Pebble Mine

![USA_Alaska_location_map.svg.png][float-right]
The Pebble Project, commonly referred to as Pebble Mine, is a proposed development targeting a world-class -- deposit located in southwest Alaska's region, approximately 200 miles southwest of Anchorage on state-owned land within the Lake and Peninsula Borough. Owned entirely by Northern Dynasty Minerals Ltd. through its Pebble Limited Partnership subsidiary, the deposit holds vast mineral resources estimated to include billions of pounds of , tens of millions of ounces of , and significant quantities of and , positioning it as one of the largest undeveloped reserves of these critical metals globally.
The project promises substantial economic advantages for , such as direct and indirect job creation numbering in the thousands during operations, billions in potential state royalties and taxes, and a new domestic supply of minerals essential for and sectors. However, it has sparked intense opposition due to concerns over irreversible environmental risks, particularly the potential for mine-related discharges to degrade water quality, destroy wetlands, and disrupt the watershed's globally significant fisheries that support commercial, sport, and subsistence economies valued in the billions annually. In January 2023, the U.S. Environmental Protection Agency invoked the rare Section 404(c) under the Clean Water Act to prohibit discharges associated with Pebble's development, citing unacceptable adverse effects on —a decision upheld by the subsequent administration but contested in ongoing federal litigation as an unlawful preemption of state regulatory processes. As of October 2025, court challenges persist, with proponents arguing that advanced engineering and phased development could mitigate impacts while delivering net societal benefits.

Location and Physical Setting

Geography and Regional Context

The deposit is situated in southwest 's region, within the Lake and Peninsula Borough, approximately 200 miles southwest of Anchorage on state-owned land. The site coordinates are approximately 59°53'49" N, 155°17'41" W, placing it near the headwaters of streams draining into the Kvichak River system of the broader watershed. It lies about 17 miles northwest of the village of Iliamna and adjacent communities like Newhalen, both on the shores of Lake Iliamna. The regional terrain features remote, relatively flat expanses of wet interspersed with low mountains, characteristic of the area's glaciated lowlands and rolling hills. Key hydrological elements include proximity to Lake Iliamna, Alaska's largest freshwater lake, and rivers such as the Koktuli and Newhalen, which originate or flow nearby before contributing to Bristol Bay's extensive drainage network. The deposit is roughly 65 miles from tidewater along to the east, underscoring its inland yet accessible position relative to coastal marine influences. Climatically, the area receives high annual precipitation, often exceeding 30 inches, fostering saturated soils and formation across the landscape. The region experiences sporadic , with discontinuous frozen ground influencing surface stability and hydrology, particularly in lower elevations. lies within a seismically active zone along the Pacific , subject to frequent earthquakes due to tectonic plate interactions, which contribute to ongoing geomorphic processes like faulting and uplift.

Geological Formation

The Pebble deposit represents a classic copper-gold-molybdenum system, characterized by disseminated and vein-hosted mineralization within and around intrusive rocks. The primary host lithologies include porphyritic to , dated to approximately 90 million years ago, intruded into older deformed sedimentary and volcanic sequences of the Peninsular terrane. Formation occurred through magmatic-hydrothermal processes, wherein volatile-rich granitic magmas, derived from of metasomatized , emplaced at shallow crustal levels and released metal-bearing fluids upon cooling. These fluids, enriched in , , , and , migrated through fractures and permeated host rocks, precipitating sulfides such as , , and in veins and as disseminations, with associated gangue minerals like and in proximal zones. Regionally, the deposit developed in a setting along the evolving margin of northwestern , driven by of oceanic plates beneath the North American , leading to arc-continent collision, lithospheric thickening, and post-collisional magmatism between 100 and 90 million years ago. Palinspastic reconstructions indicate the Pebble system originated over 1,000 kilometers south of its current position, subsequently translated northward via dextral strike-slip faulting and oroclinal bending of the Alaskan terranes. Localization of mineralization was structurally controlled by intersections of regional and local faults, including the northeast-trending Lake Clark Fault as a primary control, alongside local steep reverse and normal faults (e.g., ZE and ZF with offsets of 50-300 meters) that channeled hydrothermal fluids along a brittle-ductile shear zone extending 2.3 kilometers in length and 1.6 kilometers in depth. Hydrothermal alteration assemblages, mapped through and (IP) geophysical surveys conducted since 1989 and expanded in 2001-2004, encompass a potassic (potassium-silicate with and K-feldspar), flanked by sericite-pyrite and propylitic halos extending up to 5 kilometers outward, with advanced argillic zones peripherally; IP chargeability anomalies, such as a 3-square-kilometer feature in the 38 Zone, delineated concentrations and guided exploratory exceeding 800,000 feet.

Associated Ecosystems and Fisheries

Bristol Bay encompasses the world's largest (Oncorhynchus nerka) fishery, with annual inshore runs averaging over 50 million fish in recent decades, as reported by the Alaska Department of Fish and Game (ADF&G). The 2025 run totaled 56.7 million , the seventh largest since 2005 and 16% above the preseason forecast, while the 2020 run ranked as the fifth largest on record at approximately 70 million fish. These runs spawn across thousands of streams in the interconnected watersheds of the Nushagak, Kvichak, and Igushik river systems, which collectively drain over 40,000 square miles into the bay and sustain five Pacific salmon species alongside resident fish. The of these watersheds features high densities—exceeding 3 miles per in some subbasins—and extensive networks that regulate seasonal flows, , and critical for habitat formation. Pristine, undisturbed flow regimes support juvenile rearing in off-channel sloughs and beaver ponds, with geomorphic features like glacial valleys and braided channels fostering diverse thermal mosaics that align with life stages. Salmon nutrient cycling underpins broader , as decomposing carcasses deliver marine-derived and that enhance riparian productivity and food webs. Peer-reviewed syntheses of 31 studies document 172 positive correlations between salmon density and abundances of aquatic , stream , riparian vegetation, (e.g., bald eagles), and mammals (e.g., brown bears), with effects propagating through trophic levels via increased and detrital subsidies. In specifically, stable tracing reveals salmon incorporation into riparian tree foliage and soils at rates supporting invertebrate outbreaks that feed salmon smolts, while sustaining over 40 species and multiple populations reliant on salmon-fueled crops.

Local Human Populations

The communities nearest to the Pebble Mine site, located in the region of around Lake Iliamna, are small, predominantly Alaska Native villages including Iliamna, Newhalen, and Nondalton. According to the 2020 U.S. Census, Iliamna had a of 108 residents, of whom approximately 59% identified as Native American or Alaska Native. Newhalen recorded 168 residents, with about 76% identifying as Native American or Alaska Native. Nondalton had 116 residents, predominantly Alaska Native. These populations remain under 200 each as of recent estimates, reflecting the remote and sparsely settled character of the area. Residents rely on a subsistence economy centered on harvesting wild resources, with salmon comprising a primary food source alongside moose, caribou, and berries. Alaska Department of Fish and Game surveys document substantial annual subsistence harvests in these villages; for example, in 2004, households in Iliamna, Newhalen, and Nondalton reported using sockeye salmon extensively, with estimated community-wide harvests in the Kvichak Watershed reaching tens of thousands of fish in peak decades like the 1990s and 2000s. Moose and other ungulates provide additional protein, while berry picking supplements diets, underscoring the cultural and nutritional dependence on local ecosystems. Infrastructure in these villages is minimal, lacking connections to Alaska's road system and depending instead on air and water transport. Iliamna Airport serves as the main regional hub for scheduled flights and cargo, facilitating access to approximately 150 miles northeast, while boat travel across connects communities during ice-free months. Limited local roads exist for intra-village use, but seasonal ice on the lake can restrict overland alternatives in winter.

Mineral Resources and Potential

Ore Body Characteristics

The Pebble ore body constitutes a porphyry-style copper-gold-molybdenum deposit divided into the roughly equal-sized Pebble East and Pebble West zones, forming a multi-phase system influenced by multiple intrusive and alteration events. The deposit exhibits a tabular with a strike length of approximately 13,000 feet (4 km) and width up to 7,700 feet (2.3 km), extending from near-surface to depths exceeding 5,810 feet (1.77 km) in Pebble East and 3,000 feet (0.91 km) in Pebble West, based on drilling intersections. Mineralization occurs as disseminated sulfides and stockwork veins within a sequence of Cretaceous-age host rocks, primarily sediments (, wacke, ) intruded by , , sills (10–1,000 feet thick), and alkalic stocks such as . Dominant ore minerals include as the primary copper carrier, (locally abundant in advanced argillic zones), and , with occurring as or microscopic inclusions in sulfides and silicates; minor supergene phases feature and . Associated gangue minerals comprise (abundant in potassic and illite-pyrite domains), (in veinlets), sericite, , , , , , , and , reflecting alteration zonation from potassic cores outward to sodic-potassic, argillic, and propylitic envelopes. These assemblages are documented through assays of over 59,000 core samples from 699 holes completed between 2004 and 2018, revealing structural controls such as the east-side brittle-ductile fault and normal faults (e.g., ZG1 with 2,100–2,950 feet displacement) that localize higher-grade sets. Grade variability across the deposit, derived from core analyses, shows content ranging from 0.16% to 1.51% (with outliers capped at 9.29%), from 0.009 to 0.83 g/t, and from 0.011% to 0.042% (up to 32,200 ppm capped), with higher - concentrations in East near faults and deeper enrichment in central domains. This heterogeneity correlates with host and alteration intensity, such as elevated grades in iron-rich sills versus lower values in hornfelsed , as evidenced by intervals like 949 feet at 1.24% , 0.74 g/t , and 0.042% in hole 6348.

