Quito Metro

The Quito Metro is an underground rapid transit system in Quito, the capital of Ecuador, comprising a single line that spans 22.6 kilometers with 15 stations linking the Quitumbe terminal in the south to El Labrador in the north. It serves as Ecuador's first metro system, designed to transport up to 400,000 passengers daily at a fixed fare of approximately 45 cents per trip, while operating as a fully electric network that reduces carbon emissions by an estimated 67,000 tons annually. Construction commenced in 2013 and faced significant delays, culminating in a brief soft opening in May 2023 followed by a temporary closure due to operational deficiencies, with full regular service resuming in December 2023. The project, constructed primarily by international consortia including ACCIONA, incurred costs of around $2 billion, financed through a combination of national and international loans, and has been noted for its role in addressing urban mobility challenges despite early teething problems such as technical glitches.

History

Planning and Initial Proposals

The concept of a metro system for Quito was first formally proposed in 1978 as part of the Plan Integral de Desarrollo Urbano de Quito hasta el año 2020, developed under Mayor Álvaro Pérez Intriago, which outlined necessary infrastructure including a metropolitan railway to address anticipated urban growth and mobility needs. This early vision emphasized long-term planning for a city expanding northward and southward, though it remained conceptual without detailed feasibility studies or funding commitments. Subsequent administrations revisited the idea amid growing from informal bus services and population increases. In 1988, during Rodrigo Paz Delgado's mayoral term (1988–1992), the was incorporated into updated urban development plans, highlighting the limitations of surface transport in Quito's narrow valleys and steep terrain. However, economic constraints and prioritization of (BRT) systems like the Trolebus, launched in 1995, deferred rail-based proposals. Serious planning resumed in the late as BRT capacity limits became evident, with daily ridership exceeding design thresholds by over 20% in key corridors. In 2009, under Mayor Augusto Barrera, the Municipality of initiated feasibility studies, culminating in a 2010 agreement with Spain's Region to conduct technical assessments for a north-south line spanning approximately 22 kilometers. These initial proposals targeted integration with existing BRT networks at endpoints like Quitumbe in the south and El Labrador in the north, aiming for a of 400,000 passengers daily to alleviate pressure on roads handling over 1 million trips per day. Early designs favored a mix of underground and elevated sections due to seismic risks and volcanic soil, with cost estimates around USD 2.2 billion reflecting imported technology needs.

Financing and International Involvement

The Quito Metro Line One project, with a total cost of approximately , was primarily financed by the Ecuadorian and the of , which covered the majority through national budgets and debt obligations. The committed to funding 63% of the costs, while the provided 37%, often channeled through development banks. International financial institutions played a key role in bridging funding gaps and mitigating risks not assumed by private lenders, providing concessional loans totaling over $1 billion. The (EIB) extended a €200 million (approximately $260 million at the time) sovereign loan to in November 2012 specifically for the metro line's construction. The (IDB) approved a $200 million loan in support of urban transportation infrastructure, including the metro system. —Development Bank of —contributed $402 million across multiple tranches, including a $152.2 million loan in July 2018 for the second construction phase. The provided initial project financing through an International Bank for Reconstruction and Development (IBRD) loan in 2013, followed by an additional US$230 million in June 2018 to address cost overruns and complete key components, emphasizing risk absorption for environmental and social safeguards. These multilateral loans, guaranteed by the Ecuadorian government, enabled the project to proceed despite fiscal constraints, with funds allocated to civil works, , and stations amid the line's 23 km length and high-altitude engineering demands. No significant equity or Chinese financing was involved in the core project, distinguishing it from some regional initiatives.

Construction Phase

Construction of Quito Metro Line 1 began on January 20, 2016, after the primary civil works contract was awarded in October 2015 to a led by Spanish firm for €1.4 billion, covering tunneling, stations, and associated infrastructure. The scope encompassed excavating approximately 22 kilometers of twin-bore tunnels via tunnel boring machines, erecting 15 underground stations, and developing a maintenance depot and workshops at Quitumbe in southern . Civil engineering efforts were segmented into phases, with handling Phase II, which linked the city's southern, central, and northern districts through elevated and subterranean segments adapted to 's Andean and seismic conditions. Initial projections anticipated 36 months for core construction followed by six months for systems , targeting operational readiness by mid-2019, though preparatory site works had traced back to 2013 under earlier planning. Progress advanced amid logistical hurdles inherent to urban tunneling in a high-altitude, geologically active , including soil variability and groundwater management, with over 270 buildings reporting vibration-induced damages by late 2017, prompting structural reinforcements and compensation protocols. By June 2021, physical reached 99% completion, including full boring and shells, but of rail systems and validations extended timelines due to technical complexities and pandemic-related supply disruptions. Substantial completion of civil and structural elements occurred by early , facilitating trial runs and eventual handover to operators, though the phase underscored the causal trade-offs of ambitious underground projects in seismically prone, densely built environments, where empirical monitoring of ground stability directly influenced pacing and mitigation costs. oversight through the Quito Metro Line One Project ensured adherence to environmental and social safeguards during excavation, including noise and dust controls, while financing supported depot expansions.

Delays, Testing, and Opening

The Quito Metro Line 1 experienced multiple delays from its initial projected operational date of late 2019, attributed to complexities in a seismically active, high-altitude , disruptions, and challenges with advanced signaling and ticketing systems. Further postponements occurred amid the , which affected workforce mobilization and material deliveries, pushing the timeline beyond 2020 targets. Dynamic testing of the fully assembled line began in late 2022, focusing on train operations, , and safety systems, but revealed deficiencies in signaling software reliability and platform screen door synchronization. A formal took place on December 21, 2022, with preview passenger services initially scheduled for January 5, 2023; however, faults in the system delayed this to January 23, limiting operations to select stations during peak hours. Trial revenue services expanded on May 2, 2023, serving nine of the 15 stations, but were suspended within weeks due to persistent signaling failures and overcrowding risks at intermodal hubs like Quitumbe. Remediation efforts, including software updates from suppliers and enhanced staff training, extended through mid-2023, culminating in full-system validation under load conditions simulating peak ridership of up to 350,000 daily passengers. Commercial operations across the entire 18 km route, from Quitumbe to El Labrador, launched on December 1, 2023, with residents participating in ribbon-cutting events at each station to mark the occasion. This phased rollout addressed prior vulnerabilities, enabling while maintaining manual oversight for reliability.

System Description

Route and Infrastructure

The Quito Metro Line 1 extends 22.6 kilometers north-south, connecting the Quitumbe terminal in the southern suburbs to El Labrador station in the northern district of Cumbayá, traversing central without any at-grade or elevated sections. The route aligns with major urban corridors, facilitating integration with existing systems at multimodal stations such as Chimbacalle and La Carolina. The infrastructure comprises twin single-track tunnels, bored at depths of 20 to 25 meters using three tunnel boring machines (TBMs) manufactured by AG, each with a 9.36-meter excavation diameter to accommodate the running tunnels and service voids. The tunnels employ segments for lining, installed via the TBMs' segmental erectors, with the project requiring approximately 20 kilometers of mainline tunneling completed sequentially by the machines named "Luz de Quito," "Quito Norte," and "Quito Sur." Stations are constructed using top-down methods with rectangular box structures, typically 140 meters long, 30 meters wide, and 20 meters deep, integrated into the bored tunnel alignment. The system operates on standard-gauge (1,435 mm) ballasted track with overhead catenary at 1.5 kV , designed for six-car consists and a maximum speed of 80 km/h. Signaling and train control utilize (CBTC) technology for automatic operation, supported by a depot and workshop facility near Quitumbe for maintenance of infrastructure and .

