often cited in facility contexts, involved -adjacent release of approximately 1,158 m³ at the terminal from a overfill and issue. The most notable recent spill occurred on July 24, 2007, at the Westridge delivery point in , , where a third-party contractor's ruptured the line, releasing 224 m³ of heavy ; 95% was recovered, but 5.5 m³ entered , prompting evacuation of 225 residents and shoreline cleanup along 15 km.
DateLocationVolume (m³)CauseKey Outcomes
April 29, 1966 (pipeline)1,110Pipeline ruptureSignificant crude release; early regulatory response limited data on long-term effects.
1977Pipeline right-of-way1,031.7Undisclosed failureOne of three largest by volume; contributed to enhanced integrity management protocols.
1985 terminal/pipeline interface~1,158Tank overfill and valve malfunctionLargest recorded volume overall; mostly contained at facility but highlighted operational risks.
July 24, 2007Westridge, , BC224Third-party backhoe damagePartial marine release; led to Pipeline Protection Group formation and increased surveillance.
Analysis of incidents reveals a downward trend in both frequency and severity of spills post-1980s, attributable to improved , hydrostatic testing, and right-of-way patrolling, with no major line ruptures since . Third-party activities account for a disproportionate share of , as in the 2007 case, underscoring vulnerabilities from co-location with rather than inherent pipeline flaws. Facility spills, while more numerous, benefit from secondary , reducing off-site impacts; for instance, the June 12, 2020, leak at Sumas Pump Station involved a 1-inch tubing releasing a small of crude, contained without waterway entry. CER oversight and post-incident have driven modifications, such as advanced management verified in 2024, though critics note persistent risks from aging in populated areas. Overall, the system's spill rate compares favorably to or tanker alternatives when adjusted for transported, with empirical showing pipelines spill less per barrel-mile than other modes.

TMX-Specific Environmental Protections and Assessments

The Trans Mountain Expansion (TMX) project was subject to a comprehensive environmental assessment conducted by the National Energy Board (NEB, now the Energy Regulator or CER) under the National Energy Board Act and the Canadian Environmental Assessment Act, 2012 (CEAA 2012), beginning with the application filing in December 2013. The assessment included biophysical and socio-economic studies evaluating potential impacts from construction, operations, and accidents, with baseline data derived from field studies conducted along the pipeline corridor in 2012–2013 and filed with the NEB in late 2013. The NEB's initial 2016 report concluded that the project was unlikely to cause significant adverse environmental effects if mitigation measures were implemented, though a 2019 reconsideration report identified significant adverse effects from increased marine shipping on Southern resident killer whales and cultural use, as well as from vessels. Approval by the Governor in Council in 2019 imposed 157 binding conditions on Trans Mountain Pipeline ULC to address environmental protection, emergency response, and monitoring. TMX-specific environmental protection plans, updated and submitted to the CER in August 2018, outline mitigation strategies tailored to the expansion's route and facilities, including construction environmental protection plans, operations and maintenance plans, and emergency response plans. These plans address contamination identification and to prevent spills (under Condition 46), with enhanced systems, hydrostatic testing of pipeline segments, and thicker pipe walls (up to 0.625 inches in high-risk areas) compared to the original line. Spill prevention is further supported by site-specific risk assessments and a commitment to comply with spill response standards, including rapid deployment capabilities for potential releases in terrestrial and marine environments. Wildlife and habitat protections focus on species at risk and sensitive ecosystems, with Condition 44 requiring mitigation plans for 11 such species, including , Oregon spotted frog, and grizzly bears, alongside targeted measures for caribou, spotted owls, and old-growth forests (Condition 76). Habitat mitigation includes wetland protection and restoration protocols (Condition 41), grassland management (Condition 42), and revegetation using to restore disturbed areas post-construction. Fisheries protections involve monitoring during construction crossings (Condition 72) and an inventory of watercourse crossings to minimize impacts on fish habitats. Marine-specific assessments addressed tanker traffic increases, leading to 16 additional CER recommendations in 2019 for government implementation, such as enhanced marine mammal protection programs focusing on killer whales, including noise reduction and vessel strike avoidance. These include requirements for Trans Mountain to file a Marine Mammal Protection Program at least three months before operations commence, emphasizing monitoring and adaptive management for underwater noise and disturbance. Overall compliance is overseen by the CER, with ongoing audits ensuring adherence to conditions, though critics note that marine shipping effects remain significant despite mitigations.

Risk Comparisons with Alternative Transport Methods

Empirical assessments of oil transportation safety indicate that pipelines generally pose lower risks of spills and accidents per unit of volume transported compared to or alternatives. A study examining Canadian data from 2000 to 2013 found that pipelines spilled 4.5 times less per million barrel-kilometres than , with transport exhibiting even higher incident rates due to frequent minor leaks and collisions. Similarly, U.S. Pipeline and Hazardous Materials Safety Administration (PHMSA) data analyzed in peer-reviewed economic modeling estimates the cost of spills and accidents at $62 per million barrel-miles for pipelines versus $381 for , reflecting both lower frequency and severity when normalized for and volume. Truck transport fares worse, with spill rates averaging 20 incidents per billion ton-miles, compared to 2 for and 0.6 for pipelines, as reported in industry safety compilations.
Transport ModeSpills per Billion Ton-MilesRelative Cost of Incidents per Million Barrel-Miles
0.6$62
2$381
20Higher (not quantified in same metric)
While some analyses, such as a 2015 report commissioned by the , claim comparable safety records between pipelines and based on occurrence rates per million barrels (0.049 for pipelines versus 0.227 for from 2005-2014 U.S. data), these metrics often underweight spill volumes and consequences, where pipelines demonstrate superior containment due to fixed and automated shutoff systems. incidents, like the 2013 Lac-Mégantic derailment in that killed 47 people and spilled 5.7 million litres of crude, highlight higher potential for catastrophic fires and explosions from dynamic movement, whereas pipeline ruptures, though capable of large releases, average smaller total volumes per ton-mile over time. Truck transport amplifies risks through vulnerabilities, with data showing elevated fatality rates from collisions and higher environmental exposure from dispersed routes. For the Trans Mountain system, oversight emphasizes pipeline-specific mitigations like integrity management programs, which contribute to a 99.999% safe delivery rate for crude between 2011 and 2013, outperforming alternatives without equivalent stationary monitoring. Alternatives like would necessitate expanded track capacity through sensitive terrains, potentially increasing probabilities, while tankers for export introduce collision and grounding risks not inherent to land-based pipelines. Overall, first-principles evaluation of causal factors—such as gravitational stability, leak detection efficacy, and exposure—favors pipelines for minimizing both probabilistic spill likelihood and downstream ecological damage per barrel transported.

