Job-shop scheduling, also known as the job-shop scheduling problem (JSSP), is a problem in and . It involves scheduling a set of n jobs on m machines, where each job requires a specific sequence of operations on designated machines, subject to constraints such as no preemption of s and each machine processing at most one at a time. The goal is typically to minimize the , the completion time of the last job, though other objectives like total tardiness or energy use are also considered. The problem was classically formulated in the , with foundational instances, such as the famous 10×10 instance, introduced in the edited volume Industrial Scheduling by J. F. Muth and G. L. Thompson. JSSP is strongly NP-hard even for instances with three or more machines. Due to its , exact methods like branch-and-bound are used for small instances, while heuristics and metaheuristics, including recent integrations of and , address larger, dynamic variants in Industry 4.0 contexts. JSSP models flexible production environments in industries like and pharmaceuticals, enabling efficient and adaptation to uncertainties such as breakdowns.

Fundamentals

Definition and Overview

Job-shop scheduling is a fundamental problem in and , involving the assignment of a set of jobs to a finite number of s to determine the sequence and timing of s. Each job consists of a predefined sequence of s, where each must be processed on a specific for a given time, subject to constraints that prevent two s from overlapping on the same and prohibit preemption of any once started. The standard formulation assumes a static where all jobs are available at time zero, with a finite set of machines and no release dates or due dates unless specified otherwise; setup times are typically negligible, though variants may incorporate them. This setup emphasizes under precedence and capacity constraints to optimize performance measures in or systems. In contrast to , where every job follows an identical fixed route through all machines, job-shop scheduling permits arbitrary and job-specific routings, allowing different operations within a job to be assigned to distinct machines in varying orders and enabling recirculation if a job revisits a machine. This flexibility models diverse real-world production environments but increases problem complexity. Key terminology includes: a job (j), which represents an entire production order; an operation (O_{j,i}), the i-th task of job j processed on a specific machine m_{j,i}; machines (M_k), the processing resources; processing time (p_{j,i}), the duration required for operation O_{j,i}; completion time (C_j), the finish time of all operations in job j; and makespan (C_{\max}), defined as \max_j C_j, a primary objective often minimized to gauge overall schedule efficiency.

Historical Context

Job-shop scheduling emerged in the as a key area within , influenced by Frederick Winslow Taylor's principles of , which emphasized the separation of planning from execution to optimize industrial efficiency. Taylor's early 20th-century work laid foundational ideas for systematic , while accelerated the development of quantitative methods for and through teams addressing and bottlenecks. A pivotal milestone came in 1956 when J.R. Jackson extended S.M. Johnson's 1954 for two-machine flow shops to the more general job-shop setting, introducing rules for sequencing operations across multiple machines. In the 1960s, E.H. Bowman advanced mathematical modeling for job-shop sequencing, proposing formulations to minimize , while branch-and-bound techniques began to be applied for exact solutions to small instances. The decade also saw growing interest in simulation-based approaches to handle the problem's combinatorial nature. The 1963 edited volume Industrial Scheduling by J.F. Muth and G.L. introduced foundational instances, such as the famous 10×10 problem. By the , R.L. Graham and colleagues provided a seminal survey classifying scheduling problems and standardizing notation, alongside J.K. Lenstra and A.H.G. Rinnooy Kan's proof that minimizing in job shops with three or more machines is NP-hard, shifting focus from exact solvability to approximation methods. The marked a transition from manual to computer-aided scheduling, enabled by advances in computing power that allowed implementation of dispatching rules and optimization software for larger instances in settings. Influential figures like A.H.G. Rinnooy Kan contributed to both complexity analysis and practical heuristics, bridging theory and application. In the 1990s and 2000s, integration with and metaheuristics revolutionized the field; genetic algorithms, , and emerged as powerful tools for near-optimal solutions, with seminal work by L. Davis on genetic approaches to scheduling demonstrating their efficacy for dynamic environments. Post-2010 developments have intertwined job-shop scheduling with Industry 4.0 paradigms, incorporating cyber-physical systems, sensors, and for real-time, data-driven adaptations to disruptions like machine failures or demand fluctuations. Hybrid methods combining with traditional metaheuristics have gained traction for predictive and resilient scheduling, as seen in frameworks leveraging digital twins for and optimization in smart factories. By 2025, trends emphasize sustainable and distributed scheduling in multi-factory networks, supported by and edge to handle the increased complexity of flexible manufacturing systems.

Problem Formulation

Standard Model

The standard model of the job-shop scheduling problem (JSSP) involves scheduling a set of n jobs J_i (i = 1, \dots, n) on m M_k (k = 1, \dots, m), where each job J_i consists of a sequence of o_i operations. Each operation j of job i must be processed on a specific machine \mu_{i,j} \in \{1, \dots, m\} for a fixed processing time p_{i,j} > 0. The decision variables are the start times s_{i,j} \geq 0 for each (i,j), which determine the timing of processing on the assigned machines. The primary objective is to minimize the C_{\max} = \max_i C_i, where C_i = s_{i,o_i} + p_{i,o_i} is the completion time of job i. The model imposes two main types of constraints. First, within each job, operations must follow the prescribed sequence without preemption, so s_{i,j+1} \geq s_{i,j} + p_{i,j} for all i = 1, \dots, n and j = 1, \dots, o_i - 1. Second, on each machine k, the operations assigned to it must not overlap: for any two operations (i,j) and (i',j') with \mu_{i,j} = \mu_{i',j'} = k and (i,j) \neq (i',j'), either s_{i,j} + p_{i,j} \leq s_{i',j'} or s_{i',j'} + p_{i',j'} \leq s_{i,j}. Under the standard model, processing times are deterministic and fixed, machines do not break down, and all jobs arrive simultaneously at time zero (static arrivals). Extensions such as job-specific release dates r_i \geq 0 (where s_{i,1} \geq r_i) can be incorporated but are not part of the classic formulation. To express the disjunctive machine constraints linearly, the model is formulated as a mixed-integer program (MIP) using binary sequencing variables. For each pair of operations (i,j) and (i',j') assigned to the same k = \mu_{i,j} = \mu_{i',j'}, introduce a binary variable z_{i,j,i',j'} \in \{0,1\}, where z_{i,j,i',j'} = 1 if (i,j) precedes (i',j'). The non-overlap constraints then become: s_{i',j'} \geq s_{i,j} + p_{i,j} - U (1 - z_{i,j,i',j'}), s_{i,j} \geq s_{i',j'} + p_{i',j'} - U z_{i,j,i',j'}, where U is a sufficiently large constant (e.g., an upper bound on the , such as U = \sum_{i=1}^n \sum_{j=1}^{o_i} p_{i,j}). Additionally, to ensure , z_{i,j,i',j'} + z_{i',j',i,j} = 1 for all distinct pairs (i,j), (i',j') with \mu_{i,j} = \mu_{i',j'}. The job precedence constraints and non-negativity remain as stated. The full MIP is: \begin{align*} \min &\quad C_{\max} \\ \text{s.t.} &\quad s_{i,j+1} \geq s_{i,j} + p_{i,j}, \quad \forall i=1,\dots,n, \, j=1,\dots,o_i-1, \\ &\quad s_{i',j'} \geq s_{i,j} + p_{i,j} - U (1 - z_{i,j,i',j'}), \\ &\quad s_{i,j} \geq s_{i',j'} + p_{i',j'} - U z_{i,j,i',j'}, \\ &\quad z_{i,j,i',j'} + z_{i',j',i,j} = 1, \\ &\quad \forall (i,j) \neq (i',j') : \mu_{i,j} = \mu_{i',j'}, \\ &\quad C_{\max} \geq s_{i,o_i} + p_{i,o_i}, \quad \forall i=1,\dots,n, \\ &\quad s_{i,j} \geq 0, \quad \forall i=1,\dots,n, \, j=1,\dots,o_i, \\ &\quad z_{i,j,i',j'} \in \{0,1\}, \quad \forall (i,j) \neq (i',j') : \mu_{i,j} = \mu_{i',j'}. \end{align*} This disjunctive formulation, originally proposed by Manne, enables exact solution via branch-and-bound or other MIP solvers for small instances.

