Upper Krishna Project

The Upper Krishna Project (UKP) is a multi-purpose mega irrigation and hydropower initiative in Karnataka, India, centered on harnessing the Krishna River's waters through dams at Almatti and Narayanpur, along with an extensive canal network, to irrigate drought-prone districts including Vijayapura, Bagalkot, and Raichur. Conceived originally by the princely state of Hyderabad in the mid-20th century as part of broader Krishna basin development, the project aims to utilize approximately 173 thousand million cubic feet (TMC) of water to bring over 622,000 hectares under irrigation while generating electricity. Initiated with the foundation stone laid by on 22 May 1964, the UKP has been implemented in stages, with Stage-I focusing on initial dam construction and canal systems to stabilize in arid regions historically reliant on rain-fed . Subsequent phases, including Stage-II and the ongoing Stage-III, expand coverage to additional lakhs of hectares, incorporating schemes to counter the region's topography. By providing reliable , the project has transformed in beneficiary areas, enabling crop diversification and reducing risks, though full potential remains unrealized due to phased execution. Despite these advancements, the UKP faces persistent challenges, including interstate water-sharing disputes with and over reservoir heights and allocations, which have delayed heightening of the and overall completion. Over six decades since inception, political delays, land acquisition hurdles, and allegations of mismanagement and corruption in contracts have left significant portions incomplete, prompting ongoing farmer agitations for expedited funding and execution. Resettlement issues for displaced populations have also drawn criticism, with reports highlighting inadequate compensation and rehabilitation despite involvement in early phases.

History

Origins and Early Planning

The Upper Krishna Project originated from proposals by the of to harness waters from the upper basin for irrigation, conceived alongside the Lower Krishna Project (later developed as the Nagarjunasagar Dam) to mitigate drought in arid Deccan regions. These early ideas focused on constructing dams and diversion structures to supply water to rain-fed agricultural lands spanning what are now districts in northern . Following India's independence in 1947 and the 1948 , the upper basin territories were incorporated into the Indian Union and later redistributed under the States Reorganisation Act of 1956, placing them primarily in (subsequently , renamed in 1973). Initial post-independence planning emphasized localized schemes, such as the 1950 Lift Irrigation Scheme (later renamed Mulwad Lift Irrigation Scheme), which proposed pumping water to irrigate command areas in district as a precursor to broader basin development. By the late 1950s, the Government of commissioned detailed hydrological surveys and feasibility studies to consolidate these efforts into a unified multipurpose , targeting for approximately 1.09 million hectares across drought-prone districts including , Bagalkot, and Gulbarga. The blueprint incorporated major reservoirs at proposed sites like Almatti and Narayanpur, with associated canals and power generation components, though interstate -sharing disputes delayed formalization until the Krishna Water Disputes 's in 1961. Planning documents from this period projected utilization of 8.25 thousand million cubic meters (tmc) of annually from Karnataka's 811 tmc allocation under emerging tribunal considerations.

Post-Independence Development and World Bank Involvement

Following India's in 1947, development in the basin accelerated amid rising agricultural demands and inter-state water sharing disputes among , , and . The Upper Krishna Project, initially conceptualized under the of before 1948, was re-evaluated and prioritized by the newly formed (later ) after the linguistic reorganization of states in , which transferred the relevant territories from and Bombay states to . Detailed surveys and feasibility studies in the late confirmed the project's potential to irrigate approximately 1.536 million acres in drought-prone northern districts, including (now ), Bagalkot, and . The establishment of the (KWDT-I) in 1961 under the Inter-State Water Disputes Act addressed allocation conflicts, culminating in its 1973 report that assigned 911 thousand million cubic feet (TMC) of dependable Krishna waters, enabling structured project advancement. Construction commenced in 1963, with laying the foundation stone on May 22, 1964, marking the official launch of and canal works at Narayanpur and later Almatti sites to harness 173 TMC of water for multipurpose use. By the early , initial phases focused on Narayanpur completion in 1978, providing foundational despite ongoing tribunal-related delays and revisions to align with allocated shares. World Bank involvement began in 1978 with a credit of approximately Rs 47 (equivalent to about $5.9 million at contemporaneous exchange rates) to support early implementation components, reflecting the institution's emphasis on large-scale for food production enhancement. This funding aided Stage I Phase I, covering initial canal networks and resettlement, though the project emerged as the Bank's largest supported involuntary resettlement operation, displacing over 200,000 people amid challenges in land acquisition and . Subsequent assistance included a for Stage I Phase II, financing 60% of costs for expanded to 100,000 hectares, with total World Bank commitments exceeding $126 million by the late 1980s for dam heightening and distribution systems. These interventions were conditional on state compliance with environmental and resettlement safeguards, though evaluations later highlighted persistent landlessness among 80-90% of displacees, underscoring implementation gaps.

Technical Components

Dams and Reservoirs

The Upper Krishna Project relies on two principal dams across the Krishna River to create reservoirs for water storage, enabling irrigation, hydropower, and regulated downstream flow in drought-prone regions of northern Karnataka. The upstream Narayanpur Dam, situated near Narayanpur in Yadgir district, forms Basava Sagara reservoir with a gross storage capacity of 37.646 thousand million cubic feet (TMC) and live storage of 30.473 TMC at its full reservoir level. Constructed to a height of 29.72 meters above the lowest foundation level, the dam spans over 10.6 kilometers and features 30 gates, including 22 spillway gates, supporting Stage I canal systems for irrigating approximately 47,233 hectares via the Narayanpur Left Bank Canal. Completion of the dam and allied works occurred by the late 1970s, marking an early milestone in the project's implementation. The downstream Almatti Dam, located near Almatti village in , serves as the project's main storage facility, impounding water up to a full level of 519.60 meters with a gross capacity of 123.08 TMC and live storage of approximately 102 TMC. Standing at a height of 52.5 meters and extending about 3.5 kilometers in length, it integrates a 290 MW hydroelectric power station on its right bank, generating an annual output of 713 million kilowatt-hours. The dam's supports multipurpose utilization under Stages I and II, including releases for the Narayanpur Right Bank Canal and left bank networks, though interstate disputes have capped operations below the originally planned height of 524 meters. In September 2025, Karnataka approved raising the height to 524.256 meters to expand capacity toward 300 TMC, accompanied by compensation measures for affected farmers, pending resolution of concerns from neighboring states.

