Troll A platform

The Troll A platform is a gravity-based production and processing facility located in the Troll field in the northern , approximately 65 km west of Kollsnes near , , in water depths of 300-330 meters. Operated by since 1996, it serves as the central hub for gas extraction and compression from the Troll Øst , which holds about two-thirds of the field's total recoverable gas reserves of approximately 1,437 billion standard cubic meters, with overall field recoverable resources of around 1,600 billion sm³ oe. Installed in May 1995 after being towed from a fjord, the platform stands 472 meters tall from seabed to top, making it the tallest structure ever moved by humans, with a dry weight of 656,000 tons and a ballasted towing weight of 1.2 million tons. The Troll field was discovered in 1979, with commercial viability declared in 1983 and unitization approved in 1985; the initial plan for development and operation (PDO) was submitted in 1986 and revised in 1990 to focus on gas production via . Construction of the platform's gravity base structure (GBS) began in the early 1990s at sites in Hinnavågen and Vats, , using 250,000 cubic meters of and 100,000 tonnes of reinforcement , marking it as the last such concrete gravity base built for the Norwegian Continental Shelf (NCS). The platform was towed out to sea over seven days at a speed of 1-2 knots and positioned on 17 May 1995, with gas production commencing on 19 September 1995 and first deliveries to starting on 1 October 1996, processed at the onshore Kollsnes facility and exported via pipelines such as Zeepipe. assumed operatorship from Norske on 19 June 1996, with ownership shared among (30.55%), Petoro (55.93%), and other partners including and . Engineered as a fixed and compression with four massive concrete legs over 1 meter thick, Troll A features 39 subsea wells connected via manifolds and is designed for a 70-year production life from reservoirs 1,330-1,400 meters below . It was the first NCS to be supplied with shore-based power since its startup in 1996, enabling zero CO2 and emissions from operations, and has undergone upgrades including gas compression capacity increases in 2004-2005, 2015, and electrification projects for Troll B and C , completed in 2024, to further reduce emissions by about 90,000 tonnes of CO2 annually. The 's design supports pressure depletion extraction and includes four shore-powered compressors to maintain output as reservoir pressure declines. Troll A processes gas from the Troll field, which achieved a record 42.5 billion standard cubic meters of in 2024, an increase of nearly 10% from prior years, supported by upgrades to the onshore Kollsnes processing plant raising daily from 144.5 million to 156 million standard cubic meters. gas has reached 129 million standard cubic meters per day following recent investments, with oil from the adjacent Troll Vest area historically exceeding 400,000 barrels per day in 2002 via horizontal wells. The field remains a of Norway's exports, with cumulative investments of 247.7 billion NOK through 2023 and projected future spending of 38.2 billion NOK from 2024 onward, including a new gas export solution planned for 2025. This includes the new gas export solution from Troll B to the Kvitebjørn pipeline, approved in 2025, to maintain high levels.

Background

Troll Field Overview

The Troll field is one of Europe's largest natural gas reserves, situated in the northern approximately 65 km west of Kollsnes near , , in water depths of 300-330 meters. The field spans production licenses in blocks 31/2, 31/3, 31/5, and 31/6. Discovered in by well 31/2-1 drilled by , it consists of two main structures: Troll Øst and Troll Vest, with reservoirs primarily in the Formation and Fensfjord Formation sandstones at depths of around 1,330–1,360 m. The geology features a substantial gas cap up to 200 m thick overlying a thin oil column of 22–26 m in Troll Vest and 0–9 m in Troll Øst, making it a prime example of a gas-capped oil in the region. The field's recoverable reserves total 1,437 billion standard cubic meters (Sm³) of gas and 298.5 million Sm³ of oil, equivalent to approximately 1.88 billion barrels of oil, along with associated natural gas liquids of 21.5 million tonnes. These resources position Troll as holding about 40% of Norway's total gas reserves on the Norwegian continental shelf, with overall field reserves estimated at 1.8 trillion cubic meters of natural gas and 2 billion barrels of oil. About two-thirds of the recoverable gas is located in Troll Øst, while the oil is concentrated in Troll Vest. The development has proceeded in phases: Phase 1 focuses on gas recovery from Troll Øst via the Troll A platform; Phase 2 targets oil production from Troll Vest using subsea templates tied to floating platforms Troll B and C; and Phase 3 involves gas extraction from the Troll Vest gas cap since 2021, alongside continued oil production supported by pressure maintenance measures. The field is operated by Energy AS, which holds a 30.55% stake, with principal partners including the state-owned Petoro AS (55.93%), A/S (8.18%), EP Norge AS (3.69%), and Skandinavia AS (1.64%). A serves as the central processing unit for the field's gas production in Phase 1.

