Gotthard Base Tunnel

The Gotthard Base Tunnel is a railway base tunnel through the , extending 57 kilometres from Erstfeld in canton to Bodio in canton, and constituting the core segment of the (). With two parallel single-track bores maintaining a nearly flat profile at an elevation of around 550 metres above , it enables high-speed passenger trains up to 250 km/h and heavy freight trains, slashing transit times across the by up to an hour compared to legacy routes. Construction spanned 17 years from 1999 to 2016, involving four boring machines that excavated approximately 28 million cubic metres of rock under depths reaching 2,300 metres, with total project costs amounting to CHF 12 billion funded primarily through Swiss federal taxes and fees. The 's engineering overcame severe geological challenges, including fault zones with squeezing rock and geothermal gradients exceeding 40°C per , necessitating innovative supports, cooling systems, and protocols. Since its official opening on 1 2016 and commencement of regular operations in December, the GBT has handled over 100 trains daily, boosting rail's for transalpine freight while facing operational hurdles like a 2023 derailment from a freight failure, which exposed gaps in European and spurred stricter safety regulations. This infrastructure exemplifies causal engineering realism in prioritizing durable, low-gradient routing over topographic concessions, though initial cost estimates proved optimistic amid unforeseen subsurface complexities.

Overview and Technical Specifications

Route and Dimensions

The Gotthard Base Tunnel consists of two parallel single-track tunnels spanning 57 kilometres between the north portal at Erstfeld in canton and the south portal at Bodio in canton, forming the core of Switzerland's New Alpine Transverse Railway (NEAT) project. The route traverses the Gotthard massif at a base level significantly below the existing summit tunnel, enabling flatter gradients and higher speeds compared to the 1882 . The north portal lies at 460 metres above east of the Reuss River, while the south portal is at 312 metres above near Biasca. Inside the tunnel, the profile reaches a maximum of 550 metres near Sedrun in Graubünden before descending southward, with an overall maximum rock of 2,300 metres. This configuration results in maximum gradients of approximately 0.4%, facilitating speeds up to 160 km/h and trains up to 250 km/h. Intermediate multi-function stations at Amsteg, Sedrun, and Faido provide access for , , and , connected via cross tunnels to the main bores spaced 40 metres apart. The main tunnels feature an excavated ranging from 8.8 to 9.5 metres, with cross-passages every 312 to 325 metres for operational connectivity and safety.

Engineering and Design Features

The Gotthard Base Tunnel consists of two single-track main extending 57 km from Erstfeld to Bodio, designed to enable operations with passenger trains reaching up to 250 km/h and freight trains up to 160 km/h. The maintain a separation of 40 m between their axes under normal conditions, increasing to 70 m in fault zones to enhance against geological stresses. This twin-tube configuration provides physical separation of opposing traffic directions, minimizing collision risks and facilitating independent evacuation or ventilation in emergencies. The main tubes have an excavation diameter of approximately 9.4 m, lined to support long-term operational loads with concrete designed for a 100-year lifespan. Connecting the tubes are 176 cross-passages, spaced at intervals of 312.5 to 325 m, which serve as escape routes during incidents and allow for maintenance access while maintaining pressure balance between tubes. The tunnel's alignment features minimal curvature and gradients not exceeding levels compatible with high-speed travel, ensuring aerodynamic efficiency and reduced energy consumption. Safety design incorporates two multi-function stations at Sedrun (approximately one-third along the route) and Faido (two-thirds), equipped with crossovers for bypassing, emergency evacuation platforms, and connections to surface access via shafts. These stations enable rapid intervention, with the overall system relying on longitudinal to extract and supply through vents and side passages during fires, supported by heat detection, sensors, and thermal imaging for early warning. Cooling and addresses geothermal from the tunnel's maximum of 2,500 m, maintaining operable temperatures for both routine and emergency scenarios. Surface drainage systems using permeable gravel layers manage ingress, preventing hydrostatic pressures on the lining.

Historical Development

Early Planning and Proposals

The concept of a base tunnel through the Gotthard massif emerged in amid discussions on improving transit infrastructure, with initial proposals focusing on bypassing the steep gradients of the existing 1882 Gotthard rail tunnel. These early ideas prioritized a flatter, more efficient route to handle growing freight and passenger volumes, driven by Switzerland's need to maintain transcontinental rail links without reliance on road alternatives. In 1947, Swiss engineer Carl Eduard Gruner advanced the notion with a specific proposal for a two-story base tunnel spanning approximately 60 kilometers from Amsteg to Biasca, incorporating both rail and road levels with an intermediate stop at Sedrun to facilitate operations. Gruner's design emphasized geological stability and reduced travel times, addressing the limitations of the helical original tunnel, though it faced delays due to post-war economic constraints and competing priorities for highway development. By 1961, the Swiss Federal Department of Home Affairs formalized the first detailed project for a base tunnel, evaluating routes, variants, and connections to the existing network while conducting preliminary geological assessments. This initiative gained renewed momentum in the early 1970s, shifting focus from an tunnel to a dedicated rail solution amid rising concerns over truck and environmental impacts on passes. Exploratory boreholes and feasibility studies in the subsequent decade refined alignments, incorporating insights from seismic data and to mitigate risks like water ingress and fault zones identified in earlier surveys. These efforts culminated in the integration of the Gotthard scheme into the broader New Railway Link through the Alps (NRLA) framework by the mid-1980s, setting the stage for federal funding debates.

Political Approvals and Funding

The Gotthard Base Tunnel formed a core component of the (NRLA, or NEAT in German), a federal initiative aimed at enhancing transalpine rail capacity by constructing flat base tunnels to facilitate faster freight and passenger services across the . Swiss voters approved the NRLA project in a national held in 1992, with a clear endorsing the construction of the Gotthard, Lötschberg, and Ceneri base tunnels despite debates over environmental impacts and initial cost estimates of approximately CHF 6.3 billion for the Gotthard segment alone. This approval followed parliamentary endorsement and reflected Switzerland's emphasis on for major infrastructure, overriding concerns from environmental groups and cantonal opponents who argued the tunnels would disrupt alpine ecosystems without proportional economic benefits. Funding for the , including the Gotthard Base Tunnel, was secured through a separate 1998 national , where voters approved a dedicated financing mechanism tied to the introduction of the performance-related Heavy Vehicle Fee (HVF, or LSVA), designed to internalize the external costs of freight transport and incentivize a shift to . The HVF, levied on heavy goods vehicles based on weight, emissions, and configuration, contributed about 60% of the NRLA's overall funding, supplemented by 10% from taxes and 30% from value-added tax () allocations from the federal budget. This structure allocated roughly CHF 30 billion over two decades for the broader NRLA program, with the Gotthard Base Tunnel's share ultimately totaling CHF 12 billion upon completion—nearly double the initial projection due to geological challenges, scope changes ordered by the Federal Office of Transport, and inflation, though still within the expanded federal credit framework approved post-referendum. Subsequent bilateral agreements with the , ratified by voters on May 21, 2000, reinforced the funding model by linking HVF revenues to commitments on maximum vehicle weights (40 tonnes) and freight prioritization, ensuring long-term viability amid cross-border pressures. No additional referendums were required for the Gotthard project after , as cost overruns were managed through federal adjustments rather than new public votes, reflecting parliamentary oversight prioritizing completion over strict initial budgeting.