Canals, Irrigation Networks, and Power Facilities

The Upper Krishna Project's irrigation networks comprise an interconnected system of main canals, branch canals, distributaries, and lift irrigation schemes originating from the Narayanpur and Almatti reservoirs, designed to convey water across drought-prone terrains in northern Karnataka districts including Vijayapura, Bagalkot, Yadgir, and Raichur. These networks facilitate both gravity-fed and pumped distribution to enhance cultivable command areas, with Stage I emphasizing foundational canal infrastructure from Narayanpur and Almatti, while Stages II and III incorporate advanced lift mechanisms to access elevated lands. Prominent among the canals is the Narayanpur Left Bank Canal (NLBC), operational since 2001, which irrigates 142,580 hectares via its main canal (initially constructed up to 18 km) and distributaries, though remodelling has been pursued to mitigate seepage-induced and improve water use efficiency. From Almatti, the West Main Canal spans 61 km with 25 distributaries and the East Main Canal extends 54 km with 22 distributaries, supporting under both gravity and lift systems in early stages. Supplementary schemes, such as Yalligutti (700 hectares) and others under progress, integrate with the primary network to extend coverage, often involving feeder canals (e.g., 1.75 km lengths) and branch canals up to 40 km in targeted sub-projects. Hydropower facilities are embedded within the dam infrastructure, with the primary installation being the 290 MW Almatti Power House situated on the right bank of , commissioned in 2005 to harness reservoir releases for estimated at 672 million units annually. This facility contributes to the project's multipurpose objectives by utilizing systems downstream of the dam, though overall power development across stages has faced delays relative to components, with earlier plans for up to 1,100 MW total capacity across multiple sites remaining partially realized.

Implementation Stages

Stage I: Completion and Key Milestones

Stage I of the Upper Krishna Project primarily involved the construction of the (also known as ) and the up to a full reservoir level of 519 meters, along with allied works and initial canal networks to irrigate 424,903 hectares. The and associated infrastructure were completed, allowing for water storage, diversion, and initial generation to support downstream irrigation. The Almatti Dam's construction progressed to its Stage I height, with completion achieved in July 2005, enabling enhanced storage capacity of approximately 1.3 thousand million cubic meters at that level for and purposes. Key canal components, including the Narayanpur Left Bank Canal and branch canals like Shapur and , were developed to distribute water across the command area in northern districts. By the early 2000s, major structural elements of Stage I were operational, though full potential realization was delayed due to ongoing canal works and inter-state water disputes; official progress reports indicate Stage I and II combined as completed, achieving the targeted for over 620,000 hectares cumulatively. This phase marked the project's foundational hydraulic infrastructure, with the dams providing regulated flows critical for drought-prone regions.

Stage II: Progress and Modifications

Stage II of the Upper Krishna Project, a multipurpose initiative, seeks to harness 54 thousand million cubic feet (TMC) of for irrigating 197,120 hectares across northern Karnataka's arid regions, building on Stage I infrastructure through expanded canal networks and systems. This stage emphasizes command area development, including canals and on-farm improvements to optimize delivery efficiency. Implementation has advanced substantially, with Stage II nearing completion alongside Stage I, collectively generating an irrigation potential of 608,000 hectares as of 2025. Key achievements include the remodeling and lining of principal canals such as the Narayan Left Bank Canal (NLBC), Hagari Branch Canal (HBC), Sulebhavi Branch Canal (SBC), MBA Branch Canal (MBC), Jawalge Branch Canal (JBC), and Indira Branch Canal (IBC) from kilometer 0.00 to 64.00, allowing initial water releases for cultivation. These enhancements address seepage losses and improve conveyance, with physical works on branch and minor canals progressing to support stabilized cropping in tail-end areas. Modifications to the original blueprint have primarily involved scope adjustments for better resource utilization amid interstate water-sharing constraints imposed by the (KWDT-II), which allocated 177 TMC overall, influencing downstream priorities without altering core Stage II water quantum. Engineering tweaks, such as reinforced canal sections and pump installations for lift schemes, were incorporated to mitigate operational inefficiencies observed in early trials, though detailed cost overruns specific to Stage II remain undocumented in beyond integrated project funding. Delays in full utilization stem from land acquisition hurdles and funding intermittency, yet recent state commitments of annual allocations exceeding Rs 18,000 signal accelerated closure. Empirical outcomes indicate partial realization of ayacut potential, with stabilized in over 150,000 hectares by mid-2020s, contingent on variability and equitable distribution.

Stage III: Current Status and Planned Expansions

Stage III of the Upper Krishna Project, intended to utilize an additional 130 TMC of water for irrigating over 500,000 hectares in northern districts, has advanced to land acquisition following cabinet approvals in September 2025. The phase focuses on raising the 's height from 519.6 meters to 524.256 meters to increase storage capacity and enable expanded canal networks for and . This expansion requires acquiring 133,867 acres of land, including 75,563 acres for submergence—90% of which is currently irrigated—51,837 acres for canals, and 6,469 acres for rehabilitation colonies. On October 10, 2025, the government issued a notification for this land acquisition, committing ₹75,000 over the next four years toward implementation. Compensation rates were set at ₹40 per for irrigated land and ₹30 per for dry land, with provisions for additional benefits like job quotas and in areas. However, farmers have expressed concerns over delayed payments and pending litigations exceeding 20,000 cases seeking higher compensation, potentially hindering progress. Planned expansions under Stage III include constructing new branch canals and lifts to command an additional 12-13 acres, prioritizing drought-prone regions in Bagalkot, , and districts. The overall phase cost is estimated at ₹70,000 , funded through state budgets and potential central assistance, though interstate disputes with over water shares may complicate execution. Physical works on modifications and are slated to commence post-acquisition, aiming for phased completion to mitigate fiscal strains.

Objectives and Empirical Achievements

Irrigation Expansion and Agricultural Outcomes

The Upper Krishna Project (UKP) has expanded across drought-prone districts in northern , primarily through Stages I and II. Stage I aims to irrigate 425,000 hectares using 119 thousand million cubic feet (TMC) of , while Stage II targets 197,120 hectares with 54 TMC, for a combined potential of 622,000 hectares. As of 2016 assessments, the project was irrigating 622,023 hectares, closely matching the planned extent for these phases and enabling a shift from predominantly rain-fed to . Stage III proposals seek further expansion, potentially adding over 500,000 hectares through schemes. This irrigation development has facilitated higher cropping intensities, often reaching two to three crops per year, and diversification toward water-intensive cash crops like , , and horticultural produce alongside staples such as and pulses. Reliable canal supplies have supported these changes, with command areas exhibiting upward trends in overall agricultural production and productivity linked to consistent water availability. Empirical evaluations highlight improved use efficiency and economic returns; for example, automated canal systems in the Narayanpur command area—part of UKP—have boosted farmer incomes through better distribution and reduced losses. Precise techniques, such as in fields, have demonstrated yield gains of 6.75% to 10.64% over conventional methods while conserving . Direct-seeded practices under UKP have further elevated benefit-cost ratios to 2.77, enhancing and profitability. Broader outcomes include elevated rural and incomes for approximately 100,000 beneficiaries, contributing to regional economic stabilization despite challenges like uneven utilization and needs. productivity analyses confirm higher output per unit of in UKP compared to adjacent rain-fed zones, underscoring causal links between expanded and agricultural intensification.