Project Development

The field was discovered in 1979 by exploration well 31/2-1, drilled by Norske Shell in the northern . This initial find revealed substantial gas reserves underlying a thin oil layer, prompting further appraisal to assess commercial viability. Between 1980 and 1993, 20 appraisal wells were drilled, confirming the field's extensive hydrocarbon volumes and leading to its declaration as commercial in 1983. These efforts established the field's connection to vast gas reserves, estimated at over 1,300 billion cubic meters recoverable, making it one of Europe's largest offshore discoveries. Development planning advanced through collaboration among licensees, including Norske Shell as operator, Statoil, and others, culminating in the submission of the initial Plan for Development and Operation (PDO) in the mid-1980s. The Norwegian Parliament approved the PDO in December 1986, greenlighting the first phase focused on gas production from Troll East. The PDO was revised in 1990 to emphasize gas production from Troll Øst using the Troll A platform. Key to this approval was the decision to employ a gravity-based structure for the Troll A platform, selected over floating alternatives due to the site's 300-meter water depth and underlying soft seabed, which demanded a stable, fixed foundation to mitigate instability risks. Engineering milestones included the signing of the Troll field unitization agreement in September 1986, formalizing resource allocation among partners. Contracts for detailed and base construction were awarded to Norwegian Contractors later, with work commencing in 1991. The total project cost for Troll A development reached approximately $4.79 billion (about NOK 36 billion at 1996 exchange rates), reflecting the scale of investment in this pioneering deepwater installation. Planning addressed significant challenges, including seabed instability from soft clay layers, necessitating deep skirts on the gravity base for secure penetration—ultimately achieving 36 meters into the soil upon installation. Environmental impact assessments were integral to the PDO process, evaluating potential effects on marine ecosystems, water quality, and fisheries from , , and operations, in line with Norway's regulatory framework for offshore activities.

Design and Engineering

Structural Design

The Troll A platform employs a gravity-based structure (GBS), characterized by a substructure topped with processing facilities, forming a four-legged tower supported by 19 caisson cells for foundational . This design leverages the inherent mass of the base to provide resistance against overturning forces, making it suitable for fixed installations in challenging marine environments. The concept, developed by Norwegian engineering firms, emphasizes modular construction that allows for on-site ballasting and precise positioning. A key innovation in the platform's architecture is its slender base profile, optimized for deepwater deployment with a of approximately 226 m, which facilitates to the installation site while minimizing hydrodynamic drag during . Upon arrival, a ballast system fills dedicated cells within the base, increasing displacement to sink the structure onto the and achieve geotechnical stability on the Troll field's soft, silty clays. This approach incorporates concrete skirts beneath the base to penetrate and into the via and , extending the viability of GBS designs to sites with poor conditions where driven piles would be impractical or costly. Seismic and loading were given minimal emphasis in the design due to the North Sea's relatively low tectonic activity and absence of significant cover. The structural design incorporates load-bearing calculations tailored to extreme conditions, rated for 100-year storms with maximum significant wave heights up to 20 m and speeds of 42 m/s, ensuring operational under combined hydrodynamic, aerodynamic, and gravitational forces. mechanisms within the cells further mitigate wave-induced motions. The base directly supports integrated topsides modules for gas , separation, and initial , enabling efficient of up to 120 million cubic meters of gas per day before export through a dedicated subsea to the Kollsnes onshore facility. This integrated optimizes space and weight distribution, enhancing overall platform efficiency in the field's 303 m water depth and variable soil profile.

