Fact-checked by Grok 2 weeks ago

Short-circuit test

The short-circuit test is a fundamental diagnostic procedure in electrical engineering used to evaluate the performance parameters of transformers, particularly the equivalent series resistance, reactance, and associated copper losses of the windings. By short-circuiting the secondary winding and applying a low voltage—typically 4% to 7% of the rated value—to the primary side until the rated current is achieved, the test isolates the effects of leakage flux and winding resistance while minimizing core losses due to the reduced flux density. This test, often paired with the , enables the development of the transformer's model, which is essential for predicting , , and impedance characteristics under load conditions. Key measurements include the short-circuit voltage (VSC), current (ISC), and input power (PSC), from which the equivalent impedance (Zeq = VSC / ISC), resistance (Req = PSC / ISC2), and (Xeq = √(Zeq2 - Req2)) are calculated, assuming balanced contributions from primary and secondary windings. These parameters are crucial for design validation, fault analysis, and ensuring the transformer's ability to withstand short-circuit stresses in power systems. The procedure is typically conducted at the factory or in a controlled lab setting using instruments like voltmeters, ammeters, and wattmeters, with safety precautions to handle the high currents involved.

Background and Purpose

Definition and Scope

The short-circuit test is a fundamental diagnostic method for transformers, conducted by short-circuiting the secondary winding terminals and applying a reduced voltage—typically 4% to 7% of the rated value—to the primary winding until full-load current circulates through the circuit. This setup isolates the effects of the series branch in the transformer's , allowing measurement of parameters such as equivalent resistance and leakage reactance while the core operates near no-load conditions due to the low applied voltage. Developed in the early as part of evolving design practices, the test addresses the need to evaluate winding characteristics without full-scale delivery. Its scope encompasses single-phase and three-phase transformers used in and systems, focusing on series impedance effects rather than overall or integrity. Key benefits of the short-circuit test include the precise quantification of copper losses, representing the I²R dissipation in the windings at rated , and the assessment of leakage , which influences and fault current limiting. By avoiding core saturation and excessive magnetizing flux, the test ensures safe operation and reliable data for modeling. It serves as a complement to the , which evaluates shunt parameters like core losses.

Role in Transformer Parameter Determination

The short-circuit test serves as a fundamental method for quantifying the equivalent R_{eq}, which directly corresponds to the copper losses in transformer windings, and the equivalent leakage X_{eq}, which is critical for evaluating under load. Copper losses, arising from the of the windings, are determined through the power dissipated during the test, providing a measure of the transformer's full-load I²R inefficiencies. The leakage , derived from the impedance measurement, quantifies the due to between windings, enabling predictions of output voltage stability across varying load conditions. When paired with the , the short-circuit test facilitates the complete determination of the transformer's parameters. The isolates core-related parameters such as no-load losses and magnetizing , while the short-circuit test focuses on the series elements, allowing for a holistic model that supports assessments and operational performance forecasting. This combined approach is essential for verifying the transformer's ability to maintain and regulate voltage in practical applications. The procedure aligns with established standards for post-manufacturing , including IEEE Std C57.12.90, which outlines protocols for impedance and load loss measurements in liquid-immersed to confirm design specifications. Likewise, IEC 60076-1 specifies requirements for short-circuit impedance and load loss evaluations to ensure reliability and compliance. These tests are typically conducted at reduced voltage to minimize heating effects.

Theoretical Principles

Equivalent Circuit Representation

In the short-circuit test of a , the is simplified to focus on the series , typically referred to one side of the (e.g., the primary winding) for analysis in either actual or per-unit values. This approximate model consists of a series equivalent R_{eq} and equivalent leakage X_{eq}, representing the combined effects of the primary and secondary winding resistances and leakage inductances, with the secondary winding short-circuited. The shunt magnetizing branch, which includes the core loss resistance and magnetizing reactance, is neglected in this representation because its impedance is significantly higher than the series branch under short-circuit conditions, effectively making it infinite and rendering the excitation current negligible compared to the full-load current. This simplification isolates the series elements, allowing the test to directly measure the associated with winding losses and leakage flux. In phasor terms, the primary voltage applied during the test appears as a drop across the series combination of R_{eq} and jX_{eq} when full-load flows, forming a in the impedance diagram where the is the total equivalent impedance Z_{eq}, the adjacent side to the current phasor is R_{eq}, and the opposite side is X_{eq}. This model provides a for understanding the transformer's internal and under load without considering no-load effects.