Hydropower Generation and Water Supply Benefits

The Upper Krishna Project's hydropower component centers on facilities at the Almatti and Narayanpur dams, enabling electricity generation from the Krishna River's flow. The Almatti Dam hosts a 290 MW hydroelectric power station that supplies power to Karnataka's state grid, contributing to the region's energy requirements amid growing demand. This installation harnesses regulated reservoir releases to produce electricity, with the project overall supporting an estimated annual output in the range of hundreds of millions of kilowatt-hours. In addition to power, the reservoirs provide benefits for non-agricultural , including to nearby towns and cities in northern , thereby improving access in historically drought-affected areas. The structured water management through and associated ensures more reliable for domestic and potentially uses, reducing dependency on erratic rainfall and sources. Empirical from project operations indicate that such allocations have enhanced water security, though precise volumes for non-irrigation purposes remain integrated within broader utilization plans totaling around 173 TMC for initial stages. These elements collectively mitigate energy shortages and support basic water needs, fostering socioeconomic stability in the project zones.

Broader Economic and Regional Development Impacts

The Upper Krishna Project has facilitated economic expansion in Karnataka's semi-arid northern by stabilizing for , which constitutes the primary economic activity in the region. from the project's reservoirs and canals has supported higher cropping intensities and diversification into cash crops such as and , contributing to sustained increases in agricultural output and incomes. Empirical assessments indicate yield improvements of 25-30% in command areas over two decades, driven by reliable that mitigates drought risks historically prevalent in like Bagalkot and . Employment generation represents a key channel for regional economic upliftment, with the project creating direct opportunities for around 100,000 individuals through intensified farming and ancillary activities like agro-processing. Beyond , spillover effects include non-farm jobs in , , and small-scale industries reliant on enhanced rural , fostering gradual livelihood diversification. These developments have helped curb distress from rural areas, stabilizing local economies and supporting household income resilience. On a regional scale, the project addresses developmental imbalances between Karnataka's water-scarce north and more prosperous south by bolstering GDP contributions from in beneficiary districts, though incomplete rollout has led to uneven realization of benefits across sub-command areas. integration further amplifies economic value by providing reliable electricity for agro-industries and , indirectly promoting non-agricultural growth. Overall, these impacts underscore irrigation's role in causal pathways to , albeit constrained by factors like water distribution inefficiencies.

Challenges and Operational Realities

Financial Costs, Overruns, and Funding Mechanisms

The Upper Krishna Project's financial trajectory has been marked by substantial cost overruns, driven primarily by protracted delays, expanded scopes including additional canals and rehabilitation, inflationary pressures, and escalated land acquisition expenses amid legal disputes and compensation revisions. Early phases benefited from international loans, while later stages rely heavily on state budgetary allocations, highlighting a shift toward domestic funding amid fiscal strains. Total expenditures across phases have far exceeded initial projections, with Phase III alone seeing revisions from approximately ₹51,148 to ₹87,818 as of 2025, largely attributable to land costs rising from ₹17,627 to ₹40,558 . Phase I, initiated in the late , had an initial administrative approval cost of ₹283.65 in 1978, though earlier planning estimates were as low as ₹75 for the first stage; actual costs ballooned due to construction complexities and World Bank-assisted expansions, though precise final figures remain elusive in public records beyond the framework of a $284.4 million appraisal estimate (inclusive of contingencies). Phase II, appraised at $542.2 million in the late , incurred actual costs of $755.9 million by 1997 closure, representing a 39% overrun linked to extended timelines, additional works like components, and fluctuations. These overruns underscore inefficiencies in initial scoping and execution, compounded by inter-state disputes that halted progress. For Stage III, approved post-2000 with an early 2015 estimate of ₹17,000 , costs have escalated dramatically to projections of ₹87,818 (or up to ₹1.22 including full acquisition for 1.33 ), fueled by Court-mandated revisions, farmer agitations delaying surveys, and hiked compensations—such as ₹25-40 per finalized in September 2025 for dry/irrigated . Overruns here, exceeding 70% from baseline estimates, reflect not only economic factors but also policy shifts prioritizing , with acquisition now comprising over 45% of the . Karnataka's has committed ₹18,000 annually from 2025 onward to accelerate completion, potentially reallocating from sectors like and , while seeking 25% central assistance (₹12,000 sought in July 2025 for UKP and related projects). Funding mechanisms evolved from multilateral loans in Phases I and II—where the / covered 61% via US$165 million and US$160 million , supplemented by 38% from central/state governments and minor farmer contributions—to predominantly state-led financing via Krishna Bhagya Jala Nigam Limited (KBJNL), a government undertaking responsible for execution. KBJNL draws from Karnataka's annual budgets (e.g., ₹2,500 crore supplemental in 2021 for ), internal accruals from tariffs, and ad-hoc central grants, though recoveries via water charges have lagged, covering only operational needs rather than capital repayment. This reliance exposes the project to state fiscal volatility, with criticisms of mismanagement in audits (e.g., irregularities in KBJNL's command area programs) amplifying overrun risks.

Engineering, Maintenance, and Technical Hurdles

The Upper Krishna Project has encountered significant engineering challenges, including in reservoirs and that reduces storage and conveyance capacities. In the Indi Lift , silt accumulation reaches 1-1.5 meters in deep cut sections, while the Shahapur Right Branch experiences 0.7-0.8 meters of silt in initial reaches and 0.5 meters in distributaries. These deposits, exacerbated by upstream loads and inadequate desilting, diminish designed capacities across main canals, distributaries, and laterals, contributing to overall project inefficiencies. Seepage losses represent another persistent technical hurdle, primarily due to deteriorated linings in canals such as the Indi Branch Canal, Jevargi Branch Canal, and Mudbal Branch Canal. Leakages at head regulators, escapes, and aqueducts—such as over 250 cusecs at the Mudbal Branch Canal head—further compound water wastage, with up to 69% of inputs unaccounted for in some assessments owing to seepage and lateral flows. This issue is aggravated by improper upkeep, leading to inequitable distribution where tail-end users receive deficits, as seen in D-26 of the Mudbal Branch Canal delivering under 20-25 cusecs. Maintenance deficiencies, including damaged offtake gates (with only 60-75% functional in the Shahapur Branch Canal) and unchecked jungle growth obstructing inspections, hinder operational reliability. The absence of cross-regulators, automated monitoring systems, and proper devices in secondary and tertiary canals exacerbates water level control problems, fostering unauthorized offtakes and perturbations from power shutdowns or rainfall ingress. Waterlogging emerges as a consequential and shortfall, particularly in undrained command areas like the Shahapur Branch , where surplus and impermeable substrata cause shallow stagnation, buildup, and vegetation proliferation. Subsurface interventions have been piloted in sites such as Islampur/Devapur to mitigate these effects, but widespread lags, perpetuating degradation and ecological issues like breeding. Efforts to address these hurdles through repairs and desilting, as demanded by farmers in , underscore ongoing maintenance backlogs filling channels with silt.