Dimensions and Specifications

The Troll A platform stands as an marvel with an overall height of 472 meters, making it the tallest ever moved by humankind. Its gravity-based substructure features a base diameter of 93 meters and four legs forming a substructure approximately 369 meters tall from the base to the topsides interface, designed to reach the in 303 meters of depth. The topsides module rises 36 meters high and weighs approximately 30,000 tons. These dimensions enable the platform's legs to penetrate the soft , providing necessary stability against environmental loads. The platform's dry weight totals 656,000 metric tons, while its fully ballasted reaches 1.2 million tons to facilitate and . The volume in the gravity base structure (GBS) is 250,000 cubic meters, contributing to its massive scale and load-bearing capacity. In terms of production capacity, Troll A is equipped to process up to 121 million standard cubic meters of gas per day, with provisions for handling up to 100,000 barrels of oil per day, though its primary role focuses on gas and associated . The platform includes facilities supporting efficient export operations. The base utilizes high-strength with a exceeding 50 —specifically achieving at least 75 in modified normal density mixes—to withstand deep-water pressures and long-term durability. The topsides employ corrosion-resistant alloys to combat the harsh environment, ensuring operational integrity over the platform's 70-year design life.

Construction and Installation

Construction Process

The construction of the Troll A platform's gravity base structure (GBS) commenced in the summer of 1991 at the Hinnavågen yard in , , under the direction of Norwegian Contractors—a now integrated into —for operator Norske Shell. The project utilized a for the initial pouring of approximately 250,000 cubic meters of , forming the platform's innovative design with 19 cylindrical cells arranged in a ring configuration for buoyancy and stability. This phase, spanning 1991 to early 1995, involved meticulous vertical assembly of the four massive legs and central shafts, each exceeding 300 meters in length, to support the platform's extreme draft requirements in 303 meters of water depth. Parallel to the GBS work, the topsides—comprising processing modules for gas compression, separation, and utilities—were fabricated in separate modules at facilities including , with integration planned for later mating. The GBS was towed from to the Yrkesfjord at Vats in for final outfitting and loadout preparations, where the structure underwent rigorous testing and ballast adjustments. At its peak, the construction effort employed around 2,000 workers, highlighting the scale of coordination required for this landmark engineering endeavor. Key milestones included the completion of the GBS works by 1994 and the full at Vats later that year, setting the stage for subsequent operations. Significant challenges arose during , particularly in achieving precise of the 19 cells to ensure structural under immense loads, as even minor deviations could compromise the 's . Additionally, for curing proved demanding in Norway's harsh coastal weather, necessitating advanced monitoring techniques to prevent defects from temperature fluctuations and moisture exposure while maintaining the high-strength properties essential for deepwater deployment.

Towing and Installation

The operation for the Troll A platform began on May 10, 1995, from its construction site in Yrkesfjorden, , marking one of the most ambitious marine transports in offshore engineering . The fully assembled structure, measuring 472 meters in height and weighing approximately 1.2 million tons when ballasted, was maneuvered over roughly 200 kilometers to the Troll field using a fleet of 10 tugboats—eight for primary pulling and two for steering—at speeds of 1 to 2 knots to maintain precise control through the fjords and open sea. The was delayed by concerns following the sinking of the platform in 1994, but proceeded after rigorous safety reviews. To achieve during the , the was progressively ballasted, with significant flooding occurring on May 15 to submerge over 278 meters below the wave surface, reducing the visible height from about 245 meters to approximately 194 meters and minimizing wind exposure. This careful ballasting ensured the structure's low center of gravity, preventing excessive rolling or yawing in conditions. The operation proceeded ahead of schedule, with the platform reaching its destination on May 17, 1995, without incident. Installation commenced immediately upon arrival in 303 meters of depth. Deballasting initiated a controlled descent using systems aboard support vessels, allowing the gravity base's skirts to make initial contact with the before full penetration of 36 meters into the underlying soil layers of soft to firm clay and . Engineers monitored soil resistance in real-time through pressure sensors on the skirt walls, adjusting rates to overcome differential pressures between the platform's cellular compartments and ensure even settling without structural overload. This process, completed within days, embedded the base securely, requiring no additional due to the inherent stability of the gravity-based design. The topsides, including processing modules and living quarters, were pre-mated to the gravity base at the Vats construction yard before towing, enabling the entire integrated unit to be transported and installed as one. Post-sinking leveling and operations, including subsea connections and , extended through the summer, with physical installation finalized by September 1995. First gas production commenced on 19 September 1995 following commissioning.

