Hoosac Tunnel

The Hoosac Tunnel is a 4.75-mile-long railroad bored through Hoosac Mountain in northwestern , connecting the towns of North Adams and . Constructed from 1851 to 1875 at a cost exceeding $14 million, it was the longest transportation in upon completion and remained so until 1916. The project, undertaken by the Commonwealth of to link the and Railroad with the Railroad, provided a vital direct route for freight and passengers between and , bypassing longer circuitous paths through . The tunnel's construction was a monumental endeavor that spanned 24 years and involved overcoming severe geological challenges, including fault zones, water inflows, and unstable rock formations. Early efforts relied on hand drilling and , but progress accelerated with innovations such as the Burleigh compressed-air rock drill introduced in 1866, explosives (over 500,000 pounds used), and the first application of electric blasting caps for . Seventeen were sunk to a total depth of 3,083 feet to facilitate excavation, including a central shaft reaching 1,030 feet, which served as a key access and ventilation point. The center-cut tunneling method, where headings were advanced from multiple points and connected, became a standard technique for hard-rock tunnels worldwide. Despite its triumphs, the Hoosac Tunnel earned the grim nickname "The Bloody Pit" due to nearly 200 worker fatalities from accidents, explosions, and cave-ins during . Financial overruns, political delays, and setbacks plagued the project, which employed up to 900 workers, many of them skilled miners. Upon opening in , the first train traversed the tunnel on February 9, , marking a pivotal advancement in American rail infrastructure and hard-rock tunneling technology that influenced practices worldwide. As of 2025, the tunnel continues to operate as part of the route, operated by the & Eastern Railway, serving as a testament to 19th-century ingenuity and remaining an active freight corridor handling intermodal traffic.

Background

Location and Geography

The Hoosac Tunnel is located in northwestern , piercing the Hoosac Range of the Northern Mountains and connecting the Deerfield to the east with the Hoosic to the west. This route facilitated the Troy and Railroad line, linking to , by providing a direct passage through the mountainous barrier that otherwise required steep grades and circuitous paths. The tunnel primarily lies within County, though the broader railroad alignment extends into adjacent Franklin County. Measuring 4.75 miles (7.64 km) in length, the tunnel runs in a nearly straight line, with its east portal situated in the town of and the west portal in the city of North Adams. The east portal sits at an elevation of approximately 636 feet (194 m) above near the Deerfield River, while the west portal is at about 784 feet (239 m), resulting in a gentle westward incline over the distance. The maximum depth below the surface reaches 1,028 feet (313 m) at the central point, underscoring the tunnel's penetration into the rugged terrain. Geologically, the Hoosac Mountain consists primarily of and formations from the Hoosac Formation, with interbedded layers of and other metamorphic rocks that posed significant challenges due to their variability. Water seepage was a persistent issue, as numerous springs and aquifers intersected the path, leading to saturated "porridge-like" conditions in softer zones, particularly near the west end, where unstable rock exacerbated instability. These features, part of the broader geologic structure, highlighted the tunnel's demanding environmental context amid forested hills and river valleys.

Economic and Strategic Importance

In the pre-1850s era, the Hoosac Tunnel project emerged from the pressing need for a direct rail connection between and the Midwest, routing through , to access western markets more efficiently than the circuitous paths via or . This initiative sought to integrate with existing lines like the Vermont and Massachusetts Railroad at , forming a northern corridor that avoided the steeper grades and longer detours of southern alternatives, thereby enhancing New England's access to trans-Appalachian trade routes. The tunnel's strategic value lay in shortening the travel distance by approximately 20 miles compared to alternative paths around the Hoosac Range, which featured precipitous grades and meandering routes. This reduction facilitated faster freight and passenger transport, critical for industries such as textiles, which required timely imports of raw from the and exports to western markets, and , sourced from Midwest forests to support regional and . By streamlining , the project promised to lower shipping costs and times, bolstering economic competitiveness in an era of expanding networks. On a broader scale, the Hoosac Tunnel formed a key segment of the Boston-Troy Corridor, designed to challenge City's rail dominance and its control over western trade via the and connections. supported this effort through an initial state appropriation, including a loan of $2 million in to fund , building on the charter. Key stakeholders included the Western Railroad, which linked eastward, and the Troy and Railroad, chartered in with $3.5 million in capital to handle the tunnel and connecting line from to the border near .

