The Hunter-class is a planned class of six heavy being constructed for the Royal Australian Navy (RAN) as part of the SEA 5000 program to replace the aging Anzac-class with advanced capabilities. Based on ' Type 26 Global Combat Ship design, these warships emphasize , modularity, and superior systems to counter threats in contested maritime environments. Each Hunter-class vessel displaces approximately 8,800 tonnes at full load, measures about 150 meters in length, and accommodates a of around 180 personnel, with enabling speeds exceeding 27 knots. The design incorporates an system, advanced , and provisions for vertical launch systems to support a range of missiles, torpedoes, and helicopters for multi-mission operations including air defense and surface strike. Construction, led by at the Osborne shipyard in , began with steel cutting for the in June 2024, and by October 2025, over half of its structure was in production. The program, valued as Australia's largest surface project, aims to deliver the first by 2032 for operational service around 2034, enhancing RAN's deterrence in the amid rising regional tensions. Despite criticisms regarding costs and timelines—prompting defenses from program officials highlighting its specialized anti-submarine focus over cheaper alternatives—the initiative sustains thousands of jobs and bolsters domestic capacity.

Development history

Strategic origins and initial planning (2010s)

The strategic rationale for 's Future Frigate program, later realized as the Hunter-class, stemmed from the nation's geographic imperatives and evolving security environment in the late 2000s and . As an island continent with extensive maritime approaches, has long prioritized a strategy to protect its northern sea lines against potential adversaries, particularly those employing s to interdict trade and project power. This approach, articulated in defense policy documents, emphasized layered defenses including () capabilities to contest hostile forces in chokepoints and archipelagic waters without seeking broad sea control. The rising in the region, driven by acquisitions from powers like , underscored the need for surface combatants optimized for escort and detection roles over general-purpose versatility. The program's formal origins trace to the 2009 Defence under Prime Minister , which committed to acquiring eight Future Frigates to replace the Anzac-class vessels entering obsolescence by the 2020s. These ships were specified as larger platforms with enhanced sensors, including towed-array sonars, and helicopter facilities for helicopters, prioritizing operations in Australia's littoral and offshore zones over blue-water expeditionary tasks. The framed this acquisition within a broader force structure review, allocating initial funding amid fiscal constraints following the global financial crisis, while signaling interoperability with allies like the for joint denial operations. Initial planning in the early 2010s advanced under subsequent governments, with the 2013 Defence White Paper reaffirming the Future Frigate as a core capability and directing infrastructure preparations alongside related projects like the Future Submarine (SEA 1000). By , the administration integrated the program into a "continuous build" naval strategy to sustain domestic industry, designating it SEA 5000 Phase 1 and targeting nine vessels for delivery starting in the late 2020s. This phase emphasized risk reduction through international design partnerships, given Australia's limited experience with advanced frigates, while aligning with alliance commitments under the treaty for regional deterrence. The planning process involved capability definition studies by the Defence Materiel Organisation, focusing on modularity for future upgrades and integration of Australian-specific systems like the CEA Technologies radar, amid debates over off-the-shelf versus bespoke designs to balance cost and sovereignty.

Tender evaluation and bidder assessments

The Competitive Evaluation Process (CEP) for Project SEA 5000 Phase 1 commenced following first pass government approval in April 2016, shortlisting three international shipbuilders to refine their designs against Australian requirements for nine anti-submarine warfare-focused frigates. The bidders were with its Type 26 Global Combat Ship (adapted as the Hunter-class baseline), Italy's with a modified FREMM (Frégate Européenne Multi-Mission) design, and Spain's with an evolved F-100 class variant designated F-5000. Evaluation proceeded under a 2017 Tender Evaluation Plan (TEP) assessing tenders against 10 criteria, including compliance with 23 high-level capability requirements (emphasizing sensors, mission systems, and survivability), Australian industry participation, schedule feasibility, and budgetary constraints, with tenders rated as acceptable only if modifiable to meet thresholds. BAE's Type 26 was assessed as the sole design satisfying both core and mission system mandates, registering low risk for integration and medium risk for overall systems, owing to its purpose-built , modular mission bays, and proven electric propulsion suited to RAN operational needs. In contrast, Navantia's F-5000 and Fincantieri's FREMM each fulfilled only one of these mandates, with marginal performance attributed to less optimized forms and suites derived from general-purpose lineages rather than dedicated submarine hunting. All proposals exceeded initial budget envelopes and carried elevated pricing risks, yet BAE's bid was deemed "acceptable with changes" despite extreme risks in areas like sustainment and local content integration. The Source Evaluation Report (SER) and subsequent supplement, approved in mid-2018, recommended BAE without a formal comparative value-for-money ranking, deferring such analysis to government decision-makers, which prioritized capability delivery over holistic lifecycle costs. This led to second pass approval on 29 June 2018, selecting BAE's design for its alignment with strategic imperatives for advanced amid Indo-Pacific submarine threats, notwithstanding unaddressed trade-offs in affordability and delivery timelines. Subsequent audits by the Australian National Audit Office (ANAO) identified procedural deficiencies, including non-compliance with Commonwealth Procurement Rules due to absent value-for-money evaluations, incomplete documentation (e.g., missing rationales for shortlisting and SER approvals), and failure to provide whole-of-life cost estimates to Cabinet, potentially conflating sovereign industry goals with procurement efficacy. A 2023 parliamentary review further critiqued the process for withholding comprehensive risk disclosures from the National Security Committee, such as BAE's non-compliance on pricing and the uniform budget overruns across bids, which obscured affordability challenges from the outset. These lapses, while not altering the capability-driven selection, highlighted systemic gaps in risk communication and record-keeping within Defence's advisory framework.

Contract award to BAE Systems (2018–2019)

On 28 June 2018, the Australian Department of Defence selected ' Type 26 frigate design as the basis for the SEA 5000 Phase 2 Future Frigates program, designating the vessels as the Hunter class. This decision followed a competitive evaluation process and positioned , through its subsidiary ASC Shipbuilding, to deliver nine frigates at an estimated program cost of approximately $35 billion. The selection emphasized the Type 26's , proven global , and alignment with Australia's strategic needs for enhanced undersea threat capabilities, outperforming alternative bids such as Navantia's based on the Hobart-class destroyer. committed to local construction at Osborne Shipyard in , with design adaptations for Australian-specific requirements including integration of ' phased-array radar and Saab's 9LV combat management system. On 14 December 2018, the Australian government formalized the award by signing a head contract with ASC Shipbuilding valued at $1,904.1 million, initiating detailed design, engineering, and productionization activities for the Hunter class. This agreement established a risk-sharing partnership model, with incentives for on-time delivery and provisions for progressive contract amendments as design matured, while securing over 2,000 jobs in shipbuilding and related industries. No significant modifications or disputes were reported during the 2019 implementation phase, though subsequent audits noted early focus on design stabilization to mitigate cost risks.