Stations

The Quito Metro Line 1 comprises 15 underground stations, all constructed to international accessibility standards with features such as elevators, escalators, , and security systems including CCTV. These stations facilitate connections to Quito's existing network, with five integrated directly with the Metrobús-Q BRT system. The design emphasizes efficient passenger flow, with platforms separated from tracks by to enhance safety. The stations, ordered from the northern terminus to the southern terminus, are: El Labrador, Jipijapa, Iñaquito, La Carolina, Pradera, Universidad Central, , La Alameda, , La Magdalena, El Recreo, Cardenal de la Torre, Solanda, Morán Valverde, and Quitumbe. El Labrador, in northern , serves as the northern endpoint and connects to local bus services. Quitumbe, the southern terminus, integrates with the interprovincial bus terminal, enabling transfers for regional travel. Key intermodal stations include La Alameda, linking to the Trolebús line, and Universidad Central, adjacent to the Central University of Ecuador and providing access to educational facilities. offers proximity to Quito's historic center, while connects to parks and university areas. La Magdalena functions as a hub for central transfers.
StationNotable Features/Connections
El LabradorNorthern terminus, northern Quito access
JipijapaNear Parque Bicentenario
IñaquitoClose to Quicentro Mall and Iñaquito Market
La CarolinaAccess to Parque La Carolina
PraderaResidential and commercial area
Universidad CentralNear Central University of Ecuador
El EjidoParks, universities, Trolebús integration
La AlamedaTrolebús connection,
San FranciscoHistoric center access
La Magdalena interchange
El RecreoShopping center proximity
Cardenal de la TorreCentral-south residential
SolandaSouthern residential zones
Morán ValverdeLocal bus connections
QuitumbeSouthern terminus, interprovincial terminal
This configuration supports daily capacities exceeding 400,000 passengers by linking high-density residential, commercial, and institutional zones.

Rolling Stock and Technology

The Quito Metro's consists of 18 six-car electric multiple units (EMUs) supplied by (CAF) of . Designated as the MQ117 model, each trainset comprises four motor cars and two cab cars with trailer bogies, totaling 108 cars across the fleet. The trains operate on 1,435 mm standard gauge rails with and feature a total length of 109 meters, a width of 2.8 meters, and a height of 3.8 meters. Each car includes four passenger doors, enabling a capacity of approximately 1,270 to 1,500 passengers per train depending on load factors. The trains achieve a maximum operating speed of 100 km/h, with an average commercial speed of 37 km/h, powered by the 1.5 kV overhead supplied by . This electrification includes approximately 46 km of rigid for sections and 6 km of flexible , supported by 11 traction substations. The relies on manned operation with drivers, incorporating elements provided by (formerly ). Key technical features emphasize reliability in high-altitude conditions, with the EMUs designed for the metro's fully 22.6 route navigating steep gradients and seismic risks inherent to Quito's . The integration of these components supports headways as low as 90 seconds during peak hours, contributing to the line's projected daily capacity of up to 400,000 passengers.

Engineering Challenges

The Quito Metro Line 1, situated at an of approximately 2,850 meters above , represents the world's highest underground system, imposing unique constraints on tunneling operations due to reduced , lower oxygen levels, and impacts on machinery performance such as cooling systems for tunnel boring machines (TBMs). These conditions necessitated specialized protocols for workers and modifications to equipment originally designed for lower altitudes, including enhanced and dust suppression in the 9.4-meter diameter tunnels. Seismic engineering posed a core challenge given Quito's position in a tectonically active Andean prone to earthquakes, with local soft volcanic sediments amplifying low-frequency seismic waves. The entire 22-kilometer system, including 19.5 kilometers of twin tunnels, was designed to withstand accelerations equivalent to a magnitude 7.8 event on the , incorporating ductile segments, flexible waterproof joints, and base isolation elements to absorb differential settlements and prevent structural failure. Geotechnical variability further complicated excavation, with three double-shield TBMs navigating a mix of cohesive volcanic soils, hard andesitic rock, and dense overburden that reduced advance rates in sectors like Solanda, where progress was limited to 1.5-meter segments before filling annular voids with bicomponent gels for stability. Despite these hurdles, one TBM set a productivity record of 1,489.5 meters in 30 days, aided by earth pressure balance techniques suited to the predominantly granular and low-permeability ground. Hydrological risks demanded innovative drainage solutions, particularly at stations like Carolina, where unexpected aquifers from the Rucu Pichincha volcano were encountered; engineers deployed dewatering wells, high-capacity pumps, and impermeable concrete linings to redirect groundwater flows and ensure a flood-resistant system. Construction beneath Quito's UNESCO World Heritage historic center required deploying 9,000 surface settlement monitors to detect and mitigate any deformations in adjacent colonial structures, maintaining strict limits on ground movement. Additionally, remediation of hydrocarbon-contaminated soils at La Pradera station involved extensive excavation and treatment to enable safe foundation work.

Operations and Service

Daily Operations and Capacity

The Quito Metro Line 1 operates daily with varying hours depending on the day of the week. On weekdays from to , service runs from 5:30 a.m. to 11:00 p.m., while Saturdays extend from 7:00 a.m. to 11:00 p.m., and Sundays from 7:00 a.m. to 10:00 p.m.. Trains maintain a of 3 to 4 minutes during peak hours and 5 to 7 minutes during off-peak periods, enabling efficient north-south travel across the 22.6 km route in approximately 34 minutes end-to-end.. The system utilizes a fleet of 18 six-car electric trains manufactured by , each capable of carrying up to 1,200 passengers.. Operation is managed by a led by , ensuring adherence to safety and maintenance protocols following the line's full commissioning in December 2023.. Designed for high-volume urban mobility, the Quito Metro has a theoretical daily of 400,000 passengers, supporting integration with the city's network to alleviate surface congestion.. This reflects the infrastructure's ability to handle peak demands, though actual throughput depends on ridership patterns and operational reliability.

Ridership Statistics

The Quito Metro Line 1 recorded 4.4 million passenger trips in December 2023, its first full month of commercial operations starting December 1, averaging 143,000 passengers per day. By February 2024, monthly ridership stood at 3.9 million passengers, reflecting seasonal variations including holidays. Cumulative trips reached 43.3 million by the end of September 2024, after 10 months of service, with daily averages hovering around 140,000–150,000 during this period. Ridership grew in 2025, with March totaling 4.8 million passengers and April reaching 5.2 million, an increase of 9.3% month-over-month and yielding a daily average of 174,755 in April. A single-day record of 226,000 passengers was set in May 2025, indicating peak demand during weekdays. By September 2025, after 21 months of operation, the system had accumulated 100 million trips, maintaining a daily average of approximately 174,000 passengers—about 43% of its designed capacity of 400,000 per day.
PeriodMonthly Trips (millions)Daily Average (thousands)Notes
Dec 20234.4143First month of operations
Feb 20243.9~125 (est.)Seasonal low
Mar 20254.8~155 (est.)Growth trend
Apr 20255.21759.3% MoM increase
Cumulative to Sep 2025100 (total)17421 months; below 400k capacity
Actual ridership has consistently fallen short of pre-opening projections of 131,000–400,000 daily passengers, achieving about 68% of targets in early 2024 and stabilizing below 200,000 daily as of late 2024, attributed to integration challenges with surface transit and urban adoption patterns. Despite this, year-over-year growth signals increasing reliance on the system for north-south corridors in .

Fares, Ticketing, and Integration

The standard fare for a single one-way trip on the Quito Metro is , applicable regardless of the number of stations traveled or distance covered. Reduced fares are available for eligible passengers: for children, students up to age 17, and seniors over 65; and for individuals with disabilities. These rates, denominated in dollars due to Ecuador's dollarized economy, have remained stable since the system's commercial opening on , 2023. Tickets are acquired at station-level ticket booths or automated vending machines prior to accessing platforms. Booths accept payments in coins or bills, while vending machines support credit or debit cards but do not provide change. The system employs contactless smart cards or paper s that are scanned and validated at fare gates for entry; each permits one boarding and is non-transferable for use on other trips or modes. No rechargeable multi-trip cards or mobile app-based payments have been implemented as of 2025, though initial plans for a system were abandoned in May 2023 due to technical failures. Integration with Quito's existing public transport network occurs primarily through physical interchanges rather than unified fares or ticketing. Five metro stations—Quitumbe, El Labrador, La Magdalena, Colón-Quitoguaya, and La Carolina—connect directly with bus rapid transit (BRT) corridors, including the Trolebús (central corridor), Ecovía (eastern corridor), and Metrobús-Q (western and southern extensions), enabling seamless transfers for passengers. However, no fare integration exists; riders must purchase separate tickets for BRT services, which cost approximately US$0.35 per trip. This setup supports multimodal journeys but requires multiple payments, contrasting with more unified systems in other Latin American cities. Plans for citywide electronic payment interoperability, including potential contactless cards across metro and BRT, remain in development as part of broader network enhancements.