Planning and Construction

Proposals and Early Efforts

The concept of tunneling through Hoosac Mountain originated in 1819 as part of a proposed canal system to link Boston with upstate New York via the Deerfield River, facilitating trade connections to the Erie Canal. By 1825, with the advent of railroads, advocates adapted the idea for rail transport, prompting the Massachusetts legislature to commission a survey of potential routes through the Hoosac Range to identify a passable path. Detailed engineering surveys followed in 1827 and 1828, evaluating three possible railroad alignments: a northern route incorporating the tunnel, a middle route, and a southern deviation. The northern option, spanning about four miles through the mountain, was deemed feasible with an estimated cost under $1 million, though initial assessments underestimated geological challenges. These early efforts highlighted the tunnel's potential to shorten travel distances and reduce steep grades compared to existing paths. In the 1840s, Alvah Crocker, a prominent Fitchburg paper mill owner and railroad developer, emerged as the tunnel's chief advocate, pushing for a direct northern rail corridor from to , to compete with longer southern lines controlled by rivals. Crocker's emphasized the economic benefits for northern industries, leading to legislative approval in for the Troy and Railroad Company to build the tunnel and associated tracks. Political debates raged over the merits of full tunneling versus less costly alternatives, such as inclines, deviations around the mountain, or the competing Cheshire Railroad route through , which was ultimately rejected due to higher operational costs and less direct access. Funding disputes and engineering disagreements delayed progress through the early , as estimates revised upward to around $2 million amid concerns over rock hardness and water inflow. In 1851, after securing initial state support including a $25,000 allocation for preparatory experiments, the company broke ground on January 7 at the western portal in North Adams, marking the formal start of fieldwork despite ongoing financial hurdles.

Construction Timeline and Challenges

Construction of the Hoosac Tunnel commenced on January 7, 1851, with the initial groundbreaking at the west portal in , marking the start of a protracted effort that ultimately spanned 25 years. The project proceeded in distinct phases, beginning with the east heading from 1851 to 1866, which advanced approximately 2,399 feet by 1861 before facing significant interruptions due to funding disputes. The central initiated in December 1863, reaching a depth of 1,030 feet by August 1870, while the west heading progressed from the late 1850s onward, covering about 450 feet by 1861. Full breakthrough occurred on November 27, 1873, when the east and west headings connected after tunneling 11,274 feet from the east and 10,188 feet from the west. The first train passed through the tunnel on February 9, 1875, followed by final lining and completion on June 30, 1876, with official opening on July 1, 1876. The timeline was marred by repeated delays, including a major halt from July 1861 to 1862 over contractor payment issues and a in the central shaft in that postponed progress for over a year. Early excavation rates were agonizingly slow, averaging only 50 feet per month in the east heading initially, hampered by the project's reliance on manual labor and rudimentary supply chains across rugged terrain. Logistical hurdles compounded these issues, such as intermittent power supply from a distant on the Deerfield River, which necessitated on-site steam alternatives and further slowed operations. Water inflows presented one of the most persistent challenges, flooding workings repeatedly and requiring constant pumping; for instance, the central encountered up to 225 gallons per minute, while the west saw 1,000 gallons per minute in 1866, inundating excavations and causing structural instability. By December 1865, total penetration stood at just 4,354 feet out of the required 25,586 feet, reflecting cumulative delays from these hydrological issues and supply blockades that restricted material transport. Budget overruns epitomized the project's fiscal strains, with an initial estimate of $1,968,557 for manual excavation in 1851 escalating dramatically due to prolonged delays and escalating costs for state bonds and federal aid. The original $2,000,000 state loan from 1854 proved insufficient, leading to a final expenditure of approximately $10 million for the tunnel itself, plus $4 million for associated railroad work and $3.3 million in interest, totaling around $17.3 million by completion. These overruns, driven by the extended timeline and unforeseen logistical demands, transformed the Hoosac into a symbol of 19th-century ambition tempered by practical adversity.

