Vogtle Electric Generating Plant

The Vogtle Electric Generating Plant is a four-unit situated near , operated by Southern Nuclear Operating Company and primarily owned by , with a total of approximately 4,664 megawatts, establishing it as the largest nuclear facility in the United States. Units 1 and 2, traditional , commenced commercial operations on June 1, 1987, and May 20, 1989, respectively, providing baseload electricity with a combined capacity of about 2,430 megawatts. Units 3 and 4, employing advanced designs, represent the first newly constructed nuclear units in the United States in over three decades, achieving commercial operation on July 31, 2023, and April 29, 2024, respectively, each with a net capacity exceeding 1,100 megawatts. The plant generates over 30 million megawatt-hours of carbon-free electricity annually, sufficient to power more than 800,000 homes, underscoring its role as the nation's largest producer of clean . Despite initial projections for Units 3 and 4 completion by 2016–2017 at a cost of $14 billion, the project encountered substantial delays and escalated to over $30 billion due to complexities, supply chain issues, and the 2017 of prime contractor , yet persevered to deliver reliable, high-capacity amid a landscape where similar initiatives were abandoned.

Site Overview

Location and Ownership

The Vogtle Electric Generating Plant is situated in , near the city of Waynesboro and along the in the . The site occupies approximately 3,100 acres, providing space for cooling reservoirs, transmission infrastructure, and environmental buffers. Ownership of the plant is shared among four utility entities, reflecting a cooperative model common for large-scale nuclear projects in the region. , a subsidiary of , holds the largest stake at 45.7%. Oglethorpe Power Corporation, representing Georgia's electric membership cooperatives, owns 30%; the Municipal Electric Authority of Georgia (MEAG Power) possesses 22.7%; and Dalton Utilities maintains a 1.6% share. This structure distributes financial and operational responsibilities across investor-owned, cooperative, and municipal interests. Southern Nuclear Operating Company, also under , serves as the licensed operator for all four units, managing daily activities, , and under oversight from the U.S. .

Capacity and Operational Status

The Vogtle Electric Generating Plant features four units with a combined net summer generating capacity of 4,530 megawatts (MW), making it the largest in the United States. Units 1 and 2, four-loop designs, each provide approximately 1,215 MW of net capacity, for a combined output of 2,430 MW. Unit 1 entered commercial operation on June 1, 1987, followed by Unit 2 on May 20, 1989. Units 3 and 4, based on the two-loop design, each deliver a net capacity of 1,117 MW. Unit 3 achieved commercial operation on July 31, 2023, after completing required testing and inspections, while Unit 4 reached this milestone on April 29, 2024. These additions increased the plant's total capacity by over 2,200 MW, enabling annual generation of more than 17 million megawatt-hours of electricity. As of October 2025, all four units remain fully operational, with no extended outages reported by the . , the primary owner and operator, has proposed measurement uncertainty recapture power uprates totaling 112 MW across the units between 2028 and 2034 to further enhance output based on refined instrumentation accuracy.

Original Construction: Units 1 and 2

Development and Commissioning

Georgia Power Company began planning the Alvin W. Vogtle Electric Generating Plant in 1971 as part of efforts to expand baseload power generation in Georgia. The U.S. Nuclear Regulatory Commission issued construction permits for Units 1 and 2 in 1974, authorizing site preparation and facility construction under the Atomic Energy Act. Construction officially commenced on August 1, 1976, with both units featuring Westinghouse four-loop pressurized water reactors designed for a net electrical output of approximately 1,150 megawatts per unit. Development proceeded amid the broader challenges facing U.S. nuclear projects in the late and , including regulatory enhancements following the 1979 , which imposed additional safety analyses and design modifications. For Unit 1, the NRC granted the facility operating license on March 16, 1987, enabling low-power testing and eventual synchronization to the grid. Commercial operation followed on June 1, 1987, after completion of startup testing and verification of safety systems. Unit 2 mirrored this timeline with some delay, receiving its operating license on March 31, 1989. The unit achieved commercial operation on May 20, 1989, marking the full commissioning of the original two-unit plant and contributing over 2,000 megawatts of carbon-free electricity to the regional grid. Southern Nuclear Operating Company, a subsidiary of Southern Company, assumed operational responsibility for both units upon startup.

Operational Performance and Upgrades

Units 1 and 2 have demonstrated reliable operational performance since commercial operation began on June 1, 1987, for Unit 1 and May 20, 1989, for Unit 2, with refueling cycles typically every 18 months. The units have achieved high capacity factors, exemplified by Unit 2's summer capacity factor of 102.5% in 2021, surpassing the U.S. fleet average. Three-year net capacity factors for U.S. reactors, including those at Vogtle, averaged around 91% from 2022 to 2024, reflecting minimal unplanned outages and effective maintenance. Refueling outages have been shortened through optimized scheduling and execution, enhancing overall availability. In fall 2017, Unit 2 completed a refueling outage in 17 days, 5 hours, and 36 minutes, establishing a Southern Nuclear fleet record and returning to full power ahead of schedule. Similarly, a prior Unit 2 outage concluded 32.5 hours early, underscoring improvements in outage management. These metrics indicate strong operational discipline, contributing to sustained exceeding 30 TWh annually across both units in recent years. Key upgrades have focused on increasing output and extending service life. The NRC approved a stretch power uprate for both units in March 1993, following an application submitted in February 1992, which raised thermal capacity from original levels to support higher net electrical output. License renewals granted in June 2009 extended operations to January 16, 2047, for Unit 1 and February 9, 2049, for Unit 2, based on assessments confirming aging management adequacy. In July 2025, the Public Service Commission approved further upgrades for Units 1 and 2, enabling an additional 54 MW total capacity (approximately 27 MW per unit) through efficiency enhancements scheduled from 2028 to 2034, aimed at extending runtimes and reducing outage frequency.

Key Incidents and Reliability

Units 1 and 2 at the Vogtle Electric Generating Plant have maintained high operational reliability since their respective commercial operations began on , 1987, and May 20, 1989, with three-year rolling s averaging over 90 percent as reported by the plant's primary operator. This performance aligns with broader U.S. trends, where Vogtle Unit 1 achieved a of 95.32 percent in evaluated periods, reflecting effective maintenance and minimal forced outages. Recent (NRC) integrated inspections, such as the 2024 review covering Units 1 and 2, identified no significant safety or reliability deficiencies, affirming compliance with operational standards. A notable early incident occurred on March 20, 1990, when Vogtle Unit 2, operating at 100 percent power, experienced a loss of offsite power to vital buses due to a spurious breaker actuation, compounded by a in one emergency diesel generator, leading to a brief station blackout condition and declaration of an —the second-lowest emergency classification. Operators restored power using the remaining diesel generator and offsite sources within hours, with no radiological release or core damage; Unit 1 was in refueling outage at the time and unaffected directly. The NRC issued Information Notice 91-034 detailing the event, highlighting risks of common-mode s in vital power systems, though no enforcement action ensued as recovery procedures proved adequate. In terms of regulatory enforcement, Southern Nuclear Operating Company faced a Severity Level III violation in the early 2000s for failing to perform required periodic channel calibrations on post-accident monitoring since Unit 1's initial startup, prompting escalated NRC to address procedural lapses in safety system maintenance. More recently, in , the NRC proposed a $145,000 against Southern Nuclear for deliberate document falsification by a involving records on safety-related at Units 1 and 2, underscoring isolated issues but not impacting ongoing operations. These events, while requiring corrective actions, have not compromised the units' overall safety record, as evidenced by subsequent NRC performance assessments rating both units as green (full-performance category) in most pillars. Operational reliability has been further supported by upgrades, including the introduction of enhanced accident-tolerant fuel in Unit 2 during a refueling outage, which completed successful inspections after 36 months without performance degradation. Unplanned shutdowns remain infrequent; for instance, a July 2024 trip on one unit stemmed from a main feedwater valve malfunction causing steam generator level transients, resolved without broader safety implications per NRC oversight. Collectively, these factors demonstrate robust reliability, with no Level 2 or higher events on the International Atomic Energy Agency's for Units 1 and 2.

