Bui Dam


The Bui Dam is a gravity hydroelectric dam situated on the River in Ghana's , featuring an installed capacity of 404 megawatts from four turbine units. Constructed by China's Corporation under an engineering-procurement-construction contract, the project commenced in late 2008 and achieved full operation by December 2013, following decades of planning that originated in the early . With a maximum structural height of 108 meters and a crest length of 492.5 meters, the dam creates a reservoir supporting annual of approximately 1 billion kilowatt-hours while enabling for up to 30,000 hectares of land. As Ghana's second-largest hydropower facility after the , it addresses chronic power shortages but has drawn scrutiny for ecological disruptions in the adjacent Bui National Park, including for like hippopotamuses and the resettlement of over 1,000 local residents. The initiative, financed largely through Chinese loans totaling around $622 million, exemplifies Beijing's resource-for-infrastructure diplomacy in Africa, influencing subsequent Sino-Ghanaian economic ties.

Historical Development

Planning and Feasibility Studies

The planning phase for the Bui Dam involved multiple feasibility studies assessing , economic, and hydrological viability for a hydroelectric project on the River in . Initial reconnaissance surveys occurred in the , followed by a comprehensive in December 1976 conducted by the Snowy Mountains Engineering Corporation (SMEC) of , which identified the Bui Gorge site as suitable for power generation with an estimated of around 400 megawatts. The project gained renewed momentum in 1992 when the French engineering firm Coyne et Bellier (now part of Tractebel Engineering) performed an updated , confirming the site's geological stability and potential for formation despite seasonal flow variations in the Black Volta. This was supplemented by another Coyne et Bellier study in 1995, which incorporated economic analyses projecting benefits for Ghana's national amid growing demand. By October 2006, the 1995 study was revised by Coyne et Bellier to address updated hydrological data and project economics, enabling progression to financing and construction preparations; this revision estimated construction costs at approximately $622 million and emphasized integration with existing hydropower infrastructure like the . Parallel to technical assessments, the Ghanaian government commissioned an (ESIA) in the mid-2000s, allocating about $2 million for evaluations of biodiversity effects in the adjacent Bui National Park and resettlement needs for roughly 1,216 affected individuals, with findings submitted to the for review. These studies collectively validated the project's feasibility but highlighted risks such as downstream flow alterations and habitat inundation spanning 21% of the national park.

Approval and Initial Opposition

The Bui Dam project, first conceptualized in the 1920s as part of broader development plans, saw renewed governmental interest in the late under the National Democratic Congress administration, with the announcing intentions to construct it in mid-1999. However, following a change in government in 2001, the project was initially shelved, as confirmed by Volta River Authority president Charles Wereko-Brobby, amid competing priorities and fiscal constraints. Initial opposition emerged primarily from environmental advocates and international NGOs, who highlighted risks to the Bui National Park, including habitat disruption for endangered species such as hippopotamuses and potential increases in greenhouse gas emissions from reservoir-induced decomposition. A 2000 report by a government-commissioned panel, influenced by the World Commission on Dams' global critique of large hydropower, portrayed the project negatively, amplifying calls for alternatives like thermal power or smaller-scale renewables. Local and international researchers faced restrictions, exemplified by the 2001 expulsion of a British academic studying ecological impacts, signaling governmental sensitivity to critiques that challenged the dam's viability. Resettlement needs, though limited to 1,216 people compared to over 80,000 for prior Ghanaian dams, still raised social equity concerns among affected communities. Opposition waned after 2006 when a from the Chinese government provided critical financing, bypassing earlier funding hurdles and enabling parliamentary approval of the Bui Power Authority's creation in 2007, separating it from the Authority to oversee the project. The contract was signed on April 19, 2007, between the Ghanaian and Corporation, followed by a on August 24, 2007, led by President John Agyekum Kufuor. This marked formal approval, with the Chinese Exim Bank's $293.5 million buyer's credit facilitating progress despite lingering environmental debates.

Construction Timeline

The construction of the Bui Dam commenced with a ceremonial groundbreaking on 24 August 2007, officiated by Ghanaian President John Agyekum Kufuor at the site on the River. Preparatory activities, including field investigations, began in October 2007, with initial construction works starting in January 2008. The project was managed by the Bui Power Authority, with Corporation Limited of China serving as the primary contractor responsible for . Main dam construction, involving for the 108-meter-high structure, initiated in December 2009 following site clearance and resettlement efforts. The overall timeline targeted completion by early 2012 to address Ghana's growing energy demands, but delays pushed this milestone. By January 2013, the project reached 97% completion, encompassing the dam, powerhouse, and associated infrastructure such as spillways and saddle dams. The first of three 133 MW turbine units was commissioned in May 2013, delivering initial power to the national grid and providing approximately one-third of the facility's 400 MW capacity. The full hydropower plant became operational with the inauguration of the dam on 19 December 2013 by President John Dramani Mahama. Although commercially operational from 2013, formal handover from to the Bui Power Authority occurred on 28 November 2016 after final testing and defect rectification.

Technical Specifications

Dam Design and Engineering

The Bui Dam features a (RCC) gravity structure as its primary component, designed to withstand the hydraulic pressures of the River while optimizing material efficiency. The main dam reaches a maximum height of 108 above the foundation (90 above the riverbed) and has a crest length of 492 , with a total volume of one million cubic meters. Auxiliary saddle dams on the right bank supplement the main structure: one constructed with rock-fill and the other with earth-fill, both elevated to a height of 187 meters above to fully impound the . These elements ensure comprehensive containment of the 12.57 billion cubic meter at full supply level. The is integrated into the main body with five bays, each equipped with a 15-meter-wide radial , positioned at 169 meters and engineered for a maximum capacity of 10,450 cubic meters per second during extreme events. Three structures are also embedded in the to to the downstream powerhouse, incorporating features for sediment control and operational flexibility. The RCC construction technique, executed by Corporation Limited as the contractor, facilitated layered placement and compaction of , enhancing construction speed and seismic resilience in the region's geological context. This design prioritizes gravitational stability over arch effects, relying on the dam's mass to resist water thrust.

