MAX Blue Line

The MAX Blue Line is a route operated by , the public transit agency serving the in , extending from Hillsboro in the west through Beaverton, City Center, and East Portland to Gresham in the east. It provides service every 15 minutes or better most of the day, every day, linking residential suburbs, commercial districts, and major employment hubs across a corridor spanning the region's primary east-west axis. The line utilizes dedicated rights-of-way, street-level tracks, and a under the West Hills, accommodating high-capacity Bombardier and vehicles that operate at speeds up to 55 mph in non-street segments. Originally launched as the Eastside MAX on , 1986—one of the earliest systems —the 15-mile segment connected Portland's downtown to Gresham and quickly surpassed projected ridership, demonstrating the viability of rail transit revival in American cities. The Westside extension, completed in 1998, added 18 miles and 22 stations to reach Hillsboro, incorporating engineering feats such as twin tunnels through the West Hills and elevated sections over highways, at a cost of $963 million. This full-length Blue Line has since anchored TriMet's MAX network, facilitating over 100,000 daily boardings pre-pandemic and supporting regional economic integration without notable systemic failures in its core infrastructure.

Historical Development

Origins in Freeway Opposition and Early Planning

In the early 1970s, faced significant public opposition to proposed freeway expansions, particularly the Mount Hood Freeway, which had been planned since 1955 to connect through southeast neighborhoods to Interstate 205 and eastern suburbs. Granted interstate status in 1969, the project encountered grassroots resistance starting around 1972, driven by concerns over the demolition of over 1,700 homes, neighborhood disruption, environmental degradation, and escalating costs, amid broader national freeway revolts and federal clean air mandates. Key figures including Mayor , Multnomah County Commissioners Don Clark and Mel Gordon, and Governor mobilized against it, leading to a county moratorium on right-of-way acquisitions in November 1972. The opposition culminated in legal and political victories: a U.S. District Court ruling on February 4, 1974, deemed the route illegal under environmental laws, followed by the City Council's withdrawal of support on July 25, 1974. Governor Robert Straub formally requested its removal from the interstate system in July 1975, securing federal approval and cancellation in May 1976. This freed approximately $300 million in federal funds originally allocated for the freeway, which were redirected toward alternative transportation investments, reflecting a regional shift away from highway-centric planning—evident in the 1975 adoption of an interim plan rejecting 54 highway projects valued at $2 billion (in 1969 dollars)—toward mass transit to address congestion and air quality without further urban disruption. With the Mount Hood Freeway scrapped, attention turned to the Banfield Freeway corridor (Interstate 84) for transit improvements. In 1976, this alignment was prioritized for a transitway as a lower-impact alternative to new freeway . Initial studies considered a bus-only transitway, but input and jurisdictional decisions in 1979 selected as the preferred mode, leveraging existing rail rights-of-way and aiming to integrate with highway expansions for multimodal capacity. Federal approval followed in 1980, setting the stage for to begin in 1982, with the Eastside line—later designated the MAX Blue Line—opening in September 1986 at a cost of $214 million (1978 dollars), 83% funded by the repurposed federal freeway allocation.

Eastside Line Construction and Inauguration

The Eastside segment of the MAX Blue Line, extending 15 miles from Portland's City Center to Gresham, entered the construction phase in March 1982 following years of planning as an alternative to freeway expansion along the Banfield corridor. The project involved building dedicated , including at-grade tracks, an elevated over Interstate , and integration with existing in urban areas, with work progressing in phases starting with right-of-way preparation and utility relocation. Federal funding from the Urban Mass Transportation Administration covered approximately 75% of costs, supplemented by state and local contributions, enabling procurement of 26 Bombardier vehicles for the initial fleet. Construction faced logistical challenges such as coordinating with active highway traffic near the Banfield Freeway and minimizing disruptions in dense neighborhoods, yet proceeded on schedule due to phased staging that began trackwork in Gresham later in 1982. The total project cost reached $214 million, reflecting investments in signaling systems, stations with basic amenities, and bridges like the one over the Sandy River Boulevard interchange. By mid-1986, testing of the fully assembled line confirmed operational readiness, marking it as one of the earliest postwar systems in the United States. The line's inauguration occurred on September 5, 1986, with revenue service commencing between 27 stations under the name Metropolitan Area Express (MAX), drawing initial ridership of over 20,000 passengers on opening day. Ceremonial events included ribbon-cutting by local officials and demonstration runs, highlighting the system's role in regional transit expansion amid opposition to further automobile infrastructure. This opening established the backbone for TriMet's network, with the Eastside alignment later designated as the Blue Line following subsequent extensions.

Westside Extension Delays, Funding, and Opening

Planning for the Westside extension of the MAX Blue Line began in 1979, with alignment along selected by 1983, but the project stalled due to funding uncertainties until resuming in 1988 following the success of the Eastside line. Voters approved a local bond measure in 1990 to support regional funding, enabling federal commitment from the . The total project cost reached $963.5 million, financed by 73% federal funds ($704.1 million), 12% state transportation funds ($113.6 million), and 15% regional and local sources ($145.8 million). Construction commenced in July 1993, incorporating a 3-mile twin-tube tunnel under the West Hills to address steep grades. Tunnel boring encountered delays from fragmented rock formations, necessitating equipment modifications between 1993 and 1997, though TriMet reported overall completion on schedule and within budget. The extension opened in phases due to these tunneling challenges: an initial segment from downtown Portland's 11th Avenue to the Goose Hollow area (Kings Hill/Southwest Salmon Street station) began service in 1997, with full operations to Hillsboro commencing on September 12, 1998, spanning 18 miles and adding 20 new stations. This completed the 33-mile Blue Line from Hillsboro to Gresham.

Subsequent Improvements and Maintenance Efforts

Following the 1998 opening of the Westside extension, implemented ongoing track rehabilitation projects to address wear from high usage, including replacement of , and switches along the Blue Line corridor. In May 2021, crews completed a multi-week maintenance effort east of the , rebuilding sections of rail to enhance durability and reduce service disruptions. Similarly, in August 2020, upgraded track, switches, and signaling on the 108-year-old , a critical crossing shared by Blue Line trains, to improve operational reliability and prevent failures from aging infrastructure. Vehicle fleet modernization has been a priority to replace aging low-floor cars introduced in the late 1990s and early 2000s. In March 2025, began deploying Type 6 light rail vehicles, the first new models in over a decade, with 30 units scheduled for service integration to supplant older Type 5 cars prone to mechanical issues, thereby boosting capacity and energy efficiency on the Blue Line. Each new train undergoes a 5,000-mile operational testing phase on the system before full deployment. Recent targeted upgrades in 2025 focused on the Eastside segment, where a two-week closure east of Gateway/NE 99th Ave. Transit Center in late March to April allowed replacement of overhead wiring (approximately 8,000 feet), rail crossings, and equipment upgrades for enhanced durability and signaling. In mid-October 2025, a two-part project near Cascades Station involved curved rail replacement, tie substitutions, deep cleaning of stations and tracks, and litter removal to mitigate degradation from environmental exposure and traffic volume. These efforts reflect 's of periodic shutdowns for proactive , prioritizing and minimizing long-term downtime over reactive repairs. Station-level interventions, such as accessibility enhancements and signage updates, have complemented track work to sustain ridership amid growing demand.