Post-award adjustments and 2024 review

Following the 2019 contract award to for design and development of nine Hunter-class frigates under SEA 5000 Phase 1, the program encountered significant delays and cost escalations. An Australian National Audit Office (ANAO) performance audit released in May 2023 identified an 18-month schedule slippage, pushing initial operational capability from the early 2030s, alongside undisclosed additional expenditures beyond the original AU$35 billion envelope. These issues stemmed partly from evolving requirements, disruptions, and integration challenges with Australian-sourced components, prompting adjustments to the phased acquisition approach while maintaining the core Type 26-derived (ASW) design. A January 2024 review by the Parliamentary Joint Committee on Intelligence and Security critiqued the procurement process as flawed, noting the absence of comprehensive value-for-money assessments during tender evaluation and reliance on optimistic cost modeling that underestimated risks from design immaturity. In response, the Department of Defence defended the selection of the bid as the only shortlisted option fully meeting and mission systems criteria, emphasizing sovereign capability benefits despite higher per-unit costs, which had risen to approximately AU$9 billion per ship by mid-2024 due to scope refinements and . The pivotal 2024 Independent Analysis of the Navy’s Fleet, completed in 2024, recommended restructuring the surface fleet to address capability gaps amid regional threats. Consequently, on 20 June 2024, the Australian government amended the head contract with Maritime Australia to authorize construction of the first three frigates at Osborne Shipyard, , marking the transition from design to fabrication phases. This adjustment reduced the Hunter-class acquisition to six vessels optimized for roles, down from the original nine, while initiating a separate for 11 general-purpose frigates to fill multi-mission voids, with total costs now projected higher but distributed across diversified hull forms. Steel-cutting for the , HMAS Hunter, occurred concurrently in June 2024, aligning with revised milestones targeting delivery of the first vessel by the late , though ongoing audits continue to monitor cost controls and industrial partnerships.

Design features

Hull, dimensions, and general arrangement

The employs a hull based on a modified version of ' Type 26 Global Combat Ship design, optimized for with features to reduce underwater noise signatures. The hull incorporates modular digital design techniques, enabling flexible internal arrangements while maintaining structural integrity through consolidated units formed into 22 primary blocks per vessel during construction. These modifications from the baseline Type 26 include adaptations for Australian-specific systems, such as integration points for indigenous radars and communications, without altering core hydrodynamic properties. Key dimensions comprise a length overall of 151.4 meters, a of 20.8 meters, and a full load of approximately 8,800 tonnes, with weight around 8,200 tonnes as of September 2024. The design emphasizes through high forward freeboard and clean lines, inheriting Type 26 principles that minimize vertical surfaces to reduce cross-section, though specific metrics for the Hunter variant remain classified. General arrangement follows a conventional layout with a single island superstructure amidships, housing command facilities, sensors, and vertical launch systems forward of the funnel. Aft sections feature a combined and mission bay capable of accommodating one MH-60R Seahawk plus provisions for uncrewed systems or a second rotary-wing asset, supporting up to 208 personnel including . Internal zoning prioritizes operations, with separated compartments for , processing, and crew berthing to enhance and operational efficiency.

Propulsion, speed, and endurance

The Hunter-class frigates utilize a combined diesel-electric or gas (CODLOG) system, enabling flexible operation between efficient diesel-electric mode for sustained low-speed cruising and high-power mode for rapid acceleration and maximum speeds. This setup incorporates two electric motors driven by diesel generators during routine patrols, providing quieter operation advantageous for , while a single delivers boost power for combat maneuvers. The system's top speed exceeds 27 knots, with projections for trial speeds reaching 31 to 32 knots once sea trials commence, supporting the vessels' roles in and missions within the theater. Endurance is rated at over 7,000 nautical miles in electric-motor drive mode, emphasizing for extended deployments without compromising or sensor performance. This range aligns with the frigates' design for long-range operations, integrating advanced power management systems from contractors like to optimize propulsion and auxiliary loads.

Sensors, electronics, and command systems

The Hunter-class frigates employ the combat management system as their primary architecture, adapted with an Australian-developed tactical interface from Saab's 9LV system to enhance integration with (RAN) operations. This setup facilitates multi-mission coordination, including (), air defense, and surface strike, by fusing data from onboard sensors and weapons. The system supports networked operations with allied forces, leveraging for future upgrades. Primary surveillance is provided by the CEAFAR2 active phased-array , developed by , which offers 360-degree coverage for air and surface tracking with multi-function capabilities including fire control. Complementing this, electro-optical/infrared sensors from Chess Dynamics' system enable day/night detection and identification of threats at extended ranges. For ASW dominance, the frigates feature the S2150 hull-mounted from Ultra Maritime, optimized for medium-frequency active and passive detection in littoral and blue-water environments, with a contract awarded to in March 2025. This is augmented by the S2087 towed array and variable depth suite, capable of low-frequency passive listening for long-range submarine detection and localization. Electronic warfare capabilities include integrated support measures and countermeasures, networked for spectrum dominance and self-protection against anti-ship missiles. Additional systems encompass NAVICS for secure communications and control, Anschütz WINBS for bridge navigation integrating radars and electronic charts, and ' Integrated Platform Management System for automated monitoring of propulsion, power, and damage control.

Armament and weapon systems

The Hunter-class frigates feature a primary gun armament consisting of a single Mk 45 Mod 4 127 mm (5 in)/62 caliber naval gun, selected in November 2023 for its adaptability to advanced munitions and integration with fire control systems. This medium-caliber weapon supports , including coastal suppression roles, and provides secondary anti-air capability. For missile-based defense and strike, the ships incorporate a 32-cell Mk 41 (VLS) positioned forward, enabling the launch of quad-packed RIM-162 Evolved SeaSparrow Missiles (ESSM) for point and medium-range air defense against aircraft, drones, and anti-ship missiles. Anti-ship capabilities are provided by canister-launched over-the-horizon missiles, aligned with standards for precision strikes, though specific variants remain subject to integration decisions post-2024 program review. Anti-submarine armament includes two triple-barreled tubes firing Mk 54 lightweight torpedoes, complemented by the embarked MH-60R Seahawk helicopters' dipping and sonobuoys for extended detection and engagement ranges. Close-in defense comprises two 30 mm remote weapon stations for engaging small surface threats and two 20 mm Close-In Weapon Systems (CIWS) for terminal anti-missile and anti-air protection. Decoy launchers and electronic countermeasures further enhance survivability against incoming threats.