Estimated Reserves and Grades

The Pebble deposit's mineral resource estimate, prepared in accordance with standards and effective August 21, 2023, reports measured and indicated resources totaling 6.456 billion metric tonnes at an average grade of 0.40% , 0.34 grams per , 240 parts per million , and 1.7 grams per silver, using a 0.3% equivalent constrained by a conceptual open-pit shell. These categories contain approximately 53 billion pounds of , 53.8 million ounces of , 2.78 billion pounds of , and 249 million ounces of silver. Inferred resources add 4.454 billion metric tonnes at grades of 0.25% , 0.25 g/t , 226 ppm , and 1.2 g/t silver, with contained metals of 22.7 billion pounds , 28.1 million ounces , 1.81 billion pounds , and 122 million ounces silver. The estimates, audited by independent qualified persons, derive primarily from over 1,500 holes totaling more than 700,000 meters completed between 1988 and 2019, with verified data emphasizing empirical intersections over broader modeling.
Resource CategoryTonnage (Mt)Cu (%)Au (g/t)Mo (ppm)Ag (g/t)Contained Cu (Blbs)Contained Au (Moz)Contained Mo (Blbs)Contained Ag (Moz)
Measured5270.330.351781.73.355.90.1528.9
Indicated5,9290.410.342461.749.647.32.62220.2
Measured + Indicated6,4560.400.342401.753.053.22.78249.1
Inferred4,4540.250.252261.222.728.11.81121.7
Average grades reflect composited results from diamond , with grades verified across porphyry-style mineralization zones and /molybdenum distributions corroborated by / protocols including blanks, standards, and duplicates showing no material biases. However, inferred portions rely more heavily on geological continuity models and geophysical data for deeper extensions beyond dense coverage, introducing higher due to limited sampling in faulted or structurally complex areas. No additional has occurred since 2019, and the estimates exclude potential credits beyond regression-based modeling from molybdenum , underscoring that these resources lack demonstrated economic viability and do not constitute reserves.

Economic Valuation of Deposits

The Pebble deposit's measured and indicated resources contain approximately 57 billion pounds of , 71 million ounces of , and 3.4 billion pounds of , based on a 2020 updated mineral resource estimate prepared in accordance with NI 43-101 standards. Applying first-principles valuation to these contained metals—multiplying quantities by market prices without accounting for recovery rates, extraction costs, or metallurgical efficiencies—yields an in-situ value exceeding $300 billion using at $4 per , at $2,000 per , and at approximately $10 per . At elevated 2025 market prices ( around $5 per , over $4,000 per , and near $32 per ), this gross value surpasses $600 billion, though such figures represent theoretical maximums independent of economic extractability. Preliminary economic assessments provide net present value (NPV) estimates for potential development scenarios, discounting future cash flows from projected revenues minus capital and operating expenditures. The 2023 Preliminary Economic Assessment (PEA) for a phased open-pit operation outlines a base case pre-tax NPV of approximately $2.8 billion (at a 7% discount rate) for an initial 20-year phase producing 180,000 tons per day, with expansion potential to a 45-year life yielding higher returns, an internal rate of return (IRR) of 14.2%, and payback within 6.2 years on $4.7 billion initial capital. These figures incorporate benchmark capital costs of $20,000–$25,000 per daily tonne capacity and operating costs aligned with comparable porphyry copper-molybdenum projects, using metal prices such as $3.50 per pound copper and $1,800 per ounce gold. Adjustments for current higher commodity prices significantly enhance NPV sensitivity, with each $0.50 per pound increase in copper pricing adding billions to discounted value, underscoring the deposit's leverage to global metal cycles. The polymetallic nature of positions it to supply critical minerals like and , where U.S. production meets only about 40% of domestic demand and less than 20% for , with heavy reliance on imports from unstable sources. Realizing even partial extraction could mitigate supply vulnerabilities for these materials, essential for , infrastructure, and applications, though valuations remain contingent on volatile long-term price forecasts rather than spot levels.

Historical Development

Discovery and Initial Exploration

The Pebble deposit was discovered in 1987 by geologists from , a of Cominco Ltd. (later acquired by ), during regional for and in . Geologist Phil St. George identified color anomalies indicative of mineralization while flying over the area near Lake Iliamna, leading to ground-based surface rock sampling that confirmed elevated , , and values at what became known as Pebble Beach. Initial drilling commenced in with two helicopter-supported diamond drill holes at the site, which intersected low-grade mineralization suggestive of a system. In 1989, CAE expanded efforts with 12 additional drill holes, accompanied by soil sampling and geophysical surveys, revealing the first significant intercepts, including high-grade zones up to 1 ounce per ton in a secondary deposit. These results delineated an initial resource of approximately 500 million tons grading 0.35% and 0.012 ounces per ton by the end of 1991. Exploration continued intermittently through the early , with a short program in 1992 testing peripheral targets, followed by a second major campaign in 1997 that doubled the estimated resource to about 1 billion tons at comparable grades, solidifying the porphyry copper-gold-molybdenum nature of the deposit. In 2001, after this foundational delineation, CAE optioned the property to Northern Dynasty Minerals Ltd., marking the transition from initial discovery to advanced development planning.

Ownership and Funding Evolution

Northern Dynasty Minerals Ltd., a Vancouver-based exploration company, acquired the Pebble property in October 2001 through a purchase option held by its U.S. subsidiary from Teck Cominco, securing 100% interest in the deposit. In November 2007, Northern Dynasty formed the Limited Partnership (PLP) with , a London-based firm, granting Anglo a 50% earn-in interest in exchange for committed exploration funding of up to $310 million initially, with potential for further investment toward development. Anglo ultimately invested $573 million in the partnership before announcing its withdrawal on September 16, 2013, citing strategic reprioritization; Northern Dynasty subsequently reacquired full 100% ownership and control of the PLP by December 2013, with all Anglo representatives resigning from the board. Rio Tinto plc, another major mining company, acquired a 19.1% stake in Northern Dynasty in 2010 for approximately $25 million, providing indirect support to Pebble-related activities through shareholding. Rio Tinto divested this position in April 2014 by donating the shares to two Alaska-based charitable foundations focused on education and community development, effectively exiting its involvement without financial return on the investment. To sustain operations amid permitting delays and exploration costs, Northern Dynasty secured a $60 million net smelter return royalty financing agreement in 2022 with an undisclosed third-party investor, entitling the investor to 10% of payable production and 30% of payable silver production from Pebble upon commercial development. The deal funds in five $12 million s tied to milestones; by October 20, 2025, Northern Dynasty received the fifth and final tranche ahead of its December 31 deadline, completing the full $60 million infusion to support administrative, legal, and preparatory efforts.

Early Feasibility Studies

The Pebble Limited Partnership, formed by Northern Dynasty Minerals Ltd. and , initiated preliminary feasibility studies in the mid-2000s to assess the technical viability of developing the deposit via methods. These studies targeted completion of a pre-feasibility report by late , incorporating drilling data from ongoing since 2002 and evaluating processing flowsheets. Metallurgical testwork, including locked-cycle flotation trials on variability samples, confirmed the potential for producing marketable copper and concentrates, with recovery rates for copper aligning with expectations for deposits (typically 85-90% via ). Concurrent with technical evaluations, environmental studies commenced in 2004 to document pre-development conditions in the region. These efforts, conducted by the Pebble Partnership, encompassed assessments, terrestrial and aquatic wildlife surveys, and monitoring across study areas near the deposit. Progress reports from 2004 detailed initial findings on dynamics and ecosystem parameters, forming the foundation for subsequent environmental analyses without yet addressing measures. By 2008, these studies had compiled extensive data on local , fish populations, and , though critics later questioned the scope's adequacy for capturing seasonal variability. Early reports outlined phased development concepts to mitigate initial capital risks, proposing an initial smaller-scale operation focused on higher-grade zones before expanding to full deposit extraction. This approach, detailed in preliminary assessments by 2011, aimed to sequence phases over decades, with studies emphasizing modular to align with conditions and permitting milestones. Such concepts underscored the deposit's scale—estimated at billions of tons of —but highlighted dependencies on favorable and unresolved environmental gaps identified in work.

Proposed Project Details

Mining and Processing Methods

The Pebble Project's mining plan centers on open-pit using conventional drill-and-blast methods, with loaded and hauled by trucks to a nearby processing facility. The 2023 Preliminary Economic Assessment outlines an initial operation processing 180,000 metric tons per day of mineralized material from a low-grade deposit, achieving a strip ratio of 0.12:1 over a 20-year life. Later phases could transition to underground block-caving to access deeper zones, potentially extending operations beyond the initial period. Ore processing follows standard sulfide beneficiation flowsheets, beginning with primary crushing to reduce rock size, followed by semi-autogenous grinding (SAG) mills and ball mills to liberate minerals. The ground then undergoes in a series of cells to separate valuable s, yielding a - and a distinct , with recoveries targeted at approximately 90% for and based on metallurgical testing. Tailings management emphasizes thickened deposition to minimize free water and enhance , with non-potentially acid-generating bulk directed to a dedicated facility and potentially acid-generating pyritic to a separate lined impoundment. This method involves via thickeners prior to deposition, contrasting with unthickened impoundments by promoting faster and reducing seepage risks under seismic conditions prevalent in . Over the project's life, approximately 1.3 billion metric tons of would be generated from 1.3 billion tons of .

