Viking Link
Viking Link is a high-voltage direct current (HVDC) electricity interconnector that links the transmission grids of Great Britain and Denmark, enabling bidirectional power flows of up to 1,400 megawatts across a total distance of 765 kilometres.[1][2] The project, a 50/50 joint venture between National Grid plc of the United Kingdom and Energinet of Denmark, connects the Bicker Fen substation in Lincolnshire, England, to the Revsing substation in southern Jutland, Denmark, via submarine cable in the North Sea and onshore cables.[1][2] As the world's longest HVDC interconnector combining onshore and subsea elements, it facilitates the sharing of renewable energy resources, particularly allowing the United Kingdom to import surplus wind-generated electricity from Denmark during periods of high production.[1][3] Commercial operations began on 29 December 2023, following completion of construction in 2023, though the link operates at a reduced capacity of 800 megawatts until 2025 to accommodate limitations in the Danish grid infrastructure.[3][4][5] The £1.7 billion project supports grid stability and decarbonization efforts by balancing supply and demand across borders, with projections of significant carbon savings and consumer benefits through arbitraging price differences, despite initial archaeological disruptions during onshore works that uncovered an Anglo-Saxon cemetery.[1][3][6]Project Overview
Technical Specifications
Viking Link is a bipolar high-voltage direct current (HVDC) interconnector with a rated capacity of 1,400 MW at ±525 kV DC, enabling bidirectional electricity transmission between Great Britain and Denmark.[7][8] The system utilizes voltage source converter (VSC) technology in a modular multilevel converter (MMC) configuration, known as HVDC PLUS, provided by Siemens Energy for both converter stations.[9][10] The total route length measures 765 km, consisting of approximately 625 km of subsea cable across the North Sea and onshore underground cables of 66 km in the United Kingdom and 75 km in Denmark.[1][7] The subsea cables are mass-impregnated (MI) type, manufactured by Prysmian in two parallel circuits to support the bipolar configuration, while onshore cables were supplied by NKT.[10][7] Converter stations are situated at Bicker Fen substation in Lincolnshire, United Kingdom, connected to the 400 kV grid, and Revsing substation in southern Jutland, Denmark, also at 400 kV.[7] Although designed for full 1,400 MW operation, transmission is currently capped at 800 MW to accommodate Danish grid limitations until reinforcements are completed.[1][5]| Parameter | Specification |
|---|---|
| Rated Capacity | 1,400 MW (bipolar, 2 × 700 MW) |
| DC Voltage | ±525 kV |
| Total Length | 765 km |
| Subsea Length | 625 km (two parallel cables) |
| UK Onshore Length | 66 km |
| Denmark Onshore Length | 75 km |
| Converter Technology | VSC-MMC (HVDC PLUS) |
| Cable Type (Subsea) | Mass-Impregnated (MI) HVDC |