Engineering Innovations

The Hoosac Tunnel's pioneered several techniques that advanced tunneling practices in the mid-19th century, particularly in addressing the challenges of excavation through the Hoosac Mountain. These innovations, including , advanced explosives, a massive central access shaft, and robust lining and systems, enabled the completion of the 4.75-mile despite formidable geological obstacles. One of the most significant breakthroughs was the first use of compressed-air rock drills, specifically the Burleigh drill, introduced in 1866 at the central shaft. Invented by Charles Burleigh and powered by a hydropower-driven system established in 1864, the 372-pound drill was mounted on a mobile track carriage, allowing for efficient operation in the tunnel headings. This technology marked a shift from hand-held tools and early steam drills, which had proven ineffective in the tunnel's and rock, and it dramatically accelerated progress to up to 250 feet per month in equipped sections by enabling multiple machines to work simultaneously. The adoption of as an in , spearheaded by chief engineer Thomas Doane, further revolutionized blasting operations and complemented the pneumatic drills. Prior to this, black powder had been the standard but was inefficient in fracturing the dense rock, often requiring excessive labor to clear incomplete blasts. , manufactured on-site, reduced blasting time substantially—doubling progress rates in headings and tripling them in enlargements—while requiring fewer drill holes per round, though its volatility demanded rigorous purification and handling protocols to mitigate instability risks. The central , sunk vertically 1,030 feet from between December 1863 and August 1870, represented another landmark innovation as the deepest and most ambitious access point of its kind at the time. This elliptical , measuring 15 by 27 feet, facilitated simultaneous excavation from four headings and incorporated powerful hoisting engines to remove debris and water, alongside compressed-air lines at 90 pounds per square inch for powering tools and initial ventilation. By providing direct vertical access to the tunnel's core, it shortened haul distances and integrated the new methods, expediting overall advancement during a critical of construction. To ensure structural integrity and safe operations, the tunnel featured a comprehensive arch lining, with over 20 million s laid in a 3- to 4-foot-thick horseshoe-shaped arch where rock was unstable, covering approximately 7,573 feet of the bore. Ventilation relied on a natural draft system augmented by the central shaft and additional , which expelled fumes post-blast via a Mackenzie blower capable of clearing air in five minutes, while periodic pumps managed inflow. The single-track alignment incorporated gentle curves with a minimum radius of about 1,000 feet, optimized by engineer Thomas Doane in 1862 to balance navigational efficiency with the mountain's contours.

Labor Conditions and Fatalities

The construction of the Hoosac Tunnel relied on a primarily composed of immigrants, supplemented by , English, and Canadian miners, who endured grueling conditions in the dim, damp interior illuminated only by candlelight and facing chronic poor air quality from dust, smoke, and explosive residues. At peak employment in the mid-1860s, around 459 workers were engaged across the site, operating in three rotating eight-hour shifts around the clock to maximize progress through the . The environment was exacerbated by constant water inflows, ranging from 5 to 1,000 gallons per minute at various shafts, leading to flooding risks and heightened physical strain without modern safety regulations or protective gear. Fatalities during the 24-year project were staggering, with estimates ranging from 180 to 196 deaths, though a 1873 newspaper account cited 136 as the official tally at that time; most victims succumbed to explosions, cave-ins, falls, and drownings in the absence of systematic protocols. The deadliest incident occurred on October 17, 1867, at the central , where a ignited flammable naphtha vapors and oil, trapping and killing 13 s who had no escape routes or ladders from the 1,028-foot depth. Other notable tragedies included a 1870 failure at the central that drowned three workers, multiple cave-ins like the December 1873 that killed Miles O’Grady, and falls from heights exceeding 1,000 feet, such as that of Griffith Jones in 1871. , introduced in 1868 for blasting, contributed to further losses, including a 1869 magazine explosion at the east end that claimed three lives. Workers also suffered long-term health effects from prolonged exposure to silica dust and blast fumes, leading to respiratory ailments akin to , though contemporary records focused more on acute injuries like burns, amputations, and internal trauma from premature detonations. The 1865-1867 period marked the worst cluster of central shaft disasters, halting work for over a year after the 1867 fire and prompting public outcry over the lack of oversight. In response, post-accident inquiries, including a promised following the 1867 incident, led to limited reforms such as improved storage and handling protocols, though comprehensive safety changes remained elusive during the project's duration.

Completion and Early Operations

Opening and Initial Use

The full boring of the Hoosac Tunnel was completed on November 27, 1873, when the eastern and western headings met at the tunnel's center, marking the end of over two decades of excavation efforts. Track laying within the tunnel progressed throughout 1874 and into 1875, allowing for the first test train to pass through on February 9, 1875, followed by the inaugural on April 5, 1875, consisting of 22 cars loaded with grain from the West. These early passages confirmed the tunnel's basic operational viability, with initial inspections verifying structural stability after the breakthrough. The tunnel received its official dedication on July 1, 1876, opening for regular rail service amid ceremonies attended by local and state dignitaries at the portals in North Adams and . This event highlighted the engineering feat, with celebrations emphasizing the tunnel's role in linking eastern and western rail lines. The structure featured a single track, 24 feet wide and 20 feet high, designed with a straight alignment and a gentle to accommodate safe passage. In its initial operations, the Hoosac Tunnel supported both freight and passenger trains traveling at speeds of up to 25 , enabling efficient transport through the 4.75-mile bore. Upon completion of track work by mid-1876, the tunnel integrated into the broader network via the newly organized , Hoosac Tunnel and Western Railway in , connecting eastward to the & Maine Railroad and westward toward lines including the Fitchburg Railroad. This linkage facilitated immediate through-service for goods and passengers across .