Infrastructure and Operations Plan

The Pebble Project's infrastructure plan centers on a transportation corridor linking the mine site to a marine terminal at Amakdedori Bay (also referred to as Diamond Point), incorporating an 82-mile private, two-lane gravel access road designed for two-way traffic with heavy haul trucks, featuring a 30-foot-wide running surface, maximum 8-10% grades, and 17 bridges including a 550-foot span over the Newhalen River to minimize crossings of anadromous streams. On-site haul roads, 110 feet wide, support 400-ton trucks, while service roads handle lighter vehicles; the network avoids direct impacts to key salmon-bearing streams through elevated crossings and culverts with fish passage designs. Fly-in/fly-out operations rely on the existing Iliamna airfield with dual 4,920-foot paved runways, proposed for upgrade to a 6,000-foot length to accommodate larger , connected via a temporary spur road. Energy supply features a 164-mile natural gas pipeline from the Kenai Peninsula across Cook Inlet, comprising a 12-inch diameter steel line (12.75-inch outer diameter, API Spec 5L grade X52) buried alongside the access road in a shared trench with concentrate and water return pipelines, including a compressor station near Anchor Point delivering gas at 725 psig and fiber optic cabling for communications. This fuels a 270 MW combined-cycle gas turbine power plant at the mine site (with N+1 redundancy and diesel backup), supplemented by a 6 MW natural gas-fired facility at the marine terminal using three 2 MW reciprocating engines, eliminating reliance on diesel fuel transport and enabling a 50-year design life for the system. Workforce accommodations include modular camps at the mine site and marine terminal, initially a 250-person fabric camp expanding to 1,700 double-occupancy beds (refurbished post-construction to 850 single-occupancy rooms) for up to 2,000 personnel, with integrated dining, recreation, medical facilities, and via two Alaska Department of Environmental Conservation-approved plants. A smaller permanent at the houses up to 40 local employees. Waste rock management involves engineered stockpiles near the open (northeast and south), handling 93 million tons total (11 million preproduction, 82 million during operations), with of potentially acid-generating (PAG) material stored subaqueously in a pyritic storage facility (TSF) before backhauling to the pit during closure to prevent , while non-PAG rock supports and . comprises three facilities: Water Treatment Plant #1 (WTP#1, 3,591 gallons per minute average near the ), WTP#2 (20,646 gpm maximum near the main pond), and WTP#3 for closure phases, employing , chemical , , and to process mine-affected , seepage, and drainage, with residuals directed to the pyritic TSF or and designed to meet standards. Temporary treatment units support , emphasizing and diversion of clean runoff.

Permitting and Regulatory Pathway

The permitting pathway for the Pebble Project requires coordination among federal and state agencies to address potential impacts to waters, fisheries, and habitats under statutes including the , , and . The U.S. Army Corps of Engineers (USACE) serves as the lead federal agency, evaluating compliance with CWA Section 404, which regulates discharges of dredged or fill material into waters of the . Pebble Limited Partnership submitted its Section 404 permit application to USACE on December 22, 2017, triggering the NEPA requirement for an to analyze project alternatives, impacts, and mitigation measures through public scoping, draft and final EIS preparation, and agency review. Prior to USACE issuing a Section 404 permit, the State of must provide CWA Section 401 water quality certification via the Department of Environmental Conservation (DEC), verifying that discharges will not violate state standards for and . The Department of and Game (ADF&G) mandates separate approvals under Alaska Statute Title 16 for any alteration of or , requiring demonstrations that adverse effects can be minimized or compensated. These state permits are often coordinated through the Application for Permits to Mine in (APMA) process, administered by the Department of Natural Resources (DNR), which streamlines approvals for , water appropriation, and reclamation on state lands. Federal ESA consultations with the U.S. Fish and Wildlife Service (USFWS) are required to assess risks to listed species, such as threatened populations, ensuring project design avoids or includes adequate mitigation. Additional agency reviews, including for air quality (DEC) and navigable waters under Rivers and Harbors Act Section 10 (USACE), occur concurrently to fulfill empirical requirements for baseline data, impact modeling, and monitoring plans across the multi-year process.

Projected Timeline and Phasing

The Pebble Limited Partnership's 2017 permit application to the U.S. Army Corps of Engineers outlined Phase I as a 20-year operation processing 180,000 tons per day, designed to initiate extraction of , , and while allowing for subsequent expansions based on proven performance and additional permitting. This phased approach aimed to limit initial infrastructure footprint, with tailing storage and processing facilities scaled accordingly, prior to potential Phase II block-caving to access deeper reserves. Developer projections in the application and supporting studies anticipated federal permitting milestones, including issuance of a , within 3-4 years of submission, targeting early 2020s completion to enable state-level approvals concurrently. was scheduled to follow ROD approval, encompassing 2-3 years for site , and infrastructure buildup, and mill erection, leading to first concentrate production approximately 4 years post-permitting. Ramp-up to full capacity was projected over an additional 6-12 months, with annual production stabilizing at levels supporting economic viability per the 2023 Preliminary Economic Assessment. Subsequent phases were envisioned 20+ years into operations, contingent on reserve delineation and regulatory renewals, extending total mine life to 80 years or more through progressive pit deepening and underground methods to mitigate upfront environmental commitments. Litigation and regulatory pauses, including extensions to reviews, have empirically deferred these schedules beyond initial targets, as documented in correspondence.

Economic Projections and Benefits

Job Creation and Local Impacts

The proposed Pebble Mine project is projected to generate approximately 2,000 to 2,500 at peak during the , encompassing roles in site preparation, infrastructure development, and initial processing facilities. These estimates derive from feasibility assessments and economic modeling associated with the project's permitting process, focusing on temporary but high-intensity employment to build roads, pipelines, and the mine complex over an estimated 3-4 year period. During full operations, the mine is anticipated to sustain 750 to 1,000 direct for Alaskan residents, including miners, engineers, and support staff, with total reaching 1,500 to 2,000 when accounting for indirect and induced positions in , , and ancillary services. These figures stem from the project's 2023 Preliminary Economic Assessment () and updated projections, which incorporate regional economic multipliers estimating that each direct mining job supports 1.5 to 2 additional roles through demands in . Project developers have committed to hiring preferences for local residents and , formalized through agreements with regional Native corporations such as Iliamna Natives Limited, which facilitate access to employment via infrastructure rights-of-way connecting to villages like Iliamna and Newhalen. These arrangements prioritize recruitment from communities, where unemployment rates exceed 20% in some areas, aiming to channel a significant portion of direct jobs—potentially up to 80% in early phases based on exploration precedents—to qualified locals. To support local participation, the Pebble Partnership has outlined training and apprenticeship programs tailored for , including skill-building in operation, safety protocols, and technical trades, with staging from Native-owned facilities to integrate village residents into the . Supply chain effects are expected to extend benefits to remote villages through subcontracting for goods, transportation, and services, leveraging local coordinators to boost from regional suppliers and thereby amplifying indirect in areas with limited economic diversification.

State and National Revenue Streams

The 2023 Preliminary Economic Assessment (PEA) for the Pebble Project projects that over a 20-year operational life, the State of would generate $1.487 billion in taxes and government royalties from the mine. These figures are based on an open-pit processing 180,000 tons per day, with metal price assumptions of $3.90 per pound for , $1,700 per ounce for , and corresponding values for , silver, and . Key state revenue components include the Alaska Mining License Tax, calculated as up to 7% on from mining operations after deductions for operating costs, , and . An independent 2022 economic contribution assessment commissioned by project proponent Northern Dynasty Minerals details potential state and local breakdowns for a base-scale proposed project over 20 years of operations: $641.2 million in Alaska Mining License taxes, $283.3 million in state taxes at 3% on production value from state lands, $354.3 million in municipal taxes shared with local governments, and $9.8 million in property and other local taxes. Annual state and local taxes during steady-state operations (years 6–20) are estimated at $38.9 million, incorporating direct mine payments and induced effects from supply chains. Federally, the forecasts $1.931 billion in corporate income taxes paid to the U.S. government over the 20-year period, derived from the project's post-royalty and state-tax profits at prevailing U.S. rates. These contributions would stem primarily from after deductions, with no separate federal royalties projected given the predominance of state-owned lands at the deposit site. State analyses position such mining revenues as a means to offset fiscal pressures from declining oil production, which has historically supplied over 80% of Alaska's unrestricted general fund revenues; Pebble taxes would flow into the , supporting dividends and reducing oil dependency amid maturing North Slope fields.

Strategic Resource Contributions

The Pebble Project's resources position it as a potential contributor to addressing the U.S. supply deficit, which stood at approximately 850,000 metric tons in 2024 based on domestic mine output of 1.1 million tons against higher apparent consumption driven by and demands. , designated a critical by the U.S. Geological Survey for its indispensable role in , , and advanced , faces rising import reliance amid global supply constraints. Proponents estimate that phased development could yield annual production sufficient to meet 4-6% of U.S. needs, bolstering domestic output from one of the world's largest undeveloped deposits containing over 50 billion pounds of . This contribution would support national objectives for self-sufficiency, given that net imports currently account for over 30% of supply. Rhenium, a byproduct at Pebble expected from molybdenum processing, offers additional strategic value for high-performance alloys used in jet engines, catalysts, and military hardware. The deposit's resources, recently reassessed, could expand U.S. domestic reserves by up to 84%, with projected output reducing offshore sourcing of U.S. requirements by 25%. Although primary production occurs outside , vulnerabilities in global supply chains underscore the benefits of onshore production to mitigate risks from geopolitical disruptions. Alignment with federal policy further elevates Pebble's role, as its critical minerals qualify for production tax credits under the of 2022, which incentivizes domestic extraction and processing to secure supply chains for clean energy technologies. This framework prioritizes reducing foreign dependencies, framing such projects as essential to economic and defense resilience amid escalating global competition for strategic resources.