Operations

Production History

The Troll A platform initiated gas production in the first half of 1996, with the first commercial deliveries commencing on 1 October 1996 via the 65-kilometer pipeline to the Kollsnes processing plant. Production rapidly escalated in the early years, reaching a peak of 66 million standard cubic meters per day in 1999, establishing the platform as a cornerstone of Norway's gas export infrastructure. By 2020, cumulative gas production from the Troll field had exceeded 1 trillion standard cubic meters, underscoring the platform's long-term productivity. In recent years, the platform has maintained high output levels, achieving a record annual production of 42.5 billion standard cubic meters of gas in 2024, surpassing previous benchmarks and accounting for a significant portion of Europe's gas supply. Ongoing expansions, including Troll Phase 3, approved in 2018 with production starting in 2021, incorporate subsea tie-backs to enhance oil and gas recovery from the Troll West gas cap, adding up to 20 million standard cubic meters per day of capacity. Gas and condensate from Troll A are transported through multiphase pipelines to the Kollsnes processing plant, where the condensate is separated and further processed. In June 2025, submitted the PDO for the Sør development, which will tie gas production to Troll A, expected to start in 2029. Additionally, in September 2025, a new export solution from Troll B to the Kvitebjørn pipeline was approved to maintain high gas exports. Maintenance efforts have ensured reliable operations, with major upgrades to the systems completed in 2005–2006 to support pressure maintenance and extend recovery. The platform has experienced minimal shutdowns, achieving approximately 99% uptime over its operational life, and plans are in place to extend its productive lifespan beyond 2050 through continued investments in subsea infrastructure and power-from-shore integration.

Technological Innovations

The Troll A platform pioneered the use of shore-based power supply on the Norwegian Continental Shelf (NCS), becoming the first offshore installation to receive electricity from the onshore Kollsnes processing plant via (HVDC) technology. This system, operational since 2005 for the initial two links delivering 88 MW and expanded in 2015 with an additional 100 MW, powers critical operations including gas compressors, eliminating the need for onboard gas turbines and resulting in zero CO₂ and emissions from the platform itself. The HVDC Light® configuration transmits power over 70 km at ±60 kV in a symmetrical setup, directly connecting inverters to motors without transformers for enhanced efficiency and reliability. Central to Troll A's processing capabilities is its gas compression system, which includes four electrically driven centrifugal compressors powered by the shore supply, each capable of up to 50 MW output to maintain production as declines. These compressors, among the largest of their kind for , enable efficient handling of high-volume flows by boosting for export pipelines, with the setup operational since the mid-2010s following upgrades that increased daily capacity from 85 million to over 100 million standard cubic meters. The electric drive integration, using variable high-voltage motors, supports prolonged field recovery by compensating for natural drops without additional emissions. Troll A features advanced subsea systems that manage production from over 40 wells, primarily through its fixed design with 39 dedicated gas wells in the Troll Øst , supplemented by subsea tiebacks such as the eight wells from the Troll West gas cap commissioned in 2021. These controls utilize hydraulic and electro-hydraulic actuators integrated with the platform's topsides for remote monitoring and operation of subsea templates, ensuring precise flow regulation and intervention capabilities across distances up to 200 km of umbilicals. This setup facilitates seamless integration with the broader Troll field infrastructure, allowing gas from remote subsea manifolds to be processed centrally. Since the 2010s, has implemented technologies on Troll A, integrated with the platform's upgraded added in 2010, to monitor key assets like compressors and enable condition-based through of operational such as , , and trends. This approach enables proactive interventions that minimize downtime and optimize performance, enhancing overall system reliability in the harsh environment. Safety systems on Troll A incorporate automated emergency shutdown (ESD) mechanisms and integrated and gas detection, managed by ABB's System 800xA High platform to protect personnel, processes, and assets. These systems trigger rapid isolation of wells and sections upon detecting anomalies like leaks or , with redundant sensors and logic solvers ensuring high (SIL compliance) for shutdown sequences. The design emphasizes to support potential unmanned operations, reducing on-site personnel through remote oversight and drone-enabled for non-critical tasks. The platform's integration with the Troll field extends to subsea templates, where production from oil-focused reservoirs in Troll Vest is supported through shared , including provisions for CO₂ injection to enhance in underlying aquifers despite Troll A's primary gas orientation. Subsea manifolds and flowlines tie back to Troll A for processing, with control systems extended to handle injection operations that stabilize reservoir pressures and maximize extraction across the field's gas cap and oil legs. This interconnected design optimizes resource utilization while leveraging Troll A's electrification for low-emission handling of injected fluids.

