Fact-checked by Grok 2 weeks ago

Sunda Strait Bridge

The Sunda Strait Bridge is a proposed but unbuilt for a 30-kilometer road-and-rail spanning the to link the islands of and , facilitating direct vehicular and transport between their respective ports of Merak and Bakauheni. First conceived in the by Indonesia's founding president as a symbol of national unity and development, the project gained renewed momentum in the under President , with detailed feasibility studies and master plans envisioning it as a key component of between the country's two most populous islands. Estimated to cost between US$23 billion and US$25 billion, the bridge was promoted for its potential to alleviate chronic congestion on existing services, boost inter-island , and support Indonesia's ambitions amid rapid . Despite periodic advancements, including land acquisition and designs, the initiative has faced repeated delays and ultimate shelving due to prohibitive financing challenges, projected low returns around 7.79 percent, and geological risks from the seismically active prone to earthquakes and volcanic activity. Critics, including analysts, argued that the bridge could exacerbate overdevelopment on while diverting resources from Sumatra's broader needs, leading to its deprioritization under subsequent administrations, with no construction commenced as of 2025. Environmental concerns over disruption and the project's misalignment with Indonesia's maritime nation identity further fueled opposition.

Project Overview

Description and Objectives

The is a proposed multi-span designed to span approximately 30 kilometers across the , connecting Merak in Province on to Bakauheni in Province on . The project encompasses both road and rail infrastructure to establish a direct land link between Indonesia's two most populous islands, replacing reliance on ferry services for inter-island passenger and freight transport. Primary objectives include fostering economic integration between and by enhancing connectivity, which is expected to accelerate in line with the Masterplan for Acceleration and Expansion of Indonesia's Economic Development (MP3EI). The bridge aims to reduce travel times from 2-3 hours via to around 30 minutes, thereby improving efficiency and supporting national economic growth targets. Key design features comprise six road lanes and two railway tracks, with a minimum clearance of 70 meters above to permit passage of large vessels. The structure utilizes intermediate islands—Ular, Sangiang, and Prajurit—as supports to divide the crossing into manageable spans.

Strategic Context

Indonesia, as an archipelagic nation comprising over 17,000 islands, faces persistent challenges in inter-island connectivity that elevate logistics costs and constrain domestic trade efficiency. These issues stem from reliance on ferries and limited fixed , which bottleneck the movement of goods between resource-producing outer islands and consumption centers, thereby impeding overall . The proposed Sunda Strait Bridge aims to mitigate these constraints by establishing a direct and rail link between and , Indonesia's two most populous and economically dominant islands, which together account for a substantial portion of national GDP. Strategically, the bridge serves as a critical extension of the , a north-south highway traversing Sumatra's length, enabling seamless integration with Java's established toll road network and industrial corridors. This connectivity would facilitate the efficient transport of Sumatra's abundant natural resources—such as from plantations and minerals from operations—to Java's hubs, where value-added processing predominates. By bridging these economic imbalances, the project aligns with Indonesia's national strategy to foster balanced , reducing disparities in access to markets and that currently favor western islands over eastern ones. Analogous to China's cross-strait infrastructure, such as the Hong Kong-Zhuhai-Macao Bridge, which has enhanced regional trade flows by minimizing sea crossings, the Sunda Strait Bridge is projected to substantially lower inter-island freight logistics costs through reliable fixed-link transport. This reduction in transit times and expenses—potentially alleviating bottlenecks from dependencies—would amplify multiplier effects on national GDP by streamlining supply chains and promoting industrial agglomeration across the strait. Positioned within the Master Plan for the Acceleration and Expansion of Indonesia's Economic Development (MP3EI), the bridge underscores a causal emphasis on mega-infrastructure to drive long-term growth in an prone to fragmentation.

Historical Development

Early Proposals and Studies

The concept of a bridge across the to connect and was first proposed in the early by Indonesian engineer Dr. Ir. Wiratman Wangsadinata, who envisioned a combined road-and-rail suspension structure to enhance inter-island connectivity. Wangsadinata, founder of PT Wiratman, drew on engineering principles to address the strait's navigational demands and geological constraints, including strong tidal currents and depths varying significantly across the crossing site. In May 1997, Wangsadinata submitted a detailed feasibility report to Indonesia's BPP Teknologi, evaluating the bridge's potential as a fixed link between the islands while accounting for seismic hazards in the tectonically active region. The study incorporated empirical assessments of the strait's and risks, concluding that advanced design could mitigate vulnerabilities such as potential ground shaking and fault proximity, though it highlighted the need for site-specific geological to confirm structural integrity. Proposals gained renewed momentum in 2007, when governors of and provinces, alongside local engineering firms, committed to further feasibility studies for what would become the world's longest , spanning approximately 30 kilometers with a central span exceeding 3 kilometers. This revival was driven primarily by persistent bottlenecks at terminals in Merak () and Bakauheni (), where vessel delays and capacity limits hindered goods and passenger flows between Indonesia's most populous islands. Preliminary cost projections at the time estimated US$10–12 billion, predicated on surveys demonstrating engineering feasibility amid the area's currents and seismic profile, though full viability required addressing standards comparable to other high-risk spans.

Integration into National Plans

The Sunda Strait Bridge was formally integrated into Indonesia's Master Plan for the Acceleration and Expansion of Economic Development (MP3EI) in 2011 as a flagship infrastructure project within the Sumatra-Java economic corridor. This inclusion positioned the bridge as a critical enabler for enhancing inter-island connectivity and fostering balanced regional growth across the plan's six designated economic corridors. The MP3EI framework allocated resources toward the project, estimating initial investments on the order of Rp 150 trillion for the bridge itself, integrated with complementary transport links like roads and railways in and provinces. Alignment with national objectives emphasized the Sunda Strait's role as a strategic maritime hub, where the bridge would support logistics integration and economic expansion between Sumatra's resource-rich areas and Java's industrial base. Under President Susilo Bambang Yudhoyono's administration, this policy-driven acceleration was reinforced through Presidential Regulation No. 86 of 2011, which established the Sunda Strait Infrastructure Strategic Zone to coordinate planning and regulatory frameworks. Government commitments included directing the formation and utilization of the PT Graha Sejahtera consortium to undertake detailed viability studies, ensuring alignment with MP3EI's emphasis on public-private coordination for mega-infrastructure. These steps reflected a deliberate focus on leveraging the project to catalyze corridor-specific development without reliance on state budget financing at the integration stage.