Independent Economic Analyses

The 2023 Preliminary Economic Assessment (PEA) for the Pebble Project, prepared by independent engineering firm under NI 43-101 standards, projects an after-tax (NPV) of US$2.0 billion at a 7% for the base case, assuming long-term metal prices of US$3.30 per pound for , US$1,750 per ounce for , and US$13.00 per pound for , with an (IRR) of 13.6%. This analysis models a 20-year initial mine life producing 158 million tonnes of at a throughput rate of approximately 22 million tonnes per year, yielding 6.5 billion pounds of , 7.4 million ounces of , and 450 million pounds of over the phase. The 7% reflects norms for polymetallic deposits with significant contributions, balancing risk across base and precious metals. Earlier independent assessments, such as the 2011 Wardrop Preliminary Assessment, similarly indicated for phased development, though with lower metal price assumptions yielding NPVs in the range of $1-2 billion at comparable discount rates. Variances arise in modeling assumptions; proponent-aligned analyses maintain baseline scenarios without probabilistic permitting delays, while some third-party reviews note that opponent models often apply discount rates exceeding 10%, which disproportionately erodes NPV for long-horizon, capital-intensive ventures by overweighting near-term uncertainties over sustained cash flows. Standard benchmarks favor 5-8% rates for projects of this scale to align with weighted average costs of capital in remote, resource-backed operations. Comparative benchmarks to operational analogs underscore viability; Alaska's , a remote zinc-lead operation initiated in , has generated over US$2.4 billion in distributions to the local Native corporation through 2023, supporting average annual direct employment of 500-600 workers and indirect economic multipliers exceeding 2.5 times direct output, despite similar logistical challenges like seasonal port access and infrastructure. Pebble's polymetallic profile and larger reserve base (estimated 57 billion pounds equivalent) position it to exceed such benchmarks under equivalent , with sensitivity analyses showing NPV resilience to 20-30% metal price fluctuations. These evaluations highlight how assumption-driven divergences—particularly in selection and phasing—can swing projected returns by billions, independent of operational execution.

Environmental and Risk Assessments

Bristol Bay Watershed Dynamics

The watershed encompasses approximately 21,000 square miles in southwestern , drained primarily by the Nushagak, Kvichak, Naknek, Egegik, and Ugashik river systems, which collectively discharge into . These rivers originate from diverse headwater sources, including alpine and lowland areas underlain by glacial till, fluvial deposits, and marine sediments up to several hundred feet thick, contributing to sustained baseflows through glacial inputs during warmer months. USGS gauge data from key sites, such as those on the Nushagak River near Dillingham, record mean annual discharges exceeding 20,000 cubic feet per second, reflecting the watershed's high volumetric output driven by and melt. Hydrological connectivity is pronounced across the , with an extensive dendritic of over 10,000 miles of and rivers linked through braided channels, , and wetlands that facilitate lateral movement and hyporheic . Groundwater-surface interactions are integral, particularly in the unconfined aquifers of glacial-fluvial gravels, where seepage from recharges shallow groundwater during high-flow periods, and vice versa during , as evidenced by tracer studies and piezometric monitoring in the Nushagak and Kvichak basins. This dynamic buffers flow variability but also influences solute and pathways. Seasonal flow patterns follow a predominantly nival , with peak discharges typically occurring from May to July due to and early glacial , averaging 2-5 times levels at USGS gauges like the Kvichak River near Iliamna. Summer low flows, often in August-September, drop to 20-50% of annual means, sustained by discharge and residual melt, while autumn rains can trigger episodic floods with return intervals of 1-10 years. These high-magnitude events drive , mobilizing fine glacial silts and gravels—estimated at 10-100 tons per square kilometer annually in upper reaches—via scour and , reshaping and depositing materials in downstream floodplains. Drought-like conditions are rare but occur during prolonged dry spells, reducing flows below the 7Q10 low-flow threshold (median 7-day low flow with 10-year recurrence) at select gauges, highlighting the watershed's reliance on consistent averaging 20-40 inches annually.

Potential Ecological Impacts

The Pebble deposit's sulfide-rich ores, including and , pose a risk of (AMD) upon exposure to oxygen and water during mining operations, potentially generating that lowers stream and leaches like , , and into aquatic environments. Geochemical characterization studies have identified sulfur contents exceeding 0.2% in waste rock and materials, a threshold associated with net acid production in kinetic tests simulating long-term exposure, which could render downstream waters uninhabitable for salmonids sensitive to below 6.0 and elevated metal concentrations. Proposed mine infrastructure, encompassing open pits, tailings storage facilities, roads, and pipelines spanning approximately 20 square miles, would directly eliminate or bury up to 94 miles of salmon-bearing and 5,350 acres of wetlands, fragmenting contiguous habitat essential for spawning, rearing, and migration in the watershed. The U.S. Environmental Protection Agency's 2014 Watershed Assessment, drawing on hydrologic modeling and empirical data from analogous mines, quantified these losses as leading to modeled reductions in productivity of 50-94% in affected sub-watersheds under various development scenarios, with fragmentation exacerbating genetic isolation and population vulnerability. Alaska's seismic activity, with the Pebble site situated in a region experiencing moderate to high ground acceleration (up to 0.4g in probabilistic hazard models), elevates the likelihood of overtopping or breach during earthquakes exceeding magnitude 6.0, potentially discharging billions of cubic meters of pyritic into streams and causing events. Historical precedents, such as the 1975 failure of the Tui Mine in following seismic activity, illustrate how such events can devastate downstream ecosystems for decades via sediment smothering and metal plumes. Permafrost thaw, projected to deepen the active layer by 0.5-1 meter per decade under regional models, could destabilize mine foundations and impoundments through differential settlement, increasing failure probabilities and enabling chronic seepage of contaminants into and surface waters. This process, observed at other northern mines like Red Dog in , amplifies risks by altering and exposing additional sulfides, with ecological models indicating compounded threats to benthic and communities reliant on stable riparian zones.

Mitigation Technologies and Strategies

The Pebble Project proposes dry-stack tailings management, whereby ore processing are dewatered through to achieve approximately 80% solids content before being mechanically stacked in contained facilities, minimizing and seepage potential compared to traditional impoundments. This approach includes sub-aerial deposition techniques to form stable, terraced stacks with engineered cover systems for and acid rock drainage prevention. Accompanying infrastructure incorporates synthetic liners, such as (HDPE) geomembranes, installed beneath waste rock dumps and tailings stacks to intercept and collect any incidental drainage, directing it to treatment systems rather than allowing infiltration into or surface waters. Water management strategies emphasize zero discharge during operations, with all contact water collected, treated via and chemical precipitation plants capable of processing up to 10 million gallons per day, and recycled back into the process. Real-time integrates automated sensors for seismic activity, piezometric pressure, and parameters across the site, feeding data into centralized systems for immediate anomaly detection and response protocols. frameworks, as outlined in project permitting documents, allow for operational adjustments based on results, such as enhanced or phased facility expansions, to address site-specific hydrological variability in the region. Industry precedents for these technologies in modern operations demonstrate low failure incidences, with global facility failure rates estimated at 1.2% over the past century for all types, and dry-stack methods exhibiting even lower risks due to their and reduced potential in seismic zones. For instance, filtered dry-stack have been successfully implemented at large-scale sites without reported catastrophic releases, supported by advancements in that achieve stack angles of 3-6% slopes and integrate collection efficiencies exceeding 95%. These strategies align with post-2014 Global Industry Standard on Management guidelines, prioritizing filtered for high-risk environments to enhance long-term stability.

Critiques of Risk Modeling

Critics of the U.S. Environmental Protection Agency's (EPA) risk modeling for the Mine, particularly in the 2014 Watershed Assessment (BBWA), argue that the methodology relies on hypothetical large-scale mining scenarios rather than the actual Pebble project proposal, which was not fully permitted at the time of the assessment. The BBWA modeled potential impacts from mining operations involving massive open pits, long tunnels, and large storage facilities, predicting catastrophic outcomes such as the destruction of up to 94 miles of and 5,350 acres of lakes from a single failure event, without specifying failure probabilities or incorporating standards. This approach has been described as speculative, as it evaluated generic "worst-case" failure modes—like full breaches releasing billions of gallons of water—absent site-specific designs or historical data on modern containment systems. Further methodological flaws include the BBWA's failure to adhere to EPA's own guidelines for risk assessments, such as weighting risks by likelihood rather than assuming deterministic worst-case chains of events, and omitting evaluations of mitigation effectiveness based on contemporary technologies like thickened or real-time seismic monitoring. Independent peer reviews identified serious deficiencies, including inadequate consideration of baseline environmental variability—such as natural fluctuations in populations due to , predation, and conditions—and overemphasis on cumulative effects without empirical validation from comparable sites. For instance, the assessment did not compare projected risks to outcomes at existing Alaskan s like , which has operated since 1998 without documented large-scale aquatic ecosystem collapse despite similar geologic challenges. Critics from organizations like the contend this omission reflects a toward predetermined outcomes, as the EPA incorporated inputs from mine opponents while sidelining proponent data. The models' underestimation of technological advancements exacerbates these issues, as post-2014 developments in —such as automated dam integrity sensors and non-cyanide leaching processes—have reduced failure rates at global sites to below 0.01% annually, contradicting the BBWA's implicit assumption of inevitable breaches. State of technical comments highlighted the conservative nature of such "reasonable maximum" scenarios, urging explicit disclosure of their low-probability basis to avoid misleading decisions. Moreover, the assessment's focus on unmitigated cumulative ignores natural , evidenced by Bristol Bay's sockeye returns varying by over 50% annually pre- proposals due to non-anthropogenic factors. These critiques, primarily from industry analysts and groups skeptical of regulatory overreach, underscore a disconnect between modeled hypotheticals and causal from operational , where engineered controls have prevented the predicted ecosystem-wide failures.