Records and Significance

Engineering Records

The Troll A platform holds the record for the tallest structure ever moved by humankind, standing at a total height of 472 meters when towed to its site in the in May 1995. It also represents the heaviest object ever relocated, with a dry weight of 656,000 tonnes and a ballasted weight exceeding 1.2 million tonnes during transit. As the largest concrete gravity base structure (GBS) ever constructed, Troll A utilized 250,000 cubic meters of in its base, enabling stability in challenging conditions. It was installed at a record water depth for a concrete GBS of 303 meters, with the structure achieving a penetration of 36 meters to secure it against lateral forces. In terms of production capabilities, Troll A set the highest annual natural gas output from a single offshore platform, delivering 42.5 billion standard cubic meters in 2024. Its compression facilities include the largest single-train system, with a capacity of up to 129 million standard cubic meters per day following upgrades. Troll A pioneered the full-scale application of a narrow-base GBS for deepwater installations, optimizing the structure's to 14.5 by 22.7 meters at the base while supporting extensive compression and processing equipment. By November 2025, it has achieved the longest continuous operational history for any GBS , spanning nearly 30 years since its startup in 1996.

Economic and Environmental Impact

The Troll field, operated through the Troll A platform, has been a cornerstone of Norway's energy economy, generating substantial revenues from and production since 1995. By 2018, cumulative revenues from the field reached approximately 1,400 billion, equivalent to an average of 175 million per day, underscoring its role in funding Norway's and public services. Ongoing developments, such as the Troll Phase III project initiated in 2021, add an estimated average of 17 billion in annual state revenues. The platform and associated infrastructure support significant employment in Norway's oil and gas sector, including direct operations, maintenance, and supply chain activities across the Norwegian continental shelf. Recent tie-in projects, like Sør, are projected to create around 4,500 jobs during their execution phase, highlighting the field's ongoing economic multiplier effects. Troll's gas output is pivotal to Europe's , accounting for about 32% of Norway's total gas production in 2023 and contributing roughly 11% to the European Union's consumption. Environmentally, Troll A pioneered shore power on the Norwegian continental shelf, connecting to the onshore grid in 1996 to replace gas turbines for , thereby eliminating CO2 and emissions from platform-based power production. This innovation has set a precedent for emissions reductions across offshore operations. Recent advancements include partial integration for Troll B and C platforms in 2024, with full of Troll West expected to reduce CO2 emissions by the equivalent of 125,000 fossil-fuelled cars annually—approximately 0.5% of Norway's total yearly emissions—while also cutting levels by 95%. CO2 management efforts near the Troll field include the project, a storing up to 1.5 million tonnes of CO2 annually in a beneath the , starting operations in 2025 to support broader carbon capture initiatives. In August 2025, the first CO2 volumes were injected and successfully stored in the reservoir. Biodiversity monitoring in the , mandated under Norwegian regulations, encompasses the Troll area to assess impacts on marine ecosystems from platform activities and pipeline infrastructure. Looking ahead, electrification upgrades for the Troll complex aim for completion by the early 2030s, further minimizing operational emissions through expanded and potential renewable integration. The Sør development, with its PDO submitted in June 2025 and production startup targeted for the end of 2029, will tie into Troll C as a low-emission subsea extension, leveraging the host platform's to produce oil and gas with reduced carbon intensity. Decommissioning studies for Troll A and related assets are underway, with projections indicating operations extending beyond 2050 given remaining reserves. Challenges include the initial seabed disturbance from Troll A's gravity-based structure installation in 1995, which was mitigated through deep foundation skirts penetrating up to 36 meters into the soil to ensure without excessive disruption. Ongoing carbon capture pilots, such as those linked to , address residual emissions, with testing focused on scalable storage technologies applicable to aging fields like Troll.