Route and Infrastructure

Line Alignment and Key Stations

The MAX Blue Line follows a primarily east-west alignment spanning 33 miles (53 km) from Hatfield Government Center station in Hillsboro to Cleveland Avenue station in Gresham, serving , Multnomah, and Clackamas counties. The western segment traverses suburban areas along Tualatin Valley Highway and Beaverton-Hillsboro Highway before aligning with east of Beaverton, utilizing at-grade tracks and dedicated medians. Entering , the route descends into a 3-mile tunnel under Washington Park, emerging to connect with downtown via surface streets and the over the . East of , the line parallels the Banfield Freeway (Interstate ) through East , incorporating elevated guideways, street-level sections, and cuts to navigate urban and semi-rural terrain toward Gresham. This corridor supports regional connectivity, with infrastructure designed for high-capacity operation amid varying land uses from industrial parks to residential neighborhoods. The alignment integrates with highways to minimize conflicts while providing access to employment centers and districts. The line serves 51 stations, including several major hubs with park-and-ride lots exceeding 1,000 spaces combined at sites like Hatfield Government Center and Gresham Central Transit Center. Key stations include:
  • Hatfield Government Center: Western terminus in Hillsboro, featuring extensive park-and-ride facilities and connections to local buses.
  • Hillsboro Airport/Fairgrounds: Provides access to the Hillsboro Airport and annual events, with park-and-ride availability.
  • Sunset Transit Center: Major westside hub near Washington County offices, serving commuters with bus transfers.
  • Washington Park: Tunnel portal station offering pedestrian links to the Oregon Zoo, International Rose Test Garden, and science museum.
  • Pioneer Square: Central Portland transfer point in the business district, integrating with Red and Green lines.
  • Gateway/NE 99th Avenue Transit Center: Eastside interchange for buses and Yellow Line, near retail corridors.
  • Gresham Central Transit Center: Eastern hub with bus connections and park-and-ride, preceding the terminus.
  • Cleveland Avenue: Eastern terminus in Gresham, supporting local access without extensive parking.

Engineering Features and Technical Specifications

The MAX Blue Line spans miles from Hillsboro to Gresham, incorporating the 15-mile Eastside segment along the Banfield Freeway (I-84) and an 18-mile Westside extension through Beaverton and the Tualatin Mountains. The route features a mix of at-grade, elevated, and underground alignments, with double track throughout to support bidirectional service. Electrification is provided by a 750-volt overhead system, utilizing a single contact wire in downtown to reduce visual clutter, while dual-wire (contact and messenger wires) is employed elsewhere. Traction power substations are spaced approximately one mile apart, designed to maintain service during a single substation failure. Signaling employs an Automatic Block System (ABS) with three-aspect wayside signals and Automatic Train Stops (ATS) on 70% of the line for overspeed protection, enabling design headways as low as 2 minutes 45 seconds in key sections. Key infrastructure includes the 3-mile twin-bore Robertson Tunnel beneath the West Hills, consisting of two 21-foot-diameter bores (19 feet finished), excavated via drill-and-blast methods and a 278-foot tunnel-boring machine, with cross passages every 750 feet and maximum train speeds of 55 mph. The line traverses the Willamette River on the upper deck of the Steel Bridge, accommodating two trackways and featuring a 7% approach grade on the west side. Other notable elements encompass 48 at-grade gated crossings equipped with lights, bells, and ATS enforcement near stations, as well as maximum grades of 6% over extended segments near Highway 217 and in the West Hills. The Eastside alignment includes widened freeway shoulders and reserved downtown lanes with traffic preemption systems to optimize flow.

Integration with Transit-Oriented Development

The MAX Blue Line has integrated with (TOD) primarily through coordinated planning around its stations, emphasizing compact, mixed-use communities that prioritize pedestrian access and high-quality transit connectivity to reduce reliance on personal vehicles. This approach aligns with regional strategies by and , which define TOD as walkable, pedestrian-oriented neighborhoods centered on frequent rail service. Along the Westside extension, opened on September 12, 1998, undeveloped land near stations attracted master-planned projects that incorporated residential, commercial, and office spaces within walking distance of platforms. Orenco Station in Hillsboro exemplifies successful TOD integration, encompassing a 209-acre master-planned community developed in tandem with the line's extension. The area features approximately 1,800 homes, including single-family residences and apartments, alongside a town center with ground-floor retail, offices, and upper-level housing to foster daily activity without automobile trips. Additional parcels support shopping centers and connect to nearby employment in the , with design standards enforcing narrow streets, reduced setbacks, and direct paths to the . Further west in Beaverton, projects like The Round at Beaverton near stations such as Beaverton Creek have advanced similar principles, adding mixed-use density in station vicinities to capitalize on 15-minute-or-better service frequencies. On the Eastside, TOD has focused on revitalization, as seen at Hollywood/NE 42nd Avenue Station, where recent upgrades, including a new pedestrian ramp completed in November 2024, support emerging residential developments adjacent to the line. These efforts have collectively generated substantial private investment, with stations alone spurring over $1 billion in related construction by leveraging the Blue Line's reliability and regional connectivity.

Operations and Service Characteristics

Rolling Stock and Fleet Management

The MAX Blue Line utilizes light rail vehicles (LRVs) drawn from TriMet's shared fleet across all MAX lines, enabling flexible deployment based on maintenance needs and service demands. This fleet historically included high-floor Type 1 vehicles manufactured by Bombardier Transportation between 1983 and 1986 for the line's 1986 inauguration, but these 40-year-old cars are undergoing retirement starting in 2024 to address aging infrastructure and improve reliability. Subsequent expansions incorporated low-floor designs, such as Type 2 and Type 3 SD600 LRVs added in 1997 for the Westside Extension, which facilitate better . Type 4 and Type 5 vehicles, both S70 models, were introduced from 2007 onward, with 18 Type 5 units specifically acquired for the 2015 Portland-Milwaukie project, bringing the total fleet to 145 LRVs at that time; these offer enhanced capacity with eight additional seats per two-car consist compared to earlier types. In July 2019, ordered 30 S700 Type 6 LRVs to replace retiring Type 1 cars and support expansions like the extension, with deliveries commencing in 2023 and revenue service beginning in early 2025. These modern vehicles measure 96 feet 11 inches in length, matching Type 5 dimensions, and incorporate advanced technology for efficiency, including digital systems for to minimize downtime. Fleet management emphasizes state-of-good-repair practices, including regular inspections, component overhauls, and preventive at facilities like the Ruby Junction Maintenance and Operations Center, which handles light repairs, HVAC servicing, and rebuilds for the entire LRV inventory. conducted a comprehensive overhaul program starting in 2019 to sustain performance and safety across the fleet. achieved 99.8 percent completion of preventive maintenance work orders in 2023, reflecting robust operational oversight. Integration of IoT-based monitoring further enables , shifting from reactive to proactive repairs.