Representation Methods

The disjunctive graph model represents the job-shop scheduling problem (JSSP) as a G = (V, A, E), where V is the set of s corresponding to s, A denotes conjunctive arcs enforcing precedence constraints within each job, and E represents disjunctive arcs capturing resource conflicts on s. For each job i, conjunctive arcs connect consecutive s such that the start time s_{i,j+1} of j+1 satisfies s_{i,j+1} \geq s_{i,j} + p_{i,j}, where p_{i,j} is the processing time of j in job i. Disjunctive arcs, two per pair of s assigned to the same , model the : if s o_{k} and o_{l} share a , one arc enforces o_{k} before o_{l} and the other the reverse, with exactly one selected per pair to resolve conflicts. This model, originally proposed by and Sussman, facilitates analysis by transforming the scheduling problem into selecting a consistent set of disjunctive arcs, where the equals the length of the longest (critical path) from a source to a in the resulting . Tabular representations provide a compact input format for JSSP instances, typically using a P = [p_{i,j}] where rows correspond to jobs and columns to operations within each job, specifying durations, alongside a machine assignment or indicating the machine for each operation. These matrices encode the technological , such as fixed operation sequences per job, enabling straightforward data input for algorithms; for instance, a precedence may explicitly list successor operations to reinforce job ordering beyond the implicit row structure. Such forms are foundational in datasets, like those from Taillard, where times are drawn from distributions to test . Gantt charts offer a visual timeline-based representation of schedules, plotting operations as horizontal bars along axes for machines (vertical) and time (horizontal), highlighting start/end times, idle periods, and overlaps. In JSSP contexts, they illustrate machine utilization and job progress, aiding in identifying bottlenecks; for example, bars for operations on the same machine cannot overlap, visually enforcing disjunctive constraints. This method, while not algorithmic, supports human interpretation and validation of solutions, as seen in early scheduling practices. Alternative models include state-space representations, where the problem state comprises current operation completions and machine availabilities, used in search algorithms to explore feasible schedules via transitions like dispatching ready operations. For metaheuristics, permutation-based encodings simplify solution generation: operation-based permutations sequence all operations while preserving job order through embedded job indices (e.g., a string like 1-1, 2-1, 1-2, 2-2 for two jobs), decoded into active schedules; job-based variants prioritize job order but require additional decoding for intra-job sequencing. These encodings, prominent in genetic algorithms, reduce search space dimensionality compared to full timetable representations. The disjunctive graph model's key advantage lies in enabling efficient lower bound computations, such as via longest path algorithms on the subgraph with only conjunctive arcs (disjunctives unresolved), which underestimate the and guide branch-and-bound searches.

Objective Functions

In job-shop scheduling, the primary objective is to minimize the , defined as the maximum time across all , C_{\max} = \max_i C_i, where C_i is the time of job i. This metric focuses on overall production efficiency by reducing the total time required to process all on the available machines, ensuring high utilization and timely factory clearance. Secondary objectives often address and . Common among these is minimizing the total completion time, \sum C_i, or the mean flow time, \frac{1}{n} \sum (C_i - r_i), where r_i is the release time of job i and n is the number of jobs; these prioritize reducing holding costs and work-in-process. minimization targets \sum T_i, with T_i = \max(0, C_i - d_i) and d_i as the of job i, to penalize delays and improve reliability. Earliness and tardiness penalties extend this by balancing deviations from due dates, using \sum (E_i + T_i) where E_i = \max(0, d_i - C_i), to avoid rushed or stockpiled completions in just-in-time environments. Weighted variants incorporate job priorities, such as minimizing \sum w_i C_i for total weighted completion time or \sum w_i T_i for weighted , where w_i reflects the relative importance or cost of job i. Multi-objective formulations handle trade-offs between conflicting goals, like versus total , by approximating Pareto fronts that represent non-dominated solutions for decision-makers to select from. Additional metrics include minimizing machine idle time to enhance throughput and balancing workloads across machines to prevent bottlenecks and extend equipment life. Recent developments in the emphasize , particularly minimizing as an objective, often integrated with traditional metrics like to reduce environmental impact while maintaining productivity; this involves modeling machine speeds and idle energy use in scheduling decisions.

Variants and Complexity

Key Variations

The job-shop scheduling problem (JSSP) has been extended in various ways to better model real-world environments, incorporating elements such as dynamic arrivals, flexibility in machine assignments, and constraints on intermediate handling. These variations maintain the core structure of jobs consisting of ordered operations on specific machines but introduce additional parameters to address practical complexities like and limitations. In the dynamic JSSP, jobs arrive over time rather than all at once, typically modeled with release dates r_i > 0 for each i, requiring schedules to adapt to ongoing arrivals and potentially incomplete about future jobs. This variant is prevalent in production systems where orders arrive unpredictably, and simulation-based approaches have been used to evaluate dispatching rules under dynamic conditions. extensions further incorporate uncertainty in processing times, where operation durations follow probability distributions rather than fixed values, necessitating robust scheduling to minimize expected or . The flexible JSSP (FJSP) relaxes the strict machine-operation assignments of the model, allowing each to be processed on any of a of machines, often with varying processing times depending on the chosen machine. This reflects modern flexible manufacturing systems with multi-purpose equipment, increasing the decision space by requiring both machine assignment and sequencing. The problem was first formally introduced in the of multi-purpose machines, highlighting its NP-hard nature even for small instances. Open-shop scheduling differs from the job-shop by not prescribing a fixed of operations for each job, allowing the order to be any , while each job requires processing on every machine exactly once, with no two operations of the same job overlapping in time. This variant suits environments like chemical processing where operation order on machines is flexible beyond job-internal s, and it has been studied extensively for minimization since the 1970s. Other notable variants include the no-wait JSSP, where no intermediate storage is permitted, so consecutive operations of a job must start immediately upon completion of the previous one to avoid delays. In the preemptive JSSP, operations can be interrupted and resumed later on the same machine, allowing for better resource utilization in settings with urgent jobs. The blocking JSSP prohibits buffers between machines, meaning a job blocks the current machine until the next one is free, common in systems with limited transportation resources. Setup-dependent times extend the model by including sequence-dependent setup durations s_{i,j,i',j'}, which depend on the transition from operation (i,j) of job i to operation (i',j') of job i' on the same machine, capturing cleaning or reconfiguration needs in industries like printing or pharmaceuticals. Finally, the distributed JSSP, emerging in cloud manufacturing paradigms post-2015, involves scheduling jobs across multiple geographically dispersed factories, each operating as a local , to leverage shared resources and minimize global . This variant addresses the shift toward networked production in Industry 4.0, with jobs assignable to any factory before local routing.