Social Displacement, Rehabilitation Efforts, and Outcomes

The Upper Krishna Project has displaced approximately 70,176 families, totaling around 468,000 individuals, primarily from 187 villages submerged due to filling and construction across its stages. This figure encompasses farmers, daily wage laborers, and joint family units that were largely self-sufficient through on 2.73 acres of land, including 2.3 acres of arable territory lost since began in 1974. assessments indicate broader impacts, with the Almatti alone affecting 32,673 households (142,525 people) in 95 villages, plus additional canal and road-related displacements totaling over 150,000 individuals in Bank-financed components, and potential totals exceeding 376,000–426,000 people if heights reach projected levels. Rehabilitation efforts initially relied on cash compensation under the Land Acquisition Act of 1894, supplemented by ex-gratia payments such as house construction grants of about $629 per household and land development grants ranging from $571 to $1,714, though these were often inadequate for replacement costs. By the mid-1990s, policies evolved to include "consent awards" negotiated via Lok Adalats, raising rates to Rs 70,200 per acre for dry land and Rs 1.48 per acre for irrigated land, avoiding prolonged court disputes. Displaced families were relocated to 136 resettlement centers (RCs) across five districts, with infrastructure provisions like roads, schools, and ; income restoration programs targeted , , and , while 124 RCs were transferred to local panchayats for management. Emergency relocations, such as during 1997 floods affecting 8,000 people, involved ad-hoc measures like boats and helicopters, highlighting reactive planning. Outcomes have been marked by persistent impoverishment and inadequate restoration of pre-project living standards, with evaluations noting initial mismanagement leading to two project suspensions and widespread income losses due to unreplaceable land and flawed schemes. In RCs like Ballur, residents—numbering around 3,000—face chronic shortages of potable water (relying on a single borewell and leaking tanks), absent facilities, dilapidated roads, and clogged drainage, exacerbating risks; marginal farmers depleted compensation funds rapidly amid siphoning 10–40% of payments. Household incomes stabilized at roughly $516 by 1997 post-1993 reforms, with 69% achieved, but housing sizes shrank (from 696 to 414 square feet), and deteriorated sharply, including a 15-fold surge in affected areas from 1991–1996. No comprehensive government socio-economic assessment exists—flagged by the Comptroller and Auditor General in 2015—while second-generation displacees report cultural disconnection and ongoing grievances, underscoring failures in long-term integration despite some institutional gains like grievance mechanisms.

Controversies and Disputes

Inter-State Water Allocation Conflicts

The Upper Krishna Project (UKP) has been entangled in inter-state water allocation disputes primarily involving , , and , stemming from the Krishna River's shared basin. The Krishna Water Disputes Tribunal-I (KWDT-I), constituted in and issuing its final award in June 1976, allocated 734 thousand million cubic feet (TMC) of dependable Krishna water to , intended to support projects like UKP utilizing the state's upper basin share. This allocation, with receiving 585 TMC and 811 TMC, was based on historical use, needs, and basin hydrology, but argued it underrepresented upper riparian entitlements, leading to ongoing contentions over project-specific implementations such as UKP's diversions. A focal point of conflict has been the height of the , a key UKP component on the , where seeks to increase storage to maximize its tribunal-allocated share. Initially set at 518.2 meters full reservoir level by KWDT-I to balance downstream flows, pursued elevations up to 524.25 meters, citing KWDT-II's 2010 award that permitted adjustments for and additional allocations. has repeatedly opposed this, contending that higher storage reduces releases to its downstream regions like and , prompting threats of intervention; in September 2025, Chief Minister stated the state would approach the court if proceeded with raising the height from 519 meters to 524 meters, potentially affecting 100 TMC of additional storage. 's cabinet approved land acquisition for this raise on September 17, 2025, underscoring persistent bilateral tensions despite tribunal directives. The Krishna Water Disputes Tribunal-II (KWDT-II), reporting on December 30, 2010, addressed further claims by allocating Karnataka an additional 130 TMC for UKP Stage-III, bringing its total share toward 911 TMC, but implementation has been stalled by objections from and over verification of unutilized waters and equitable division. challenged the award in the , arguing it over-allocated to upstream at downstream expense, while has pressed the for notification to operationalize UKP expansions as of May 2025. These disputes have delayed UKP's full potential, with 's utilization often contested amid claims of excess drawals during droughts, reflecting broader riparian inequities where upstream projects like UKP amplify downstream shortages without resolved return flow accounting.

Rehabilitation Shortcomings and Displacement Criticisms

The Upper Krishna Project has displaced approximately 70,176 families, totaling around 468,000 individuals, from 187 villages primarily in Bagalkot and districts, submerging 273,000 acres of land including 230,000 acres of arable farmland since land acquisition began in 1974. Rehabilitation efforts have involved relocating affected persons to 136 centers across five districts, but these sites often lack basic infrastructure such as adequate —with some centers relying on a single borewell for thousands of residents—functional toilets, paved roads, and proper drainage systems, leading to persistent health and sanitation issues. A 2015 Comptroller and Auditor General (CAG) report highlighted non-adherence to the Resettlement Act of 1987 and the National Rehabilitation and Resettlement Policy of 2007, noting the absence of updated socio-economic assessments for displaced populations. World Bank evaluations of the project's phases underscore systemic failures in resettlement, particularly the inability to allocate sufficient for livelihood restoration; in Phase I, affecting about 19,000 families, virtually no productive land was identified despite requirements for around 10,000 hectares, resulting in incomplete relocation and ongoing court cases as new villages lacked viable economic bases. Displaced farmers, many marginal or landless laborers, report widespread , with compensation funds—totaling over Rs. 2,414 crore spent on and resettlement by 2006—often depleted quickly without generating local or restoring pre-project incomes, exacerbating marginalization. The suspended twice due to these deficiencies, resuming only after government commitments to improved plans, though Phase II preparations remained weak per 1987 appraisals. Criticisms persist into recent years, with Karnataka Excise Minister R.B. Thimmapur in June 2025 publicly condemning delays in rehabilitating farmers displaced by the Almatti Dam's heightening under Phase III, attributing stagnation to administrative inaction despite allocated funds. Affected communities cite in compensation claims, inadequate land quality in allotted plots, and social fragmentation from relocation to isolated centers, where access to original networks and resources remains limited even two decades post-displacement. While some centers have been transferred to local panchayats with enhanced compensation via consent awards—such as Rs. 70,200 per acre for dry land—rejections of at least 12 sites due to resource constraints indicate unresolved implementation gaps.