Controversies and Stakeholder Perspectives

Political Debates and Interprovincial Tensions

The Trans Mountain pipeline expansion project became a flashpoint for political contention in , highlighting divisions between resource-dependent provinces favoring economic growth and coastal provinces prioritizing environmental safeguards. Alberta's political leadership, including Premier Rachel Notley's NDP government (2015–2019), strongly advocated for the project as essential for diversifying export markets beyond the and mitigating price discounts on heavy oil, arguing it would generate substantial revenue and jobs. In contrast, British Columbia's governments expressed opposition rooted in concerns over potential spills in the and inadequate risk mitigation, with Premier Christy Clark's administration (2011–2017) conditioning support on five specific requirements announced in May 2015, such as world-leading spill response systems and fiscal benefits for the province. Interprovincial frictions intensified after British Columbia's 2017 shift to an NDP-Green coalition under Premier , which rejected the project outright and pursued regulatory delays through provincial environmental assessments and permit denials. Alberta responded aggressively, with Premier Jason Kenney's government (2019–2022) launching constitutional challenges and invoking federal paramountcy over interprovincial trade, framing BC's actions as an existential threat to western economic viability and national unity. These tensions manifested in legal battles, including Alberta's 2019 lawsuit against BC's Bill 51—legislation passed in May 2018 to restrict increased heavy oil flows—which the struck down in January 2020, affirming exclusive federal jurisdiction over interprovincial pipelines under sections 91 and 92 of the Constitution Act, 1867. The federal Liberal government under Prime Minister intervened decisively on May 29, 2018, acquiring the existing pipeline and expansion rights from for C$4.5 billion after the company suspended non-essential activities in April 2018, citing regulatory uncertainty and protests as eroding commercial feasibility. This purchase, justified by as safeguarding amid threats of Alberta economic isolation, drew criticism from fiscal conservatives for exposing taxpayers to overruns—ultimately exceeding C$30 billion—and from provincial sovereigntists who viewed it as central overreach. BC Premier , as of October 2025, continues to resist similar Alberta-proposed pipelines, underscoring persistent jurisdictional clashes despite the Trans Mountain expansion achieving mechanical completion in 2023 and initial operations in 2024.

Indigenous Consultations, Rights Claims, and Diverse Viewpoints

The Canadian Crown's constitutional duty to consult and, where appropriate, accommodate Indigenous peoples arises when Crown actions may adversely affect established or potential Aboriginal or treaty rights, as affirmed by the Supreme Court in Haida Nation v. British Columbia (2004). For the Trans Mountain Expansion (TMX) project, initial consultations occurred through the National Energy Board (NEB) regulatory process starting in 2013, involving over 130 Indigenous groups across Treaty 6 and Treaty 8 territories in Alberta and traditional territories in British Columbia. In August 2018, the Federal Court of Appeal quashed the federal approval partly on grounds of inadequate consultation with affected First Nations, such as the Tsleil-Waututh and Squamish Nations, which claimed the process failed to meaningfully address risks to their asserted rights, including fishing and cultural practices. The government conducted a second phase of consultations from 2018 to 2019, leading to project modifications and additional benefit agreements; the Federal Court of Appeal upheld the re-approval in February 2020, ruling that the duty to consult does not grant Indigenous groups veto power over development. Trans Mountain Corporation signed 43 benefit agreements with groups by April 2018, including 33 in , providing for capacity funding, employment, and opportunities; by mid-2021, this expanded to 66 agreements involving 73 groups, with some securing stakes offering ongoing shares projected to generate hundreds of millions in economic benefits. Proponents among signatory nations, such as the First Nation, emphasize these arrangements as enabling via resource for community , , and diversification from , with one analysis estimating up to $1.2 billion in value across similar projects. In March 2024, Trans Mountain and partners formalized a joint monitoring agreement with the to enhance oversight of environmental and cultural impacts. Opposing Indigenous viewpoints center on claims of unresolved title, inadequate accommodation of environmental risks, and procedural deficiencies, often invoking the United Nations Declaration on the Rights of Indigenous Peoples (UNDRIP) for —stronger than Canada's duty-to-consult standard. The Tsleil-Waututh Nation, for instance, pursued arguing TMX infringed section 35 without sufficient mitigation for loss, though courts dismissed these post-reconsultation. In May 2024, the Stk'emlupsemc te Secwepemc Nation escalated claims in British Columbia's interior after construction disturbed an ancestral village site containing over 50 human remains, alleging failure to protect sacred grounds despite prior notifications. Critics, including some hereditary chiefs and alliances like the against TMX, frame the project as perpetuating colonial resource extraction without veto-equivalent consent, leading to blockades and injunction challenges, though federal courts have prioritized through economic over halting development. These divisions underscore empirical variances: supportive groups report tangible fiscal returns exceeding $600 million in contracts by 2019, while opponents highlight unmitigated spill risks to unceded territories, with no uniform consensus despite media emphasis on dissent. Activist opposition to the Trans Mountain pipeline expansion primarily centered on environmental risks, potential oil spills, and impacts on lands and , leading to widespread protests and legal efforts to halt . In November 2014, over 100 and environmental protesters were arrested during blockades on Burnaby Mountain in to prevent preliminary surveys for the project. These actions involved camping in areas and chaining to , drawing comparisons to broader anti-pipeline movements. Civil disobedience escalated in subsequent years, with notable events including a September 9, 2017, rally in where demonstrators demanded consent from affected . On March 23, 2018, Leader and NDP MP Kennedy Stewart were arrested at a protest site opposing the expansion. The Secwépemc-led Tiny House Warriors employed a strategy of constructing portable tiny homes along the pipeline route starting around 2018, aiming to physically block construction sites and assert Indigenous jurisdiction; this led to confrontations, including rock-throwing incidents in September 2021 and subsequent convictions for assault and mischief in June 2024. Opposition strategies also encompassed political alliances, such as the May 2017 coalition between British Columbia's NDP and Green parties, which pledged to exhaust all legal and regulatory tools to stop the project. Environmental organizations like Ecojustice pursued litigation focused on threats to endangered Southern Resident killer whales from increased tanker traffic. Legal challenges peaked in August 2018 when the Federal Court of Appeal quashed the federal approval, determining that consultations with affected had been inadequate despite extensive engagement. After further consultations, the government re-approved the in June 2019 subject to 156 conditions. Subsequent appeals by and environmental groups were dismissed by the Court on February 4, 2020, which ruled the consultations reasonable and meaningful, emphasizing that 120 of 129 affected groups supported or did not oppose the expansion and that power does not exist under Canadian . Courts repeatedly granted injunctions against protesters to enable , resulting in over 300 arrests across related actions since 2013. Despite these efforts, no legal challenges succeeded in permanently blocking the after the 2020 ruling.