Key Milestones and Setbacks

In 2012, the Indonesian government advanced planning for the Sunda Strait Bridge, with feasibility studies completed and construction tentatively scheduled to begin in 2014, aiming to connect Merak on to Bakauheni on at an estimated cost of US$23 billion. A led by PT Wijaya Karya and involving Japanese firms pushed detailed engineering assessments, emphasizing economic connectivity benefits. By late 2013, officials described the project as urgent to alleviate overloads handling 25,000 vehicles daily, though funding disputes persisted between coordinating and officials. The project faced a major setback in November 2014 when President Joko Widodo's administration canceled it, citing fiscal priorities amid 's maritime fulcrum policy that favored sea-based infrastructure over land megaprojects, as the bridge mismatched the nation's archipelagic identity. Widodo argued it would exacerbate economic disparities by concentrating development in western , diverting resources from eastern regions and risking inefficient public expenditure benefiting select private interests. This decision shelved efforts despite prior land acquisitions covering 40,000 hectares. The December 22, 2018, , triggered by Anak Krakatau's partial collapse and killing over 430 people across and coasts, underscored persistent geological hazards in the strait, including volcanic instability and seismic activity that had long complicated bridge feasibility studies. While the disaster did not directly halt active planning—already canceled—it reinforced causal risks from the region's active and eruption-prone , prompting reevaluations in subsequent discussions without resuming . Policy oscillations continued post-2014, with intermittent revivals in expert consultations but no funding commitments or groundbreaking; for instance, August 2025 technical talks involving Indonesian and international engineers focused on structural viability yet highlighted unresolved public-private partnership ambiguities, where state subsidies might disproportionately favor private developers amid high costs. Repeated shelving stemmed from these fiscal and risk factors, leaving the project in conceptual limbo as of October 2025.

Technical Design and Engineering

Proposed Structure and Specifications

The Sunda Strait Bridge is envisioned as a multi-span system spanning approximately 29 to 30 kilometers across the , divided into sections utilizing existing islands such as Ular and Sangiang for intermediate anchors, supplemented by artificial islands where necessary to shorten individual spans and distribute structural loads. This approach avoids the engineering challenges of a single continuous span exceeding practical limits, with two primary bridges each featuring main spans of about 2.5 kilometers—lengths that would position them among the world's longest if realized. Tower structures are planned to rise sufficiently to provide a minimum vertical clearance of 75 meters above mean , ensuring unobstructed passage for large vessels navigating the strait. The deck adopts a double-deck configuration, with the upper level dedicated to multi-lane highway traffic (including provisions for vehicles, buses, and trucks) and the lower level for twin railway tracks to facilitate integrated freight and passenger rail services between and . Engineering specifications emphasize in a harsh marine environment, incorporating corrosion-resistant materials such as high-strength steels with protective coatings and alloys suited to saltwater exposure and strong tidal currents. Seismic resilience is addressed through flexible elements and designs capable of withstanding regional tectonic forces, drawing on geotechnical investigations from 1997 onward that analyzed subsurface profiles, formations, and fault lines for anchor stability. These features reflect iterative conceptual designs aimed at balancing span efficiency with site-specific hazards like deep water depths up to 70 meters at locations.

Geological and Environmental Considerations

The Sunda Strait lies within the tectonically active Sunda Arc, part of the Pacific Ring of Fire, characterized by frequent seismic and volcanic events due to subduction along the Sunda Trench. The region accommodates complex plate interactions between the Sunda Plate and the overriding Indo-Australian Plate, resulting in elevated seismic hazard levels, with probabilistic assessments identifying it as one of Indonesia's riskiest inter-island zones for earthquakes. Proximity to Anak Krakatau volcano, formed post-1883 caldera collapse, introduces ongoing volcanic risks, including potential flank collapses that triggered tsunamis as recently as 2018. Water depths in the strait vary significantly, reaching up to 150 meters in central channels, necessitating deep foundations for bridge piers, with preliminary designs specifying placements at approximately 70 meters depth to anchor into stable seabed layers. Strong tidal currents, often exceeding navigation limits due to shallow northeastern shoals and constricted flows, combined with maximum wave heights of 3.2 meters and periods up to 17 seconds, pose hydrodynamic challenges addressable through numerical modeling of seafloor morphology. Seismic resilience in proposed flexible suspension designs draws from empirical precedents like Japan's Akashi Kaikyō Bridge, which has withstood magnitude 7+ earthquakes via damped oscillations and deep caisson foundations, suggesting analogous viability for spans exceeding 3,000 meters amid active faults. Environmental baselines indicate a diverse marine ecosystem influenced by Indian Ocean inflows, with assessments noting potential habitat disruptions from construction but emphasizing mitigation via localized dredging controls and monitoring, rather than inherent barriers to feasibility. Quaternary seismic profiling reveals sediment deposition primarily from Bay sources, supporting engineered adaptations like scour-resistant footings over ecosystem-wide preclusion.