Economic Impact in the 19th Century

The completion of the Hoosac Tunnel in 1875 dramatically enhanced trade between and western markets by providing a direct link through the Hoosac Range, reducing the time required to traverse the mountain barrier from approximately 18 hours via earlier canal routes to about 1 hour and 15 minutes by . This shortcut lowered freight costs, such as by about one cent per of or barrel of flour, enabling more efficient movement of commodities like and from the Midwest to ports and onward to . By the early 1880s, the tunnel supported over 300 freight cars daily, with 20 freight trains operating each day. The tunnel spurred industrial growth in North Adams, transforming it into a manufacturing hub by improving access to raw materials and markets. Textiles emerged as a dominant sector, with the Blackinton Woolen Company becoming Berkshire County's largest mill by 1864 and expanding further post-completion, while the Arnold Print Works grew to employ 2,000 workers by 1883, producing 200,000 yards of dyed fabric daily in the 1890s. This growth was supported by the influx of 125 daily freight trains through the tunnel by 1880. Financially, the tunnel began recouping its $14 million construction cost—largely funded by state loans and bonds—through tolls and operational leases shortly after opening. The route stimulated migration to surrounding towns and increased land values, as enhanced trade prospects attracted settlers and investors to northern . However, initial traffic remained low due to competition from established lines like the , which diverted some freight via longer but more developed routes. Full profitability was not achieved until the 1890s, following leases to operators such as the Fitchburg Railroad, which integrated the tunnel into broader networks before its eventual control by the .

20th and 21st Century Developments

Ownership Changes and Modernization

Following the completion of the Hoosac Tunnel in 1875 by the Troy and Greenfield Railroad, ownership transitioned in 1877 when the Fitchburg Railroad acquired the Troy and Greenfield Railroad, including the tunnel, for $1,900,000, integrating it into its main line from Boston to Albany via the tunnel's east-west route. In 1900, the Fitchburg Railroad was leased to the Boston & Maine Railroad (B&M) for 99 years, placing the tunnel under B&M operation as part of its Fitchburg Division, which facilitated expanded freight and passenger services through the Berkshires. The B&M fully merged the Fitchburg in 1919, solidifying its control over the tunnel and associated trackage. By 1910, the New York, New Haven & Hartford Railroad had acquired a in the through stock purchases, effectively absorbing operational oversight of the tunnel's line amid growing consolidation, though formal ownership remained with the until antitrust actions in 1918 forced divestiture. The encountered financial difficulties in the mid-20th century, filing for in amid broader industry challenges, but it was excluded from the formation of in 1976, which consolidated other Northeastern bankrupt carriers like Penn Central; instead, the underwent independent reorganization. In 1983, Guilford Transportation Industries purchased the out of , renaming it in 2006 and continuing freight operations through the tunnel. A significant shift occurred in 2009 with the creation of , a 50-50 between and , which assumed ownership and management of the tunnel and the Ayer to Mechanicville main line to enhance east-west freight capacity while complying with approvals for infrastructure investments exceeding $87.5 million. Modernization efforts focused on adapting the 19th-century for safer, more efficient rail traffic, beginning with in 1911 when the installed an 11,000-volt single-phase AC overhead system through the tunnel to mitigate smoke and issues, enabling electric operation until its abandonment in 1946 following the widespread adoption of diesel-electric locomotives. To address , a dual-fan system was installed at the between 1943 and 1946, improving air quality and allowing consistent through-traffic without prior restrictions. In the , the reduced the tunnel to single track in 1957 to provide adequate clearance for larger diesel units and modern , while mid-century upgrades included reinforced track beds and improvements for higher speeds. Later 20th-century work emphasized structural integrity and , with steel liner plates installed in sections of the tunnel during the late and under and early Guilford management to repair deteriorating brick and stone linings damaged by water infiltration and age. By the and , additional liner plate installations, tie replacements, and stone ballasting were undertaken to meet (FRA) safety standards for , load capacity, and hazard mitigation, ensuring the tunnel's viability for freight while addressing ongoing maintenance needs without electrification revival. These upgrades prioritized conceptual enhancements like improved and over exhaustive overhauls, maintaining the tunnel's role in networks.