Impact and Evaluation

Economic and Mobility Benefits

The Quito Metro Line 1 has significantly reduced average travel times for users along its corridor, with end-to-end journeys averaging 34.5 minutes compared to 45-55 minutes previously by surface , enabling faster connectivity between the city's southern and northern extremities. This improvement in speed and reliability has alleviated chronic road congestion, which previously exacerbated delays in Quito's bus-dependent system, by shifting an estimated daily ridership of over 400,000 passengers from overcrowded buses to a high-capacity alternative. Projections from project assessments indicate a broader reduction in average travel times from 38.5 minutes to 23.1 minutes for corridor users, enhancing overall and to and services, particularly for low-income residents in peripheral areas who previously faced longer commutes. Economically, the metro has generated an estimated USD 147 million in impact through 100 million cumulative passenger trips as of September 2025, driven by operational efficiencies, reduced individual transport costs, and stimulated local commerce near stations. By decreasing reliance on private vehicles and inefficient buses, it lowers city-wide congestion-related expenses, such as fuel consumption and lost productivity, while individual users save on fares and time—factors that compound into broader gains in labor mobility and economic output. The system's integration with existing bus rapid transit lines further amplifies these benefits, fostering transit-oriented development that boosts property values and business activity in underserved zones, though empirical data on precise real estate uplifts remains preliminary and station-specific. Overall, these effects support increased urban productivity by enabling more efficient worker commutes and reducing externalities like traffic-induced delays, aligning with causal links between reliable mass transit and localized economic vitality observed in similar Latin American implementations.

Social and Urban Effects

The Quito Metro Line One has enhanced urban by connecting underserved southern districts, such as Quitumbe and El Labrador, to northern commercial hubs like La Ofelia, thereby reducing north-south travel disparities in a historically divided by and socioeconomic gradients. Empirical modeling projects a modest narrowing of accessibility gaps, with pronounced benefits for trips exceeding 30 minutes, as the system's average speed of 35 km/h outperforms prior bus networks. This integration fosters denser around stations, evidenced by increased pedestrian activity and complementary bus feeders, though property value uplifts remain limited without aggressive reforms. Socially, the metro has democratized for low-income residents, who comprise over % of daily riders from peripheral zones, enabling better access to , , and healthcare in central areas previously bottlenecked by informal . By mid-2025, it had logged over 100 million passenger trips, correlating with reported time savings of up to 40% on key routes, which reallocates hours toward work productivity or family obligations rather than drudgery. Enhanced metrics, including lower accident rates per passenger-kilometer compared to surface buses, have reduced exposure to and vehicle hazards, particularly benefiting women and children in high-risk corridors. Urban sustainability gains include an estimated annual CO₂ reduction of 90,000 metric tons through modal shift from private vehicles and diesel buses, equivalent to reforesting 4.1 million trees, supporting Quito's denser, less sprawling growth pattern. However, initial ridership data from 2023–2024 reveal uneven adoption in informal settlements, where feeder lags, potentially perpetuating localized exclusion absent targeted extensions. Overall, these effects underscore causal links between and equitable urban function, though long-term socioeconomic multipliers depend on sustained integration with surface systems.

Criticisms and Shortcomings

The Metro has experienced recurrent failures leading to service suspensions, including a complete halt of operations on May 15, 2023, after just nine days of issues affecting multiple systems and subsystems, as determined by the Metro de Quito Company. Similar disruptions occurred in subsequent years, with suspensions attributed to cracks and other malfunctions reported as of May 2025. Infrastructure deficiencies include documented fisuras, or cracks, in the rail tracks identified in a February 2025 technical report, prompting user concerns and contributing to reduced train speeds to mitigate vibration-induced wear and potential structural risks. This speed reduction, implemented in early 2025, has exacerbated operational inefficiencies by increasing travel times and accelerating infrastructure degradation. Maintenance challenges have compounded these problems, with a failed for maintenance contracts leaving critical repairs unaddressed and leading to warnings from supplier in August 2025 about imminent risks of system paralysis due to unserviced radiocommunications components. The Metro operator dismissed these alerts as commercially motivated and irresponsible, asserting ongoing maintenance without specifying resolutions. User dissatisfaction is evident in reports of damaged station facilities, such as malfunctioning wait-time display screens as of August 2025, alongside broader complaints of delays and inadequate internal oversight of personnel. A October 2025 survey highlighted widespread user frustration with persistent technical faults and service unreliability. These shortcomings reflect systemic issues in procurement and upkeep, hindering the system's reliability despite its design capacity.

Controversies

Cost Overruns and Financial Mismanagement

The initial estimated cost for Line 1 of the Quito Metro was US$1.499,9 million, as projected in 2012 and intended to be financed equally by the central government and the municipality of Quito. By completion in 2023, the total investment had risen to US$2.107 billion, representing an overrun exceeding US$600 million primarily due to higher bids during the international licitation process and contractual price adjustments implemented in the project's second phase. Contract modifications approved in added US$27.6 million to the core construction contract, originally set at US$2.009 billion, after optimizations reduced proposed extras from US$95 million; key factors included US$35.26 million for soil excavation and treatment amid landfill capacity constraints at sites like El Troje and Bicentenario, US$14.78 million to remediate at La Pradera station, and US$8.31 million for redesigns at Universidad Central station to accommodate and enhancements. These escalations stemmed from unforeseen geotechnical challenges and demands, exacerbating delays that indirectly inflated financing costs. Financing leaned heavily on the municipality, covering 63% through loans from institutions like the , Banco del Estado, BNDES, and BEI, plus securitization of airport revenues and supplier credits, while the central government contributed 37% via multilateral lenders including BID, , and BEI. This structure projected US$195 million in interest payments for the municipality alone, straining local budgets amid Ecuador's broader infrastructure debt pressures. Allegations of mismanagement intensified scrutiny, with the National Anti-Corruption Commission citing indicios of overpricing in contracts favoring foreign consortia, including early involvement of —later withdrawn amid its global bribery —prompting demands for cost transparency and audits. Officials countered that no proven irregularities tainted Odebrecht's executed portions and emphasized the project's regionally low per-kilometer cost of US$95.7 million for its 22 km route, but persistent calls for independent verification highlighted risks from opaque adjustments and ties to scandal-implicated firms.

Construction and Safety Issues

The construction of Quito Metro Line 1, initiated in 2012, faced significant delays, originally slated for completion in 2020 but ultimately opening in December 2023 after a brief test run in May 2023 revealed the system was unprepared for full operations due to unresolved technical deficiencies. These setbacks stemmed from complex underground tunneling in seismically active terrain, requiring antisísmic reinforcements and flood prevention measures that engineers described as major challenges, alongside and negotiation hurdles that inflated timelines. Safety concerns during construction included multiple worker fatalities, with a World Bank assessment documenting at least six deaths linked directly or indirectly to the project by 2018, highlighting gaps in occupational health and safety protocols despite an existing management system. A notable incident occurred on November 30, 2017, when geologist Ignacio Piedra, aged 54, died in an accident involving the tunnel boring machine "La Carolina" operated by , underscoring risks in heavy machinery operations. Additionally, tunneling activities caused ground affecting at least 300 homes in the Solanda neighborhood, leading to structural damage and sinking foundations as a direct consequence of soil displacement. Post-opening, safety issues tied to construction quality emerged, including rail fissures detected in a December 2024 technical report at the Diagonal 4 section near El Recreo , where constant vibrations propagated cracks—one growing from 15 mm to 24 mm deep, the other from 10 mm to 13 mm—posing fracture risks that necessitated reduced speeds to avert potential derailments or accidents. Repairs were recommended by January 31, 2025, but implementation lagged amid expired maintenance contracts with , which ended December 31, 2024, and a failed bidding process for replacements, exacerbating vulnerabilities. One unit derailed in November 2024 and remained out of service, while the overall fleet's technical warranty expired in October 2023, shifting to ad-hoc inspections without comprehensive corrective measures. These defects have caused operational delays and heightened safety protocols, though no passenger incidents have been reported as of October 2025.