Stakeholder Positions and Debates

Arguments Supporting Development

Proponents of Pebble Mine development emphasize its potential to deliver substantial economic benefits to and the , including direct and indirect job creation exceeding 4,000 positions annually during operations. An independent assessment by IHS Global Insight projects that a conceptual Pebble Mine would support an average of 4,725 across , , and supply chains, with on-site workers earning approximately $109,500 per year on average. Over the project's estimated 90-year lifespan, annual state tax and royalty revenues could average $72 million, providing about $14,400 per year to eligible Native corporation shareholders through dividends and community funds. These economic multipliers are argued to surpass any projected declines in regional fisheries output, as mining-induced activity generates broader fiscal inflows for , , and diversification beyond seasonal harvests. Independent economic modeling, such as the analysis, highlights that Pebble's contributions to —through wages, procurement, and exports—would amplify local and national wealth, positioning the project as a counterbalance to import-dependent supply chains for critical minerals. Development is further justified by the strategic value of domestic , , and extraction, reducing U.S. reliance on foreign sources amid rising demands for and . Pebble's reserves could supply up to 7% of annual U.S. needs, enhancing and economic independence without compromising feasibility, as preliminary assessments confirm positive projected financial returns under conservative commodity price assumptions. On technical grounds, modern practices demonstrate feasibility through low historical failure rates for management, with global tailings storage facilities experiencing breaches at approximately 1.2% over the past century, mitigated further by upstream deposition, seismic-resistant designs, and real-time monitoring systems applicable to Pebble's engineered plans. Proponents cite vested property under mining laws and Alaska's selection of Pebble lands pursuant to the Alaska National Interest Lands Conservation Act (ANILCA), which explicitly accommodates responsible resource extraction on state-conveyed properties to balance conservation with economic utilization.

Arguments Opposing Development

Opponents argue that development of Pebble Mine would cause irreversible loss of in the watershed, primarily through the and diversion of essential for spawning and rearing. The U.S. Environmental Protection Agency's 2014 Watershed Assessment concluded that large-scale could directly eliminate 55 to 87 miles of streams supporting coho, sockeye, and , alongside up to 1,800 acres of wetlands, based on hydrological modeling of headwater disturbances. A 2019 analysis by applied this framework to Pebble's 2018 proposal, estimating losses exceeding EPA thresholds for adverse effects on fishery areas, including of tributaries critical to life cycles. While the EPA models generalized mining footprints rather than Pebble's engineered designs, opponents emphasize the empirical reality of stream as a causal mechanism for , given the site's location in pristine headwaters producing over 50 million sockeye annually. Financial instability in the mining sector heightens risks of abandoned liabilities, as evidenced by historical precedents where operators declared amid environmental failures. The in Canada's , closed in 1999, left 237,000 tonnes of dust requiring perpetual freezing and monitoring at costs surpassing $1 billion CAD, after the responsible firm collapsed under remediation burdens. Similarly, Brazil's 2015 Samarco dam collapse released 43 million cubic meters of toxic mud into the Doce River, killing 19 people and contaminating waters for hundreds of kilometers; the entered proceedings, prompting ongoing class-action suits seeking $64.6 billion CAD in damages from parent companies Vale and . Opponents contend these cases demonstrate systemic vulnerabilities in ore projects like , where acid-generating tailings demand indefinite treatment; a 20-year mine life could yield insufficient revenue to fund multi-decade closures if commodity prices fluctuate or operational issues arise, potentially orphaning cleanup to taxpayers. Threats to subsistence practices form a core opposition pillar, with rural in relying heavily on for cultural and nutritional sustenance. The EPA assessment documents that communities in the Nushagak and Kvichak harvest at rates supporting traditional diets, where fish comprise up to 50% of caloric intake in some villages, sustained by intact ecosystems. Native Corporation surveys and statements highlight that 2025's record 56 million sockeye return underpins this , but mine-induced declines could disrupt harvests quantified at tens of thousands of fish annually across Native households. Polling of local residents shows 80% perceive as a serious subsistence threat, reflecting empirical dependence where fish consumption exceeds national averages by factors of 10 to 20. Limitations in such data include self-reported biases in surveys, yet the causal chain from habitat loss to reduced runs aligns with observed responses to alterations elsewhere.

Fisheries and Indigenous Perspectives

Commercial fishers in , whose livelihoods depend on the world's largest fishery, have consistently opposed the Pebble Mine due to perceived risks to spawning habitats and fish populations. A 2011 survey of Bristol Bay commercial fishers found 85% opposition, with 80% strongly opposing the project on grounds that it would jeopardize the of runs essential to their operations. More recent statements from fisher organizations, such as Commercial Fishermen for Bristol Bay, reiterate this stance, emphasizing the mine's potential to disrupt the $2 billion annual economic activity supported by wild salmon harvests. Indigenous perspectives on the Pebble Mine reveal significant intra-community divisions, reflecting tensions between subsistence traditions and opportunities. The Native Corporation (BBNC), representing over 11,000 Native shareholders, has opposed the project since 2009, prioritizing the preservation of salmon-dependent ways of life; a 2019 survey of more than 4,000 BBNC shareholders showed 75% opposition, while another BBNC poll indicated 76% opposition. In contrast, Iliamna Natives Limited, serving shareholders in villages near the proposed site, has pursued agreements with the Pebble for road access to facilitate local employment, viewing development as a means to retain residents and fund community services; the group sued the EPA in 2024 over the veto, contending it deprived members of job prospects that had prompted returns to the area. Subsistence harvesting underscores these divides, as Bristol Bay villages depend heavily on salmon for nutrition and cultural practices. Annual subsistence salmon harvests total approximately 150,000 fish, with 60-80% consisting of Chinook, coho, and sockeye species; in local villages, salmon accounts for 29% to 82% of all harvested subsistence resources by volume. This reliance amplifies concerns among opposing indigenous factions about potential contamination or depletion of fish stocks, while pro-development groups argue that mine revenues could supplement food security through diversified income.

Key Permit Denials and Vetoes

On November 25, 2020, the U.S. Army Corps of Engineers (USACE) denied Pebble Limited Partnership's application for a Section 404 permit under the Clean Water Act, determining that the proposed mine would result in unacceptable adverse effects to habitat in the watershed, including the permanent loss of approximately 2,128 acres of wetlands and 11.6 miles of streams, as assessed in the project's . Prior to this denial, Pebble Partnership had adjusted its project footprint multiple times, withdrawing larger-scale proposals in favor of a smaller plan submitted in December 2017, which reduced the initial disturbance area but still encompassed significant aquatic resource impacts; concurrently, the Agency (EPA) withdrew its 2014 proposed determination under Section 404(c) on July 30, 2019, rescinding preemptive restrictions to allow the USACE permitting process to proceed based on the revised application. On January 30, 2023, the EPA issued a final determination exercising its Section 404(c) authority, prohibiting the specification of certain waters in the Deposit area for discharge of dredged or fill material due to the project's potential for unacceptable adverse effects on Bristol Bay's fishery resources, including an estimated permanent destruction of up to 94 miles of streams and 5,350 acres of wetlands and ponds under the proposed mining and tailings facilities. This veto, the 14th in history and only in over three decades, directly blocked federal permitting for mine-related discharges in the specified area, reinforcing the USACE's prior assessment of irreversible ecological harm.

Major Lawsuits and Court Rulings

Northern Dynasty Minerals Ltd., the parent company of Pebble Limited Partnership, initiated multiple lawsuits challenging the U.S. Agency's (EPA) January 30, 2023, under 404(c) of the Clean Water Act, which prohibited discharges into approximately 309 square miles of waters in the watershed to protect . In April 2024, Northern Dynasty filed suit in the U.S. District Court for the District of , alleging the was arbitrary, capricious, and exceeded statutory authority by preempting permitting processes without sufficient evidence of unavoidable harm. The company argued the EPA relied on speculative risks from undefined future mine configurations rather than site-specific data, violating precedents like Mfrs. Ass'n v. requiring reasoned decision-making. Conservation groups, including the Center for Biological Diversity, intervened to defend the , citing peer-reviewed studies on watershed degradation from large-scale mining. In March 2025, Northern Dynasty escalated with separate actions in federal district court and the U.S. Court of Federal Claims, asserting the veto constituted a regulatory taking of mineral rights without compensation under the Fifth Amendment, seeking damages for devaluation of state-leased lands designated for mining by Congress via the . The of Federal Claims filings by Pebble Limited Partnership and the State of claimed over $1 billion in losses from foregone development of the deposit, estimated to contain 57 billion pounds of , 71 million ounces of , and other metals. On July 17, 2025, Northern Dynasty moved for in the district court, contending the EPA's veto ignored congressional intent for mineral development on Mental Health Trust lands and lacked empirical basis beyond modeled scenarios critiqued for overpredicting impacts. Negotiations for settlement with the EPA under the incoming Trump administration failed by August 2025, with the case advancing toward trial in 2026 amid new EPA counsel transitions. The State of Alaska separately ed the U.S. on July 26, 2023, for to vacate the EPA , asserting it unlawfully bypassed the U.S. Army Corps of Engineers' permitting authority and encroached on state sovereignty over public lands. The invoked precedents like Sackett v. EPA (2023), which narrowed federal , to argue the veto's scope over non-navigable waters was unconstitutional. On January 8, 2024, the denied the without or , upholding the and foreclosing direct high-court review. This ruling prompted the state's shift to takings claims in the Court of Federal Claims, where it alleged the nullified vested property interests without . Earlier tribal litigation included the 2011 Alaska Superior Court decision in Nunamta Aulukestai v. State of , where plaintiffs from villages challenged the Department of Natural Resources' (DNR) issuance of exploration s to for inadequate and failure to weigh impacts under Alaska's trust doctrine. The court found DNR violated notice requirements but upheld the leases, ruling the agency had discretion absent proven arbitrariness, a decision appealed by opponents seeking . In a related 2012 case, State v. Nondalton Tribal Council, an Alaska court dismissed tribal claims against state approvals for lack of standing, limiting challenges to lease validity and marking a setback for litigants asserting concurrent water rights for fisheries. These precedents established procedural hurdles for opponents but did not resolve underlying conflicts over land use prioritization.