Scheduling, Frequencies, and Daily Operations

The MAX Blue Line provides service seven days a week, spanning approximately 22–23 hours daily on weekdays. Trains begin departing from the Gresham terminus (Cleveland Avenue station) around 4:10 a.m. westbound and arrive at the Hillsboro terminus (Hatfield Government Center) by early morning, with eastbound service from Hillsboro starting similarly early; the final eastbound train from Hillsboro departs after midnight, reaching Gresham around 1:00 a.m., while westbound service from Gresham ends around 12:00 a.m. Service frequencies are designed for reliability under TriMet's Frequent Service designation, with headways of or less during most daytime hours every day, including periods (typically 7:00–9:00 a.m. and 3:00–6:00 p.m.), when intervals may shorten further due to shared trackage with and lines in central . Off-peak daytime headways remain at approximately , though early morning, late evening, and overnight periods extend to 30 minutes or more to align with lower demand. Weekend schedules follow a comparable structure but with reduced span, starting around 5:00 a.m. and concluding by , and uniform 15-minute headways during core hours to support consistent . publishes detailed timetables online, updating them periodically—such as minor shifts of up to 8 minutes in August 2025—to optimize operations and respond to ridership patterns. Daily operations emphasize punctuality and adaptability, with real-time arrival information available via the TransitTracker app and website; disruptions from events like closures or trigger alerts, potential , or bus (bus bridges) to maintain . Crewed by trained operators, trains adhere to signal systems and automated controls for safe passage over the 26-mile route, with overnight periods dedicated to track inspections and minor repairs. The MAX Blue Line consistently ranks as TriMet's highest-ridership service, reflecting its extensive span across key suburban and urban corridors. Weekday boardings averaged approximately 25,000 in mid-2025, with monthly figures showing modest variability amid ongoing post-pandemic recovery. Overall system trends indicate MAX ridership remains down roughly one-third from pre-pandemic levels, with partial rebound driven by resumed commuting and events but constrained by persistence and economic factors. Historical patterns demonstrate growth following the 1998 Westside extension, which boosted capacity and connectivity, leading to pre-2010 weekday averages exceeding 60,000 boardings on the Blue Line. The caused a precipitous drop, with system-wide MAX boardings falling over 50% in 2021 from 2019's 38.8 million annual total, and Blue Line usage following suit due to reduced travel. Recovery has accelerated since 2022, with FY2025 MAX boardings reaching 22.8 million annually—a 5.9% increase from FY2024—but still below historical peaks, signaling incomplete return to prior demand. Specific 2025 weekday averages for the Blue Line illustrate this stabilization:
MonthAverage Weekday Boardings
May 202525,019
June 202526,302
July 202527,182
August 202525,845
September 202524,380
Performance metrics emphasize operational reliability, with on-time (OTP) for MAX lines—including the —typically ranging 79-82% in recent quarters, below TriMet's 88% due to signal issues, maintenance, and track conflicts. For example, MAX OTP stood at 79.6% in May 2025 and 80.2% in July 2025, reflecting steady but suboptimal adherence amid upgrades. Labor productivity and cost-per-ride metrics, tracked system-wide, further highlight efficiency challenges, with Blue Line operations benefiting from high utilization yet facing capacity strains during peak hours.

Financial and Economic Dimensions

Construction and Capital Costs

The MAX Blue Line originated with the Eastside segment, constructed from March 1982 to August 1986 at a total capital cost of $214 million in then-year dollars, encompassing infrastructure and associated Banfield Freeway (I-84) widening. This funding derived primarily from federal sources amounting to 83% ($178.3 million), reallocated from the terminated Mt. Hood Freeway project, supplemented by 17% state and local contributions ($35.7 million total). The project marked one of the earliest modern implementations in the United States, prioritizing existing rail rights-of-way to minimize new land acquisition expenses. The Westside extension, adding 18 miles from downtown to Hillsboro, underwent construction starting in July 1993, with tunnel boring from 1993 to 1997 and track laying from 1994 to 1998, culminating in on September 12, 1998. reached $963.5 million, financed through federal grants ($704.1 million), state allocations ($113.6 million), and regional/local funds ($145.8 million), following voter approval of a 1990 bond measure. Delays in tunnel construction elevated expenses beyond initial projections, though the alignment leveraged surface rights-of-way where feasible to contain costs relative to full underground alternatives. Combined, these phases established the Blue Line's core infrastructure at approximately $1.18 billion in nominal terms across eras, with federal funding dominating both to leverage interstate highway trust reallocations amid 1970s-1980s urban freeway opposition. Subsequent minor capital outlays for stations and integrations have been incremental, not altering the foundational expenditures.

Operating Expenses, Subsidies, and Funding Mechanisms

The operating expenses for the MAX light rail system, of which the Blue Line forms the longest and highest-ridership segment spanning approximately 33 miles from Hillsboro to Gresham, are aggregated within TriMet's Rail Transportation and Rail Maintenance divisions rather than delineated per line. In fiscal year 2026 (FY2026), the Rail Transportation Department's operating budget totals $39.7 million, consisting primarily of $38.1 million in personnel services for operators and support staff, with materials and services at $1.5 million; this represents a 3.2% increase from $38.5 million in FY2025. Rail maintenance expenses add significantly, with Rail Equipment Maintenance budgeted at approximately $40 million and Rail Maintenance of Way at $26 million in FY2025 figures, driven largely by labor costs for vehicle upkeep, track inspections, and electrification systems, reflecting the aging infrastructure of lines operational since 1986. Overall, light rail operating costs per boarding have risen, reaching an average of $7.60 system-wide for fixed-route services in July 2025, up 9.2% from the prior year, amid personnel-driven inflation and maintenance demands on a fleet averaging over 20 years old. Subsidies constitute a substantial portion of funding, with federal operating grants totaling $19.2 million in FY2026 for debt service and enhancements, supplemented by $147.5 million in broader federal allocations including Sections 5307 and 5337 formulas that indirectly support MAX operations. State subsidies via the Statewide Transportation Improvement Fund (STIF) provide $83.7 million in FY2026, earmarked for service reliability and low-income fare programs that reduce revenue recovery from passengers. These subsidies offset the low , where passenger revenues cover only about 6% of fixed-route costs, necessitating taxpayer support to sustain operations amid post-pandemic ridership below 2019 levels. Funding mechanisms for Blue Line operations rely heavily on TriMet's 0.8237% regional payroll tax on wages over $1,000 monthly, generating $555 million or 49% of FY2026 operating revenues across fixed routes, a stable local mechanism established by voter approval in 1969 and adjusted periodically for inflation. Passenger fares, collected via the Hop system, contribute $62.7 million or 6%, with discounts and subsidies further eroding direct recovery. Remaining funds derive from federal and state grants (combined 20-25%), bond proceeds for capital debt service, and minor local contributions, enabling TriMet to allocate 47% of its $918 million day-to-day operating requirements to fixed-route services including light rail; however, escalating personnel costs—up 11.5% to $509.8 million system-wide in FY2026—have prompted efficiency measures and service adjustments without proportional revenue growth.