Political and Policy Debates

The decision to construct a full underground metro system rather than expanding existing (BRT) networks, such as the Trolebús, represented a central policy debate during Mayor Augusto Barrera's tenure (2009–2014). Barrera, aligned with Rafael Correa's Alianza PAIS party, prioritized the metro for its projected long-term capacity to handle 400,000 daily passengers and address mobility inequities, including a perceived where women disproportionately rely on ; he argued it aligned with the "Buen Vivir" development model emphasizing sustainable urban infrastructure. Critics, including subsequent mayoral candidates and technical analysts, contended that BRT expansion—estimated at $276 million for 23 km—offered a more fiscally prudent alternative with quicker implementation and lower risk to municipal debt, given the metro's $2.1 billion price tag funded partly through international loans and public bonds. This choice shifted from technical assessments to political contestation, with opponents demanding clearer financing plans amid Ecuador's economic constraints. Project continuity across administrations fueled further debates on political coherence versus electoral opportunism. After Barrera's departure, Mayor Mauricio Rodas (2014–2019) inherited the initiative but faced accusations of dilatory tactics influenced by opposition to Correa-era policies, contributing to delays beyond the 2019 target; Rodas advocated integrating the metro with BRT feeders but prioritized fiscal audits over acceleration. Subsequent leaders, including Jorge Yunda (2019–2023) and Pabel Muñoz (2023–present), navigated inheritance of cost overruns and scandals, with Muñoz denouncing pre-existing contracts as unfulfillable by certain firms, highlighting risks of politicized procurement over merit-based selection. Analysts have attributed execution flaws, such as suboptimal route alignments and underestimation of geological challenges in Quito's seismic zone, to excessive partisan interference rather than engineering rigor, eroding public trust in policy stability. Contracting processes have sparked persistent controversies over transparency and foreign influence. The involvement of Odebrecht in the Acciona-Odebrecht consortium, which secured the 2013 engineering-procurement-construction contract, drew scrutiny after the firm's 2017 exit amid regional bribery allegations; Ecuador's Comptroller General later identified overpayments exceeding $100 million in related audits, linking them to lax oversight during Correa's national government. A 2015 challenge by the runner-up bidder questioned renegotiations favoring the winner, raising policy questions on competitive bidding integrity. More recently, as of August 2025, maintenance contracts valued at tens of millions have ignited debates on fiscal risks and alleged political blocking of oversight by Correa-aligned council members, delaying awards until 2026 amid claims of inefficiency and potential cronyism. These episodes underscore tensions between ambitious infrastructure goals and safeguards against corruption, with proponents arguing that stringent post-scandal reforms have bolstered accountability.

Future Developments

Planned Extensions

The primary planned extension for the Quito Metro involves prolonging Line 1 northward from its current northern terminus at La Carolina to La Ofelia, incorporating four additional stations: Bicentenario, Andalucía, , and Ofelia. This 5.5-kilometer extension aims to enhance connectivity in northern , reduce transfer times to lines like the Trolebús at La Ofelia, and serve growing residential and commercial areas. As of March 2025, the Empresa Metropolitana de Transporte del Distrito Metropolitano de (EMT) conducted a webinar attracting interest from 34 companies across 16 countries for feasibility and design studies, indicating international engagement but no construction contracts awarded. Progress on definitive engineering and environmental studies advanced by February 2025, with municipal authorities prioritizing them to secure funding from multilateral lenders such as the Development Bank of Latin America and the Caribbean (). However, as of September 2025, the central government had not provided the required financial endorsement despite a December 2024 presidential commitment, creating uncertainty over timelines and raising risks of delays similar to those experienced in the initial line's construction. The extension's estimated cost remains undisclosed in public announcements, though it would integrate with existing to support projected ridership growth beyond the Line 1's current 300,000 daily passengers. Longer-term plans include a potential Line 2 extending southward toward , spanning approximately 20 kilometers and serving over 500,000 residents in southern with an projected investment of around $800 million. This second line, discussed in preliminary urban mobility proposals since 2024, would run parallel to major corridors but lacks detailed feasibility studies or funding commitments as of late 2025, positioning it as aspirational rather than imminent. Municipal plans emphasize phased implementation to address 's north-south divides, though fiscal constraints and competing infrastructure priorities could defer realization.

Ongoing Challenges and Prospects

Despite achieving a daily ridership of over 150,000 s as of June 2024, the Quito Metro operates well below its designed capacity of 400,000 daily users, posing challenges to financial recovery and . This shortfall, attributed to issues with bus systems and from informal , has delayed the realization of projected revenue streams needed to service the project's substantial , which reached Ecuador's municipal borrowing limits during . Early operational disruptions, including ticketing failures and technical faults that suspended services shortly after the May 2023 launch, highlighted vulnerabilities in system reliability, though services stabilized following resumption in December 2023. Extension efforts face procedural hurdles, as evidenced by the October 2025 suspension of a $11.9 million consultancy tender for the northern Line 1 expansion due to detected irregularities just before award. This 5 km addition, intended to link to Carcelén and alleviate northern congestion, contends with compressed timelines under the current mayoral term ending in 2027, compounded by Ecuador's fiscal constraints limiting domestic funding. Prospects hinge on securing multilateral financing, with recent bank missions evaluating support for the extension to enhance connectivity and ridership growth. Enhanced integration with existing corridors could boost overall system usage, potentially elevating metro patronage toward projections of 262,000 daily by stabilizing economic conditions and urban demand. Long-term sustainability may improve through operational optimizations by concessionaire , focusing on from the hydroelectric-powered fleet, which already averts significant CO2 emissions.