Current Operations and Maintenance

On June 1, 2022, completed its acquisition of for approximately $700 million, integrating the Hoosac Tunnel into the between and , with operations handled by the & Eastern Railroad, a subsidiary. As of 2025, the tunnel supports freight operations exclusively, handling about 5 to 8 trains per day carrying commodities such as single-stack intermodal containers, chemicals, and aggregates, limited by the structure's 20-foot clearance. No passenger service has operated through the tunnel since the late 1950s, when the Boston & Maine discontinued regular runs. The maximum speed remains restricted to 25 mph due to the tunnel's curvature, grades, and structural constraints. Maintenance efforts focus on preserving the 19th-century infrastructure amid ongoing challenges like water seepage and rock stability. The tunnel receives annual inspections to monitor water intrusion, lining condition, and overall structural integrity, in line with federal rail safety standards. In 2023, upgrades to ventilation systems at the central shaft improved air quality and safety for operations. A significant repair project followed a partial wall collapse in February 2020, which closed the tunnel for two months; crews stabilized the affected section through concrete reinforcement and debris removal, reopening it fully in April 2020. The Hoosac Tunnel remains fully operational in 2025, with no closures recorded that year, playing a key role in efficient freight movement across by connecting Boston-area terminals to and beyond. Its endurance was celebrated during 150th anniversary events in October 2025, including public talks and historical exhibits in , underscoring its vital place in regional rail logistics.

Legacy and Significance

Historical Recognition

In 1975, the (ASCE) designated the Hoosac Tunnel as a National Historic Civil Engineering Landmark, recognizing its pioneering role in 19th-century tunneling techniques and its status as a major infrastructure achievement. On November 2, 1973, the tunnel was listed on the under the name "Hoosac Tunnel," highlighting its contributions to commerce, engineering, and transportation during the period from 1854 to 1875. Upon its completion in 1875, the Hoosac Tunnel measured 4.75 miles in length, making it the second-longest railroad tunnel in the world at the time, surpassed only by the 8.5-mile Mont Cenis Tunnel in the . It held the distinction of being the longest tunnel in until the opening of the 5-mile in in 1916. The tunnel's construction innovations, particularly the early use of for blasting and compressed-air drilling machines, have been extensively covered in engineering literature as benchmarks in rock tunneling technology. A seminal early account is Edward Sandford Martin's 1877 book History of the Hoosac Tunnel, which details the project's technical challenges and the adoption of these explosives and tools to advance excavation rates. Commemorations of the tunnel's milestones have underscored its enduring place in U.S. railroad , including events for its in that featured historical exhibits celebrating its opening. In 2025, for the 150th anniversary, activities such as public talks by historians like Carl R. Byron at the North Adams Public Library emphasized the tunnel's visionary and its impact on regional .

Cultural and Environmental Impact

The Hoosac Tunnel has left a lasting mark on local , earning the moniker "Bloody Hoosac" due to numerous ghost stories stemming from construction accidents that claimed nearly 200 lives. These apocryphal tales of apparitions, including the spirits of workers like Ned Brinkman and Billy Nash—allegedly killed in a —and glowing blue phantoms wandering the dark passages, have persisted in oral traditions and media portrayals despite lacking historical confirmation. These narratives, often shared during Halloween events and in regional podcasts, reflect the era's industrial perils and continue to draw enthusiasts to the site. The tunnel's completion spurred significant community growth in North Adams, transforming it from a modest of approximately 6,000 residents in 1850 to a bustling industrial hub of 24,200 by 1900, fueled by rail access that attracted immigrant laborers and factories. Today, this legacy supports tourism through guided walking tours of the east portal and exhibits at the Western Gateway Heritage State Park, which highlights the tunnel's role in regional rail history via interactive displays and artifacts. Local historical societies, such as the North Adams Historical Society, further preserve these stories through programs that emphasize the immigrant contributions to the project. Environmentally, the tunnel's construction disrupted the Hoosac Valley ecosystem, involving extensive deforestation for access roads and spoil disposal, alongside alterations to the Deerfield River watershed through blasting and excavation that connected previously separate hydrological systems. Ongoing challenges include from adjacent historical workings, such as the Davis Mine, which contaminates local streams with low pH and , affecting aquatic life in the Deerfield River. In the , mitigation efforts by state agencies have focused on wetland restoration in the watershed, including passive treatment systems to neutralize drainage and revegetation projects to rebuild riparian habitats, balancing the tunnel's industrial heritage with modern ecological priorities. As a symbol of ambition, the Hoosac Tunnel exemplifies the era's reliance on immigrant labor—primarily and workers enduring hazardous conditions—while highlighting tensions with contemporary goals in rail infrastructure, such as reducing emissions and . Its enduring presence underscores the trade-offs between economic progress and in America's industrial landscape.