Construction Process

Timeline and Excavation Methods

The construction of the Gotthard Base Tunnel commenced with preparatory works at the Sedrun site in April 1996, followed by the official start of excavation on 4 November 1999 at the Amsteg access point. Major tunneling advanced from multiple portals, including Erstfeld in the north, Sedrun and Faido in the central section, and Bodio in the south, with the first tunnel boring machine (TBM) breakthrough occurring on 6 September 2006 between Sedrun and Faido. Subsequent milestones included a drill-and-blast breakthrough on 23 September 2009 in the western tube's central section and the final main tube breakthroughs on 15 October 2010 (eastern tube) and 23 March 2011 (western tube). Fitting-out and testing phases followed, with trial operations beginning in October 2015, leading to the tunnel's inauguration on 1 June 2016 and full commercial service in December 2016.
Key DateEvent
April 1996Preparatory works begin at Sedrun.
4 November 1999Official excavation starts at Amsteg.
6 September 2006First TBM breakthrough (Sedrun-Faido).
23 September 2009Central section drill-and-blast breakthrough (western tube).
15 2010Eastern tube main breakthrough.
23 March 2011Western tube main breakthrough.
2015Trial operations commence.
1 June 2016Inauguration.
December 2016Full service begins.
Excavation employed a hybrid approach tailored to geological conditions, with approximately 75% of the main 57-kilometer single-track tubes driven by four hard-rock TBMs, each with a 9.43-meter cutterhead, operating from the Erstfeld-Bodio and Sedrun-Faido sections. These machines advanced at rates up to 40 meters per day in competent rock, installing segmental lining immediately behind the face for stability. The remaining length, including cross passages, ventilation shafts, and areas of faulted or weak rock such as the , utilized conventional drill-and-blast methods, involving full-face or systematic advance cycles with rock bolts, , and steel arches for support. This combination allowed adaptation to the tunnel's exceeding 2,500 meters and variable rock types, from to , minimizing risks in squeezing ground while optimizing progress. Over 28 million cubic meters of rock were removed in total.

Key Challenges and Safety Incidents

The construction of the Gotthard Base Tunnel encountered significant geological challenges due to the terrain's complexity, including varied rock formations such as Penninic , Gotthard , and Piora sedimentary rocks, which complicated excavation stability. High overburden pressures reaching up to 2,500 meters exacerbated risks of rock deformation and required advanced geotechnical monitoring to manage surface and tunnel lining stresses. Fault zones, particularly cataclastic ones, posed hazards of high-pressure inflows, necessitating pre-grouting and sealing techniques to prevent flooding during tunneling. Squeezing rock conditions were prominent in sections like Sedrun and the Northern Tavetsch, where weak, deformable strata caused , demanding innovative supports such as yielding elements in linings and systematic rock mass "calming" through controlled deformation rather than rigid reinforcement. Conventional excavation methods were employed in these unstable areas instead of boring machines, with arch pre-supports to mitigate collapses. Environmental strains included ambient temperatures inside the exceeding 45°C—well above the workplace safety limit of 28°C—prompting enhanced and cooling systems to sustain worker productivity over extended shifts. Safety incidents during construction resulted in nine worker fatalities, attributed to various accidents in the hazardous environment; the victims included four , three , one South African, and one national. These deaths occurred amid rigorous protocols, including monitoring of rock pressures and emergency response training, which limited the toll compared to the 199 fatalities in the 19th-century construction. No single large-scale collapse or influx event was publicly detailed as causing multiple deaths, underscoring the efficacy of phased excavation and support installation despite the project's scale.

Costs, Workforce, and International Involvement

The Gotthard Base Tunnel's construction incurred significant costs, with the final expenditure reaching CHF 12.2 billion (approximately or €11 billion) upon completion in 2016. This figure represented an overrun from the initial 1998 projection of CHF 6.323 billion, escalating due to extended timelines, geological complexities, and scope adjustments within the broader New Railway Link through the Alps (NRLA) program. Funding was primarily sourced from the Swiss federal government through voter-approved initiatives, including a 1992 referendum allocating CHF 1.3 billion initially, supplemented by later bonds and taxes dedicated to rail infrastructure without reliance on subsidies. The project employed a peak workforce of around 2,600 personnel during active excavation phases, with up to 2,400 workers engaged over the 17-year construction period from 1999 to 2016. Labor was organized in round-the-clock shifts across multiple sites, involving skilled tunneling crews, engineers, and support staff, with total man-hours exceeding those of comparable projects due to the tunnel's scale and safety requirements. International involvement was substantial, with contractors and workers from approximately 15 countries contributing to specialized tasks such as (TBM) manufacturing and supply. German firm AG provided four hard-rock TBMs critical for the main tubes, while Austrian company Getzner Werkstoffe supplied materials for the . A Swiss-led , AlpTransit Gotthard AG, oversaw integration, but foreign expertise in (e.g., ABB-TLT Turbo) and consulting enhanced efficiency without compromising national control.

Commissioning and Early Operations

Inauguration Event

The Gotthard Base Tunnel was officially inaugurated on June 1, 2016, marking the completion of 17 years of construction since the initial blast in 1999. The event featured a five-hour ceremony divided into segments for dignitaries and the public, with festivities held at portals in Erstfeld (north) and Bodio (south), attracting over 100,000 visitors overall. High-profile attendees included German Chancellor Angela Merkel, French President François Hollande, and Italian Prime Minister Matteo Renzi, alongside Swiss Federal Council members and representatives from funding nations. The official program emphasized the tunnel's engineering significance, with speeches highlighting its role in enhancing trans-Alpine rail connectivity, followed by the symbolic breakthrough reenactment and the first passage of a special train. A central element was a theatrical performance directed by German artist Volker Hesse and produced by Swiss broadcaster SRF, intended to artistically depict the tunnel's construction history, , and the interplay between humans and . The show incorporated hundreds of performers portraying miners, workers, and mythical figures such as , goats, and haystacks in choreographed sequences simulating excavation struggles, worker sacrifices (referencing 9 fatalities during building), and elemental forces like avalanches and underground spirits. Surreal vignettes included dancers in provocative poses, a single figure emerging from a tunnel-like structure, and group movements evoking ritualistic or pagan themes drawn from local legends. The performance elicited mixed reactions, with some praising its bold symbolism of labor and landscape taming, while others condemned its eccentricity and perceived indecency. figures, including a politician who misinterpreted haystack dancers as whirling dervishes, decried it as culturally alien or overly provocative, fueling online debates about taxpayer-funded excess (the event cost approximately 8 million Swiss francs). Fact-checks later clarified misattributions linking the footage to unrelated conspiracies, such as rituals, confirming it as a standalone artistic production without intent, though its opacity invited speculative interpretations absent explicit directorial clarification beyond . Following the ceremony, public trains traversed the tunnel for celebratory rides, but regular freight testing preceded passenger service rollout in December 2016.

Initial Service Implementation

Following the ceremonial inauguration on June 1, 2016, the Gotthard Base Tunnel entered a commissioning phase involving extensive test runs by Swiss Federal Railways (SBB), including up to 5,000 trains—predominantly freight—to validate systems and operational protocols before full public service. The first scheduled freight train traversed the 57-kilometer tunnel on June 3, 2016, marking the onset of limited commercial freight operations alongside continued testing, which facilitated early integration into the north-south rail corridor. Regular timetabled services for both passenger and freight trains commenced on December 11, 2016, after handover from the AlpTransit Gotthard AG consortium to SBB for operational control. The inaugural regular passenger train, an SBB InterCity service, departed Zurich at 6:09 a.m. and reached Lugano approximately 25 minutes faster than comparable old-route journeys, demonstrating immediate efficiency gains from the base tunnel's flat gradient and high-speed capability up to 250 km/h. Initial schedules incorporated around 50 daily passenger trains, primarily InterCity services linking Zurich to Milan and beyond, while freight operations ramped up to handle up to 260 trains per day in mixed traffic patterns, prioritizing separation via timed slots to maintain safety and capacity. SBB's early operational reports indicated smooth implementation, with the tunnel achieving near-target throughput in the first weeks—handling thousands of passengers and tens of thousands of tonnes of freight daily—without major disruptions, though signaling and ventilation systems underwent real-time adjustments to optimize bidirectional flows. This phased rollout aligned with the New Railway Link through the Alps (NRLA) project goals, enabling faster trans-Alpine connectivity while adhering to strict European Train Control System (ETCS) Level 2 standards for automated train protection. By late December 2016, journey times on key routes like Zurich-Milan had stabilized at reductions of 30-60 minutes compared to the legacy Gotthard route, underscoring the tunnel's role in enhancing reliability amid variable Alpine weather.

