The Fehmarnbelt Fixed Link is an 18-kilometre immersed tube tunnel under construction beneath the , linking Rødbyhavn on Denmark's Lolland island to Puttgarden on 's island. It incorporates a four-lane motorway and double-track electrified railway within 79 standard and 10 special elements, each approximately 217 metres long, forming the world's longest such tunnel upon completion. Designed to slash crossing times to 10 minutes for vehicles and 7 minutes for trains—compared to the current ferry's hour-long journey—the project aims to alleviate a key bottleneck in Europe's transport network, promoting efficient freight movement via electric rail and integrating with corridors like the Scan-Med route. Construction, Denmark's largest infrastructure endeavor with costs exceeding €7 billion, commenced in 2020 on the Danish side and 2021 in , involving of a 15 million (now complete) and ongoing portal works, though immersion of elements faces delays of up to 18 months due to challenges with specialized vessels and related equipment. Despite these setbacks, the link promises substantial economic gains by enhancing connectivity between and , with tunnel elements now entering final outfitting in the Rødbyhavn factory.

Overview

Project Description

The Fehmarn Belt fixed link is an tunnel measuring 18 kilometres in length, linking Rødbyhavn on the Danish of Lolland with Puttgarden on the German of Fehmarn across the strait. It incorporates a four-lane motorway and an electrified within a rectangular cross-section structure positioned approximately 40 metres below the seabed. The tunnel comprises 79 prefabricated elements, each 217 metres long and weighing around 73,000 tonnes, which are manufactured in a at Rødbyhavn, floated out, and immersed into a pre-dredged on the before being joined and sealed. This method leverages Danish expertise from projects like the Øresund Tunnel, utilizing standard immersed tunnel technology adapted for the conditions. Developed and owned by the Danish state-owned Femern A/S, the project represents Denmark's largest initiative, with commencing in 2020 on the Danish side and 2021 on the German side, targeting operational readiness in 2029. Upon completion, it will become the world's longest combined road-and-rail immersed , designed to handle high-volume freight and while incorporating features for self-rescue and accident prevention.

Strategic Purpose and Regional Integration

The Fehmarn Belt fixed link serves as a strategic project to replace the existing service with a permanent, weather-independent connection between Rødbyhavn in and Puttgarden in , reducing rail travel time from over an hour (including wait and crossing) to 7 minutes and travel to 10 minutes. This enhancement addresses capacity limitations in current cross-Baltic routes, enabling up to 70 freight and 38 passenger trains daily alongside four lanes, thereby streamlining freight logistics from to and mitigating delays that currently affect approximately 2 million annual vehicle crossings via . The project's design prioritizes multimodal integration, combining electrified double-track rail with capacity to support both passenger mobility and heavy goods transport, aligning with broader goals of decarbonizing long-haul routes by shifting volume from to rail. In terms of , the fixed link forms a critical segment of the European Union's (TEN-T) core network, specifically the Scandinavian-Mediterranean corridor, which extends from the region through to the Mediterranean. By closing a key gap in this corridor, it facilitates seamless connectivity between northern ports like and , cutting overall journey times from to by hours and integrating peripheral Danish islands (Lolland and Falster) more effectively into European supply chains. The has allocated approximately €1.288 billion from the Connecting Europe Facility for the rail components, emphasizing its role in enhancing network cohesion, reducing congestion on alternative routes (such as via or ), and promoting economic convergence between , , and adjacent Scandinavian states. The initiative also aims to catalyze cross-border economic synergies, with analyses projecting increased trade flows, job creation in and , and strengthened regional competitiveness through dynamic effects like improved labor and investment attraction. For instance, Danish surveys indicate that 60% of respondents anticipate net economic gains for , while German assessments highlight potential for cultural exchange via easier accessibility. These outcomes depend on complementary investments in access infrastructure, such as rail upgrades in and , to fully realize the link's integrative potential without exacerbating local bottlenecks.

Historical Background

Initial Bridge Proposals

Proposals for a fixed crossing of the between and date to the , with early concepts favoring a bridge structure to accommodate road and rail traffic. These initial ideas aimed to shorten travel routes across the region, building on precedents like earlier services and needs. By the late 1990s, feasibility studies revived bridge plans, prompted by the Denmark-Sweden fixed link treaty, under which Sweden requested Denmark investigate a connection. The proposed bridge would feature a four-lane motorway and two electrified rail tracks, designed as a cable-stayed with pylons up to 272 meters high—upper levels for vehicles and lower for trains—to span the 18-kilometer efficiently. Danish and German governments initially designated this bridge option as preferred following technical and economic assessments. A 1999 feasibility study examined operational aspects, including potential wind-induced traffic restrictions on the bridge deck, forecasting measures to mitigate closures during high winds in the exposed location. These studies, conducted amid growing demands, positioned the bridge as the leading scheme for enhancing north-south freight and passenger links until environmental and navigational evaluations prompted further review in the early 2000s.

Transition to Immersed Tunnel

Initial proposals for a fixed crossing of the , dating back to the late following the success of Denmark's in 1998, predominantly envisioned a to connect the islands of Lolland and . These designs required spans exceeding 700 meters to accommodate deep shipping channels, surpassing any previously constructed bridge and introducing substantial engineering uncertainties. By the mid-2000s, feasibility studies evaluated multiple alternatives, including 16 bridge variants and 20 tunnel routes, alongside a bored tunnel option ultimately rejected for its higher estimated costs and larger environmental footprint on land. The immersed tunnel emerged as preferable due to lower technical risks, minimal disruption to maritime navigation by avoiding surface obstacles, and a reduced permanent environmental impact compared to elevated structures. The transition crystallized in February 2011 when the Danish parliament formally rejected bridge plans in favor of a 17.6-kilometer immersed , emphasizing its superior safety for shipping and routes as well as greener profile with less visual and ecological intrusion. This choice aligned with Denmark's prior experience in immersed tube construction, such as the Link's partial tunnel segment completed in 2000, enabling efficient prefabrication and immersion techniques suited to the Belt's seabed conditions. The 2008 treaty between and had committed to a fixed link but deferred specifics, allowing this evidence-based shift after 1.5 years of preliminary assessments.

Planning and Approvals

Preliminary studies for a fixed link across the commenced in the late 1990s, building on experience from the between and , with initial feasibility assessments focusing on bridge and tunnel options to enhance connectivity between and . These efforts culminated in a bilateral signed on 3 September 2008 by and , which outlined the project's framework, including the selection of an immersed tunnel as the preferred solution over a bridge due to navigational, environmental, and cost considerations; the entered into force on 14 January 2010. The project was integrated into the European Union's (TEN-T) as part of the Scandinavian-Mediterranean corridor, providing a basis for subsequent funding and strategic alignment, though national approvals remained the primary hurdles. In , the state-owned Femern A/S was established to manage planning, design, and financing, conducting environmental impact assessments and detailed engineering studies from the early onward. The Danish Parliament approved the Construction and Operation Act on 28 April 2015 with broad support, authorizing Femern A/S to proceed with the tunnel's development and operation, setting a of approximately 52.6 billion Danish kroner and enabling preparatory works. This legislative step followed extensive public consultations and technical evaluations, prioritizing the design for its minimal disruption to shipping routes compared to bridge alternatives. Germany's approval process proved more protracted, involving the rigorous Planfeststellungsverfahren regulatory procedure to integrate the tunnel with national infrastructure while addressing environmental and local concerns. Plan approval for the core tunnel structure was granted on 31 January 2019 after submission of detailed plans in December 2018, covering the immersed elements and immediate connections. Legal challenges delayed finalization until 3 November 2020, when the Federal Administrative Court dismissed all remaining appeals, clearing the path for construction; this process highlighted differences in administrative timelines between the two nations, with Germany's emphasis on comprehensive hinterland integration contributing to the extended duration. EU co-financing commitments, including €1.288 billion for rail components under the Connecting Europe Facility, supported the planning phase but did not supplant national sovereignty over approvals.