References

  1. [1]
    Hoosac Tunnel - ASCE
    The Hoosac Tunnel, completed in 1876, was the largest and longest transportation tunnel in the Western Hemisphere, taking 20 years to build. It was 4.75 miles ...Missing: significance | Show results with:significance
  2. [2]
    Hoosac Tunnel - Rowe Historical Society
    The Hoosac Tunnel, a 4¾ mile engineering marvel, was the longest in North America until 1916, and was built with innovative techniques and significant loss of ...
  3. [3]
    [PDF] Construction of the Hoosac Tunnel, 1855 to 1876
    The Hoosac Tunnel is a truly great civil engineering accomplishment. Constructed through Hoosac Mountain in Northwestern Massachusetts from 1855 to 1876 ...
  4. [4]
    Facts and Figures Concerning the Hoosac Tunnel - Project Gutenberg
    Oct 23, 2024 · For its construction 17 shafts were sunk, their total depth being 3,083 feet, the least depth of any one being 63 feet, and the greatest, 344 ...
  5. [5]
    The Story of the Hoosac Tunnel - The Atlantic
    The requisite depth of this was 1028 feet. The magnitude of the tunnel ... The greatest difficulty in constructing the Hoosac Tunnel was found at the ...Missing: maximum | Show results with:maximum
  6. [6]
    Hoosac Tunnel | SAH ARCHIPEDIA
    The Hoosac Tunnel passes through 4.75 miles of solid rock in the northwestern corner of Massachusetts. Laboriously constructed between 1851 and 1875, ...
  7. [7]
    BUILDING BIG: Databank: Hoosac Tunnel - PBS
    Cost: $21 million ; Length: 25,081 feet (4.75 miles) ; Purpose: Railway ; Setting: Rock ; Materials: Brick
  8. [8]
    Hoosac Tunnel, Town of Florida, Berkshire County ... - Mindat
    Town of Florida, Berkshire County, Massachusetts, United States · 42° 40' 9" N · 72° 59' 34" W · 42.66925,-72.99288 · Dfb : Warm-summer humid continental climate.
  9. [9]
    [PDF] plate 1 - USGS Publications Warehouse
    Hoosac Tunnel о. Peru O. Becket. Ch. Deerfield. Ohv. DSg. Heath о. North o Colrain ... Gray or black carbonaceous schist and quartzite lo- cally interbedded ...
  10. [10]
    [PDF] The Hoosic Matters: A Brief History of the Hoosac Valley
    contain layers of rock formed under the ocean, such as quartzite, schist, and limestone. ... Hoosac Tunnel, at a cost of 195 workers' lives, connected the ...
  11. [11]
    Workers Complete Hoosac Tunnel - Mass Moments
    The Hoosac Tunnel took over 20 years, $17 million, and 196 lives to complete, with 750 men working in shifts. The first train passed through in 1875.Missing: importance lumber
  12. [12]
    Hoosac Tunnel (Massachusetts): Map, Length, Location, History
    Feb 27, 2025 · The T&G made a connection from the V&M at Greenfield and was created to reach Troy/Albany, New York via the southern tip of the Green Mountains ...<|control11|><|separator|>
  13. [13]
    New explosives, pneumatic drills aid decadeslong tunnel construction
    Jan 8, 2024 · Incorporated June 1, 1848, the Troy and Greenfield Railroad received permission to build a line from Greenfield, Massachusetts, to Troy, New ...
  14. [14]
    Tri-nitro-glycerin As Applied in the Hoosac Tunnel, by George M ...
    In 1866, I received a communication from Thomas A. Doane, Esq., chief engineer of the Hoosac Tunnel, who was keenly alive to the necessity of more efficient ...
  15. [15]
  16. [16]
    [PDF] Hoosac Tunnel Accidents Compiled by Charles Cahoon January 2 ...
    Jan 2, 2015 · A newspaper article of 1873 reported that 136 men were killed during the construction of the. Hoosac Tunnel. Most histories of the 1880's ...
  17. [17]
    The Project Gutenberg eBook of Report On The Hoosac Tunnel And ...
    A slight change in laying the track will increase the radius of these curves to 1,000 feet. ... Profile of Hoosac Mountain. Length of Tunnel when finished ...
  18. [18]
    The Hoosac Tunnel Disaster of 1867 - New England Historical Society