References

  1. [1]
    Troll - an oil and gas field in the North Sea - Equinor
    Troll A was the first platform on the NCS to receive power from shore. We took over the Troll Gas operatorship from Norske Shell on 19 June 1996 with gas coming ...
  2. [2]
    Field: TROLL - Norwegianpetroleum.no - Norsk petroleum
    Troll is a field in the northern part of the North Sea. The water depth is 300-330 metres. Troll was discovered in 1979, and the initial plan for development ...
  3. [3]
    How large is a troll? - Industriminne.no
    Aug 11, 2022 · Troll A was the last concrete gravity base structure (GBS) – which sits on the seabed through its own weight – and extends 472 metres from ...
  4. [4]
    The highest natural gas production ever from a Norwegian field
    Jan 6, 2025 · The Troll field in the North Sea has set a historic production record, delivering 42.5 billion standard cubic metres of natural gas in 2024.Missing: sources | Show results with:sources
  5. [5]
    Investing to maintain high gas production at Troll - Equinor
    May 24, 2024 · Maximum production from Troll used to be 121 million standard cubic metres of gas per day. This has now been increased to 129 million.
  6. [6]
    Troll West Oil and Gas Field Project - Offshore Technology
    May 16, 2000 · The field is estimated to have recoverable resources of 1.8 trillion cubic metres of natural gas and two billion barrels of oil. Block 31/2 ...
  7. [7]
    Ocean Installer awarded further work under existing Statoil contract
    Dec 14, 2015 · The Troll C field is located in Blocks 31/2, 31/3, 31/5 and 31/6 ... 80km west of Bergen at a water depth at of approximately 338m. The ...
  8. [8]
  9. [9]
    1980s: Giant without compare - Havtil
    May 24, 2022 · After well 31/2-1 in 1979 had proven what was to become the Troll ... The longest well on Troll is 10 042 metres, with a horizontal ...Missing: appraisal | Show results with:appraisal
  10. [10]
    [PDF] statoil-annual-report-1986.pdf - Statóil - Equinor
    Apr 17, 1997 · Recommended dividends to the Norwegian government are at NOK 871 million. In spring 1986, the Troll and Sleipner owners com pleted sales ...
  11. [11]
    Norway's Troll Gives Europe Energy Access Into 21st Century
    Jul 30, 1996 · Troll's development cost around $4.79 billion, but its gas at today's prices is estimated at a market value of $108 billion. Of the total value ...
  12. [12]
    Foundation Behaviour Of A Giant Gravity Platform On Soft Soils As ...
    Sep 11, 2007 · The Troll A platform in the Norwegian trench rests on a huge gravity-based structure (GBS) with 36m deep concrete skirts.
  13. [13]
    Environmental effects of offshore produced water discharges
    The activities started in 1980 but only two fields (Snøhvit and Goliat) have so far been developed and a third field (Johan Castberg) is presently being ...
  14. [14]
    Installation of the Troll Phase I Gravity Base Platform - OnePetro
    May 6, 1996 · The TROLL Phase 1concrete Gravity Base Platform is located in 303 m of water in the Norwegian Trench some 80 kilometers northwest of Bergen.
  15. [15]
    [PDF] Concrete solutions
    Condeep. The world's tallest fixed concrete platform, Troll A, is based on Condeep. The. Hibernia platform offshore Canada, with its special features to ...
  16. [16]
    [PDF] Offshore concrete structures
    Probably the most impressive Condeep is the Troll A platform, shown in Fig. 6 and Fig. 7. The platform was complete with its 22,000t topside 150m above the sea.
  17. [17]
    Troll A | Heidelberg Materials