Computational Complexity

The job-shop scheduling problem with makespan minimization, denoted Jm \| C_{\max}, is NP-hard in the strong sense for any fixed number of machines m \geq 3, even when restricted to unit processing times. This strong NP-hardness follows from a polynomial-time reduction from the 3-partition problem, which is known to be strongly NP-complete. The decision version of Jm \| C_{\max}, asking whether there exists a schedule with makespan at most some value K, is NP-complete for m \geq 3, with proofs typically employing reductions from or problems to construct job routings and processing times that encode the original instance. In contrast, the problem is solvable in polynomial time for m = 1, where it reduces to sequencing jobs in non-decreasing order of processing times. For m = 2, an optimal schedule can be found in O(n^2) time using a network flow formulation that models disjunctive constraints as a bipartite matching problem. When processing times are unit length, the two-machine case further simplifies to linear time solvability via greedy assignment rules. Regarding approximation, Jm \| C_{\max} for fixed m \geq 2 admits no constant-factor unless = , as established by inapproximability results derived from label cover reductions. Recent work on has explored structural parameters; for instance, the problem is fixed-parameter tractable when parameterized by the of the conflict graph underlying the job routings, enabling dynamic programming approaches that run in time exponential only in the treewidth.

Special Solvable Cases

The two-machine job-shop scheduling problem (J2||C_max) admits an efficient exact solution through an adaptation of , originally developed for flow shops, to handle arbitrary routings where each job has at most two operations, one on each machine. Jobs are classified into categories based on their routing: those processed only on the first machine, only on the second, or on both in either order (M1 then M2 or M2 then M1). The algorithm sequences jobs starting with those only on M1, followed by those with M1-M2 routing ordered by using their processing times on M1 and M2, then those with M2-M1 routing ordered by on M2 and M1 times (reversed), and finally those only on M2; this produces an optimal schedule in O(n^2) time. For instances with unit-time operations (p_{ij} = 1 for all operations), polynomial-time algorithms exist using network flow models, particularly when routings form acyclic structures or have bounded usage. These approaches model the problem as a maximum flow in a time-expanded , where nodes represent machine-time pairs and edges enforce precedences and non-overlap constraints, enabling exact solutions in O(n^3) time for fixed numbers of machines or specific topologies like series-parallel routings. Finally, when all jobs share the identical machine sequence, the job-shop problem reduces to the problem (F_m||C_max), which is solvable in polynomial time for m=2 machines via in O(n log n) time, though NP-hard for m ≥ 3; this preserves optimality by treating the common route as a schedule.

Solution Techniques

Exact Methods

Exact methods for job-shop scheduling aim to find optimal solutions by exhaustively exploring the solution space while pruning infeasible or suboptimal branches, guaranteeing optimality at the cost of potentially high computational demands. These approaches are particularly valuable for small to medium-sized instances where precision is critical, such as in high-value processes. Key techniques include branch-and-bound, linear programming, dynamic programming, and , each leveraging different mathematical frameworks to model and solve the problem. Branch-and-bound algorithms systematically enumerate possible operation sequences on machines, building a where nodes represent partial schedules and branches correspond to decisions on operation ordering. The method prunes branches using lower and upper bounds on the objective, such as , to avoid exploring suboptimal ; a common lower bound is derived from the critical path length in the disjunctive graph representation, which estimates the minimum time required along the longest path considering precedence and machine constraints. Seminal work by Carlier and Pinson introduced an efficient branch-and-bound based on solving one-machine subproblems to compute tight bounds and demonstrated its ability to solve instances like the 10x10 problem. Subsequent improvements, such as those by Brucker, Jurisch, and Sievers, enhanced pruning through better relaxation techniques and solved larger instances, including the challenging 10x10 in under a minute on contemporary hardware. These algorithms often incorporate energetic reasoning to further tighten bounds by considering cumulative resource usage over time intervals, reducing the search space for resource-constrained variants. Integer linear programming (ILP) formulations model the job-shop problem as a set of linear constraints and binary variables, solved using commercial solvers like CPLEX or Gurobi. A classic approach uses time-indexed variables to indicate whether an operation starts at a specific time slot, ensuring no overlapping on machines via disjunctive constraints linearized with big-M formulations; this captures precedence within jobs and resource exclusivity across machines. Alternatively, position-based variables assign operations to sequence positions on each machine, minimizing by ordering decisions without explicit time variables, which can be more compact for permutation schedules. The foundational ILP model was proposed by Manne, who framed the problem with sequencing restrictions and noninterference constraints to minimize , enabling techniques. Modern implementations leverage these formulations with advanced solver heuristics, achieving optimality for instances up to 20 jobs and 15 machines on standard hardware, though preprocessing and symmetry-breaking cuts are essential for efficiency. Dynamic programming exploits the structure of small instances by defining states that capture the progress of jobs and machines, computing recursively. A typical state might include the current time, the completion status of each job's operations, and the availability of each machine, with transitions corresponding to scheduling the next feasible operation; the value function minimizes the from that state onward. This approach, adapted from the Held-Karp dynamic programming for the traveling salesman problem, avoids enumerating all permutations by building solutions incrementally. Approaches inspired by the Held-Karp dynamic programming for the traveling salesman problem have been adapted, such as by Gromicho et al. (2012), achieving exact solutions for instances with up to 10 jobs and 10 machines by efficiently managing state explosion through bound propagation. While theoretically sound, the method's state space grows exponentially with the number of operations, limiting practicality to very small problems. Constraint programming (CP) models the problem declaratively using variables for operation start times and domains constrained by precedence, resource availability, and no-overlap conditions, with search guided by arc consistency propagation to reduce domains iteratively. For job-shop scheduling, global constraints like no-overlap on machines and cumulative for resource limits enforce feasibility, while energetic reasoning propagates bounds on (processing time) consumption over time windows to detect infeasibilities early. Caseau and Laburthe developed a CP framework for job-shop problems, integrating task intervals for improved propagation and solving benchmark instances optimally through search enhanced by constraint-directed heuristics. CP solvers like CP Optimizer apply these techniques effectively, handling instances up to 50 operations with minimization by combining propagation with bounding. In general, exact methods exhibit time complexity due to the NP-hard nature of the job-shop scheduling problem, proven strongly NP-hard even for minimization with three or more machines. Practical solvability is limited to instances with n ≤ 10 and m ≤ 10 machines, where branch-and-bound and often outperform others in speed, though larger problems require hours or days on high-end hardware.