Reservoir Formation and Hydrology

The Bui Reservoir was formed by impounding the River following the closure of the dam's main structure, with the filling process commencing on June 8, 2011. This marked a key milestone in the project, with water levels rising progressively over the subsequent years; by March 2013, the reservoir had accumulated sufficient volume to support initial operations, coinciding with the dam's commissioning in December of that year. The impoundment submerged approximately 444 km² of land at full supply level (FSL), extending the reservoir's average length to about 40 km upstream. At FSL of 183 meters above , the attains a surface area of 444 km² and a total storage capacity of 12,600 million cubic meters, enabling regulation of seasonal flows from the . The minimum operating level is maintained to preserve ecological and operational functions, though specific thresholds vary with hydrological conditions and protocols. from upstream inflows has begun accumulating in the , potentially affecting long-term storage efficiency, as observed in comparable impoundments on sediment-laden rivers. Hydrologically, the reservoir intercepts annual inflows from the catchment, which exhibit variability influenced by upstream changes and patterns, with modeled water yields increasing from 3.25 million cubic meters in 2000 to 4.75 million cubic meters in 2020. Outflows are regulated primarily for generation, resulting in attenuated peak discharges during wet seasons and augmented base flows in dry periods, which alters downstream flow regimes and reduces the frequency of extreme events. This management has implications for water availability, with analyses confirming shifts in reversal frequencies, flow change rates, and minimum discharges post-impoundment.

Hydropower Infrastructure

The Bui Hydropower Station features an installed capacity of 404 MW, comprising three main turbines each rated at 133.33 MW and one auxiliary 4 MW turbinette. The turbines, housed in the main powerhouse, are designed for high-head operation and fed by water from the reservoir via three structures and associated penstocks, enabling efficient conversion of hydraulic energy to . The turbinette, located in a separate mini powerhouse, utilizes minimum environmental flow releases to generate supplemental power, ensuring compliance with ecological requirements while contributing to overall output. The powerhouse infrastructure supports peaking operations, with the station capable of rapid startup and load adjustments to stabilize Ghana's . Electric generators synchronized with the turbines, supplied by , deliver power at 161 kV through a 500 MVA switchyard equipped with five bays for interconnection. A 241 km evacuates generated to key substations at Sawla, Kintampo, , and , facilitating integration into the national . Annual energy production averages 969 GWh, with peaks reaching 1,547 GWh in high-inflow years like 2022, reflecting variability tied to seasonal River flows. The system's design emphasizes reliability, providing ancillary services such as frequency regulation amid Ghana's reliance on for baseload and .

Financing and International Partnerships

Project Costs and Sources

The total cost of the Bui Dam project was initially estimated at US$622 million in the mid-2000s. A cost review conducted in 2012 increased this figure by US$168 million, bringing the final project cost to US$790 million. Funding was primarily secured through loans from the Export-Import Bank of China (China Exim Bank), with the Government of Ghana providing a smaller equity contribution. The financing structure included a concessional loan of approximately US$263.5 million at a low interest rate of 2% and a 20-year repayment term including a five-year grace period, alongside a buyer's credit facility of US$298.5 million tied to procurement from Chinese contractors. The concessional loan was approved and disbursed starting in 2007, while the buyer's credit was formalized in September 2007 to support engineering, procurement, and construction by Sinohydro Corporation Limited. Ghana's contribution amounted to US$60 million in public funds, covering about 10% of the initial estimated costs and allocated toward local components and contingencies.
Funding SourceAmount (US$)TypeKey Terms
China Exim Bank (Concessional Loan)263.5 millionLoan2% interest, 20-year term, 5-year grace period
China Exim Bank (Buyer's Credit)298.5 millionLoanTied to Chinese procurement; disbursed 2007–2013
Government of Ghana60 millionEquityPublic spending for project equity and overruns
The loans from , totaling around US$562 million by 2008 approvals, were structured as an export credit mechanism to facilitate Chinese firm involvement, with no reported additional international donors or multilateral financing. Cost overruns beyond the initial budget were absorbed through adjustments in loan disbursements and Ghanaian fiscal allocations, though specific breakdowns for the US$168 million increase remain tied to construction delays and scope changes rather than new funding rounds.

Role of Chinese Entities

The Bui Dam project received substantial financing from the Export-Import Bank of (China Exim Bank), which extended a buyer's of $293.5 million to the Ghanaian government on September 25, 2007, to cover a significant portion of the costs. This funding was part of a broader resource-backed arrangement, where committed to exporting to to service part of the debt, reflecting 's strategy of tying infrastructure finance to commodity exports from recipient countries. The total project cost reached approximately $790 million, positioning Bui as the largest Chinese-funded infrastructure initiative in and underscoring Exim Bank's role as a key financier of projects during this period. Construction responsibilities were assigned to Corporation Limited, a state-owned enterprise and subsidiary of the Power Construction Corporation of , under an () contract awarded following a 2005 memorandum of understanding between Sinohydro and the Ghanaian . managed the core implementation from site preparation through to commissioning in December 2013, supplying expertise, , and a substantial portion of the labor force, which included expatriates and local hires. While focused on execution rather than initial planning—such as environmental impact assessments or dam design, which involved input from Ghanaian agencies and European consultants—the company's involvement exemplified 's model of integrated overseas infrastructure delivery, prioritizing rapid deployment over extensive host-country in pre-construction phases. Chinese entities' participation extended beyond direct finance and construction to influence project oversight, with coordinating with the Bui Power Authority for implementation monitoring, though retained ultimate regulatory control. This arrangement facilitated the dam's completion despite delays from funding disbursements and environmental disputes, but it also highlighted dependencies on Chinese technical know-how, as brought experience from over 300 global projects. Overall, the involvement of Exim Bank and advanced 's geopolitical and economic objectives in , including resource access and market expansion for its firms, while providing with infrastructure it might otherwise have struggled to fund through Western lenders due to environmental safeguards.

Operational Performance

Capacity and Energy Output

The Bui Generating Station has an installed capacity of 404 megawatts (MW), comprising three main turbines each rated at 133.33 MW and one auxiliary turbinette unit of 4 MW. This capacity was fully commissioned by December 2013, contributing to Ghana's national infrastructure alongside larger facilities like and Kpong. The plant's long-term average annual energy output is designed at 969 gigawatt-hours (GWh), corresponding to a of 27% under typical hydrological conditions in the Black Volta River basin. Actual generation has frequently exceeded this benchmark due to favorable inflow variability, with operational data indicating peaks above 1,500 GWh in high-rainfall years; for instance, net evacuation to the national grid reached 1,547 GWh in 2022, reflecting a 50% increase from 1,028 GWh in 2021. In 2024, output totaled 1,348 GWh, surpassing the annual target of 1,333 GWh, with the hydro plant accounting for 94.4% of Bui Power Authority's generation. Performance metrics demonstrate high reliability, including a 92.24% rate for main generating units in 2022 and downtime limited to 1.85%, well below the 2% target. Output fluctuations are primarily driven by seasonal river flows and upstream water management, underscoring the plant's sensitivity to regional climate patterns despite its baseload potential.