    Troll A is a gas production platform and the pinnacle of the Norwegian condeep concept: moveable deepwater concrete structures.Missing: 19 foundation cells design<|control11|><|separator|>
  18. [18]
    How Waves and Wind Shape Offshore Platform Architecture
    It's designed to withstand 100-year storm conditions with significant safety margins. The hydrodynamic stability of Troll A is enhanced by damping chambers and ...
  19. [19]
    Troll A - A Behemoth Of The North Sea - NES Fircroft
    Jul 22, 2020 · Once the largest oil platform in the world, Troll A is a true colossus of the North Sea, where it has stood above the waves since 1996.
  20. [20]
    Troll Phase Three Development, North Sea - Offshore Technology
    Aug 17, 2018 · Operator Equinor, formerly known as Statoil, currently holds 30.58% ownership ... Total E&P Norge (3.69%) and ConocoPhillips Skandinavia (1.62%).
  21. [21]
    Troll-A Platform: Largest Object Ever Moved by Man | Amusing Planet
    Mar 12, 2013 · The Troll A platform is an offshore natural gas platform in the Troll gas field off the west coast of Norway. At 1.2 million ton ballasted under tow.
  22. [22]
    Modified Normal Density (MND) Concrete for the Troll GBS Platform
    Oct 1, 1994 · A concrete mixture with reduced density has been developed, providing a characteristic 28-day cube compressive strength of at least 75 MPa and an in situ ...
  23. [23]
    Modified Normal Density (MND) Concrete for the Troll GBS Platform
    The Troll GBS platform is the world's largest concrete offshore concrete platform. The platform is designed for an operational life time of 70 years, and will ...
  24. [24]
    Troll A – giant move from fjord to field - Industriminne.no
    Jun 13, 2022 · A little over 245 metres of the platform's 472-metre height were visible, with 225 metres below sea level. A speed of one-two knots (about ...
  25. [25]
    Installation of the Troll Phase I Gravity Base Platform
    ### Summary of Troll A Platform Installation Process
  26. [26]
    Top dollar oil & gas FID plays in 2024 with offshore development ...
    May 1, 2025 · The second stage of the Troll Phase 3 (TP3 II) project is made up of ... The project's field development plan was approved in December 2023.
  27. [27]
    Pressure boost for Troll Gas - equinor.com
    Oct 3, 2005 · Two compressors have accordingly been installed on the A platform, and new technology allows these units to be powered from land. That in turn ...Missing: 2006 | Show results with:2006
  28. [28]
    Submitting plan for the record-breaking Troll project - equinor.com
    Jul 3, 2018 · The expected future value creation from Troll is estimated at NOK 1,650 billion. A large share of the Troll cashflow goes to the Norwegian ...
  29. [29]
    Troll A | Hitachi Energy
    Troll A 3&4, provides a total of 100 MW to the platform to power two compressor drive systems. It is in operation since in 2015.Missing: 2006 | Show results with:2006
  30. [30]
    ABB completes Troll A platform's second power-from-shore system
    Oct 22, 2015 · It also provided the 50 megawatts (MW)/60 kilovolts (kV) high-voltage motors that will operate the compressors. center. An ABB engineer at ...
  31. [31]
    Troll A gets new compressors - Offshore-Energy.biz
    Jun 5, 2014 · The two compressors can deliver an output of 50 megawatts each when in maximum operation mode.Missing: details | Show results with:details<|separator|>
  32. [32]
    Equinor Moves Forward on $1.1-Billion Troll Infrastructure Plan
    May 24, 2024 · Phase 3 involves producing the gas cap overlying the oil column in Troll West while continuing to produce oil. The produced gas will flow to ...Missing: CO2 | Show results with:CO2