References

  1. [1]
    About Us - Trans Mountain
    We have the capacity to deliver approximately 890,000 barrels of petroleum products each day through a pipeline system of more than 1,180 kilometres of pipeline ...
  2. [2]
    Canada's Trans Mountain Pipeline expansion reportedly 95 ... - EIA
    Jan 8, 2024 · The Canadian government acquired the pipeline from Kinder Morgan for CA $4.5 billion in 2018 and formed the Trans Mountain Corporation (TMC) to ...
  3. [3]
    Trans Mountain Expansion Project - Canada.ca
    Mar 23, 2025 · The Trans Mountain Expansion Project (TMX) involved the construction (or twinning) of a second pipeline along the route of the existing Trans Mountain pipeline.Missing: capacity | Show results with:capacity
  4. [4]
    Challenging the Trans Mountain Pipeline Expansion - Ecojustice
    The Trans Mountain pipeline project and associated tanker traffic pose a significant threat to the future of endangered Southern Resident killer whales.<|separator|>
  5. [5]
    Trans Mountain Pipeline Expansion Clears Major Legal Hurdle - NPR
    Feb 5, 2020 · "The city remains of the view that the Trans Mountain pipeline project would have significant environmental impacts, including the unacceptable ...
  6. [6]
    Trans Mountain Pipeline – 2024 Report - Parliamentary Budget Officer
    Nov 8, 2024 · the total project cost estimate for the TMEP increased from $21.4 billion to $34.2 billion.
  7. [7]
    Trans Mountain pipeline's soaring cost provides more proof of ...
    Mar 20, 2024 · Since the government purchased the project for $4.5 billion, the cost of the Trans Mountain expansion has ballooned to $34 billion.
  8. [8]
    Trevor Tombe: The Trans Mountain pipeline was worth every penny ...
    Apr 30, 2024 · The Trans Mountain pipeline is now shipping oil. Finally. Canada's west coast has not seen a new pipeline in over 70 years.
  9. [9]
    TMEP Benefits - Trans Mountain
    Trans Mountain has invested more than $5 million into local infrastructure improvements such as sewer and water upgrades in Clearwater and sewer, water and road ...
  10. [10]
    Trans Mountain - Homepage
    ### Summary of Trans Mountain Pipeline System
  11. [11]
    Trans Mountain Expansion: What's the Impact on the Canadian ...
    Aug 21, 2024 · As a result, the impact of the new pipeline on real GDP should be moderate in the near term and well below the Bank of Canada's ambitious growth ...
  12. [12]
    Past Project: TMEP - Trans Mountain
    It will create a pipeline system with the nominal capacity of the system going from approximately 300,000 barrels per day to 890,000 barrels per day. On June ...
  13. [13]
    Trans Mountain Pipeline Expansion Project, Canada
    May 16, 2024 · The Trans Mountain pipeline is connected to the 111 km-long Trans Mountain Puget Sound pipeline system from the Sumas pump station and terminal.
  14. [14]
    Terminals - Trans Mountain
    The system starts in Edmonton, Alberta and terminates on the West Coast of British Columbia in Burnaby. Thirty- three active pump stations located along the ...
  15. [15]
    Market Snapshot: Trans Mountain Expansion eases pipeline ... - CER
    Sep 3, 2025 · The Trans Mountain pipeline historically transported mostly light oil, but heavy oil has increased to approximately match light oil volumes ...
  16. [16]
    Trans Mountain Pipeline ULC – Trans Mountain Expansion Project
    Apr 30, 2024 · Reactivation of 193 km of pipeline between Edmonton and Burnaby; and; Increasing Trans Mountain's shipping capacity from 300,000 bbl/d to ...
  17. [17]
    [PDF] Trans Mountain - Q1 2025 Presentation
    • Current pipeline capacity of 890 kbpd. • Line 1: 350 kbpd of (light/refined products) primarily to land destinations in B.C. and WA. • Line 2: 540 kbpd ...
  18. [18]
    Update: October 2025 Capacity Announcement for the…
    Oct 1, 2025 · Total system nominations for the Trans Mountain Pipeline system are not apportioned for October 2025. What is pipeline 'apportionment' and why ...Missing: current | Show results with:current
  19. [19]
    Canada's Trans Mountain eyes open season later this ... - Reuters
    Jul 30, 2025 · A C$34 billion expansion was completed last year, tripling the pipeline's capacity. The pipeline is currently about 84% full, but Trans Mountain ...
  20. [20]
    The Trans Mountain pipeline is delivering - Statistics Canada
    Aug 26, 2025 · In March 2025, crude oil pipeline movements totalled 2 797 999 cubic metres. In April 2025, crude oil pipeline movements totalled 2 561 515 ...