Economic Rationale and Projected Benefits

Anticipated Economic Impacts

The Sunda Strait Bridge is projected to substantially lower inter-island logistics costs by reducing travel time across the strait from 2-3 hours via ferry to approximately 30 minutes, enabling more efficient freight and passenger movement between Sumatra and Java. Early feasibility assessments indicate this would strengthen trade flows and regional competitiveness by integrating Sumatra's natural resource processing hubs with Java's industrial base, with analogous infrastructure enhancements in the region yielding cumulative GDP gains of around 20% for Indonesia over a decade through improved connectivity. Such reductions align with broader multipliers from fixed-link projects, where transport efficiency gains propagate to 1-2% annual GDP uplift in connected corridors via lowered operational expenses and expanded market access. Construction and operational phases are expected to generate significant direct and indirect , leveraging the project's scale—estimated at IDR 150 trillion in —to stimulate job multipliers in labor-intensive sectors like Sumatra's and alongside Java's . These effects would extend to ancillary industries, including expansions and estates, fostering formal opportunities as outlined in national development frameworks. The bridge's inclusion of , pipelines, and fiber optics would further amplify economic activity by supporting resource export chains and digital connectivity, countering current bottlenecks in inter-island goods distribution. In the long term, the infrastructure would enhance trade volumes and tourism between Indonesia's two most populous islands, while providing resilience to disruptions such as ferry strikes or adverse weather, which currently inflate variability in supply chains. Projections draw parallels to the , where post-completion trade interconnectivity rose markedly—facilitating millions of annual freight movements and leisure trips—despite upfront debts, ultimately yielding sustained regional economic expansion through cross-border efficiencies. This positions the bridge as a catalyst for the Sumatra-Java economic corridor's targeted 12.5% annual GDP growth trajectory under the MP3EI framework, prioritizing production and energy sector synergies over isolated island development.

Strategic and Logistical Advantages

The Sunda Strait Bridge would replace the existing ferry-dependent crossing between Java and Sumatra, addressing chronic bottlenecks at the Merak-Bakauheni route where services frequently experience overloads, delays, and disruptions due to weather or mechanical issues. This fixed link would enable uninterrupted vehicular and rail transport, streamlining supply chains critical to Indonesia's economy, which reached a nominal GDP of approximately $1.44 trillion in 2025. By eliminating ferry wait times—often exceeding several hours during peak periods—the bridge would reduce logistics costs and enhance the efficiency of goods movement between the islands. Strategically, the project would integrate , which hosts over 56% of Indonesia's population and the bulk of its industrial base, with Sumatra's abundant natural resources including plantations, operations, and agricultural output. This connectivity would mitigate regional economic disparities by facilitating the flow of raw materials westward and manufactured goods eastward, promoting balanced national development and reducing Java's pressures through industrial relocation incentives. Enhanced infrastructure cohesion across the archipelago would also bolster defense logistics, allowing faster deployment of military assets without reliance on vulnerable sea crossings amid potential geopolitical tensions in the strategically vital . Projections from feasibility studies indicate the bridge could accommodate significantly higher volumes than the current ferry system's roughly 5.55 million vehicles annually, potentially handling tens of millions to support expanded trade and foster special economic zones at the bridgeheads in and provinces. Such capacity would underpin Indonesia's ambitions for economic corridors linking population centers with resource hubs, contributing to overall national resilience against supply disruptions.

Financing and Implementation Challenges

Cost Estimates and Funding Models

Cost estimates for the Sunda Strait Bridge have varied significantly over time, reflecting evolving assessments and economic conditions, with figures ranging from US$9 billion in calculations to as high as US$25 billion in more recent conceptual designs. Early projections in 2010 pegged the total at approximately Rp 170 trillion (US$18.87 billion), nearly double an initial US$11 billion estimate, incorporating factors such as seismic reinforcements and the bridge's 30-kilometer span across a seismically active . By 2014, updated figures approached Rp 200 trillion (about US$16.5 billion), emphasizing components like land acquisition in and provinces, foundational for deep-water pylons, and contingency allowances for . These breakdowns highlight that while core might account for 60-70% of costs, ancillary expenses for access roads, integrations, and geological surveys inflate the total, often exceeding initial bids due to Indonesia's regulatory and inflationary pressures. Funding models have centered on public-private partnerships (PPP), with consortia like the Artha Graha Network proposing to lead development alongside provincial governments as minority stakeholders. However, historical proposals reveal a pattern of private entities seeking state guarantees to mitigate risks, potentially shifting burdens to public finances without proportional risk-sharing, as seen in stalled negotiations where consortia demanded government-backed loans or viability gap funding. In 2012 estimates, consortium financing was projected at Rp 100 trillion (US$10 billion), blending equity from investors with instruments, though unresolved debates over revenue streams like tolls and have delayed commitments. Critics of such models argue that overly cautious fiscal evaluations, which prioritize immediate budgetary constraints over discounted long-term cash flows from trade efficiencies, undervalue the project's viability, drawing parallels to global megaprojects where bridges exhibit higher upfront capital (e.g., 20-30% more than equivalent tunnels) but 15-25% lower lifecycle maintenance due to reduced submersion vulnerabilities. Empirical data from similar spans, such as the , underscore that while initial overruns are common, PPP structures succeed when anchored in realistic traffic forecasts rather than optimistic projections reliant on public bailouts.

Public-Private Partnership Dynamics

The Sunda Strait Bridge project initially relied on a public-private partnership () model led by PT Graha Banten Lampung Sejahtera (PT GBLS), a formed in 2009 comprising private entities under the Artha Graha Network and minority stakes from and provincial governments. PT GBLS conducted the pre-feasibility study and proposed developing supporting economic zones at bridge endpoints to generate revenue through land value appreciation and integrated infrastructure. Under this structure, private investors were positioned to lead and operations, with anticipated toll revenues and zone developments offsetting costs, while public entities provided regulatory support and partial equity. In 2012, PPP execution faltered due to misaligned incentives, as proposals emerged to inject public funds into the private-led initiative, including compensation of approximately US$60 million for PT GBLS's preparatory expenditures despite no construction commencement. This arrangement allowed private members to capture gains from land acquisition and zoning privileges—such as exclusive development rights in growth areas—while shifting potential cost overruns and viability risks to the state budget, contradicting standard PPP risk-sharing principles. Bids and progress stalled amid disputes over funding guarantees, highlighting how private profit motives clashed with public fiscal constraints, resulting in prolonged delays without advancing to tender stages. Alternatives to the PPP framework were discussed, including full state funding to treat the bridge as a strategic asset or reliance on loans with and during construction estimated at 10-15 percent. Proponents argued that sovereign mechanisms, such as direct budgetary allocation, could bypass private incentive distortions for infrastructure of and connectivity importance, though these options raised concerns over debt burdens exceeding US$27 billion in total costs. Finance Ministry statements emphasized avoiding state budget strain, yet unresolved PPP ambiguities contributed to the model's causal breakdown, deferring implementation.