Operational Performance

Passenger Traffic and Travel Efficiency

The Gotthard Base Tunnel facilitates approximately 50 passenger trains daily under normal operations, primarily services connecting northern to and . In its early years following the December 2016 opening, the tunnel accommodated an average of 11,000 passengers per day, representing a 30% increase over the previous Gotthard route's volume. Passenger traffic grew steadily thereafter, with projections estimating up to 15,000 daily users by 2021, driven by enhanced connectivity along the north-south axis. However, a on August 10, 2023, led to a year-long partial closure for passenger services until September 2, 2024, during which trains were rerouted over the higher line, reducing tunnel-specific volumes to near zero for passengers. Post-reopening, (SBB) restored full passenger access, with weekend services increasing from 31 to 38 trains starting March 2024 to accommodate rising demand. The tunnel's design enhances travel efficiency by enabling consistent speeds of up to 250 km/h on a flat, gradient-free alignment, eliminating the steep inclines and curves of legacy routes that previously capped velocities at 100-140 km/h. This results in a reduction of Zurich-to-Milan journey times by approximately one hour, from over 3.5 hours pre-tunnel to about 2 hours 40 minutes with the integrated (NEAT) network, including the operational since 2020. Actual end-to-end times stabilized at around 3 hours 17 minutes following the 2024 reopening, reflecting operational realities like border procedures and track sharing with freight. Reliability improves markedly due to the subsurface routing, avoiding weather-related disruptions such as snow or landslides that historically affected surface passes, thereby minimizing delays and enabling a half-hourly timetable for key intercity links. Capacity for passengers remains underutilized relative to the tunnel's potential for up to 250 daily trains, as priority allocation favors freight to alleviate road congestion on parallel highways. This prioritization, while boosting overall system efficiency, has prompted SBB to incrementally expand slots, such as the 2024 weekend enhancements, to capture growing transalpine demand amid Europe's shift toward for short-haul travel. Empirical data indicate a 30% post-opening surge in ridership, underscoring the causal link between reduced transit times and modal shift from automobiles, though full economic benefits hinge on sustained balancing.

Freight Capacity and Economic Role

The Gotthard Base Tunnel provides a designed daily for up to 260 freight trains, each permitted to operate at speeds of 100 km/h, substantially exceeding the constraints of the legacy Gotthard route's summit tunnel. This infrastructure, integrated into Switzerland's New Railway Link through the (NEAT) program alongside the , targets an annual freight throughput of approximately 50 million tonnes along the north-south axis, more than doubling the prior volume of around 20 million tonnes. Freight trains average lengths of 434 meters and loads of about 1,080 tonnes, enabling efficient handling of intermodal containers and bulk goods primarily along the Rotterdam-Genoa Rhine-Alpine freight corridor. Economically, the tunnel bolsters transalpine trade by shortening transit times from northern Europe to Italy by up to an hour for freight services, fostering reliability for industries reliant on just-in-time logistics and reducing vulnerability to weather-induced delays on legacy routes. It supports Switzerland's federal policy of modal shift, which has diverted over 650,000 heavy goods vehicles annually from Alpine roads since the early 2000s through tonnage limits and rail subsidies, thereby mitigating road wear, emissions, and accident risks associated with truck dominance. In its first year of partial freight operations (2017), the tunnel accommodated over 17,000 trains, transporting roughly 67,000 tonnes daily, contributing to a measurable uptick in rail market share for cross-Alpine goods despite initial ramp-up limitations. The tunnel's role extends to regional , enhancing supply chain efficiency for manufacturing hubs in , , and while aligning with (TEN-T) objectives for sustainable freight corridors. Empirical assessments indicate sustained growth in rail freight volumes post-opening, driven by competitive rail tariffs and reliability, though actual reductions have proven modest in some econometric analyses, underscoring the persistence of trucking in short-haul segments. Overall, it reinforces Switzerland's position as a transit hub, with freight revenues underpinning ' investments in and signaling upgrades to sustain long-term throughput.

Safety Protocols and Record

The Gotthard Base Tunnel integrates advanced safety protocols prioritizing , rapid detection, and controlled emergency response within its 57 km single-bore configuration. The (ETCS) Level 2 governs train operations via cab signaling, eliminating lineside signals and enforcing automatic speed supervision, emergency braking, and movement authority to avert collisions or derailments from . Fire safety relies on automated sensors for early detection of smoke, heat, or hazardous materials like hot axles, triggering immediate alerts and isolation measures before trains fully enter the tubes. Comprehensive video surveillance with over 160 cameras monitors critical sections, supplemented by environmental sensors for real-time . Ventilation systems form a core defensive layer, featuring 24 high-capacity jet fans and extraction units designed to extract smoke longitudinally while injecting through cross-passages and vents, maintaining visibility and breathable conditions during events. Two multifunctional emergency stations at Sedrun (1,334 m elevation) and Faido (757 m elevation) serve as evacuation hubs, housing firefighting equipment, medical facilities, and access points for rescue teams, with pressurized cross-tunnels enabling safe pedestrian transit between bores. These protocols adhere to and railway standards, emphasizing prevention over reaction through redundant power supplies, seismic monitoring, and periodic drills coordinated by (SBB). Since full timetabled service commenced on 11 December 2016, the tunnel has facilitated up to 260 freight and 50 passenger trains daily, cumulatively handling over 17,000 freight trains in its first operational year alone and millions of passengers annually thereafter, with no fatalities or major passenger injuries recorded in standard operations. This record reflects the efficacy of ETCS and monitoring systems in maintaining , though freight-specific vulnerabilities—such as wheel fatigue—have prompted post-incident enhancements like stricter inspections and risk controls following the 2023 , which caused structural damage but no casualties. Overall uptime exceeds 99% outside maintenance windows, underscoring causal links between proactive protocols and minimized disruptions in high-volume alpine transit.

Major Incidents and Responses

2023 Freight Derailment

On August 10, 2023, a operated by SBB Cargo derailed within the Gotthard Base Tunnel, disrupting rail operations through the 57 km . The train, designated 45016, comprised two locomotives and 30 wagons of varying types and ownership, traveling southbound when 16 wagons derailed in the western bore near the Sedrun intermediate access point. No injuries occurred, but the incident caused significant structural damage to the slab track, emergency systems, and a track switch, initially underestimated but later assessed as requiring extensive repairs estimated at over 100 million Swiss francs. The primary cause was a fractured disc on a BA 390-type , leading to loss of wheelset stability and subsequent . The Swiss Accident Investigation Board () final report, released in June 2025, confirmed this through metallurgical analysis, attributing the fracture to fatigue cracks that propagated undetected despite routine inspections. Investigations revealed potential systemic vulnerabilities in similar wheels across freight fleets, as manufacturing defects or maintenance gaps may affect multiple units, prompting concerns over broader fleet safety. Repairs involved removing debris, replacing over 1 km of damaged slab track, and restoring signaling, with the tunnel partially operational via the eastern bore during the closure. Full reopening of both bores occurred on September 5, 2024, after 389 days of intensive work by SBB crews. In response, the Swiss Federal Office of Transport mandated enhanced wheel inspections, ultrasonic testing protocols, and phased retirement of BA 390 wheels in September 2025 to mitigate recurrence risks. These measures address identified lapses in defect detection, underscoring ongoing challenges in maintaining high-speed freight integrity within the tunnel's demanding environment.