Engineering and Design

Tunnel Specifications

The Fehmarnbelt Tunnel comprises an 18-kilometer-long structure, making it the longest of its kind upon completion. It consists of 89 elements placed in a dredged approximately 40 meters below , with immersion precision maintained to within 15 millimeters. The elements are constructed from designed for a 120-year , incorporating waterproof bulkheads and pressure-sealed connections to ensure structural integrity. The tunnel features a rectangular cross-section varying slightly by element type, with standard elements measuring 217 meters in length, 42 meters in width, and approximately 9-10 meters in height, each weighing 73,500 tonnes. Special elements, numbering ten, accommodate service and technical functions; for instance, certain variants are 39 meters long, 47 meters wide, 13 meters high, and weigh 21,000 tonnes. Overall width reaches up to 45 meters in sections, housing five parallel tubes: two two-lane road tubes for a four-lane motorway, two single-track rail tubes for electrified double-track railway service, and one central technical tube for maintenance, ventilation, and emergency access.
Element TypeQuantityLength (m)Width (m)Height (m)Weight (tonnes)
Standard7921742~9-1073,500
Special10Varies (e.g., 39)Varies (e.g., 47)Varies (e.g., 13)Varies (e.g., 21,000)
Safety systems include transverse escape routes between tubes, integrated , camera surveillance, and communication infrastructure to facilitate self-rescue and minimize incident consequences. The design supports motorway speeds up to 130 km/h and speeds up to 200 km/h, enhancing connectivity without intermediate ventilation shafts due to the immersed configuration.

Construction Methods

The Fehmarnbelt fixed link utilizes an tunnel construction method, a proven technique involving of tunnel elements onshore, flotation to the crossing site, and controlled submersion into a pre-dredged trench spanning 18 kilometers. This approach enables efficient assembly under marine conditions while minimizing on-site risks compared to bored tunneling. Tunnel elements are fabricated in a purpose-built factory near Rødbyhavn, Denmark, equipped with six parallel casting lines for continuous production of precast concrete segments. Standard elements measure 217 meters long, 42 meters wide, and 9 meters high, each weighing about 73,000 metric tons; the project requires 79 such elements plus 10 specialized units for transitions and service areas. Segments are cast in 30-36 hours without interruptions to ensure structural integrity, involving 50-60 workers per cycle. Completed elements slide into an adjacent dry dock, which is flooded to enable flotation and towing to the immersion site via a dedicated work harbor. Prior to immersion, specialized dredging vessels excavate the trench to accommodate the elements and protective overburden, with excavated material repurposed for . Elements are then lowered into the trench using immersion pontoons equipped with ballast tanks for precise vertical control, achieving sub-millimeter alignment onto a prepared foundation via steel guide cables. A dedicated immersion vessel, arriving on-site in October 2024, supports this process by positioning and submerging the 73,000-tonne units sequentially from the Danish side. Following placement, elements are sealed at joints with watertight gaskets and temporary bulkheads, allowing internal fit-out for road, rail, and utility systems. The assembled is backfilled with layers of , , and stone for stability and scour protection, restoring seabed contours. portals employ segmented cut-and-cover construction: trenches are excavated, lined with walls fitting 20-meter segments, and roofed before backfilling, integrating seamlessly with land-based approach roads and rail.

Financing and Economic Viability

The Fehmarn Belt fixed link operates under a user-financed model, with toll revenues from road and rail traffic designated to repay construction loans raised by Femern A/S, the Danish state-owned project company. Femern A/S funds its activities primarily through on-lending from Danmarks Nationalbank and EU grants, supplemented by Danish public appropriations as outlined in the 2015 Construction Act, which set the overall financial framework at DKK 55.1 billion in 2015 prices (approximately €7.4 billion). The European Commission approved this public financing structure in 2015 and again in 2020 under EU state aid rules, determining that it complies with market economy operator principles and that the project's positive socio-economic effects for the EU justify the aid element. The contributes directly via the Europe (CEF), granting €540 million in June 2022 for tunnel construction and related , while an additional €49 million supports the connection on the Fehmarn side. Germany finances its landside connections separately, including motorway and links, with federal and Länder budgets covering costs estimated at around €800 million for road integration, though exact allocations remain subject to ongoing planning. No private equity or direct user pre-payments fund the core project; instead, post-opening tolls—projected at €335 per heavy goods vehicle and lower for cars and freight—are structured to achieve financial self-sufficiency over a 30-40 year concession period, with reserves for contingencies. Economic viability assessments, primarily from Danish Transport Ministry-commissioned analyses, project a positive driven by time savings, reduced emissions, and increased trade flows between and . A 2015 updated cost-benefit analysis estimated a 5.0% economic over 50 years for European users, factoring in broader regional productivity gains and modal shifts from ferries to . The financial supports a 32-year , including 13.6% reserves for cost overruns and traffic shortfalls, based on forecasted annual volumes of 6-10 million vehicles and equivalent traffic. These projections assume conservative traffic growth post-2030 opening, with socio-economic benefits accruing as a €3.5 billion net profit in time and operational efficiencies for businesses. Critics, including analyses commissioned by competing ferry operators, contend that official forecasts overestimate traffic diversion from existing routes and underestimate construction risks, potentially rendering the project financially unviable without sustained subsidies. Independent economic modeling, such as from the , highlights sensitivity to assumptions on modal competition and highlights that duopoly dynamics with ferries could erode toll revenues, questioning the robustness of profitability claims. Despite these concerns, approvals and Danish parliamentary ratification in affirm the project's viability under baseline scenarios, emphasizing long-term integration benefits over short-term fiscal risks.

Construction and Progress

Preparatory and Dredging Works

Preparatory works for the Fehmarn Belt fixed link commenced in 2020 on the Danish side, focusing on site clearance, establishment of construction facilities, and initial portal preparations at Rødbyhavn and Puttgarden. The Femern Link Contractors consortium (FBC), comprising Boskalis, Hochtief, BAM, and other partners, handled preparatory activities for the tunnel portals on both Danish and German sides, including groundwork for access ramps, ventilation buildings, and service facilities. These efforts involved land acquisition, environmental mitigation measures, and installation of temporary infrastructure to support subsequent phases. Dredging operations for the 18-kilometer trench began in 2021, executed primarily by under a dedicated separate from the main . The required excavating approximately 15 million cubic meters of material to create a up to 17 meters deep, 75 meters wide at the base, and 120 meters wide at the top, accommodating the immersed elements and protective layers. Up to 60 vessels, including cutter suction dredgers, trailing suction hopper dredgers, and support equipment, were mobilized simultaneously to handle the multifaceted across Danish and German waters, ensuring compliance with cross-border environmental standards. Dredged sediments, consisting of sand, gravel, and clay, were repurposed for , creating new coastal areas on Lolland and Fehmarn islands to offset habitat disruption. The reached completion on April 16, 2024, marking a key ahead of gravel bedding and element immersion. Approximately 2 million tonnes of Norwegian were additionally imported and placed to form protective coastlines and backfill zones during reclamation efforts integrated with . This phase emphasized sustainable practices, such as precise to minimize ecological impact, with monitoring confirming adherence to permit conditions for and protection. Post- surveys verified the geometry, preparing the for the next stages.

Element Fabrication and Immersion

The Fehmarnbelt tunnel consists of 89 precast elements, including 79 standard units each measuring 217 meters in length, 42 meters in width, and 9 meters in height, with a weight of 73,000 tonnes, alongside 10 special elements for entrance and exit ramps. Fabrication occurs in a purpose-built tunnel element factory at Rødbyhavn, Denmark, equipped with six production lines for casting the standard elements. The process involves pouring concrete into large formwork systems, followed by curing, internal fitting of rails, roads, and services, and testing for watertightness before elements are slid into adjacent flooded basins for flotation. Casting of the first element was completed on May 6, 2024, with initial production activities announced as underway in July 2023; full-scale output is projected to continue through 2027 to meet the element requirements. In early 2025, milestones included the successful transfer of the initial standard elements into production basins and their flotation for testing, with the first two units departing the dry dock in February. Immersion entails towing floated elements via barge to the 18-kilometer dredged trench across the Fehmarn Belt, where the specialized vessel Ivy—a custom-designed immersion pontoon—lowers them vertically into position using ballast tanks and winches for sub-millimeter alignment. The Ivy reached the site in September 2024, but extensive delays in vessel commissioning, testing, and regulatory approval have postponed immersions. As of September 2025, no elements had been immersed, resulting in a confirmed 18-month setback to the project schedule, primarily attributed to these vessel issues alongside ancillary factors like trench preparation and noise mitigation. Once placed, adjacent elements are sealed with hydrophilic gaskets, aligned via hydraulic jacks, and connected through in-situ concrete pouring in the end bulkheads to form a continuous, watertight structure.