Anti-submarine warfare specialization

The Hunter-class frigate is optimized for (ASW), incorporating advanced acoustic stealth, sophisticated arrays, and integrated weapon systems to detect, track, and neutralize submarines in high-threat environments. This specialization stems from the ship's modified Type 26 design, which prioritizes low-noise propulsion and hull form to minimize self-generated noise, enabling passive detection at extended ranges. Central to its ASW role are dual sonar systems: the Ultra Maritime S2150 hull-mounted sonar for medium-frequency active and passive detection of submerged threats, and the Thales low-frequency towed array with variable-depth capabilities for long-range passive surveillance and localization of quiet diesel-electric submarines. The towed array, deployable at variable depths up to several hundred meters, enhances performance in layered ocean environments by exploiting thermal and gradients, while the hull-mounted system provides rapid, close-in search and attack capabilities. Armament includes two twin Mk 32 Mod 9 surface vessel torpedo tubes (SVTT) launching EuroTorp MU90 Impact lightweight torpedoes, which feature advanced acoustic homing, wire guidance, and a 23 kg warhead optimized for shallow-water engagements against fast-escort or supercavitating threats. These systems integrate with the ship's Aegis-based for automated fire control and multi-threat handling. Aviation support comprises a hangar and flight deck accommodating one MH-60R Seahawk helicopter, equipped with AN/AQS-22 dipping sonar, sonobuoys, and Mk 54 torpedoes for extended-range operations, extending the ship's sensor envelope beyond line-of-sight horizons. The design also includes a mission bay for potential unmanned underwater vehicles or additional sonobuoys, further augmenting persistent subsurface surveillance. These elements position the Hunter-class as a core enabler for the Royal Australian Navy's undersea dominance in operations.

Construction and production

Shipbuilding facilities and partnerships

The primary shipbuilding facility for the Hunter-class frigates is the Osborne Naval Shipyard in , , managed by BAE Systems Maritime Australia (BAESMA), a of . This site has been selected for the assembly of the six frigates due to its existing infrastructure for naval , with upgrades including initiatives to enhance efficiency and capacity. Construction of the first three ships commenced following a amendment signed on 20 June 2024, marking the transition to the build phase. To support production across , BAESMA utilizes additional fabrication sites, including its Henderson facility in for machinery units and other components. This distributed approach aims to leverage national industrial capabilities while adhering to the program's emphasis on maximizing content. BAESMA has forged strategic supplier partnerships with local firms to augment capacity at the full-utilization Osborne yard and mitigate schedule risks. Key partners include Century Engineering in North, , which delivers critical elements for the first ship, and Engineering in , , responsible for fabricating specific hull units such as B21 and C31B, encompassing side shells, bulkheads, and seating structures. These agreements, announced in April 2025, represent the first off-site primary structures outsourced for the program. Further partnerships with are planned for onboarding in 2025 and 2026 to sustain production momentum. Specialized subcontractors contribute to subsystem integration, such as Australia partnering with Defence in August 2025 to supply communications masts essential for the frigates' sensor suites. Overall, these facilities and collaborations underscore a sovereign build strategy, with over half of the first frigate's blocks in production by October 2025.

Fabrication progress and key milestones (up to 2025)

The fabrication of the Hunter-class frigates began in earnest with the cutting of first steel for Ship 1 on 20 June 2024 at ' Osborne Naval Shipyard in , following the Australian Department of Defence's amendment to the head contract with Maritime Australia to authorize of the initial three vessels. This milestone transitioned the program from design and prototyping phases—where steel had been cut for prototype blocks as early as December 2021 to test manufacturing processes—to active . Progress accelerated thereafter, with the successful consolidation of the first two Category A machinery units for Ship 1 completed in July 2025, enabling the integration of core propulsion and power systems under the construction phase. By September 2025, the installation of the fin stabiliser on Ship 1 was achieved, a complex structural feat that advanced stability features. In October 2025, reported that, just 15 months after steel cutting, more than half of Ship 1's 78 units and 22 blocks were in , underscoring efficient refinements and supply chain mobilization across Australian industry partners. Complementary advancements included the lifting of a pre-outfitted baseplate into the structure, employing innovative modular strategies to minimize rework and enhance build efficiency. Parallel efforts saw ongoing supplier integrations, such as the onboarding of Liferaft Systems in September 2025 for survival equipment. Combat systems development remained aligned with fabrication timelines, with plans for onboard testing during construction confirmed on track as of May 2025, supported by enhanced integrations derived from the RAN's . These milestones reflect a focus on scaling production capacity, with workforce expansion targeting over 400 new tradespeople in 2025 to sustain momentum for the six-ship class.

Production challenges and mitigations

The Hunter-class frigate program has faced persistent production challenges stemming from design immaturity, supply chain complexities, and industrial capacity constraints at the Osborne shipyard. In March 2020, the project was designated a "Project of Interest" by the Australian Department of Defence due to elevated risks in schedule adherence, technical integration, workforce availability, and cost management, exacerbated by the need to localize elements of the Type 26-derived design for Australian requirements. An December 2024 Australian National Audit Office (ANAO) review identified accumulated technical debt and design delays as key vulnerabilities, noting that incomplete maturation of the vessel's architecture could hinder efficient fabrication and increase integration errors during block assembly. These issues contributed to the first ship's delivery slipping to approximately 2033, with initial steel cutting occurring only in June 2024 after prior cost overruns and capability reassessments delayed full-rate production. Workforce and infrastructure limitations at ' Osborne facility have compounded these delays, including shortages of skilled welders, engineers, and modular construction specialists required for the frigates' 78 production units and 22 blocks. shortcomings, such as inadequate evaluation of tender bids in the SEA 5000 phase, further eroded early momentum, with Defence conceding procedural lapses in assessing BAE's bid against competitors. Supply chain disruptions, including dependencies on international vendors for propulsion and sensor components, have mirrored broader Type 26 program hurdles like gearbox failures and communication gaps observed in the UK variant, though Australian-specific mitigations were implemented to avoid direct replication. Mitigation efforts have focused on industrial ramp-up and process optimization, with refining fabrication workflows through prototyping and digital tools at since 2022 to address . In June 2024, Defence amended the head contract with to prioritize construction of the first three frigates, enabling phased investment in shipyard capacity and supplier partnerships to localize over 60% of content. By July 2025, the first two machinery units for Ship 1 were consolidated, demonstrating improved block integration, followed by the installation of the initial Category A major equipment in October 2025. As of October 2025, over half of Ship 1's units—more than 39 of 78—were in active production, just 15 months post-steel cutting, signaling accelerated throughput via modular assembly and workforce training initiatives. These steps, coupled with ANAO-recommended risk assessments for capability gaps, aim to stabilize the program amid ongoing scrutiny of its $45 billion budget.