Debates and Criticisms

Technical Feasibility Concerns

The Sunda Strait's proximity to the seismically active , characterized by high probabilistic with peak ground accelerations up to 0.465g at a 7% probability of exceedance in 75 years, raises significant concerns about structural integrity during major earthquakes. Critics argue that fault lines and the 150-meter-deep trench beneath the proposed crossing could lead to differential settlement or collapse, exacerbated by the region's history of tsunamis and volcanic activity near . However, feasibility studies have incorporated advanced seismic damping technologies, such as base isolators and tuned mass dampers, drawing from successful implementations in Japan's earthquake-resistant bridges, to mitigate these risks and ensure stability. Deep-water construction poses additional hurdles, including the need for extensive piling into unstable seabeds amid strong currents influenced by seafloor morphology, which could complicate foundation stability and increase vulnerability to scour. Corrosion from saline waters and hydrodynamic pressures further threatens long-term durability, with parallels drawn to the Channel Tunnel's underwater challenges, where water ingress and material degradation required extensive remediation. Proponents counter that Indonesia-specific geotechnical assessments favor a suspension bridge design over a tunnel, citing super-long-span configurations exceeding 3,000 meters that leverage aerodynamic stabilization and corrosion-resistant coatings validated in Chinese and Japanese engineering simulations. Skeptics, including some infrastructure analysts, advocate abandoning the project due to these compounded geological threats, deeming it impractical despite prior studies. In rebuttal, detailed reports emphasize feasibility through technology transfers from and , including flutter control mechanisms for spans up to 5,000 meters and robust probabilistic hazard modeling, which demonstrate that the bridge can withstand regional extremes comparable to those engineered in other tectonically active straits.

Economic and Financial Critiques

Critics have highlighted the project's enormous estimated costs, ranging from in initial 2010 proposals to revised figures of by 2011, inclusive of surrounding economic zones, as a potential strain on Indonesia's fiscal resources despite assurances from officials that it would not burden the state budget. Finance Minister Agus Martowardojo expressed reservations in 2012, objecting to the scale amid stalled discussions on funding, which underscored risks of escalating public debt in a developing with competing priorities. Return on investment remains contentious, with early projections assuming within 15 years under optimistic timelines starting in 2014, but subsequent cost doublings extended the anticipated payoff period, potentially exceeding decades given demand uncertainties and high maintenance expenses for a 30 km structure vulnerable to seismic activity. Some analyses suggest benefits may disproportionately accrue to landowners and elites near the bridge endpoints through appreciation, rather than broadly distributing economic gains across Indonesia's population. Public-private partnership (PPP) models amplify risks of "" outcomes, where private investors bear full construction costs—estimated at Rp 225 trillion (US$24 billion)—but face revenue shortfalls if traffic volumes underperform, as seen in broader Asian debates on over-optimistic forecasts. However, lifecycle cost analyses using (IRR) and (NPV) metrics indicate positive financial feasibility when incorporating and additional revenue streams like tolls and economic zones, projecting growth multipliers from enhanced connectivity. Rebuttals emphasize opportunity costs of inaction, including persistent ferry inefficiencies in the , where weather-dependent services contribute to Indonesia's elevated expenses—comprising 24% of GDP annually—and delay trade between and , two economic powerhouses representing over 60% of national output. Empirical models counter low-impact claims by demonstrating NPV positivity through reduced transport times and induced , paralleling successful Asian bridges where indirect gains from effects outweighed initial skepticism.

Environmental and Social Objections

Critics of the Sunda Strait Bridge project have raised concerns about its potential to disrupt marine ecosystems in the , which serves as a critical for diverse fish species and migration routes. Construction activities could lead to , water degradation, and threats to , including coral reefs and fisheries that support local economies in and provinces. The 2018 Anak Krakatau volcanogenic , which generated waves up to 13 meters and affected coastal areas across the strait, has amplified fears of compounded environmental vulnerabilities in this seismically active region. Feasibility studies, however, emphasize that such impacts remain hypothetical and largely mitigable through environmental impact assessments (AMDAL) incorporating eco-designs like minimized pillar footprints to preserve currents and , with projected effects confined to construction phases rather than permanent alterations. Social objections focus on risks to coastal communities, including potential of residents near landing sites in Merak () and Bakauheni (), where land acquisition could affect thousands reliant on fishing and small-scale . Assessments indicate variable community readiness, with lower adaptive capacities in rural areas due to limited access to information and relocation support, potentially exacerbating inequalities if benefits accrue disproportionately to urban or elite interests. Cultural impacts, such as alterations to traditional practices and sites tied to historical routes, have also been cited by analysts wary of undermining Indonesia's archipelagic identity. Proponents counter that like the bridge could foster equitable growth by generating an estimated 100,000 construction jobs and enhancing regional connectivity, outweighing static preservation by enabling in fisheries through improved logistics and reduced ferry dependency. Empirical data from analogous projects suggest that with robust resettlement frameworks, net gains—such as better public services and economic diversification—can mitigate effects.