Heuristic and Approximate Methods

Heuristic and approximate methods provide efficient solutions to the job-shop scheduling problem (JSSP) by prioritizing computational speed and over guaranteed optimality, making them suitable for large-scale industrial applications where exact methods are impractical. These approaches often generate initial feasible schedules and iteratively improve them using problem-specific operators, drawing on principles from and . Key categories include dispatching rules for dynamic decision-making, local search techniques for neighborhood exploration, and population-based metaheuristics for global search, with recent advancements incorporating for adaptive rule learning. Dispatching rules, also known as priority rules, offer simple, real-time heuristics that select the next operation to process whenever a machine becomes available, based on job attributes like processing times or due dates. The shortest processing time (SPT) rule prioritizes operations with the smallest processing duration on the current machine, aiming to minimize average flow time and work-in-process inventory in job shops. Similarly, the earliest due date (EDD) rule sequences operations by their job's due date, promoting on-time completion and reducing tardiness in due-date-driven environments. For weighted tardiness objectives, the apparent tardiness cost (ATC) rule computes a composite priority index that balances processing time and estimated tardiness, defined as I_j(t) = \frac{w_j}{p_{ij}} \exp\left( -\frac{\max(0, d_j - t - p_{ij} - \hat{\tau}_j )}{k \bar{p}} \right), where w_j is the job weight, p_{ij} the processing time of the current operation, d_j the due date, t the current time, \hat{\tau}_j the estimated lead time for the remaining operations of job j (often approximated as the total remaining processing time divided by the number of machines), \bar{p} the average processing time, and k a scaling factor; this rule has demonstrated superior performance in minimizing total weighted tardiness compared to SPT or EDD in simulation studies of job shops. These rules are applied sequentially at each dispatching event, often combined in hybrid schemes for robustness across varying shop loads. Local search methods start from an initial schedule and iteratively apply neighborhood operators to explore nearby solutions, accepting improvements to reduce or other objectives. Common operators for JSSP include block swaps, which interchange two contiguous blocks of operations on the same machine to resolve critical path delays, and insert moves, which relocate an operation to a different position within its job sequence while respecting precedence. To escape local optima and prevent cycling, incorporates short-term memory (tabu lists) that forbid recent moves for a fixed tenure, as introduced by Glover and adapted for JSSP. A seminal tabu search variant, i-TSAB, uses non-improving moves with adaptive tabu tenures and critical block interchanges, achieving solutions within 1% of optimal on standard Taillard benchmarks for instances up to 100 jobs and machines, often matching known optima in under a minute of computation. The shifting bottleneck heuristic iteratively identifies and optimizes the most loaded machine (bottleneck) using exact methods on subproblems, re-optimizing sequentially to approximate global solutions; it has been effective on medium-sized instances. Metaheuristics extend local search through population diversity and stochastic mechanisms to navigate the vast JSSP search space. Genetic algorithms (GAs) represent schedules as chromosomes encoding operation permutations (e.g., job-based or operation-based sequences), evolving them via selection, crossover (e.g., precedence preserving order crossover), and mutation to minimize makespan; Dorndorf and Pesch's evolution-based GA optimizes sequences of dispatching rules, outperforming standalone heuristics like shifting bottleneck on benchmark instances. Simulated annealing (SA) mimics metallurgical cooling by probabilistically accepting worse solutions with probability \exp(-\Delta / T), where \Delta is the makespan increase and T the temperature; Van Laarhoven et al.'s SA for JSSP uses swap neighborhoods and logarithmic cooling schedules, yielding solutions 5-10% above optimal on 10x10 instances in early benchmarks. Particle swarm optimization (PSO), adapted for discrete permutation spaces, updates particle positions (schedules) toward personal and global bests using velocity-like operators; Xia and Wu's hybrid PSO with local search achieves average relative deviations of 0.5-2% from optima on Taillard's 10x10 to 20x20 benchmarks, competitive with GAs in convergence speed. Ant colony optimization (ACO) builds solutions by ants depositing pheromones on promising operation sequences, with evaporation to diversify; Colorni et al.'s ant system for JSSP uses pheromone trails on job-machine assignments, producing near-optimal schedules on small instances through iterative colony updates. Recent developments integrate (DRL) to learn dispatching policies dynamically, treating scheduling as a where states are encoded via graph neural networks on disjunctive graphs. Zhang et al.'s DRL agent, trained on 10x10 to 30x20 Taillard instances, learns priority dispatching rules that outperform traditional rules like SPT by reducing gaps to 17.7% on 6x6 instances and generalizing to unseen 100x20 instances with 10.9% gaps relative to best-known solutions, all within seconds per . Empirical evaluations across these methods show genetic algorithms and routinely achieving less than 5% deviation from optimal on standard benchmarks like Taillard's suite, enabling practical deployment in systems with hundreds of operations.

Flow Shop Specializations

Flow shop specializations arise in job-shop scheduling when all jobs follow identical machine routings, effectively reducing the problem to a permutation flow shop. In such cases, particularly for two machines, exact polynomial-time algorithms exist to minimize , providing a tractable substructure within the otherwise NP-hard job-shop framework. addresses the two-machine flow shop problem (denoted F2||C_max), where n jobs must be processed sequentially on machine 1 followed by machine 2, with the goal of minimizing the makespan C_max. The algorithm partitions jobs into two groups: those with processing time on machine 1 less than or equal to that on machine 2 (p_{1j} ≤ p_{2j}), and the rest. Jobs in the first group are sorted in non-decreasing order of p_{1j} and scheduled first, while jobs in the second group are sorted in non-increasing order of p_{2j} and scheduled last. This permutation yields the optimal sequence. The steps of can be outlined in as follows:
Input: n jobs with processing times p[1..n][1] on machine 1 and p[1..n][2] on machine 2
Output: Optimal job [permutation](/page/Permutation) to minimize C_max

1. Initialize two empty lists: GroupA and GroupB
2. For each job j from 1 to n:
   If p[j][1] <= p[j][2]:
       Add j to GroupA
   Else:
       Add j to GroupB
3. Sort GroupA in non-decreasing order of p[j][1]
4. Sort GroupB in non-increasing order of p[j][2]
5. Optimal sequence = GroupA followed by GroupB
This procedure runs in O(n log n) time, dominated by the sorting steps. In job-shop settings, Johnson's algorithm applies directly when routings are flow-like, meaning all jobs visit the machines in the same order without skips or reversals. For instance, in a two-machine job shop where every job processes first on machine 1 and then on machine 2, the problem reduces to F2||C_max, and the algorithm sequences the jobs optimally. The algorithm assumes identical machine sequences for all jobs and is limited to two machines; for m > 2 machines in flow shops, it does not guarantee optimality, as Fm||C_max is NP-hard for m ≥ 3. Extensions such as the NEH adapt the partitioning idea by iteratively inserting jobs into partial sequences to approximate solutions for multi-machine cases, often yielding near-optimal results in practice. The optimality of is proven via a pairwise interchange argument: consider any non-optimal ; if two adjacent jobs i and j violate the (e.g., min{p_{1i}, p_{2j}} > min{p_{2i}, p_{1j}}), swapping them reduces or maintains the , and repeating such swaps leads to the algorithm's sequence without increasing C_max. This demonstrates that no better exists.