    The Hoosac Tunnel disaster killed 13 miners in 1867, but the tunnel took the lives of an estimated 180 workers during decades of construction.Missing: conditions primary sources
  19. [19]
    The Hoosac Tunnel Completed | Beehive
    Nov 27, 2011 · The Hoosac Tunnel, 4.75 miles long, was completed in 1877, with the center opened in 1873. It was the longest tunnel in the western hemisphere ...
  20. [20]
    [PDF] NORTH ADAMS INDUSTRIALIZES | Farewell to Factory Towns?
    Apr 18, 2012 · Diverse, but continuous waves of immigrants, helped to form the growing industrial labor force, making Adams the most industrialized community ...
  21. [21]
    150 years on, the Hoosac Tunnel tells a story of vision, risk, tragedy ...
    Oct 16, 2025 · Historian Carl R. Byron recalls the highs and lows of the building of the Hoosac Tunnel. When it was complete, it was the longest tunnel in ...
  22. [22]
    The Project Gutenberg eBook of Facts and Figures Concerning the ...
    We have now placed before our readers such facts in relation to European tunnels, and more particularly in relation to that under the Alps, as will enable them ...
  23. [23]
    History of the B&M Railroad
    The B&M's most famous engineering landmark was the five-mile-long Hoosac Tunnel. Hundreds of the railroad's bridges enhanced the New England landscape ...
  24. [24]
    [PDF] Boston and Maine Railroad - A History of the Main Road, with
    took over the Fitchburg Railroad under a lease guaranteeing five per ... Boston, Hoosac Tunnel and Western, whose road ran from Rotterdam Junction, N ...
  25. [25]
    Fitchburg Railroad - Special Collections & University Archives
    In 1900, the Fitchburg Railroad was leased for 99 years to the Boston and Maine. It operated as the Fitchburg Division until the two companies merged in 1919.Missing: 1877 | Show results with:1877
  26. [26]
    Fitchburg Railroad: Map, History, Timetables - American-Rails.com
    Feb 11, 2025 · The Fitchburg Railroad, the Boston & Maine's most important acquisition, was leased on July 1, 1900. This system provided a key western outlet to easetern New ...
  27. [27]
    Boston and Maine Railroad: Map, Roster, Logo, History
    Nov 14, 2024 · The most important component of the B&M was the Fitchburg Railroad, leased on July 1, 1900. It provided access across Massachusetts to important ...
  28. [28]
    [PDF] News Release - 09-07Approved: NS & Pan Am joint control ...
    Mar 10, 2009 · NS has committed to infuse $87.5 million into PAS for infrastructure improvements in order to improve traffic flows and expand capacity. In ...
  29. [29]
    Online Archives - Boston & Maine Railroad Historical Society
    The Eastern Railroad gained control of Maine Central in 1871. B&M leased ERR in 1884 and thereby controlled MEC. When, in 1907, New Haven gained control of ...
  30. [30]
    MEC/B&M Track Conditions 1981/1983 - RAILROAD.NET
    new rail from British Steel (of all places), stone ballasting and tie work and some more liner plate in the Hoosac Tunnel. The freight speed limit was 40 ...
  31. [31]
    CSX Completes Acquisition of Pan Am Railways - GlobeNewswire
    Jun 1, 2022 · JACKSONVILLE, Fla., June 01, 2022 (GLOBE NEWSWIRE) -- CSX Corp. (NASDAQ: CSX) today announced it has completed the acquisition of Pan Am ...
  32. [32]
    CSX aims to expand Northeast reach with Pan Am acquisition
    Dec 1, 2020 · UBS analysts estimated the purchase price to be less than $700 million, in a research note published Monday. Pan Am Railways owns and operates ...
  33. [33]
    CSX begins operating New England regional Pan Am Railways
    Jun 1, 2022 · CSX plans to spend more than $100 million over the next three years to improve Pan Am's main lines and yards. The deal adds Vermont, New ...
  34. [34]
    Hoosac Tunnel Facts for Kids
    In 1848, Crocker helped get a special permission, called a charter, for the Troy & Greenfield Railroad. This charter included plans for the Hoosac Tunnel.
  35. [35]