Broader Economic Impacts and Cost-Benefit Assessments

The MAX Blue Line has been associated with significant (TOD) in station areas, with reporting over $8 billion in new construction across stations since the line's opening in 1986, including mixed-use projects adding thousands of units and commercial square footage. Specific to the Blue Line's 33-mile corridor, approximately $6.6 billion in TOD investment has occurred, yielding $3.74 in per dollar of transit . However, much of this growth stems from non-transit factors, such as Portland's , high-density zoning overlays, tax abatements like the Multiple-Unit Limited program, and broader investments, rather than the rail line serving as a primary catalyst. Property values near Blue Line stations have shown premiums attributable to transit accessibility, with empirical analysis indicating positive effects on single-family home values and a 0.65 higher floor-area ratio in station areas compared to surrounding zones, equating to an additional 650 square feet of building per 1,000 square feet of land. These uplifts are most pronounced for the initial alignment but tend to dissipate over time, with subsequent expansions yielding unless separated by at least 15 years. Redevelopment rates in Blue Line station areas exceed non-station corridors by 69%, particularly for low- and moderate-value lots, though gentrification risks and displacement have been noted in projects near stations like Killingsworth. Employment impacts from the Blue Line remain limited and inconclusive, with case studies of Portland's system finding no clear causal link to job growth in retail, knowledge, or service sectors along corridors, and only modest long-term effects in select areas like the . Broader claims of economic stimulus, such as reduced vehicle miles traveled or benefits, have been critiqued for overstating rail's role amid competing urban policies. Cost-benefit assessments specific to the Blue Line are sparse, with analyses for related extensions like the Westside segment employing benefit-cost frameworks that quantify cumulative benefits in and values but often lack disclosure of ratios below 1.0 after for costs. Pro-transit sources assert returns like 5:1 from transit investments regionally, yet independent reviews highlight that rarely generates sufficient ridership or spillover effects to offset high capital and operating costs without heavy subsidization, with Portland's system exemplifying modest net benefits overshadowed by policy-driven development. Skeptical evaluations emphasize that while improves, economic multipliers are attenuated by factors like fare recovery rates below 25% and reliance on non-transit incentives for observed growth.

Safety, Security, and Public Concerns

Crime Statistics and Incident Patterns

TriMet's system, including the MAX Blue Line, records crime incidents at rates low relative to ridership volume, with approximately 1,247 reported s system-wide in amid nearly 99 million trips, equating to roughly 1.26 incidents per 100,000 boardings. The majority of these—about 588—occurred on rail lines like the Blue Line, compared to 343 on buses and 316 at facilities. Among rider-targeted offenses that year, 733 involved customers, comprising 532 property crimes (predominantly theft from person or unattended items), 188 assaults or intimidations, and 12 sex offenses. Recent trends show a contraction in reported police calls for service, declining 14% from 2021 to 2022 to around 7,300 agency-wide, and nearly halving overall by 2024, potentially reflecting reduced ridership during the period or shifts in reporting practices amid national transit spikes followed by partial recoveries. characterizes serious criminal events as infrequent, noting one police response per substantial weekly ridership volume exceeding 1.3 million trips across modes. However, violent incidents on MAX trains, including the Blue Line, have persisted at notable levels, with patterns favoring assaults and stabbings often described as unprovoked or involving transient populations. Specific to the Blue Line, which traverses high-density corridors from Hillsboro through downtown to Gresham, documented cases include a 2023 stabbing of two juveniles in the Lents neighborhood, resulting in an 18-year sentence for the perpetrator; a March 2024 fatal of a 51-year-old rider; an 2024 unprovoked lethal in Northeast ; and a mid- 2024 deadly shooting at an East Burnside station. Other patterns encompass sexual assaults at stations, such as a 2023 incident involving an unconscious visitor, and drug-influenced behaviors contributing to disruptions. Incidents cluster at urban stops like Gateway/Transit Center (historically 72 reports in 2010 data) and Northeast areas, with assaults comprising a larger share post-2020 amid broader fluctuations that saw temporary elevations before a 17% citywide drop in 2025. Rider surveys underscore a disconnect between aggregate statistics and experiential safety, with only 42% rating MAX as safe (score of 5+ on a 7-point scale) in 2024, down from prior years, and 82% of users attributing unease primarily to disruptive behaviors by fellow passengers, including visible drug use and aggression. Detailed annual crime breakdowns segmented by Blue Line remain limited in public disclosures, which prioritize injury targets (e.g., under 1.9 injuries per million revenue miles for ) over criminal categorizations, potentially obscuring granular patterns tied to line-specific demographics and routing through higher-risk zones.

Major Safety Incidents and Response Measures

On November 15, 2023, a westbound MAX Blue Line collided with a northbound at Northeast Weidler Street and Boulevard near , causing the train to derail partially off the tracks. The incident injured two individuals—the train operator and a streetcar passenger—with minor injuries requiring hospital transport, and resulted in temporary service disruptions across multiple MAX lines. Investigations attributed the crash to the streetcar failing to yield at a signal, highlighting signaling and priority issues in shared transit corridors. Pedestrian collisions have accounted for numerous fatalities on the Blue Line, often involving trespassers bypassing barriers or ignoring signals. On November 12, 2024, a 61-year-old , , was struck and killed by an eastbound Blue Line train near East Burnside Street and Southeast 141st Avenue while working on a nearby project, prompting a review of site safety protocols around active tracks. Earlier, on June 18, 2025, a bicyclist died after crossing track barriers into the path of a Blue Line train around 1:30 p.m., underscoring persistent challenges with unauthorized track access. In May 2023, two separate pedestrian strikes on the Outer East Portland segment of the line resulted in one death, with reports noting victims entering tracks against active warnings. TriMet has implemented response measures including expanded blue-light emergency call stations along the eastside MAX corridor, which connect riders directly to dispatchers and have correlated with reduced reported security incidents at equipped sites. The agency launched a Safety Response Team in 2021, deploying unarmed specialists to address non-violent disruptions, alongside a unified opened in 2024 for real-time monitoring and faster incident response via integrated cameras and reports. In October 2025, Police rejoined 's transit policing efforts after a 2020 hiatus, aiming to bolster enforcement amid lingering post-pandemic crime spikes on public transit, though rider safety perceptions remain mixed with 41% rating MAX experiences below average. also conducts periodic emergency drills, such as a 2023 exercise simulating MAX disruptions, to refine coordination with .

Debates on Social and Operational Efficacy

Critics of the MAX Blue Line's operational efficacy point to chronic delays caused by at-grade street crossings, the , and the Rose Quarter Transit Center, which bottleneck service and contribute to monthly on-time varying between 60% and 100%. These issues have persisted since the line's 1986 opening, with recent examples including two-week service disruptions for maintenance in April 2025 and heat-related delays of 15-30 minutes during summer peaks. Proponents counter that such supports with urban fabric, but empirical data shows average speeds remain low—often under 20 mph in city sections—limiting capacity compared to dedicated rail alternatives. On social efficacy, debates focus on the line's ability to foster equitable amid challenges that deter ridership, particularly among women and non-regular users. Surveys indicate 48% of MAX riders felt unsafe in , with 82% attributing this to disruptive behaviors like open use and , including stabbings and assaults reported on trains. Trace fentanyl and residues detected on 100% of sampled train surfaces in 2023, though deemed non-harmful by experts, exacerbate perceptions of uncleanliness and insecurity. While the line connects underserved eastside communities to jobs, enhancing for low-income groups per analyses, critics argue these benefits are undermined by losses exceeding $70 million annually and fare-free policies that correlate with increased , reducing appeal for working-class riders. Broader efficacy debates weigh capital-intensive against alternatives, with studies showing buses achieving comparable ridership at lower costs in low-density corridors like the Blue Line's extensions. System-wide ridership in May 2025 stood at levels 3.5% above prior year but roughly two-thirds of 2019 peaks, fueling arguments that operational subsidies—averaging $10-18 per boarding ride—fail to deliver promised congestion relief or economic multipliers without denser land-use policies. Supporters cite station-area densities post-investment as evidence of induced growth, yet independent assessments highlight cost overruns and ridership shortfalls typical of U.S. rail projects, questioning causal links to gains amid persistent auto dominance. Equity-focused reports acknowledge displacement risks from near stations, recommending mitigation but noting limited empirical proof of net .