Operational capabilities and strategic role

Primary missions and tactical roles

The Hunter-class frigates are optimized for anti-submarine warfare (ASW) as their primary mission, equipping the Royal Australian Navy (RAN) with advanced capabilities to detect, track, and neutralize threats in contested maritime environments. This focus addresses the RAN's need for enhanced undersea dominance in the region, where submarine proliferation poses significant risks to naval operations and . The vessels incorporate sophisticated sonar systems, towed array sensors, and integration with RAN and submarines to form layered ASW defenses. In tactical roles, Hunter-class ships serve as escorts for high-value assets, including amphibious task groups and allied strike formations, providing persistent protection during transit and operations. They enable independent or task-group deployments for maritime interdiction, contributing to deterrence through high lethality against subsurface, surface, and aerial threats. Secondary missions include limited air defense via vertical launch systems and surface strike with missiles, supporting multi-domain operations while prioritizing specialization over general-purpose versatility. These frigates will replace the aging Anzac-class, restoring and amplifying the RAN's proficiency diminished since the , with operational entry targeted for the early 2030s to counter evolving submarine threats from peer adversaries. Their design emphasizes endurance for extended patrols, with partners' Type 26 variants, and resilience in high-threat scenarios through features and suites.

Integration with RAN fleet and alliances

The Hunter-class frigates are designed to serve as specialized platforms within the Royal Australian Navy's surface combatant fleet, complementing the three -class air warfare destroyers by providing undersea threat protection for task groups including amphibious ships and future aircraft carriers. They integrate with RAN aviation assets through compatibility with MH-60R Seahawk Romeo helicopters for embarked operations, enabling coordinated ASW missions alongside Collins-class submarines and Arafura-class offshore patrol vessels. This configuration supports the RAN's enhanced lethality strategy, where the six Hunters form the core of Tier 1 combatants optimized for high-end warfare, operating in conjunction with upgraded destroyers and eleven planned general-purpose frigates under Project SEA 3000 for multi-domain operations. Key to fleet integration is the adoption of the Aegis combat management system with a Saab Australia interface, which aligns the Hunters' command and control with the RAN's Hobart-class destroyers and enables seamless data sharing via Link 16 and other tactical networks. Australian-developed CEAFAR2 phased-array radar further enhances sensor fusion with RAN-wide systems, while the combination of hull-mounted S2150 sonar, towed S2087 array, and variable-depth sonar allows the frigates to contribute to layered ASW defenses across the fleet. On the alliance front, the Hunter-class derives from the UK's Type 26 Global Combat Ship design, fostering interoperability with Royal Navy City-class frigates through shared modular architecture, BAE Systems combat systems, and common ASW sensors, as evidenced by ongoing GCS program collaboration announced in May 2025. This extends to Canada's River-class (CSC) frigates, also Type 26-based, enabling joint exercises and technology exchanges under Five Eyes frameworks. Within AUKUS, the Aegis integration and US-sourced elements like vertical launch systems ensure compatibility with U.S. Navy Arleigh Burke-class destroyers and carrier strike groups, supporting trilateral operations in the Indo-Pacific as outlined in the 2024 National Defence Strategy. These features position the Hunters for coalition task forces, with BAE Systems' experience enhancing AUKUS Pillar II advanced capabilities sharing.

Comparative advantages and limitations

The Hunter-class frigate excels in anti-submarine warfare through its low acoustic signature achieved via hybrid electric propulsion and a stealthy hull form, enabling superior detection and tracking of submerged threats compared to less specialized platforms like the U.S. Constellation-class. This design, derived from the Type 26, incorporates advanced sonar suites and a modular mission bay for deploying unmanned underwater vehicles or additional ASW payloads, positioning it as one of the most capable ASW vessels globally for escorting high-value assets such as carrier groups or submarines. Integration of the Australian-developed CEAFAR2 phased-array radar and Aegis combat system further enhances sensor fusion and cooperative engagement capabilities with allied forces, surpassing the multi-role flexibility of smaller frigates like Japan's Mogami-class in sustained underwater threat neutralization. However, the class's baseline configuration limits its versatility with only 32 Mk 41 vertical launch system (VLS) cells, constraining loadouts for air defense or strike missions relative to destroyers like the Arleigh Burke-class (96 cells) or even regional competitors such as China's Type 052D (64 cells). This reduced "magazine depth" heightens vulnerability in attacks, where the frigate's reliance on quad-packed ESSMs or limited SM-series missiles may prove insufficient without external from Hobart-class destroyers. Recent design weight increases to approximately 8,800 tonnes lightship have further compromised maximum speed to around 27 knots, below initial targets, potentially forcing inefficient operation that erodes stealth and endurance during long transits. A narrow 3% design margin exacerbates these issues by restricting future retrofits for emerging threats, such as hypersonic missiles, without major hull modifications, unlike more modular peers with greater growth potential. While proposals exist to expand to 96 VLS cells by sacrificing the mission bay—trading modularity for enhanced surface/air warfare—these remain unadopted for the initial batch, underscoring a core tension between specialization and balanced lethality in high-intensity peer conflicts. Critics, including analyses from the Australian Strategic Policy Institute, argue this -centric focus misaligns with RAN operational needs favoring distributed aviation and for underwater dominance, rendering the Hunter less adaptable than hybrid designs like the Constellation-class for NATO-style multi-domain operations.

Controversies and program evaluations

Cost escalations and budgetary impacts

The Hunter-class frigate program under SEA 5000 Phase 1 was initially budgeted at AU$35 billion for nine vessels when approved in 2018. By the 2020 Force Structure Plan, the reported out-turned cost had risen to AU$45.6 billion, reflecting early adjustments for design maturation and Australian-specific modifications. Actual expenditure reached AU$2.226 billion by January 2023, with AU$1.308 billion allocated to the primary contract with Maritime Australia. Cost pressures intensified in subsequent years due to technical complexities, workforce constraints, and issues, elevating the to a "Project of Interest" status in March 2020 for heightened oversight on schedule, technical, and cost risks. The 2023–24 Major Projects Report documented a net budget increase of AU$19.7 billion upon approval for Batch 1 construction of the initial three ships, plus associated program elements like support and training systems, bringing the subtotal for these vessels to AU$19.87 billion. Per-unit costs escalated accordingly, reaching approximately AU$6.4 billion (or €4 billion) per by 2024 assessments, driven by extensive local content mandates and custom integrations that deviated from the baseline Type 26 design. These overruns prompted a 2024 strategic review that reduced the planned fleet from nine to six ships, aiming to contain total program costs while preserving core anti-submarine capabilities. Budgetary impacts included reallocation pressures within the AU$36.8 billion 2024–25 defense portfolio, with AU$813 million earmarked for Hunter-class advancement amid competing priorities like submarine acquisitions. Critics, including defense analysts, highlighted diminished value for money, noting per-ship costs exceeding those of comparable Western frigates by factors of two to four, potentially constraining future naval expansions and exposing systemic inefficiencies in Australia's sovereign shipbuilding model. The Australian National Audit Office has emphasized ongoing risks to affordability, recommending enhanced cost controls to mitigate further fiscal strain.