Delays and Current Status

The Fehmarnbelt Fixed Link project has experienced significant delays, primarily due to challenges with the specialized immersion IVY, essential for submerging the 79 tunnel elements into the . Announced on September 17, 2025, these issues, including incomplete testing and regulatory approval of the vessel, have placed the original 2029 completion target under considerable pressure. A confirmed delay of approximately 18 months stems from the vessel's unreadiness and related complications in preparation. As of October 2025, no elements have been immersed, despite ongoing fabrication at the Rødbyhavn , where the first two elements were completed and relocated to the adjacent on February 6, 2025. Preparatory works continue, with the Danish portal approaching completion as of September 5, 2025, including final soil covering on Lolland. German land connections face independent delays, particularly in railway hinterland links overseen by Deutsche Bahn, which will not align with the 2029 tunnel opening. These rail extensions are projected to lag by at least three years, potentially postponing full operational service until 2032 or later. Overall, while marine and portal construction advances incrementally, integration risks from these synchronized delays threaten the project's economic and logistical benefits.

Complementary Infrastructure

Danish Land Connections

The Danish land connections for the Fehmarnbelt Fixed Link primarily involve upgrades to the railway infrastructure leading to the tunnel portal at Rødbyhavn on the island of Lolland, ensuring seamless integration with the national transport network. These enhancements are designed to accommodate increased passenger and freight traffic post-tunnel opening in 2029, reducing journey times from to from approximately five hours to 2.5 hours. The core component is the 115-kilometer Ringsted-Rødby railway line, managed by Banedanmark, which spans from on , across bridges to Falster and Lolland, to Rødbyhavn. Upgrades include full of the previously non-electrified sections, construction of double tracks along the entire route, and curve straightening to enable speeds of up to 200 km/h, up from prior limits of 120-160 km/h. These modifications also support freight operations, allowing heavier loads and higher frequencies without detours via western . Construction of this line, initiated in coordination with works, was reported on schedule as of September 2025. Road connections at Rødbyhavn link the tunnel's four-lane motorway directly to local roads and the broader Danish network, including Route 9 and eventual ties to the E47 European route via existing bridges from Lolland to the mainland. While less extensive than rail upgrades, these include new access ramps and portal infrastructure to handle projected traffic volumes of up to 11,000 vehicles daily, replacing operations. Preparatory at the site has created additional space for these integrations, minimizing disruptions during construction. These landside improvements, funded separately from the core tunnel by Danish state entities, form part of the Scandinavia-Mediterranean TEN-T corridor, prioritizing rail for sustainability while enhancing overall connectivity.

German Land Connections

The German land connections for the Fehmarn Belt fixed link integrate the Puttgarden tunnel portal with upgraded road and rail infrastructure in Schleswig-Holstein, facilitating access to the national networks. The road approach utilizes Bundesstraße 207 (B207), which links the portal to the Autobahn 1 (A1) near Heiligenhafen, approximately 40 kilometers southwest. This route is being expanded from a two-lane road to a four-lane motorway standard, with a length of about 30 kilometers, to accommodate projected traffic volumes of up to 6,000 vehicles per hour in peak periods once the tunnel opens. Regulatory approval for the B207 expansion was issued by authorities on September 26, 2019, following environmental assessments and public consultations. Construction preparations, including earthworks and preliminary alignments, became visible in the regional landscape by early 2025, though full completion is targeted to align with the tunnel's scheduled opening in late 2029. The upgrade aims to reduce bottlenecks on the current single-carriageway B207, which previously handled ferry traffic, and ensure seamless integration with the A1 corridor connecting to (about 100 kilometers south) and further to . Rail connectivity relies on the Lübeck–Puttgarden line, a 76-kilometer route that will interface directly with the tunnel's bi-level rail tracks at Puttgarden. is doubling the single-track sections, electrifying the line at 15 kV 16.7 Hz, and modernizing signaling to support freight and passenger services at speeds up to 200 km/h for trains. The hinterland connection sub-project includes track doubling over key segments and integration with the existing Lübeck station, enhancing links to Hamburg's main hub. Portions north of Neustadt in Holstein have been closed since 2023 for fixed-link-related works, with the full upgrades projected for completion post-2029 due to permitting and funding timelines. These enhancements, part of the broader coast-to-coast infrastructure under the EU's TEN-T network, received state aid approval from the in March 2020, with committing federal funds alongside regional contributions. Delays in rail permitting have raised concerns among stakeholders like the STRING cooperation forum, which advocates for accelerated timelines to avoid post-tunnel capacity constraints.

Economic Analysis

Projected Benefits and Trade Impacts

The Fehmarnbelt Fixed Link is projected to reduce travel times by approximately one hour for road vehicles and 2.5 hours for rail freight relative to existing crossings, enabling 24-hour operations without weather disruptions. These reductions stem from the tunnel's 18-kilometer immersed-tube , which eliminates ferry loading/unloading delays and seasonal variability, with transit times of 10 minutes by car and 7 minutes by train. Lower transport costs from these efficiencies are anticipated to stimulate cross-border , especially for time-sensitive such as perishables and just-in-time manufacturing components, by decreasing holding needs and improving reliability. In transport chains spanning 24 to 48 hours, the 2.5-hour savings equate to a 5-10% overall time reduction, enhancing 's competitiveness against longer or routes. Projections indicate potential doubling of freight volumes across the link, driven by redirected flows from ferries to fixed infrastructure. The link's integration into the European rail network is expected to expand for Nordic exporters to and , fostering regional economic cohesion in the STRING corridor (Scandinavia-). Analysis of Swedish trade flows suggests measurable increases in exports to post-opening, as reduced barriers lower effective distances and encourage specialization in high-value sectors like machinery and pharmaceuticals. Surveys among Danish stakeholders reflect broad agreement, with two-thirds anticipating heightened Scandinavia- trade due to streamlined . By providing a direct, high-capacity corridor, the project is forecasted to accelerate intra-EU trade dynamics, potentially shifting modal shares toward for sustainability-aligned freight while amplifying bilateral Denmark-Germany exchanges, which already exceed €100 billion annually. These benefits hinge on complementary land connections, with full realization projected after completion, though actual outcomes depend on global demand and infrastructure synchronization.

Cost-Benefit Evaluations

A socio-economic cost-benefit analysis conducted in 2015 for the Danish Ministry of Transport estimated the Fehmarn Belt fixed link would yield a of DKK 28 billion for and DKK 26 billion across all affected countries over a 50-year period, based on a of 4% for the first 35 years and 3% thereafter. The analysis projected an of 5.4% for and 5.0% overall, driven primarily by time savings—approximately 65 minutes per car trip and a reduction in Copenhagen-to-Hamburg travel to 2.5 hours—as well as increased freight efficiency and modal shifts from road to . Assumptions included project completion in 2022 and cessation of operations upon opening, with sensitivity tests indicating viability under variations in growth and costs up to 20% overruns. From the German perspective, a separate reported a benefit-cost ratio of 6.7, emphasizing broader European connectivity gains and justifying the project's value despite its scale. The endorsed this in approving state aid under the Important Project of Common European Interest framework, citing a positive socio-economic return for the EU as a whole, supported by an EUR 1.3 billion grant from the Connecting Europe Facility. Femern A/S, the project company, has maintained that the user-financed model—relying on toll revenues to repay DKK 55.1 billion in total costs (2015 prices, including DKK 7.3 billion in reserves audited by )—remains robust, with a 2020 confirming repayment feasibility through traffic volumes. Independent reviews have questioned these projections' optimism. A 2015 statement by DIW Econ, commissioned by ferry operator , identified methodological flaws in traffic demand modeling and inadequate sensitivity to downside risks, concluding the net benefits were marginally positive at best under realistic scenarios. A 2017 assessment using simulations found payback periods exceeding 50 years in over 85% of cases under base assumptions, attributing high uncertainty to overestimated traffic growth, potential cost escalations beyond reserves, and dependency on EU subsidies, potentially necessitating taxpayer support if toll revenues fall short. Such critiques align with patterns in Danish mega-transport projects, where historical data show systematic underestimation of costs by 20-50% and overestimation of demand, though project-specific delays to a 2029 opening have not prompted a full update as of 2025.
EvaluationKey MetricScopeSource
Danish CBA (2015)IRR 5.4%; NPV DKK 28 billionDenmark, 50 yearsMinistry of Transport
Overall CBA (2015)IRR 5.0%; NPV DKK 26 billionAll countries, 50 yearsMinistry of Transport
German EvaluationBCR 6.7Germany/EUBMV
Risk Assessment (2017)Payback >50 years (87.7% probability)Financial viabilitySCIRP Journal