Expansion Project: Units 3 and 4

Planning and Regulatory Approval

The planning for the expansion of the Vogtle Electric Generating Plant to include Units 3 and 4 originated in the mid-2000s amid renewed interest in following the , which provided production tax credits and loan guarantees to support new reactor construction. Southern Nuclear Operating Company, acting on behalf of the plant's co-owners— (45.7% ownership), Oglethorpe Power Corporation (30%), Municipal Electric Authority of Georgia (22.7%), and the City of Dalton Utilities (1.6%)—identified the Vogtle site as suitable for two additional pressurized water reactors, each rated at approximately 1,117 megawatts electric. This decision leveraged the existing infrastructure from Units 1 and 2, operational since the , to minimize new site development needs while addressing projected electricity demand growth in . Regulatory approval began with the submission of an Early Site Permit (ESP) application to the U.S. (NRC) as part of the streamlined licensing process under 10 CFR Part 52, which allows for early site characterization separate from design and operational reviews. The NRC issued ESP-4 on August 26, 2009, authorizing site preparation activities and limited construction not affecting safety-related structures, marking the first such permit referencing a certified reactor design (). Concurrently, on March 28, 2008, Southern Nuclear submitted the Combined License Application (COLA) for Units 3 and 4, seeking integrated approval for construction and operation. The NRC granted the COLs (NPF-91 for Unit 3 and NPF-92 for Unit 4) on February 10, 2012, after a multi-year review involving public hearings, environmental assessments, and safety evaluations, including confirmation of compliance with seismic, emergency preparedness, and financial qualification standards. This approval enabled full construction commencement, with the COL process incorporating the previously certified design to reduce licensing uncertainties. At the state level, the Public Service Commission certified the project in early , allowing cost recovery through rate base mechanisms contingent on milestones. These federal and state approvals positioned Vogtle as the first new U.S. nuclear units to proceed under the modern framework, though subsequent delays highlighted challenges in first-of-a-kind engineering validations.

Technological Design and Innovations

Units 3 and 4 at the Vogtle Electric Generating Plant utilize the , a Generation III+ (PWR) design featuring a two-loop configuration that generates over 1,100 megawatts electric per unit. This evolutionary advancement over prior PWR generations incorporates a simplified with reduced components, including fewer safety-related valves, pumps, and piping, which minimizes potential failure points and enhances operational reliability. The AP1000's hallmark innovation lies in its fully passive safety systems, which enable core cooling and reactor shutdown without reliance on external power, operator intervention, or active mechanical components for up to 72 hours following an incident. These systems leverage natural forces such as gravity, natural circulation, and convection; for instance, the passive core cooling system directs water from elevated tanks directly into the reactor core or via heat exchangers, while the passive cooling system uses a vessel surrounded by a water storage tank for heat dissipation through evaporation and radiation. This design provides multiple layers of defense-in-depth, addressing scenarios like station blackout, and contrasts with earlier reactors that depend on generators and pumps for cooling. Modular construction represents another key , with large structural modules prefabricated in factories and transported to the for assembly, reducing on-site labor hours by approximately 30-45% compared to traditional stick-built methods and improving through controlled manufacturing environments. At Vogtle, this approach facilitated the installation of over 200 modules per unit, including the Passive Cooling Water Storage Tank (CB-20), a critical passive component completed in 2021. The design also features advanced digital instrumentation and control systems, fully integrated and automated, which streamline operations, reduce cabling by up to 80% in safety systems, and support . Additional design elements include a compacted footprint with reduced seismic building volume for enhanced structural integrity and a canned rotor configuration in the coolant to eliminate seal failures, contributing to higher and longer operational cycles. These features collectively position the as a standardized, scalable platform for future deployments, drawing on decades of PWR experience while prioritizing and economic viability.

Construction Timeline and Milestones

Construction activities for Vogtle Units 3 and 4 initiated with site preparation and limited work authorization in 2009, preceding full regulatory approval. The U.S. issued combined licenses (COLs) on February 10, 2012, enabling nuclear-specific construction. These approvals followed earlier early site permits and represented a critical step after years of planning under the design certification. The pouring of first nuclear concrete for Unit 3 commenced on March 12, 2013, and concluded on March 14, 2013, encompassing about 7,000 cubic yards for the nuclear island basemat. Unit 4 followed with its basemat concrete placement later in 2013. Subsequent milestones included the installation of the CA-20 module in 2016, one of the heaviest lifts at over 2 million pounds. In April 2017, Bechtel assumed primary responsibility for construction from Westinghouse, amid ongoing delays from design revisions and quality issues. Unit 3 advanced to initial fuel loading in late 2022, achieving first criticality on March 6, 2023. It synchronized with the on April 1, 2023, and entered commercial operation on July 31, 2023. For Unit 4, initial criticality occurred on February 14, 2024, followed by grid synchronization on March 1, 2024, and commercial operation on April 29, 2024. The project, originally targeting in-service dates of 2016 and 2017, experienced multiple extensions due to supply chain disruptions, regulatory inspections, and contractor changes, ultimately spanning 15 years from early works to full completion.
MilestoneUnit 3 DateUnit 4 DateNotes
Site Preparation Begins20092009Early works under LWA
COL IssuanceFebruary 10, 2012February 10, 2012NRC approval
First Nuclear ConcreteMarch 12-14, 2013November 2013Basemat pour
CA-20 Module Installation2016N/AHeavy lift milestone
Bechtel Takes Over ConstructionApril 2017April 2017Management transition
Initial CriticalityMarch 6, 2023February 14, 2024Reactor startup
Grid SynchronizationApril 1, 2023March 1, 2024First power generation
Commercial OperationJuly 31, 2023April 29, 2024Full revenue service

Financial Challenges and Westinghouse Bankruptcy

The Vogtle Units 3 and 4 expansion project faced escalating financial pressures from the outset, driven by the complexities of deploying first-of-a-kind pressurized water reactors. Initial cost estimates in 2009 pegged the total project at approximately $14 billion, with commercial operation targeted for 2016 and 2017, respectively. By 2017, expenditures had already surpassed $9 billion amid delays in licensing, disruptions, and iterative design modifications required by the . These challenges compounded as progressed, pushing cumulative costs to over $25 billion by 2018 and ultimately exceeding $30 billion upon completion in 2024, representing more than a doubling of the original budget. The overruns stemmed partly from the fixed-price (EPC) contract structure, which incentivized aggressive bidding but exposed contractors to unforeseen technical hurdles in modular and integrated safety systems. Westinghouse Electric Company, as the prime EPC contractor responsible for design, engineering, and much of the construction, absorbed substantial losses that precipitated its financial collapse. The firm, owned by Japan's Corporation, had committed to delivering the units under a turnkey agreement, but escalating on-site rework, labor shortages, and subcontractor disputes inflated its liabilities. Parallel issues at the V.C. Summer project in amplified the strain, with combined overruns exceeding $10 billion across both sites by early 2017. On March 29, 2017, Westinghouse filed for Chapter 11 bankruptcy protection in U.S. courts, citing $5.8 billion in project-related debts as the primary trigger. subsequently recorded a $6.3 billion impairment charge on Westinghouse, contributing to its own corporate . The bankruptcy disrupted Vogtle's momentum, as Westinghouse relinquished project control in May 2017, nullifying the fixed-price terms and forcing the owner consortium—led by (a subsidiary) with shares held by Oglethorpe Power, MEAG Power, and Dalton Utilities—to assume direct oversight. This transition added hundreds of millions in renegotiation and management costs, while exposing utilities to uncapped liabilities previously borne by the contractor. 's share alone ballooned from an initial $6.1 billion cap to over $10 billion, prompting Georgia Public Service Commission approvals for customer rate hikes totaling about 12% phased over three years starting in 2023 to recover prudent expenditures. Despite the turmoil, the episode underscored the risks of novel nuclear deployments without sufficient learning curves from prior builds, though proponents argued the investments secured long-term baseload capacity amid rising fossil fuel volatility.