Schedule delays and delivery timelines

The Hunter-class frigate program, designated SEA 5000 Phase 1, originally anticipated initial operational capability for the lead ship, HMAS Hunter, around the early 2030s following contract award to in June 2018. However, the project encountered early scheduling pressures due to the immature of the baseline , leading to an 18-month postponement of detailed and construction start agreed in June 2021, at additional cost to achieve greater design assurance before . Subsequent delays were attributed to a combination of factors, including disruptions to supply chains and collaboration with the Kingdom's Type 26 program, as well as ongoing refinements to integrate Australian-specific requirements such as vertical launch systems and mission systems. Steel cutting for the first vessel commenced in June 2024 at Osborne , marking the formal start of fabrication after these adjustments, with block progressing to over 50% production by October 2025. The current official timeline targets delivery of the first Hunter-class frigate to the Royal Australian Navy in 2032, followed by subsequent ships at intervals supporting fleet integration, though independent analyses have projected potential slips to 2033 or later due to persistent integration complexities and historical precedents in allied programs. has affirmed commitment to the 2032 milestone, with the lead ship scheduled for rollout from the construction hall in 2028 ahead of trials and commissioning. Critics, including Australian National Audit Office assessments, highlight that cumulative delays from design immaturity have extended the overall project phase by years, risking capability gaps in until full fleet entry.

Design and capability critiques

The Hunter-class frigate's design has been criticized for its limited vertical launch system (VLS) capacity of 32 Mk 41 cells, which analysts contend is insufficient for sustained operations in missile-intensive conflicts, offering fewer cells than the RAN's smaller Hobart-class destroyers (48 cells) and far less than U.S. Arleigh Burke-class destroyers (96 cells). This constraint hampers the ship's multi-role potential, particularly in offensive strike missions, as it restricts loadouts of versatile missiles like SM-6 or , prioritizing (ASW) at the expense of broader firepower. Critics argue the frigate's heavy specialization reflects an outdated ship-centric model ill-suited to modern , where distributed sensors and effectors could better leverage allied assets like or . Design modifications, including the removal of the mission bay, have further degraded effectiveness by eliminating space for a second or towed-array deployment, shifting emphasis toward air defense despite the platform's primary underwater threat focus. A 2022 Department of Defence review expressed low confidence in the vessel achieving expected performance thresholds amid these changes. The design's has grown to nearly 10,000 tons from an initial 8,800 tons due to Australian-specific integrations like the CEA and combat system, resulting in a heavier that risks reduced speed below operational requirements, diminished , and higher consumption. With only a 3% margin for future upgrades, the platform's adaptability is constrained, exacerbating concerns over its value relative to cost. Propulsion via the CODLOG (combined diesel-electric or gas) system draws scrutiny for inefficiency and high maintenance demands, potentially requiring constant operation that undermines acoustic stealth and further erodes endurance. Analysts, including those from Strategic Analysis Australia, describe the resulting vessel as attempting versatility across domains but excelling in none, yielding suboptimal combat power for its size and expense.

Procurement process deficiencies

The Australian Department of Defence's procurement of the Hunter-class frigates under project SEA 5000 Phase 1 employed a limited process involving shortlisted bidders, including and , but suffered from significant deficiencies that undermined and . The Australian National Audit Office (ANAO) determined that Defence failed to conduct an effective , with inadequate preventing reconstruction of key decision rationales, such as the down-selection of Navantia's Alpha 3000 in favor of BAE's Type 26. This lack of proper record-keeping extended to criteria application and risk assessments, complicating verification of whether value for money was achieved. An internal Defence review released in November 2023 identified further flaws across the planning, shortlisting, and down-select stages, noting that these shortcomings hindered Defence's capacity to secure optimal outcomes despite ministerial involvement from successive governments. Defence Secretary acknowledged the process as "poorly executed" with "numerous shortcomings," including insufficient rigour in assessing bidder capabilities and alignment with operational requirements. These procedural lapses contributed to perceptions of bias toward the UK-aligned BAE design, as the evaluation lacked robust comparative analysis of alternatives like Navantia's offering, which had been adapted from proven in-service platforms. The ANAO highlighted that the Future Frigate Team's outlined roles and responsibilities were not consistently followed, leading to fragmented oversight and delayed milestone achievements during the down-select phase completed in June 2018. Critics, including the ANAO, pointed to inadequate probity measures and failure to mitigate risks from immature designs, though Defence maintained that strategic imperatives, such as with allies, justified despite errors. Overall, these deficiencies eroded confidence in the program's foundational decisions, prompting calls for enhanced governance in subsequent naval acquisitions.

Fleet composition

Planned vessels and naming

The Royal Australian Navy plans to acquire six Hunter-class frigates under the SEA 5000 Phase 1 to enhance its capabilities, replacing ageing Anzac-class vessels. This number reflects a reduction from an initial plan for nine ships, following the 2023 Defence Strategic Review, which prioritized a balanced fleet structure integrating Hunter-class assets with additional general-purpose frigates and optionally crewed vessels. Construction of the lead ship, HMAS Hunter, commenced with steel-cutting in July 2023 at the Osborne shipyard in , managed by in partnership with ASC . The naming convention for the class draws from significant Australian geographical regions and historical naval precedents, emphasizing national identity and operational heritage. The first three vessels are designated HMAS Hunter, HMAS Flinders (II), and HMAS Tasman, announced by the Australian government in June 2018 to honor key areas: the in , Flinders as a nod to the explorer and prior RAN service, and the bordering and . These names were selected to perpetuate traditions of regional tribute seen in prior RAN classes, such as the Anzac frigates. Names for the remaining three frigates have not been publicly disclosed as of October 2025, pending further program milestones.

Acquisition strategy and future expansions

The SEA 5000 Phase 2 program, initiated to procure frigates replacing the Anzac-class, adopted a competitive global tender process emphasizing local and for sovereign capability development. In 2018, the Australian Department of Defence selected BAE Systems Australia's bid, adapting the United Kingdom's into the Hunter-class configuration optimized for RAN requirements, including enhanced anti-submarine sensors and Australian combat systems integration. A $1.9 billion and productionisation contract followed, enabling detailed engineering, prototyping, and facility upgrades at the Osborne Naval Shipyard in . Construction strategy prioritizes domestic industry sustainment, with Maritime Australia—a of —leading assembly alongside partners like ASC for hull modules, targeting modular block fabrication to mitigate risks from 's limited recent large-warship experience. On 20 June 2024, the Head Contract was amended and executed for the first three vessels, marking transition from design to steel-cutting and initial block production, with first-of-class HMAS Hunter delivery projected for the early 2030s. This phased approach, informed by audit recommendations for improved risk management, allocates over $30 billion across the build phase, focusing on workforce training and supply chain localization to support 2,000 direct jobs. Post-2023 Defence Strategic Review and 2024 , the Hunter-class acquisition was refined to six ships, prioritizing high-end specialization amid fiscal pressures and capability gaps, while deferring the original nine-ship plan. Future expansions integrate Hunter-class into a tiered fleet structure, with up to 11 general-purpose frigates—selected as Japan's Mogami-class in 2024—providing multi-role versatility and transitioning builds to for geographic industry distribution. This complements Hunter's focus, enabling Anzac-class life extensions into the mid-2030s and aligning with priorities for enhanced deterrence, without confirmed Hunter variants or additional units beyond the adjusted baseline.