Investigations, Repairs, and Regulatory Changes

The Swiss Accident Investigation Board (SUST) conducted a detailed probe into the August 10, 2023, freight train derailment, releasing an interim report on September 28, 2023, and a final report on June 2, 2025, which confirmed that a fractured wheel disc on a BA 390-type wheel of a freight wagon initiated the incident. The fracture stemmed from undetected cracks propagating under cyclic loading and thermal stresses, potentially indicating a broader vulnerability in similar wheelsets across the European fleet. Repair efforts by (SBB) addressed severe infrastructure damage, including derailed wagons that mangled approximately 700 meters of slab track, rails, and ties between the Sedrun and Faido portals. The total cost reached an estimated 150 million Swiss francs (approximately 176 million USD at the time), encompassing direct repairs and revenue losses from tunnel closures. Partial operations resumed for passengers by December 10, 2023, via a single track, but full bidirectional freight and passenger capacity was not restored until September 2, 2024, following 389 days of intensive , testing, and trial runs. In response, the Swiss Federal Office of Transport implemented stricter freight wagon safety regulations in September 2025, mandating minimum wheel diameters, enhanced ultrasonic inspection frequencies for wheelsets, and revised maintenance protocols to mitigate fatigue-related failures. These unilateral measures, applied specifically to Gotthard Base Tunnel transits, have drawn criticism from rail freight operators and wagon owners for potentially disrupting cross-border without coordinated EU-wide standards, prompting threats of legal challenges from affected companies. Swiss freight associations have similarly contested the rules as overly burdensome, arguing they could inadvertently shift cargo to roads.

Economic and Strategic Impacts

Achievements in Connectivity and Efficiency

The Gotthard Base Tunnel has significantly enhanced north-south rail connectivity across the European Alps, forming a key segment of the trans-European freight corridor. By providing a direct, high-capacity rail link beneath the Gotthard massif, it facilitates seamless integration between northern European economic centers like and with southern hubs in , reducing reliance on circuitous mountain routes and supporting the European Union's (TEN-T) objectives. Following its operational start on June 1, 2016, passenger travel times along the axis were reduced by approximately one hour to 2 hours and 40 minutes, enabling up to 70 daily passenger trains at speeds of 250 km/h. In terms of efficiency, the tunnel's near-flat profile—with a maximum gradient of 0.4% and broad-radius curves—allows for consistent high speeds without the braking and acceleration demands of the legacy Gotthard line, which had steeper inclines exceeding 20‰. This design supports longer, heavier freight trains carrying up to 4,000 tons at 160 km/h, doubling the route's overall freight capacity from prior levels of around 180 trains per day to a designed maximum of 260. Operational data post-opening confirm improved reliability, with fewer locomotives required per train and lower per-unit production costs for freight haulers, promoting a modal shift from trucks to rail and alleviating alpine road congestion.

Criticisms, Costs, and Overruns

The Gotthard Base Tunnel's construction budget was initially estimated at approximately CHF 6 billion in the late , but the final cost reached CHF 12.2 billion by completion in , representing an overrun of over 100%. Geological challenges, including unexpected rock formations and water ingress during tunneling, contributed significantly to these escalations, necessitating additional measures and contingency funds. Critics, including fiscal watchdogs and opposition parliamentarians, argued that the overruns strained finances, with the project financed entirely through taxpayer credits and bonds without external subsidies, diverting resources from other needs. The Federal Audit Office highlighted in reports that cost management relied on adaptive financing models, yet early underestimations of subsurface risks amplified the financial burden. Environmental groups raised concerns over potential long-term ecological impacts, such as surface and disruption from tunneling activities, though efforts like real-time monitoring limited observed damage. Safety criticisms during construction focused on worker hazards in the deep alpine geology, with incidents of rockfalls and flooding prompting enhanced risk protocols, but no fatalities were reported among the 2,400 peak workforce. Despite the cost excesses, the project avoided major schedule delays, achieving in 2010 and operational readiness by the planned 2016 opening, contrasting with overruns in comparable megaprojects. Post-completion analyses attributed the overruns to inherent uncertainties in base tunnel rather than mismanagement, underscoring the causal role of geological variability in such endeavors.

Future Prospects

Capacity Expansion Projects

The Gotthard Base Tunnel's design supports up to 260 freight trains and 70 passenger trains daily at speeds of 200–250 km/h for passengers and 100–160 km/h for freight, enabling a theoretical maximum throughput of over 330 trains per day under optimal conditions. Following the full restoration after the 2023 derailment, the (SBB) achieved this operational capacity by September 2, 2024, with enhanced signaling via the (ETCS) Level 2 facilitating denser train intervals of approximately 15 minutes. Timetable adjustments implemented from December 10, 2023, prioritized weekday freight slots, adding paths for up to 10 additional daily freight trains while maintaining mixed operations to balance passenger and cargo demands. Access line upgrades form a core component of capacity realization, as bottlenecks outside the tunnel limit effective utilization. The Ceneri Base Tunnel, the southern NRLA segment measuring 15.4 km, entered full service in December 2024, enabling end-to-end flat routing at up to 250 km/h and boosting southbound capacity from 290 to 400 trains per day across the Gotthard axis. Complementary projects include station expansions, such as at , where infrastructure enhancements accommodate heightened volumes from the Gotthard and Ceneri tunnels, incorporating additional tracks and signaling to prevent cascading delays. North of Erstfeld, capacity enhancements between Arth-Goldau and the portal address pinch points through track duplications and electrification improvements, aligning with the "Bahn 2030" initiative to sustain throughput. Long-term sustainability projects ensure enduring capacity without major structural overhauls. SBB plans comprehensive rail renewal between 2032 and 2034, replacing the initial concrete sleepers and tracks to preserve high-speed integrity amid cumulative wear from heavy freight loads exceeding 2,000 tons per train. These interventions, budgeted under routine , incorporate upgraded materials for reduced and extended service life, indirectly supporting denser operations by minimizing speed restrictions. While operational tweaks like longer 1,400-meter freight trains have already doubled pre-tunnel freight volumes on the route, no approved infrastructure for a parallel bore exists; preliminary studies for further scaling remain exploratory amid debates over cost and environmental impact. Parallel relief via the Lötschberg Base Tunnel's full double-tracking by 2034 will distribute Alpine loads, indirectly easing Gotthard pressures without direct expansion.

Maintenance and Long-Term Sustainability

The Gotthard Base Tunnel's maintenance regime prioritizes minimal operational disruption given its role in handling up to 260 freight and 65 passenger trains daily. The (SBB) utilizes integrated planning software to coordinate activities such as track slab inspections, ventilation shaft servicing, and electrical system overhauls, often scheduling them during overnight possession times to avoid peak-hour interference. Access for these tasks occurs via dedicated portals at Amsteg (507 m elevation), Sedrun (1,334 m), and Faido (757 m), supplemented by cross-passages and ventilation tunnels totaling over 150 km in the network. Post-incident repairs underscore the robustness of these procedures; following the August 10, 2023, caused by a failure, approximately 7 km of slab and associated in the western bore were rebuilt, restoring full bidirectional service by September 2, 2024. The tunnel's slab design, laid on a 35-40 cm thick base without , demands specialized non-disruptive interventions, including robotic inspections and for wear detection to extend beyond initial 100-year projections. Long-term sustainability hinges on addressing hydrological and geomechanical stressors inherent to the 2.5 km and fractured crystalline rock. Inflow management involves continuous pumping from intercepted aquifers, averaging several liters per second across 122 major fractures identified during , to maintain dry conditions and prevent hydrostatic pressure buildup. However, this induces subsurface and surface , with models attributing up to 5-10 cm of cumulative in overlying valleys since 2016, necessitating geospatial monitoring and potential injection for stabilization. The double-shell lining—comprising outer shells and reinforced inner —resists squeezing ground pressures observed in fault zones like Piora, where rates stabilized post-construction through systematic anchoring and yielding supports. Ventilation and systems, including longitudinal airflow without mechanical aids in the main tubes, support energy-efficient operations, aligning with Switzerland's transit policy to curb road freight emissions by 30% via modal shift. Periodic full-system audits, mandated under TSI standards adapted for , ensure resilience against seismic activity (up to magnitude 6.5) and climate-driven thaw, though escalating repair demands from intensive use may require capacity upgrades by 2035.