Performance and Analysis

Makespan Minimization

Makespan minimization in job-shop scheduling seeks to determine a schedule that completes all jobs as early as possible, where the makespan C_{\max} is defined as the completion time of the last operation across all jobs. This objective is central to the classical job-shop problem (JSP), where each job consists of a sequence of operations processed on specified machines without preemption, and no two operations can share a machine simultaneously. The problem is NP-hard even for two machines, necessitating both exact methods for small instances and approximation techniques for larger ones. Seminal work modeled the JSP using a disjunctive graph, where nodes represent operations (plus source and sink nodes), conjunctive arcs enforce job precedence, and disjunctive arcs represent machine conflicts; resolving these disjunctions yields a feasible schedule whose length equals the longest path from source to sink, providing a natural framework for bounding C_{\max}. Lower bounds are essential for pruning search spaces in exact algorithms and assessing approximation quality. A basic machine-based lower bound is the maximum machine load, \max_k \sum_i p_{ik}, where p_{ik} is the processing time of job i's operation on machine k, reflecting the minimum time any single machine requires. Similarly, the job-based lower bound is the maximum job length, \max_i \sum_k p_{ik}, capturing the minimum time for the longest job. These trivial bounds can be tightened using the critical path method in the disjunctive graph: the length of the longest path, treating disjunctive arcs as optional, serves as a lower bound on C_{\max}. Further improvements involve relaxations, such as resolving disjunctions via linear programming or two-job subproblem relaxations, which yield stronger bounds by considering subsets of operations. For instance, solving two-job relaxations provides bounds that are often closer to the optimum for benchmark instances. Upper bounds are typically obtained through constructive heuristics that generate feasible schedules. Priority dispatching rules, applied at each scheduling (e.g., becomes free), select the next operation based on criteria like shortest remaining processing time (SRPT) or longest remaining processing time (LRPT); these rules iteratively build a , yielding an upper bound on C_{\max} that can initialize branch-and-bound searches. For example, the apparent cost () rule combines due dates and processing times for effective upper bounds in practice. More advanced heuristics, such as shifting bottleneck procedures, iteratively optimize subproblems to refine these bounds further. The distinction between offline and online settings is crucial for makespan minimization. In the offline case, all jobs and their details are known in advance, allowing via exact methods like branch-and-bound or schemes; this static environment enables tight bounds and schedules near optimality for moderate-sized instances. In contrast, scheduling assumes jobs arrive dynamically, requiring decisions without future knowledge; list scheduling, which assigns arriving jobs to the earliest available compatible machine, provides a competitive ratio of 2 for makespan in job shops, though better ratios exist for restricted cases like two machines. Recent focus remains on offline minimization due to its tractability for planning, with online variants often using dispatching rules for adaptation. For approximation, no polynomial-time approximation scheme (PTAS) exists even for a fixed number of machines m \geq 2, with inapproximability results showing hardness within non-constant factors. In restricted cases, such as certain batch-processing variants, improved schemes have been developed, though general job shops remain challenging.

Efficiency Measures

In job-shop scheduling, machine utilization serves as a key indicator of , measuring the proportion of time machines are actively jobs relative to their available time. It is typically calculated as the of the total time across all operations to the product of the C_{\max} and the number of machines m, expressed as a : \text{Utilization} = \left( \frac{\sum p_{ij}}{C_{\max} \times m} \right) \times 100\%, where p_{ij} denotes the time of operation j of job i. This metric highlights how effectively the shop floor exploits its capacity, with higher values indicating better but potentially at the cost of increased congestion. Flow time and lateness provide insights into job completion timeliness and . Average flow time quantifies the mean duration jobs spend in the system, often computed as the average completion time \bar{C} minus any release times (assuming zero release times in classical formulations, it simplifies to \bar{C}). Maximum lateness L_{\max} measures the worst-case deviation from s, defined as L_{\max} = \max_i (C_i - d_i), where C_i is the completion time of job i and d_i its . These metrics are critical for due-date-oriented objectives, as minimizing them reduces holding costs and improves delivery performance. Robustness evaluates a schedule's to disruptions, such as breakdowns or time variations, by assessing to perturbations. Common measures include the expected deviation in values under simulated disturbances or the variance in rescheduling costs required to restore feasibility. For instance, robustness can be quantified as the minimal adjustment needed to maintain performance bounds after realization, emphasizing schedules that minimize propagation of delays across the shop. Recent advances incorporate techniques, such as , to predict and enhance robustness in dynamic environments as of 2025. Benchmarking efficiency relies on standardized instances like Taillard's test problems, which provide a diverse set of job-shop configurations ranging from 15×15 to 200×20 jobs and machines, enabling comparative evaluation of algorithms across utilization, flow time, and robustness. These instances facilitate objective , with on metrics like C_{\max} serving as proxies for overall . Efficiency measures often reveal trade-offs, such as high machine utilization increasing C_{\max} due to queuing delays, necessitating balanced workload distributions. Measures for workload balance include the variance in machine loads (total assigned processing time per machine) or the maximum load minus minimum load, aiming to even out utilization while controlling and flow time.

Infinite Cost Scenarios

In variants of job-shop scheduling, such as no-wait or blocking flow shops, infinite cost scenarios can arise in pathological cases where no feasible schedule exists, resulting in unbounded or perpetual delays. A primary cause in these extensions is or infeasibility due to s in the disjunctive graph representation, where the conjunctive arcs enforce job precedences and disjunctive arcs model machine conflicts; a implies that operations cannot be sequenced without violating constraints, leading to infinite delays as jobs loop indefinitely without completion. Such cycles can be detected using adaptations of the Bellman-Ford algorithm in the alternative graph , which extends the disjunctive model by introducing pairs of zero-weight arcs for each machine conflict; the presence of a positive-weight (equivalent to any given positive times) signals infeasibility, as it allows unbounded longest paths from the source to nodes representing start and end. This , seminal for handling extensions like blocking constraints, computes critical paths while identifying inconsistencies that would cause infinite costs. In dynamic or job-shop environments, infinite costs manifest as unbounded waiting times from priority-induced , where dispatching rules favor high-priority jobs, causing low-priority ones to accumulate indefinitely without , escalating delays and potential system overload. For instance, continuous job release without controls can starve downstream machines, amplifying wait times to under persistent high-priority arrivals. Resolution strategies include feasibility checks via bipartite matching algorithms to validate operation-to-machine assignments in flexible variants, ensuring no overloads precede sequencing; if cycles persist, dummy operations can be inserted to break loops or redistribute loads, while priority aging mechanisms promote starved jobs to prevent unbounded waits. Examples of infeasibility include machine loads where the sum of processing times exceeds a fixed , violating bounds, or precedence constraints forming unavoidable cycles in no-wait settings; theoretical feasibility bounds, such as those derived from acyclicity conditions, guarantee existence only if machine utilizations fall below unity without conflicts. In contemporary cyber-physical systems integrating job-shop scheduling with , these scenarios extend to system crashes, where deadlocks trigger failures or violations, incurring infinite operational costs through ; recent models emphasize predictive avoidance to maintain in interconnected .

Advanced Topics

Theoretical Results

In the context of job-shop scheduling, foundational theoretical results begin with solvable special cases on a single machine. For the problem of minimizing the sum of completion times, denoted as $1 \parallel \sum C_i, the shortest processing time (SPT) rule—scheduling jobs in non-decreasing order of processing times—is optimal. This result, originally established by , ensures that any deviation from SPT increases the total completion time, as proven through pairwise interchange arguments showing that swapping longer and shorter jobs out of order leads to a higher value. A landmark complexity result is the strong NP-hardness of the job-shop makespan minimization problem for three or more machines, J3 \parallel C_{\max}. Garey, Johnson, and Sethi demonstrated this in 1976 by reducing from the 3-partition problem, showing that even with unit processing times on two machines and arbitrary times on the third, deciding if a schedule of length at most B exists is NP-complete. This establishes that no polynomial-time algorithm exists unless =, and the proof extends to general m \geq 3 machines. For the two-machine case J2 \parallel C_{\max}, the problem is solvable in polynomial time via dynamic programming. More broadly, for general m-machine job shops, inapproximability results show that no polynomial-time algorithm can achieve a constant factor better than certain thresholds; specifically, under standard complexity assumptions, the problem resists approximation ratios better than \ln m / \ln \ln m for large m, as derived from reductions involving label cover problems. These results underscore the inherent difficulty while guiding the development of logarithmic-factor approximations. Key lower bounds for the C_{\max} in general job-shop scheduling provide essential theoretical benchmarks for optimality. A fundamental bound is C_{\max} \geq \max\left\{ \max_{j} \sum_{o \in J_j} p_{j,o}, \max_{m} \sum_{j: o_{j,m} \exists} p_{j,m} \right\}, where the first term captures the longest job chain (total processing time per job) and the second the maximum machine load (total processing on each machine). These bounds are tight in like open shops with two machines, where an optimal always achieves equality. For large instances with n jobs and m machines, reveals that the makespan grows as \Theta(\max(n, m)) under uniform unit processing times, reflecting balanced load distribution in random instances. Recent theoretical advances up to 2025 explore quantum and average-case perspectives. Quantum algorithms, such as variational quantum eigensolvers and annealing-based methods, offer potential exponential speedups for small-scale job-shop instances by encoding permutations into states and minimizing via quantum optimization; for example, non-variational shallow-circuit approaches on NISQ devices solve 10x10 instances with errors under 10% compared to classical solvers. In 2025, further non-variational quantum methods improved efficiency for instances. In average-case , random job-shop instances exhibit phase transitions where difficulty peaks near critical densities (e.g., \rho \approx 1), with expected optimality gaps shrinking as O(1/\sqrt{n}) for uniform distributions, enabling probabilistic guarantees on solver performance. These developments bridge classical hardness with emerging computational paradigms.