References

  1. [1]
    Hunter Class frigate | Royal Australian Navy
    The Hunter Class frigate, which is a modified version of BAE System's Type 26 frigate, will be one of the most advanced anti-submarine warships in the world.
  2. [2]
    Hunter Class Frigate | Defence
    The Hunter Class Frigate Program will provide the Australian Defence Force with the highest levels of anti-submarine capability.
  3. [3]
    Product | Hunter class frigate - BAE Systems
    The design and build of Hunter class frigates (SEA 5000), led by BAE Systems Australia, is the biggest surface ship project in Australia's defence ...
  4. [4]
    Australia Cuts Steel on its First Hunter-class Frigate - Naval News
    Jun 21, 2024 · Hunter-class frigate specifications: Displacement: 8,800 t full load. Length: 151.4 m (496 ft 9 in) Beam: 21.4 m (70 ft 3 in) Propulsion ...
  5. [5]
  6. [6]
    [PDF] HUNTER CLASS COMBAT SYSTEM PROGRESS
    May 11, 2025 · for the program, Defence replied: “The first Hunter Class frigate is expected to be delivered in 2032 and operational in 2034. Ships 2 and 3 ...
  7. [7]
    Hunter Class frigate director-general hits back at renewed criticism
    Sep 4, 2025 · Australia's Hunter Class frigate program has come under renewed fire after Norway secured a deal to buy new British-designed warships for ...
  8. [8]
    [PDF] pacific: australian defense strategy and the future of the australia
    Jun 24, 2013 · overriding aim of our naval forces should be to help deny the sea approaches to Australia and our close neighbours to hostile forces, and to ...
  9. [9]
    [PDF] Full report for Australia's Maritime Strategy
    Jun 4, 2004 · The key to defending Australia is 'to control the air and sea approaches to our continent, so as to deny them to hostile ships and aircraft, and ...
  10. [10]
    [PDF] Australia's 2009 Defense White Paper
    Nevertheless, the white paper proposes a robust future defense force with a very strong maritime emphasis, in- cluding a sea-based strike capacity and the ...
  11. [11]
    [PDF] Defence White Paper 2009 - Defending Australia in the Asia Pacific ...
    Apr 15, 2009 · 9.13 The Government will also acquire a fleet of eight new Future Frigates, which will be larger than the. Anzac class vessels. The Future ...
  12. [12]
    Department of Defence's Procurement of Hunter Class Frigates
    The 2009 Defence White Paper announced that: The Government will also acquire a fleet of eight new Future Frigates, which will be larger than the Anzac class ...
  13. [13]
    SEA 5000: Building Australia's Future Frigates - Naval Technology
    Jun 25, 2018 · Dive into the Sea 5000 program and its role in shaping Australia's future frigates. This feature explores the design, technology, ...Missing: origins | Show results with:origins
  14. [14]
    [PDF] Future Frigates - Australian National Audit Office
    Jun 30, 2020 · SEA 5000 Phase 1 – Future Frigate Design and Construction will deliver nine Hunter Class Frigates optimised for anti-submarine.Missing: origins | Show results with:origins
  15. [15]
    Hunter-class Frigate Procurement Flawed: Review - Naval News
    Jan 15, 2024 · A review into Australia's procurement of the Hunter-class frigate has found serious issues with the procurement process that led to the BAE Systems Type 26 ...
  16. [16]
    Reports: Australia Picks BAE Systems Design for $26B Warship Deal
    Jun 28, 2018 · BAE Systems won a $26 billion contest to design and build nine frigates for the Royal Australian Navy, according to Thursday media reports.
  17. [17]
    BAE Systems Starts Design Work on Hunter-class Australian Frigate
    Dec 14, 2018 · In June, BAE subsidiary ASC Shipbuilding signed a $26-billion contract to design and build nine Hunter-class frigates based on the company's ...
  18. [18]
    Auditor fires off scathing assessment of $45 billion future frigates ...
    May 9, 2023 · An ANAO report found the Hunter-class program is experiencing an 18-month delay and additional costs · The report has also found the scheduled ...<|separator|>
  19. [19]
    [PDF] SEA5000 Phase 1 - Australian National Audit Office
    Dec 18, 2024 · ... Future Frigate program to replace the Anzac Class Frigates as part of a continuous onshore build program to commence in 2020. • September ...Missing: origins | Show results with:origins
  20. [20]
    €4bn per Hunter class frigate! What's wrong with Australia?
    Oct 4, 2024 · ... Review 2024, this program, initially of 9 ships for $35 billion, has been reduced to only 6 units, while a new class of 11 multi-purpose ...
  21. [21]
    Hunter Class Multi-Mission Frigates, Australia - Naval Technology
    Jul 17, 2020 · The length and beam of the frigate will be 149.9m and 20.8m respectively, while the full load displacement will be 8,800t. The Hunter-class ...Missing: specifications | Show results with:specifications
  22. [22]
    Construction advances on Australia's first Hunter-class frigate
    Each of the six Hunter-class frigates will be made up of 22 hull blocks that, in turn, will be comprised of between one and seven consolidated steel units.Missing: dimensions arrangement<|separator|>
  23. [23]
    [PDF] Hunter Class Frigate Project – the Path to Designing and Building ...
    Altering the General Arrangement and/or moving equipment from one compartment to another requires reiteration of the HVAC design to balance cooling loads ...
  24. [24]
    [PDF] Australia's Hunter Class Frigate Program
    Under Project SEA5000 Phase 1, the Hunter Class Frigate Program (HCFP) is re- capitalising the majority of Australia's surface combatant fleet with a state ...
  25. [25]
    Australia's anti-submarine frigate program sails rough seas
    Dec 21, 2023 · Analysts have criticized the program, citing the frigate design's weight growth, scheduling delays and what they view as an inadequate ...Missing: results | Show results with:results
  26. [26]
    L3Harris UK to Optimize New Australian Hunter-class Frigates for ...
    Mar 31, 2025 · Under this contract award, L3Harris will design and deliver the IPMS, a sophisticated solution for managing ship's propulsion, power generation ...
  27. [27]
    [PDF] hunter class ffg fact sheet - Royal Australian Navy
    The first Hunter class frigate will be introduced into service from the late 2020s. ... TECHNICAL SPECIFICATIONS. The Future Frigate will be based on BAE ...
  28. [28]
    BAE Systems selects Combat Systems Integration partners for ...
    Nov 23, 2018 · The Combat Management System for the new Hunter Class frigate fleet will be the Aegis System, together with an Australian tactical interface ...Missing: control | Show results with:control<|control11|><|separator|>