Future Directions

Ongoing and Planned Upgrades

TriMet's Eastside MAX Improvements Project, launched in mid-October 2025, encompasses rail infrastructure renewal, station enhancements, and safety modifications along the Blue Line's eastside corridor between the Rose Quarter Transit Center and Gateway/NE 99th Avenue Transit Center. This two-part initiative includes a week-long closure for track work, overhead wiring replacements, and platform upgrades, with shuttle bus service substituting for trains during disruptions to minimize rider impact. Preceding this, in September 2025, completed a focused upgrade within the Robertson Tunnel on the Blue Line's westside segment, replacing approximately one mile of overhead wire, installing a modern tensioning system to enhance wire reliability, and renewing about 700 feet of track to address wear and improve operational smoothness. Earlier in the year, from April 27 to May 10, 2025, crews performed track resurfacing, switch replacements, and vegetation clearance east of Gateway/NE 99th Avenue Transit Center, aiming to extend asset lifespan and reduce future maintenance needs. Station-specific upgrades are scheduled for completion by the end of 2025, featuring rebuilt stairways, refurbished shelters, improved sight lines, and added guardrails at select Blue Line stops to bolster pedestrian safety and accessibility. These efforts form part of TriMet's broader rail revitalization strategy, prioritizing deferred maintenance on aging infrastructure dating back to the line's opening and subsequent extensions. No major capacity expansions or vehicle fleet overhauls specific to the Blue Line have been announced for the near term, with focus remaining on sustaining current service levels amid budget constraints outlined in TriMet's FY2026–2030 .

Extension Proposals and Feasibility Challenges

Several regional transportation plans have identified potential extensions for the MAX Blue Line beyond its current endpoints at Hatfield Government Center in Hillsboro and Cleveland Avenue in Gresham. Westward, long-range concepts in Metro's 2023 Regional Transportation Plan outline corridor refinement from Beaverton to Forest Grove, approximately 10 miles further west, potentially incorporating along existing rail rights-of-way or highway alignments to connect underserved suburban areas. However, these remain conceptual, with no funded projects or environmental reviews initiated as of 2025, prioritizing enhancements like 's FX service on Tualatin Valley Highway instead. Eastward extensions from Gresham have not advanced in recent or planning documents, reflecting limited demand projections for further suburban outreach amid stagnant regional growth in that corridor. A more prominent proposal affecting Blue Line operations is the MAX Tunnel Study, jointly pursued by and Oregon Metro since 2019, which evaluates a subsurface under downtown Portland and the to bypass the capacity-constrained . This approximately 3-mile alignment would enable higher speeds (up to 50 mph underground) and frequencies for east-west lines like the , potentially reducing end-to-end travel times by 10-15 minutes while accommodating projected ridership growth to 2040. The study, entering detailed engineering phases by 2025, aims to integrate with existing infrastructure but requires federal environmental clearance under NEPA. Feasibility challenges for these initiatives include substantial , estimated at $2-5 billion for the tunnel alone based on preliminary scoping, exacerbating TriMet's shortfalls that already necessitate potential cuts without new revenue by 2027. Ridership forecasts for peripheral extensions like Forest Grove indicate marginal returns, with daily boardings potentially under 1,000 due to sparse and from enhanced bus services, questioning cost-benefit ratios under federal grant criteria. Construction risks encompass geological instability in Portland's sedimentary soils, prolonged disruptions to commerce, and acquisition of private properties, compounded by political hurdles such as voter resistance to bond measures amid competing priorities like systemwide maintenance backlogs. Environmental reviews could delay timelines by 5-10 years, while interstate coordination for any Vancouver, WA., linkage—occasionally floated but not Blue Line-specific—faces federal barriers and cross-jurisdictional disputes. TriMet's 20-year Strategic Transit Vision emphasizes reliability upgrades over expansions, reflecting empirical data showing higher returns from frequency increases (e.g., 7.5-minute headways) than linear growth in low-density areas.