Current Status and Future Outlook

Recent Developments

As of October 2025, the Sunda Strait Bridge has seen no activity since its effective shelving in 2014, when Joko Widodo's administration deprioritized it in favor of maritime-focused development. Engineering firm Wiratman & Associates, a key proponent since the project's inception, reiterated its vision for the 30 km road-and-rail link in a September 2025 publication, emphasizing its role in integrating and economies amid Indonesia's ongoing infrastructure expansion. Academic evaluations persist, including a value engineering analysis of conceptual designs that projects potential national economic benefits but highlights unresolved financial hurdles, with no evidence of government adoption. The administration, in office since October 2024, has advanced alternative mega- initiatives, such as a coastal sea wall to mitigate flooding for 50 million residents, without announcing any revisit or studies specific to the bridge.

Alternatives and Policy Shifts

Proposals for an undersea tunnel as an alternative to the bridge have been considered but largely sidelined due to the Sunda Strait's challenging geology, including depths exceeding 50 meters in parts and high seismic activity, which elevate construction costs and engineering risks beyond feasible levels for Indonesia's budget. Enhanced services, including faster vessels and upgrades at Merak and Bakauheni, emerged as a lower-cost interim option, with investments directed toward increasing capacity to handle growing vehicle traffic across the strait. links via ferries have also been suggested, but these rely on transfers that introduce delays and limit scalability for freight integration. In November 2014, President announced the deprioritization of the bridge project, aligning with the newly launched Global Maritime Fulcrum policy that pivoted national development toward sea-based connectivity over land megaprojects. This shift emphasized the Sea Toll program, which subsidizes regular shipping routes to eastern , aiming to lower logistics costs by 10-15% through vessel acquisitions and route standardization rather than fixed crossings. The policy rationale cited fiscal prudence, redirecting funds from the estimated $33 billion bridge to more immediate maritime enhancements, though ferry-dependent crossings continue to face capacity constraints, with daily vehicle backlogs exceeding 10,000 units during peak periods. Recent policy evaluations under the 2025-2045 National Long-Term Development Plan signal potential reevaluation, referencing a 24.5 km option for the as part of broader priorities, potentially reviving fixed-link ambitions amid persistent gaps. This comes against a backdrop of that has sustained reliance on sea tolls, yet empirical data from strait crossings indicate ferries' vulnerability to disruptions—causing up to 20% annual —underscoring bridges or tunnels' causal advantage in enabling uninterrupted economic flows between and . Such alternatives, while pragmatic for short-term equity, perpetuate inefficiencies in high-density corridors where fixed demonstrably accelerates GDP contributions from integrated transport networks.