Leakage Impedance and Losses

The leakage flux in a transformer originates from the imperfect between the primary and secondary windings, where not all flux generated by the current in one winding links with the other. This phenomenon, quantified by a coupling coefficient k < 1, results in flux paths that do not mutually couple, primarily due to the physical separation and geometry of the windings around the core. The presence of this leakage flux introduces an equivalent leakage X_{eq}, which manifests as a across the under load, typically accounting for 5-10% of the rated voltage at full load conditions. Copper losses in the transformer windings, known as I^2 R losses, arise from the resistance of the conductor material and become the dominant loss component during the short-circuit test. In this test, a reduced voltage is applied to drive full-load current through the windings while the secondary is shorted, minimizing core-related effects and isolating the ohmic heating in the copper conductors. These losses represent the full-load copper losses of the transformer, providing a direct measure of the equivalent resistance R_{eq} without significant interference from other dissipative mechanisms. The overall leakage impedance combines these effects through the equivalent impedance Z_{eq} = \sqrt{R_{eq}^2 + X_{eq}^2}, where R_{eq} captures the resistive losses and X_{eq} the reactive component from leakage . This impedance is commonly expressed in terms as \%Z = \left( \frac{V_{sc}}{V_{rated}} \right) \times 100\% at full-load current, with typical values for transformers ranging from 4-6%, influencing short-circuit current limits and . In the representation, these parameters simplify the transformer's behavior under short-circuit conditions to a series of and .

Test Procedure

Equipment and Setup

The short-circuit test on a requires specific apparatus to apply a reduced voltage to one winding while the other is shorted, enabling measurement of leakage impedance and losses under conditions approximating full-load . Essential includes a variable (such as a Variac) to provide a controlled low-voltage supply, typically limited to 5-10% of the rated voltage; ammeters and voltmeters, preferably true types for accurate and voltage readings; and a to measure input power. Additionally, a short-circuiting link or heavy bar with low is used to fully short the secondary winding, ensuring minimal additional impedance in the circuit. In the setup configuration, the transformer's secondary winding is completely shorted using the low-resistance link or bar, with all terminals securely connected to prevent arcing or incomplete shorting. The primary winding is then connected to the variable output, which serves as the power source, while the measuring instruments— in series with the primary, across the primary, and in the primary —are positioned to capture readings without introducing errors from lead drops. Proper grounding of the transformer frame and of unused circuits are critical to avoid stray currents or hazardous potentials during the test. For enhanced precision in modern applications, digital test systems like the TESTRANO 600 can integrate , metering, and in a single unit. Safety considerations are paramount, as the test induces full-load currents in a low-impedance path, risking overheating or mechanical stress if not controlled. Voltage is gradually increased from zero via the to reach the desired current level, never exceeding equipment ratings or allowing prolonged exposure beyond a few minutes to prevent thermal damage. Protective relays or circuit breakers should be incorporated in the setup to interrupt power in case of faults, and all connections must be verified for tightness to minimize risks of arcing or .