Political Protests, Delays, and Regional Neglect Claims

The Upper Krishna Project, initiated in 1964 to irrigate drought-prone regions in , has faced significant implementation delays spanning over six decades, primarily attributed to and inconsistent prioritization by successive state governments. As of 2025, key phases, including the third phase involving land acquisition and canal networks, remain incomplete despite allocations exceeding ₹75,000 in recent budgets, with critics pointing to bureaucratic hurdles and electoral politics diverting funds to other regions. These delays have exacerbated in the Krishna basin, where intended beneficiaries have waited generations for promised benefits. Political protests have intensified in response to these delays, with farmers' groups staging relay hunger strikes and sieges against government offices. In December 2024, the UKP Affected Farmers Association launched protests in Bagalkot, accusing the government of financial mismanagement and demanding immediate completion of basin projects alongside fair compensation for displaced landowners. Demonstrators, supported by leaders from both and BJP, renewed agitations starting December 3, 2024, highlighting unfulfilled land rights and stalled relief payments for the third phase, which risks further losses if not addressed timely. Earlier in September 2025, farmers urged time-bound relief disbursements to mitigate acquisition-related hardships, warning of intensified unrest absent government action. Claims of regional neglect have fueled demands for separate statehood for , portraying the Krishna basin districts—such as Bagalkot and —as systematically sidelined in favor of southern and coastal areas. Protesters in December 2024 explicitly threatened a statehood movement if the government failed to expedite UKP completion, arguing that chronic underfunding reflects broader developmental disparities. Activists have criticized state planning bodies for lacking regional balance, with the Upper Krishna basin's irrigation woes cited as emblematic of 's marginalization despite the project's multipurpose mandate for and . These grievances underscore perceptions of political favoritism, where successive administrations have deprioritized arid northern districts, leading to persistent agrarian distress and heightened separatist rhetoric.

Recent Developments and Future Prospects

Ongoing Works and Policy Discussions (Post-2020)

In September 2025, the Cabinet approved Phase-III of the Upper Krishna Project (UKP-III), estimated at ₹70,000 crore, which includes raising the height of the from 519.6 meters to 524.256 meters to enhance storage capacity and facilitate for an additional 1.46 million acres across districts including , , , , Gadag, and . This phase requires the acquisition of 133,867 acres in total, comprising 75,563 acres for submergence (90% irrigated land), 51,837 acres for canal construction, and 6,469 acres for rehabilitation sites. To expedite implementation, the state government announced plans in October 2025 to establish a dedicated land acquisition authority specifically for UKP-III, addressing delays in securing the required land while integrating canal network expansions and modernization efforts under the broader project framework. Policy discussions have centered on funding sustainability, with the government committing ₹18,000 crore annually toward the project, potentially necessitating budget reallocations from sectors like education and health to cover the ₹70,000 crore land acquisition costs alone. Compensation policies for displaced farmers were revised in September 2025, offering up to ₹40 lakh per acre for affected irrigated land, alongside a new rehabilitation framework approved by the Cabinet to replace prior shortcomings, with Chief Minister Siddaramaiah urging farmers to forgo court challenges in favor of negotiated settlements finalized within weeks. Special Cabinet meetings in September 2025 resolved inter-party consensus on these measures, emphasizing the project's role in mitigating drought in northern Karnataka despite historical political delays spanning over 60 years. The overall UKP cost has escalated to ₹1.22 lakh crore, reflecting cumulative overruns but underscoring commitments to complete irrigation infrastructure amid ongoing efficiency improvements like canal lining under earlier stages.

Farmer Agitations and Implementation Pushback

In late November 2024, farmers affected by the Upper Krishna Project (UKP) in announced plans to renew agitations starting , demanding government action on land rights, , and compensation for lands acquired under the project's third phase. This followed prolonged delays in project execution, with protesters citing stalled land acquisition and inadequate resettlement as key grievances. On December 4, 2024, farmers initiated a hunger strike in , accusing the state government of financial mismanagement that had extended implementation timelines by years, exacerbating economic distress in the basin region. Implementation pushback intensified under the previous BJP-led government in 2023, when proposed compensation rates—deemed too low by affected landowners—resulted in zero voluntary land surrenders, halting Phase III progress. Farmers withheld consent, leading to legal challenges and project stagnation despite allocations for canals and reservoirs intended to irrigate over 100,000 hectares in districts like Bagalkot and . By mid-2025, concerns over resettlement delays persisted, with Excise Minister R.B. Thimmapur publicly criticizing the government for failing to provide timely housing and amenities to displaced families, affecting thousands in Bagalkot. In response, the government under escalated efforts in September 2025, announcing enhanced compensation of ₹40 per for irrigated land and ₹30 for dry land, alongside a award mechanism to expedite acquisitions. This package, covering an estimated 76,000 s of submergence and additional construction land, aimed to unlock ₹75,000 in spending over four years following the October 2025 land acquisition notification. However, farmers conditioned acceptance on time-bound payments, warning of renewed protests if delays continued, as interim crop losses from withheld land use could undermine the relief's value. These agitations reflect broader implementation hurdles, including fragmented land parcels requiring over 50,000 individual consents and historical mistrust from prior phases where lagged, leaving some oustees without promised like roads and schools. Government appeals urged farmers to avoid courts to prevent further delays, but skepticism persists amid accusations of bureaucratic inertia and funding shortfalls, with Phase III works—critical for drought-prone —remaining incomplete as of late 2025.