Integration into Ghana's Power Grid

The Bui Generating Station's hydropower output is evacuated from its onsite switchyard via four 161 kV transmission lines to the Ghana Grid Company (GRIDCo) substations at Sawla, , Kintampo, and , facilitating injection into the national transmission network. These lines, constructed as part of the project infrastructure, span approximately 200-300 km in total to connect the remote Bui site in the to the southern and northern load centers, enabling bidirectional power flow for grid stability. Synchronization with began on May 3, 2013, with the first unit, followed by full operational commissioning of all three units totaling 404 MW by December 19, 2013, allowing consistent baseload contribution to Ghana's interconnected system managed by GRIDCo. This setup integrates Bui as a key northern anchor in the 161 and higher voltage backbone, which spans over 4,000 km nationwide, supporting peak demand evacuation and reducing reliance on thermal imports during high-water periods. Subsequent enhancements, including the 2019-2021 hydro-solar hybrid additions of up to 22.25 MW floating and ground-mounted capacity, utilize the existing Bui Switchyard for seamless tie-in, optimizing dispatch by complementing hydro variability with diurnal solar output directly into the same 161 kV lines. constraints, such as occasional line faults or loading limits on downstream 161 kV segments, have periodically limited full offtake, prompting GRIDCo upgrades like the Anwomaso-Kintampo 330 kV reinforcements to bolster evacuation reliability.

Economic Contributions

National Energy Security and Growth

The Bui Dam bolsters Ghana's by adding 404 MW of installed capacity to the national grid, operational since its commissioning on December 6, 2013, which helps mitigate supply deficits amid rising demand driven by and . As a peaking facility on the River, it delivers ancillary services including reactive power compensation, frequency regulation, and spinning reserves, enhancing grid resilience and power quality, particularly in northern regions previously underserved by major transmission infrastructure. The dam's average annual energy production of 969 GWh has been consistently surpassed, reaching a record 1,547 GWh in , thereby reducing vulnerability to fluctuations in , which relies on imported and has historically contributed to load-shedding episodes known as "." This capacity expansion has played a key role in diversifying Ghana's mix, where constituted 29.1% of generation in 2021, supporting total output of 20,170 GWh in 2020 and contributing to a more than doubling of national installed capacity over the preceding decade alongside thermal additions. By providing a renewable, domestic source of baseload and flexible power, the project lessens reliance on imports, which accounted for significant portions of costs prior to 2013, and aligns with efforts to stabilize supply amid projected peak loads exceeding 4,000 MW by the mid-2020s. Economically, the dam's reliable output has facilitated industrial expansion and manufacturing growth by enabling consistent power for factories and urban centers, with macroeconomic modeling indicating positive ripple effects across sectors such as and services through improved infrastructure performance. Financing arrangements, including cocoa export collateral to , have amplified these benefits, nearly doubling the project's net positive impact on GDP by optimizing in a capital-constrained . Enhanced access has also driven household-level gains, including higher ownership of appliances in urban areas near the project, correlating with broader via productive uses of .

Local Employment and Infrastructure

The phase of the Bui Dam generated significant local employment opportunities, with the majority of workers being Ghanaian nationals. Studies indicate that most laborers hired during building were locals paid wages substantially exceeding Ghana's at the time, contributing to short-term income gains in the surrounding communities. Project announcements projected around 3,000 jobs, encompassing roles in , services, and ancillary activities, which temporarily boosted incomes in the . Post-commissioning in 2013, the dam's operations sustained a smaller but ongoing demand for local in , , and , with some communities reporting over 30% of residents shifting to new income sources linked to the facility. However, challenges persisted, including limited skill transfer to locals due to reliance on contractors for technical roles, which constrained long-term job quality improvements. Infrastructure development accompanied employment efforts, including the construction of roads, schools, health centers, markets, and community facilities as part of resettlement and project mitigation. These enhancements improved connectivity and access to services in previously remote areas near the Black Volta River. Additionally, the dam's integration increased local electricity access by approximately 4% overall, with urban households experiencing a 14.5% rise, facilitating greater use of electrified infrastructure and appliances. Such developments supported ancillary economic activities, though evaluations note uneven distribution favoring resettled groups over unaffected peripherals.

Environmental Assessments

Impacts on Flora, Fauna, and Water Quality

The construction of the Bui Dam resulted in the inundation of approximately 444 square kilometers of land, primarily within the Bui National Park, leading to the direct submergence and loss of terrestrial flora, including savanna woodlands and riverine vegetation that supported diverse plant species. This habitat destruction eliminated vegetation cover in the reservoir area, contributing to deforestation and altered land use patterns, with forest cover decreasing notably post-impoundment as detected through remote sensing analyses. Aquatic weed proliferation emerged following reservoir formation, as stagnant conditions in the Black Volta River promoted the growth of invasive macrophytes, potentially exacerbating eutrophication risks. Faunal impacts included the displacement and of terrestrial and aquatic species, with the flooding affecting an estimated 25% of Bui National Park's biodiversity hotspots, home to endangered mammals such as the West African hippo (Hippopotamus amphibius). Pre- and post-impoundment surveys documented declines in fish populations due to disrupted migratory patterns and altered hydrological regimes, including reduced sediment transport and flow variability that impacted species from families like , Anabantidae, and . Overall alterations, such as temperature fluctuations and prolonged dry-season flows, further threatened downstream by modifying spawning grounds and food webs, though some adaptive relocation of hippos upstream was observed. Water quality in the Black Volta River exhibited measurable changes post-2013 impoundment, with physico-chemical parameters including electrical conductivity (EC) decreasing, as monitored in nutrient studies, potentially stressing osmoregulatory capabilities of resident fish species. Impoundment fostered biological shifts, such as increased accumulation and weed growth, leading to perceptions among local communities of diminished potability due to and potential contaminants. While initial assessments noted pollution risks from reduced flow velocities and trapping, long-term data indicate variable impacts, including influences from reservoir seepage, though broader threats from upstream activities like have compounded dam-related quality declines.