Step-by-Step Execution

The short-circuit test on a is executed by applying a reduced voltage to the primary winding while the secondary is short-circuited, enabling measurement of parameters related to leakage impedance and losses without significant effects. This low-voltage approach ensures that the magnetizing remains negligible, isolating the equivalent series impedance of the . The procedure begins with short-circuiting the secondary terminals using a low-resistance of sufficient cross-sectional area, typically rated for at least 2.5 A/mm² to minimize additional resistance. Instruments are then connected to the primary side: a across the supply terminals, an in series with the line, and a to measure input power. With the (variac) set to zero output, the power supply is switched on at the rated frequency. Voltage is gradually increased via the variac until the ammeter indicates the rated full-load primary current, which typically requires only 5-10% of the rated primary voltage. At this point, the readings are recorded promptly: the short-circuit voltage V_{sc} from the , the full-load current I_{sc} from the , and the power P_{sc} from the . For three-phase transformers, the of the three-phase instrument readings is used for voltage and current to account for any imbalances. The voltage is then slowly reduced to zero, the supply is switched off, and connections are safely disconnected. Key precautions include ensuring the transformer windings are at ambient temperature before starting, with any temperature rise during the test limited to 10-15°C to prevent thermal effects on measurements; the test should be completed quickly, often within seconds, to achieve this. The transformer must be properly grounded, and the test area restricted to authorized personnel wearing appropriate protective equipment, such as insulated gloves and safety glasses, due to the high currents involved. For three-phase setups, phase balance must be verified to avoid uneven loading. Instruments should be calibrated beforehand, and no connections altered while voltage is applied. Common errors that can compromise accuracy include incomplete shorting of the secondary terminals, which introduces extraneous and inflates voltage readings, or poor in test leads that alters the measured impedance. Exceeding the rated current due to inadequate monitoring risks winding damage, while uncalibrated instruments lead to erroneous data. In modern practice, manual procedures are increasingly supplemented by automated benches compliant with updated standards like IEEE C57.12.90-2021, which enhance precision and safety but require verification against traditional methods for reproducibility.

Data Analysis and Calculations

Measuring Parameters

During the short-circuit test on a , the primary parameters measured are the short-circuit voltage V_{sc}, which is the reduced input voltage applied to the primary winding to produce full-load rated I_{rated} with the secondary short-circuited; the active power P_{sc}, indicating the full-load copper losses; and the I_{sc}, verified to equal the rated value. These measurements provide immediate insight into the transformer's leakage impedance and without requiring full rated voltage. To achieve reliable results, a measures the real power P_{sc}, while a and record V_{sc} and I_{sc}, respectively; these instruments, including any used, should have accuracy classes of 0.3 or better to minimize measurement errors in low-voltage, high-current conditions. The power factor \cos \phi is derived indirectly from the relation \cos \phi = \frac{P_{sc}}{V_{sc} I_{sc}}, offering a quick assessment of the phase angle between voltage and current. Data validation is essential, with I_{sc} confirmed to closely match the rated current through voltage adjustment during the test; readings are repeated multiple times for consistency, and instrument calibration is checked to address potential errors from drift or environmental factors. This ensures the recorded parameters accurately reflect the transformer's performance under simulated full-load conditions.

Deriving Equivalent Impedance

The short-circuit test provides the raw measurements of short-circuit voltage V_{sc}, short-circuit current I_{sc}, and short-circuit power P_{sc}, which are used to compute the transformer's equivalent series referred to the primary side. These parameters include the equivalent R_{eq}, equivalent X_{eq}, and the overall equivalent impedance Z_{eq}, enabling the modeling of the transformer's series branch in the . The full-load copper loss, representing the total I^2R losses across both primary and secondary windings at rated current, is directly obtained from the test as P_{cu} = P_{sc}. This value accounts for the combined resistive losses under full-load conditions. The equivalent resistance R_{eq} is calculated from the power measurement and current, as the power dissipated in the short-circuit test is primarily due to the resistive components: R_{eq} = \frac{P_{sc}}{I_{sc}^2}. This resistance is the sum of the primary resistance and the secondary resistance referred to the primary side. The magnitude of the equivalent impedance Z_{eq} is determined by the ratio of the applied voltage to the resulting under short-circuit conditions: Z_{eq} = \frac{V_{sc}}{I_{sc}}. The equivalent X_{eq}, which captures the leakage effects, is then derived using the Pythagorean in the impedance : X_{eq} = \sqrt{Z_{eq}^2 - R_{eq}^2}. These steps yield the series branch components R_{eq} and X_{eq}. The short-circuit power factor is given by \cos \phi_{sc} = \frac{R_{eq}}{Z_{eq}}, indicating the phase angle between and during the test, typically low due to the inductive nature of the . Additionally, the percentage impedance, a key performance metric, is expressed as \%Z = \left( \frac{V_{sc}}{V_{rated}} \right) \times 100, where V_{rated} is the rated primary ; this quantifies the and short-circuit withstand capability. To illustrate, consider sample measurements from a short-circuit test: V_{sc} = 50 V, I_{sc} = 10 A, and P_{sc} = 100 W. The full-load copper loss is P_{cu} = 100 W. The equivalent resistance is R_{eq} = \frac{100}{10^2} = 1 \, \Omega. The equivalent impedance magnitude is Z_{eq} = \frac{50}{10} = 5 \, \Omega, and the equivalent reactance is X_{eq} = \sqrt{5^2 - 1^2} = \sqrt{24} \approx 4.9 \, \Omega. The short-circuit power factor is \cos \phi_{sc} = 1/5 = 0.2. Assuming a rated voltage of 1000 V, the percentage impedance is \%Z = (50/1000) \times 100 = 5\%. These values allow direct incorporation into the transformer's equivalent circuit model.