Political Interventions and Ballot Measures

In 2008, voters rejected Ballot Measure 4, which sought to amend the state constitution to require legislative approval by a three-fourths for large-scale metallic mines in the , a provision critics argued would impose undue barriers to development while proponents viewed it as a safeguard against environmental risks. The measure, opposed by then-Governor and mining advocates who contended it bypassed standard permitting processes, failed with approximately 54% voting against it, preserving the existing regulatory framework for potential projects like . Subsequent local and statewide ballot efforts intensified opposition. In October 2011, voters in the Lake and Peninsula Borough, encompassing part of the deposit area, narrowly approved a non-binding advisory measure (51.7% to 48.3%) urging the borough assembly to deny large-scale permits within its boundaries, signaling grassroots resistance from rural communities reliant on fisheries. This outcome faced legal challenges from Pebble proponents, who argued it infringed on property rights and state authority, though it underscored localized political pushback. By 2014, statewide Ballot Measure 4 passed with 65.8% support, mandating legislative enactment of a law affirming that any large-scale metallic in the Fisheries Reserve posed no significant risk to salmon habitats before permits could proceed, effectively raising the bar for Pebble amid concerns over watershed integrity. Federal political shifts marked contrasting interventions. Under the Obama administration, the EPA's 2014 Watershed Assessment, drawing on peer-reviewed ecological data, prompted a proposed determination under Section 404(c) to preempt discharges that could harm spawning grounds, reflecting an aggressive use of federal authority criticized by mining interests as regulatory overreach without full permitting review. The Trump administration reversed course in 2017 by settling a with Pebble , rescinding the proposed and remanding the assessment for revisions, thereby reopening the permitting pathway and prioritizing over preemptive restrictions. This pivot aligned with broader deregulation efforts but drew accusations from environmental groups of undermining science-based protections for irreplaceable fisheries. At the state level, legislative actions complemented ballot outcomes with targeted protections. In response to threats, expanded designations for anadromous waters—key spawning areas—under protection statutes, prohibiting certain disturbances in streams like those in the region, as part of broader efforts to enforce fish standards amid mining pressures. These measures, enacted through bills like those strengthening the Alaska Department of Fish and Game's oversight, aimed to preserve hydrological connectivity without outright bans, though their efficacy against large-scale operations remained contested in subsequent permitting disputes.

Current Status as of 2025

Recent Regulatory Actions

In April 2024, the U.S. Army Corps of Engineers finalized its review of the Pebble Limited Partnership's appeal and reaffirmed the November 2020 denial of a key Section 404 permit for the proposed mine, citing the EPA's veto as rendering the project infeasible under federal regulations. The EPA's January 2023 Section 404(c) , which prohibits discharge of dredged or fill material into waters associated with the deposit due to anticipated adverse effects on Bristol Bay's , remained in effect through 2025, with no revocation or modification issued. In July 2025, the U.S. Department of Justice, representing the administration, confirmed its intent to defend both the Army Corps' permit denial and the EPA in ongoing federal litigation, despite earlier indications of potential settlement discussions that ultimately failed to materialize. State-level regulatory efforts faced parallel challenges, as Alaska's March 2024 lawsuit against the EPA —arguing it unlawfully encroaches on state-owned lands designated for mineral development under the —proceeded without resolution by October 2025, while no new state leases or approvals advanced amid the . In October 2025, plaintiffs including proponents filed joint motions in U.S. District Court, contending the exceeds EPA authority and violates commitments to Alaska's resource access, but regulatory agencies maintained their positions pending judicial outcome.

Ongoing Litigation and Funding

As of October 2025, Northern Dynasty Minerals Ltd., the parent company of Pebble Limited Partnership, continues to pursue federal litigation challenging the U.S. Environmental Protection Agency's (EPA) 2023 veto of the Pebble Project under Section 404(c) of the Clean Water Act, which prohibited discharges into specified waters of the Bristol Bay watershed. On October 3, 2025, plaintiffs including Northern Dynasty, the State of Alaska, Iliamna Natives Ltd., and Alaska Peninsula Corporation filed summary judgment briefs in the U.S. District Court for the District of Alaska, arguing that the EPA exceeded its statutory authority by issuing the veto without sufficient evidence of unacceptable adverse effects and without following proper procedures. These filings mark the first joint request for a court ruling on the veto's legality, following failed settlement discussions with the EPA earlier in 2025, where no agreement was reached despite indications of potential reconsideration under the Trump administration. A parallel lawsuit against the U.S. Army Corps of Engineers (USACE) remains active in the same , stemming from the agency's 2024 denial of the required [Clean Water Act](/page/Clean Water Act) Section 404 permit after reconsideration of its initial 2020 approval. Filed by Northern Dynasty in March 2024, the suit contends that the USACE's denial was arbitrary and capricious, influenced by external pressures rather than environmental assessments. The inclusion of the USACE in these proceedings underscores ongoing disputes over permitting processes, with court dates set but no resolution by mid-2025. To sustain operations amid litigation, Northern Dynasty completed a royalty investment agreement in October 2025, receiving the fifth and final $12 million tranche on October 20 from an undisclosed investor, bringing total payments to $60 million across five installments. This funding, structured as net smelter return royalties on future Pebble production, enhances liquidity through at least 2027 and supports legal efforts without diluting equity. The tranches were advanced ahead of deadlines, with the final payment preceding the December 31, 2025, cutoff.

Future Prospects and Uncertainties

The viability of the Pebble Project hinges on the outcome of ongoing federal litigation challenging the U.S. Environmental Protection Agency's (EPA) 2023 veto under Section 404(c) of the Clean Water Act, which prohibits discharges into Bristol Bay watershed waters; as of July 2025, the Trump administration's EPA has reaffirmed the veto and declined settlement, though Northern Dynasty Minerals Ltd. filed summary judgment briefs on October 6, 2025, arguing the veto is illegal and should be withdrawn. Seismic hazards in , including proximity to active faults like the Castle Mountain fault capable of magnitude 7+ earthquakes, pose risks of failure or infrastructure collapse, as evidenced by analyses showing inadequate seismic modeling in project assessments; compounded by climate-driven thaw and increased precipitation, these factors could elevate operational costs and failure probabilities, precedents from events like the underscoring vulnerabilities in similar terrains. Proponents have floated smaller-scale alternatives, such as the 2017 plan for a 20-year surface producing 320 million pounds of annually without underground expansion, potentially bypassing some regulatory hurdles; however, global demand—projected to rise with electrification needs, where Pebble's resources could supply significant U.S. portions—creates economic incentives, though independent analyses question overall financial feasibility amid permitting delays and capital requirements exceeding $5 billion.