Mitigation Measures and Long-Term Monitoring

Mitigation efforts for the Bui Dam's environmental impacts focused on habitat compensation, wildlife relocation, and vegetation management. The Bui Power Authority (BPA) implemented a habitat offset program by earmarking new areas north, south, and east of the existing for gazetting via legislative instrument, aiming to compensate for the inundation of approximately 21% of the park's area. protection included collaboration with the Division to relocate upstream from the reservoir and conduct rescue operations, alongside for park wardens to reduce through enhanced patrolling and infrastructure improvements. For flora, selective salvaging of tall trees occurred across the 444 km² inundation zone prior to impoundment in 2013, with additional targeted vegetation clearance proposed to minimize from submerged . Water quality mitigation involved routine physicochemical parameter testing, conducted monthly to monitor compliance with standards, though sedimentation effects on downstream habitats were anticipated as minor without specific structural interventions like fish ladders, as no migratory of conservation concern were identified in pre-construction assessments. Non-governmental organizations, including International Rivers, have critiqued these measures as insufficient, arguing that they fail to address broader ecological disruptions such as altered river flows and potential long-term in the Black basin. Long-term monitoring provisions under the project's Environmental Management Plan emphasize adaptive adjustments to based on ongoing observations, with BPA responsible for tracking and park . Post-impoundment studies have documented persistent changes, including reduced downstream water availability and shifts in nutrient dynamics, prompting calls for expanded hydrological and ecological surveillance using and GIS to quantify cumulative impacts. However, comprehensive, independent long-term programs remain limited, with reliance on periodic BPA reports and academic assessments rather than systematic, multi-decadal frameworks to evaluate effectiveness against baseline conditions established in the 2000s .

Social and Resettlement Outcomes

Affected Communities and Displacement

The Bui Hydroelectric Project, operational since December 2013, necessitated the involuntary displacement of 1,216 residents from eight communities situated within the reservoir inundation zone along the River in Ghana's . These communities, primarily comprising small-scale farmers, fishermen, and Gonja ethnic group members reliant on riverine livelihoods, included Bui Village, Bator, and six others such as Dampong and Brewohodi, which faced submersion due to the 444-square-kilometer reservoir created by the 60-meter-high dam wall. Resettlement efforts, managed by the Bui Power Authority under Ghana's 1992 Resettlement Act and World Commission on Dams guidelines, relocated the affected populations to two planned townships: (accommodating 217 individuals from four source communities) and Bongasi. Compensation packages included payments, replacement , agricultural land allocations (approximately 2.5 hectares per ), and infrastructure like schools and boreholes, though independent assessments noted deficiencies in land fertility and water access at new sites compared to original locations. Downstream communities, such as those in the Black Volta basin below the dam, experienced indirect effects including altered river flows and reduced , impacting an estimated additional 1,000-2,000 seasonal fishermen without formal displacement but with livelihood disruptions from irregular water releases. Cultural sites, including sacred groves and ancestral burial grounds in the affected villages, were inundated or relocated, leading to reported losses of heritage artifacts with religious significance for local indigenous groups. Governance of the process involved consultations via local chiefs and district assemblies, but studies highlight limited participation by displacees in decision-making, with property rights over resettled lands remaining insecure due to communal tenure systems. The Bui Power Authority's monitoring extended post-relocation, yet empirical reviews indicate persistent vulnerabilities, such as inadequate integration of host community dynamics, exacerbating tensions over shared resources.

Livelihood Adaptations and Socioeconomic Studies

The of the Bui Dam led to the of 219 households comprising 1,219 individuals, primarily affecting livelihoods dependent on , , and resources in the Black basin. Resettled communities, including those in Lucene and Agbegikuro, experienced reduced access to and traditional grounds due to inundation covering approximately 444 km², prompting shifts toward diversification such as petty trading, labor, and non-farm activities. Empirical socioeconomic studies indicate that assets, including improved road access and housing provided during resettlement, positively influenced adaptive strategies by enabling diversification away from primary agriculture and fishing, though losses—such as diminished and riverine resources—constrained overall . One analysis found that resettled households increased reliance on off-farm income sources, with physical assets correlating to higher diversification indices, but human and deficits, including skill gaps and fragmented social networks, limited long-term gains. Positive infrastructural changes, like electrified homes and better in some sites, were offset by persistent challenges including food insecurity and elevated rates compared to pre-dam baselines. Post-construction evaluations highlight mixed outcomes in livelihood revitalization efforts, with Chinese-led dam builders and Ghanaian authorities implementing compensation packages that included farmland allocation and vocational , yet implementation shortfalls resulted in net socioeconomic costs for many displacees. A 2023 study on host communities near Bui documented adaptive coping mechanisms, such as communal resource sharing and for seasonal labor, but emphasized that without sustained , these remained vulnerable to from altered . Overall, underscores that while some households achieved partial adaptation through asset leveraging, the majority faced enduring vulnerabilities, with diversification serving more as survival than prosperity enhancement.

Controversies and Evaluations

Debates on Development vs. Costs

Proponents of the Bui Dam's construction emphasized its role in enhancing Ghana's energy security and fostering economic diversification, arguing that the 400 MW hydroelectric capacity would address chronic power shortages and support industrial growth in the northern regions. The project was projected to generate electricity at a lower cost than thermal alternatives reliant on imported oil, while also enabling irrigation for approximately 30,000 hectares of land to boost agricultural output. During the construction phase from 2009 to 2013, it created temporary employment opportunities and stimulated local infrastructure development, with macroeconomic models indicating positive GDP contributions through increased energy supply and reduced import dependence. Ghanaian government officials and supporters highlighted these benefits as essential for bridging developmental disparities between the resource-rich south and the underserved north, positioning the dam as a catalyst for national progress. Critics, including environmental advocacy groups like International Rivers, contended that the developmental gains were overstated relative to the substantial environmental and social costs, particularly given the dam's location within Bui National Park, where reservoir flooding would submerge 21% of the area and threaten such as the remaining viable populations in . The total construction cost of $622 million, largely financed through loans from China's after Western institutions declined funding due to environmental safeguard concerns, imposed a long-term debt burden on without commensurate equitable benefits for affected communities. Resettlement of over 2,500 people disrupted traditional livelihoods in and farming, leading to reported increases in , issues, and loss of cultural artifacts, with empirical studies on resettled households revealing persistent shortfalls in compensation and adaptation despite some improvements like roads and water access. These debates intensified prior to construction approval in 2006, with opponents citing global precedents of dams causing net socioeconomic harm through ecosystem degradation and greenhouse gas emissions from reservoirs, while proponents dismissed such concerns as impediments to Africa's energy needs, ultimately prevailing through alternative Chinese financing that bypassed stringent World Bank-style environmental protocols. Post-completion assessments have shown mixed outcomes: aggregate electricity access rose by about 4% nationally (14.5% in urban areas), supporting broader economic activity, yet micro-level analyses of displaced groups indicate livelihood challenges outweighed localized gains, underscoring causal disconnects between macro benefits and direct costs borne by vulnerable populations. Ongoing evaluations question the project's amid variability, which could reduce output reliability and exacerbate financial strains without robust .