Long-Term Regional Development

The Fehmarn Belt fixed link is projected to foster long-term economic integration between southern Denmark and northern Germany by reducing travel times, thereby enhancing cross-border trade, labor mobility, and regional attractiveness. Studies anticipate annual trade increases of approximately €940 million across the STRING megaregion (encompassing Zealand, Scania, Hamburg, and Mecklenburg-Vorpommern), driven by shorter routes for freight and passengers between Scandinavia and Central Europe. This connectivity is expected to mirror effects observed after the Øresund Bridge opening in 2000, where integrated labor markets and innovation hubs emerged, though realization depends on complementary infrastructure and policy measures to exploit opportunities. In peripheral Danish regions like Lolland-Falster (part of Storstrøms Amt), the link addresses chronic depopulation and economic stagnation, with construction activities already slowing population decline in areas such as as of 2024. Projections from earlier analyses foresaw up to 6,000 additional jobs by around 2011 through export growth and , though updated assessments emphasize sustained employment from the permanent element factory in Rødbyhavn, securing roles in and beyond project completion. could see a 20% job increase (around 650 positions) due to improved accessibility for visitors, while cross-border may rise, with models predicting 11,600 German workers entering annually post-opening. On the German side, regions including (Kreis Ostholstein) and stand to gain from hubs and , with net employment gains of about 325 jobs despite ferry-related losses. Property values are forecasted to rise by €3 billion in total (2009 prices), split roughly evenly between sides, reflecting enhanced residential and commercial appeal from reduced Hamburg-Copenhagen travel times (from 4.5 to 3 hours by train). Broader effects include over 1,400 additional cross-border commuters and expanded labor pools, potentially boosting business relocation to lower-cost areas while strengthening knowledge-based sectors like and renewables.
RegionProjected GDP/Trade ImpactEmployment ProjectionPopulation/Labor Effect
Lolland-Falster (Denmark)Catalyst for 0.15% GDP growth; export boosts+6,000 jobs (historical model); factory permanenceSlowed decline; + commuting
Ostholstein/Fehmarn (Germany)Tourism/logistics gainsNet +325 jobs post-ferry lossesIncreased in-commuting attractiveness
STRING Megaregion€940M annual tradeEnhanced via labor access+3,400 commuters total
These projections, derived from consultancies like and regional councils, assume full utilization of the link's 120-year but note risks from unaddressed structural weaknesses, such as low rates in SMEs (over 80% with fewer than 20 employees in similar areas). Empirical parallels from the and links suggest causal benefits in trade volumes but highlight the need for proactive business development to counter peripheral challenges like aging populations and below-average productivity (e.g., 15% lower in Ostholstein).

Environmental and Ecological Aspects

Assessed Impacts on Marine Environment

The for the Fehmarn Belt fixed link, finalized in reports approved by Danish and German authorities between 2013 and 2015, identifies the construction phase as the primary period of marine disturbance, driven by approximately 19 million cubic meters of to form an 18 km trench for the immersed . This process generates suspended plumes, increasing and causing temporary smothering of benthic communities, including infaunal organisms in the soft sediments characteristic of the . Recovery of affected habitats is projected within months to years post-, informed by the area's natural hydrodynamic regime that promotes redistribution. Underwater noise from operations, involving continuous low-frequency sources, is assessed to induce behavioral avoidance in marine mammals such as harbour porpoises (Phocoena phocoena), with baseline surveys from 2008–2010 indicating seasonal presence in the Belt. The EIA concludes that porpoises exhibit lower sensitivity to such prolonged noise compared to impulsive blasts, predicting no permanent displacement or population-level effects, though short-term reductions in acoustic detections near worksites are anticipated. Harbour seals and grey seals face similar transient disturbances but benefit from nearby haul-out sites outside the primary impact zone. Fish assemblages, including migratory species like (Gadus morhua) and (Clupea harengus), are expected to experience localized disruption and reduced prey availability during peaks, potentially affecting juvenile in nursery grounds. However, assessments based on habitat suitability models determine that these changes do not alter overall community structure or abundance long-term, given the Belt's connectivity to broader Baltic populations. Planktonic and water column biota may encounter minor chemical releases from sediments, assessed as low-risk due to limited contamination levels in Fehmarn Belt deposits, with no exceedance of environmental quality standards predicted. Individual-based modeling applied in the EIA further supports negligible population impacts on foraging marine birds like common eiders (Somateria mollissima), even under conservative scenarios of habitat loss. Operational impacts are deemed minimal, as the tunnel lies fully buried beneath the , avoiding alterations to surface currents or serving as a migration barrier, in contrast to bridge alternatives evaluated. A comprehensive regime, initiated with project approvals and utilizing acoustic, visual, and hydrodynamic sensors, verifies these predictions in real-time, with data transparently reported to authorities via platforms like the Ægir portal. Sedimentation spill is controlled to permitted thresholds, with coastal measurements confirming localized deposition without broader shifts.

Mitigation Strategies and Monitoring

The Fehmarnbelt fixed link incorporates mitigation strategies primarily aimed at minimizing temporary disturbances to the marine environment during construction, such as for the 18 km immersed tunnel trench. noise from and vessel operations is managed through a combination of predictive modeling, acoustic measurements, and adherence to regulatory thresholds designed to protect marine mammals, including harbour porpoises (Phocoena phocoena), which are sensitive to anthropogenic sound levels exceeding specified limits. These measures include source-level assessments of equipment like dredgers and weekly compliance reporting to ensure noise immissions do not surpass permitted values, as validated by near modeling during operations. Sediment dispersion from trench excavation is addressed via hydrodynamic modeling to predict and limit plume spread, alongside on-site sedimentation measurements along the coastline to evaluate impacts on benthic and habitats. emissions from sites are controlled to reduce risks of collisions with nocturnal migratory songbirds, employing targeted protocols during peak periods. No permanent marine habitat compensation is required, as assessments indicate no significant long-term loss of protected habitats or under the tunnel alternative, with impacts confined to reversible disturbances in the . Monitoring is conducted through an adaptive marine environmental programme that verifies predicted impacts and adjusts measures in response to data, involving Danish and German authorities. This includes continuous hydrographic surveys of water quality parameters like currents, turbidity, oxygen, and temperature via buoy networks, acoustic monitoring for mammals, aerial photography for birds, and ecosystem assessments for flora and fauna. The ÆGIR portal serves as a centralized repository for these datasets, providing live updates and reports to stakeholders for operational planning and , encompassing data, , and surveys. Environmental construction monitoring, led by specialized firms, documents noise and light effects with instrumentation for real-time validation against thresholds.

Scientific Debates on Net Effects

Environmental impact assessments for the Fehmarnbelt Fixed Link conclude that construction-phase disturbances, primarily from approximately 20 million cubic meters of seabed material, will cause temporary and increases affecting benthic organisms and light-dependent species in the . Recovery of affected habitats is projected within 5-10 years following completion, based on modeling of dispersion and historical data from similar projects. A focal point of debate centers on harbor porpoises (Phocoena phocoena), the only year-round resident cetacean in the , where the population numbers fewer than 500 individuals and is classified as . Construction noise from pile driving and dredging, potentially exceeding 160 dB re 1 μPa, risks auditory injury, behavioral displacement, and masking of echolocation, with studies indicating porpoises in the area already experience high ambient shipping noise levels of 109-132 dB. Mitigation strategies, including soft-start ramp-ups and acoustic deterrents, are mandated, and assessments deem porpoises less sensitive to continuous noise sources, predicting no permanent population-level decline. However, conservation analyses argue these measures insufficiently address cumulative stressors in this bottleneck habitat, potentially exacerbating decline given slow reproductive rates and limited . Operationally, the tunnel is expected to yield net ecological gains by eliminating ferry traffic, which currently contributes to chronic and collision risks, while reducing overall transport emissions by shifting modes to and shortening routes—estimated at 140,000 tons of CO2 savings annually. The immersed minimizes permanent alteration compared to a alternative, avoiding ongoing shading and bird collision hazards. Critics counter that construction-phase habitat fragmentation could irreversibly disrupt migratory pathways for and , with sediment spill posing risks to downstream food webs already strained by and pressures. Empirical analogies from the Fixed Link suggest post-construction benthic community resilience and even enhanced diversity in stabilized areas, supporting proponents' view of transient net costs against enduring connectivity benefits. Independent evaluations, such as those by the Helmholtz Centre for Ocean Research (GEOMAR), highlight the Baltic's overall , questioning whether localized mitigations adequately offset regional degradation in a exhibiting persistent oxygen deficits and . Official transboundary assessments affirm compliance with EU standards, with monitoring programs to verify recovery, yet ongoing delays—such as 18 months in 2025 due to noise compliance issues—underscore unresolved tensions between engineering imperatives and ecological safeguards. The net effect remains contested, with project-aligned studies emphasizing reversible impacts and transport decarbonization, while ecological advocates prioritize precaution for amid incomplete baseline data on residency.