Makespan Prediction Models

Regression-based approaches to makespan prediction in job-shop scheduling employ linear models that leverage aggregate instance features, such as the total processing time across all operations \sum p_{ij}, the number of jobs n, and the number of machines m. These models approximate the optimal makespan C_{\max} through equations of the form C_{\max} \approx \alpha \sum p_{ij} + \beta n m + \gamma, where coefficients \alpha, \beta, and \gamma are derived from regression on solved instances. Seminal work by Raaymakers and Weijters (2003) demonstrated the efficacy of such linear regression techniques in batch process industries akin to job shops, using features like average processing times and resource overlaps to estimate makespan with relative errors under 10% on simulated datasets. Machine learning methods extend these predictions by training on instances, such as Taillard's test sets, to capture nonlinear interactions. For instance, neural networks can ingest features extracted from disjunctive representations of the scheduling problem, including precedences and compatibilities, to forecast C_{\max}. Yildiz and Saygin (2022) developed a three-layer artificial neural network trained on Taillard instances (e.g., 15×15, 20×20 configurations), achieving average relative errors of 2.5–3.7% in compared to optimal solutions. Recent advancements incorporate , particularly neural networks (GNNs), which model the job shop as a disjunctive and predict makespan via message-passing that spatial-temporal dependencies. A survey by Wang et al. (2024) highlights GNN-based predictors, such as those using attention networks, attaining near-optimal estimates with optimality gaps of 6–20% on Taillard when integrated with imitation learning. Lower bound estimators provide quick approximations of the minimal possible , often serving as surrogates for relaxed integer linear programming formulations. surrogates, such as convolutional neural networks applied to matrix representations of instances, can predict these bounds efficiently; for example, the CONVJSSP model (Brahimi et al., 2021) uses CNNs to estimate optimal as a tight lower bound proxy, enabling faster branch-and-bound searches with mean squared errors low enough for practical acceleration. These estimators typically relax precedence and disjunctive constraints to yield feasible lower bounds like machine or job-based relaxations. Accuracy of these prediction models is evaluated using statistical measures, with neural network approaches often achieving R^2 > 0.95 on held-out test sets from benchmarks like Taillard, indicating strong explanatory power. Relative errors below 5% are common for mid-sized instances, though performance degrades for larger, highly constrained problems. Such predictions find applications in algorithm selection, where estimated guides the choice of exact or solvers—for instance, selecting over metaheuristics when predicted optima suggest tractability—thereby improving overall solving efficiency in hybrid frameworks.

Examples and Applications

Illustrative Example

To illustrate the concepts of job-shop scheduling, consider a small instance with three jobs (J1, J2, J3) to be processed on three machines (M1, M2, M3), where each job consists of a specific of operations with given times. The sequences and times are as follows:
JobOperation Sequence and Processing Times
J1M1 (3 units), M2 (2 units), M3 (2 units)
J2M1 (2 units), M3 (1 unit), M2 (4 units)
J3M2 (4 units), M3 (3 units)
This setup requires determining start times for each operation such that no two operations overlap on the same machine, operations within a job maintain precedence, and the makespan (C_max, the completion time of the last operation) is minimized. A feasible schedule achieving the optimal makespan of C_max = 11 can be constructed as follows, with start times for each operation:
  • J1: M1 starts at 0 (ends 3), M2 at 4 (ends 6), M3 at 6 (ends 8)
  • J2: M1 starts at 3 (ends 5), M3 at 5 (ends 6), M2 at 7 (ends 11)
  • J3: M2 starts at 0 (ends 4), M3 at 8 (ends 11)
This schedule can be visualized in a , where the horizontal axis represents time from 0 to 11, and bars indicate machine occupations:
  • M1: J1 (0-3), J2 (3-5); idle 5-11
  • M2: J3 (0-4), J1 (4-6), J2 (7-11); idle 6-7 and 11+
  • M3: J2 (5-6), J1 (6-8), J3 (8-11)
No overlaps occur on any machine, and job precedences are respected, confirming feasibility and C_max = 11 as the completion time of the last operation. In job-shop scheduling, deadlocks can arise from improper ordering, creating cyclic dependencies; for instance, if J1 occupies while waiting for (held by J2), and J2 waits for , a cycle forms that halts progress unless resolved by delaying one operation—this can be detected via the disjunctive representation for the instance. , designed for two-machine flow shops to minimize by sequencing jobs based on processing times, can be applied illustratively to a subset of this problem (e.g., considering only and across jobs, treating sequences as flow-like where possible), yielding a partial order that prioritizes jobs with shorter times on the first machine. A simple heuristic like the shortest processing time (SPT) dispatching rule... produces a suboptimal with C_max = 12—for example, by sequencing J1 first on all machines followed by J2 and J3, leading to unnecessary idle time on M3—highlighting the gap between s and the optimal solution verified via exact methods like branch-and-bound.

Real-World Implementations

Job-shop scheduling (JSSP) finds extensive application in environments, particularly in sectors requiring custom of components with varying specifications. In (PCB) assembly, JSSP models are used to sequence jobs across multiple assembly lines, accounting for different ready times and due dates to minimize delays and optimize throughput. For instance, scheduling micro-hole drilling operations in PCB involves optimizing complex event-based sequences to reduce setup times and improve efficiency. Similarly, in automotive parts , flexible JSSP addresses operational challenges like release dates and deadlines for injection-molded components, enabling better in dynamic settings. Software solutions such as Advanced Planning and Optimization (APO), particularly its /Detailed Scheduling (PP/DS) module, support JSSP by integrating finite and heuristic-based optimization for execution in these industries. In service-oriented sectors, JSSP adapts to resource-constrained environments like healthcare and high-tech fabrication. Hospital operating rooms exemplify this, where surgeries represent jobs and rooms or specialized equipment act as machines; generalized JSSP formulations allocate cases to minimize and maximize utilization while considering availability and durations. In semiconductor wafer fabrication, the process embodies a complex JSSP due to diverse processing steps, batching requirements, and time constraints between operations, with techniques like modified shifting heuristics applied to balance cycle time and due-date performance across hundreds of tools. Implementing JSSP in real-world settings faces significant challenges, including seamless integration with (ERP) systems for accurate data flow and the management of real-time disruptions such as machine breakdowns or order changes. Poor ERP-shop floor synchronization often leads to outdated schedules and conflicts, while dynamic events require adaptive rescheduling to maintain viability without excessive computational overhead. Case studies highlight practical adaptations. In , the (TPS), originally designed for flow lines, has been extended to job shops through lean principles like just-in-time and to level workloads and reduce variability in custom assembly. For airline maintenance, robust scheduling models treat heavy checks as jobs on specialized bays (machines), using genetic algorithms to generate long-term plans that buffer against disruptions and minimize downtime. Emerging trends as of 2025 emphasize integration in smart factories, where enhances JSSP by enabling predictive adjustments for high-mix environments, outperforming traditional in dynamic job shops through real-time optimization of priorities and capacities. Sustainable scheduling for green manufacturing incorporates multi-objective JSSP to minimize and carbon emissions alongside , often via algorithms like improved wolf pack optimization that account for time-of-use and learning effects in flexible setups.