Empirical Reviews of Benefits and Drawbacks

The Bui Dam, with an installed of 400 MW, has empirically contributed to Ghana's electricity supply, generating an average of 969 GWh annually and operating primarily as a peaking plant to supplement baseload power from other sources like the and Kpong dams. An economy-wide model evaluation across construction, financing, and operational phases estimated positive macroeconomic effects, including GDP growth from direct construction activities (peaking at 0.15% in 2011) and indirect multipliers in sectors like and services during operation, though these gains were modest relative to overall economy size. Household-level surveys near the dam site found statistically significant improvements in urban access (from 78% to 92% post-commissioning) and ownership of appliances such as refrigerators and fans, attributing these to grid extensions enabled by the project. Empirical social impact assessments, however, reveal substantial drawbacks in resettlement outcomes for the 1,216 individuals displaced from six communities, with post-relocation studies documenting persistent declines: resettled farmers experienced a 30-50% drop in crop yields due to inferior soils and reduced access to former grounds, compounded by inadequate compensation and limited skill programs. Qualitative and quantitative data from affected households indicate heightened vulnerability to food insecurity, with 40% reporting worsened metrics five years post-resettlement, as alternative income sources like wage labor failed to offset losses in and riverine resources. Environmental monitoring and ecological surveys post-2013 commissioning have quantified drawbacks including altered downstream —reducing seasonal flow variability by up to 25%—which disrupted patterns for like Labeo senegalensis, leading to a 20-30% decline in commercial catches reported by local fishers. assessments detected elevated and nutrient levels in the , correlating with algal blooms and potential risks, while terrestrial surveys noted affecting hotspots, including the displacement of the last viable population of West African manatees and hippopotamuses from the Bui area. A sustainability framework analysis rated the project's overall environmental score low due to unmitigated cumulative effects on services, estimating long-term buildup could reduce storage by 1-2% annually without sustained . Cost-benefit evaluations highlight uneven trade-offs: while operational phase projections from feasibility studies promised a benefit-cost of 1.2-1.5 based on sales, ex-post analyses incorporating and environmental externalities adjust this downward to near parity or negative when factoring in resettlement failures and losses valued at $10-20 million in foregone services. Independent reviews critique the original for underestimating downstream effects and climate variability, noting that actual generation has averaged below 80% of designed output in dry years due to variable inflows, amplifying economic risks amid Ghana's dependency. These findings underscore a pattern in large dam projects where short-term energy gains often mask enduring socio-ecological costs, as evidenced by longitudinal data from similar Volta Basin developments.