Completion, Testing, and Commercial Operation

Unit 3 underwent hot functional testing prior to fuel loading, verifying reactor coolant system integrity and auxiliary systems at operating temperatures and pressures without . Initial fuel loading commenced in October 2022, with all 157 assemblies installed by October 17. The unit achieved initial criticality in March 2023, marking the start of low-power physics testing to confirm control. Synchronization to the grid occurred in April 2023, followed by power ascension testing to validate performance across operating ranges. All startup testing concluded by July 2023, enabling to declare commercial operation on July 31, 2023, with the unit delivering full power to the grid. For Unit 4, hot functional testing wrapped up on May 1, 2023, confirming system readiness for fuel introduction after addressing construction-related issues. Fuel loading followed, leading to initial criticality on February 14, 2024, which initiated precritical and low-power testing phases. Power ascension testing progressed through April, with full startup testing completed on April 25, 2024, and the unit returning to rated thermal power the next day. Commercial operation commenced on April 29, 2024, adding approximately 1,114 megawatts of capacity to serve Georgia's needs. These milestones represented the final phases of the design's first-of-a-kind implementation, incorporating iterative testing to resolve novel engineering challenges like integrated plant control systems. Post-commercial operation, both units entered routine monitoring under oversight, with Unit 3 demonstrating stable output exceeding 1,100 MW electrical. Delays in testing were attributed to disruptions and regulatory reviews, yet completion affirmed the viability of advanced passive reactors for baseload .

Cost Overruns: Causes and Lessons

The expansion project for Vogtle Units 3 and 4 experienced substantial cost overruns, with the total expenditure reaching approximately $35 billion, more than double the initial estimate of around $14 billion. also faced delays exceeding seven years beyond the original schedule, extending the overall timeline to about 15 years from planning to commercial operation. These escalations contributed to the bankruptcy of in March 2017, as the firm absorbed unmanageable costs from Vogtle and a parallel project at V.C. Summer. Primary causes included the first-of-a-kind implementation of the reactor design, which introduced inherent complexities and required extensive rework due to component test failure rates of 40% to 80%. disruptions exacerbated issues, with late or incomplete modules, post-production design changes, and deficiencies in quality-assurance documentation necessitating corrections. An inexperienced workforce, marked by high attrition rates such as 50% turnover among electricians, combined with inadequate and a lack of domestic nuclear construction expertise following decades without new builds, led to low productivity and (EPC) overruns. External factors like the further delayed progress, with over 2,800 cases reported among workers in December 2021 alone. Lessons from the project highlighted the necessity of finalizing designs prior to initiating to minimize changes and rework. Application of these insights improved efficiency in Unit 4, reducing hot functional testing from 94 days for Unit 3 to 42 days, and lowering its costs by about 30% relative to Unit 3 through better and . Industry experts emphasize the value of serial production of standardized designs, robust supply chains, and a skilled labor pool supported by stable regulatory frameworks to achieve cost reductions in future deployments. While the overruns underscore risks in large-scale nuclear projects without prior learning curves, proponents argue that federal incentives and replicated builds could enable , potentially making subsequent units more viable.

Technical and Safety Features

Reactor Specifications

The Vogtle Electric Generating Plant comprises four pressurized water reactors (PWRs). Units 1 and 2 are Westinghouse four-loop PWRs, each rated at a thermal power of 3,626 megawatts thermal (MWt) and capable of producing a net electrical output of 1,152 megawatts electric (MWe). Each core contains 193 fuel assemblies composed of Zircaloy, ZIRLO, or Optimized ZIRLO fuel rods. Units 3 and 4 utilize the Generation III+ design, featuring a two-loop configuration with a thermal power of 3,400 MWt per unit and a net electrical capacity of 1,117 . The cores hold 157 fuel assemblies, incorporating advanced features such as integral moisture-separating steam generators and enhanced systems integrated into the reactor vessel design. Key specifications for the reactors are summarized below:
Unit(s)TypeLoopsThermal Power (MWt)Net Capacity (MWe)Fuel Assemblies
1, 2 PWR43,6261,152193
3, 4 PWR23,4001,117157
These parameters reflect licensed operational limits approved by the , with Units 3 and 4 demonstrating improved through simplified modular and reduced reliance on active components compared to earlier designs.

Safety Systems and Innovations

The AP1000 reactors at Vogtle Units 3 and 4 incorporate passive safety systems that rely on natural physical phenomena such as , natural circulation, and condensation to achieve core cooling and containment integrity without requiring active components, operator intervention, or off-site power for the first 72 hours following a design-basis accident. These systems include the passive core cooling system, which injects borated water from in-containment refueling water storage tanks via gravity-driven flow, and the passive residual heat removal system, which uses natural circulation to transfer to the environment. A key innovation is the dual certification containment structure, featuring an outer shell and an inner containment vessel separated by an air space that facilitates through natural and radiative , eliminating the need for mechanical containment sprays or fans. The also includes an in-vessel and ex-vessel cooling mechanisms to retain and cool molten core material in severe scenarios, enhancing beyond-design-basis mitigation. This approach reduces the number of -related pumps, valves, and motors by approximately 50% compared to earlier pressurized water reactors, minimizing failure points and simplifying maintenance. Additional safety enhancements at Vogtle involve the integration of digital instrumentation and control systems with diverse actuation and manual overrides, providing against common-mode failures, and the use of probabilistic risk assessments during design to optimize safety margins. Recent innovations include the testing of accident-tolerant fuel assemblies in Vogtle Unit 2, which offer improved performance under high-temperature conditions and are planned for broader deployment to further enhance accident response time and fuel reliability in Units 3 and 4. These features collectively enable automatic reactor shutdown and sustained cooling without external inputs, addressing lessons from prior incidents like by prioritizing over engineered redundancies.

Seismic and Environmental Risk Assessment

The Vogtle Electric Generating Plant site, located in , approximately 4 miles east of Waynesboro, has undergone site-specific seismic evaluations as required by the U.S. Nuclear Regulatory Commission (NRC) for both existing units 1 and 2 and the reactors in units 3 and 4. The safe shutdown earthquake (SSE) ground motion for the design at Vogtle is established at 0.3g (), incorporating site-specific soil properties, embedment effects, and updated seismic hazard estimates derived from probabilistic analysis (PSHA). This design basis accounts for regional in the , where seismic activity is historically low, with the nearest significant faults (such as the Carolina trough) posing minimal threat due to distance and attenuation. Following the 2011 Fukushima Daiichi accident, the NRC mandated reevaluations under Near-Term Task Force (NTTF) Recommendation 2.1, prompting Southern Nuclear to submit updated PSHA results for Vogtle in and subsequent seismic probabilistic risk assessments (SPRAs). These assessments modeled core damage frequencies from seismic events at approximately 1 in 10,000 to 1 in 100,000 years for units 1 and 2, with margins confirmed adequate for units 3 and 4 through plant-specific analyses that exceed regulatory minima. The NRC staff verified that the site's foundation stability and structural reinforcements provide resilience beyond the design basis, with no required modifications identified after review. Regional earthquake records, including minor events like the (magnitude 7.0, over 200 miles away), inform these models but indicate negligible exceedance probability for Vogtle's levels. Environmental risk assessments for Vogtle, detailed in the NRC's Final Supplemental (EIS) for combined licenses of units 3 and 4 (NUREG-1947, 2011, with supplements), evaluate impacts across , air quality, , and , concluding no significant adverse effects from construction or operation. Units 3 and 4 employ mechanical-draft cooling towers, resulting in consumptive water use of about 28 million gallons per day on average, withdrawn from the under permitted limits that restrict withdrawals during low-flow conditions to protect downstream aquatic habitats. Thermal discharges are minimized compared to once-through cooling in units 1 and 2, reducing river temperature rises to below 2°F, with modeled impacts on fish populations (e.g., ) deemed small based on empirical data from similar plants. Radiological environmental risks remain low due to the AP1000's passive safety features, which limit off-site releases even in severe accidents, with annual public dose estimates under 0.003 millisievert—far below natural background levels of about 3 millisievert. Air emissions, including oxides and from and auxiliary diesel generators, comply with Clean Air Act standards, with operational impacts classified as minor after dispersion modeling. Terrestrial effects, such as on the 3,100-acre site, are mitigated through wetland restoration and monitoring, while follows NRC regulations for low-level radioactive storage on-site, avoiding significant groundwater contamination risks as verified by routine radiological surveys. Independent reviews, including the Department of 's EIS for loan guarantees (EIS-0476, 2012), corroborate these findings, attributing any localized effects (e.g., noise or traffic) to short-term phases rather than enduring operational hazards.