Variations and Applications

High-Power Testing Methods

High-power short-circuit testing methods for involve applying full-rated voltage to the primary winding while the secondary is short-circuited, generating the through the windings for a controlled duration of typically 2 seconds per sequence, initiated and terminated by high-speed circuit breakers. This approach subjects the transformer to the full of electromagnetic forces and stresses encountered during actual faults, with multiple sequences (e.g., three tests) performed to verify repeated withstand capability. The primary purpose of these tests is to simulate external fault scenarios, assessing the mechanical integrity of windings, core clamps, and support structures against axial and radial forces that can reach hundreds of tons in peak moments. By operating at rated voltage, the method captures saturation effects and transient asymmetries not fully replicated in low-voltage tests, ensuring the can endure dynamic overloads without deformation or failure. Post-test evaluations include visual inspections, winding measurements, and checks to confirm no permanent damage, with acceptance criteria limiting winding temperatures to 250°C for conductors in oil-immersed units. Essential equipment comprises high-capacity short-circuit generators or supplies delivering currents up to several kiloamperes, oscilloscopes for recording waveforms and factors, and strain gauges or fiber-optic sensors affixed to windings to quantify mechanical deformations in . These tests comply with IEC 60076-5 standards, which outline symmetrical RMS requirements (within 10% ) and based on the X/R , often exceeding 2.5 for power transformers. For impulse withstand aspects, the standard integrates coordination with lightning impulse tests per IEC 60076-3. For ultra-large transformers exceeding 500 MVA, full short-circuit tests are often impractical due to limited high-power facilities worldwide; instead, compliance is demonstrated through detailed calculations, testing of scaled or similar designs, or exemption under provisions. Emerging synthetic testing methods, primarily developed for , are being explored for replicating fault stresses in transformers with reduced power requirements, enabling validation for high-voltage applications up to 1200 kV while maintaining fidelity to IEC criteria.

Use in Other Electrical Machines

The short-circuit test principles, adapted from transformer testing, are applied to induction motors through the locked-rotor test, where the rotor is mechanically prevented from rotating, and reduced voltage is applied to the stator terminals to measure the equivalent rotor-referred impedance under near-short-circuit conditions. This test determines parameters such as leakage reactance and resistance, typically at 25% of rated voltage to limit current to rated full-load value, enabling calculation of starting torque and current without excessive heating. For synchronous generators, the sustained short-circuit test involves applying a three-phase short circuit to the armature terminals from a no-load condition while maintaining constant field excitation and prime-mover input to assess the direct-axis synchronous reactance X_d. The armature current is measured under steady-state conditions, with the ratio of open-circuit voltage to short-circuit current yielding X_d, which is crucial for stability analysis and fault current prediction. Adaptations for synchronous machines incorporate measurement of field excitation current during the short-circuit test to account for voltage variations, improving parameter estimation accuracy by mitigating errors from constant field assumptions in transient conditions. In modern applications, such as transformers integrated into (EV) chargers and like , short-circuit tests ensure compliance with updated standards, including IEC 60076 requirements for withstand capability under fault conditions in offshore step-up transformers. These tests verify impedance and thermal limits, supporting integration of variable renewables as per emerging 2025 guidelines in IEC TS 61400 series for electrical characteristics. The short-circuit test is not directly applicable to DC machines, as their steady-state operation lacks the inductive reactance dominant in AC machines, rendering short-circuit conditions primarily a direct resistive fault without equivalent impedance derivation. Typical percent impedance (%Z) values derived from these tests in motors range from 15-20%, higher than the 5-10% in transformers, reflecting greater starting demands.