  29. [29]
    Combat systems providers chosen for Hunter class
    Nov 23, 2018 · The Combat Management System for the new Hunter class frigate fleet will be the Aegis System, together with an Australian tactical interface ...
  30. [30]
    Australia integrates Sea Eagle surveillance to Hunter-class frigates
    Mar 25, 2024 · Chess Dynamics will provide its Sea Eagle electro-optical surveillance systems to the Royal Australian Navy's six Hunter-class frigates.
  31. [31]
    Ultra Maritime Australia to provide hull mounted sonar on Hunter ...
    Mar 10, 2025 · The Royal Australian Navy's Hunter-class frigates will be fitted with Ultra Maritime's world-leading 2150 hull mounted sonar under a contract with BAE Systems ...Missing: S2087 | Show results with:S2087<|separator|>
  32. [32]
    Hunter Class Frigate - Defense Update:
    Jun 29, 2018 · For its anti-submarine role, the vessel will use an Ultra S2150 hull-mounted sonar, The S2087 Towed Array and Variable Depth Sonar system from ...
  33. [33]
    Comms system to be integrated onto Australian frigates by Rohde ...
    Rohde & Schwarz Australia won a contract to deliver its NAVICS integrated communication and control systems for the first three Hunter class frigates of the ...<|separator|>
  34. [34]
    Anschütz WINBS selected for Hunter-class frigates - Anschuetz
    Nov 6, 2023 · Anschütz will deliver WINBS including multifunctional consoles for warship electronic chart display and information systems, naval radars, as well as ...
  35. [35]
    BAE Systems to equip Royal Australian Navy's Hunter class frigates ...
    Nov 15, 2023 · BAE Systems has received a contract to deliver multiple shipsets of the Mk 45 Medium Caliber Gun and automated Ammunition Handling System (AHS) for the Royal ...
  36. [36]
    Hunter class Guided Missile Frigate Royal Australian Navy
    The Hunter class is a six-ship, advanced anti-submarine frigate with a 7,000 NM range, 180 crew, and a 27+ knot speed, capable of various missions.
  37. [37]
    Confirmation Australia to fit British sonar to new frigates
    Dec 17, 2024 · The UK Government has confirmed that Australia will equip its Hunter-class frigates with the Thales 2087 sonar system.
  38. [38]
    Navy strengthens Global Combat Ship links | Defence
    May 8, 2025 · “The capability the Hunter-class will bring is set to transform the Navy's Anti-submarine Warfare capacity, supporting the National Defence ...
  39. [39]
    Digitally transforming the Osborne Naval Shipyard - BAE Systems
    Oct 9, 2024 · Constructing the Hunter Class Frigate Program's six anti-submarine warships across Australia's largest shipyard – Osborne Naval Shipyard in ...
  40. [40]
    BAE Systems Hunter Class Frigate Program
    During the D&P Phase we will publish further details of the Hunter program's Australian Industry Capability (AIC) strategy. The AIC strategy will seek to ...
  41. [41]
    BAESMA expands Hunter supplier partnerships - APDR
    Apr 30, 2025 · BAE Systems Maritime Australia is expanding its Strategic Supplier Partnerships to protect the construction schedule of Hunter Class ...
  42. [42]
    Progress continues on Hunter Class frigate build with expanded ...
    Apr 29, 2025 · To date, two partnerships are in place: Century Engineering at Edinburgh North and MG Engineering at Port Adelaide, both delivering critical ...
  43. [43]
    Rohde & Schwarz Australia and STS Defence team up for Hunter ...
    Aug 11, 2025 · As a key partner in the HCFP program, Rohde & Schwarz Australia has selected STS Defence to supply the critical communications masts that, when ...
  44. [44]
    BAE Systems Hunter Class Frigate Program - ICN Gateway
    Since being selected as the preferred tenderer and signing the Head Contract in December 2018 ... Awarded. Full scope EOI closes on. 10 Dec 2019. BAE Systems ...
  45. [45]
    Building on Hunter with the first machinery unit consolidation
    Jul 9, 2025 · Each of the six Hunter class frigates will be made up of 22 hull blocks that, in turn, will be comprised of between one and seven consolidated ...
  46. [46]
    Construction advances on Australia's first Hunter-class frigate
    Jul 9, 2025 · Each of the six Hunter-class frigates will be made up of 22 hull blocks that, in turn, will be comprised of between one and seven consolidated ...
  47. [47]
    BAE Systems Australia - Facebook
    Sep 30, 2025 · Another big milestone for Ship 1 of the Hunter Class Frigate Program! Installing the fin stabiliser is no small feat.
  48. [48]
    Innovation drives milestone on Hunter Class Frigate Program
    Oct 1, 2025 · “This strategy reduces rework, improves safety and quality, increases build efficiency, and lowers cost. The baseplate was lifted into the hull ...
  49. [49]
    Liferaft Systems comes onboard Australia's Hunter-class frigate ...
    Sep 17, 2025 · Hobart-based Liferaft Systems Australia (LSA) has been selected to supply marine evacuation systems (MES) for the Hunter-class frigates.
  50. [50]
    Delivering a stronger Navy, faster - ASPI
    Nov 2, 2021 · The first Hunter frigate is already delayed to around 2033 and, with the program facing complex integration challenges and vanishing design ...
  51. [51]
    First steel cut for Australia's Hunter Class frigates - Marine Log
    Jun 21, 2024 · BAE Systems was first contracted to build nine Hunter frigates in 2018, but after the project was delayed due to cost blowouts and design issues ...
  52. [52]
    Defence admits numerous failings in Hunter class frigate program ...
    Nov 15, 2023 · The Defence Department has conceded it failed in several key procedural areas during the assessment and subsequent recommendation to government of the winning ...Missing: bidders | Show results with:bidders
  53. [53]
    The Type 26 frigate serves as a cautionary tale about our Navy
    Jul 14, 2025 · The Type 26 program faced issues due to a failed gearbox, poor communication, and a mismatch between ambitions and industrial capabilities, ...
  54. [54]
    Troubled $45b future frigate project starts turnaround - AFR
    Aug 29, 2022 · BAE Systems' Hunter class frigate program is overcoming some delays. The setbacks with the project, coupled with the federal government ...Missing: production | Show results with:production
  55. [55]
    FROM THE MAGAZINE: Combat management system integration on ...
    Apr 27, 2025 · The RAN's six Hunter class frigates will be among the most powerful ships in their class by combining Australian and US combat system elements.
  56. [56]
    RAN strengthens Global Combat Ship links - CONTACT magazine