References

  1. [1]
    The New Rail Link through the Alps NRLA - UVEK
    The Gotthard Base Tunnel went into operation in 2016 and, at 57 kilometres, is the longest railway tunnel in the world. It took 17 years to build. The existing ...
  2. [2]
    [PDF] The Gotthard Base Tunnel - admin.ch
    Cost of the Gotthard Base Tunnel: CHF 9.7 billion (cost dating from 1998 ... Official opening of the Gotthard Base Tunnel: 11 December 2016. Page 7 ...Missing: specifications | Show results with:specifications
  3. [3]
    The Gotthard Base Tunnel - Alptransit Portal
    In 1962 the company develops the first project for a Gotthard Base Tunnel, which would have connected Amsteg with Giornico.
  4. [4]
    Ceneri - ticino.ch
    The tunnel of the records ; Total length of tunnels. 152 km ; Maximum depth. 2300 m ; Excavated materials. 28.2 m tons ; Real cost. CHF 12 bn ...
  5. [5]
    Gotthard Base Tunnel: Surveying the Drive, Laser Scanning and ...
    The Gotthard Base Tunnel runs from its north portal at Erstfeld through the Swiss Alps to the south portal at Bodio. With rock overburden of up to 2300 m the ...Missing: website | Show results with:website
  6. [6]
    Gotthard Base Tunnel - Herrenknecht AG
    The Gotthard Base Tunnel connects Erstfeld and Bodio at a length of 57 kilometers. On June 1, 2016, the longest railway tunnel in the world opened its doors.
  7. [7]
    Gotthard accident: Wheel defect pinpoints systemic safety flaw
    Feb 27, 2025 · The disastrous derailment in the Gotthard Base Tunnel in August 2023 might have been caused by a systematic problem possibly affecting a great number of wagons.Missing: controversies delays
  8. [8]
    Swiss take measures to avoid repeat of Gotthard rail derailment
    Sep 12, 2025 · The Swiss Federal Office of Transport has issued new safety measures for freight wagons, aimed at preventing further accidents such as the ...Missing: controversies delays
  9. [9]
    Gotthard Base Tunnel, Switzerland - Railway Technology
    Sep 17, 2021 · The test operations for Gotthard Base Tunnel began in October 2015 and the tunnel was officially opened in June 2016. Commercial train ...Missing: specifications depth<|separator|>
  10. [10]
    The world's longest rail tunnel: the Gotthard Base Tunnel - DW
    May 30, 2016 · The 57-kilometer (35-mile) two-single track Gotthard Base Tunnel links Erstfeld in the Uri canton and Bodio in the southern canton of Tessin.Missing: length | Show results with:length
  11. [11]
    [PDF] GOTTHARD BASE TUNNEL, SWITZERLAND EXPERIENCES WITH ...
    The Gotthard Base Tunnel consists of two parallel single-track tubes with an excavation diameter varying from. 8.8 to 9.5 m and linked by cross-passages ...Missing: gradient | Show results with:gradient
  12. [12]
    Gotthard Base Tunnel – Technical project ... - Wiley Online Library
    Apr 4, 2016 · The tunnel system consists of two parallel single-track tunnels with the axes 40 m apart (in fault zones up to 70 m), connected every 312.5 m ...Missing: spacing | Show results with:spacing
  13. [13]
    [PDF] building a modern railway line in the gotthard base tunnel | imia
    The technical solution developed by AlpTransit Gotthard fulfils all the project design specifications and consists fundamentally in: Twin tubes providing total ...Missing: engineering features
  14. [14]
    [PDF] Ventilation with Safety - HBI Haerter AG
    The main elements of the Gotthard base tunnel are shown on Fig. 1. The tunnel system is based on a physical separation of the two tracks (twin tube system). The ...
  15. [15]
    Gotthard Base Tunnel: High-accuracy at final breakthrough
    The moment of the 9.4 m diameter tunnel-boring machine's breakthrough in the Foto: ATG ... With the final breakthrough in the western bore the two 57 km long main ...
  16. [16]
    [PDF] Gotthard Base Tunnel, Switzerland - Sika Group
    1980 – OPENING OF THE ROAD TUNNEL The next Gotthard record belongs to the 16.9 kilometre road tunnel, inaugurated in 1980 and for many years the longest in the ...
  17. [17]
    NEW RAILWAY UNDER THE ALPS GOTTHARD BASE TUNNEL ...
    Feb 23, 2017 · In addition to the main tubes, 176 cross passages connecting the two tunnels were built, spaced every 325 metres. These were then finished with ...
  18. [18]
    Gotthard Base Tunnel: Construction of the Access Route in the ...
    The Gotthard Base Tunnel consists of two parallel, 57 km long single-track bores, which are linked to each other by means of 40 m long cross-passages at 325 m ...
  19. [19]
    Rail Technology for the Gotthard Base Tunnel
    Route alignment: High speeds call for as straight a route alignment as possible with only slight gradients. Curves in the AlpTransit project must have a ...
  20. [20]
    Gotthard Base Tunnel: Industrial Safety
    The 57 km long Gotthard Base Tunnel with its 2 single-track bores and 2 Multi-Function Stations 1/3rd and 2/3rds of the way along the tunnel with emergency ...
  21. [21]
    Keeping Europe's longest railway tunnel safe
    Jun 15, 2016 · Powerful ventilation systems are designed to extract smoke in the case of a fire on a train, and pump in fresh air through vents and side ...
  22. [22]
    Gotthard Base Tunnel - Siemens Global
    At 57 km long the tunnel is the longest railway tunnel in the world and the paradigm of modern tunnel technology.Missing: features specifications
  23. [23]
    A Swiss Engineering Team Designs a Ventilation System for the ...
    The GBT ventilation system must provide comfortable working conditions for maintenance staff and enable safe evacuation in the event of an emergency.
  24. [24]
    [PDF] DESIGN OF THE VENTILATION AND COOLING SYSTEM FOR THE ...
    The flexible venting and cooling system allows coping with possible deviations of the assumptions made during the design phase. Keywords: Gotthard Base Tunnel, ...
  25. [25]
    The Longest Tunnel in the World - NORMA Group Blog
    Oct 19, 2017 · The Gotthard Base Tunnel specially deploys so-called surface drainage. It consists of layered gravel which allows water to seep through. Below ...
  26. [26]
    The Gotthard Base Tunnel – 60 years in planning
    Ideas for a base tunnel were first developed in the 1930s. In the early 1970s the idea for a railway base tunnel instead of the autobahn tunnel was again taken ...Missing: proposals | Show results with:proposals
  27. [27]
    Impulse Lecture by Heinz Ehrbar in Munich/D - tunnel
    During the 1930s, the initial proposals for a Base Tunnel were developed. ... On 1 June 2016, 17 years after the first blast in the main tunnel, the Gotthard Base ...<|control11|><|separator|>
  28. [28]
    World's Longest and Deepest Rail Tunnel, Through Swiss Alps, Opens
    Jun 1, 2016 · In 1947, the Swiss engineer Carl Eduard Gruner proposed a Gotthard base tunnel, between Amsteg and Bodio, but the route had to be altered ...Missing: early | Show results with:early
  29. [29]
    The Gotthard Base Tunnel and Sedrun
    Jun 11, 2010 · The first ideas for the Gotthard base tunnel were raised in 1947. A first preliminary project design was developed in 1962. Approval for the ...Missing: early proposals
  30. [30]
    Planning | Alptransit-Portal
    The first project for a Gotthard base tunnel dates back to 1961. From that time onwards, plans are drawn up for routes, tunnel variants, approaches, new ...Missing: proposals | Show results with:proposals
  31. [31]
    Yes to the NRLA - Events | Alptransit-Portal
    Swiss voters approve the NRLA proposal by a clear majority, paving the way for construction of the new Gotthard, Ceneri and Lötschberg tunnels.
  32. [32]
    Democracy made world's longest tunnel possible - SWI swissinfo.ch
    Dec 10, 2016 · In 1992, Swiss voters went to the polls and approved a CHF10 billion ($10 billion) construction project, billed as the greatest of the ...