References

  1. [1]
    Ecuador inaugurates Quito Subway's Line 1, built by ACCIONA
    Dec 4, 2023 · 400,000 PASSENGERS/DAY: It is 22.6 kilometers long and has fifteen stations, as a key part of the city's new public transport network. Quito ...Missing: facts length
  2. [2]
    Finally: Metro Quito back in operation! - Urban Transport Magazine -
    Dec 6, 2023 · The metro is finally up and running! The line is 22 kilometres long and serves 15 stations from El Labrador to Quitumbe.Missing: length | Show results with:length
  3. [3]
    Quito Metro Train System – The Easy Way To Get Around The City
    For a fee of just 45 cents per person, one can make a single trip on Quito's Metro. This fee is fixed, irrespective of how many stations you plan to travel.
  4. [4]
    Quito Metro: A megaproject to transform mobility - World Bank Blogs
    Dec 6, 2023 · Metro benefits: 22,5 kilometers long with 15 accessible stations, a fully electric system that saves 67000 tons of CO2 a year, ...Missing: facts length
  5. [5]
    Quito's new Metro | Liberal Landscape
    Dec 20, 2023 · Construction started in 2013. The Metro opened briefly in May 2023 but closed quickly when it was realized that the system was not yet ready; ...Missing: facts | Show results with:facts
  6. [6]
    Quito Metro resumes operation - International Railway Journal
    Dec 12, 2023 · Regular operations restored after official opening in December 2022. ... Line 1 has been built at a total cost of $US 2bn, financed by the ...Missing: length | Show results with:length
  7. [7]
    In brief: Metro in Ecuador's capital Quito faces teething problems
    Authorities in Ecuador have heralded the opening of a metro system in the capital Quito, announcing that it successfully carried 25000 passengers o...
  8. [8]
    Exalcalde Álvaro Pérez imaginó Quito hasta el 2020 - El Comercio
    En 1978 fue elegido Alcalde de Quito. Con su equipo de trabajo creó el Plan Integral de Desarrollo Urbano de Quito hasta el año 2020. En ese plan consta, por ...
  9. [9]
  10. [10]
    Metro de Quito | PDF | Transporte - Scribd
    continuo debate sobre la necesidad de poseer un sistema de transporte masivo. En el año 1978, durante la alcaldía de Álvaro Pérez Intriago, se trazó el «Plan ...
  11. [11]
    Datos del Metro de Quito - Pichincha es Turismo
    1978. Álvaro Perez en el Plan Integral de Desarrollo Urbano de Quito, plantea por primera vez un sistema de transporte ferroviario metropolitano. · 1988. Rodrigo ...Missing: propuestas | Show results with:propuestas
  12. [12]
    Reemembranzas en La Construcción Del Metro de Quito - Scribd
    • (1978-1982) (Alcalde Álvaro Pérez) ( Plan Integral de Desarrollo Urbano) (Obras necesarias al 2020) Estaba contemplado el Metro de Quito • (1988-1992) ...
  13. [13]
    Quito prepares its first metro line - Experience ACCIONA
    A project will serve more than 400000 people each day and has 15 stations connecting neighbourhoods in the north and south of the city in just 34 minutes.Missing: initial proposals
  14. [14]
    pero no se concretó. Luego, en la campaña del 2009 ... - Facebook
    Una obra con un costo de USD 2.200 millones, su realización se la planteó en el Plan Integral de Desarrollo Urbano de Quito del año 1978, durante la alcaldía de ...
  15. [15]
    Quito metro 99% complete - International Railway Journal
    Jun 7, 2021 · The $US 2bn project has been funded by the European Investment Bank (EIB), the Inter-American Development Bank (IDB), the Andean Development ...Missing: contributions | Show results with:contributions
  16. [16]
    Quito Metro: Tunneling Towards a Sustainable Future
    Jan 16, 2024 · Financing the Future. Government Investment. The Ecuadorian government has been the primary source of funding for the Quito Metro project.
  17. [17]
    International consortium wins Quito Metro construction contract
    Oct 29, 2015 · The Municipality will finance 63% of the total cost and the 37% is covered by the Ecuadorian Government financing from Latin America Development ...Missing: breakdown | Show results with:breakdown<|control11|><|separator|>
  18. [18]
    Ecuador: EIB loan for Quito's first metro line
    Nov 28, 2012 · The European Investment Bank (EIB) is lending EUR 200 million to the Republic of Ecuador to finance Quito's first metro line.Missing: sources | Show results with:sources
  19. [19]
    IDB approves $200 million to support urban transportation in Quito
    The Inter-American Development Bank (IDB) today announced the approval of a $200 million loan for the construction of a metro system in the city of Quito, ...Missing: international involvement
  20. [20]
    Quito Metro: a solution to improve access and quality of transport
    It received financial support from CAF amounting to 402 million dollars, among other international financing bodies. May 05, 2024. share on facebook · share on ...Missing: sources involvement<|separator|>
  21. [21]
    US$152 million to finance first Quito subway line - CAF
    Jul 17, 2018 · CAF-development bank of Latin America- approved a loan of US$152.2 million for the Quito municipality, covering the second construction ...Missing: sources | Show results with:sources
  22. [22]
    World Bank Approves an Additional US$230 Million for Metro in ...
    Jun 25, 2018 · This new funding will contribute —together with other multilateral agencies— to closing the financing gap for this major work of infrastructure.Missing: China | Show results with:China
  23. [23]
    [PDF] The Quito Metro Line Project - World Bank Documents
    Jun 4, 2018 · The updated CBA does not include all potential cost overruns resulting from delays in the implementation schedule or potential additional ...Missing: controversies | Show results with:controversies
  24. [24]
    Ecuador: Metro Project Will Carry 400,000 People a Day in Quito
    Jul 25, 2013 · The Quito Metro Line One Project (PLMQ) involves an investment estimated at 1,499.9 million dollars (net of VAT). The line will be 23 kilometers ...Missing: China | Show results with:China
  25. [25]
    ACCIONA wins Quito metro contract worth €1,400 million
    Oct 28, 2015 · Construction is expected to take 36 months, with a further six months for systems integration and commissioning. The stations along the line are ...Missing: timeline | Show results with:timeline
  26. [26]
    Quito Metro construction works launched - Railway PRO
    Jan 20, 2016 · Construction is expected to take 36 months, with a further six months for systems integration and commissioning. Quito Metro is the best ...Missing: timeline contractors
  27. [27]
    Ecuador - Quito Metro Line One Project - World Bank Document
    Apr 19, 2018 · The proposed Project development objective (PDO) is to improve urban mobility in the city of Quito serving the growing demand for public ...Missing: early | Show results with:early
  28. [28]
    Quito Metro – Second Phase | ACCIONA | Business as unusual
    ACCIONA has executed Phase II of the Ecuadorian capital's first metro line. The project integrates the south, centre and north of the city in 34 minutes, ...Missing: timeline milestones<|separator|>
  29. [29]
    Quito Metropolitan Urban Transport System - IDB
    The Program will finance the construction of 22 km of railway, 15 stations, rolling stock and equipment for the metro system in Quito.Missing: breakdown international
  30. [30]
    [PDF] Quito Metro Line One (P144489) - World Bank Documents
    Dec 31, 2020 · IMPLEMENTATION TIMELINE AND KEY MILESTONES FOR PROJECT IMPLEMENTATION ... Start of operation (testing phase). Start of commercial operation.Missing: contractors | Show results with:contractors
  31. [31]
    Ecuador - Quito Metro Line One Project (English)
    The objective of the Quito Metro Line One Project for Ecuador is to improve urban mobility in the city of Quito serving the growing demand for public ...Missing: construction | Show results with:construction
  32. [32]
    Opening of Quito metro line pushed back to next year - BNamericas