References

  1. [1]
    [PDF] A Research Review on Job Shop Scheduling Problem
    At first, the job shop scheduling problem was studied as a mathematical problem, focusing on theory, mostly using the optimization methods of mathematics and.
  2. [2]
    [PDF] A computational study of the job-shop scheduling problem
    fact that a specific instance, with 10 machines and 10 jobs, posed in a book by Muth and Thompson[19] in 1963 remained unsolved for over 20 years. This ...
  3. [3]
  4. [4]
    [PDF] A Survey of Static Job Shop Scheduling Theory
    Apr 1, 1978 · state of theoretical knowledge in the area of static job shop scheduling. Specifically, the general problem to be addressed involves a given.
  5. [5]
    [PDF] An Efficient Approach to Job Shop Scheduling Problem using ...
    The static job shop-scheduling problem makes assumption that all jobs are available at the very beginning and the processing and set up times are.
  6. [6]
    [PDF] Chapter 1 A HISTORY OF PRODUCTION SCHEDULING
    Abstract: This chapter describes the history of production scheduling in manufacturing facilities over the last 100 years. Understanding the ways that ...
  7. [7]
    [PDF] Survey of Job Shop Scheduling Techniques
    Scheduling has been defined as "the art of assigning resources to tasks in order to insure the termination of these tasks in a reasonable amount of time" ...<|separator|>
  8. [8]
    Deterministic job-shop scheduling: Past, present and future
    This criterion has much historical significance and was the first objective applied by researchers in the early 1950s to the so-called easy problems which later ...
  9. [9]
    A Critical Analysis of Job Shop Scheduling in Context of Industry 4.0
    This paper aims to provide a comprehensive review of centralized and decentralized/distributed JSSP techniques in the context of the Industry 4.0 environment.
  10. [10]
    Real-time multi-factory scheduling in Industry 4.0 with virtual alliances
    Industry 4.0 integration in job shop systems provides advantages such as tracking and monitoring components of job shop systems in the shortest time (Kamble ...Missing: post- | Show results with:post-
  11. [11]
    [PDF] Mixed Integer Programming Models for Job Shop Scheduling
    Apr 18, 2016 · In this paper we present and evaluate four MIP formulations for the classical job shop schedul- ing problem (JSP). While MIP formulations for ...
  12. [12]
    On the Job-Shop Scheduling Problem | Operations Research
    ... Bowman, E. H. 1959 ... Mathematical modeling and two efficient branch and bound algorithms for job shop scheduling problem followed by an assembly stage.
  13. [13]
    (PDF) Job shop scheduling: Classification, constraints and objective ...
    Feb 8, 2020 · The job-shop scheduling problem (JSSP) is an important decision facing those involved in the fields of industry, economics and management.
  14. [14]
    The disjunctive graph machine representation of the job shop ...
    The disjunctive graph proposed by Roy and Sussman [9] is one of the most popular models used for describing instances of the job shop scheduling problem, which ...
  15. [15]
    The Disjunctive Graph Representation and Extensions - SpringerLink
    Balas, E., “Machine Sequencing via Disjunctive Graphs: An Implicit ... Balas, E., “Project Scheduling with Resource Constraints”, in Applications of ...
  16. [16]
    [PDF] CHAPTER 3 JOB SHOP SCHEDULING
    job shop scheduling problem. One ... where pij represents time of jth operation of ith job. The technological matrix and the processing time matrix P are.
  17. [17]
    Correlation of job-shop scheduling problem features with scheduling ...
    Nov 15, 2016 · In this paper, we conduct a statistical study of the relationship between Job-Shop Scheduling Problem (JSSP) features and optimal makespan.
  18. [18]
    6.1. The Job-Shop Problem, the disjunctive model and benchmark ...
    In the disjunctive graph, we have two kind of edges to model a feasible schedule: conjunctive arcs modelling the order in which each task of a job has to be ...Missing: seminal paper
  19. [19]
    Job shop scheduling - Optimization Wiki
    Dec 15, 2021 · The aim of the problem is to find the optimum schedule for allocating shared resources over time to competing activities.Introduction · Theory/Methodology/Algorithms · Methods · Job-Shop Scheduling...Missing: scholarly | Show results with:scholarly
  20. [20]
    [PDF] Job Shop Scheduling: Classification, Constraints and Objective ...
    From the mid-50s onwards, many researchers have been interested in expanding the theoretical models of the JSSP and have introduced algorithms to solve them.
  21. [21]
  22. [22]
    An efficient Pareto approach for solving the multi-objective flexible ...
    In this paper, a general local search approach for the Multi-Objective Flexible Job-shop Scheduling Problem (MOFJSP) is proposed to determine a Pareto front ...
  23. [23]
    Energy-efficient scheduling for a flexible job shop with machine ...
    Energy-efficient scheduling for a flexible job shop with machine breakdowns considering machine idle time arrangement and machine speed level selection.
  24. [24]
    Multi-Objectives Optimization Model for Flexible Job Shop ...
    Machines' workload balancing is important in production scheduling as it can eliminate bottleneck problem, maximize the output, and minimize the operating costs ...
  25. [25]
    Instance Configuration for Sustainable Job Shop Scheduling - arXiv
    Sep 12, 2024 · This research delves into the intricacies of JSP, focusing on optimizing performance metrics and minimizing energy consumption while considering various ...
  26. [26]
    Four decades of research on the open-shop scheduling problem to ...
    Dec 1, 2021 · In general, the open-shop problem concerns scheduling a set of jobs, each with a set of operations, on a set of different machines, where each ...
  27. [27]
    Dynamic job shop scheduling: A survey of simulation research
    This paper provides a state-of-the-art survey of the simulation-based research on dynamic job shop scheduling with a distinct emphasis on two important aspects.Missing: seminal | Show results with:seminal
  28. [28]
    Reactive scheduling in a job shop where jobs arrive over time
    Abstract. The paper considers the dynamic job shop scheduling problem (DJSSP) with job release dates which arises widely in practical production systems.Missing: seminal | Show results with:seminal
  29. [29]
    Finding Robust Solutions for the Stochastic Job Shop Scheduling ...
    Because of the flexibility of simulation, each stochastic variable can have its own probability distribution, and the variables do not have to be independent.
  30. [30]
    Open Shop Scheduling to Minimize Finish Time
    ABSTRACT A linear time algorithm to obtain a minimum finish time schedule for the two-processor open shop together with a polynomial time algorithm to ...<|separator|>
  31. [31]
    Complexity of Scheduling Shops with No Wait in Process
    We show that obtaining minimum finish time schedules with no wait in process is NP-Hard for flow shops, job shops and open shops. Specifically, it is shown ...
  32. [32]
    [PDF] Preemptive Job-Shop Scheduling using Stopwatch Automata
    In this paper we show how the problem of job-shop scheduling where the jobs are pre- emptible can be modeled naturally as a shortest path problem de ned on an ...
  33. [33]
    Job-shop scheduling with blocking and no-wait constraints
    With a blocking constraint a job, having completed processing on a machine, remains on it until the next machine becomes available for processing. A no-wait ...