  33. [33]
    World's longest and deepest rail tunnel opens in Switzerland - BBC
    Jun 1, 2016 · The project, which cost more than $12bn (£8.3bn) to build, was endorsed by Swiss voters in a referendum in 1992. Voters then backed a proposal ...Missing: approval | Show results with:approval
  34. [34]
    [PDF] GOTTHARD BASE TUNNEL – Questions & Answers | MultiVu
    Dec 11, 2016 · In a nationwide vote in 1998, the Swiss electorate approved funding for the construction of the "New Rail Link through the Alps" (NRLA). Voters ...<|control11|><|separator|>
  35. [35]
    Swiss Review: Switzerland bores underground
    Jul 29, 2016 · Almost everything is on a gigantic scale at the new Gotthard Base Tunnel. Costing over CHF 12 billion, the tunnel, between the north portal in ...
  36. [36]
    [PDF] UPDATE ON INVESTMENTS IN LARGE TEN-T PROJECTS
    The cost of the Gotthard base tunnel increased by about 55% compared to the initial cost estimate of CHF 6,323 million. Figure C10-7 shows the different ...
  37. [37]
    Risk, Contract Management, and Financing of the Gotthard Base ...
    Jun 15, 2019 · For the Gotthard Base Tunnel alone, the increase in credit that occurred—from the original 6.3 billion CHF to 9.9 billion CHF (part of the ...Missing: HVF | Show results with:HVF
  38. [38]
    Breakthrough in the Gotthard - Events | Alptransit-Portal
    The first breakthrough by a boring machine in the Gotthard Base Tunnel takes place on 6 September 2006. The breakthrough in the second bore follows on 26 ...
  39. [39]
    Switzerland inaugurates Gotthard Base Tunnel
    Initial preparatory works began at Sedrun in April 1996 and major construction started with the blasting of access shafts in 1999. The project involved the ...
  40. [40]
    Gotthard base Tunnel - ITA-AITES
    The Gotthard Base Tunnel (GBT) is a railway tunnel under construction in Switzerland. With a planned length of 57 km (35.4 mi) and a total of 153.5 km (95.4 mi ...
  41. [41]
    Selection of tunnelling methods at the Gotthard Base Tunnel / Wahl ...
    Aug 6, 2025 · This paper compares and assesses tunnel excavation by Tunnel Boring Machine (TBM) excavation or drill and blast method for the OMT. Rock ...
  42. [42]
    Gotthard Base Tunnel | ISSMGE: Heritage Time Capsule (HTC) Project
    May 1, 2024 · The 57-km long railway tunnel connects northern to southern Europe, enabling passenger and goods transport to reduce travelling time by one hour between Zurich ...Missing: features specifications
  43. [43]
    [PDF] The Gotthard Base Tunnel Project in Switzerland – Construction of ...
    T single track tubes 40m apart connected every. 300m by cross passages. It also includes two multifunctional stations at the third-points with double crossovers ...
  44. [44]
    Gotthard Base Tunnel - Amberg Group
    The geology proved itself as a very challenging factor for the construction as well. Penninic Gneiss, the Gotthard Granite massif, the Piora sedimentary ...
  45. [45]
    [PDF] EOSC547: Tunnelling & Underground Design - UBC EOAS
    Geological Challenges: Gotthard Base Tunnel. Geologic Unit. Potential. Key Hazard. Tectonic. Unit. Max. Length. Cataclastic Faults. High pressure water inflow ...
  46. [46]
    Deep down and squeezed tight at Sedrun - Tunnels
    Dec 6, 2010 · “You can describe it as 'calming down' the rock,” he says. “You have not to be afraid of deformation, but know it is under control.” How to do ...Missing: ingress | Show results with:ingress
  47. [47]
    (PDF) Gotthard Base Tunnel, Swizerland, experiences with different ...
    an arch dam is especially critical. In the Gotthard Base Tunnel project, many mitigation measures are foreseen to avoid unacceptable deformations. tunnelling ...
  48. [48]
    Engineers meet challenge of Gotthard tunnel - SWI swissinfo.ch
    Sep 22, 2014 · The Gotthard base tunnel is 57 km long. The tunnel between Erstfeld and Bodio, linking central with southern Switzerland, is the longest railway ...<|separator|>
  49. [49]
    Construction - Keeping danger in check - Alptransit Portal
    In total, 199 workers are killed building it. Nineteen lose their lives during the construction of the Gotthard road tunnel that opens in 1980, while nine ...Missing: challenges incidents
  50. [50]
    The New Rail Link through the Alps (NRLA) serving Europe
    May 7, 2024 · With a total cost of CHF 12.2 billion, it took 70 years of work and 17 years of construction. In 2020 it was the longest rail tunnel in the ...
  51. [51]
    Gotthard tunnel – DW – 06/01/2016
    Jun 1, 2016 · While the tunnels were neither easy nor cheap to build - Switzerland paid a total of 12.2 billion Swiss francs ($12.2 billion, 11.0 billion ...
  52. [52]
    Gotthard Base Tunnel - The longest tunnel in the world - ALLPLAN
    Jun 18, 2018 · 57 km long. Up to 2,300 meters deep. 28.2 million cubic meters of rock. The Gotthard Base Tunnel from Erstfeld to Bodio is a project of ...Missing: specifications | Show results with:specifications
  53. [53]
    Risk, Contract Management, and Financing of the Gotthard Base ...
    ... cross passages approximately every 300 m. At two positions—one-third and two-thirds of the way along the base tunnel—multifunctional stations are located ...
  54. [54]
    The Gotthard Base Tunnel Project wins the 2018 European Railway ...
    Feb 20, 2018 · The Gotthard Base Tunnel in figures: 57 km length; up to 2300 m deep; 28.2 million tonnes total volume of excavated material; 2600 persons ...<|separator|>
  55. [55]
    A construction project serving Europe – The opening of the Gotthard ...
    May 25, 2016 · Companies and workers from around 15 countries were involved in the construction project.
  56. [56]
    Getzner Werkstoffe provides expertise for Gotthard tunnel construction
    Buers. Vorarlberg vibration expert Getzner Werkstoffe is supplying the elastic support for the railway line in the Gotthard base tunnel.Missing: contractors | Show results with:contractors
  57. [57]
    Switzerland celebrates the Gotthard Base Tunnel
    On 1 June 2016, 17 years after the first blast in the main tunnel, the Gotthard Base Tunnel was officially opened at a five-hour ceremony.Missing: details | Show results with:details
  58. [58]
    High-profile guests at the opening ceremony - Alptransit Portal
    (2016, Keystone). No expense is spared at the Gotthard Base Tunnel inauguration ceremony in 2016. Merkel, Hollande and Renzi are in attendance, but not the ...Missing: details | Show results with:details
  59. [59]
    Switzerland tunnel: The oddest moments of the opening ceremony
    Jun 1, 2016 · The Gotthard base tunnel, the longest and deepest in the world, was inaugurated on Wednesday. Here are some of the most striking moments from the ceremony.Missing: details | Show results with:details
  60. [60]
    Gotthard Tunnel: dancing haystacks not whirling dervishes - Swissinfo
    Jun 8, 2016 · The recent opening ceremony for the world's longest rail tunnel has had an amusing epilogue: a politician from the Swiss People's Party, spying ...
  61. [61]
    Bizarre Stage Show Opens Gotthard Rail Tunnel in Switzerland
    Jun 1, 2016 · Performers dressed as miners perform at the opening ceremony of the tunnel, now officially the world's longest and deepest rail tunnel. Designed ...
  62. [62]
    Old video wrongly linked to CERN to push satanic conspiracy theory
    Apr 10, 2024 · VERDICT. False. The video footage is unrelated to CERN. It shows the opening ceremony of a railway tunnel in Switzerland on June 1, 2016.
  63. [63]
    Sound The Alphorns: World's Longest, Deepest Tunnel Is Officially ...
    a record-setting 35.4 miles long, and farther below ground than any other tunnel — was inaugurated Wednesday. The ...
  64. [64]