References

  1. [1]
    KRISHNA BHAGYA JALA NIGAM LIMITED - Upper Krishna Project
    The Upper Krishna Project consists of construction of two dams across the river Krishna and a network of canals. The main storage is at Almatti Dam, ...
  2. [2]
    Upper Krishna Project | Bagalkote District | India
    The Upper Krishna Project (UKP) is an irrigation project across the Krishna River to provide irrigation to the drought-prone areas of Bijapur, Bagalkot, ...
  3. [3]
    Brief-history-of-upper-krishna-project - ಕೃಷ್ಣ ಭಾಗ್ಯ ಜಲ ನಿಗಮ ನಿಯಮಿತ
    The Upper Krishna Project was originally conceived by the erstwhile State of Hyderabad along with the Lower Krishna Project (now known as Nagarjunasagar project) ...
  4. [4]
    [PDF] UKP Stage-II
    Upper Krishna Project Stage-II is a multipurpose project to utilise 54 tmc of water and to irrigate 1.97 lakh ha. of land. The projects included in Stage-II ...
  5. [5]
    [PDF] PROGRESS REPORT OF UPPER KRISHNA PROJECT AS AT 31
    Jun 30, 2023 · The Upper Krishna Project (UKP) Stage-III is designed to provide irrigation to 5.94 lakh. Hectares area situated in Vijayapura, Bagalkote,.
  6. [6]
    [PDF] 40 years of upper krishna project
    The Upper Krishna Project is a mega project and the largest multi-purpose project in Karnataka State. A comprehensive document on this was a long felt need. It ...
  7. [7]
    BRS questions Congress silence over Karnataka's resolution to ...
    Sep 19, 2025 · The Congress-led Karnataka government argues the project will bring huge benefits, saying 12 to 13 lakh acres will come under irrigation.
  8. [8]
    60 years on, Upper Krishna Project still incomplete due to political ...
    Jun 7, 2025 · Bagalkot: Although the Upper Krishna Project (UKP) was initiated in 1964, even after 60 years, the project remains incomplete.Missing: facts history
  9. [9]
    Farmers Unite for Indefinite Agitation Demanding Upper Krishna ...
    Dec 3, 2024 · Former MLC GS Nyamagouda criticised CM Siddaramaih for backing out on his promise of completing the project by providing Rs 40,000 crore every ...Missing: achievements | Show results with:achievements
  10. [10]
    Upper Krishna Project becomes a victim of widespread waste ...
    Aug 15, 1986 · The Upper Krishna Project began in the late 1950s as a relatively modest irrigation scheme designed to cover about 2.6 million acres of parched territory.Missing: facts | Show results with:facts
  11. [11]
    [PDF] Upper Krishna Irrigation Project (02) - The World Bank
    Aug 13, 2024 · for the first time in the history of Karnataka the legal right to resettlement and rehabilitation for all persons displaced. 7. Mr. Nayak's ...<|separator|>
  12. [12]
    Upper Krishna: displaced people in deep water - Deccan Herald
    Jan 12, 2019 · In its 1998 report, the World Bank noted that resettlers were upset at the compensation process.Missing: controversies | Show results with:controversies
  13. [13]
    [PDF] final environment impact assessment report - environmental clearance
    Aug 1, 2016 · The Upper Krishna Project was originally conceived by the erstwhile State of Hyderabad along with the Lower Krishna Project (now known as ...<|separator|>
  14. [14]
    40 Yrs UKPHistory | PDF | Dam | Water Resources - Scribd
    The document summarizes the 40-year history of the Upper Krishna Project in Karnataka, a major irrigation project. It details the project's conception in ...
  15. [15]
    [PDF] lift irrigation schemes in bagalkot district under uppar krishna project
    The Vijayapura Lift Irrigation Scheme was a plan in this direction that was created in 1950. (subsequently called the Mulwad Lift Irrigation. Scheme). The Upper ...Missing: early | Show results with:early
  16. [16]
    Irrigation Developments in the Krishna Basin since 1947 - jstor
    Upper Krishna project.20 Project administrators were organizing conferences ... sively on head-end lands during the early years of a project, when the dam.
  17. [17]
    [PDF] Krishna Basin - Version 2.0
    The practice of basin planning has developed due to the changing demands on river systems and the changing conditions of rivers by human interventions. The ...<|separator|>
  18. [18]
    India's Upper Krishna Irrigation Project, 1964-present
    In 1964, construction began on the Upper Krishna Project, an irrigation works in the Indian state of Karnataka; fifty years and several highly-publicized rounds ...Missing: origins early planning
  19. [19]
    Impact of Developmental Interventions in Upper Krishna Project ...
    The Upper Krishna Project (UKP) is one of the biggest projects in India and was started as multipurpose irrigation project in the drought prone northern ...Missing: facts | Show results with:facts
  20. [20]
    India - Upper Krishna (Phase II) Irrigation Project (English)
    The project will support phase II of the first stage of the Upper Krishna Program, which is a long term 2-stage, multi-phase plan to develop the irrigation ...
  21. [21]
    Recent experience with involuntary resettlement - India
    The Upper Krishna Project (UKP) is the largest resettlement operation the World Bank has ever supported. The project's objective was the construction of dams onMissing: involvement | Show results with:involvement
  22. [22]
    Basava Sagara - Wikipedia
    The dam is 29 meters high and over 10.637 kilometres (6.610 mi) long, and has 30 gates for water release. 22 Spillway Gates are present in the Dam It took Rs.
  23. [23]
    UKP STATUS - Angelfire
    PROGRESS OF UPPER KRISHNA PROJECT. AS AT 31st MARCH 1999. PROGRAM. PROGRESS. NARAYANPUR DAM AND ALLIED WORKS. COMPLETED. ALMATTI DAM AND ALLIED WORKS. LEFT BANK ...
  24. [24]
    Almatti Dam | Vijayapura District, Government Of Karnataka | India
    The annual electric output of the dam is 713,000,000 kilowatts (KW). The Almatti Dam is the main reservoir of the Upper Krishna Irrigation Project; the 290 ...
  25. [25]
    Almatti Dam - INSIGHTS IAS
    Sep 24, 2025 · About Almatti Dam: What it is? A hydroelectric and irrigation project forming the main reservoir of the Upper Krishna Irrigation Project.
  26. [26]
    KRISHNA BHAGYA JALA NIGAM LIMITED - Health-wing
    The Upper Krishna Projectis the biggest Irrigation project in Karnataka covering the districts of Bijapur, Bagalkot, Yadgir and Raichur Districts.
  27. [27]
    [PDF] preliminary report for remodelling of narayanpur left bank canal and ...
    The canal network is under irrigation since from 2001. The construction of main canal from 0.00 to 18.00km and distributaries 1 to 4 were taken up and ...
  28. [28]
    [PDF] Almatti Dam Salient Features Photo
    Irrigation System. Under 1st Stage Lift : Canal Network Irrigation. West Main Canal : 61 Km (Dy.1 to 25). East Main Canal : 54 Km (Dy.1 to 22). Under 2nd Stage ...
  29. [29]
    [PDF] progress report of upper krishna project as on 31.12.2021
    Dec 31, 2021 · The intended project for providing irrigation facility through canal network is under progress. 15 Yalligutti Lift Irrigation. Scheme. 700. 0.
  30. [30]
    Almatti Dam | Bagalkote District | India
    The Almatti Dam is the main reservoir of the Upper Krishna Irrigation Project; the 290 MW power station is located on the right side of the Almatti Dam. The ...
  31. [31]
    Karnataka proceeds with Upper Krishna project