References

  1. [1]
    Bui Generating Station - Bui Power Authority
    The main components of the Project included a concrete gravity dam, which had a maximum dam height of about 108m and a crest length of about 492.5m.
  2. [2]
    Ghana Bui Hydroelectric Power Station - POWERCHINA
    Oct 20, 2023 · The Bui Hydroelectric Power Station has a 404 MW capacity, generates 1 billion kWh annually, and includes a 240.74 km transmission line. ...
  3. [3]
    Bui Dam Hydroelectricity Project, Ghana - Power Technology
    Feb 10, 2014 · The dam generates 400MW of power and facilitates irrigation of about 30,000ha of land. Construction was initially estimated at $622m, but a cost ...
  4. [4]
    Project Background - Bui Power Authority
    The proposed 400 MW Bui hydropower scheme was considered to be the most technically and economically attractive hydropower site in Ghana after the Akosombo and ...Missing: facts | Show results with:facts
  5. [5]
    An economy-wide evaluation of Ghana's Bui Dam - ScienceDirect
    The total financial cost of the Bui Dam is estimated at 622 million USD and was financed through foreign loans and public spending. The Akosombo Dam, located ...
  6. [6]
    [PDF] Bui ui Hydroelectric Power dam Project in Ghan am Project in Ghana
    The Bui Dam is a 400 megawatt hydroelectric project under construction at the Bui Gorge at the southern end of Bui National Park in. (Figure 1). Bui National ...
  7. [7]
    Bui Will Add 17% to Ghana's Hydropower
    Jan 31, 2005 · Another was the Bui Hydroelectric Project Feasibility Report of December 1976 by Snorry Mountains Engineering Corporation and the Bui ...
  8. [8]
    Bui Dam project, Ghana - NS Energy
    May 27, 2014 · ... Feasibility Study by Snowy Mountains Eng. Corp (SMEC) of Australia in 1976 and another Feasibility Study by Coyne et Bellier in 1995, which ...Missing: date | Show results with:date
  9. [9]
    Ghana: A dam at the cost of forests | World Rainforest Movement
    Jan 8, 2006 · Two million dollars are earmarked for the Environmental Impact Assessment (EIA) bound to prepare the ground for the take-off of the project, ...
  10. [10]
    [PDF] Weighing the Environment: Ghana's Bui Dam - AWS
    Environmental and Social Impact Assessment of the Bui Hydropower Project. Page 18. 18. Appendix 10: Excerpts from Environmental and Social Impact Assessment.
  11. [11]
    Controversy over proposed construction of Bui hydropower Dam ...
    Jul 12, 2007 · For them, the Wildlife Division's decision echoes Ghana's new government's position on the Bui Hydropower dam project and the message is clear.Missing: initial | Show results with:initial
  12. [12]
    Ghana's Bui Dam and the Contestation over Hydro Power in Africa
    Sep 18, 2020 · The Bujagali Dam, which was finally completed in 2012 (with European, Asian, and World Bank funding), has an installed capacity of 250MW. The ...
  13. [13]
    Ghana's Bui Dam raises concerns – again – about hydro power ...
    Mar 21, 2021 · Only 1,216 people needed to be resettled for the Bui Dam in contrast to the over 80,000 for the country's two previous hydro electric projects.Missing: approval process
  14. [14]
    Weighing the Environment: Ghana's Bui Dam | FSI
    Sep 20, 2018 · Environmental advocates and NGOs are concerned that the dam will negatively impact surrounding wildlife, especially the endangered hippos ...Missing: assessment | Show results with:assessment
  15. [15]
    Perceptions of people in host communities on the implementation of ...
    The planning and implementation of the Bui Dam resettlement programme by the government was aimed at reducing the ill-effects of dam displacements in Ghana on ...
  16. [16]
    Ghana's cocoa to help pay China for building 400-MW Bui
    Sep 7, 2007 · Ghana President John Agyekum Kufuor formally began construction of the project in a groundbreaking ceremony August 24. He formally thanked China ...
  17. [17]
    China Eximbank provides $293.5 million buyer's credit loan for Bui ...
    The dam was inaugurated on December 19, 2013. However, the project was not completed and handed over to the Ghanaian authorities until November 28, 2016. There ...
  18. [18]
    Ghana launches construction of 400-MW Bui
    Aug 28, 2007 · Ghana President John Agyekum Kufuor formally began construction of the 400-MW Bui hydroelectric project in a groundbreaking ceremony August 24 on Ghana's Black ...Missing: timeline | Show results with:timeline
  19. [19]
    MILLS COMPLETES BUI DAM -1st Power Supply Expected in ...
    May 7, 2012 · The Bui hydro-electric dam has first been envisaged in 1925 by the British-Australian geologist and naturalist Albert Ernest Kitson when he ...
  20. [20]
    Bui Dam in the Black Volta River, Ghana - Ej Atlas
    Apr 25, 2022 · The Bui Dam is a 400-megawatt hydroelectric project built on the Black Volta river at the Bui Gorge, at the southern end of Bui National Park.
  21. [21]
    Construction of Bui Dam begins - Ghana Web
    Aug 24, 2007 · President Kufuor said the Project, programmed for completion in early 2012, was part of the overall strategy to triple the country's energy ...
  22. [22]
    Bui Dam 97 per cent complete - MyJoyOnline
    Jan 31, 2013 · The project, which is being financed by China Exim Bank, started in January 2008 and is expected to be completed this year. The cost of the ...
  23. [23]
    Prez Mahama commissions Bui dam - Ghana Web
    Dec 19, 2013 · The first unit of the Project which provided about 133 megawatts of power was inaugurated in May to augment energy supply in the country. CEO of ...
  24. [24]
    Filling Of Bui Dam Reservoir Begins - Modern Ghana
    Jun 10, 2011 · The impoundment process marked a milestone in the implementation of the Bui hydroelectric power project which is expected to be completed in ...
  25. [25]
    Bui Power Authority reduces power production - MyJoyOnline
    Jun 2, 2014 · Filling of the Bui reservoir therefore commenced on June 8th 2011 and about two years later; ie by March 2013, the water level had risen from ...
  26. [26]
    Seasonal variations in phytoplankton diversity in the Bui dam area of ...
    The Bui dam will create a reservoir covering an area of about 444km2 at full supply level (FSL) (at 183masl) and holding about 12 600million m3 of water which ...Missing: specifications | Show results with:specifications
  27. [27]
    Modelling the impact of Bui dam operations on downstream ...
    The reservoir created by the construction of the Bui Hydropower dam has a design maximum level of 183 meters above sea level and a minimum operating level of ...Missing: specifications | Show results with:specifications<|separator|>
  28. [28]
    Hydro-power dam construction and water availability in the Bui ...
    Sep 26, 2025 · This study evaluates the hydrological impacts of the 400 megawatt hydroelectric Bui Dam built on Ghana's Black Volta River using remote ...
  29. [29]
    Hydro-power dam construction and water availability in the Bui ...
    Commissioned in 2013, the Bui Hydroelectric Project stands as Ghana's second largest dam infrastructure. The hydro plant was constructed across the Black ...Missing: facts | Show results with:facts
  30. [30]
    404MW Bui Generating Station - Bui Power Authority
    Key Features of the Bui Generating Station include a 1,000,000m3 volume and 108m high Roller Compacted Concrete Gravity Dam; 400MW Powerhouse housing 3 Unit ...Missing: engineering | Show results with:engineering