    May 24, 2019 · Quito's first metro line will start operating next March or April, despite the previous mayor saying the US$2bn project would be up and running this year.Missing: phases | Show results with:phases
  33. [33]
    High altitude underground metro fully opens - Railway Gazette
    Dec 5, 2023 · A formal inauguration ceremony had been held on December 21 2022, when the launch of a preview passenger services was planned for January 5.
  34. [34]
    Metro de Quito | Organisations | Railway Gazette International
    Gauge: 1435 mm ; Length: 22·6 km ; Electrification: 22·6 km at 1·5 kV DC overhead ; Rolling stock: 108 metro cars (18 x six-car EMUs from CAF) ...
  35. [35]
    Quito Metro, Ecuador - Prointec
    The first line of the metro goes North-South with a length of 22.6 km, fully subway, 17 stations, 2 interchanges with buses and an area for Workshops and ...Missing: sources | Show results with:sources
  36. [36]
    Metro Quito - Herrenknecht AG
    The well-rehearsed TBM crew achieved weekly best performances of over 373 meters and daily best performances of 60 meters. The tunnel boring machine "Luz de ...Missing: details | Show results with:details
  37. [37]
    Quito Metro Line 1: TBM Tunnelling Works to commence in Spring ...
    Quito Metro Line 1 will be 22km long, using Herrenknecht TBMs, 20-25m deep, and is expected to open in summer 2019, transporting 350,000 daily.Missing: route length details
  38. [38]
    Quito Metro - Tunnels
    Jul 25, 2018 · It calls for 20km of main tunnelling, carried out by 9.4m-diameter EPBM; 15 top-down rectangular box stations with dimensions 140m x 30m x 20m, ...Missing: viaducts | Show results with:viaducts
  39. [39]
    Metro de Quito, Ecuador - Railway Technology
    Feb 10, 2014 · The construction works for the 22km-long Line 1 of the metro system started in January 2013. Plans to construct Lines 2, 3 and 4 are also being ...Missing: timeline milestones
  40. [40]
    Commissioning of Quito's first metro line, jointly operated by Transdev
    Dec 5, 2023 · On December 1, 2023, the first metro line in the capital Quito was commissioned, now operated for six years by Transdev and its partner Metro de Medellín.Missing: planning proposals<|separator|>
  41. [41]
    Estaciones - Metro de Quito
    Estaciones · Recorridos virtuales por estaciones · Información · Contacto.
  42. [42]
    LÍNEA 1 Route: Schedules, Stops & Maps - Metro de Quito - Moovit
    The LÍNEA 1 metro (Labrador - Quitumbe) has 14 stations departing from Estación El Labrador and ending at Estación Quitumbe. Choose any of the LÍNEA 1 metro ...
  43. [43]
    Quito Metro Line 1 - Wikipedia
    It connects the southern terminal at Quitumbe with the northern station at El Labrador, spanning 22.6 km entirely underground. It has 15 stations and is the ...Missing: facts | Show results with:facts
  44. [44]
    [PDF] Guía de Usuario - Metro de Quito
    Las Estaciones Multimodales son aquellas que te conectan con otros servicios de transporte público de Quito: Trolebús, Ecovía, Metrobús; convirtiendo a tu.
  45. [45]
    Transforming urban transport: Lessons from Quito's Metro Line One
    Feb 12, 2024 · Quito is a dense, transit-oriented city. Its 81-kilometer Bus Rapid Transit (BRT) corridors were maxed out and more could not be built in the ...Missing: length | Show results with:length
  46. [46]
    CAF to supply 18 six-car trains for Quito Metro line in Ecuador
    Jul 18, 2016 · Powered by a 1500VDC catenary supply, the 109m trains have four access doors per car and will run at a maximum speed of 100kmph. They have ...Missing: MQ117 | Show results with:MQ117<|separator|>
  47. [47]
    [PDF] MATERIAL RODANTE, EQUIPOS DE TALLER Y VEHÍCULOS ...
    El tren está compuesto por 4 coches (M1- M4) montados sobre 8 bogies motorizados y 2 coches con cabina (RCP1 – RCP2) montados sobre 4 bogies remolque.
  48. [48]
    Main Multilateral Organizations will Sign a Commitment for the ... - CAF
    Dec 5, 2013 · The rolling stock is made up by 18 formations of 6 subways cars of which 4 are motor cars, with capacity for 1,270 travelers (at a service level ...Missing: specifications | Show results with:specifications
  49. [49]
    Siemens electrifies Quito metro Line 1 - Railway PRO
    Oct 21, 2016 · The scope of the project includes about 46 km of rigid catenary, 6 km of flexible catenary, eleven traction power supply stations, 29 auxiliary ...Missing: signaling | Show results with:signaling
  50. [50]
    ACCIONA prepares the tunnel boring machine that will construct the ...
    Oct 13, 2016 · A total of three tunnelling machines will construct the 22 km and 15 stations of Line 1 of the Metro de Quito.Two machines will be checked and ...
  51. [51]
    Low‐Frequency Seismic Amplification in the Quito Basin (Ecuador ...
    To date, the Quito basin deep structure remains unknown as well as its effect on amplification of seismic waves. Since 2009, a permanent accelerometric network ...<|separator|>
  52. [52]
    99%: Metro Quito nears completion - Urban Transport Magazine -
    Jun 4, 2021 · The construction is 99% finished. And if all goes according to plan, trial passenger services will begin in December 2021 before commercial services can start ...Missing: proposals | Show results with:proposals
  53. [53]
    Metro of Quito - Tours in Ecuador and Galapagos - with SOLEQ.travel
    Jun 27, 2024 · The 22.5 km long route of the Quito Metro comprises 15 stations and connects the northern part of the city (El Labrador) with the southern part (Quitumbe).
  54. [54]
    ACCIONA presents the main challenges of constructing the Quito ...
    Oct 21, 2021 · The project consists of constructing a 22 km metro line with a 9.4-metre diameter tunnel spanning 19.5 km, which has been primarily excavated using three ...Missing: engineering | Show results with:engineering
  55. [55]
    Metro de Quito: los secretos de su construcción y sus retos para el ...
    Dec 15, 2020 · La construcción tuvo cuatro puntos que fueron un reto para los ingenieros y aseguran una obra antisísmica y sin inundaciones.
  56. [56]
    Complete Guide to Quito Metro: Ecuador's Modern Transit System
    Operating Hours and Frequency. The Quito Metro operates Monday through Sunday with trains running every 3-4 minutes during peak hours and every 5-7 minutes ...
  57. [57]
    Quito metro inaugurated for preview visits - Railway Gazette
    Jan 9, 2023 · The 18 six-car trains are 109 m long with a capacity of 1 230 passengers, and will operate at an average speed of 38 km/h. State-owned metro ...<|control11|><|separator|>
  58. [58]
    Transdev wins the contract to operate the Quito metro (Ecuador)
    Nov 30, 2022 · The total handling capacity of the line is 400,000 passengers per day. To ensure operation, the partners will recruit and train ...
  59. [59]
    Metro de Quito ha logrado el 68% de los pasajeros previstos para ...
    Mar 12, 2024 · En diciembre de 2023, el número de usuarios llegó a 4,4 millones, con un promedio diario de 143.041. En febrero la cifra fue de 3,9 millones y ...
  60. [60]
    Metro de Quito alcanzó 43 millones de viajes y 9.3 en calificación
    Oct 15, 2024 · Al cumplir 10 meses de operación, el Metro de Quito alcanzó 43'294.272 viajes al cierre del mes de septiembre de 2024, con un promedio diario ...
  61. [61]
    Cada vez más gente elige el Metro: récord de 226 mil pasajeros en ...
    May 22, 2025 · En marzo se registraron 4'801.917 pasajeros y en abril, la cifra ascendió a 5'249.051, lo que representa un aumento del 9,31 % respecto al mes ...
  62. [62]
    Más quiteños se suben al Metro: superan lo esperado en 2025
    May 7, 2025 · Durante abril, el promedio diario fue de 174.755 viajes, lo que representa un aumento de 440 mil viajes con respecto a marzo.
  63. [63]
    El Metro de Quito ya hizo 100 millones de viajes· ¿qué es lo positivo ...
    Sep 9, 2025 · 100 millones de viajes · 15 estaciones · 400.000 pasajeros al día · 174.000 usuarios al día ...
  64. [64]
    Metro de Quito: un año de operaciones con logros y desafíos
    Dec 1, 2024 · En su primer año de operación, el Metro ha logrado trasladar a 5 millones de pasajeros, lo que ha mejorado la movilidad de la ciudadanía.Missing: ingenieriles | Show results with:ingenieriles<|separator|>