Controversies and Stakeholder Views

Environmental Opposition Claims

Environmental organizations, particularly the German Nature and Biodiversity Conservation Union (), have claimed that the Fehmarn Belt fixed link will cause significant damage to biodiversity in the EU-protected Fehmarn Belt area, including threats to such as harbour porpoises and larvae. NABU has specifically argued that underwater noise from construction activities, including of approximately 14.5 million cubic meters of marine sediments for the tunnel trench, will harm sensitive species in the , a region already under ecological stress. Opponents further assert that dredging operations will lead to water clouding and , degrading and long-term marine habitats while exacerbating the Sea's precarious ecological condition. Local resistance groups, including the Action Alliance against a Fehmarnbelt Fixed Link, have highlighted risks to coastal ecosystems and from and extraction, claiming these activities overlook cumulative impacts on the socio-ecological fabric of the region. Additional claims focus on climate-related effects, with critics arguing that emissions from and production for the tunnel undermine assertions, contributing to a substantial without adequate offsetting. NABU's head, Malte Siegert, has contended that the inclusion of four lanes for cars and trucks conflicts with European green ambitions, prioritizing road traffic over ecological preservation in an area vital for larval habitats and populations. These groups pursued legal challenges, such as NABU's 2020 federal court case in alleging insufficient environmental assessment, though the claims were ultimately dismissed.

Local and Financial Criticisms

Local communities on both sides of the , particularly in Germany's and Denmark's Lolland region, have raised concerns over construction-related disruptions to daily life, including noise, , and landscape alterations from and land works. Fishermen and farmers in coastal areas fear permanent loss of access to traditional grounds and agricultural lands due to degradation and restricted navigation during and after tunnel immersion. Small tourism operators dependent on unspoiled rural and environments anticipate declines in numbers, as the prioritizes high-volume freight and over nature-based recreation, potentially eroding local cultural ties to the coastline. Opposition has coalesced into groups like the German "Action Alliance against a Fehmarnbelt Fixed Link," involving residents, trade unions, and conservationists, who criticize inadequate public consultation processes, such as the ineffective dialog forums organized by project operator Femern A/S. These stakeholders argue that decision-making favors urban centers like Hamburg and Copenhagen, imposing environmental and infrastructural burdens on peripheral rural communities without commensurate local benefits. Protests, including rallies outside approval hearings, highlight perceived dismissal of grassroots input in favor of supranational economic priorities. Financially, the project faces scrutiny for escalating costs and uncertain returns, with initial estimates of €5 billion in 2009 rising to €7.4 billion by 2023, driven by delays, issues, and additional land works. A 2015 independent analysis projected a of approximately 50 years—ten years longer than developer forecasts—citing insufficient toll revenues from cars (€65) and trucks (€267) to cover operations without subsidies. Danish taxpayers bear the majority burden, as the government guarantees loans and funds most construction, with tolls projected inadequate for full recovery amid competition from ferries. Critics, including transport economists, highlight inadequate external of the , labeling it a high-risk venture prone to overruns similar to prior Danish megaprojects, with 22-30% contingency reserves already strained. Delays pushing completion from 2025 to at least 2029 exacerbate financing pressures, as standby fees to contractors accrue without progress, potentially requiring further public funds despite EU contributions of €1.3 billion. Germany's €800 million commitment for motorway connections underscores asymmetric funding, with Denmark subsidizing cross-border benefits disproportionately.

Pro-Project Arguments and Empirical Support

Proponents argue that the Fehmarn Belt fixed link will substantially reduce travel times across the strait, enhancing connectivity between and . Road travel duration will decrease from about 45 minutes by to 10 minutes via the tunnel, while rail journeys will shorten from 45 minutes to 7 minutes, based on operational projections from the project's design specifications. This time savings is expected to lower costs for , which currently handles over 10 million tons annually via ferries, by providing a weather-independent alternative that avoids delays from adverse conditions. Economic analyses support these claims through cost-benefit evaluations demonstrating positive returns. A 2015 analysis commissioned by the Danish Ministry of Transport calculated a 5.0% for Europe over 50 years, factoring in direct user benefits like time savings valued at empirical rates from stated choice experiments, alongside indirect effects such as increased trade volumes. Complementary studies by Copenhagen Economics and Prognos AG highlight dynamic economy-wide benefits, including agglomeration effects and strategic trade enhancements, drawing parallels to observed traffic growth post-Øresund Bridge opening, where cross-border flows exceeded initial forecasts by integrating regional markets. The project is projected to stimulate regional development by boosting freight capacity to 25 million tons per year initially, facilitating smoother integration of exports into European supply chains. Ramboll's assessment for the STRING region estimates amplified trade impacts for countries compared to German counterparts, with potential GDP uplifts from enhanced labor mobility and business clustering. phase , involving over 3,000 workers at peak, provides immediate empirical economic injection, as evidenced by ongoing site activities since 2021. These arguments are grounded in models validated against historical fixed-link outcomes, underscoring net societal gains despite upfront costs.