  31. [31]
    Power plant profile: Bui, Ghana - Power Technology
    Oct 21, 2024 · The company provided 3 units of francis turbines, each with 133MW nameplate capacity. GE Renewable Energy supplied 3 electric generators for ...
  32. [32]
    Financing structure of the Bui Power Project - ResearchGate
    The Government of Ghana received two credits from the China Exim Bank for the Bui Dam: a concessional loan of US$ 263.5 m and a buyer's credit of US$ 298.5 m ( ...
  33. [33]
    Ghana and China sign loan agreement on Bui Dam Project
    Sep 26, 2007 · Ghana has contracted a Buyer Credit facility of 292 million dollars from the Export-Import Bank (EXIM) of China to finance the Bui ...<|control11|><|separator|>
  34. [34]
    Report: China releases US$562 million for Ghana's 400-MW Bui
    Aug 13, 2008 · The government of China has approved release of a US$562 million loan for construction of Ghana's 400-MW Bui hydroelectric project.
  35. [35]
    [PDF] Do China-Financed Dams in Sub-Saharan Africa Improve the ...
    According to China's Ministry of Commerce, in August 2007, construction commenced on the Bui hydroelectric dam project at the Bui Gorge in the Brong-Ahafo.
  36. [36]
    Full article: The role of the state in Sino-Ghanaian relations
    At the cost of 790 USD million, Bui dam is the largest Chinese-funded project in Ghana and the largest foreign investment in Ghana since the construction of the ...
  37. [37]
    From Chinese dam building in Africa to the Belt and Road Initiative
    Officially commissioned at the end of 2013, the Bui dam was built by Sinohydro as an Engineering-Procurement-Construction (EPC) turnkey contract beginning ...Missing: history | Show results with:history
  38. [38]
    How the Bui Dam set up China's future engagement strategy with ...
    Jul 27, 2021 · The Bui Dam was erected about 200km upstream of Akosombo and Kpong across the Black Volta river, in the Bono region. Before China's involvement, ...
  39. [39]
    the Bui dam in Ghana
    The study analyses the role of Chinese companies and financing institutions and Ghanaian governmental agencies in planning and constructing the Bui Dam.
  40. [40]
    [PDF] Interaction of Chinese institutions with host governments in dam ...
    In Bui's case, as we shall see, Sinohydro, the contractor, was not involved in any of the planning (Environmental Impact Assessment, resettlement and dam design) ...
  41. [41]
    Chinese Overseas Hydropower Dams and Social Sustainability: The ...
    Sep 9, 2015 · The Bui Dam is an Engineering, Procurement, Construction (EPC) contract, which is a turnkey contract in which the Chinese dam builders ...
  42. [42]
    [PDF] 2022 Corporate Annual Report - Bui Power Authority
    This increase in power generation resulted in a 44% increase in revenue, from $110.3 million to $158.8 million. This is largely due to higher water inflows into ...
  43. [43]
    Bui Power Authority - Facebook
    Aug 29, 2025 · BPA generated a total of 1,348GWh of electricity into the NITS in 2024, surpassing its target of 1,333GWh. The Bui Hydro Plant contributed 94.4% ...Missing: actual | Show results with:actual
  44. [44]
    Bui Dam Comes Alive … Ghana Energy Problems Now Over
    Dec 20, 2013 · The power station will have an installed capacity of 400 MW and an estimated average annual generation of 980 GWh http://en.wikipedia.org/wiki/ ...
  45. [45]
    Bui Project will generate electricity from April - Ghana Web
    Feb 27, 2013 · ... Bui generating plant to the national grid. “These four lines will send power produced from the plant to the four GRIDCo substations in Sawla ...
  46. [46]
    Bui Dam Nearing Completion - Ghana Web
    Jul 27, 2012 · It said power produced from the plant would be evacuated from the Bui Switchyard through four 161kv transmission facilities, which would ...
  47. [47]
    Ghana expands generation capacity to improve the reliability of ...
    According to GRIDCo, Ghana's transmission system includes over 4000 km of high-voltage transmission lines operating at 161 KV and 69 KV, as well as a 225-KV ...
  48. [48]
    Bui adds 22.25MW solar power to augment national grid
    Apr 12, 2021 · The hydro-solar project is to augment the target to have 10 per cent renewable energy, which translates to about 5,000MW, in the national grid ...Missing: connection | Show results with:connection
  49. [49]
    Hydro Solar Hybrid - Bui Power Authority
    This will be Ghana's first hybrid plant utilizing both solar and hydro resources to generate and supply power to the national grid.
  50. [50]
    [PDF] 2020 Electricity Supply Plan - Ghana Grid Company
    To mitigate the constraints in Kumasi, GRIDCo needs to complete the 330kV Anwomaso – Kintampo transmission lines to relieve the high loadings on the 161kV ...
  51. [51]
    Bui Power CEO is wrong, Energy Minister not misled by GRIDCo
    Apr 16, 2021 · Therefore, to say that the Minister of Energy has been misled by GRIDCo to believe that Kumasi Power issues is substantially caused by Bui Dam's ...
  52. [52]
    Electricity | Ghana Energy Database
    Over the last decade, installed capacity of the nation has more than doubled due to the coming on stream of Bui Dam and new thermal plants. Thus, the ...
  53. [53]
    An economy-wide evaluation of Ghana's Bui Dam - ResearchGate
    Sep 26, 2025 · The collateral from the infrastructure loan agreement consisting in cocoa exports to China nearly doubles the project's positive GDP impact and ...
  54. [54]
    Do China-financed dams in Sub-Saharan Africa improve the ...
    Through the case study of Ghana's Bui Dam, we find that the Bui Dam has significantly improved local urban households' access to electricity and increased ...
  55. [55]
    [PDF] The Case of Ghana's Bui Dam - Oxford University Research Archive
    Built on the Black Volta River in Western. Ghana, the Bui Dam is a multi-purpose-dam with the key aims of electricity generation and water supply. The history ...
  56. [56]
    The Case of Ghana's Bui Dam - ResearchGate
    Aug 6, 2025 · Lastly, we find that most workers employed during construction were Ghanaian, paid significantly above the country's minimum wage. Nevertheless, ...
  57. [57]
    Bui Dam project to offer job opportunities - MyJoyOnline
    President Kufuor says some 3000 people will be employed under the Bui Dam project. He says the project will cover the construction of a new metropolis, ...Missing: creation | Show results with:creation
  58. [58]
    THE SOCIO - ECONOMIC IMPACT OF BUI DAM ON RESETTLED ...
    Job opportunities and infrastructure improved after the dam creation with Lucene recording > 30 % of its people changing their source of livelihood from farming ...Missing: growth | Show results with:growth
  59. [59]
    the case of Ghana's Bui Dam - Practical Action Publishing
    We draw on the Bui Dam, a major dam in Ghana, financed by China Exim Bank (CEB), the largest financier of infrastructure in Africa, and constructed by Sinohydro ...
  60. [60]
    [PDF] Infrastructure for Project Affected People In Ghana
    Aug 25, 2021 · The resettlement infrastructure included the construction of public roads,schools,local councils, health centers, markets and private ...
  61. [61]
    [PDF] The impacts of dams on local livelihoods: a study of the Bui ...
    Mar 18, 2015 · It had a maximum height of 110m from the foundation and two saddle dams, with a reservoir area of 444km2 at full supply level.Missing: specifications surface