    Jul 17, 2000 · The Supreme Court of India recently allowed Karnataka to raise the dam to 519.6m, which is still below the proposed height of 524m. The final ...Missing: specifications | Show results with:specifications
  32. [32]
    [PDF] KRISHNA BHAGYA JALA NIGAM LIMITED - environmental clearance
    Upper Krishna irrigation project across Krishna river provides irrigation facility to desert areas of Bijapur district and drought prone areas of Bagalakot, ...
  33. [33]
    Almatti Dam – CrackitToday Affairs
    Sep 17, 2025 · The dam holds a gross water storage capacity of 123.08 TMC at 519 meters MSL. Standing at a height of 52.5 meters and extending 3.5 kilometers ...Missing: FRL | Show results with:FRL
  34. [34]
    KRISHNA BHAGYA JALA NIGAM LIMITED - Upper-krishna-project
    The Upper Krishna Project consists of construction of two dams across the river Krishna and a network of canals. The main storage is at Almatti Dam, ...
  35. [35]
    [PDF] PROGRESS REPORT OF UPPER KRISHNA PROJECT AS AT 31
    Dec 31, 2022 · Wadavatti Branch Canal km 0.00 to. Page 3. 10.00 has been completed and canal network from km 10.00 to 28.77 works are in completion stage and ...Missing: milestones | Show results with:milestones
  36. [36]
    multi-page.txt - World Bank Documents
    The Upper Krishna Scheme has been under construction since the 1960s; the first stage Involves the construction of two dams and the irrigation of 425,000 ha; it ...<|separator|>
  37. [37]
    KRISHNA BHAGYA JALA NIGAM LIMITED - Erm-works-details
    PHYSICAL PROGRESS DETAILS · Already the remodeling of Main / Branch Canals of NLBC, HBC, SBC, MBC, JBC and IBC (KM 0.00 to 64.00) were completed and water was ...
  38. [38]
    Govt commits to spending Rs 18,000 crore annually on Upper ...
    Oct 11, 2025 · "Initial project cost was Rs 51,148 crore, revised to Rs 87,818 crore. Land acquisition was Rs 17,627 crore, now Rs 40,558 crore," he said, ...
  39. [39]
    Karnataka Cabinet approves Upper Krishna Project Phase-3
    Sep 17, 2025 · The project will require 1,33,867 acres, including 75,563 acres which will submerge, 51,837 acres for canals, and 6,469 acres for rehabilitation ...Missing: III expansions
  40. [40]
    UKP phase-III: Cabinet gives nod for acquisition of 1.33 lakh acres in ...
    Sep 16, 2025 · Cabinet approves land acquisition for Almatti dam height increase, farmers to receive compensation, total project cost ₹70000 crore.Missing: expansions | Show results with:expansions
  41. [41]
    Karnataka enhances compensation for UKP-III land acquisition
    Sep 16, 2025 · Karnataka Chief Minister Siddaramaiah announced a substantial hike in compensation for farmers whose land will be acquired for phase III of ...<|separator|>
  42. [42]
    Karnataka govt. notifies land acquisition for UKP-III - The Hindu
    Oct 10, 2025 · A total of 1,33,867 acres would be acquired for increasing the height of the Almatti dam from 519.60 metres to 524.256 metres. Land would be ...
  43. [43]
    Karnataka cabinet approves UKP Phase-3, to increase height of ...
    Sep 17, 2025 · Height to go up from 519.6m to 524.25m Requires 1.33 lakh acres, including 75,563 acres that'll submerge Compensation of `40L/acre for ...<|control11|><|separator|>
  44. [44]
    UKP 3rd phase: Farmers demand time-bound payment of relief
    Sep 17, 2025 · Farmers in Upper Krishna Project area seem to be reluctantly agreeing to uniform price fixed by the state with a rider that the land acquisition ...
  45. [45]
    Litigation will only delay UKP Stage-3, CM Siddaramaiah tells farmers
    Sep 7, 2025 · Legal battles will only delay justice and the project's progress. ... “The government is committed to completing UKP Stage-3 at the earliest,” he ...
  46. [46]
    Karnataka Announces ₹40 Lakh Per Acre for Irrigated, ₹30 Lakh ...
    Sep 17, 2025 · Chief Minister Siddaramaiah revealed that the height of the Almatti Dam will be raised from 519.6 metres to 524.256 metres, which will submerge ...<|separator|>
  47. [47]
    karnataka upper krishna irrigation project rs 70,000 crore ... - NDTV
    Sep 19, 2025 · This phase will involve increasing the height of the Almatti dam from 520 to 524 metres. The raised levels will lead to around 76,000 acres of ...Missing: progress modifications
  48. [48]
    Karnataka to acquire 75,563 acres for Upper Krishna Project Phase-3
    Oct 13, 2025 · To implement Phase-3 of the Upper Krishna Project (UKP), including raising the Almatti dam height from 519.6 mtrs. to 524.256 mtrs., ...Missing: initial | Show results with:initial<|separator|>
  49. [49]
    (PDF) Agricultural diversification in the Upper Krishna river basin, India
    Apr 19, 2025 · Regular water supply to crops along with other inputs goes to a long way in increasing the production and productivity of the agriculture sector ...
  50. [50]
    [PDF] Impact of Automated Canal Irrigation System on Farmers' Income in ...
    The adoption of the automated canal irrigation system in the NLBC command area of the Upper Krishna. Project has significantly enhanced key performance.
  51. [51]
    [PDF] Assessment of Irrigation Methods on Water Productivity, Growth and ...
    irrigated area in Upper Krishna Project (UKP) com- mand area. The upper end ... There was increase in crop yield of 10.64 % and 6.75 % in TO1 and TO2 ...<|separator|>
  52. [52]
    [PDF] Impact of Direct Seeded Rice in Paddy Crop under Upper Krishna ...
    Jan 20, 2020 · Increase in crop yield stretched the B:C ratio up to Rs. 2.77 higher than traditional practices. It also helps in maintaining soil health by ...
  53. [53]
    [PDF] an economic evaluation of water productivity - krishikosh
    Page 1. AN ECONOMIC EVALUATION OF WATER PRODUCTIVITY. IN UPPER KRISHNA PROJECT (UKP) AND MALAPRABHA. GHATAPRABHA PROJECT (MGP) COMMAND AREAS IN. KARNATAKA.
  54. [54]
    address during the dedication of the Upper Krishna Project to ... - PIB
    Aug 21, 2006 · I dedicate the Upper Krishna Project to the Nation and wish success in the mission of providing quality water in adequate quantities for ...Missing: reservoirs | Show results with:reservoirs
  55. [55]
    Almatti Dam - GKToday
    Sep 14, 2019 · Hydropower generation: Houses a 290 MW hydroelectric power station, supplying electricity to the state grid. Drinking water supply: Supplies ...
  56. [56]
    [PDF] Irrigation Projects as a Solution to Regional Disparity: A Strategic ...
    May 5, 2025 · The Upper Krishna Project, for instance, has enabled farmers in the command area to transition from rain-fed farming to irrigation-based farming ...
  57. [57]
    ₹87,818 crore will be required for UKP phase-III: CM - The Hindu
    Sep 10, 2025 · Chief Minister Siddaramaiah on Wednesday said an estimated ₹87,818 crore would be required for implementation of the Upper Krishna Project ...Missing: expenditure | Show results with:expenditure
  58. [58]
    [PDF] mobilisation of world bank funding for the upper krishna ... - ¸ÀÈd¤
    UPPER KRISHNA PROJECT. The Upper Krishna Project was originally conceived by the then-state of. Hyderabad along with the Lower Krishna. Project (now known as ...
  59. [59]
    [PDF] The World Bank
    Jun 29, 1998 · Upper Krishna. Irrigation/Phase II is such a project, being part of the larger Upper Krishna Project development program. Sunk cost from ...Missing: history | Show results with:history