Economic and Societal Impacts

Power Generation and Grid Contributions

The Vogtle Electric Generating Plant consists of four units with a combined net generating capacity of approximately 4,664 megawatts (MW). Units 1 and 2, each with a net capacity of about 1,215 MW, have been operational since June 1, 1987, and May 20, 1989, respectively, providing baseload electricity to . Unit 3, an reactor with a net capacity of 1,117 MW, entered commercial operation on July 31, 2023, followed by Unit 4 with identical capacity on April 29, 2024. The plant's units demonstrate high operational reliability, with historical capacity factors exceeding 90% for Units 1 and 2 over multiple years, reflecting power's ability to deliver consistent output. Since commercial operation, Unit 3 has maintained a greater than 98%, operating at full power continuously. Collectively, the four units are projected to generate over 30 million megawatt-hours (MWh) of annually, equivalent to powering more than 2 million homes and businesses in . Vogtle contributes significantly to the Southeastern electric as the largest facility , supplying carbon-free baseload that enhances stability and meets growing demand without intermittent variability. Owned primarily by (45.7% share) and co-owned by entities including Oglethorpe Power Corporation, the plant integrates via high-voltage transmission infrastructure, such as the Thomson-Vogtle 500 kV line, to deliver reliable energy across the region. Units 3 and 4 alone are expected to produce 17.2 million MWh yearly, offsetting approximately 10 million metric tons of emissions compared to alternatives.

Job Creation and Regional Economy

The construction of Vogtle Units 3 and 4 generated peak onsite employment of more than 9,000 workers, making it the largest in by job numbers during that phase. This workforce included skilled trades such as electricians, welders, and engineers, drawn from across the to support the assembly of the reactors over a period spanning from 2013 to 2024. Upon completion, Units 3 and 4 added approximately 800 permanent, high-paying positions to the plant's operations, focusing on , operations, and technical support. The entire Vogtle facility now employs over 1,600 personnel, contributing to sustained employment in Burke County and surrounding areas. The project stimulated the regional economy through billions of dollars in positive impacts, including local spending by workers, from over 200 new suppliers established in , and infrastructure investments. These activities boosted tax revenues for local governments and supported ancillary businesses such as , , and transportation in the Augusta-Waynesboro . Despite the substantial upfront , the long-term and economic multipliers from operations have provided a foundation for regional growth in an area historically reliant on and .

Long-Term Value Versus Short-Term Criticisms

Despite substantial short-term criticisms centered on delays exceeding seven years and total costs for Units 3 and 4 reaching approximately $35 billion—far above the initial $14 billion estimate—the plant's long-term operational profile demonstrates enduring value through reliable, low-carbon baseload expected to span 60 to 80 years. Each new reactor, with a net capacity of about 1,114 megawatts, contributes to a combined output capable of powering roughly 500,000 homes annually per unit, bolstering Georgia's grid amid rising demand from and centers. This dispatchable power source maintains high capacity factors, aligning with U.S. fleet averages exceeding 90% in recent years, enabling consistent output that offsets in variable renewables and reduces reliance on peaker plants during peak loads. Economically, the units provide insulation against fuel price volatility and inflationary pressures inherent in gas or coal alternatives, with nuclear fuel costs representing less than 10% of total generation expenses over the plant's lifecycle, yielding stable electricity pricing for ratepayers after amortization of upfront capital. While critics highlight immediate rate impacts from cost recovery—such as Georgia Power's approved pass-through of over $7.5 billion—these are offset by sustained job retention of around 800 high-wage positions at the site and broader regional stimulus, including billions in cumulative economic activity from supply chains and infrastructure. Over decades, the avoided emissions—equivalent to removing millions of vehicles from roads annually—align with empirical decarbonization needs, as nuclear's levelized costs, post-construction, compete favorably with unsubsidized renewables when factoring in full-system reliability and storage requirements. Short-term setbacks, including Westinghouse's 2017 bankruptcy amid design and issues, amplified perceived risks but did not undermine the intrinsic causal advantages of : near-zero marginal operating costs and 24/7 availability that enhance resilience against weather extremes or geopolitical fuel disruptions. Analyses post-commercial operation, with Unit 3 online since July 2023 and Unit 4 since April 2024, affirm that the investment secures for Georgia, producing over 20% of the state's electricity from the full Vogtle complex while minimizing exposure to market swings that have driven recent wholesale price spikes. Thus, empirical performance metrics prioritize the plant's multi-decade contributions to affordable, emissions-free power over transient fiscal hurdles.

Controversies and Debates

Regulatory and Construction Delays

The Vogtle Electric Generating Plant Units 3 and 4 experienced extensive regulatory and construction delays, pushing commercial operations over seven years beyond the original 2016–2017 targets. The U.S. (NRC) issued combined construction and operating licenses (COLs) on February 10, 2012, following Southern Nuclear Operating Company's application submitted on March 28, 2008. Limited work authorizations preceded full construction, but the novel design necessitated prolonged NRC reviews for design certifications, exemptions, and inspections, including re-evaluations of departures from certified designs that contributed to scheduling inefficiencies. Construction commenced with the first concrete pour for Unit 3 on March 14, 2013, and for Unit 4 on November 19, 2013. Initial criticality was achieved for Unit 3 on March 6, 2023, and for Unit 4 on February 14, 2024, reflecting approximately 10 years from first concrete to this milestone for each unit. Regulatory milestones, such as the NRC's 10 CFR 52.103(g) finding authorizing fuel loading for Unit 3 in August 2022 and acceptance criteria confirmation for Unit 4 in July 2023, occurred late in the process after extensive preoperational testing and verifications. Key construction delays stemmed from first-of-a-kind engineering challenges with the reactors, including incomplete initial designs requiring iterative NRC-approved modifications, supply chain disruptions following Westinghouse's 2017 bankruptcy, and management transitions. Specific incidents exacerbated timelines, such as a vibrating pipe in Unit 3's cooling system identified during January 2023 testing, delaying startup, and a motor fault in Unit 4's forcing a schedule shift to 2024. NRC oversight intensified due to findings, including special inspections for safety-related issues, ensuring but adding to rework cycles. Despite these hurdles, the regulatory framework upheld safety standards amid the complexities of resuming large-scale builds after a decades-long hiatus in the U.S.