References

  1. [1]
    Femern
    The Fehmarnbelt Fixed Link is part of a greener traffic corridor in Europe and will boost the transport of freight by electric trains. News. October 23 2025 ...Fehmarnbelt tunnel · Construction phases · The tunnel · The construction
  2. [2]
    Fehmarnbelt tunnel - Femern
    The Fehmarnbelt link will cut travel time between Denmark and Germany and will be part of Europe's sustainable transport network of the future.A safe link · Project status · Building the tunnel · Read more
  3. [3]
    Project status - Femern
    View of the southern coast of Lolland on the Fehmarnbelt. The tunnel construction site is. Project status. Autumn 2025.
  4. [4]
    Fehmarnbelt delayed 18 months due to issues with submersion ...
    Sep 18, 2025 · A delay of around 18 months to the completion of the Fehmarnbelt Tunnel between Denmark and Germany has been confirmed following issues with ...
  5. [5]
    News - Femern
    The first two completed elements for the Fehmarnbelt tunnel have now been moved out into the basin in front of the tunnel factory at Rødbyhavn.
  6. [6]
    Fehmarnbelt: World's longest immersed tunnel - Ramboll
    The Fehmarnbelt tunnel is an 18-kilometre long immersed tunnel located 40 meters beneath the Baltic Sea connecting the Danish island of Lolland with the ...Missing: timeline | Show results with:timeline
  7. [7]
    Fehmarnbelt Fixed Link - BMV
    The approval documents for the Fehmarnsund tunnel submitted to the Federal Railway Authority early July 2025 include a timeline for the construction work and ...
  8. [8]
    Fehmarnbelt Fixed Link: building the world's longest immersed tunnel
    An 18 km tunnel for road and rail traffic 40 metres below the surface of the Baltic Sea. It will be the longest immersed tunnel in the world.
  9. [9]
    How we're building the Fehmarnbelt tunnel - Femern
    A small work harbour and a concrete batching plant will be built at Puttgarden. They will be used for the construction of the tunnel portal.
  10. [10]
    Fehmarnbelt Fixed Link - Arup
    18km-long Fehmarnbelt Fixed Link, a strategic underwater transport link between Scandinavia and continental Europe. Connecting Denmark and Germany.
  11. [11]
    Benefits of the link
    The fixed link across the Fehmarnbelt will reduce travel time between Scandinavia and Continental Europe. Today it takes 45 minutes by ferry (plus waiting ...
  12. [12]
    The Fehmarnbelt tunnel: delivering a new European link
    Jun 11, 2018 · The Fehmarnbelt link is part of the European TEN-T network, a portfolio of hundreds of projects that aim to boost the cohesion, interconnection ...
  13. [13]
    Scandinavian-Mediterranean Core Network Corridor
    The most important projects in this corridor are the fixed Fehmarnbelt crossing and Brenner base tunnel, including their access routes. It extends, across the ...
  14. [14]
    Fehmarnbelt Tunnel: Great expectations for economic growth and ...
    As many as 60 percent of the surveyed Danes believed that the Fixed Link will benefit the Danish economy, with 50 percent and 51 percent also believing that it ...Missing: connectivity | Show results with:connectivity
  15. [15]
    [PDF] FIXED FEHMARNBELT LINK
    The fixed Fehmarnbelt link will not only promote the economic but also the cultural integration of both regions. The easier and faster accessibility will ...
  16. [16]
    [PDF] Regional Effects of a Fixed Fehmarn Belt Link - IHK
    The analysis of the dynamic and strategic effects of a fixed link across Fehmarn Belt ... However, it is very important to integrate the possibilities of a ...
  17. [17]
    Tunnel Trumps Bridge: Denmark to Build Underwater Link to Germany
    Feb 2, 2011 · Plans for a link across the Fehmarn Belt strait between Denmark and Germany go all the way back to the 1920s, so the idea is hardly new. For ...
  18. [18]
    History - Femern
    In Germany, permission for the construction of a fixed link across the Fehmarnbelt was granted on the basis of a regulatory approval procedure known as ...Missing: crossing bridge 1920s 1960s
  19. [19]
    [PDF] FEHMARNBELT: - IADC Dredging
    Three options initially proposed for the link. (see Figure 5) include: • a cable-stayed bridge,. • a bored tunnel and. • an immersed tunnel. The immersed ...
  20. [20]
  21. [21]
    Innovations for the Fehmarnbelt tunnel option - TunnelTalk.com
    In order to achieve this within the given time frame of about 2.5 years for the construction of the elements, a number of production facilities are needed.The ...Missing: specifications timeline
  22. [22]
    [PDF] Traffic restrictions due to wind on the Fehmarn Belt bridge
    Jun 21, 2005 · In the Fehmarn Belt feasibility study, reported in 1999, it was foreseen that it could be necessary to introduce measures for reducing the ...
  23. [23]
    The Insane Scale of Europe's New Mega-Tunnel - The B1M
    Nov 23, 2022 · The expected economic benefits are huge but it still all costs a lot of money. The budget for the project currently stands at USD $7.5BN. Half a ...
  24. [24]
    Construction of a Tunnel instead of a Bridge at Fehmarn Belt
    Fehmarn A/S has proposed a 17.6 km long immersed tunnel to cross the Fehmarn Belt between the Baltic Sea islands of Fehmarn and Lollar instead of a cable- ...Missing: timeline | Show results with:timeline
  25. [25]
    [PDF] Meet the Challenges of the Fehmarnbelt Fixed Link - ResearchGate
    than an immersed tunnel, was rejected because its estimated cost was higher [5]. At a later stage, significant weaknesses in the safety concept of the.<|separator|>
  26. [26]
    [PDF] The Fehmarnbelt Tunnel: Regional Development Perspectives 3
    The third fixed link, the Fehmarnbelt Link forms a giant step in the creation of a new. North-European corridor. The first stage of the Northern European.
  27. [27]
    Fehmarn link: Denmark opts for sea tunnel to Germany - BBC News
    Feb 2, 2011 · The Danish parliament rejected plans for a bridge across the Fehmarn Strait in favour of the tunnel, deciding it would be safer and greener.
  28. [28]
    Fehmarnbelt tunnel - TEC Tunnel
    The concrete tunnel will be constructed in 89 massive tunnel elements sunk into position 40 m below sea level - with a 15 mm precision. 79 of the elements will ...
  29. [29]
    Building the tunnel - Femern
    The portal is the entrance to the tunnel · A standard-element is 217 meters long and weighs 73,500 tonnes · Casting the tunnel elements · See how an immersed ...Missing: specifications | Show results with:specifications
  30. [30]
    Challenges in the Fehmarnbelt project - Femern
    Sep 17, 2025 · When the construction contracts were signed in 2016, the German plan approval for the project had not yet been granted. As a result, specific ...
  31. [31]
    Fehmarnbelt tunnel | How 73000t elements will be connected to mm ...
    Feb 19, 2024 · The tunnel will be made up of 89 precast concrete elements. The 79 standard elements will be 217m long and 42m wide, weighing 73,000t. The 10 “ ...Missing: depth | Show results with:depth
  32. [32]
    First Special Element for the Fehmarn Tunnel Cast
    Oct 21, 2024 · First Special Element for the Fehmarn Tunnel Cast · Number: 10 · Length: 39 meters · Width: 47 meters · Height: 13 meters · Weight: 21,000 tons ...
  33. [33]
    Fehmarnbelt Tunnel Insights - PERI Group
    The Fehmarnbelt Tunnel will be the longest immersed tunnel in the world and is considered one of the largest infrastructure construction sites in Europe.
  34. [34]
    Fehmarnbelt tunnel - WTM Engineers
    It is designed to have a length of 18.1 km and to be built as an immersed tunnel. The individual tunnel segments would be manufactured with a rectangular cross ...Missing: timeline | Show results with:timeline
  35. [35]
    the world's longest immersed tube tunnel - Construction Briefing
    Oct 30, 2023 · Each segment takes 30-36 hours to cast with no stops to prevent cold joints. Over the course of that process, 50-60 people are involved. Optimum ...
  36. [36]
    Construction phases - Femern
    1. Site preparation · 2. Construction of work harbours at Rødbyhavn and Puttgarden · 3. Dredging in the Fehmarnbelt and establishment of new land areas · 4.Missing: timeline | Show results with:timeline
  37. [37]
    Fehmarnbelt | Specialised tunnel element immersion vessel arrives ...
    Oct 2, 2024 · A unique vessel that will aid in the immersion of the 73,000t precast concrete elements to form the Fehmarnbelt tunnel between Germany and ...
  38. [38]
    Fehmarnbelt tunnel - Doka
    The project involves the construction of an 18 km immersed tunnel between Rødbyhavn on Lolland in Denmark and Puttgarden on Fehmarn in Germany.
  39. [39]
    Finance - Femern
    The Fehmarnbelt link is user-financed, with a total framework of DKK 55.1 billion. The EU granted EUR 1.3 billion for construction.
  40. [40]
    Finance of the Fehmarnbelt link
    The Fehmarnbelt Fixed Link's overall financial framework of DKK 55.1 billion (2015 prices) is determined in the 2015 Construction Act.
  41. [41]
    [PDF] Annual Report - Femern
    Apr 24, 2025 · In 2024, the company financed its activities via EU funding and on-lending through Nationalbanken via A/S. Femern Landanlæg. In total ...
  42. [42]
    State aid: Fehmarn Belt fixed rail-road link - European Commission