    May 8, 2025 · “Australia's participation in the GCS program is central to the success of the Hunter-class frigate – the Navy's next generation of warships,” ...
  57. [57]
    BAE Systems submission to - UK Parliament Committees
    This includes collaboration on advanced anti-submarine warfare capability through the Royal Australian Navy's Hunter Class Frigate, a ship based on the UK's ...
  58. [58]
    Australian Navy capability head : 'zero-change' is right strategy for ...
    May 28, 2024 · These new ships will operate independently and in conjunction with the Hobart class air warfare destroyers and Hunter class frigates to secure ...
  59. [59]
    [PDF] bae systems proprietary - UK Parliament Committees
    May 2, 2025 · BAE Systems' contribution to AUKUS will be further enhanced by the recent experience it has gained from the Hunter Class Frigate Programme. This ...
  60. [60]
    BAE Offers Evolved, Up-armed Hunter for Australia - Naval News
    Nov 7, 2023 · Hunter Class Frigate A rendering of a Batch I Hunter with 32 VLS cells . (Image: BAE Systems Maritime Australia). BAE is also exploring ...
  61. [61]
    Global Combat Ship Ultra-Quiet Hybrid Electric ASW Frigate
    Jan 17, 2022 · GE technology delivers an extremely low noise signature, with high shock performance and action damage tolerance. The Type 26 Frigate Global ...
  62. [62]
    Well worth the wait? Discussing the inconsistencies and focusing on ...
    Nov 27, 2024 · As a maritime nation, Australia depends on a lethal, survivable and robust naval capability, something the Hunter Class frigates will play a pivotal role in ...
  63. [63]
    Type 26 Frigate - Defence Equipment & Support
    May 4, 2023 · The Type 26 frigate is set to be the Royal Navy's most advanced Anti-Submarine Warfare (ASW) warship of her time, designed for critical protection.Missing: advantages | Show results with:advantages
  64. [64]
    Hunter-class frigates won't meet the RAN's needs - ASPI Strategist
    Apr 13, 2022 · The Hunter is designed to follow in the Hobart's footsteps and, despite its limited firepower (32 VLS cells), will possess one significant advantage.
  65. [65]
    Hunter class frigate program passes Preliminary Design Review ...
    Nov 30, 2023 · Everyone is being cagey about the maximum weight of the ship. The light weight has increased by 10% from 8,000 tonnes to 8,800 tonnes. The ...
  66. [66]
    BAE unveils 'upgunned' Hunter proposal
    Nov 7, 2023 · ... Hunter-class frigate design, which will increase the number of vertical launch system (VLS) cells from 32 to 96. The changes will come at ...
  67. [67]
    2023–24 Major Projects Report - Australian National Audit Office
    In June 2024 the JCPAA tabled Report 503: Inquiry into the Defence Major Projects Report 2020–21 and 2021–22 and Procurement of Hunter Class Frigates. The ...
  68. [68]
    Attack Submarines Dominate Record High $36.8B Australian ...
    May 20, 2024 · The Hunter-class program will receive AU$813 million in the year ahead, while the OPVs will garner AU$587 million. Regarding the antisubmarine ...<|control11|><|separator|>
  69. [69]
    Opinion: Hunter-Class Frigates - More Costs, Less Value
    Sep 30, 2024 · In the case of the future frigate program, the estimated cost looks like going from around $3.3 billion per vessel to something in excess of ...Missing: escalations impacts
  70. [70]
    ANAO report critical of Navy's frigate program
    May 16, 2023 · The report also disclosed that the SSAC had been asked to review cost, schedule and risk across the Sea 5000 Phase 1 program and provide input ...
  71. [71]
    Contract award and steel cut marks historic day for Hunter Class ...
    Jun 21, 2024 · The Commonwealth of Australia has awarded BAE Systems Maritime Australia a contract to build the first three Hunter class frigates.Missing: 2018 2019
  72. [72]
    The Hunter frigate: An assessment - ASPI
    Apr 28, 2022 · This report explores the disconnect between doctrine and policy, which has led Australia to building a warship that is unsuited for its purposes.<|separator|>
  73. [73]
    Adding firepower to the Type 26 Frigate - Navy Lookout
    Nov 24, 2023 · The standard Hunter class missile fit – 32 Mk 41 cells forward and 2 x quad Harpoon Block II launchers behind the funnel. Note the bulk of the ...
  74. [74]
    The Type 26 frigate serves as a cautionary tale about our Navy
    Jul 14, 2025 · A formal review by the Australian Department of Defence in 2022 expressed “low confidence” in the vessel meeting ASW performance expectations ...Missing: criticisms | Show results with:criticisms
  75. [75]
    [PDF] HUNTER CLASS FRI GA TE PROCUREMENT INTERNAL REVIEW ...
    Nov 10, 2023 · 1. Across the planning, shortlisting and down-select stages of the procurement, deficiencies in the process complicated the ability of Defence ...
  76. [76]
    Defence admits 'poorly executed' process in $45 billion future frigate ...
    Nov 12, 2023 · Defence's secretary says successive ministers were closely involved in a process with numerous shortcomings. In 2018 the Turnbull government ...Missing: deficiencies | Show results with:deficiencies
  77. [77]
    Sea - BAE Systems
    BAE Systems Australia today welcomed a $45 million, three year contract extension with the Commonwealth of Australia to provide in-service periscope support for ...Missing: 2 date
  78. [78]
    Batch one Hunter class build contract signed
    Jun 21, 2024 · The signing of a build contract for the first three Hunter class frigates. The first Hunter-class frigate is expected to be operational in 2034 according to ...
  79. [79]
    Australia's defence industrial base expanded to deliver Navy's ...
    Feb 20, 2024 · In South Australia, the construction of the Hunter class frigates at Osborne will sustain at least 2,000 jobs and create at least 500 new ...
  80. [80]
    Understanding the cost of Australia's naval defence
    Jun 7, 2025 · Under SEA 5000, six advanced Hunter‑class frigates optimised for antisubmarine warfare are to be acquired, along with their associated support ...<|separator|>
  81. [81]
    AUSTRALIA ACCELERATES NAVAL EXPANSION WITH ...
    Future builds will transition to Western Australia, supporting around 10,000 skilled jobs and contributing to a $55 billion naval investment. This decision is ...
  82. [82]
    The Hunter-class frigate program: delivering less, costing more ...
    Sep 27, 2024 · SEA 5000, the future frigate program, was originally scoped to acquire nine frigates. Its provision in the 2016 Integrated Investment ...Missing: origins | Show results with:origins