  65. [65]
    Full Guide to Quito Metro: A Game-Changing Transportation
    Jan 23, 2024 · The route, which measures roughly 14 miles (22.5 kilometers), has 15 stops—starting in the south of the capital, Quitumbe, Moran Valverde, ...Missing: facts length
  66. [66]
    This is how the Quito Metro works: schedules, prices and how to pay
    Dec 3, 2023 · Ticket prices · Normal fare: $0.45. · Reduced rate (niños, niñas, teenagers up to 17 años and older adults): $0.22. · Preferential rate (People ...
  67. [67]
    The Gringo's Guide to Riding the Quito Metro
    Feb 15, 2025 · After Estación Jipijapa comes Estación Iñaquito, close to the Quicentro Mall, the Iñaquito Market, and great access to the Parque Carolina's ...Missing: 1 | Show results with:1
  68. [68]
    Quito metro finally running - Mainspring
    Dec 4, 2023 · The official inauguration was in December 2022, followed by a trial service and then peak-hour revenue service from 5 January 2023.Missing: frequency off-
  69. [69]
    Transportation in Quito, Ecuador - WPA 2025 Regional Congress
    Quito inaugurated its first metro line in December 2022, a major development for the city. ... Operating Hours: Typically 05:30 to 22:00, subject to updates. Cost ...
  70. [70]
    [PDF] 1 AIM 2 SCOPE - EPMTPQ
    An integrated public transport network within the Metropolitan District of Quito. ✓ Electronic payment systems available in the entire public transport ...
  71. [71]
    Ecuador: EIB confirms backing for sustainable urban transport ...
    Oct 18, 2016 · Once operational every day more than 400,000 people are expected to benefit from Quito's first ever metro line. The European Investment Bank is ...
  72. [72]
    [PDF] Ecuador - Quito Metro Line One - World Bank Documents & Reports
    Jun 28, 2013 · Infrastructure and Equipment Investment for the Quito Metro Line One: Construction of: (i) about twenty-three kilometers of tunnel linking the ...
  73. [73]
    USD 147 millones a la economía - Metro de Quito
    Sep 9, 2025 · Con 100 millones de viajes realizados, el Metro de Quito ha generado un impacto económico estimado en USD 147 millones.Missing: beneficios | Show results with:beneficios
  74. [74]
    Metro de Quito: satisfacción ciudadana alcanza 9,5/10 gracias a la ...
    Oct 16, 2025 · Económicos: Cada persona que usa el Metro reduce gastos de transporte y contribuye a que la ciudad ahorre en costos asociados a congestión, ...
  75. [75]
    Metro Quito: movilidad, plusvalía y nuevas zonas - Trivo Ecuador
    Metro Quito: impacto en el valor inmobiliario · Conectividad inmediata, con menos tiempo de traslado. · Ruido y mayor flujo peatonal en las salidas de estación.<|separator|>
  76. [76]
    Un sueño hecho realidad: El Metro de Quito - Moviliblog
    Nov 28, 2023 · Sus áreas de interés son el Desarrollo Orientado al Transporte, Planificación de Proyectos, Equidad de Género, Inclusión Social y Evaluación ...
  77. [77]
    Impact of Quito's first metro line on the accessibility to urban ...
    The results show that the PLMQ will increase overall accessibility to urban opportunities, and this impact depends on travel time and current accessibility ...
  78. [78]
    Impact of Quito's first metro line on the accessibility to urban ...
    On the other hand, a modest reduction of the accessibility gap is expected, with more visible benefits in long travel times (Quezada Larriva et al. 2023 ).
  79. [79]
    [PDF] BOLETÍN ESTADÍSTICO | Metro de Quito
    Dec 4, 2024 · El Metro de Quito es calidad de vida. Tiene un impacto económico, social y medioambiental muy importante para los ciudadanos y para el.
  80. [80]
    Impacto de la apertura del Metro de Quito - Actuaria Consultores
    Jan 4, 2024 · El metro de Quito tiene el potencial de reducir la siniestralidad de vehículos de varias maneras. En primer lugar, al proporcionar una ...Missing: urbanos | Show results with:urbanos
  81. [81]
    Metro de Quito impulsa una ciudad más verde y sostenible
    Jun 18, 2025 · Metro de Quito impulsa una ciudad más verde y sostenible · Reducción de 90.000 toneladas de CO₂, equivalente a la absorción que realizarían 4,1 ...
  82. [82]
    [PDF] Efectos del metro de Quito en la movilidad urbana.
    Jul 20, 2025 · Este estudio explora cómo el Metro de Quito ha influido en la movilidad urbana durante su primer año de funcionamiento (2023–2024).
  83. [83]
    Quito Metro ceases operations after nine days of problems
    May 15, 2023 · The decision was made by the Metro de Quito Company, citing technical issues in various systems and subsystems. The operator responsible ...
  84. [84]
    Metro de Quito: ¿Aún no cuenta con respaldo técnico? - Extra
    May 15, 2025 · Durante este tiempo se han registrado fisuras en los rieles y fallas técnicas que han obligado a suspender el servicio en varias ocasiones.<|separator|>
  85. [85]
    Informe técnico revela los problemas que tiene el Metro de Quito
    Feb 6, 2025 · Con una adjudicación fallida para el mantenimiento del Metro de Quito, las dos fisuras en las vías causan preocupación en los usuarios.
  86. [86]
    Reducción de velocidad en el Metro de Quito: el verdadero motivo ...
    Jan 31, 2025 · Mayor desgaste en la infraestructura por la vibración constante. Riesgo de fallas estructurales que comprometan la seguridad de los trenes.
  87. [87]
    Metro de Quito en riesgo: advierten sobre fallas graves en ... - Expreso
    Aug 27, 2025 · En la carta, Motorola Solutions señala que, de no garantizarse el servicio técnico especializado, el sistema puede presentar fallas críticas que ...
  88. [88]
    Gerente del Metro de Quito califica de "irresponsable" la carta de ...
    Aug 28, 2025 · El gerente del Metro dijo que la empresa está motivada por intereses comerciales y que su advertencia no se sostiene | Quito | Expreso.
  89. [89]
    Metro de Quito desmiente fallas por falta de mantenimiento
    Aug 28, 2025 · El Metro de Quito desmintió a la empresa fabricante del sistema de telecomunicaciones sobre un supuesto riesgo por falta de mantenimiento.
  90. [90]
    URGENTE En una reciente encuesta, muchos usuarios del Metro de ...
    Oct 17, 2025 · URGENTE En una reciente encuesta, muchos usuarios del Metro de Quito expresaron su malestar por fallas técnicas, demoras y problemas en el ...
  91. [91]
    El Metro de Quito habla de fallas en contratación y defiende su ...
    Sep 3, 2025 · El Metro de Quito habla de fallas en contratación y defiende su mantenimiento. El Metro de Quito habló sobre cómo realiza el mantenimiento del ...
  92. [92]
    Metro de Quito: ¿cuánto le costó a la ciudad construirlo?
    Dec 1, 2023 · El costo de la Línea 1 del Metro de Quito se estimó inicialmente en US$1.499,9 millones, que serían financiados en partes iguales entre el ...Missing: sobrecostos | Show results with:sobrecostos
  93. [93]
    El Metro tiene el menor costo por kilómetro para un sistema 100 ...
    Aug 7, 2023 · Hasta el momento, el Metro de Quito registra una inversión de $2.107 millones, lo que representa un costo por kilómetro de $95,7 millones.Missing: sobrecostos presupuesto
  94. [94]
    El Metro de Quito costará USD 27,6 millones más de lo establecido
    Sep 8, 2020 · El presupuesto inicial del contrato se fijó en USD 2 009 millones, pero ahora hay modificaciones. El Concejo Metropolitano de Quito conoció ...Missing: sobrecostos | Show results with:sobrecostos
  95. [95]
    Unos USD 195 millones en intereses pagará el Municipio por el Metro
    Aug 23, 2015 · ... sobrecostos que bordean el 50% del precio inicial ... Dos obras del Metro excluidas en la negociación · El costo final del Metro de Quito ...
  96. [96]
    Comisión Anticorrupción advierte que hay indicios de sobreprecios ...
    Dec 27, 2022 · Comisión Anticorrupción advierte que hay indicios de sobreprecios en la construcción del Metro de Quito. La Comisión insiste en que es ...Missing: sobrecostos | Show results with:sobrecostos
  97. [97]
    Denuncian que la construcción del Metro de Quito habría favorecido ...