References

  1. [1]
    Pebble Project - Project Overview - Northern Dynasty Minerals Ltd.
    The Pebble Project is located in southwest Alaska. Northern Dynasty is 100% owner of the Pebble Partnership, which is advancing the world-class Pebble deposit ...
  2. [2]
    History and Location | Northern Dynasty Minerals Ltd.
    The Pebble Project is located approximately 200 miles southwest of Anchorage in the Bristol Bay region. The deposit lies entirely within the Lake and Peninsula ...
  3. [3]
    Project Overview - The Pebble Partnership
    Pebble Limited Partnership (PLP) is proposing to develop the Pebble copper-gold-molybdenum porphyry deposit (Pebble Deposit) in southwest Alaska as an open-pit ...
  4. [4]
    Final Determination for Pebble Deposit Area | US EPA
    Jan 30, 2023 · EPA determined that certain discharges associated with developing the Pebble deposit would have unacceptable adverse effects on certain salmon fishery areas.
  5. [5]
    News Releases - Northern Dynasty Minerals Ltd.
    Oct 6, 2025 · EPA has made it impossible to mine the deposit even though Congress specified that the state lands in which Pebble is located should be ...
  6. [6]
    Pebble back in court over EPA veto - North of 60 Mining News
    Oct 6, 2025 · The summary judgment filing marks the first time all plaintiffs have jointly sought a court ruling on the legality of the EPA's Pebble veto, ...
  7. [7]
    Pebble Project – Alaska Division of Mining, Land, and Water
    The project is located on state land in the Bristol Bay Region of southwest Alaska, approximately 17 miles northwest of the community of Iliamna. The ...
  8. [8]
    Locality Maps - Pebble Copper prospect, Bristol Bay Mining ... - Mindat
    Locality Maps - Pebble Copper prospect, Bristol Bay Mining District, Lake and Peninsula Borough, Alaska, USA ; 59° 53' 49'' North , 155° 17' 41'' West.Missing: exact geography
  9. [9]
    FAQ - Pebble Watch
    Where is the Pebble deposit located? The mineral deposit is located in the Bristol Bay region in Southwest Alaska, near Iliamna Lake and Lake Clark.
  10. [10]
    Pebble Mine (Copper/Gold Prospect) | Ground Truth Alaska
    Location. The Pebble prospect is located in an area of wet tundra surrounded by low mountains approximately 16 miles west of the village of Nondalton.Missing: distance | Show results with:distance
  11. [11]
    [PDF] Pebble Deposit Area, Southwest Alaska
    Jan 2, 2023 · ... located at the headwaters of the pristine Bristol Bay watershed. The Pebble deposit underlies portions of the South Fork Koktuli River (SFK) ...
  12. [12]
    Koktuli River | Dave Fish Alaska River Guides
    The Koktuli River is a headwater of the Nushagak, known for salmon and rainbow/grayling. It winds 50 miles from tundra to forested lowlands.<|separator|>
  13. [13]
    [PDF] ENVIRONMENTAL, SOCIAL AND GOVERNANCE REPORT
    Apr 26, 2021 · The proposed Pebble site is located in southwest Alaska, approximately 65 miles from tidewater on Cook. Inlet, 19 miles northwest of the Alaska ...
  14. [14]
    [PDF] ANNUAL REPORT 2023 - Alaska Climate Research Center
    Jan 5, 2024 · Bristol Bay region, which had around 95% of normal annual precipitation. ... Due to the special geology of the region, seismic waves get.
  15. [15]
    [PDF] Permafrost and Ground Water in Alaska
    BRISTOL BAY REGION. By E. H. MULLEE. PHYSIOGRAPHY, CLIMATE, AND VEGETATION. The Bristol Bay region lies principally in the zone of sporadic permafrost but ...Missing: seismic | Show results with:seismic
  16. [16]
    Geology and Exploration | Northern Dynasty Minerals Ltd.
    Pebble Deposit​​ This type of deposit is referred to as a porphyry copper with associated gold, molybdenum and silver. More than 800,000 feet of the more than 1 ...Missing: Alaska | Show results with:Alaska
  17. [17]
    [PDF] Chapter 3: Geology and Mineralization (Bristol Bay Drainages)
    May 9, 2011 · Localization of the Pebble Deposit was controlled by fault structures and alteration. The principal regional control is the northeast ...
  18. [18]
    [PDF] 2025 Bristol Bay Salmon Season Summary - Advisory Announcement
    Sep 24, 2025 · The 2025 inshore Bristol Bay sockeye salmon run of 56.7 million fish (Table 1) was the 7th largest inshore run since 2005 and was 16% above the ...
  19. [19]
    [PDF] 2025 Bristol Bay Sockeye Salmon Forecast - Advisory Announcement
    Nov 7, 2024 · The sockeye salmon total run forecast for Bristol Bay in 2025 is predicted to be strong with a point estimate of 51.38 million fish and a ...
  20. [20]
    [PDF] 2020 BBRSDA Processor Survey - Squarespace
    The 2020 Bristol Bay sockeye run, the fifth largest on record, was 45 percent above the average run over the last 20 years and 25 percent above the Alaska ...<|separator|>
  21. [21]
    Bristol Bay Salmon, Alaska Department of Fish and Game
    Inseason Information · Harvest · Commercial Operator's Annual Report (COAR) Data · Management · Regulations · Forecasts · Maps · Bristol Bay Salmon Escapement.Salmon Escapement · Daily Run Summary · Inseason Harvest Summary
  22. [22]
    Geomorphology controls the trophic base of stream food webs in a ...
    Jul 1, 2015 · We sampled 16 streams within the Wood River basin in the Bristol Bay region of Alaska (59°20′ N, 158°40′ W), which has a total drainage area of ...
  23. [23]
    Association between geomorphic attributes of watersheds, water ...
    Mar 1, 2013 · Here, we examine the association between geomorphic attributes of streams and their watersheds, stream water temperature, and the seasonal spawn ...
  24. [24]
    Relationships between Pacific salmon and aquatic and terrestrial ...
    Apr 8, 2020 · We found 31 studies that provided 172 relationships between salmon density (or salmon abundance) and species abundance, species diversity, food ...
  25. [25]
    Examining Soil's Role in Tracing Nutrients From Salmon into ...
    Scientists from USGS and the University of Washington used a 20-year salmon manipulation experiment in Bristol Bay, Alaska to evaluate how marine nitrogen ...
  26. [26]
    [PDF] Alaska Salmon Research 2005 - Scholarly Publishing Services
    Bristol Bay has the greatest abundance and diversity of sockeye salmon in the world. The Wood River system is home to dozens of genetically and ecologically ...
  27. [27]
    Iliamna (Lake and Peninsula, Alaska, USA) - City Population
    Iliamna. 108 Population [2020] – Census. 96.39 km² Area. 1.120/km² Population Density [2020]. -0.090% Annual Population Change [2010 → 2020]. Map Chart Weather ...
  28. [28]
    Iliamna, AK Demographics - Map of Population by Race - Census Dots
    Iliamna, Alaska had a population of 108 in 2020. It was 23.1% White, 0.0% Black, 0.9% Asian, 0.9% Hispanic, 59.3% Native American/Other, and 15.7% Multiracial.Missing: US | Show results with:US
  29. [29]
    Newhalen, AK Demographics - Map of Population by Race
    Newhalen, Alaska had a population of 168 in 2020. It was 9.5% White, 0.0% Black, 0.0% Asian, 1.2% Hispanic, 75.6% Native American/Other, and 13.7% Multiracial. ...Missing: US | Show results with:US
  30. [30]
    Nondalton Demographics | Current Alaska Census Data
    With 116 people, Nondalton is the 225th most populated city in the state of Alaska out of 332 cities according to the most current US Census data. But watch out ...
  31. [31]
    Nondalton, Alaska Population 2025
    Nondalton has a 2025 population of 110. Nondalton is currently declining at a rate of -3.51% annually and its population has decreased by -14.73% since the most ...
  32. [32]
    [PDF] Technical Paper No. 302 - Alaska Department of Fish and Game
    Subsistence harvests and uses of wild resources in. Iliamna, Newhalen, Nondalton, Pedro Bay, and Port Alsworth, Alaska, 2004. ... Iliamna, Newhalen, Nondalton, ...
  33. [33]
    Technical Paper No. 352 - The Kvichak Watershed Subsistence ...
    Oct 15, 2007 · Figure 4.–Estimated subsistence harvests of sockeye salmon, Iliamna/Newhalen, Nondalton, and Port. Alsworth, by decade, 1963–2006. With this ...
  34. [34]
    ILIAMNA: General - Alaska Aviation System Plan
    Airport Reference Point (ARP):, 59.755578° N,154.917753° W ; Last scored APEB: 2/23/2023 ; Seasonal Closures: None ; Road Access: None ; ALP Approved: 2/5/2014.
  35. [35]
    [PDF] Chapter 19: Transportation (Bristol Bay Drainages)
    A restricted-access spur road about 10 miles north of Iliamna provides access to the. Tazimina Hydroelectric Project. For many years, the State of Alaska has ...
  36. [36]
    [PDF] 2014 TECHNICAL REPORT ON THE PEBBLE PROJECT ...
    Dec 31, 2014 · Location of the Pebble Deposit and Regional Geological Setting of Southwest Alaska ... The Pebble deposit is located primarily within the Lake and ...
  37. [37]
    [PDF] Pebble Project NI 43-101 Technical Report Update
    Aug 21, 2023 · This certificate applies to the technical report titled “Pebble Project, NI 43-101 Technical Report Update Preliminary. Economic Assessment, ...
  38. [38]
    Reserves and Resources - Northern Dynasty Minerals Ltd.
    The mineral resource estimate is constrained by a conceptual pit shell that was developed using a Lerchs-Grossmann algorithm and is based in the following ...Missing: NI 43-101
  39. [39]
    Copper - Price - Chart - Historical Data - News - Trading Economics
    Copper rose to 5.09 USD/Lbs on October 24, 2025, up 0.29% from the previous day. Over the past month, Copper's price has risen 7.74%, and is up 17.33% compared ...
  40. [40]
    Gold - Price - Chart - Historical Data - News - Trading Economics
    Gold fell to 4111.89 USD/t.oz on October 24, 2025, down 0.34% from the previous day. Over the past month, Gold's price has risen 9.66%, and is up 49.65% ...
  41. [41]
    Molybdenum Price (USD / Pound) for the Last Day - Daily Metal Price
    Molybdenum Prices for the Last Day. Molybdenum (lb), Date. $32.319, Oct 24, 2025. Molybdenum Price (USD / Pound). Link directly to this result here: http://www ...
  42. [42]
    positive projected financial results, excellent optionality and ...