  62. [62]
    effects of hydroelectric dam construction on land use land cover ...
    Significant reduction in rainfall and an increase in temperature were observed between the pre-and post-dam construction periods. Increased human activities ...
  63. [63]
    A Perspective Analysis of Dams and Water Quality: The Bui Power ...
    Oct 1, 2018 · The aim of this study was to investigate perceptions of drinking water quality among inhabitants of selected communities within the Bui Dam environs.Missing: inflow | Show results with:inflow
  64. [64]
    [PDF] China's Environmental Footprint in Africa - Johns Hopkins SAIS
    Sinohydro's Bui Dam, a project being financed by China Exim Bank, will flood about a quarter of Bui National Park in Ghana. The Lower Kafue Gorge Dam, a ...
  65. [65]
    Nutrients monitoring on the Bui multipurpose dam project in the ...
    Decreasing EC levels in the Bui dam directly affects fish species such as Alestidae, Anabantidae and Bagridae family. •. Irrigational water quality index shows ...Missing: fauna | Show results with:fauna
  66. [66]
    A Perspective Analysis of Dams and Water Quality: The Bui Power ...
    Oct 1, 2018 · However, the construction of such dams can have a detrimental effect on the environment. The aim of this study was to investigate perceptions of ...
  67. [67]
    physico-chemical characteristics of the bui dam area of the black ...
    The spatial area and dimension of reservoir formed is approximately 366.95 km at a spatial elevation of 176 m. Also, informal information solicited from ...
  68. [68]
    Assessing the influence of a dam reservoir on groundwater quality ...
    pH of groundwater in the Bui Dam Catchment is influenced by aquifer lithology. · Residence time and geochemical dissolution impact aesthetic characteristics to ...
  69. [69]
    Galamsey on Black Volta threatens livelihoods, Bui Dam
    Dec 30, 2024 · The river's pollution has led to a decrease in fish populations, impacting the local fishing industry. Moreover, the contaminated water poses a ...
  70. [70]
    Environmental, Social Issues & Mitigation Measures
    Mitigation Measures being implemented by BPA: Habitat Offset, Creation and Wildlife Protection and Rescue (Bui National Park – BNP), Tree salvaging and ...
  71. [71]
    [PDF] RP1139 V1 - World Bank Documents
    The proposed Bui Dam project in the north-western part of Ghana is expected to ... and adjust the mitigation measures where necessary. Monitoring and.
  72. [72]
    [PDF] A Case Study of the Bui Hydropower Dam in Ghana
    The study found that the dam has significantly changed river flow, soil characteristics, and the local ecosystem. This has affected how local communities ...
  73. [73]
    Nutrients monitoring on the Bui multipurpose dam project in the ...
    Aug 6, 2025 · Electrical Conductivity of Lake Water as Environmental Monitoring –A Case study of Rudra sagar Lake ... Bui dam project in Ghana. The study ...
  74. [74]
    BPA Resettlement Programme - Bui Power Authority
    The Bui Hydroelectric Project involved the resettlement of eight (8) communities with a total population of 1,216 people who were going to be affected by the ...
  75. [75]
    [PDF] Relocation exercise - Bui Power Authority
    The Bui Hydroelectric Project involved the resettlement of eight (8) communities with a total population of 1,216 people who were going to be affected by ...<|separator|>
  76. [76]
    [PDF] Interviews with People to be Affected by Bui Dam: A Field Report
    Bui Village and Bator are to be resettled as they are located within the area that will be flooded for the reservoir.
  77. [77]
    Bui Dam in the Black Volta River, Ghana - Ej Atlas
    The Bui Dam is a 400-megawatt hydroelectric project built on the Black Volta river at the Bui Gorge, at the southern end of Bui National Park.
  78. [78]
    [PDF] A Case Study of the Bui Dam Jama Resettlement Community, Ghana
    In this study, we examined how the BHP affected households and communities that were displaced and resettled. Varied impacts on livelihood assets (decline ...
  79. [79]
    Assessing Governance in Resettlement of Ghana's Bui Dam Project
    Resettlement resulting from dam construction has raised several concerns due to the negative aftermath impacts. In Ghana, the construction of three ...
  80. [80]
    The livelihood challenges of resettled communities of the Bui dam ...
    Apr 9, 2017 · While Chinese dam-builders played a major role in financing and enabling the dam's construction, the Ghanaian governance arrangements were found ...
  81. [81]
    Full article: Impact assessment of the governance principles in the ...
    Sep 12, 2024 · This study seeks to investigate the impact of governance principles applied in the implementation of dam-induced involuntary resettlement on host communities.
  82. [82]
    A Case Study of the Bui Dam Jama Resettlement Community, Ghana
    Study aimed to examine the impacts of the Bui-Dam Hydroelectric Power (BHP) project resettlement on communities' livelihoods.
  83. [83]
    The Livelihood Challenges of Resettled Communities of the Bui ...
    Aug 7, 2025 · Emerging issues from Bui hydro-power project are suggesting that the experiences of two earlier hydropower projects in Ghana failed in ...
  84. [84]
    (PDF) Effect of Bui Hydroelectric Dam on Household Livelihood ...
    The Bui Dam affected 1,219 people, displacing 219 households and covering 444 km² of agricultural land. Positive impacts include improved access to water, roads ...
  85. [85]
    the socio -economic impact of bui dam on resettled communities
    Aug 21, 2015 · Current scholarly works examining local scale socioeconomic and livelihood impacts of the Bui dam from our review have mostly concentrated ...
  86. [86]
    Impacts of livelihood assets on hydropower displacees' livelihood ...
    These outcomes can include increased income, improved well-being, reduced vulnerability, enhanced food security, and more sustainable resource use. The outcome ...
  87. [87]
    [PDF] Living with the Bui Dam; Implications for Community Livelihoods
    These issues were examined through a study of how the construction of Bui Dam was perceived by local communities representing several ethnic-linguistic groups,.
  88. [88]
    [PDF] Post-dam construction and livelihood revitalization of affected ...
    Nov 28, 2023 · This study examines if new programs at the Bui dam have revitalized local livelihoods disrupted by dam construction and resettlement.<|separator|>
  89. [89]
    [PDF] COMPARING THE AKOSOMBO AND BUI DAM PROJECTS
    1 The new 400 megawatt (MW) power project promises to guarantee Ghana's electricity supply and to develop neglected parts of the north.<|separator|>
  90. [90]
    A Case Study of the Bui Dam Hydroelectric Project
    Feb 11, 2020 · This paper examined the impact of the Bui Dam Hydroelectric project on the livelihood of the people affected, especially farmers in the Bono Region of Ghana.
  91. [91]
    The impacts of dams on local livelihoods: a study of the Bui ...
    Oct 19, 2025 · Large dams also have adverse local socio-economic impacts, such as negatively modifying the rural economy and rural employment structure (Obour ...
  92. [92]
    Sustainability Assessment of the Bui Hydropower System - MDPI
    PD has been used as an indicator to assess the environmental impact of a hydropower dam [31,34]. We used PD to evaluate how much power the Bui dam is creating ...