  60. [60]
    Karnataka gives Rs 2500 crore boost to Upper Krishna Project
    Sep 29, 2021 · An official said the allocation of Rs 2,500 crore will give a big push to the project. In the budget, Rs 1,200 crore was allocated and of that, ...
  61. [61]
    [PDF] Answer
    874.83 lakh reportedly the expenditure incurred by Krishna Bhagya Jal Nigam (KBJNL) for implementation of the Command Area Development Programme under Upper ...
  62. [62]
    [PDF] Masscote applications in Upper Krishna project - KJBNL
    The Upper Krishna Irrigation Systems is a set of systems using water from the Naryanpur reservoir located in the downstream part of the Upper Krishna. A total ...
  63. [63]
    (PDF) Subsurface Drainage to Combat Waterlogging and Salinity in ...
    Aug 10, 2025 · 1). Islampur/Devapur pilot area is located in the Upper Krishna. Project ... seepage from the canal. network, lack of land development ...
  64. [64]
    Farmers seek repairs to Upper Krishna canals - The Hindu
    Apr 4, 2015 · Due to improper upkeep and lack of maintenance, several channels coming under left bank canal of Upper Krishna Project are filled with silt ...Missing: siltation | Show results with:siltation
  65. [65]
    [PDF] Involuntary Resettlement - World Bank Documents and Reports
    Socio-Economic Survey ofProject Displaced Families Under Narayanpur Reservoir Area, Upper Krishna Project: Summary (Final) Report, Om Consultants (India) ...
  66. [66]
    [PDF] further report of the krishna water disputes tribunal
    The Krishna Water Disputes Tribunal investigated the matters referred to it under section 5 (1) of the Inter-State Water Disputes Act, 1956 and forwarded its.
  67. [67]
    BJP delegation meets Union Minister over raising Almatti Dam ...
    Aug 7, 2025 · Bommai said that the Krishna Water Disputes Tribunal II has approved raising the height of the Almatti dam to 524 m. “Prior to this, a joint ...
  68. [68]
    Maharashtra will move SC if Karnataka goes ahead with plan to ...
    Sep 17, 2025 · The proposal involves raising the dam height from 519 metres to 524 metres, increasing storage capacity by 100 TMC ft. To implement this, the ...Missing: dispute | Show results with:dispute
  69. [69]
    Karnataka's push on Almatti Dam height sets off Congress vs ...
    Sep 23, 2025 · On September 17, the Karnataka Cabinet decided to raise the Almatti Dam's height from 519.6 metres to 524.25 metres, claiming that the height ...
  70. [70]
    Karnataka gears up to put pressure on Centre to issue notification ...
    May 3, 2025 · The KWDT-II allocated 73 tmcft of water to Karnataka, of which 130 tmcft has been allocated for the Upper Krishna Project-III (UKP-III). All ...Missing: inter- conflicts
  71. [71]
    Upper Krishna Project: Consensus tough but necessary
    Aug 28, 2025 · The Upper Krishna Project (UKP) has long been envisioned as a lifeline for the parched districts of North Karnataka.
  72. [72]
    [PDF] India - Second Upper Krishna Irrigation Project (02) Phase II
    Jun 3, 2024 · The records in this folder were created or received by The World Bank in the course of its business. The records that were created by the staff ...
  73. [73]
    Ground realities - Frontline - The Hindu
    Nov 3, 2006 · The families displaced by the Upper Krishna Project in Karnataka are unhappy at the rehabilitation centres. RAVI SHARMA in Bagalkot.Missing: GDP | Show results with:GDP
  74. [74]
    Karnataka Minister RB Thimmapur criticises own government over ...
    Jun 30, 2025 · Karnataka Excise Minister RB Thimmapur criticised his own government over delays in rehabilitating farmers displaced by the Almatti dam.
  75. [75]
    Farmers in Upper Krishna Project Set to Renew Agitation for Land ...
    Nov 29, 2024 · Farmers impacted by the Upper Krishna Project are mobilizing for a renewed agitation starting December 3 to demand government action on land ...
  76. [76]
    Karnataka: Farmers protest over delay in Krishna Upper River ...
    Dec 4, 2024 · Farmers have launched a relay hunger strike, calling for immediate action and accusing the government of financial mismanagement over the prolonged delay in ...
  77. [77]
    Protesting farmers make an attempt to lay siege to rehabilitation ...
    Dec 5, 2024 · UKP Affected Farmers Association demands completion of Krishna basin projects and fair compensation, staging protest in Bagalkot.
  78. [78]
    Bagalkot farmers protest gets support of leaders from ... - The Hindu
    Dec 5, 2024 · Leaders from Congress and BJP support Bagalkot farmers' protest for timely completion of Upper Krishna irrigation projects.
  79. [79]
    Farmers protest over neglect of Upper Krishna Project, threaten to ...
    Dec 6, 2024 · The farmers have threatened to begin a protest demanding a separate statehood for North Karnataka if the demands are not fulfilled.<|separator|>
  80. [80]
    Activists slam govt over lack of regional balance in planning body ...
    Sep 13, 2025 · "The Upper Krishna Project is a burning issue, and farmers of the Krishna River basin are struggling to get a price for their land for the third ...
  81. [81]
    Karnataka to set up authority for land acquisition, raising height of ...
    Oct 10, 2025 · BENGALURU: To implement the Upper Krishna Project (UKP) Phase-3, which also involves raising the height of the Almatti dam from 519.6m to ...
  82. [82]
    Karnataka Upper Krishan Project III farmers to get Rs 40 lakh per ...
    Sep 16, 2025 · Chief Minister Siddaramaiah stated that the Almatti Dam height will be raised from 519.6 metres to 524.256 metres, a move that will submerge ...Missing: 2021-2025 | Show results with:2021-2025<|control11|><|separator|>
  83. [83]
    Compensation package for Upper Krishna Project third phase, to be ...
    Sep 6, 2025 · Siddaramaiah said under the third phase of Upper Krishna Project height of Almatti dam would be increased from 519.6 m to 524.25 m to store 130 ...<|separator|>
  84. [84]
    Karnataka cabinet takes major decisions on Upper Krishna Project ...
    Sep 18, 2025 · We have decided to bring in a new policy for rehabilitation." The Upper Krishna Project, a major irrigation scheme designed to improve water ...
  85. [85]
    Special Cabinet meeting on September 16 to discuss UKP-III
    Sep 11, 2025 · State government plans special Cabinet meeting to resolve land acquisition issue for Upper Krishna Project Phase III.
  86. [86]
    Upper Krishna Project: K'taka Govt Prioritises Rapid Implementation ...
    Sep 16, 2025 · The Cabinet resolved that Rs 25 lakh per acre should be given as compensation for dryland and Rs 30 lakh per acre for irrigated land acquired ...<|separator|>
  87. [87]
    Upper Krishna Phase 3: Minister slams Karnataka govt for delay in ...
    Jun 27, 2025 · Upper Krishna Phase 3: Minister R.B. Thimmapur slams Karnataka government over delay in resettlement and rehabilitation. Says he will appeal to ...Missing: displaced families<|separator|>
  88. [88]
    Relief package to UKP-3 landlosers: State to announce consent ...
    Sep 6, 2025 · Relief package to UKP-3 landlosers: State to announce consent award soon. Siddaramaiah appealed to farmers not to approach the court seeking an ...