References

  1. [1]
    Indonesia cancels Sunda Strait Bridge connecting Java and Sumatra
    Indonesia appears to have shelved construction of a 30km bridge that would have connected the islands of Sumatra and Java – a US$23 billion project.Missing: details | Show results with:details
  2. [2]
    Sunda Strait Bridge: Connecting Java and Sumatra, Shaping ...
    Sep 15, 2025 · The Sunda Strait Bridge is an unbuilt 30 km road-and-rail link between Java and Sumatra. Conceived by Prof. Dr. Ir. Wiratman Wangsadinata in ...
  3. [3]
  4. [4]
    Long and winding road towards Sunda Strait Bridge - ANTARA News
    Nov 29, 2012 · However, more than 50 years have been spent on discussions, processes and controversies, so construction of the bridge has not yet begun.Missing: history | Show results with:history
  5. [5]
    Location of Sunda strait bridge - ResearchGate
    Sunda Street Bridge (SSB) is one of the mega projects offered by the Indonesia government that would spend about US$ 25 billion. In line with the SSB main ...Missing: details | Show results with:details
  6. [6]
    No more Sunda Strait Bridge plan - National - The Jakarta Post
    Nov 3, 2014 · Instead of fostering development in Sumatra, the bridge could encourage the further urbanization of Java, adding more economic problems to ...Missing: history controversies
  7. [7]
    News - PT Buana Safira Abadi
    Aug 19, 2024 · THE CONSTRUCTION OF THE SUNDA STRAIT BRIDGE HAS NOT BEEN REALIZED, WHY? The Sunda Strait Bridge is planned to be a connecting economic path ...
  8. [8]
    Sunda Strait Bridge Compromises Indonesia's Identity: Analyst
    Oct 18, 2013 · The construction of the Sunda Strait Bridge connecting Java with Sumatra will undermine Indonesia's identity as a maritime country, ...<|control11|><|separator|>
  9. [9]
    [PDF] Indonesia Master Plan Acceleration and Expansion of Indonesia ...
    JSS will shorthened the travel time to only 30 minutes compared to ferry services that take on average of 2-3 hours. Moreover, JSS will be provided with ...
  10. [10]
    Sunda Strait Bridge Project To Boost Economic Growth
    May 11, 2012 · The bridge will be 75 meters high, to enable ships to pass under it, and will be constructed over three small islands in the strait - Prajurit, ...
  11. [11]
    The Sunda Straits Bridge, between Java & Sumatra Islands Will be ...
    Oct 7, 2007 · The bridge across the Sunda Strait will connect Merak Port in western Java with Bakauheni Port in southern Sumatra, and is expected to alleviate chronic ...
  12. [12]
    New bridge planned for key Indonesia link - Global Highways
    The Sunda Straits Bridge will actually be a series of links connecting the smaller Indonesian islands of Prajurit, Sangiang and Ular directly with the larger ...Missing: intermediate | Show results with:intermediate
  13. [13]
    Indonesia's Strategic Ports: Gateways to Global Trade and ...
    Indonesia's vast archipelagic geography poses unique challenges in terms of logistics connectivity and costs. Improving the efficiency of port operations and ...
  14. [14]
    Government to Go Ahead With Sunda Strait Bridge Project
    Mar 1, 2014 · JSS, as Sunda Strait Bridge is called, is expected to boost connectivity and logistics transport between the countrys two most densely populated ...
  15. [15]
    Trans-Sumatra turnpike project set to start - Sat, November 3, 2012
    Nov 3, 2012 · The Trans-Sumatra toll road is planned to connect to the Sunda Strait Bridge, slated to be built in the near future. “The Trans-Sumatra toll ...
  16. [16]
    Joko Widodo: Construction Sunda Strait Bridge is No Priority
    Nov 4, 2014 · The administration of Indonesian President Joko Widodo (popularly known as Jokowi) will not give priority status to the Sunda Strait Bridge project.Missing: travel time reduction dependency
  17. [17]
    National Engineers must Dominate Sunda Strait Bridge Project
    The plan to build the bridge, which was first conceived 16 years ago, hangs in limbo. The government is divided over the issue.
  18. [18]
    [PDF] ADVANCED SUSPENSION BRIDGE TECHNOLOGY AND ... - Free
    This paper is based on a report prepared by the author for BPP Teknologi as the executing agency of the Sunda Strait Bridge Project, presented on 1 May 1997.
  19. [19]
    Feat of engineering: huge bridge planned for quake zone - ABC News
    Oct 5, 2007 · Indonesia plans to build the world's longest suspension bridge to link Java and Sumatra across an earthquake-prone strait.Missing: revival | Show results with:revival
  20. [20]
    Indonesia's transport planning lacks rigour - East Asia Forum
    Jul 8, 2014 · For example, a bridge across Sunda Strait is technologically feasible and would break the bottleneck at the ferry crossing between Java and ...Missing: motivation | Show results with:motivation
  21. [21]
    Indonesia plans to build the longest bridge in the world between ...
    The bridge intended for road and rail transport is expected to cost around ten billion dollars (195.6 billion CZK) and, if completed, will become the longest ...
  22. [22]
    Indonesia to build suspension bridge in earthquake hot spot
    Oct 5, 2007 · The bridge, traversing 30 kilometres, will link Indonesia's main islands of Java and Sumatra at an estimated cost of $12 billion.Missing: revival | Show results with:revival
  23. [23]
    [PDF] MASTERPLAN - ThaiPublica
    Sunda Strait Bridge. 150,000. 2011. 2025. Lampung &. Banten. 2. Road. Trans Sumatra 1,580 km. 55,300. 2012. Sumatra. 3. Railway. Railway development from ...
  24. [24]
    Indonesia's Sunda Strait Bridge Project - Jembatan Selat Sunda (JSS)
    Apr 8, 2013 · The Sunda Strait bridge, a planned road and railway connection between the two western Indonesian islands of Sumatra and Java, has been a dream ...Missing: details | Show results with:details
  25. [25]
    Sunda Strait Bridge to be constructed in 2014 - ANTARA News
    Aug 5, 2012 · The minister believed that the JSS construction will help boost the Indonesian economy because the bridge is the main gate of the land ...Missing: cancellation | Show results with:cancellation
  26. [26]
    Construction of Sunda Strait bridge urgent - ANTARA News
    Dec 1, 2013 · Construction of the 30-kilometer bridge will cost US$10 billion and development of the areas in both end of the bridge will cost around US$15 billion.Missing: connecting | Show results with:connecting
  27. [27]
    Sunda Strait Bridge Lacks National Identity, Official Says - En.tempo.co
    Nov 7, 2014 · Sunda Strait Bridge construction project was canceled because it did not match with Indonesia's identity as a maritime state.
  28. [28]
  29. [29]
    Indonesia's new landmark bridge project for Sunda Strait