  21. [21]
    Both Sides Now - Has the Trans Mountain Expansion Shifted ...
    Jan 2, 2025 · Crude on the combined system is shipped from Edmonton, AB, to several points in the Burnaby, BC, area, including the Parkland Fuel Refinery ( ...<|separator|>
  22. [22]
    Trans Mountain Reports Q2 2025 Results, Delivering Strong Cash…
    Aug 27, 2025 · Trans Mountain has nominal capacity to deliver 890,000 barrels of petroleum products each day through a pipeline system of more than 1,180 ...
  23. [23]
    Trans Mountain expects to pay federal government $1.25-billion in ...
    May 30, 2025 · Trans Mountain Corp. expects to pay Ottawa $1.25-billion this year, due partly to record shipments on the federally owned oil pipeline and a refinancing deal.
  24. [24]
    Management - Trans Mountain
    Management · Mark Maki · Michael Davies · Jennifer Pierce · Todd Stack · Corey Goulet · Rob Van Walleghem.
  25. [25]
    Trans Mountain Pipeline - Lifecycle Transition from Construction to ...
    Jul 9, 2025 · The Canada Energy Regulator (CER) expects pipelines and associated facilities within the Government of Canada's jurisdiction to be constructed, ...
  26. [26]
    Trans Mountain Releases 2024 Environmental, Social…
    Jun 23, 2025 · Trans Mountain Corporation (“Trans Mountain” or “the Company”) today released its 2024 Environmental, Social, and Governance (“ESG”) report.
  27. [27]
    Trans Mountain Expansion pipeline project has financial issues ...
    Sep 16, 2025 · Fact Sheet Infrastructure Pipelines Regulation Canada. Trans Mountain Expansion pipeline project has financial issues despite government bailout.
  28. [28]
    Trans Mountain Pipeline System - A Strategic Canadian Asset
    Feb 3, 2025 · First, to give more capacity for responsibly produced Canadian crude oil to grow and meet the energy needs of the world. Second, to give ...
  29. [29]
    Operations - Trans Mountain
    Trans Mountain operates Canada's only pipeline system transporting oil products to the West Coast. We deliver approximately 890,000 barrels of petroleum ...
  30. [30]
    Trans Mountain TMX Pipeline | Canada's Energy Export Boom
    May 7, 2025 · TMX pipeline triples capacity, boosts oil exports & adds $10B in 2024 revenue. Canada's most strategic energy project is now a global trade ...
  31. [31]
    Canada's Trans Mountain Oil Pipeline Has a New Major Buyer—China
    Jun 16, 2025 · China has overtaken the United States as the top oil purchaser from the Trans Mountain pipeline, displacing it in its quest to diversify supplies.
  32. [32]
    Our History - Trans Mountain
    Trans Mountain was established on March 21, 1951, when the Parliament of Canada granted the company a charter, setting in motion the construction of a pipeline.
  33. [33]
    Trans Mountain pipeline - Wikipedia
    TMC is a Crown corporation, a subsidiary of the Canada Development Investment Corporation (CDEV). Until the purchase by CDEV, the Trans Mountain Pipeline was ...
  34. [34]
    Trans Mountain Pipeline under construction in 1953 - CBC
    Jul 4, 2018 · To that end, the 718-mile-long (or 1,150-kilometre-long) Trans Mountain Pipeline was engineered and built. Workers blasted through rock, drained ...Missing: initial | Show results with:initial
  35. [35]
    A timeline of the Trans Mountain pipeline expansion's ... - BOE Report
    Jan 30, 2024 · Oct. 17, 1953: The first shipment of oil reaches the Trans Mountain Burnaby Terminal, following a feat of engineering that saw the construction ...
  36. [36]
    Timeline: Key dates in the history of the Trans Mountain pipeline - CBC
    Jun 18, 2019 · October 1953: The Trans Mountain pipeline begins shipping oil with an initial capacity of 150,000 barrels per day. The project features four ...
  37. [37]
    Timeline: Key dates in the history of the Trans Mountain pipeline
    October 1953: The Trans Mountain pipeline begins shipping oil with an initial capacity of 150,000 barrels per day. The project features four pump stations along ...
  38. [38]
    Vancouver's first shipment of Alberta crude oil -
    Apr 27, 2017 · Gardner Johnson Co. Ltd. In 1957, the Trans Mountain pipeline capacity was expanded with the addition of a 160-kilometre loop. The Flying A ...
  39. [39]
    The Big Squeeze: Lessons from the Trans Mountain Pipeline about ...
    Aug 13, 2024 · TMPL began shipping crude oil in 1953 and was modified to allow for batching to facilitate refined product shipments in 1983. In the period ...
  40. [40]
    Batching, treating keys to moving refined products in crude-oil line
    Batching, treating keys to moving refined products in crude-oil line ... Trans Mountain pipeline travels approximately 1,260 km and crosses both the ...
  41. [41]
    [PDF] Historical Background Report: Trans Mountain Pipeline, 1947-2013
    May 25, 2015 · In 1950, Interprovincial. Pipe Line Company (now Enbridge) started the effort with the completion of an oil pipeline from. Edmonton, Alberta to ...
  42. [42]
    A History of Oil Spills on Long-Distance Pipelines in Canada
    On 15 July 2015, Nexen, an oil and gas company headquartered in Calgary, notified the Alberta Energy Regulator (aer) of a massive pipeline spill in northern ...
  43. [43]
    Spill History - Trans Mountain
    Trans Mountain has reported approximately 85 spills since the enactment of the CER in 1961. The CER's spill history records is available on their website.
  44. [44]
    [PDF] Spill History - Regulatory Document Index
    Aug 20, 2012 · Since 1961, Trans Mountain has reported 81 spills on its pipeline system to the NEB, some of which are below the reportable threshold. It is ...
  45. [45]
    What is Kinder Morgan's record of spills? - Sacred Trust
    June 4, 2007: 69,950 litres (440 barrels) of crude oil were spilled at former Wahleach pump station, and reports indicate that the Kinder Morgan pipeline may ...