    Mar 19, 2020 · In July 2015, the Commission approved the public financing model of the Fehmarn Belt fixed rail-road link between Denmark and Germany under EU ...<|separator|>
  43. [43]
    Commission approves public financing of Fehmarn Belt fixed rail ...
    Jul 22, 2015 · The costs of the entire project are estimated to be DKK 64.4 billion (€8.7 billion), part of which is funded by the European Union through the ...Missing: sources | Show results with:sources
  44. [44]
    The Fehmarnbelt tunnel receives EUR 540 million in EU funding
    Jun 30, 2022 · ... (TEN-T) during the 2021-2027 EU budget period. The TEN-T aims to strengthen the internal market by removing bottlenecks and promoting more ...Missing: fixed link designation date
  45. [45]
    [PDF] Cost–benefit analysis of The Fehmarn Belt Fixed Link
    Finally, Denmark is expected to receive significant grants from the EU for the tunnel and the onshore facilities. Thus, there will be a net benefit for ...<|control11|><|separator|>
  46. [46]
    [PDF] Cost–benefit analysis of The Fehmarn Belt Fixed Link
    Jan 5, 2015 · The updated financial analysis shows that the Fehmarn Belt Fixed Link has a payback period of 32 years with reserves of 13.6 per cent included ...
  47. [47]
    [PDF] fehmarnbelt business council - IHK
    Jun 28, 2016 · This socio-economic return equates to a net profit of €3.5 billion that will benefit tunnel users, and therefore companies, in terms of time ...
  48. [48]
    More financial doubt over proposed Fehmarn Belt Tunnel
    The proposed Fehmarn Belt Tunnel to link Denmark and northern Germany will never be economically viable, according a report commissioned by German ferry ...
  49. [49]
    How reliable are the profitability analyses for the fixed link across the ...
    Current studies on the fixed link across the Fehmarnbelt paint an optimistic picture when they conclude that the tunnel is worthwhile both from an economic and ...
  50. [50]
    Approved IPCEI Fehmarn Belt fixed rail-road link - Competition
    The tunnel will be approximately 19 kilometres long and consist of an electrified, double-track railway and a four-lane motorway. Based on an intergovernmental ...
  51. [51]
    The contractors on the Fehmarnbelt tunnel - Femern
    FBC also performs the preparatory work for the tunnel portals on the Danish and German sides. FBC consists of the following companies: Contractors: Boskalis ...
  52. [52]
    Megaproject: Fehmarnbelt tunnel - Witteveen+Bos
    Sep 21, 2024 · The Fehmarnbelt fixed link will be the longest immersed tube tunnel in the world. ... dredging the tunnel trench, constructing service ...
  53. [53]
    Fehmarn Belt Fixed Link dredging and reclamation works | Van Oord
    The Fehmarn Belt Fixed Link project consists of four contracts: the north tunnel, the south tunnel, tunnel dredging and reclamation, and the tunnel portals and ...Missing: preparatory | Show results with:preparatory
  54. [54]
    Dredging works on the Fehmarnbelt tunnel trench completed - Femern
    Apr 16, 2024 · Dredging of the 18 kilometre long tunnel trench between Denmark and Germany is now complete. Around 15 million cubic meters of soil have been dredged from the ...Missing: preparatory | Show results with:preparatory
  55. [55]
    A vast undersea tunnel is being built that will change the road ... - CNN
    Mar 12, 2025 · Linking Denmark and Germany, the Fehmarnbelt will carry two-lane road highways under the water in both directions, plus two electrified rail ...
  56. [56]
    The Fehmarnbelt tunnel trench dredging project
    The Fehmarnbelt Fixed Link, an 18-kilometre-long immersed tunnel between Rødbyhavn in Denmark and Puttgarden in Germany.
  57. [57]
    DFSI Magazine features article about the Fehmarnbelt tunnel trench ...
    Aug 22, 2025 · This vision is now being realized with the construction of the Fehmarnbelt Fixed Link – an immersed tunnel that will cross the approximately ...
  58. [58]
    First special element pushed - Femern Link Contractors
    Sep 30, 2024 · The Fehmarnbelt Tunnel by FLC for The Fehmarnbelt Project is built of 79 standard tunnel elements and 10 special elements.
  59. [59]
    Important Milestone reached in the Fehmarnbelt Tunnel project
    Jul 4, 2024 · PERI supplied the formwork to produce the 79 standard tunnel elements, each 217,00 m in length and weighing 73.000 t. Upon its scheduled ...
  60. [60]
    The Fehmarnbelt tunnel's first tunnel element now cast - Femern
    May 6, 2024 · The first of the 89 tunnel elements has now been cast at the tunnel factory in Rødbyhavn. The first tunnel element for the coming Fehmarnbelt ...
  61. [61]
    Casting of the tunnel elements for the Fehmarnbelt link now underway
    Jul 10, 2023 · Casting of the tunnel elements for the 18 km immersed tunnel between Rødbyhavn on Lolland in Denmark and Puttgarden on the German island of Femern is underway.
  62. [62]
    Specialised Vessel To Aid Construction Of Fehmarnbelt Tunnel
    Oct 15, 2024 · The production of the concrete tunnel elements on Lolland is expected to continue until 2027, and the tunnel is scheduled to be completed in ...
  63. [63]
    Exciting milestone at the Fehmarnbelt tunnel project - DEME Group
    Feb 19, 2025 · The first two massive 73,500-ton tunnel elements for the Fehmarnbelt tunnel project have successfully been floated up from the skidding beams ...
  64. [64]
    Fehmarnbelt tunnel | First 73000t tunnel elements moved into basin ...
    Feb 7, 2025 · The concrete elements, measuring 217m in length and 42m in width, are being cast on-site on Lolland, Denmark.
  65. [65]
    Video: How the tunnel elements are connected - Femern
    Feb 15, 2024 · A standard element weighs 73,500 tonnes and is 217 meters long. Therefore, the immersion requires a specially built vessel that can place the ...
  66. [66]
    Fehmarn Belt Tunnel facing delays - International Railway Journal
    THE project to construct the Fehmarn Belt Tunnel and a new cross-border railway between Denmark and Germany is facing delays due to challenges ...
  67. [67]
    Fehmarnbelt tunnel timeline under pressure due to 'significant ...
    Aug 28, 2025 · The construction schedule for the Fehmarnbelt tunnel is under “considerable pressure” with no tunnel elements yet immersed.
  68. [68]
  69. [69]
  70. [70]
  71. [71]
    Rail connection for Fehmarn Belt Tunnel delayed by three years
    Aug 1, 2025 · The completion of the German railway link to the Fehmarn Belt Tunnel will be delayed by at least three years, which constitutes a potential ...Missing: Bahn | Show results with:Bahn<|control11|><|separator|>
  72. [72]
  73. [73]
    Why we're building the Fehmarnbelt fixed link - Femern
    The Ringsted-Fehmarn Railway. As part of the construction of the Fehmarnbelt link, the Danish railway from Ringsted to Rødbyhavn will be substantially upgraded.
  74. [74]
    The record-breaking tunnel being built from Denmark to Germany
    Apr 22, 2025 · With a price-tag around €7.4bn ($8.1bn; £6.3bn) the scheme has mostly been financed by Denmark, with €1.3bn from the European Commission. It's ...
  75. [75]
    Ringsted-Fehmarn - English language | UkBane
    Towards the opening of the fixed-link Banedanmark will be upgrading and modernizing the appr. 115 km line between Ringsted and Rødby, providing commuters and ...
  76. [76]
    Fehmarnbelt Tunnel, Denmark - Railway Technology
    Apr 11, 2023 · It will include 89 tunnel elements each measuring 217m in length and 73,000t in weight, including 79 standard elements and ten special elements.Missing: fixed depth<|separator|>
  77. [77]
    The Fehmarnbelt link - Sund & Bælt
    The Fehmarnbelt link was approved in Denmark through the Danish Parliament's adoption of the Construction Act in 2015. Approval of the project, including ...
  78. [78]
    FEHMARNBELT TUNNEL LINK - European Investment Bank
    The upgrade includes the increase of line speed to 200 km/h for passenger trains, electrification of the track, constructing a double track for the whole ...
  79. [79]
    German regulatory approval of four-lane motorway to the ...
    Sep 29, 2019 · The route runs between the end of the A1 motorway at Heiligenhafen to the upcoming Fehmarnbelt tunnel and the ferry port at Puttgarden.
  80. [80]
    The Fixed Fehmarnbelt Connection: Getting ahead in 2018
    Sep 29, 2019 · In Germany, route B207 between the end of the A1 motorway at Heiligenhafen to Puttgarden is to be expanded to a four-track motorway. A ...
  81. [81]
    How the connection to the Fehmarn Belt Link is being built on the ...
    Jan 6, 2025 · Preparations for the upcoming four-lane road connection to the Fehmarn Belt Link are now visible in the northern German landscape.
  82. [82]
    Rail link for the Fehmarn Belt Fixed Link | DB E&C
    Modernization work will include 90 new bridges, six new stops, complete electrification along the line and the roll-out of a new train protection system, ETCS ...
  83. [83]
    Fehmarnbelt Tunnel: STRING Highlights Urgent Need for German ...
    The policy paper highlights the urgency of completing the feeder routes on the German side of the Fehmarnbelt tunnel by 2029—the year the tunnel is set to open.
  84. [84]
    Rail Freight with the Fehmarn Belt Fixed Link - STRING Megaregion
    May 16, 2023 · The Fehmarn Belt Fixed Link will be completed in 2029, eliminating the need for a 160 km detour through Denmark for freight trains.
  85. [85]