Cost Allocation and Ratepayer Burden

The construction of Vogtle Units 3 and 4 involved significant cost overruns, with the total project exceeding $30 billion, more than double the initial estimates, of which 's 45.7% ownership share amounted to approximately $10.2 billion in recoverable costs under regulatory review. In a regulated utility framework, recovered most construction expenses through customer rates via a Construction Work in Progress (CWIP) tariff approved by the Georgia Public Service Commission (PSC), which allowed billing for costs incurred during building, including a for the utility. By late 2023, ratepayers had already contributed about $3.5 billion through this mechanism. In December 2023, the unanimously approved a settlement allocating $7.56 billion of the $10.2 billion in Vogtle-related costs to customers, with the company absorbing $2.63 billion—representing a limited sharing of overruns beyond a predefined threshold. This decision capped customer exposure at roughly $7.6 billion for the disputed overruns, tied to conditions such as expanded programs and low-income assistance, but shifted the bulk of the financial burden to ratepayers despite the project's delays and escalations attributable to design changes, issues, and contractor failures. The allocation resulted in a cumulative 10% increase for Georgia Power customers, adding approximately $14.38 per month to the average residential bill (based on 1,000 kWh usage), compounding prior hikes approved in for Unit 3 integration. Critics, including consumer advocates, argued this imposed an undue "financial hit" without commensurate short-term benefits, as cheaper alternatives like were available, while supporters emphasized the long-term value of carbon-free baseload power over 60-80 years. Higher rates correlated with increased disconnections, totaling around 190,000 in amid the hikes, though direct causation remains debated amid broader economic pressures.

Broader Implications for Nuclear Revival

The completion of Vogtle Units 3 and 4 marks the first construction and commercial operation of new reactors since , demonstrating the technical feasibility of deploying advanced pressurized reactors like the design amid a 30-year hiatus in large-scale builds. These units, each generating over 1,100 megawatts, have operated at capacity factors exceeding 95% since entering service—Unit 3 on July 31, 2023, and Unit 4 on April 29, 2024—providing dispatchable, low-carbon baseload power equivalent to serving more than one million households annually without reliance on intermittent sources. This operational reliability underscores 's role in addressing rising electricity demands from , data centers, and , where firm capacity is essential to complement variable renewables. Lessons from Vogtle's construction, which spanned 15 years and incurred $35 billion in costs due to disruptions, first-of-a-kind engineering challenges, and regulatory adaptations, highlight pathways for cost reductions in subsequent projects through design standardization, modular , and enhanced . Analyses indicate that applying these insights could lower overnight costs for follow-on units to approximately $10,000 per kilowatt within three additional builds, leveraging a observed in global deployments. The U.S. Department of Energy has codified recommendations from Vogtle, including early securing and workforce training, to mitigate delays that amplified financing burdens. Such empirical adjustments counter narratives of inherent infeasibility, as standardized designs have historically reduced costs by 20-30% in repeated builds elsewhere. Broader revival hinges on policy reforms to internalize nuclear's long-term externalities, such as zero-emission credits under the 2022 , which Vogtle partially utilized, and innovative financing to distribute upfront capital risks beyond ratepayers. While critics emphasize short-term overruns, lifecycle analyses project Vogtle's new units delivering electricity at 3-5 cents per over 60-80 years, competitive with gas and superior to unsubsidized renewables when factoring grid stability. Success here could catalyze a resurgence, with over 10 gigawatts of proposed advanced reactors in development, but requires addressing regulatory predictability and fuel innovation to outpace alternatives amid decarbonization mandates. Failure to scale would exacerbate insecurity, as nuclear's 93% average U.S. dwarfs wind (35%) and solar (25%).