    Switzerland inaugurates Gotthard Base Tunnel
    Jun 1, 2016 · During the commissioning phase SBB will operate up to 5000 trains, most of them freight trains, through the tunnel before the start of full ...<|separator|>
  65. [65]
    New Gotthard Tunnel set to open – DW – 12/09/2016
    Dec 9, 2016 · The railway in Switzerland starts running scheduled passenger and freight service through the new Gotthard Base Tunnel on Sunday, December 11.Missing: initial | Show results with:initial
  66. [66]
    World's longest rail tunnel begins regular service in Switzerland
    Dec 11, 2016 · Regular passenger trains start using the 35-mile Gotthard Base tunnel, which took 17 years to build.
  67. [67]
    World's longest railway tunnel gets go-ahead for commercial use
    Dec 6, 2016 · Scheduled to come into service on Dec 11, the world's longest railway tunnel will be used by some 50 passenger trains every day, with a further ...
  68. [68]
    Switzerland: Successful launch of commercial services through the ...
    Jan 17, 2017 · On 11 December 2016, SBB started running passenger services through the new Gotthard Base Tunnel (GBT). The first weeks of operation through ...
  69. [69]
    Swiss trains now rolling through world's longest rail tunnel
    Dec 12, 2016 · Switzerland's national rail company has begun regular service through the Gotthard Base Tunnel, which at 35.4-miles is the world's longest railway tunnel.Missing: initial | Show results with:initial
  70. [70]
    Gotthard Base Tunnel
    Around 50 passenger trains travel through the tunnel of the century each day. The number of freight services will increase from 160 to 210 trains in future.
  71. [71]
    Record number of passengers through Gotthard rail tunnel - Swissinfo
    Dec 11, 2017 · The new tunnel opened on December 11, 2016. Since then, passenger and freight train traffic through the Alps has increased significantly. Over ...Missing: attendees | Show results with:attendees<|control11|><|separator|>
  72. [72]
    The Gotthard Base Tunnel project wins the 2018 European Railway ...
    Feb 20, 2018 · From 9 000 daily passengers in 2015, the Gotthard passenger traffic is expected to nearly double to 15 000 daily passengers in 2021. When ...<|separator|>
  73. [73]
    Gotthard Base Tunnel Fully Operational Again
    The Gotthard Base Tunnel is fully open to rail traffic as of September 2, 2024, after a derailment on August 10, 2023. Repairs included replacing 7km of ...Missing: statistics | Show results with:statistics
  74. [74]
    SBB boosts Gotthard Base Tunnel capacity | Latest Railway News
    Feb 9, 2024 · From 2 March 2024, the number of passenger trains through the Gotthard Base Tunnel on weekends will increase from 31 to 38, providing an ...
  75. [75]
    Gotthard Tunnel, Switzerland - Hochtief
    The traveling time between Zürich and Milan was reduced by an hour. The tunnel is regarded as an extraordinary masterpiece of engineering. Together with ...
  76. [76]
    The Gotthard Base Tunnel is fully operational again
    Sep 13, 2024 · Since 2 September 2024, the travel time from Milan to Zurich is only 3 hours and 17 minutes. Guests will once again benefit from rapid ...Missing: statistics | Show results with:statistics
  77. [77]
    The New Rail Link through the Alps (NRLA) - FOT - BAV
    Jun 11, 2025 · The tunnel has been in use since December 2016 and up to 260 freight trains can travel through it every day. A half-hourly regular timetable ...
  78. [78]
    Swiss plan will significantly increase weekend passenger traffic ...
    Nov 18, 2023 · The Swiss Federal Railways plans to begin operating 31 passenger trains through the Gotthard Base Tunnel on weekends beginning in December, while increasing ...Missing: numbers | Show results with:numbers
  79. [79]
    Gotthard Base Tunnel – the longest rail tunnel in the world
    Jul 25, 2016 · When it opened on 1 June 2016, ownership of the Gotthard Base Tunnel was transferred from the construction company Alptransit Gotthard AG to SBB ...Missing: timeline | Show results with:timeline
  80. [80]
    Over 17000 freight trains passed Gotthard Base Tunnel
    Aug 9, 2017 · In the past few months, freight trains passing the tunnel averaged 1080 tonnes in weight and 434 meter in length. With accessibility to 750 ...
  81. [81]
    New Transalpine Rail Link NEAT - Global Infrastructure Hub
    Jan 26, 2021 · A project that that drastically cuts travel, transportation and freight times from one side of the Alps to the other along the Rhine-Alpine Corridor.<|separator|>
  82. [82]
    Swiss Alps still see 300,000 trucks too many - RailFreight.com
    Mar 27, 2019 · “Due to Swiss policy, 650 thousand trucks have been taken off the road in the past 20 years. We are now shortly under a million trucks on the ...<|separator|>
  83. [83]
    World's longest railway tunnel victim of own success - SWI swissinfo.ch
    Jun 2, 2017 · Almost 10,000 passengers and around 67,000 tonnes of freight pass through the 57-kilometre-long Gotthard Base Tunnel each day. Opened a year ago ...<|separator|>
  84. [84]
    Gotthard and Ceneri: the impact of the new rail infrastructure on ...
    Jan 24, 2024 · The Gotthard Base Tunnel has been in operation for almost eight ... The number of travellers per day rose 48 percent between 2016 and 2022.
  85. [85]
    [2505.21129] The Effect of the Gotthard Base Tunnel on Road Traffic
    May 27, 2025 · Our results reveal only a modest but statistically significant decline in the number of cars between the actual and the synthetic Gotthard ...
  86. [86]
    Control & Communications in the Gotthard Base Tunnel
    Dec 2, 2016 · The Gotthard Base Tunnel uses ETCS Level 2, a dual ring fiber cable, a control center at Pollegio, and a comprehensive telecom network with a ...
  87. [87]
    Train protection | SBB
    ETCS Level 2 increases the safety of rail traffic compared to lineside signalling, contributes to timetable stability in the face of high train density and ...
  88. [88]
    [PDF] Safety through video surveillance in the world's longest tunnel.
    With the video surveillance system being used in the Gotthard Base Tunnel, they now rely on the proven solution in all of Switzerland.
  89. [89]
    Gotthard Base Tunnel: prepared for emergencies - Save
    Feb 3, 2016 · Even in the event of a fire with thick clouds of smoke, two powerful ventilation systems and 24 jet fans ensure good air in the tube, SBB ...
  90. [90]
    First train through world's longest rail tunnel – DW – 12/11/2016
    Dec 11, 2016 · After 17 years and 11 billion euros, the first Gotthard Base Tunnel passenger train departed Zurich on Sunday morning. The express train ...
  91. [91]
    Gotthard Base Tunnel (#8): Safety and control tasks clearly distributed
    Nov 16, 2023 · Harmonised safety in the European rail freight system · Maintenance work monitored by independent bodies · Wheelset inspections in operation and ...<|separator|>
  92. [92]
    Gotthard Base Tunnel: World's longest rail tunnel to close for months
    Aug 17, 2023 · The project, which opened to enormous fanfare in 2016, took 17 years to complete and cost an estimated $12 billion. Recognized as a feat of ...Missing: specifications length depth
  93. [93]
    Broken wheel responsible for 2023 Gotthard tunnel derailment
    Jun 2, 2025 · The cause of the derailment of a goods train in the Gotthard Base Tunnel in August 2023 was a broken wheel disc. The wheel cracks are a ...
  94. [94]
    Broken wheel disc caused Gotthard derailment
    Jun 2, 2025 · A broken wheel disc was the cause of the derailment of a freight train in the Gotthard Base Tunnel on August 10 2023, a new report has revealed.
  95. [95]
    Gotthard rail tunnel, world's longest, closes for months after Swiss ...