References

  1. [1]
    MAX Blue Line Map and Schedule - TriMet
    The MAX Blue Line connects Hillsboro, Beaverton, Portland City Center, East Portland, and Gresham, with service every 15 minutes or less most of the day.Gresham/Hillsboro · Route description · TriMet logo
  2. [2]
    MAX Blue Line - TriMet
    MAX Blue Line runs every 15 minutes or better most of the day, every day. 3. Service Alerts. Get updates by email. To Gresham To Hillsboro. Hatfield Government ...
  3. [3]
    Westside MAX Blue Line Project - TriMet
    The MAX Blue Line opened in 1998, connecting Hillsboro to Downtown Portland, is 18 miles long, has 32 stations, and includes a 3-mile tunnel. Washington Park ...
  4. [4]
    Celebrating 25 Years of MAX Blue Line to Gresham - TriMet
    The MAX Blue Line opened in 1986, was among the first in the U.S., connects Gresham and Portland, and has exceeded ridership expectations.
  5. [5]
    [PDF] banfield light rail - eastside max blue line - TriMet
    The MAX Blue Line light rail connects Hillsboro, Beaverton, Portland City Center, East Portland, and Gresham, and is a 15-mile line from Gresham to Downtown ...
  6. [6]
    Feb. 4, 1974: Portland kills the Mount Hood Freeway...
    Nov 4, 2014 · The Mount Hood Freeway plan took a hit in 1973, when the environmental impact study showed that it would dump more traffic into downtown than ...
  7. [7]
    [PDF] Transportation Politics in Portland, Oregon, and the Revolt Against ...
    By the early 1960s freeway planning and development efforts were well under way for I-5 and I-405. At this time, the Oregon State Highway Department turned its.
  8. [8]
    Eastside MAX Blue Line Project - Portland - TriMet
    Opened: September 5, 1986 · Length: 15 miles · Stations: 30 · Construction: March 1982–September 1986 · Cost: $214 million ...Missing: inauguration | Show results with:inauguration
  9. [9]
    MAX Light Rail Project History - Portland - TriMet
    Eastside MAX Blue Line. Gresham/City Center The Portland area's first light rail line, Eastside MAX Blue Line connects Gresham with Portland City Center.
  10. [10]
    First MAX Light Rail Opens - Sept 5, 1986 | KATU In The Archives
    Sep 5, 2022 · KATU News stories from the launch of the first TriMet MAX light rail line on September 5, 1986 and a story following up on train ridership a ...
  11. [11]
    The TriMet Story
    1993. Construction began on the Westside MAX Blue Line, starting with the three-mile-long twin tunnels under Portland's West Hills. Construction of ...
  12. [12]
    [PDF] BLUE LINE EXTENSION - Portland - TriMet
    By 1988, Eastside MAX light rail was met with wide approval and planning resumed on Westside light rail. The first hurdle was crossing the West Hills, which.
  13. [13]
    TriMet upgrades large section of rail as it wraps up spring project on ...
    May 24, 2021 · Crews completed the maintenance project that began a few weeks ago on the MAX Blue Line, with the final phase involving rebuilding rail near I- ...<|separator|>
  14. [14]
    MAX Improvements - Making Transit Better - TriMet
    In August 2020, we replaced and upgraded track, switches and the signal system across the 108-year-old Steel Bridge, which help improve reliability and keep ...
  15. [15]
    TriMet's newest MAX trains begin rolling through Portland - KGW
    Mar 5, 2025 · The first new MAX trains in a decade are rolling out on TriMet's light rail system. Thirty will enter service this year, replacing the ...
  16. [16]
    Meet the New MAX - TriMet
    We require every new MAX train to undergo operational testing before we put them into service. This includes a 5,000-mile “burn-in” on the MAX system and in our ...
  17. [17]
    (VIDEO) Improvements coming this spring to TriMet's MAX Blue Line ...
    Mar 26, 2025 · The two-week-long East Burnside MAX Improvements Project will require crews to work on and above the tracks to replace and upgrade equipment for ...
  18. [18]
    Major improvements coming in April to TriMet's MAX Blue Line ...
    Additionally, crews will replace approximately 8,000 feet of overhead wire as part of the improvements. This work, along with rail crossing replacement and ...Missing: maintenance | Show results with:maintenance
  19. [19]
    (VIDEO) Two-part MAX improvements project coming to TriMet's ...
    Sep 17, 2025 · Additionally, crews will replace more curved rail near Cascades Station, deep clean stations, remove litter from our track and replace rail ties ...Missing: vehicle maintenance
  20. [20]
    MAX Blue and Red Line regular service has resumed! Thanks for ...
    Sep 15, 2025 · During the disruption, crews will replace rail, perform deep cleaning at stations and in the track, and replace rail ties. Regular MAX ...
  21. [21]
    MAX Light Rail Stations - Portland - TriMet
    Click on a station name to view connections, amenities and other details. You can also view a detailed map of the MAX system, or find MAX stations on the map.Missing: alignment key
  22. [22]
    Park & Ride Locations - TriMet
    24-hour limit. Connections. MAX Blue Line · MAX Red Line · MAX Green Line · 15-Belmont/NW 23rd · 19-Woodstock/Glisan · 22-Parkrose · 23-San Rafael · 24-Fremont ...
  23. [23]
    [PDF] POWER, SIGNALS AND TRAFFIC INTERFACE - Portland - TriMet
    The TriMet light rail system is powered by a conventional 750-volt DC overhead system. In central city areas, a single contact wire is used to minimize the.Missing: gauge electrification<|separator|>
  24. [24]
    [PDF] Transit-Oriented Development Plan - TriMet
    Transit-oriented development, or TOD, is the creation of compact, walkable, pedestrian-oriented, mixed-use communities centered around high-quality.
  25. [25]
    Orenco Station | CNU - Congress for the New Urbanism
    Orenco Station stands as a transit-oriented development featuring 1,800 homes, a Town Center, offices, retail options, and nearby employment on 209 acres.
  26. [26]
    Orenco Station in Hillsboro, Oregon : UnSprawl Case Study
    Orenco Station is a new transit-oriented community of 1,800 homes, a town center, office, retail and nearby employment on 209 acres in the town of Hillsboro, ...
  27. [27]
    Orenco | City of Hillsboro, OR
    Orenco Station is a mixed-use area located adjacent to the North Hillsboro Industrial District. It is a 135-acre space originally planned in the 1990s.
  28. [28]
    [PDF] Transit-Oriented Development in Portland:
    primarily developments along the Westside MAX line in Washington County, including sites at or near Orenco Station and The Round at Beaverton (Table 2-1).
  29. [29]
    (VIDEO) Transit-Oriented Development near TriMet's Hollywood ...
    Nov 1, 2024 · The new ramp gives all riders access to the Hollywood/NE 42nd Ave MAX Station. It replaces the temporary structure that has been in place since ...
  30. [30]
    MAX Light Rail Service - Portland - TriMet
    MAX (Metropolitan Area Express) Light Rail connects Portland City Center with Beaverton, Clackamas, Gresham, Hillsboro, Milwaukie, North/Northeast Portland and ...
  31. [31]
    Decommissioning TriMet's Type 1 MAX light rail vehicles - YouTube
    Feb 5, 2024 · As we say "farewell" to our Type 1 MAX light rail vehicles, we look back at the history of TriMet's first MAX trains, which went into ...Missing: manufacturers | Show results with:manufacturers
  32. [32]
    [PDF] RAIL VEHICLE FLEET - TriMet
    A new low-floor vehicle was built for the light rail project that became the MAX Green Line. These Type. 4 LRVs are three feet longer than Type 2 or Type 3 LRVs.
  33. [33]
    New digital technology drives future of TriMet light rail vehicles
    A successful pilot project demonstrated the advantages TriMet is gaining by digitalizing its rail fleet with Siemens Railigent X and Wi-Tronix Violet IoT ...
  34. [34]
    [PDF] RAIL MAINTENANCE FACILITIES - TriMet
    MAX Blue Line. • It's North America's first facility expressly designed to accommodate low-floor cars. • All work areas were equipped with roof-level service ...Missing: replacement | Show results with:replacement
  35. [35]