  33. [33]
    [PDF] Energy efficiency measures for oil rig operations - Magna Scientia
    Oct 11, 2024 · Another case study is the Troll A platform, operated by Equinor, which uses a combination of automated control systems and predictive ...
  34. [34]
    ABB safety system protects StatoilHydro's Troll A platform
    System 800xA High Integrity will provide emergency shut down applications, to protect the personnel on the platform, processes and production assets, as well as ...
  35. [35]
    ABB's System 800xA High Integrity now operating on StatoilHydro's ...
    Jun 22, 2009 · System 800xA High Integrity will provide emergency shut down applications, to protect the personnel on the platform, processes and production ...
  36. [36]
    Installation of the Troll Phase I Gravity Base Platform - OnePetro
    May 6, 1996 · This paper describes the major aspects in the design, preparation and performance of the platform installation operation. The extreme height of ...Missing: innovations | Show results with:innovations
  37. [37]
    Submitting plan for the record-breaking Troll gas project
    Jul 3, 2018 · The gas from Troll will ensure reliable, profitable and carbon-efficient gas supply equivalent to the consumption of 50 million households in ...Missing: uptime 99%
  38. [38]
    Highly profitable Troll phase 3 project on stream - equinor.com
    Aug 30, 2021 · Converted into oil equivalent this amounts to 2.2 billion barrels. Investments are approximately NOK 8 billion.Missing: total 2.3
  39. [39]
    More Oil and Gas to Europe from the Fram and Troll Area
    Jun 27, 2025 · The subsea templates will be tied back to existing Fram infrastructure and to the Troll C platform for processing and export. Oil from the Fram ...Missing: integration injection<|control11|><|separator|>
  40. [40]
    Remaining resources - The Norwegian Offshore Directorate
    117 billion scm of gas were exported in 2023. The Troll field produces the most gas, and in 2023 it accounted for 32 per cent of Norwegian gas production.
  41. [41]
    Equinor's Troll field produced record-high amount of gas in 2024
    Jan 6, 2025 · The field set a historic production record, delivering 42.5 billion standard cubic metres of natural gas in 2024, an increase of almost ten ...<|control11|><|separator|>
  42. [42]
    Reducing emissions from the Troll field - Equinor
    Sep 10, 2024 · The licensees in Troll Unit are Equinor 30.6% (operator), Petoro 56%, A/S Norske Shell 8.1%, TotalEnergies 3.7% and ConocoPhillips Skandinavia ...
  43. [43]
    Equinor Starts Conversion of Troll Field to Onshore Power - Rigzone
    Sep 11, 2024 · The total project investment cost was $100 million (NOK 1.08 billion). The company noted that all installations on the Utsira High are also ...<|separator|>
  44. [44]
    The Northern Lights project - Equinor
    Phase 1 includes capacity to transport, inject and store up to 1.5 million tonnes of CO2 per year. Once the CO2 is captured onshore, it will be transported by ...
  45. [45]
    [PDF] Power from shore - The Norwegian Offshore Directorate
    Oct 29, 2025 · Additional emission reductions are expected when all projects currently under development come on stream. Increased CO cost. The most important ...
  46. [46]
    More oil and gas to Europe from the Fram and Troll area - Equinor
    Jun 26, 2025 · The development will put new oil and gas resources on stream by connecting new infrastructure to existing facilities that provide good and robust profitability.Missing: assessments | Show results with:assessments