  46. [46]
    Trans Mountain Expansion – Project Background
    Mar 20, 2024 · Kinder Morgan Canada shareholders voted to approve the transaction at a meeting on August 30, 2018. The NEB will continue to regulate the ...Original Project filing and... · Purchase Agreement · Federal Court of Appeal...
  47. [47]
    Project Rundown: 2012 to Today - Trans Mountain
    Aug 1, 2017 · As a result, in May 2012, Kinder Morgan Canada announced the Trans Mountain Expansion Project. Four years later, in May 2016, following a ...Missing: proposal | Show results with:proposal
  48. [48]
    Trans Mountain Files Facilities Expansion Application with the ...
    Dec 16, 2013 · In spring 2012, Kinder Morgan Canada announced it would move forward with its proposed plans to expand the existing Trans Mountain pipeline ...
  49. [49]
    [PDF] Trans Mountain Expansion Project
    Dec 31, 2013 · ... 2012, announced a proposed expansion of the TMPL system ... finance the Project with equity supplied by the parent company Kinder Morgan.
  50. [50]
    Trans Mountain Updates Customer Commitments for Proposed ...
    Jan 10, 2013 · These additional commitments will result in an increase in the proposed expansion capacity from 750,000 bpd to 890,000 bpd. The expansion ...
  51. [51]
    ARCHIVED – NEB report recommends conditional approval ... - CER
    The National Energy Board (NEB or the Board) has issued a 533-page report recommending Governor in Council approve the Trans Mountain Expansion Project (Project) ...
  52. [52]
    Trans Mountain Receives Final Federal Approval of Expansion
    Nov 29, 2016 · Trans Mountain Receives Final Federal Approval of Expansion: Company Advancing Project for the Benefit of Canadians. November 29, 2016.
  53. [53]
    Trans Mountain Expansion Project | West Coast Environmental Law
    Following a flawed and controversial process, Canada's National Energy Board (NEB) recommended the approval of the Trans Mountain Expansion in May of 2016.
  54. [54]
    Federal Court of Appeal rejects Trans Mountain pipeline expansion ...
    On August 30, the Federal Court of Appeal (FCA or Court) denied the federal government's approval of the Trans Mountain pipeline expansion project (Project).
  55. [55]
    Trans Mountain Pipeline System and Expansion Project to Be Sold ...
    May 29, 2018 · The Trans Mountain Pipeline system and expansion project will be sold to the Government of Canada for C$4.5 billion, with a seek for a third ...
  56. [56]
    Details of Agreement for the Completion of the Trans Mountain ...
    May 16, 2018 · ... Government of Canada agreed to purchase Kinder Morgan Inc.'s Trans Mountain Expansion Project and related pipeline and terminal assets. The ...
  57. [57]
    CER – ARCHIVED – Court Challenges to Canada Energy Regulator ...
    Trans Mountain Expansion Project Reconsideration. On 30 August 2018, the Federal Court of Appeal quashed Order in Council P.C. 2016-1069 and remitted the matter ...
  58. [58]
    Federal Court of Appeal Upholds Approval of Trans Mountain ...
    Feb 7, 2020 · The Federal Court of Appeal dismissed the challenges to the federal approval of the pipeline. The Court said it was reasonable for the Governor in Council to ...
  59. [59]
    Major victory for Trans Mountain after federal court dismisses appeal
    Feb 6, 2020 · On February 4, 2020, the Federal Court of Appeal dismissed the final legal challenge to the Trans Mountain Expansion Project (Project).
  60. [60]
  61. [61]
    Trans Mountain Corporation Updates Expansion Project…
    Feb 18, 2022 · The total Project cost has increased from $12.6 to $21.4 billion. This estimate includes the costs of all known Project enhancements, changes, delays and ...
  62. [62]
    Trans Mountain pipeline faces 9-month delay over route dispute
    Sep 12, 2023 · The expansion of a Canadian government-owned oil pipeline from Alberta to the Pacific Coast could be delayed by nine months if regulators don't approve a route ...<|separator|>
  63. [63]
    Trans Mountain Announces Milestones of Commercial Service for…
    May 1, 2024 · Recent milestones of the Trans Mountain Expansion Project include: The “Golden Weld”: On April 11, 2024, at 8:11 pm MST, the Golden Weld ...
  64. [64]
    The Trans Mountain Expansion Project: Crossing the Finish Line
    May 14, 2024 · Originally built in 1953, the expansion project triples the pipeline's capacity from 300,000 to 890,000 B/d. This significant expansion of ...
  65. [65]
    CER issues final authorization for Trans Mountain Expansion Project ...
    Apr 30, 2024 · CER issues final authorization for Trans Mountain Expansion Project to operate. News Release For Immediate Release. April 30, 2024. The Canada ...Missing: commissioning | Show results with:commissioning
  66. [66]
    Canada's long-delayed Trans Mountain oil pipeline starts operations
    May 1, 2024 · Trans Mountain Corp said May 1 marks the commercial commencement date for the project, and tankers will be able to load at Westridge Marine ...Missing: commissioning | Show results with:commissioning
  67. [67]
  68. [68]
    Exclusive: Canada's Trans Mountain pipeline lowers forecasts for ...
    Apr 2, 2025 · Canada's Trans Mountain oil pipeline has downgraded forecasts for the amount of oil expected to flow through its system over the next three years.Missing: post- startup incidents
  69. [69]
    Trans Mountain faces $292k environmental fines after 2024 B.C. ...
    Oct 16, 2025 · The inspection order details alleged issues with watercourse crossings, questionable response times, broken wildlife fencing and a small ...Missing: incidents | Show results with:incidents
  70. [70]
    Canada should not rush potential sale of TMX pipeline, Trans ...
    Jun 11, 2025 · Maki said on Wednesday he believes the government can recover its investment in the pipeline, but will receive a better sale price for the asset ...
  71. [71]
    Trans Mountain Pipeline ULC – Salmon River Replacement Project
    Construction of the Project is anticipated to begin in Q2 of 2025. Engagement. Trans Mountain commenced formal early engagement activities pursuant to the ...