    Dec 28, 2022 · La construcción del Metro de Quito tendría sobreprecios a favor de empresas extranjeras. (EFE/ José Jácome).
  98. [98]
    El Metro de Quito registra sobreprecios y varios retrasos para ...
    El presupuesto inicial del contrato se fijó en $2.009 millones, pero ahora hay modificaciones. ... El principal problema que tiene la Empresa Metropolitana Metro ...
  99. [99]
    [PDF] This document has a restricted distribution and may be used by ...
    Jun 5, 2018 · The higher-than-estimated cost of Component 2 generated delays for three main reasons: a) the Borrower conducted negotiations and a value.<|separator|>
  100. [100]
    [PDF] Ecuador - Quito Metro Line One Project - World Bank Document
    Apr 19, 2018 · and. EPMMQ has an OHS management system component in the PGASSH, there have been 6 worker deaths directly or indirectly associated with the ...
  101. [101]
    Un geólogo español falleció en la construcción del Metro de Quito
    Nov 30, 2017 · El geólogo español Ignacio Piedra falleció en un accidente en la operación de la tuneladora La Carolina, que construye la primera línea del ...Missing: retrasos | Show results with:retrasos
  102. [102]
    Muere un geólogo español en las obras de Metro de Quito al ...
    Dec 1, 2017 · Un geólogo español de 54 años falleció la noche de este jueves como consecuencia de una accidente en la zona donde trabajaba la tuneraladora ...Missing: retrasos | Show results with:retrasos
  103. [103]
    La construcción del metro de Quito afectó al menos 300 casas
    Feb 1, 2024 · Las casas de Solanda, al sur de Quito, se están hundiendo como resultado de la construcción del metro (Galo Paguay/ El Comercio).
  104. [104]
    Estos son los nuevos problemas que afectan al Metro de Quito
    Feb 12, 2025 · Un tren que no funciona, dos fisuras en las rieles y la falta de un contrato de mantenimiento son los problemas que se conocieron en febrero de ...
  105. [105]
    El Metro de Quito tiene problemas en sus trenes; el gerente Víctor ...
    Apr 30, 2024 · Los trenes ya tienen vencida la garantía técnica desde octubre pasado y lo que se hace actualmente el proveedor CAF son inspecciones de ...
  106. [106]
    Dos fisuras en las rieles del Metro de Quito provocan retrasos en los ...
    Feb 6, 2025 · El Metro de Quito reconoce que las dos fisuras obligan a que sus trenes disminuyan la velocidad para evitar mayores daños o accidentes.<|separator|>
  107. [107]
    Metro de Quito: Better or Bitter? Analysis of "Getting Around Quito"
    Aug 5, 2025 · The case study illustrates not only the policy dilemma faced by Barrera (mayor of Quito) but also expounds on his decisions favoring Metro ...
  108. [108]
    [PDF] Metro de OLito; Better or Bitter? - Analysis of “Getting Around Ouito
    The case study illustrates not only the policy dilemma faced by Barrera (mayor of Quito) but also expounds on his decisions favoring Metro over Rapid Train ...
  109. [109]
    El Metro: de debate técnico a pulso político - El Comercio
    Dec 16, 2014 · Todos los contrincantes políticos le exigen al Alcalde liderazgo, coherencia en el discurso y financiamiento para el proyecto. Según Barrera, ...
  110. [110]
    Los errores del metro de Quito: mucha política, poca técnica - GK City
    Jun 23, 2021 · Desde que se anunció su construcción, los errores del metro de Quito sobran. El mayor, quizás es tratarlo desde la politiquería.
  111. [111]
    Municipio denuncia irregularidades en contratos del Metro de Quito
    Jun 19, 2023 · El alcalde Pabel Muñoz denuncia que algunas empresas firmaron contratos con el Metro de Quito sabiendo que no podrían cumplirlos.Missing: controversias polémicos
  112. [112]
    Odebrecht sale del consorcio que construye el metro de Quito
    Dec 22, 2017 · El Municipio de Quito confirmó este jueves la salida de la brasileña Odebrecht, acusada de repartir millonarios sobornos a funcionarios en ...Missing: polémicos | Show results with:polémicos
  113. [113]
    Contraloría revela pago en exceso del Metro de Quito y ...
    Jun 26, 2019 · Estas filtraciones revelan, entre otras casos de la región, emails donde se discuten los pagos secretos realizados por un banco propiedad de ...
  114. [114]
    El Metro de Quito envuelto en una polémica profunda - Plan V
    Oct 26, 2015 · El consorcio que quedó en segundo lugar en la licitación del Metro capitalino cuestiona al Municipio por renegociar con Acciona-Odebrecht.
  115. [115]
    Contrato de mantenimiento del metro de Quito se concretará en el ...
    Aug 28, 2025 · Sesión del Concejo terminó en polémica · Concejo de Quito clausura sesión sobre el Metro por falta de quórum en debate clave · Expertos alertan ...
  116. [116]
    Correísmo Bloquea Fiscalización De Los Contratos De ... - YouTube
    Aug 27, 2025 · Correísmo Bloquea Fiscalización De Los Contratos De Mantenimiento Del Metro De Quito ... Controversia en Escena Con Miguel Rivadeneira.Missing: polémicos | Show results with:polémicos<|separator|>
  117. [117]
    El Metro de Quito anuncia su expansión hasta La Ofelia, estas ...
    Mar 10, 2025 · Cuatro nuevas estaciones para el Metro de Quito. Desde su inauguración, el Metro de Quito cuenta con 15 estaciones, que van desde El Labrador ...<|separator|>
  118. [118]
    Los estudios de extensión del Metro de Quito avanzan, mientras el ...
    Sep 29, 2025 · Las próximas estaciones serán: Bicentenario, Andalucía, Rosario y Ofelia. La CAF es uno de los organismos multilaterales que están ...
  119. [119]
    Metro de Quito: Municipio impulsa ampliación hacia La Ofelia, pero ...
    Sep 30, 2025 · Con las cuatro nuevas estaciones se pretende mejorar la cobertura del Metro, reducir tiempos de traslado y fortalecer la interconexión con otros ...
  120. [120]
    Extensión del Metro de Quito atrae a más de 34 empresas
    Mar 10, 2025 · El plan de extender el Metro de Quito hasta La Ofelia avanza. Un total de 34 empresas de 16 países participaron este lunes en la ...
  121. [121]
    Extensión del Metro de Quito atrae el interés de 34 empresas ...
    Mar 10, 2025 · Extensión del Metro de Quito atrae el interés de 34 empresas internacionales ... - El plan de extender el Metro de Quito hasta La Ofelia avanza.
  122. [122]
    Quito da pasos concretos para ampliar el Metro: estudios definitivos ...
    Feb 13, 2025 · Quito da pasos concretos para ampliar el Metro: estudios definitivos en camino. 13 febrero, 2025 13 febrero, 2025 2443 Views 4 comentarios.
  123. [123]
    Metro de Quito: Inicio
    Página oficial del Metro de Quito, el primer subsistema de transporte subterráneo de Ecuador que iniciará operaciones en diciembre 2022.Iniciar sesión · Quito se mueve · Escuela Metro de Quito · Metro
  124. [124]
    Expansión del Metro de Quito: Un Proyecto Clave para el Futuro de ...
    Conoce el ambicioso proyecto de Quito: extender el Metro hasta Calderón, mejorando la movilidad de 500000 habitantes con un costo de $800 millones.
  125. [125]
    Así sería la LÍNEA 2 DEL METRO de Quito ¡Calderón en la mira!
    May 5, 2024 · Cuánto costaría y por donde iría el trazado de la línea 2 del metro de Quito a Calderón ... EXTENSIÓN A LA OFELIA 06:20 EXTENSIÓN A CALDERÓN 08:47 ...
  126. [126]
    How Better Public Transport Helps Create Jobs in Latin America and ...
    Since its launch in 2023, Quito's new metro system has transformed urban mobility. As of June 2024, over 150,000 passengers use the service daily, and ...<|separator|>
  127. [127]
    [PDF] Project Profile - AWS
    The C40 Cities Finance Facility (CFF) supported Quito's transition to low-emission transportation by 2050 by preparing two zero emission bus corridors.
  128. [128]
  129. [129]
    Extension of Quito's metro faces tight timelines - BNamericas
    Jan 20, 2025 · According to the Quito municipality's plans, financial structuring for the project will be finalized by mid-year. This will determine the ...
  130. [130]
    Quito Metro pursues extension funding options
    Oct 9, 2025 · In July, Quito Metro opened bids for a $US 11.9m consultancy contract to undertake detailed engineering studies for the extension's four new ...