References

  1. [1]
    Nuclear - Energy Sources - Georgia Power
    Vogtle Units 3 & 4 Expansion​​ Completed on April 29, 2024, Plant Vogtle Units 3 & 4 are the first newly constructed nuclear units to be built in the United ...
  2. [2]
    Plant Vogtle Unit 4 begins commercial operation - U.S. Energy ... - EIA
    May 1, 2024 · The two new reactors bring Plant Vogtle's total generating capacity to nearly 5 gigawatts (GW), surpassing the 4,210-MW Palo Verde plant in ...
  3. [3]
    Vogtle Electric Generating Plant, Unit 1
    Vogtle Electric Generating Plant, Unit 1 ; Location: Waynesboro, GA (26 miles SE of Augusta, GA) in Region II ; Operator: Southern Nuclear Operating Co., Inc.
  4. [4]
    VOGTLE | Department of Energy
    As America's first new nuclear reactors in 30 years, Vogtle is bringing the next generation of advanced nuclear power to the U.S..
  5. [5]
    First new U.S. nuclear reactor since 2016 is now in operation - EIA
    Aug 1, 2023 · Georgia Power expects another similar-sized fourth reactor, Vogtle Unit 4, to begin operation sometime between November 2023 and March 2024. The ...<|separator|>
  6. [6]
    Plant Vogtle is the Largest Generator of Clean Energy in the U.S.
    Plant Vogtle is the largest nuclear plant and clean energy generator in the U.S., with a capacity of 4.66 GW, producing over 30 million MW hours annually.
  7. [7]
    Plant Vogtle Units 1, 2, 3, & 4 | Georgia Power
    Plant Vogtle is the largest generator of clean energy in the United States. Nuclear energy is a secure, dependable source of power for the United States.
  8. [8]
    Potential Cost Reduction in New Nuclear Deployments Based on ...
    The completion of Vogtle Units 3 and 4, despite significant cost and schedule overruns, a major bankruptcy, and a pandemic, demonstrates that the U.S. nuclear ...
  9. [9]
    Alvin W. Vogtle Electric Generating Plant - Southern Nuclear
    With the recent completion of Units 3 & 4, the first new nuclear units to be constructed in the U.S. in the last 30 years, Plant Vogtle is now the largest ...
  10. [10]
    Plant Vogtle Units 3 & 4 Overview - Georgia Power
    Nuclear power units, like those at Plant Vogtle, are the most reliable energy source, able to generate electricity at full power 24/7 – more than twice as much ...
  11. [11]
    How many nuclear power plants are in the United States, and ... - EIA
    May 8, 2024 · Vogtle Electric Generating Plant in Georgia is the largest U.S. nuclear power plant with 4 reactors and a total nameplate electricity generating ...
  12. [12]
  13. [13]
    Nuclear Energy - Southern Company
    The Vogtle Electric Generating Plant is jointly owned by Georgia Power (45.7%), Oglethorpe Power Corporation (30%), Municipal Electric Authority of Georgia ( ...
  14. [14]
    Power Reactor Status Report for October 24, 2025
    Power Reactor Status Report for October 24, 2025 · Region 1 Reactors · Region 2 Reactors · Region 3 Reactors · Region 4 Reactors ...Missing: capacity | Show results with:capacity
  15. [15]
    Georgia Power plans additional nuclear capacity
    Feb 4, 2025 · Between 2028 and 2034, it plans to add a total of an additional 112 MWe of capacity at the four units: 27 MWe each at Vogtle 1 and 2; 30 MWe at ...Missing: operational | Show results with:operational
  16. [16]
    [PDF] Alvin W. Vogtle Electric Generating Plant - Georgia Power
    In addition to the clean air features of nuclear power, Plant Vogtle has been a certified Wildlife Habitat Council site since 1993. More than 600 acres have ...<|control11|><|separator|>
  17. [17]
    [PDF] Vogtle Electric Generating Plant, Units 1 and 2
    Jun 15, 2023 · The Vogtle 1 & 2 construction permits were issued in 1974; therefore, the criteria of IEEE. 279-1971 are used as a basis for this safety ...
  18. [18]
    Safety Evaluation Report Related to the License Renewal of Vogtle ...
    The NRC issued the operating licenses for Unit 1 on March 16, 1987, and on March 31, 1989, for Unit 2. Units 1 and 2 are of a dry ambient containment ...
  19. [19]
    Scheduled refueling activities underway at Plant Vogtle Unit 1
    Sep 17, 2018 · Each of the two units at Plant Vogtle requires new fuel every 18 months. The most recent refueling outage for Unit 1 was completed in the spring ...
  20. [20]
    This nuclear plant had the highest summer capacity factor in 2021
    Aug 30, 2022 · According to EIA data, 21 reactors achieved a capacity factor above 100% last year. ... Vogtle unit 2: 102.5%; Limerick unit 1: 102.5%; Byron unit ...
  21. [21]
    U.S. nuclear capacity factors: Stability and energy dominance
    May 2, 2025 · The median DER net capacity factor of the 92 reactors included in this survey for the three-year period 2022–2024 is 90.96 percent.
  22. [22]
    Plant Vogtle Unit 2 returns to service, sets Southern Nuclear fleet ...
    Oct 9, 2017 · The outage duration was 17 days, 5 hours and 36 minutes – a Southern Nuclear fleet record. Plant operators safely took the unit offline Sunday, ...
  23. [23]
    Southern Nuclear Sets New Outage Record at Vogtle Unit 2
    Feb 20, 2017 · Vogtle electric generating station in eastern Georgia, workers were ahead of schedule and gaining momentum. Vogtle ended the outage 32.5 hours ...
  24. [24]
    Vogtle Electric Generating Plant, Units 1 And 2 | NRC.gov
    Oct 23, 2024 · Facility Operating License Nos. NFP-68 and NFP-81(Docket Nos. 50-424 ... Accession No. 03/22/1993, Issuance of Amendments - Vogtle Nuclear ...
  25. [25]
    Georgia Public Service Commission approves plan to reliably ...
    Jul 15, 2025 · In this IRP, the company received approval to reinvest in Vogtle Units 1 & 2 upgrades to enable those units to deliver an additional 54 MW of ...
  26. [26]
    [PDF] U.S. nuclear capacity factors: Buoyed by record generation
    May 2, 2019 · Vogtle-2. 96.54. 1169. PWR Southern. 9. Nine Mile Point-1 ... same owner; the two-unit Nine Mile Point plant had a capacity factor of 93.17.
  27. [27]
    [PDF] Integrated Inspection Report 05000424/2024004 And 05000425 ...
    Feb 11, 2025 · On December 31, 2024, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Vogtle Electric Generating Plant, Units 1 and 2.
  28. [28]
    [PDF] NRC Information Notice 1991-034 - Nuclear Regulatory Commission
    Jun 3, 1991 · Description of Circumstances: On March 20, 1990, a loss of offsite power to the vital buses occurred at the. Alvin W. Vogtle Nuclear Plant, Unit ...
  29. [29]
    Fission Stories #45: Station Blackout at Vogtle
    Jun 21, 2011 · The plant's owners declared an Alert, the second lowest of the NRC's four emergency classifications as a result of the loss of power and its ...
  30. [30]
    Escalated Enforcement Actions Issued to Reactor Licensees - V
    Specifically, Southern failed to adequately perform periodic channel calibrations for post-accident monitoring equipment since initial startup of Vogtle Units 1 ...Missing: key | Show results with:key
  31. [31]
    NRC investigation reveals document falsification at Georgia's Plant ...
    Feb 22, 2018 · NRC investigation reveals document falsification at Georgia's Plant Vogtle 1&2 ... The US Nuclear Regulatory Commission has proposed a $145,000 ...
  32. [32]
    Framatome's GAIA Enhanced Accident Tolerant Fuel completes ...
    Oct 25, 2022 · Vogtle Electric Generating Plant Unit 2. Following 36 months of operations, inspections confirm the chromium-coated fuel rods maintain their ...Missing: incidents | Show results with:incidents<|separator|>
  33. [33]
    NRC hosting open house this week to discuss Vogtle plant ...
    May 13, 2025 · One shutdown last July was to the result of “lowering water levels in the steam generators caused by a valve issue on one of the three main ...Missing: incidents | Show results with:incidents
  34. [34]
    Issued Combined Licenses and Limited Work Authorizations for ...
    The following table provides access to the COL Application that SNC submitted for Vogtle, Units 3 and 4. Some combined license applications were submitted with ...
  35. [35]
    Nuclear Regulatory Commission approves construction of first ... - EIA
    Mar 5, 2012 · Southern Company expects Vogtle Units 3 and 4 to be operational in 2016 and 2017, respectively. The construction of the Vogtle units is ...
  36. [36]
    Issued Early Site Permit - Vogtle Site
    Vogtle Early Site Permit​​ On August 26, 2009, the NRC issued the Vogtle Electric Generating Plant ESP for a site located approximately 26 miles southeast of ...
  37. [37]
    How the Loan Programs Office and Plant Vogtle are Shaping the ...
    Oct 28, 2022 · The Vogtle Units 3 and 4 project was the first new nuclear power plant to be licensed and begin construction in the United States in more than 30 years.
  38. [38]
    AP1000® Pressurized Water Reactor - Westinghouse Nuclear
    The AP1000 reactor represents the most advanced technology available today, able to supply over 1 GW of electricity to centralized power grids.
  39. [39]