    Siemens to overhaul TriMet light-rail vehicles - Mass Transit Magazine
    Jun 4, 2019 · Through the overhaul, TriMet will be able to maintain a State of Good Repair for the fleet and retain its fleet safety, performance and ...
  36. [36]
    [PDF] FY2023 – FY2027 - FINAL April 2022 - TriMet
    ▫ Light rail fleet replacement and remanufacturing ... ▫ Vehicle preventive maintenance work order completion improved to 99.8 percent for light rail vehicles.<|control11|><|separator|>
  37. [37]
    MAX Blue Line Weekday Eastbound to Portland City Center ... - TriMet
    Hatfield Government Center MAX Station · Hillsboro Airport/Fairgrounds MAX Stn · Willow Creek/SW 185th Ave TC MAX Station · Elmonica/SW 170th Ave MAX Station.Missing: alignment key
  38. [38]
    MAX Blue Line Weekday Westbound to Portland City Center ... - TriMet
    3:11am. —. 3:46am. 3:49am. —. 4:14am. 4:30am. —. —. —. 4:52am. 5:05am. 5:11am. —. 5:19am. 5:25am. 5:34am. 5:37am. 5:44am. —. 5:46am. 5:49am. 5:53am. 6:07am.Missing: frequencies daily
  39. [39]
    Frequent Service Lines - TriMet
    Frequent Service bus lines and MAX Light Rail run every 15 minutes or less most of the day, every day. Frequent Service map Download PDF ...
  40. [40]
    Plan and track your trip on TriMet
    Get arrival times, plan trips, see route maps and check service alerts, all in one place.
  41. [41]
    TriMet ridership remains down by a third from 2019 ... - Oregon Live
    Apr 27, 2025 · Ridership plunged by nearly 60% early in the pandemic and remains down by almost a third compared to 2019. (TriMet's fiscal year runs from July ...
  42. [42]
    TriMet's busiest MAX stations (plus daily on off stats for all others)
    2010 data from TriMet site: "Weekday ridership averaged 62,800 on the Blue line, 22,700 on the Red line, 15,900 on the Yellow line, and 21,700 on the Green line ...
  43. [43]
    TriMet Ridership
    FY2025 Boardings · Bus - Annual. 42,180,399 · MAX - Annual. 22,760,092 · WES - Annual. 124,008 · Total - Annual. 65,064,489 ...Missing: Blue 2020-2025
  44. [44]
    [PDF] Quarterly Performance Report - TriMet
    MAX OTP decreased to 81.9% compared to the previous quarter; this is below the target of 88.0% on time. ○ WES OTP increased to 99.6% compared to the previous ...Missing: historical trends
  45. [45]
    [PDF] TriMet FY2026 Adopted Budget
    Jun 30, 2025 · ... funding. • Day-to-day Operating Requirements of $918.1 million ... Sections of our MAX light rail system have been in operation since 1986.
  46. [46]
    [PDF] FY2025 TriMet Adopted Budget - Portland
    Jun 30, 2025 · Government Finance Officers Association of the United States and Canada (GFOA) presented a. Distinguished Budget Presentation Award to ...
  47. [47]
  48. [48]
    [PDF] Livable Portland: Land Use and Transportation Initiatives
    Eastside MAX Blue line was constructed with little focus on TODs. As local ... The Westside segment of the MAX Blue Line is an 18-mile light rail ...<|control11|><|separator|>
  49. [49]
    [PDF] More Development For Your Transit Dollar
    Portland MAX Blue Line LRT. Much of the TOD impact of the Portland MAX Blue Line LRT can be attributed to non-transit factors. The 33-mile MAX Blue Line LRT ...
  50. [50]
    Light-Rail-Transit Impacts in Portland: The First Ten Years
    Empirical analysis provides evidence that light rail has had some positive effects on single-family property values, transit use, and slower growth of two-plus ...
  51. [51]
    Property Value Premium of Transit Accessibility and Light Rail ...
    May 13, 2024 · The east-side case is served by three MAX lines: Blue (opened in 1986), Red (opened in 2001), and Green (opened in 2009) lines, while the west- ...<|separator|>
  52. [52]
    "The Impact of New Light Rail Service on Employment Growth in ...
    The new LRT increased employment along the Greenline corridor in the long-term. Clackamas Town Center saw short-term growth, while Lents Town Center had no  ...
  53. [53]
    Labor Market Effects of Light Rail Transit: A Case Study of Portland's ...
    The study found no clear effect of the transit investment on employment growth, with limited evidence of substantial job creation.
  54. [54]
    Light-Rail Transit: Myths and Realities | St. Louis Fed
    Proponents of light rail argue that rail transit increases community well-being by creating jobs, by boosting economic development and property values, and by ...
  55. [55]
    [PDF] TCRP Report 35: Economic Impact Analysis of Transit Investments
    Benefit-Cost Analysis (BCA) was carried out for the proposed Westside. Light Rail Transit (LRT) extension in Portland. Cumulative benefits were measured over ...<|separator|>
  56. [56]
    [PDF] High Capacity Transit Strategy Update - Portland - Oregon Metro
    May 13, 2024 · Light rail provides a higher passenger capacity per hour of service. The MAX system was developed to fit downtown Portland's 200-foot blocks; ...<|separator|>
  57. [57]
    [PDF] IBR Program Update - Clark County
    Feb 26, 2025 · ▸The fare recovery rate is expected to be around 25% ($5.45 million) of the $21.8 million estimated cost for light rail and express bus.
  58. [58]
    TriMet Report: Majority Of Transit Crimes Occur On Rail System - OPB
    Jul 26, 2017 · A new report from TriMet says there were 1,247 alleged crimes reported out of nearly 99 million rides taken on the transit system in 2016.Missing: Blue | Show results with:Blue<|separator|>
  59. [59]
    TriMet crime statistics low but murky under new system
    588 — happened on the rail system. The bus lines accounted for 343 crimes, while 316 happened at stations or on other ...
  60. [60]
    Crime flat on TriMet, agency says, but data lacking - oregonlive.com
    Jul 26, 2017 · 733 crimes against customers, including 532 property crimes -- mostly theft -- 188 incidents of assault or intimidation, and 12 sex offenses · 62 ...
  61. [61]
    Transit leaders acknowledge safety issues on TriMet, promise more ...
    Oct 17, 2023 · Calls to transit police for service decreased 14% from 2021 to 2022, to about 7300 overall.
  62. [62]
  63. [63]
    Survey shows approval of TriMet increasing as agency investments ...
    Sep 30, 2024 · Serious incidents are rare on our transit system, which provides more than 1.3 million rides per week—resulting in one call to police for every ...
  64. [64]
    MAX passenger lunged at rider unprovoked, stabbed him to death ...
    Apr 1, 2024 · In December 2023, a 23-year-old man was stabbed at or near the Providence Park MAX station, and he died after he stepped through the open doors ...
  65. [65]
    UPDATE: Adrian Cummins Enters Guilty Plea, Sentenced to 18 ...
    A Multnomah County Circuit Court judge sentenced Adrian Austin Cummins, 26, to 18 years in prison for a September 2023 stabbing on a MAX light rail train in ...
  66. [66]
    UPDATE: MAX Train Stabbing Victim Identified (Photo) - Portland.gov
    Apr 3, 2024 · The man killed on a MAX train on Friday, March 29, 2024, has been identified as Michael Matthew Brady, 51, of Portland.<|separator|>
  67. [67]
    Survey finds TriMet's approval rating has grown, but about half of ...
    Oct 1, 2024 · In mid-September, Portland police responded to a deadly shooting at a MAX Blue Line stop near East Burnside. ... Downtown Portland saw 4-year high ...
  68. [68]
    Grandmother, 63, sexually assaulted at light rail station after falling ...
    Apr 18, 2024 · A woman visiting Oregon for her grandson's graduation was sexually assaulted after falling unconscious at a TriMet station last year, ...
  69. [69]
    Crime on Portland-area MAX trains increases; did TriMet cut too ...
    Mar 31, 2011 · The worst stop was Gateway, with 72 reported crimes. Parkrose/Sumner on the Red Line came in a distant second with 21. The safest stop? The Mt.Missing: Blue incidents trends
  70. [70]
    Portland Sees Decline in Violent Crime; Homicides Down 51% in ...
    Aug 8, 2025 · Compared to January through June 2024, overall violent crime in Portland fell by 17 percent. Aggravated assaults dropped by 18 percent, ...
  71. [71]
    [PDF] TriMet Attitude Awareness Survey - Portland