  72. [72]
    Done: Expanded Trans Mountain pipeline launches May 1
    Apr 15, 2024 · ... date for commercial operation of the expanded system will be May 1, 2024. Trans Mountain anticipates providing service for all contracted ...
  73. [73]
    Facilities Construction - Trans Mountain
    To support the expanded pipeline system, we're adding 11 new pump stations along the route and one new pump station will be added on the existing pipeline.
  74. [74]
    [PDF] Volume 4A - Project Design and Execution - Engineering
    new pump stations at existing sites will be constructed entirely on Trans Mountain owned land except for the Hinton and Rearguard, which will require some ...
  75. [75]
    [PDF] Expansion Project Details - Trans Mountain
    An increase in isolation valves on the pipeline resulting in a significant reduction of potential spill volumes. ○ An increase in pipeline wall thickness.
  76. [76]
    Leak Detection - Trans Mountain
    The SCADA system monitors rate-of-flow in the pipeline, pressure, temperature and density of product, among other things. The Leak Detection System then ...Missing: features | Show results with:features
  77. [77]
    Trans Mountain - Connecting With You Series
    Sep 4, 2025 · This includes Supervisory Control and Data Acquisition (SCADA) systems tracking pressure and flow, a 24/7 Control Centre in Edmonton with ...
  78. [78]
    [PDF] Final Audit Report - Trans Mountain Pipeline ULC - CV2324-218
    Feb 15, 2024 · Trans Mountain has implemented two leak detection systems on the Trans Mountain line 1 pipeline and will utilize this approach for Trans ...Missing: features | Show results with:features
  79. [79]
    Trans Mountain Signs 10-Year Pipeline Monitoring Deal with Hifi ...
    Oct 9, 2024 · The high-fidelity distributed sensing (HDS) system will provide additional protection for the pipeline, complementing existing leak detection ...Missing: features | Show results with:features
  80. [80]
    Trans Mountain Announces 10-Year Monitoring Agreement with Hifi ...
    Oct 7, 2024 · State-of-the-art fibre optic system will enhance leak detection technology for monitoring Trans Mountain's expanded pipeline system.Missing: features | Show results with:features<|separator|>
  81. [81]
    What you Need to Know: Pump Station Construction - Trans Mountain
    Apr 24, 2020 · As part of the Trans Mountain Expansion Project, we're adding 12 new pump stations to the pipeline system, 11 for the new pipeline and one for ...
  82. [82]
    CER approves operation of Trans Mountain crude pipeline expansion
    May 1, 2024 · The expansion included 988 km of new pipeline, 193 km of reactivated pipeline, 12 new pump stations, 19 new storage tanks, and three new berths ...<|separator|>
  83. [83]
    CER – Trans Mountain Pipeline ULC - Project Conditions
    Mar 20, 2024 · The following table is available to explore the 156 conditions of the Trans Mountain Expansion Project and view condition filings submitted by Trans Mountain.Missing: enhancements | Show results with:enhancements
  84. [84]
    [PDF] Trans Mountain Expansion: Connecting Canada's Energy to the World
    Feb 17, 2025 · TMX added 590,000 b/d of export pipeline capacity, and for the first time provides Canada meaningful access to global markets. The project has ...
  85. [85]
    Varcoe: Billion-dollar benefits of TMX help make case for pipelines
    Aug 7, 2025 · The increased pipeline capacity has allowed producers to ramp up output without triggering a widening in the price differential between Western ...
  86. [86]
  87. [87]
    Trans Mountain pipeline delivers $12.6 billion in new revenue to ...
    Aug 6, 2025 · Trans Mountain has increased Canadian oil shipments to refineries in the United States and more than tripled the share of exports to countries ...<|separator|>
  88. [88]
    Canada's Anniversary Wish: More Trans Mountain Expansions
    The project has helped diversify markets for Canada's crude oil while spurring upstream expansions in the Western Canadian Sedimentary Basin (WCSB).Missing: importance | Show results with:importance
  89. [89]
    [PDF] Trans Mountain Corporation
    Total capital investment in TMEP is expected to contribute $26.3 billion in gross domestic product (GDP), 67,423 person-year full-time equivalent jobs (FTEs), ...
  90. [90]
    Minister Morneau Highlights the Economic Benefits of Building the ...
    Feb 10, 2020 · At peak construction there are expected to be 5,500 people employed on sites in Alberta and British Columbia. The goal is to have the Project in ...Missing: actual | Show results with:actual
  91. [91]
    Does British Columbia rely on the jobs created through the ...
    Trans Mountain promises that the pipeline would create 50 permanent jobs in British Columbia, and 40 in Alberta. Temporary jobs created: Trans Mountain has been ...Missing: numbers | Show results with:numbers
  92. [92]
  93. [93]
    Trans Mountain returns $1.25 billion to federal coffers as Asia-bound ...
    Jun 3, 2025 · Trans Mountain Corp. expects to return $1.25bn to the federal government in 2025, according to The Globe and Mail, driven by record crude shipments and lower ...
  94. [94]
    Trans Mountain expansion has delivered so far on some profitable ...
    Jan 23, 2025 · The Trans Mountain pipeline expansion promised to allow Canada to diversify oil markets and vastly increase exports to Asia, where it could ...
  95. [95]
    Trans Mountain pipeline delivers $12.6B in new revenue
    Aug 6, 2025 · The Trans Mountain pipeline has delivered an estimated $12.6 billion in new revenues to the Canadian oilpatch. Find out more.
  96. [96]
    [PDF] Trans Mountain Expansion Could Never Return the Expected $26.1 ...
    Mar 3, 2022 · Cost of Kinder Morgan's Trans Mountain expansion quietly rises to $6.8 · billion. November 17, 2015. 9 Trans Mountain. Trans Mountain ...<|separator|>
  97. [97]
    Trans Mountain Completes Final Cost Estimate Review with Shippers
    Mar 9, 2017 · Kinder Morgan's final cost estimate and increased tolls reflect the updated project cost of $7.4 billion CAD.Missing: original | Show results with:original
  98. [98]
    Agreement Reached to Create and Protect Jobs, Build Trans ...