    Final module placed for Vogtle 3 & 4 project - Southern Company
    Apr 26, 2021 · The Passive Containment Cooling Water Storage Tank, known as CB-20, is a major part of the AP1000 reactor's advanced passive safety system.
  40. [40]
    First nuclear concrete placed at Plant Vogtle expansion - PR Newswire
    Mar 14, 2013 · ATLANTA, March 14, 2013 /PRNewswire/ -- Georgia Power has completed the placement of basemat structural concrete for the nuclear island at ...Missing: pour date
  41. [41]
    [PDF] Vogtle 3&4 - Georgia Power
    Mar 21, 2022 · Georgia Power received unanimous approval from the Georgia Public Service Commission to complete Vogtle units 3 & 4. 2019 • The top of the ...Missing: COLA | Show results with:COLA
  42. [42]
    Commercial Operations at Vogtle Unit 3 is an Important Milestone for ...
    In 2017, Bechtel was brought in by Georgia Power and Southern Nuclear to take over construction of Vogtle Units 3 and 4, bringing extensive experience ...Missing: timeline | Show results with:timeline
  43. [43]
    Plant Vogtle Unit 3 Enters Commercial Operations, Bringing Carbon ...
    Jul 31, 2023 · Plant Vogtle Unit 3 has safely reached the start of commercial operations, and the unit is now serving customers and the State of Georgia.Missing: initiation | Show results with:initiation
  44. [44]
    Vogtle Unit 4 connects to electric grid for the first time - Georgia Power
    Mar 1, 2024 · The in-service date for Unit 4 is projected during the second quarter of 2024. The new Vogtle units are an essential part of Georgia Power's ...Missing: milestones | Show results with:milestones
  45. [45]
    Vogtle Builders Note Progress on New Project Timeline | ENR
    Mar 7, 2018 · The new schedule marked a roughly 29-month extension of the previous targets of 2019 and 2020. Originally, Georgia Power had planned to have ...
  46. [46]
    Westinghouse Congratulates Vogtle Team on First Criticality at Unit 4
    Feb 14, 2024 · Plant Vogtle, located near Waynesboro, Georgia, is the site of the first two AP1000® reactors built in the U.S.. Vogtle Unit 4_resize. Plant ...<|separator|>
  47. [47]
    [PDF] Southern Company's Troubled Vogtle Nuclear Project | IEEFA
    The owners now estimate commercial operation will not begin until 2022 and 2023—more than six years behind schedule. Georgia Power asked the Georgia Public ...
  48. [48]
    How Westinghouse, Symbol of U.S. Nuclear Power, Collapsed
    Mar 30, 2017 · Plant Vogtle Units 3 and 4, which were certified by the Georgia Public Service Commission in March 2009 at $14.3 billion is more than $3 billion ...
  49. [49]
    How two cutting edge U.S. nuclear projects bankrupted Westinghouse
    May 2, 2017 · Overwhelmed by the costs of construction, Westinghouse filed for bankruptcy on March 29, while its corporate parent, Japan's Toshiba Corp, is ...
  50. [50]
    Westinghouse Bankruptcy Shakes The Nuclear World - Forbes
    Mar 31, 2017 · Westinghouse Electric Company filed for Chapter 11 Bankruptcy in New York to restructure itself as a result of costly problems at the AP1000 power plants it's ...
  51. [51]
    Westinghouse Files for Bankruptcy, in Blow to Nuclear Power
    Mar 29, 2017 · Westinghouse Electric Company, which helped drive the development of nuclear energy and the electric grid itself, filed for bankruptcy protection on Wednesday.
  52. [52]
    Westinghouse relinquishes control of Vogtle project - E&E News
    May 15, 2017 · Westinghouse filed for Chapter 11 bankruptcy protection in March because of significant financial pressures from Vogtle and a nuclear project ...
  53. [53]
    [PDF] Vogtle 3 & 4 - Georgia Power
    Georgia Power currently projects a Unit 3 in-service date in the second quarter of 2022 and a Unit 4 in-service date in the first quarter of 2023. • Unit 3 has ...
  54. [54]
    [PDF] Vogtle 3 & 4 - Georgia Power
    Significant progress continues to be made at the Vogtle 3 & 4 nuclear expansion site with the total project approximately 98.5% complete as of January 31, 2023.
  55. [55]
    Vogtle AP1000 project: the end is in sight, at last
    Oct 5, 2023 · The AP1000 units at Vogtle, with their Generation III+ classification, have fully passive safety systems, relying on gravity and natural ...
  56. [56]
    Vogtle Unit 3 goes into operation - Georgia Power
    Jul 31, 2023 · Georgia Power declared today that Plant Vogtle Unit 3 has entered commercial operation and is now serving customers and the State of Georgia. ...
  57. [57]
    Hot Functional Testing completed for Vogtle Unit 4 - Georgia Power
    May 1, 2023 · Georgia Power today announced the completion of hot functional testing for Unit 4 at the Vogtle nuclear expansion project near Waynesboro, Ga.
  58. [58]
    Vogtle 4 reaches first criticality - World Nuclear News
    Feb 14, 2024 · The new Vogtle unit 4 AP1000 reactor has reached initial criticality, with the unit's in-service date now projected to be during the second quarter of 2024.
  59. [59]
    [PDF] Vogtle Electric Generating Plant, Units 3 And 4
    Aug 1, 2024 · The unit completed all startup testing on April 25, 2024, and was returned to RTP on April. 26, 2024. On April 29, 2024, Southern Nuclear ...
  60. [60]
    nuclear power plants, and when was the newest one built? - EIA
    Vogtle Electric Generating Plant in Georgia that began commercial operation on April 29, 2024. The next-youngest operating reactor is Vogtle Unit 3, which began ...Missing: 2 milestones<|separator|>
  61. [61]
    [PDF] Vogtle Electric Generating Plant, Units 3 & 4, Revision 7 to Updated ...
    ... .................... 14.2-19. 14.2.7. Initial Fuel Loading and Initial Criticality .................................... 14.2-20. 14.2.7.1. Initial Fuel Loading ...
  62. [62]
    [PDF] NUCLEAR POWER SUMMARY –NEWS & NOTES
    Jul 27, 2023 · The reactor was expected to enter commercial operation in. June 2023, however on June 21st, the company announced that the commercial operation ...
  63. [63]
    What Was Learned from Building New Nuclear Reactors?
    Apr 1, 2025 · The recently completed Vogtle reactors exceeded $35 billion for construction and financing. This excessive cost was due in large part to the inherent design.
  64. [64]
    Georgia nuclear rebirth arrives 7 years late, $17B over cost | AP News
    May 25, 2023 · Construction delays drove Westinghouse Electric Co., a titan of American industrial history, into bankruptcy when the company couldn't absorb ...
  65. [65]
    Vogtle's troubles bring US nuclear challenge into focus | Reuters
    Aug 24, 2023 · Cost and schedule overruns have plagued the construction of two large modern reactors at the Vogtle nuclear power station but industry participants say lessons ...
  66. [66]
  67. [67]
    Georgia's Vogtle plant starts a new nuclear era — or ends it early
    Apr 8, 2024 · The reactors, first approved by Georgia regulators in 2009, are reckoned to be the most expensive infrastructure project of any kind in American ...
  68. [68]
    [PDF] Vogtle Electric Generating Plant, Units 1 and 2
    Aug 1, 2023 · This license amendment is effective as of its date of issuance and shall be implemented within 30 days of issuance. The accident tolerant fuel ...
  69. [69]
    Vogtle 2 - World Nuclear Association
    Specifications. Capacity Net, 1152 MWe. Capacity Gross, 1229 MWe. Thermal Capacity, 3626 MWt. Design Net Capacity, 1101 MWe. To navigate the map with touch ...Missing: electrical | Show results with:electrical
  70. [70]
    [PDF] ALVIN W. VOGTLE - Electric Generating Plant - Southern Nuclear
    Full-time on-site U.S. Nuclear Regulatory Commission (NRC) inspectors monitor the plant to ensure it is safely maintained and operated. • Plant Vogtle's four ...Missing: timeline | Show results with:timeline
  71. [71]
    Southern Nuclear Operating Company; Vogtle Electric Generating ...
    Aug 7, 2023 · The Vogtle reactors each contain 193 fuel assemblies. Each assembly consists of a matrix of 264 Zircaloy, ZIRLO® , or Optimized ZIRLO ...
  72. [72]
    Vogtle Electric Generating Plant, Unit 3
    Vogtle Electric Generating Plant, Unit 3 ; Location: Waynesboro, GA (26 miles SE of Augusta, GA) in Region II ; Operator: Southern Nuclear Operating Co., Inc.
  73. [73]
    Vogtle 4 - World Nuclear Association
    Construction Start, Tuesday, 19 November 2013. First Criticality, Wednesday, 14 February 2024. First Grid Connection, Friday, 1 March 2024.
  74. [74]
    [PDF] Vogtle, Units 3, 4 - Nuclear Regulatory Commission
    Mar 18, 2024 · The AP1000 steam generator is a vertical-shell U-tube evaporator with integral moisture separating equipment.
  75. [75]
    AP1000 ® Nuclear Power Plant - Passive Safety Systems
    The AP1000 plant uses passive safety systems which provides a major safety advantage, requiring no operator actions for design-basis accidents.Missing: Vogtle | Show results with:Vogtle
  76. [76]
    5 Things You Should Know About Plant Vogtle | Department of Energy