    Aug 17, 2023 · Sixteen freight carriages run off rails, tearing up eight kilometres of train track and leaving engineering marvel inaugurated in 2016 unable to
  96. [96]
    [PDF] nes Güterzuges im Gotthard-Basistunnel
    Jun 2, 2025 · Am 10. August 2023 war der Güterzug 45016 von SBB Cargo mit zwei Lokomotiven und 30 Güterwagen unterschiedlicher Bauart und Eigentümer auf dem ...Missing: Frachtzug | Show results with:Frachtzug
  97. [97]
    Serious Damage in the Gotthard Base Tunnel
    The derailment of a cargo train in the Gotthard Base Tunnel on 10 August 2023 caused considerably more serious damage than initially assumed.Missing: challenges | Show results with:challenges
  98. [98]
    Nach Gotthard-Unfall: Abschlussbericht ist da - Blick
    Jun 2, 2025 · Am 10. August 2023 entgleiste im Gotthard-Basistunnel ein Güterzug. Grund dafür war ein Radbruch ...Missing: Frachtzug | Show results with:Frachtzug
  99. [99]
    Swiss investigators' final report confirms cause of Gotthard Base ...
    A broken wheel was the cause of the derailment in the Gotthard Base Tunnel that disrupted traffic through the world's ...Missing: controversies | Show results with:controversies
  100. [100]
    Gotthard Base Tunnel fully reopens after derailment damage is ...
    Sep 5, 2024 · The 57 km Gotthard Base Tunnel has fully reopened, 389 days after a derailed freight train caused extensive damage to the slab track in the western bore.
  101. [101]
    Gotthard repaired: first trains cross world's longest rail tunnel after ...
    Aug 19, 2024 · Authorities have set Gotthard's full reopening for 2 September 2024. There will be an extensive period of testing and trial operations, similar ...
  102. [102]
    Swiss freight wagons face new rules: What it means - Trains Magazine
    Sep 19, 2025 · Damage from the Aug. 10, 2023, derailment inside the Gotthard Base Tunnel is clearly visible during repair work in November.<|separator|>
  103. [103]
    Rail freight associations urge co-ordinated response to Swiss base ...
    Oct 16, 2025 · SWITZERLAND: Wagon owners remain concerned about changes to the rules governing freight trains passing through the Gotthard Base Tunnel.
  104. [104]
    'Major companies' to take Switzerland to court over new wheels rules
    Oct 17, 2025 · The broken wheel that caused the derailment in the Gotthard Base Tunnel in August 2023. Image: © Swiss Safety Investigation Board (SUST).
  105. [105]
    Swiss rail hauliers slam new safety measures - SWI swissinfo.ch
    Sep 12, 2025 · Swiss freight rail safety measures, following anaccident in the Gotthard Base Tunnel in 2023, have been criticised by the Swiss Association ...
  106. [106]
    The world's longest tunnel - The Wider Image - Reuters
    Oct 7, 2013 · The tunnel helps reduce the travel time between Zurich and Milan by an hour, to two hours and 40 minutes. Over the course of the dig, 13 ...
  107. [107]
    Opening of the Gotthard Base Tunnel benefits for Italy - FS Italiane
    Jun 17, 2016 · Resources of 3.5 billion euros are currently committed taking into account the fourth project (1.6 billion) which is subject to approval by the ...<|separator|>
  108. [108]
    Gotthard Base Tunnel | Definition, Switzerland, Opening, & Facts
    Oct 12, 2025 · Comprising two single-track tunnels, the Gotthard Base Tunnel (GBT) is 57 km (35 miles) in length and has a maximum depth of 2,300 metres (7,546 ...Missing: specifications | Show results with:specifications
  109. [109]
    AlpTransit Rail Tunnels Exhaust Credit Line - tunnelbuilder.com News
    Costs for the St Gotthard project have risen by SFr500 million because of geological problems, while the operators of the Loetschberg tunnel are having to fork ...<|control11|><|separator|>
  110. [110]
    (PDF) FINANCING AND COST MANAGEMENT - ResearchGate
    Mar 20, 2021 · This paper shows the long history of the cost development and the adaptation of the financing model in order to create a story of success also with regard to ...
  111. [111]
    The costs - Events | Alptransit-Portal
    In 2003 a report concludes that the costs of the Gotthard line could rise by 516 million francs and those of the Lötschberg by just under 300 million.Missing: AG | Show results with:AG
  112. [112]
    Transient surface deformations caused by the Gotthard Base Tunnel
    This paper presents the results from this monitoring system and explains the observed hydro-mechanically coupled and transient rock mass behavior.
  113. [113]
    What's behind the delays in large infrastructure projects?
    Jul 26, 2016 · On 1 June 2016, the Gotthard Base Tunnel opened, on time and marginally over budget. The 57-kilometre tunnel, which runs 2,300 metres under ...
  114. [114]
    Gotthard-Basistunnel wieder vollständig in Betrieb - SBB News
    Seit der Entgleisung eines Güterzugs im Gotthard-Basistunnel am 10. August 2023 hat die SBB die Arbeiten zur Wiederinstandsetzung mit Hochdruck vorangetrieben.Missing: Frachtzug | Show results with:Frachtzug<|control11|><|separator|>
  115. [115]
    New timetable increases Gotthard Tunnel's freight capacity on ...
    Nov 28, 2023 · SBB will implement timetable changes on 10 December that will affect operations through the impaired Gotthard Base Tunnel.
  116. [116]
    Kapazitätserhöhung im Bahnhof Chiasso SBB - CSC costruzioni SA
    Die Eröffnung der neuen Alpenübergänge (Gotthard-Basistunnel und Monte Ceneri) erfordert eine Kapazitätserweiterung in Chiasso Viaggiatori. Der Bau der ...
  117. [117]
    [PDF] Herzstücke der «Bahn 2030» - Zentralschweizer Regierungskonferenz
    >> eine Kapazitätserweiterung zwischen Arth-Goldau und dem Nordportal ... Mit dem Gotthard-Basistunnel ist das Herz der Nord-Süd-Achse erstellt. Die ...<|control11|><|separator|>
  118. [118]
    Swiss Railways to replace tracks in Gotthard Tunnel earlier than ...
    Sep 15, 2025 · The replacement is scheduled to take place between 2032 and 2034. A total closure is not planned.Missing: construction timeline
  119. [119]
    SBB: Gotthard base tunnel maintenance - valantic
    ... Base Tunnel. The commissioning of this tunnel is planned for 2020. A modern high-speed SBB train with a red and white design speeds through the. Christian ...
  120. [120]
    [PDF] LP60 Tunnel Control System - Digital Asset Management - Siemens
    Maintenance. A rail tunnel the size of the Gotthard Base Tunnel requires a comprehensive maintenance system. As an additional component of the Tunnel Control ...
  121. [121]
    Switzerland's Gotthard Base Tunnel resumes full operation - Trains
    Sep 2, 2024 · Passenger use of the base tunnel has gradually increased, but most passenger traffic has continued to use the Gotthard Pass route until today.
  122. [122]
    Unique water samples from the Gotthard rail base tunnel, Switzerland
    The construction of the new 56 km long Gotthard railway base tunnel in Switzerland opened a large number water conducting fractures and 122 water samples ...
  123. [123]
    Causal mechanism of Gotthard Base Tunnel-induced ground ...
    Our model indicates that ground surface displacements originate from GBT-induced water drainage and rock mass consolidation in the deep subsurface.Missing: alignment | Show results with:alignment
  124. [124]
    Groundwater Drainage-Induced Rock Mass Deformation During the ...
    Jun 26, 2022 · ABSTRACT: The Gotthard Base Tunnel (GBT), constructed between 2000 and 2011, is a 57 km long and up to 2.5 km deep high-speed ...
  125. [125]
    [PDF] Gotthard Base Tunnel Risk Management for the World's Longest ...
    Even if the delays did not become longer after the middle of 2005, the TBMs would only reach the Faido/Sedrun lot boundary around three years after the ...Missing: accidents | Show results with:accidents<|control11|><|separator|>