    May 29, 2018 · ... purchase the company's Trans Mountain Expansion Project and related pipeline and terminal assets for $4.5 billion. The transaction is ...
  99. [99]
    Trans Mountain paid McKinsey $32M to save money | The Narwhal
    which ballooned from $5.4 billion to $34 billion between 2013 and 2024 — has ...
  100. [100]
    Six months on, what has the Trans Mountain pipeline project ... - CBC
    Oct 21, 2024 · The federal government purchased the pipeline for $4.5 billion in 2018 in an effort to get the project over the finish line. Once construction ...
  101. [101]
    Trans Mountain Over-Budget; Fossil Support Nears $30B for 2024
    Apr 7, 2025 · The government purchased the pipeline in 2018 for $7.4 billion, but costs have since ballooned to $34.2 billion. Through the many years that the ...
  102. [102]
    Westridge 2007 Spill - Trans Mountain
    On July 24, 2007, a backhoe operated by a third-party contractor accidentally ruptured the Trans Mountain pipeline carrying crude oil to the Westridge Martine ...
  103. [103]
    Oil Pipeline Spill History at the National Energy Board of Canada ...
    May 8, 2014 · 29 April 1966 Trans Mountain Pipeline crude oil spill in Alberta = 1.1 million litres · 26 April 1971 Trans Mountain Pipeline crude oil spill in ...
  104. [104]
    Pipeline transportation safety investigation report P20H0023
    Apr 13, 2021 · At 2256, the SCADA system detected combustible gas in the pump building and raised a high-severity alarm, which triggered an automatic emergency ...
  105. [105]
    Summary of Recommendation - Trans Mountain Expansion Project
    Mar 20, 2024 · The Project proposes to expand the existing Trans Mountain pipeline system between Edmonton, AB and Burnaby, BC, nearly tripling the capacity to ship oil.Missing: enhancements | Show results with:enhancements
  106. [106]
    Environmental Protection Plans - Trans Mountain
    Guide Trans Mountain's committed protection and mitigation methods. These studies covered environmental features such as: wildlife, fisheries, plants, species ...
  107. [107]
    Reconsideration Report – Trans Mountain Expansion Project
    Mar 20, 2024 · The Reconsideration report concludes that Project-related marine shipping is likely to cause significant adverse environmental effects.
  108. [108]
    Protecting the environment - Canada.ca
    Mar 22, 2025 · TMX is clear evidence that Canada can grow its economy and deliver its natural resources to international markets while safeguarding the ...
  109. [109]
    Canada Energy Regulator 16 Recommendations
    Mar 23, 2025 · These recommendations are intended to mitigate, avoid or lessen potential effects associated with TMX and related marine shipping.
  110. [110]
    Trans Mountain Expansion Project Reconsideration Report
    Mar 20, 2024 · Trans Mountain must file with the NEB, on or before 31 January of each year after commencing operations, confirmation, signed by an officer of ...<|control11|><|separator|>
  111. [111]
    [PDF] Safety in the Transportation of Oil and Gas: Pipelines or Rail?
    As figure 3 shows, from 2002 to 2009, the vol- umes spilled per million ton-miles of petro- leum transport was generally larger for pipe- lines than for rail ( ...
  112. [112]
    [PDF] External Costs of Transporting Petroleum Products - Randall Walsh
    As noted above, PHMSA's central esti- mates of the costs from spills and accidents for rail and pipelines are $381 and $62 per million-barrel miles. Firms ...
  113. [113]
    Pipelines safer than rail or truck for oil: report - EDI Weekly
    According to the report, there are an average of 20 spills per billion ton-miles in trucking, two in rail shipping, and 0.6 in pipelines. Pipeline spills ...
  114. [114]
    [PDF] Canadian Crude Oil Transportation Comparing the Safety of ...
    Based on this data, it is our contention that, with current regulation and investment, both rail and pipeline have comparable safety records and are safe means ...Missing: truck | Show results with:truck
  115. [115]
    Gas & Oil Transportation: Pipeline Vs Rail - ACTS
    Aug 29, 2018 · Overall in this period, rail experienced 0.227 occurrences per million barrels of oil equivalent transported compared to 0.049 for pipelines.” ...
  116. [116]
  117. [117]
    Which Is Safer For Transporting Crude Oil: Rail, Truck, Pipeline Or ...
    Oct 11, 2018 · The Congressional Research Service estimates that transporting crude oil by pipeline is cheaper than rail, about $5/barrel versus $10 to $15/ ...
  118. [118]
    Alberta government announces new pipeline proposal—yet ...
    Oct 2, 2025 · A key problem for any pipeline development is the lack of private-sector firms interested in investing in Canada, which is understandable given ...Missing: conflicts | Show results with:conflicts
  119. [119]
    A short history of the Trans Mountain expansion's troubled completion
    Oct. 17, 1953: The first shipment of oil reaches the Trans Mountain Burnaby Terminal, following a feat of engineering that saw the construction and completion ...
  120. [120]
    B.C. and Alberta are about to renew old hostilities. It could get ugly
    Jun 17, 2025 · As inter-provincial contretemps go, the one emerging between BC and Alberta over the future of pipeline construction in Canada is shaping up to be a doozy.
  121. [121]
    The Supreme Court of Canada has dismissed BC's attempt to block ...
    Jan 20, 2020 · The Supreme Court of Canada (SCC) dismissed an appeal by the government of British Columbia in which it sought to defend its beleaguered anti-pipeline ...Missing: disputes | Show results with:disputes
  122. [122]
  123. [123]
    Canadian Government to Buy Kinder Morgan's Trans Mountain ...
    May 29, 2018 · The Canadian government on Tuesday said it would buy an oil pipeline to the country's west coast, ensuring that its widely protested expansion will go forward.<|separator|>
  124. [124]
    Canada to buy controversial Trans Mountain pipeline - Al Jazeera
    May 29, 2018 · Canada's government has said it is buying a controversial pipeline expansion project to ensure it gets built in the face of stiff opposition ...Missing: tensions | Show results with:tensions
  125. [125]
    Canada should learn from the Trans Mountain Expansion pipeline's ...