    Construction work on Indonesia's Sunda Straits Bridge is planned to start in 2014. The 40,000ha of land required for the project has been prepared by the ...Missing: details | Show results with:details
  30. [30]
    The 22 December 2018 Mount Anak Krakatau volcanogenic tsunami ...
    Feb 24, 2020 · This article investigates the impacts of the 2018 Sunda Strait tsunami on the affected areas and presents an analysis of the impacts of pure hydrodynamic ...
  31. [31]
    Tsunami in Indonesia Kills Over 280, With No Warning or Quake
    Dec 23, 2018 · At least 281 people who died when a tsunami in Indonesia's Sunda Strait struck without warning on the country's two most-populous islands.
  32. [32]
    Sunda Strait Bridge | PDF | Transport | Disaster And Accident - Scribd
    Rating 5.0 (1) This is my paper for a task on iGeo National Training for Indonesia's National Team about geographical review on Sunda Strait Bridge project in Indonesia.<|separator|>
  33. [33]
    THE GEOTECHNICAL SUBSURFACE AND ENVIRONMENTAL ...
    Sunda Strait Bridge will stretch along 30 km with two suspension bridges, each main span approximately will be 2.5 km long, as its main bridge. Conditions and ...Missing: artificial anchors 1997-2013
  34. [34]
    RI to have world`s longest bridge - ANTARA News
    May 10, 2012 · He said the bridge will have a height of 75 meters to enable ships passing under it. ... Earlier Minister Coordinating the Economy Hatta Rajasa ...Missing: towers | Show results with:towers
  35. [35]
    SUNDA STRAIT BRIDGE by FX Supartono For ACF Seoul - Scribd
    The document summarizes the proposed Sunda Strait Bridge project, which would connect Java Island and Sumatra Island in Indonesia with a 29.5 km long bridge ...
  36. [36]
    Mega project for Indonesia | Global Highways
    The structure will feature six traffic lanes for cars, buses and trucks as well as twin rail tracks and additional lanes for motorcycles.Missing: specifications engineering
  37. [37]
    Connecting Java and Sumatra: Why Building a Sunda Strait Bridge ...
    Aug 3, 2024 · This massive construction could disrupt the rich marine ecosystem, destroy natural habitats, and threaten the lives of various marine species.
  38. [38]
    Sunda Strait | Research Starters - EBSCO
    The Sunda Strait is part of the so-called Ring of Fire, a region of the Pacific Ocean that experiences frequent volcanic and seismic activity. This activity is ...
  39. [39]
    [PDF] Seismotectonic and Probabilistic Seismic Hazard of Sunda Strait ...
    Abstract. The Sunda Strait region is the riskiest area between Java and Sumatra. The impact of seismic activities must be considered to reduce disaster risk ...
  40. [40]
    Krakatau - Global Volcanism Program
    Geologic map of Krakatau volcano complex, Sunda Strait, Lampung Province. ... Volcanic earthquake activity had decreased to background levels by early March 2011.Missing: fault | Show results with:fault
  41. [41]
    Sunda Strait tsunami launched by sudden collapse of Krakatau ...
    Dec 23, 2018 · This area of the world is best known for the 1883 eruption of Krakatau (or Krakatoa). This is a region of active tectonics and the deadly ...Missing: fault lines activity<|separator|>
  42. [42]
    Sunda Strait - Wikipedia
    It would use the islands of Ular, Sangiang and Prajurit to create a four-part suspension bridge reaching 70 metres (230 ft) above sea level. This bridge ...Sunda Strait Bridge · Battle of Sunda Strait · 2018 Sunda Strait tsunami<|separator|>
  43. [43]
    Study of Wind, Tidal Wave and Current Potential in Sunda Strait as ...
    Sunda Strait as one of the path of the water mass movement from Java Seas to ... Strait is wave energy (maximum wave height of 3.2 m and a period of 17 ...
  44. [44]
    [PDF] Seafloor Morphology Influences on Current Condition in a Sunda Strait
    This paper would perform a description about the effect of a seafloor morphology to the water current condition, especially along a Sunda Strait Bridge. Project ...
  45. [45]
    Quaternary deposition and erosion in the northeastern Sunda Strait
    Dec 1, 2024 · The northeastern Sunda Strait is a narrow strait separating Java and Sumatra islands. Currently, it forms a seaway between the Java Sea and the Indian Ocean.<|separator|>
  46. [46]
    [PDF] Chapter 4 Economic Assessment of the CADP - ERIA
    As a result, the total economic effect on the region as a whole is. 0.014% greater than the level expected when considering the size of the development project.Missing: projected | Show results with:projected
  47. [47]
    The Channel Tunnel - Global Infrastructure Hub
    Nov 30, 2020 · The speed and efficiency of transport offered by the Channel Tunnel has significantly increased trade interconnectivity between the UK and the ...Missing: comparison | Show results with:comparison
  48. [48]
    Indonesia - IMF DataMapper
    Indonesia. Indonesia. Datasets. World Economic Outlook (October 2025) 15 indicator s , 1980 - 2030. Collapse all. Real GDP growth. Annual percent change. 4.9.
  49. [49]
    (PDF) Conceptual Design of Sunda Strait Bridge Using Value ...
    Sunda Strait Bridge (SSB) is a mega-infrastructure project offered by the Indonesian government, expected to contribute to national economic growth by bridging ...Missing: details | Show results with:details
  50. [50]
    SUNDA STRAIT BRIDGE IN INDONESIA TO GENERATE ...
    Jun 18, 2010 · "The Sunda strait bridge presence will help shift industry to the area so that the density in Java could be reduced. After all, the flow of ...
  51. [51]
    Navigational Regimes of Particular Straits, Sunda and Lombok case ...
    Sunda Strait, located between the Indonesian islands of Sumatra and Java, provides the major sea link between the Indian Ocean and the Java Sea and into ...
  52. [52]
    Sunda strait bridge's construction to take 10 years - ANTARA News
    Sep 29, 2011 · The JSS would be 60 meters wide and have three lanes among others for roads and railway tracks.
  53. [53]
    financial feasibility of the sunda strait bridge conceptual design ...
    Aug 8, 2025 · The life-cycle cost analysis by IRR and NPV approaches confirmed that SSB development with additional functions increased the internal rate of ...Missing: logistics | Show results with:logistics
  54. [54]
    Cost of Sunda Strait bridge may balloon to US$18.87 billion
    Apr 27, 2010 · ... bridge in the world, may cost as much as Rp 170 trillion (US$18.87 billion), almost double the initial estimate of $11 billion, an official said ...
  55. [55]
    Sunda Strait Bridge public-private partnership (PPP) - InfraPPP
    A consortium consisting of companies controlled by Tomy's Artha Graha Network and the governments of Lampung and Banten provinces as minority shareholders, ...
  56. [56]
    Insight: Sunda Strait Bridge and public-private partnership confusion