References

  1. [1]
    [PDF] Chapter 5
    Define transformer exciting current. • Develop transformer equivalent circuits from open-circuit and short- circuit test data. • Analyze transformer operation.
  2. [2]
    [PDF] Ex- S - 326
    The short-circuit test i-s an experimental- method of determining the equivalent resistance, impedance, and. reactance of a transformer.Missing: parameters | Show results with:parameters
  3. [3]
    [PDF] EXPERIMENT 2 - page for courses.ece.vt.edu
    Sep 9, 2021 · We will use the results of short circuit (SC) test and open circuit (OC) test to find the values for a transformer equivalent circuit as shown ...
  4. [4]
    Charles Steinmetz - Lemelson-MIT
    Mathematician, engineer and inventor Charles Proteus Steinmetz was responsible during the latter part of the 19th and early part of the 20th century for ...
  5. [5]
    Transformer Short Circuit Test - Voltage Disturbance
    Nov 26, 2020 · Short circuit test is performed on a transformer to measure the equivalent series resistance and reactance.
  6. [6]
    Open and Short Circuit Test of Transformer - Electrical4U
    Jul 14, 2012 · Copper Losses Measurement: In the short circuit test, the wattmeter reading measures copper losses since the applied voltage is low and core ...
  7. [7]
    Determination of Transformer equivalent circuit from ... - Virtual Labs
    Short Circuit Test: · It determines the copper loss occurs on the full load. The copper loss is used for finding the efficiency of the transformer. · The ...
  8. [8]
    Short Circuit Test and Open Circuit Test of Transformer
    The open circuit and short circuit tests are performed to find circuit parameters, regulation, and efficiency of a transformer.
  9. [9]
    Open and Short Circuit Test of Transformer - GeeksforGeeks
    Oct 18, 2023 · Open and short circuit tests are performed on a Transformer to evaluate its performance characteristics and parameters which mainly determine the Voltage ...
  10. [10]
    IEEE C57.12.90-2021
    Feb 4, 2022 · IEEE Standard Test Code for Liquid-Immersed Distribution, Power, and Regulating Transformers ... short-circuit tests, audible sound level ...
  11. [11]
    [PDF] IEC 60076-1:2011 - iTeh Standards
    Short-circuit impedance and voltage drop ... the assembly of turns forming an electrical circuit associated with one of the voltages.
  12. [12]
    ECE 342 - Lab 3: Power Transformer Open and Short Circuit Tests
    The short circuit test is used to determine the values Rs and Xs of the series branch of the equivalent circuit. These impedances are usually very low, but ...
  13. [13]
    [PDF] Lecture 10. Ideal transformers
    Imperfect coupling (k < 1) leakage flux path. +. N1I1. +. N2I2. Rcore. ϕ1. ϕ2. Rleak. Flux from coil 1 partially received by coil 2, and partially leaked out.
  14. [14]
    A simple analytical method for accurate prediction of the leakage ...
    The value of the leakage reactance usually ranges between 4% and 20% of the base transformer rating (Dawood and Komurgoz, 2019). Voltage drop, short-circuit ...
  15. [15]
    Open-Circuit and Short-Circuit Tests in Transformers - EEPower
    Sep 9, 2022 · A transformer could be tested under no-load and full-load conditions to determine its turns ratio, regulation, and efficiency.
  16. [16]
    How to correctly size a transformer - Consulting - Specifying Engineer -
    Dec 24, 2019 · For instance, %Z for transformer with high-voltage side less than 34.5 kilovolts is between 5.5% and 7.5%. Note that the typical %Z for 13.8 ...
  17. [17]
    How To Test A Transformer | Meta Power Solutions
    The Short-Circuit test measures the full-load losses of a transformer. It is performed by energizing a transformer with its secondary winding shorted. Thus, the ...
  18. [18]
    [PDF] TRANSFORMERS
    Constraint: The current delivered to the winding under test must not exceed 1 Amp. b. Connect the primary of the transformer to the autotransformer. Open.
  19. [19]
    [PDF] Model of a Power Transformer - Electrical & Computer Engineering
    In this experiment you will perform a short-circuit (S.C.) test and find RS and XS to complete the transformer model. Finally, you will compare some lab ...