    Sep 16, 2025 · The direct funding Canada provided for TMX totals $35.6 billion—roughly $1.4 billion more than typically reported.Missing: 2020-2024 | Show results with:2020-2024
  126. [126]
    Eby says he will not support pipeline from Alberta. Can he stop it?
    Oct 7, 2025 · As discovered with the attempts to block the Trans-Mountain pipeline, B.C.'s tool box is limited when it comes to stopping energy projects.Missing: conflicts | Show results with:conflicts
  127. [127]
    Interprovincial pipelines fall under federal responsibility, former ...
    Oct 16, 2025 · “This is a guy who's in office, who wants to use his political authority to block a prospective interprovincial pipeline,” Kenney said about Eby ...
  128. [128]
    Indigenous Engagement - Trans Mountain
    Trans Mountain's expanded pipeline system spans Treaty 6 and Treaty 8 areas in Alberta and the Traditional Territories of more than 130 Indigenous groups.
  129. [129]
    Trans Mountain and the problem with pipeline consultation in Canada
    Sep 4, 2018 · Forty-three Indigenous groups eventually concluded impact-benefit agreements supporting the project. Phase II consisted of the NEB hearing ...
  130. [130]
    43 Indigenous Groups Have Signed Agreements in…
    Apr 19, 2018 · “Trans Mountain has signed 43 Benefit Agreements with Aboriginal groups in BC and Alberta, 33 of which are located in BC.” Share.
  131. [131]
    Equity partnerships represent a turning point for Indigenous ...
    Mar 11, 2025 · And as of summer 2021, Trans Mountain had 66 agreements with 73 Indigenous groups in BC and Alberta. Since then, four Indigenous groups have ...
  132. [132]
    Indigenous Participation in the Economic Development of the Trans ...
    Jun 18, 2019 · Interested Indigenous groups have stated that greater economic participation in TMX is an opportunity to create additional economic benefits for ...
  133. [133]
    How First Nations Benefit from Pipeline Construction - Fraser Institute
    Jun 11, 2019 · Forty-three First Nations and other Indigenous groups support the proposed Trans ... opposition to Trans Mountain, are active in real-estate ...
  134. [134]
    Joint agreement to make continual improvements to Indigenous ...
    Mar 20, 2024 · Joint agreement to make continual improvements to Indigenous monitoring on the Trans Mountain pipeline and expansion project [PDF 787 KB].
  135. [135]
    Achieving Indigenous led pipeline justice - ScienceDirect
    Another example is the issuance of injunctions in the Trans Mountain Pipeline case to side-line efforts of Indigenous legal orders (recognized by indigenous ...
  136. [136]
    Chronicling the Trans Mountain Expansion Project's Path to Legal ...
    Jul 13, 2020 · Below we provide an outline of the legal challenges the Project has faced since it was proposed in 2013.
  137. [137]
    Trans Mountain: Could an Indigenous Rights case impact operations?
    May 1, 2024 · The Trans Mountain pipeline expansion trenched through an Indigenous burial ground. The nation is now boosting title claim efforts.
  138. [138]
    The First Nations' movement against the Trans Mountain Expansion ...
    The Trans Mountain Pipeline Expansion Project (TMX) is part of a structurally violent system with a history of violations against Indigenous Rights.
  139. [139]
    Trans Mountain pipeline: Why some First Nations want to stop it - CBC
    Oct 5, 2019 · A group of Indigenous communities want to buy the Trans Mountain pipeline to help alleviate First Nations poverty, while others say the ...
  140. [140]
    Timeline: Key dates in the history of the Trans Mountain pipeline
    May 29, 2018 · October 1953: The Trans Mountain pipeline begins shipping oil with an initial capacity of 150,000 barrels per day. The project features four ...
  141. [141]
    'It's Standing Rock North': Trans Mountain pipeline in Canada stirs ...
    Nov 26, 2016 · Feb. 23: Dakota Access Pipeline protest camp closed; 46 holdouts arrested. Feb. 22: Preparing to leave, Standing Rock protesters ceremonially ...
  142. [142]
    Trans Mountain pipeline: A look at key dates in the history of the ...
    Jul 2, 2020 · March 23, 2018: Green party Leader Elizabeth May and NDP MP Kennedy Stewart are arrested at a protest against the pipeline expansion; Federal ...
  143. [143]
    Tiny House Warriors found guilty of all charges for TMX altercations
    Jun 3, 2024 · The Tiny House Warriors are a Secwépemc-led resistance group in opposition to the Trans Mountain pipeline expansion's (TMX) operation on their ...
  144. [144]
    Occupy Blue River: High-conflict protest, two rules of law
    Mar 14, 2022 · Al Jazeera+ was on hand to film when Tiny House protesters threw rocks at pipeline workers and smashed solar panels on September 15, 2021 ...
  145. [145]
    Court quashes Canadian approval of Trans Mountain oil pipeline
    Aug 30, 2018 · A Canadian court on Thursday overturned approval of the Trans Mountain oil pipeline expansion, ruling that Ottawa failed to adequately ...
  146. [146]
    1. Case Study 1 : Trans Mountain Pipeline Expansion - Saskoer.ca
    Construction was initially scheduled to finish in 2022 and cost Canadian taxpayers $12.6 billion. In 2020, the pipeline won a major victory when the Supreme ...Missing: original length
  147. [147]
  148. [148]
    How a Major Tar Sands Pipeline Project Threatens Indigenous Land ...
    May 1, 2022 · Construction of Line 3 was finally completed in September 2021, after overcoming a large opposition movement that saw over 900 arrests in ...
  149. [149]
    In a major victory for Trans Mountain, Federal Court dismisses ... - CBC
    Feb 4, 2020 · The Federal Court of Appeal has dismissed an appeal by Indigenous groups challenging the federal government's approval of the Trans Mountain expansion project.