  34. [34]
    An approach to job shop scheduling with sequence-dependent setups
    This paper addresses the job shop scheduling problem with release dates, due dates, and sequence-dependent setup times with the scheduling objective to ...
  35. [35]
    Scheduling in cloud manufacturing: state-of-the-art and research ...
    This article aims to provide a state-of-the-art literature survey on scheduling issues in cloud manufacturing.
  36. [36]
    Complexity of Machine Scheduling Problems - ScienceDirect.com
    After a brief review of the central concept of NP-completeness we give a classification of scheduling problems on single, different and identical machines and ...
  37. [37]
    [PDF] Sequencing and scheduling : algorithms and complexity - Pure
    Jan 1, 1989 · J.R. JACKSON (1956). An extension of Johnson's results on job lot scheduling. Naval Res. Logist. Quart. 3,. 201-203. [14.1]. J.M. JAFFE (1980A) ...
  38. [38]
    Structural parameters for scheduling with assignment restrictions
    Dec 6, 2020 · We introduce a graph framework based on the assignment restrictions and study the computational complexity of the scheduling problem with ...
  39. [39]
    [PDF] MINIMIZING THE MAKESPAN IN TWO-MACHINE JOB SHOP ...
    Abstract: This paper deals with two-machine job shop scheduling problems working under the no-idle constraint, that is, machines must work continuously ...
  40. [40]
    A polynomial-time algorithm for the two-machine unit-time release ...
    We consider a polynomial-time algorithm for the following scheduling problem: Given two machines, where each machine can process at most one job at a time; ...
  41. [41]
    A polynomial algorithm for the two machine job-shop scheduling ...
    Mar 1, 1994 · A fully polynomial time approximation scheme for scheduling on parallel identical two-stage openshops. Article 05 June 2018. Explore related ...
  42. [42]
    [PDF] Flow Shop - NYU Stern
    While the flow shop problem F2||Cmax with m=2 machines is solvable in polynomial time by. Johnson's algorithm, the problem F||Cmax with m≥3 machines is NP-hard.
  43. [43]
    Optimal two‐ and three‐stage production schedules with setup times ...
    A simple decision rule is obtained in this paper for the optimal scheduling of the production so that the total elapsed time is a minimum.
  44. [44]
    [PDF] Flow shops - Elements of Scheduling
    Johnson gave an O(nlogn) algorithm to solve F2||Cmax. The algorithm is surprisingly simple: first arrange the jobs with p1j ≤ p2j, in order of nondecreasing p1j ...
  45. [45]
    [PDF] a descriptive proof for johnson's - algorithm for solving two-machine
    This paper shows a demonstrative proof of Johnson's algorithm to the problem F2||Cmax. By the help of the applied method an algorithm can be formed to solve ...
  46. [46]
    [PDF] A New Approach to Computing Optimal Schedules for the Job Shop ...
    The job shop scheduling problem is NP hard and has proven to be very difficult even for relatively small instances An instance with jobs and machines posed ...
  47. [47]
    The flexible job shop scheduling problem: A review - ScienceDirect
    Apr 16, 2024 · The flexible job shop scheduling problem (FJSP) is an NP-hard combinatorial optimization problem, which has wide applications in the real world.
  48. [48]
    [PDF] Heuristics for Job-Shop Scheduling - DTIC
    Aug 2, 2025 · In this algo- rithm, dynamic programming along with a partial-order decomposition allows exact solution of sequencing problems with worst case ...<|separator|>
  49. [49]
    Online scheduling of ordered flow shops - ScienceDirect.com
    Jan 1, 2019 · We consider online as well as offline scheduling of ordered flow shops with the makespan as objective. In an online flow shop scheduling problem, jobs are ...
  50. [50]
    Automatically evolving preference-based dispatching rules for multi ...
    Apr 29, 2023 · Dispatching rules represent a simple heuristic for finding good solutions for job shop scheduling problems. Due to their fast applicability ...
  51. [51]
    Randomized approximation schemes for minimizing the weighted ...
    Mar 31, 2024 · The objective is to minimize the weighted makespan of jobs, i.e., the maximum weighted completion time of jobs. This scheduling problem is a ...
  52. [52]
    A Genetic Algorithm for Job Shop Scheduling with Load Balancing
    Aug 7, 2025 · This paper deals with the load-balancing of machines in a real-world job-shop scheduling problem with identical machines. The load-balancing ...
  53. [53]
    Incorporating a starvation avoidance trigger into continuous release
    These methods use the starvation avoidance trigger, to avoid premature workstation idleness, in combination with the new breed of continuous release methods ...
  54. [54]
    New complexity results for shop scheduling problems with ...
    Oct 8, 2021 · The optimal schedule is obtained by searching a maximum matching in the constructed bipartite graph. We denote this algorithm by Algorithm 2. ...
  55. [55]
    Novel robotic job-shop scheduling models with deadlock and robot ...
    A deadlock appears if the single robot delivers a product A to a destination machine while that machine is occupied by another product B. Since only one robot ...
  56. [56]
    The Complexity of Flowshop and Jobshop Scheduling - PubsOnLine
    In this section we will briefly describe the process of proving that a problem is NP-complete, and then illustrate the technique on the 3-machine flowshop ...Missing: hard | Show results with:hard
  57. [57]
    [PDF] Chapter 11 - Elements of Scheduling
    Problem O||Cmax is NP-hard in the strong sense. Proof. The proof is a polynomial time reduction from the 3-PARTITION problem, which is NP-complete in the strong ...
  58. [58]
    An improved approximation algorithm for the two-machine ... - HAL
    For this NP-hard problem the literature contains (5/4)-approximation algorithms that cannot be improved on using the class of group technology algorithms in ...
  59. [59]
    Hardness of Approximating Flow and Job Shop Scheduling Problems
    On minimizing average weighted completion time: A PTAS for the job shop problem with release dates. ... We study the approximability of two natural NP-hard ...
  60. [60]
    Evaluating the job shop scheduling problem on a D-wave quantum ...
    Apr 21, 2022 · This paper studies the application of quantum annealing to solve the job shop scheduling problem, describing each step required from the problem formulation to ...Quantum Annealing On A... · Job Shop Scheduling · Classical Job Shop...
  61. [61]
    [PDF] How the Landscape of Random Job Shop Scheduling Instances ...
    The connection between a schedule and its disjunctive graph is established by the following proposition (Roy & Sussmann, 1964). Proposition 1. Let S be a ...
  62. [62]
    [PDF] Development of a Neural Network Algorithm for Estimating the ...
    Oct 10, 2022 · This study develops a neural network to produce an optimal or near-optimal solution for job shop scheduling, which is a complex, NP-hard ...
  63. [63]
    The Job Shop Problem | OR-Tools - Google for Developers
    Aug 28, 2024 · The job shop scheduling problem involves optimizing the allocation of machines to tasks within multiple jobs to minimize the total ...
  64. [64]
    Solving the Job Shop Problem using Google's OR-Tools - LinkedIn
    Nov 11, 2019 · In this example an improved solution resulting in a makespan of 11 vs 12 was found. No alt text provided for this image. Businesses using ...