    About half of all respondents say they would feel safe using. TriMet services, with 54% and 42% rating safety as 5+ on. TriMet buses and MAX trains respectively ...
  72. [72]
    [PDF] Agency Safety Plan - TriMet
    Dec 31, 2023 · General Manager's Safety Management Policy Statement. The Tri-County Metropolitan Transit District of Oregon strives to provide safe, ...<|control11|><|separator|>
  73. [73]
    MAX train, Portland Streetcar derail after crash; 2 injured | kgw.com
    Nov 15, 2023 · Two people, the operator and a passenger on the streetcar, were taken to the hospital with minor injuries, according to Portland Fire.
  74. [74]
    Construction worker hit, killed by MAX train in East Portland - KPTV
    Nov 12, 2024 · A person was hit and killed by a MAX train near East 148th Avenue at about 2:00 pm Tuesday. The construction worker who was killed was found to have been a ...
  75. [75]
    Construction worker killed by MAX train in Portland - DJC Oregon
    Nov 13, 2024 · The person killed was identified as 61-year-old Anthony Davis of Salem. Davis was a member of a Moore Excavation Inc. construction crew working on a project.<|separator|>
  76. [76]
    Bicycle rider struck and killed by MAX train after crossing barriers
    Jun 18, 2025 · A person riding a bicycle died after being involved in a collision with a MAX light rail train today around 1:30 pm.Missing: derailment | Show results with:derailment
  77. [77]
    Outer East Portland MAX trains mow down two people; one dies
    On the evenings of May 13 and May 15, pedestrians were struck on TriMet MAX Light Rail “Blue Line” tracks. Man struck by MAX train in Glenfair, dies. Streets ...Missing: derailment | Show results with:derailment
  78. [78]
    (VIDEO) TriMet expands safety network with more blue-light security ...
    Sep 30, 2025 · Call stations, installed first along the east side MAX corridor, connect riders to dispatchers within seconds, deterring crime.Missing: report data
  79. [79]
    The Promises and Perils of TriMet's Safety Response Team
    Mar 6, 2025 · When TriMet launched its Safety Response Team in 2021, sending unarmed workers trained in de-escalation onto Portland's public transit ...
  80. [80]
    (VIDEO) TriMet's new Security Operations Center unifies years of ...
    Oct 23, 2024 · Just call or text 503-238-7433 (RIDE), press the button on a blue-light security phone or submit a security report online at trimet.org. For ...
  81. [81]
    MAX Blue and Red lines disrupted on Sunday, Nov. 5, as TriMet and ...
    Oct 30, 2023 · The Washington Park MAX Station will be closed and off limits to the public on Sunday, Nov. 5, and MAX Blue and Red lines will be disrupted for the entire ...
  82. [82]
    Performance Dashboard - TriMet
    The dashboard tracks ridership, cost per ride, revenue, collisions, on-time performance, and other measures to identify trends and measure efficiency.Missing: Blue | Show results with:Blue
  83. [83]
    MAX Blue Line service to be disrupted for 2 weeks starting Sunday
    Apr 26, 2025 · A potential slowdown for Portland MAX riders is ahead, as service on the Blue Line is set to be disrupted for two weeks starting Sunday.<|separator|>
  84. [84]
    Tension at TriMet when temps top 100 - BikePortland
    Jul 9, 2024 · TriMet has told MAX riders to expect delays of up to 15-30 minutes due to the heat. Why does this keep happening?
  85. [85]
    The Portland MAX is slow. This is how to fix it. - Reddit
    Jul 20, 2024 · 40 minutes seems insane: what was the maximum operating speed and how many stops? Not to mention the Blue Line alignment is a direct route ...Missing: efficacy debates
  86. [86]
    Roughly half of TriMet riders feel unsafe. 82% say ... - Oregon Live
    Oct 1, 2024 · By 2022, the number had dropped to 54% feeling safe on buses and 48% on MAX. The number held steady in 2024 on buses, but continued to slide to ...
  87. [87]
    Survey shows TriMet riders feel safety is a concern | kgw.com
    Oct 1, 2024 · A recent survey done by a Seattle-based research firm shows 73% approve of the job TriMet is doing and nearly half say safety concerns stop them from riding.
  88. [88]
    100% of sampled MAX trains test positive for low levels of meth - KPTV
    Sep 7, 2023 · According to a study by the University of Washington, 100% of sampled surfaces on TriMet light rails tested positive for low levels of meth.
  89. [89]
    Drug residue widespread on MAX trains, unlikely to harm | kgw.com
    Sep 7, 2023 · Though MAX trains are replete with trace amounts of fentanyl and meth, experts say it's not enough to harm riders · Is it safe to ride? · A call ...
  90. [90]
    Portland: Frequent Bus Performance Approaching Light Rail's
    Jun 8, 2015 · The comparison I like to go to to prove rail's greater cost effectiveness is Calgary and Ottawa. Both are cities of similar size, but Ottawa is ...
  91. [91]
    Cost Overruns and Ridership Shortfalls - The Thoreau Institute
    Jul 27, 2021 · Rail transit projects built in the United States typically suffer severe cost overruns and end up carrying far fewer riders than originally projected.<|separator|>
  92. [92]
    TriMet To Start Two-Part Eastside MAX Improvements Project in ...
    Sep 18, 2025 · - TriMet announces a two-part MAX improvements project will start in October 2025. ... The MAX Blue, Green, and Red lines will have a one-day ...
  93. [93]
    TriMet's Robertson Tunnel to close for weeklong MAX improvements ...
    Aug 13, 2025 · TriMet says the project will replace about one mile of overhead wire, add a modern tensioning system west of the tunnel, and renew roughly 700 ...
  94. [94]
    [PDF] BUSINESS PLAN - TriMet
    Mar 18, 2025 · This Business Plan is for FY2026 through FY2030, the five fiscal years starting July 1, 2025. Our focus is to provide an excellent customer ...
  95. [95]
    [PDF] Future corridor refinement planning - Oregon Metro
    Aug 23, 2024 · In 2019, Metro and TriMet documented the feasibility and benefits of the tunnel in the MAX Tunnel Study, examining the feasibility of faster ...
  96. [96]
    Proposed 2024–25 Service Changes - TriMet
    New night bus lines would be added for the MAX Blue, Green, Red and Yellow lines, and we will move late-night/early-morning MAX trips to those buses for the ...
  97. [97]
    MAX Tunnel Study - Oregon Metro
    A light rail tunnel from approximately Lloyd Center to Goose Hollow in Southwest Portland to improve transit as the region grows.Missing: engineering features
  98. [98]
    [PDF] Tunnel Study - Oregon Metro
    Oct 25, 2019 · The tunnel study examines faster light rail to improve mobility, reduce congestion, and improve travel times, especially at the Steel Bridge, ...Missing: features | Show results with:features
  99. [99]
    Early Scoping Notice - Federal Register
    Jul 17, 2019 · The purpose of this early scoping notice is to advise other agencies and the public of the intent to further study the feasibility of a tunnel ...Missing: challenges | Show results with:challenges
  100. [100]
    How you can help prevent cuts to transit service; MAX Blue Line ...
    Apr 24, 2025 · Urging state legislators to fund transit service. Without additional funding, TriMet may be forced to eliminate as many as 34 bus lines starting in 2027.Missing: feasibility challenges extensions
  101. [101]
    Exclusive: TriMet Conceptualizes Next 20 Years of Portland Transit ...
    Apr 11, 2025 · Major improvements proposed in the presentation include increasing service on all MAX segments to 7.5 minute or shorter headways, bringing MAX ...
  102. [102]
    Portland Transit Tunnel Concept Under Exploration
    Aug 19, 2019 · The study, currently ongoing and entering a budget estimating and planning strategy stage, expects to identify opportunities and challenges with ...
  103. [103]
    Portland: Facing the East-West Chokepoint - Human Transit
    Jul 9, 2019 · A long overdue study is looking at the complex of capacity problems, and while it's looked at some half-measures, the only thing that solves ...Missing: challenges | Show results with:challenges<|separator|>