    Proudly supporting the Fehmarnbelt Tunnel - Thinkproject
    The travel time through the tunnel itself amounts to seven minutes by train and ten minutes by car. In the future, freight trains will save 160 kilometres by ...
  86. [86]
    [PDF] Rail Freight with the Fehmarn Belt Fixed Link - Greater Copenhagen
    Mar 31, 2023 · The Fehmarn Belt Fixed Link (FBFL) removes a bottleneck, reducing transport times and costs, but rail transport is struggling to meet demand, ...
  87. [87]
    Connecting Denmark and Germany - WorldCargo News
    Jun 23, 2025 · Once completed, the 18km immersed tunnel will connect Rødbyhavn in Denmark with Puttgarden in Germany, establishing a permanent road and rail ...<|separator|>
  88. [88]
    Economic impacts in the STRING region from the FBFL
    May 16, 2023 · This new study documents the massive potential within trade, business, innovation, and labour market impacts related to the fixed link ...
  89. [89]
    [PDF] Predicting Changes in Swedish Trade Flows from the Fehmarnbelt ...
    May 18, 2025 · This immersed tube tunnel aims to streamline transportation between the two countries, fostering economic growth and regional integration ( ...
  90. [90]
    Fehmarn Belt Fixed Link to accelerate European trade | World Finance
    The Fehmarn Belt Fixed Link is designed to close a gap in the infrastructure between Scandinavia and continental Europe. This will foster a higher level of ...
  91. [91]
    Statement on the current cost-benefit analysis for a fixed link across ...
    DIW Econ has examined the current cost-benefit analysis of the planned fixed link across the Fehmarn Belt from 2015.
  92. [92]
    Construction and Operation of the Fehmarn Belt Immersed Tunnel Is ...
    There are two types of tunnel elements: 79 standards and 10 special elements. Each of the standard elements is approximately 217 m long, 42 m wide and 9 m high.
  93. [93]
    Inaccuracy of traffic forecasts and cost estimates on large transport ...
    An examination of construction costs and traffic in seven large Danish bridge and tunnel projects shows that construction costs have been underestimated and ...Missing: critique | Show results with:critique
  94. [94]
    [PDF] The Peripheral City and Rotten Bananas The Case of Nakskov
    Oct 11, 2024 · The construction activity surrounding the Fehmarn Belt construction project seems to have slowed down the population decline, although it has ...
  95. [95]
    Tremendous effect of permanent tunnel factory in Rødbyhavn
    Apr 13, 2021 · A permanent tunnel element factory will secure jobs on Lolland for many years to come, as well as ensuring a better economy in future Danish ...
  96. [96]
    [PDF] TRANSBOUNDARY ENVIRONMENTAL IMPACT ASSESSMENT
    Jun 27, 2013 · The planned immersed tunnel across the Fehmarnbelt will consist of a cut-and-cover tunnel at the two approaches and an immersed tunnel between ...Missing: specifications | Show results with:specifications
  97. [97]
    eia for the fehmarnbelt crossing – the world's longest immersed tunnel
    May 2, 2025 · This article describes the role of environmental impact assessment, and gives an overview of the environmental effects of dredging operations.
  98. [98]
    Fehmarnbelt Fixed Link – environmental impact assessment
    Environmental impact assessment for marine mammals, non-breeding waterbirds, bird as well as bat migration. Between 2008 and 2010, BioConsult SH, as part of ...
  99. [99]
    [PDF] managing dredging noise during the construction of the world's ...
    May 18, 2022 · The. Environmental Impact Assessment concluded that porpoises are less sensitive to continuous noise and that the construction of the Tunnel ...
  100. [100]
    [PDF] Fish and Fisheries - Femern VVM
    abundance due to the construction of a tunnel are not considered to impact the fish communi- ties in Fehmarnbelt. The habitat suitability of fish in ...
  101. [101]
    [PDF] FEHMARNBELT FIXED LINK MARINE BIOLOGY SERVICES (FEMA)
    EQS Environmental Quality Standards are levels used to assess the risk of chemical pollutant effects on water quality to the health of aquatic plants and ...
  102. [102]
    Individual-based modelling supports environmental impact ...
    The major aim of this study is to demonstrate the usefulness of applying an IBM in an EIA. Using the Fehmarn Belt Fixed Link project as a case-study, we predict ...
  103. [103]
    Marine environment - Femern
    The Fehmarnbelt project's marine monitoring programme has been developed to document any environmental impacts and verify the environmental consequences ...
  104. [104]
    Fehmarnbelt Fixed Link – construction monitoring - BioConsult SH
    Monitoring of underwater noise and light emissions. Environmental construction monitoring serves to prepare, monitor and document the environmental measures ...Missing: strategies | Show results with:strategies
  105. [105]
    An environmental portal for the Fehmarnbelt tunnel project
    The ÆGIR data portal helps communicate findings from marine and land assessments and supports operational planning for the world's longest immersed tunnel.Missing: strategies | Show results with:strategies
  106. [106]
    [PDF] Potential Implications for Harbour Porpoises in the Baltic Sea
    The construction of a fixed Fehmarnbelt Link leaves numerous open questions and poses serious potential risks on the Baltic harbour porpoise and other marine ...Missing: sedimentation | Show results with:sedimentation
  107. [107]
    Impact of High Marine Traffic on Harbor Porpoise - ResearchGate
    Jan 10, 2024 · ... Fehmarn Belt indeed found a stronger. correlation between hydrodynamic parameters and porpoise activity (FEMM 2013). Harbor porpoises require ...
  108. [108]
    Deconstructing the Fehmarnbelt fixed link: Local resistance and ...
    Feb 22, 2024 · Besides the eager promotion of the project, there has been considerable opposition against the construction of the tunnel from a broad alliance ...Missing: bridge rejected
  109. [109]
    Fehmarn Belt Link: Do the benefits of the world's longest underwater ...
    Jun 27, 2024 · The mega project, the largest engineering project ever undertaken in Denmark set to cost upwards of €4.8 billion, is part of the European ...Missing: details | Show results with:details
  110. [110]
    [PDF] Asymmetric legitimacy perception across megaproject stakeholders
    As the Fehmarnbelt project proceeded, Germany moreover experienced a string of major megaprojects' failures and controversies, such as massive social resistance ...
  111. [111]
    Environmentalists Criticize Planned Link from Germany to Denmark
    Jun 16, 2009 · Jürgen Boos of the Action Alliance Against a Fixed Fehmarn Belt Crossing claims that Germany didn't conduct the required European Union-wide ...
  112. [112]
    Engineering the World's Longest Underwater Tunnel Against ...
    Nov 6, 2023 · With its environmental impacts, carbon footprint, and potential benefits in mind, the Fehmarn Belt Fixed Link symbolizes the delicate balance ...<|separator|>
  113. [113]
    Protesters rally as court decides on Denmark-Germany tunnel - DW
    Sep 22, 2020 · Environmentalists have held protests outside a court that is deciding on a tunnel link between a German island and a Danish one.Missing: residents | Show results with:residents
  114. [114]
    Fehmarn Belt fixed link - Wikipedia
    Fehmarn Belt tunnel is an under-construction immersed tunnel, which will connect the Danish island of Lolland with the German island of FehmarnFehmarn Sound Tunnel · Fehmarn Sound Bridge · Immersed tube
  115. [115]
    New study suggests Fehmarn Belt payback close to 50 years
    Also, driver fees alone are unlikely to be sufficient for the financing of the link. Danish taxpayers will likely have to contribute to the project. More ...
  116. [116]
    External Quality Assurance of the Fehmarn Belt Fixed Link Business ...
    However, tunnel construction costs were increased by DKK 2 billion and reserves reduced by DKK 1.8 billion, see Table 2. A brief status report was issued at the ...Missing: critique | Show results with:critique
  117. [117]
    [PDF] External quality assurance of the Fehmarn Belt fixed link business ...
    Mar 18, 2017 · Section 4 focuses on quality assurance of the construction costs of hinterland constructions, tunnel construction and allocated reserves and the ...Missing: critique | Show results with:critique
  118. [118]
    The Record-Breaking Tunnel Connecting Denmark To Germany
    The total cost of the project is estimated at €7.4 billion, with the majority funded by Denmark and a significant €1.3 billion contribution from the European ...
  119. [119]
    [PDF] Economy-wide benefits
    Modelling the transport costs. The reductions of transport costs due to the Fehmarn Belt fixed link is deducted from the latest forecast by FTC (2003). The ...Missing: viability | Show results with:viability<|separator|>
  120. [120]
    [PDF] Ramboll - Economic impacts in the STRING region of the FBFL
    The Fehmarn Belt Fixed Link has a higher potential to positively affect trade to and from the STRING regions located in the Scandinavian countries, compared to ...<|separator|>
  121. [121]
    [PDF] Annual Report - 2023 - Femern
    Apr 22, 2024 · In 2023, the Fehmarnbelt project made its most impressive progress so far on the construction of the fixed link between Denmark and Germany.