  36. [36]
  37. [37]
    Hoosac Tunnel Central Shaft Updates - Then vs Now - YouTube
    Feb 27, 2023 · There have been some big improvements happening at the Central Shaft of the Hoosac Tunnel. Both of the old horns have been replaced with ...
  38. [38]
    Hoosac Tunnel in North Adams reopens to trains
    Apr 8, 2020 · The Hoosac Tunnel reopened to trains on Saturday after a two-month closure for repairs. Credit: Courtesy photo/Scott Stafford.
  39. [39]
    Hoosac Tunnel open again after 'partial' collapse in February
    Apr 7, 2020 · Crews have been working to repair the tunnel since the collapse in February that was caused by "structural wear and tear." The tunnel has been ...<|control11|><|separator|>
  40. [40]
    150 years on, the Hoosac Tunnel tells a story of vision, risk, tragedy ...
    Oct 16, 2025 · The Hoosac Tunnel was, until 1916, the longest tunnel in North America. It opened up the northern Berkshires to trade and tourism, creating an ...
  41. [41]
    NAPL: The Hoosac Tunnel at 150 Years - iBerkshires.com
    Oct 3, 2025 · The reopening of the in-patient beds last year at the hospital filled a substantial health-care gap in North County. The hospital closed in 2014 ...Missing: Franklin Hampshire
  42. [42]
    NPGallery Asset Detail - National Park Service
    Hoosac Tunnel. National Register Information System ID: 73000294 ... National Register of Historic Places. Locations: State: Massachusetts. County ...
  43. [43]
    Catalog Record: History of the Hoosac tunnel
    History of the Hoosac tunnel. Published: 1878. History of the Hoosac Tunnel. Author: Martin, Edward Sandford, 1856-1939. Published: 1877. History of the Hoosac ...Missing: scholarly books nitroglycerin drilling innovations
  44. [44]
    US Postal History Railroad Hoosac Tunnel Opening 100th Anniv ...
    US Postal History Railroad Hoosac Tunnel Opening 100th Anniversary Postmarked 7/1/1976 Charlemont MA Commemorative Cacheted Cover - Midwest Railway ...Missing: 150th | Show results with:150th
  45. [45]
    These Berkshire ghost stories have cultural value — they're just not ...
    Nov 1, 2024 · The Hoosac Tunnel is the focus of many ghost stories, including that of Ned Brinkman and Billy Nash, two tunnel workers said to have been killed by a ...Missing: legacy | Show results with:legacy
  46. [46]
    HISTORY OF NORTH ADAMS, BERKSHIRE CO., MASSACHUSETTS
    1850 6,172; 1860 6,924; 1870 12,090; 1880 Adams 5,591; 1880 North Adams 10,191. In 1885 the population of the north village alone is 12,540 inhabitants.
  47. [47]
    [PDF] The Gritty Berkshires - Westfield State University
    In the 1850s, the state, along with several private investors, chose the Hoosac Range as a site to drill a 4.75- mile railway tunnel that would offer a western ...<|control11|><|separator|>
  48. [48]
    Western Gateway Heritage State Park - Mass.gov
    Visitors to this former railroad yard in North Adams, MA will learn about the controversial and dangerous construction of the Hoosac Tunnel.
  49. [49]
    NORTH ADAMS HISTORICAL SOCIETY - Updated October 2025
    Rating 5.0 (1) More info about North Adams Historical Society · Map · 40 Main St. North Adams, MA 01247. Directions · (413) 664-4700. Call Now · Other Amenities. Does North Adams ...
  50. [50]
    [PDF] DEERFIELD RIVER WATERSHED 2000 WATER QUALITY ...
    ... acid mine drainage. The upper portion of Davis Mine Brook and the remaining ... Hoosac Tunnel it turns south and east entering Charlemont where the ...
  51. [51]
    [PDF] 33wqar appendix - Mass.gov
    the Hoosac Tunnel it turns south and east entering Charlemont where the gradient lessens. ... Cessation of further acid mine drainage, if determined to be ...
  52. [52]
    [PDF] THE TRAGEDY OF THE DEERFIELD RIVER
    Alvah Crocker, a paper manufacturer from nearby Fitchburg, Massachusetts who proposed using ... Hoosac Tunnel & Wilmington RR, 3rd Printing edition (Stephen ...