    Apr 18, 2019 · Vogtle Units 3 & 4 are expected to generate more than 17 million megawatt-hours of clean and reliable electricity. That's enough to power ...
  77. [77]
    The Art of Innovation: AP1000® Nuclear Power Plant Safety
    Jul 29, 2016 · It harnesses simple, proven, driving forces, like gravity, natural circulation and condensation to provide an advanced, passive safety system.
  78. [78]
    [PDF] Vogtle, Units 3 and 4, Updated Final Safety Analysis Report ...
    The AP1000 design process includes a risk assessment of the design prior to being finalized to optimize the plant with respect to safety.
  79. [79]
    Vogtle Accelerates Innovation in Nuclear Energy With Accident ...
    Apr 5, 2019 · These advanced fuel designs will make plants even safer by allowing plant operators more time to respond to reactor conditions.
  80. [80]
    Enhanced Safety of Advanced Reactors | Department of Energy
    Passive safety refers to the ability of advanced reactors like the AP1000 or newer designs under development to shut down and remove excess heat without human ...
  81. [81]
    [PDF] AP1000 Vogtle Site Specific Seismic Evaluation Report
    Oct 29, 2008 · The seismic analyses performed for the Vogtle site includes site-specific soil properties and embedment effects and uses the current seismic ...
  82. [82]
    [PDF] Seismic Probabilistic Risk Assessment.
    Mar 27, 2017 · 4. NRC Letter, Vogtle Electric Generating Plant Units 1 and 2, Staff Assessment of. Seismic Hazard Reevaluations Pertaining to Recommendation ...
  83. [83]
    [PDF] Vogtle Electric Generating Plant, Units 1 and 2
    Mar 31, 2023 · The purpose of this letter is to document the U.S. Nuclear Regulatory Commission (NRC) staff's latest understanding of seismic hazards at the ...
  84. [84]
    Final Supplemental Environmental Impact Statement for Combined ...
    Final Supplemental Environmental Impact Statement for Combined License (COLs) for Vogtle Electric Generating Plant Unit 3 and 4 (NUREG-1947). On this page ...
  85. [85]
    [PDF] Environmental Impact Statement for the Proposed Vogtle Electric ...
    Proposed Action: The U.S. Department of Energy (DOE) is proposing to issue a loan guarantee to several applicants to support funding for construction and ...
  86. [86]
    [PDF] Prevention of Significant Air Quality Deterioration Review
    Mar 3, 2010 · On May 27, 2009, Vogtle Electric Generating Plant (hereafter Plant Vogtle) submitted an application for an air quality permit to construct and ...<|separator|>
  87. [87]
    Vogtle 3 - World Nuclear Association
    Construction Start, Saturday, 2 March 2013. First Criticality, Monday, 6 March 2023. First Grid Connection, Saturday, 1 April 2023.Missing: concrete pour date
  88. [88]
    Thomson-Vogtle Reliability Project - Georgia Power
    The Thomson-Vogtle 500 kV transmission line is being built to add the necessary transmission infrastructure to support the two new nuclear units.
  89. [89]
    Commercial operation marks completion of Vogtle expansion
    Apr 29, 2024 · Vogtle 4 reached first criticality in February and was connected to the grid in March, following Vogtle 3 which entered commercial operation in ...
  90. [90]
    [PDF] Vogtle 3&4 - Georgia Power
    The projected peak rate impact to retail customers for Vogtle units 3 and 4 is approximately 10%, with approximately 3.4% already in rates.
  91. [91]
    Inside Plant Vogtle, the largest generator of carbon-free nuclear ...
    Plant Vogtle features ...<|control11|><|separator|>
  92. [92]
    Georgia Power & Plant Vogtle Energize Columbia County Economy
    Plant Vogtle's expansion will create 5,000 construction jobs and 800 full-time positions, with $4 billion in added economic value. Georgia Power has attracted ...
  93. [93]
    New operating nuclear power plant in the U.S
    May 8, 2024 · On April 29th, Georgia Power announced the commercial operation of the Vogtle 4 nuclear power plant to serve costumers all over the state of ...<|separator|>
  94. [94]
    A Strategy for Financing the Nuclear Future
    Aug 12, 2025 · Since being placed into commercial operation, both new Vogtle reactors have run at 95%–100% capacity factors,58 well above the nuclear industry ...
  95. [95]
    Vogtle Was a Smart Investment - ClearPath
    Jul 23, 2024 · One evergreen benefit of this energy is its resistance to price inflation, fuel risks, and global economic conditions. The Vogtle reactors are ...
  96. [96]
    Vogtle Unit 4 enters commercial operation - Georgia Power
    Apr 29, 2024 · ... Vogtle has provided billions of dollars of positive economic impact for Georgia and local communities. In addition to the 800 permanent jobs ...
  97. [97]
    After Vogtle, what's next for nuclear? - E&E News by POLITICO
    Apr 30, 2024 · But critics say Plant Vogtle's delays and costs are the norm for the nuclear industry. “Despite massive subsidies and support … only one reactor ...Missing: management | Show results with:management
  98. [98]
    Why Does Nuclear Power Plant Construction Cost So Much? | IFP
    May 1, 2023 · Nuclear power plants cost more and more​​ Today the Vogtle 3 and 4 reactors are likely to come in at around $8000/KWe in overnight costs ($6000/ ...
  99. [99]
    [PDF] New Reactor Licensing Process Lessons Learned Report
    In these cases, the NRC staff has to re-review portions of the DC application, thus causing schedule delays and reducing review efficiency.
  100. [100]
  101. [101]
    Vogtle Unit 3 reaches initial criticality - Georgia Power
    Mar 6, 2023 · Georgia Power today announced that Vogtle Unit 3 has safely reached initial criticality. Initial criticality is a key step during the startup testing sequence.
  102. [102]
    Southern Nuclear Operating Company, Inc.; Vogtle Electric ...
    Aug 2, 2023 · The finding that the acceptance criteria in the combined license are met became effective on July 28, 2023. Published Content - Document Dates.
  103. [103]
    Vogtle Unit 3 Has Started Commercial Operations. What's Next for ...
    Jul 31, 2023 · After years of schedule delays and cost overruns, the Vogtle Unit 3 nuclear generating facility has finally begun commercial operations.
  104. [104]
    Pipe Issue Delays Startup of New Vogtle Nuclear Unit
    Jan 11, 2023 · 11 said startup will be delayed due to a vibrating pipe in the cooling system, which was noted during recent testing of the Unit 3 reactor.Missing: hurdles | Show results with:hurdles
  105. [105]
    Vogtle Unit 4 successfully connected to grid after delay
    Mar 4, 2024 · Last October, Georgia Power said the in-service date for Unit 4 was being pushed back to 2024 due to a motor fault in one of four reactor ...
  106. [106]
    Vogtle / Safety-Related Issues Could Lead To Increased Oversight ...
    Regulator releases initial conclusions from special inspection at AP1000 new-build project. Safety-Related Issues Could Lead To Increased Oversight, ...Missing: causes | Show results with:causes<|separator|>
  107. [107]
    State regulators pass along $7.6B tab to ratepayers for Georgia ...
    Dec 19, 2023 · Georgia regulators vote on Dec. 19 agreement on how overrun costs for Plant Vogtle is be split between ratepayers and shareholders.
  108. [108]
    Georgia Power's Plant Vogtle, high rate hikes, disconnections
    Mar 25, 2025 · Georgia Power's Vogtle Units 3 & 4 cost $36.8B, doubling the budget and timeline. Rate hikes caused 190K disconnections, sparking debates on ...
  109. [109]
    Georgia Power rates: Public to pay bulk of Plant Vogtle costs
    Unit 3 — ...Missing: lifetime | Show results with:lifetime
  110. [110]
    Georgia Power, state regulators agree to division of Vogtle nuclear ...
    Aug 31, 2023 · The settlement calls for capping the maximum amount paid by Georgia Power customers at $7.6 billion, just north of the $7.3 billion threshold ...
  111. [111]
    The Era of Advanced Nuclear Energy Arrives in the U.S. with First ...
    Jul 31, 2023 · The AP1000 units at Plant Vogtle, located near Waynesboro, GA, are Generation III+ pressurized water reactors with fully passive safety systems, ...
  112. [112]
    AI's Energy Demands Spark Nuclear Revival
    Jan 10, 2025 · The commercial start of Unit 4 completes the 11-year expansion project at Plant Vogtle. A Historic Site With a New Mission. Three Mile Island ...
  113. [113]
    [PDF] Potential Cost Reduction in New Nuclear Deployments Based on ...
    Apr 30, 2025 · The completion of Vogtle Units 3 and 4, despite significant cost and schedule overruns, a major bankruptcy, and a pandemic, demonstrates ...
  114. [114]
    Report: New Financing Strategy Needed to Spark America's Nuclear ...
    Aug 12, 2025 · The sticker shock from Georgia Power's Vogtle Units #3 and #4 at $16,000 per kilowatt still looms large, even though much of that cost ...
  115. [115]
    Difficulties in Bringing New Units Online at Vogtle Could Help Future ...
    Oct 10, 2024 · Interest in reviving nuclear power has increased in recent years despite the numerous challenges and cost overruns that plagued the Vogtle ...