  20. [20]
    Common Electrical Tests on Power Transformers - OMICRON
    With TESTRANO 600 you can measure transformer turns ratio, DC winding resistance, dynamic resistance, leakage reactance / short-circuit impedance and frequency ...
  21. [21]
    Precautions for Transformer Short Circuit Test - Knowledge
    Oct 16, 2023 · (1) During the test, the tested winding should be on the rated tap. (2) Test wires, especially those used for short circuits, must have sufficient cross- ...
  22. [22]
    Transformer Short Circuit Test: Purpose, Procedure & Calculations
    Oct 29, 2025 · Always verify that the transformer is properly grounded before beginning the test. The test area should be clearly marked and restricted to ...<|control11|><|separator|>
  23. [23]
    Short Circuit Test of Single Phase Transformer - Theory and Practical
    This is obtained by using the equivalent circuit (phasor diagram) of the transformer with purely resistive load and putting ZL' = 0. Measuring power input (WSC ...
  24. [24]
    Open and Short Circuit Test of Transformer - Elentechpk
    Aug 28, 2025 · The Short Circuit Test (SC Test / Impedance Test) is primarily performed to determine a transformer's: Copper losses (I²R losses); Equivalent ...
  25. [25]
    None
    Summary of each segment:
  26. [26]
    [PDF] IEC 60076-5 - iTeh Standards
    This part of IEC 60076 identifies the requirements for power transformers to sustain without damage the effects of overcurrents originated by external short ...
  27. [27]
    [PDF] On line analysis of short circuit tests on windings
    For two winding transformers of category 1, three tests of 0.5 s each are required to be performed. The short circuit test is equally valid for voltage.
  28. [28]
    [PDF] Short-circuit withstand capability of power transformers - ABB
    ABB's transformers have outstanding short-circuit performance, handling high voltages and ratings, and are designed to pass short-circuit tests. Short-circuits ...
  29. [29]
    Improved Testing Method Using the Multi-Transformers Synthetic ...
    Jun 16, 2023 · This paper proposes a new multi-transformer synthetic circuit (MTSC) test method that replaces the general synthetic test method using capacitor banks.
  30. [30]
    [PDF] Testing, Inspections - CESI
    KEMA Labs are equipped to test large power transformers with an extremely high short-circuit capability. ... testing platform for synthetic testing, high.
  31. [31]
    Blocked Rotor Test of Induction Motor | Electrical4U
    Jun 5, 2024 · The blocked rotor test is similar to the short circuit test of a transformer. In this test, the motor's shaft is blocked, and the rotor ...
  32. [32]
    Determination of the Synchronous Reactance | OCC and SCC test
    During the short circuit test the loss can be obtained by measuring the mechanical power required to drive the machine. The loss comprises the following items:.
  33. [33]
    Parameter estimation of synchronous machines considering field ...
    This work examines the influence of field voltage variation during a sudden short-circuit test and its direct impact on the parameter identification of ...
  34. [34]
    What Are the IEC Standards for Power Transformers? Complete Guide
    Oct 30, 2025 · IEC mandates comprehensive electrical, mechanical, and thermal tests, including dielectric, short-circuit, and temperature rise evaluations.
  35. [35]
    IEC TS 61400-21-4:2025
    Apr 16, 2025 · IEC TS 61400-21-4:2025 specifies a methodology for measuring and assessing electrical characteristics of wind turbine components and subsystems.
  36. [36]
    Testing of DC Machine - GeeksforGeeks
    Jul 23, 2025 · The short-circuit test is performed to create the short-circuit characteristic curve of the machine. In this test, the end parts of the armature ...
  37. [37]
    Typical Values For Motor Impedances and KVA Ratings PDF - Scribd
    Table 7-3—Typlcal values of motor impedances and kVA ratings to use when exact values are not known® Induction motor Thp = kVA Synchronous motor, 0.8 pf Tbp = L ...