    Jul 26, 2012 · With the cost expected to reach Rp 225 trillion (US$24 billion) according to Deputy National Development Planning Minister Lukita D. Tuwo, this ...Missing: logistics savings<|separator|>
  57. [57]
    Sunda Strait Bridge project for Indonesia - Global Highways
    Plans are in hand in Indonesia for the Sunda Strait Bridge project. The Indonesian Government intends construction work to commence in 2014. The project ...Missing: MP3EI inclusion
  58. [58]
    Editorial: Intervention into $10b project - Fri, July 6, 2012
    Jul 6, 2012 · ... feasibility study on the US$10 billion Sunda Strait Bridge project appeared to be an act of insubordination, a “renegade” attitude that ...
  59. [59]
    Issues of the day: Sunda Strait Bridge and PPP confusion
    Jul 30, 2012 · Paradoxically, the partnership in the Sunda Strait's case might end up as public money injected into a private project. ... Your comments: If this ...
  60. [60]
    Sunda Strait Bridge befouled by Cabinet hi jinx - Fri, June 29, 2012
    Jun 29, 2012 · • The initiator : PT Graha Banten Lampung Sejahtera, a consortium that includes the Banten and Lampung administrations and PT Bangungraha ...
  61. [61]
    Financing Sunda Strait Bridge - Sun, July 17, 2011 - The Jakarta Post
    Jul 17, 2011 · If all contract work can be exempted from VAT and income tax, the project costs can be reduced by 11.5 percent. The next cost component is ...Missing: logistics | Show results with:logistics
  62. [62]
  63. [63]
    Sunda Strait Bridge project for Indonesia | Global Highways
    Financing has still to be finalised however with discussions on-going within Indonesia as to whether the project will be funded by private sources or the ...
  64. [64]
    Key Indonesia bridge project proves unfeasible | Global Highways
    Safety risks from earthquakes, tsunami, high tides and extreme weather conditions make the project impractical. A US$75.46 million feasibility study was carried ...Missing: concerns seismic
  65. [65]
    Sunda Strait bridge feasible to be built - ANTARA News
    Jul 11, 2013 · The minister said the feasibility studies on the bridge were related to its resistance to earthquake, volcanic activity, and sea current. "The ...
  66. [66]
    [PDF] Aerodynamic challenge and limitation in long-span cable-supported ...
    The main section of the bridge was designed as a typical three-span suspension bridge with the span arrangement of 510m + 1490m. + 510m and the deck cross ...
  67. [67]
    Flutter control optimization for a 5000 m suspension bridge with ...
    Mar 15, 2024 · The construction of bridges in the Sunda Strait in Indonesia, various straits in the Philippines, the Qiongzhou Strait and Taiwan Strait in ...
  68. [68]
    [PDF] Aerodynamic stabilization and robustness evaluation of cable ...
    Critical flutter speeds of Sunda Strait Bridge. With the emphasis on aerodynamic stabilization for super-long span length, a typical three-span suspension ...
  69. [69]
    Financial feasibility of the sunda strait bridge conceptual design ...
    Sunda Strait Bridge (SSB) is a mega-infrastructure project offered by the Indonesian government, expected to contribute to national economic growth by ...
  70. [70]
    Indonesia claims massive bridge project viable - Global Highways
    Construction of a 30km bridge spanning Indonesia's Sunda Strait would be viable according to Graha Banten Lampung Sejahtera, the consortium tasked with the ...
  71. [71]
    Stalled Discussions on Sunda Straits Bridge Project - En.tempo.co
    Aug 24, 2012 · ... bridge project estimated to cost about Rp200 trillion. This is particularly after Minister of Finance Agus Martowardojo objected to ...
  72. [72]
    Hatta says yes, Agus says no on Sunda bridge - Fri, October 5, 2012
    Oct 5, 2012 · ... bridge to connect Java and Sumatra islands that has a price tag estimated at least Rp 100 trillion. Or did it? Agus, who was one of the ...<|separator|>
  73. [73]
    [PDF] Politics, Risk, and White Elephants in Infrastructure PPPs
    Although public-private partnerships (PPPs) have long been seen as a potential filter for white elephants, warnings regarding the strict conditions for them to ...Missing: Sunda Strait Bridge bridges
  74. [74]
    Groundbreaking of Sunda Strait Bridge Project Unlikely to Occur in ...
    Jul 31, 2013 · Firstly, it can be financed by Indonesia's State Budget (APBN), or, secondly, by state-owned enterprises and the Graha Banten Lampung Sejahtera ...
  75. [75]
    (PDF) Forecasting Demand on Mega Infrastructure Projects
    Aug 6, 2025 · The lifecycle cost analysis using the IRR and NPV approach confirms The Sunda Strait Bridge (SSB) project with additional functions increases ...
  76. [76]
    Proyek Jembatan Selat Sunda Rp200 Triliun Masih Tertunda ...
    Sep 4, 2023 · Alasan lain adalah karena potensi dampak lingkungan yang besar dari proyek ini. Jembatan Selat Sunda akan melintasi jalur migrasi ikan dan ...
  77. [77]
    PATHOLOGIES OF PLANNING (Studi Kasus : Jembatan Selat Sunda)
    Selain udara, faktor lingkungan yang perlu dipertimbangkan juga adalah ekosistem laut. Karena, proyek JSS ini berpotensi mengancam/merusak keanekaragaman biota ...
  78. [78]
    50 Persen Pengembangan Jembatan Selat Sunda Untuk Lingkungan
    Apr 29, 2014 · Selain itu, kata Agung, Selat Sunda, akan menjadi jalur akses yang lambat laun dapat menggantikan peran signifikan dari Selat Malaka bagi akses ...<|separator|>
  79. [79]
    assessing the local community readiness to sunda strait
    ASSESSING THE LOCAL COMMUNITY READINESS TO SUNDA STRAIT BRIDGE DEVELOPMENT PLAN Download ...
  80. [80]
    impact assessment of sunda strait bridge utilization to economy ...
    The objective of the present study is to identify how Sunda Strait Bridge will affect in economic condition and accessibility to public services in Cilegon ...
  81. [81]
    Ini Alasan Jokowi Tak Akan Lanjutkan Proyek Jembatan Selat Sunda
    Nov 2, 2014 · Pemerintah Joko Widodo berpotensi besar menghentikan pembangunan megaproyek Jembatan Selat Sunda karena dianggap mematikan identitas maritim ...
  82. [82]
  83. [83]
    [PDF] The Economic and Maritime Impact of Indonesia's Sea-Toll Road ...
    1.2 Sea-Toll Road Project​​ The aim of this policy was to bridge the discrepancy between the regions by subsidizing the logistic costs, in terms of vessel voyage ...
  84. [84]
    [PDF] RECENT DEVELOPMENTS AND NAVIGATING INDONESIA ...
    Sep 27, 2024 · Each province has a strategic role in driving the overall economic growth rate ... Percentage contribution of GDP from renovating damaged schools.
  85. [85]
    Three Options for Sunda Strait Project - En.tempo.co
    Sep 1, 2009 · Government will decide on options about how to connect the islands of Sumatra and Java via the Sunda Strait in October.