    Sep 5, 2023 · The 2023 PEA is a preliminary analysis of the potential viability of the Pebble Project's mineral resources, and should not be considered the ...
  43. [43]
    Pebble: Origins of the enduring controversy - North of 60 Mining News
    Nov 2, 2023 · Explore the beginnings of the Pebble Mine, Alaska's statehood, resource rights, and the battle for environmental preservation.
  44. [44]
    Anglo American statement re: Pebble project
    Sep 16, 2013 · The Pebble Limited Partnership (PLP) was created in 2007 between AA Pebble and an affiliate of Northern Dynasty Minerals Ltd.
  45. [45]
    News Releases - Pebble Project - Northern Dynasty Minerals Ltd.
    Dec 13, 2013 · Northern Dynasty has now re-acquired 100% ownership and control of the Pebble Partnership. All Anglo American representatives have resigned.
  46. [46]
    Rio Tinto Gives Away Stake in Gold Mine - 24/7 Wall St.
    Apr 8, 2014 · The company announced that decision Monday: it is giving away its 19% stake for which it paid about $25 million. Two of Rio's large ...
  47. [47]
    Rio Tinto grants Northern Dynasty shares to Alaska-based ...
    Apr 7, 2014 · Rio Tinto has advised management that it intends to divest of its 19.1% shareholding in Northern Dynasty by way of gifting its shares to two Alaskan charitable ...Missing: rounds | Show results with:rounds
  48. [48]
    Rio Tinto divests stake in controversial Pebble mine
    Apr 8, 2014 · Rio Tinto is divesting its stake in the Pebble mine prospect in south-west Alaska by donating its shares to two Alaskan charitable foundations.Missing: funding | Show results with:funding
  49. [49]
    What to watch for in 2025 - Pebble Watch
    Dec 5, 2024 · Since 2022, the Pebble project has been funded mainly through a royalty agreement that offers future gold and silver production profits to a ...
  50. [50]
  51. [51]
    Fourth Tranche of $12 million Royalty Investment Received, Update ...
    Sep 25, 2025 · Withdrawal of the illegal veto will be a step towards developing this very large new source of copper and rhenium, as well as significant ...
  52. [52]
    News Releases - Pebble Project - Northern Dynasty Minerals Ltd.
    Feb 23, 2011 · If a feasibility study for the project is completed after 2011, Anglo American's overall funding requirement increases from $1.425 billion to ...
  53. [53]
    [PDF] Northern Dynasty Minerals - Kerrisdale Capital
    Feb 1, 2017 · Our focus has been to prioritise capital to projects with the highest value and lowest risks within our portfolio, and reduce the capital.
  54. [54]
    [PDF] draft environmental baseline studies 2004 progress reports chapter ...
    This chapter presents the findings of the hydrogeology study carried out in 2004 for the Pebble Project. ... In order to support groundwater studies at the mine ...
  55. [55]
    [PDF] Pebble Project Environmental Baseline Document 2004 through 2008
    This environmental baseline document (EBD) describes studies conducted in Southwest Alaska between. 2004 and 2008 on behalf of the Pebble Partnership and its.
  56. [56]
    [PDF] Pebble Project Environmental Baseline Studies 2004 through 2008 ...
    Sep 7, 2011 · Page 1. Pebble Project. Environmental Baseline Studies. 2004 through ... Terrestrial and marine wildlife studies. – Caribou Use of Pebble Mine ...
  57. [57]
    [PDF] February 15th, 2011 Issue Date - Pebble Watch
    ... studies toward the completion of a Prefeasibility Study for the Pebble ... mine development within the 'Exploration Lands' portion of the Pebble property only.
  58. [58]
    Northern Dynasty Minerals Ltd.: Exhibit 99.1 - SEC.gov
    Feb 23, 2011 · The Pebble Partnership continues to separately undertake detailed engineering studies toward the completion of a Prefeasibility Report for the ...
  59. [59]
    [PDF] Pebble Project Preliminary Economic Assessment NI 43-101 ...
    Oct 1, 2022 · The Pebble deposit is located in southwest Alaska, approximately 200 miles (mi) southwest of Anchorage, 17 mi northwest of the village of ...
  60. [60]
    [PDF] Proposed Determination of the US Environmental Protection Agency ...
    Jul 17, 2014 · NDM has stated to the public that “the Pebble deposit supports open pit mining utilizing conventional drill, blast and truck‐haul methods, with ...
  61. [61]
    [PDF] The Pebble Project - Wild Salmon Center
    In 1988, Cominco America Inc. began investigat- ing a low-grade copper-gold-molybdenum ore body on. Alaska state land in a region within the Bristol Bay basin.
  62. [62]
    Pebble Project, Alaska - Mining Technology
    Jan 2, 2014 · Pebble is a copper-gold-molybdenum porphyry deposit with the ore body extending up to 1,700m deep from the surface. The deposit is located in ...Missing: characteristics | Show results with:characteristics
  63. [63]
    [PDF] PEBBLE MINE SITE OPERATIONS WATER MANAGEMENT PLAN
    Jul 6, 2018 · The Bulk Tailings Storage Facility. (Bulk TSF) will manage non potentially acid generating tailings (bulk tailings), and the Pyritic Tailings.
  64. [64]
    [PDF] Pebble Project Description - Regulations.gov
    May 8, 2020 · • A natural gas pipeline and gas-fired electrical generation are being used to power the. Project, thereby eliminating the need to transport ...Missing: airstrip | Show results with:airstrip
  65. [65]
    [PDF] Permitting Processes for the Pebble Project - Alaska State Legislature
    Feb 21, 2018 · PEBBLE: SITE HISTORY. • Baseline Environmental Studies. – 2004 – 2008 baseline studies by PLP. • available on DNR website. (http://dnr.alaska ...
  66. [66]
    U.S. Army Corps of Engineers Announces Pebble Mine Permit ...
    Apr 25, 2023 · On January 30, 2023, the EPA issued its Final Determination under section 404(c) of the Clean Water Act, limiting the use of certain waters in ...
  67. [67]
    US Army Corps of Engineers confirms Pebble permit application ...
    ... 404 permitting documentation it submitted on December 22, 2017 has been accepted. ... To initiate the NEPA EIS permitting process, the Pebble ...
  68. [68]
    USACE Extends Pebble Mine EIS Scoping Period through June 29
    Apr 17, 2018 · In December 2017, Pebble submitted its first Clean Water Act 404 permit application to the U.S. Army Corps of Engineers which triggered the ...
  69. [69]
    Mining Apply for a Permit - Alaska Department of Fish and Game
    The APMA is an application form for the permits required to explore for and mine locatable minerals and to conduct reclamation.
  70. [70]
    Application for Permits to Mine in Alaska (APMA)
    The APMA is an application form for the permits required to explore for and mine locatable minerals and to conduct reclamation.
  71. [71]
    Pebble to initiate federal and state permitting on December 22, 2017
    Dec 21, 2017 · Under the development scenario the Pebble Partnership will submit for federal and state permitting on December 22, 2017: The footprint of ...Missing: timeline | Show results with:timeline
  72. [72]
  73. [73]
    [PDF] Alaska's Pebble Project approaches key permitting milestone as
    May 14, 2020 · These include: Northern. Dynasty's 100%-owned Pebble Project, expected to receive a Final Environmental Impact Statement (EIS) and Record of ...
  74. [74]
    Independent Preliminary Economic Assessment for Northern ...
    Sep 5, 2023 · "The proposed mine for the Pebble Project would provide good-paying, year-round employment for thousands of Alaskans, something desperately ...
  75. [75]
    Corps extends comment period for Pebble draft EIS
    May 3, 2019 · The extension brings the length of the public comment period to 120-days. During April, the Corps conducted nine public hearings in Alaska to ...Missing: timeline milestones
  76. [76]
    [PDF] ti-committee-pebble-mine-report-and-appendix-1.pdf - Turtle Talk
    Beginning in 2007, Pebble Limited Partnership (Pebble LP) pursued efforts to develop an open pit mine for copper and other minerals on state-owned land near ...
  77. [77]
    Pebble Mine 2025: Unveiling Alaska's Environmental Dilemma
    Oct 3, 2025 · Located in southwestern Alaska's Bristol Bay region, this massive undeveloped mineral resource has been the subject of ongoing debates for ...
  78. [78]
    [PDF] A FUTURE WITH PEBBLE
    Sep 16, 2025 · Within these categories, we anticipate that the project will generate 750 to 1,000 direct jobs for Alaskans and 1,500 to 2,000 jobs overall.Missing: projections | Show results with:projections
  79. [79]
    Pebble Alaska: Major Copper-Gold-Molybdenum-Silver Project
    Jul 11, 2025 · Mineral Resource Estimates · Copper with an average grade of 0.41% · Gold at 0.34 grams per tonne · Molybdenum at economically significant ...
  80. [80]
    [PDF] THE PEBBLE PROJECT - Northern Dynasty Minerals Ltd.
    Oct 6, 2025 · Given the polymetallic nature of the Pebble deposit and the large contributions of gold to total project revenues, a ... • Tailings management ...
  81. [81]
    Pebble Partnership, Iliamna Natives Limited Reach Right-Of-Way ...
    May 15, 2019 · Roads connecting to the villages of Iliamna and Newhalen will allow local residents to access jobs at the Pebble mine site and associated ...Missing: hiring | Show results with:hiring
  82. [82]
    [PDF] Local Jobs and Income from Mineral Exploration
    Most residents of these communities are Alaska Native, and the communities are small—most with populations considerably smaller than 500— except for Dillingham ...Missing: demographics | Show results with:demographics
  83. [83]
    Pebble Partnership completes summer work program at Southwest ...
    Oct 4, 2021 · The 2021 field program was staged out of facilities owned by Alaska Native village corporations in Iliamna, Alaska (most of whom are contracted/ ...Missing: hiring | Show results with:hiring
  84. [84]
    [PDF] Mining Tax Overview - Alaska State Legislature
    The Mining License Tax is an income tax (tax is calculated on net income from the mining property). • Net income is gross income from mining operations less.
  85. [85]
  86. [86]
    Economic Contribution Assessment study for Alaska's Pebble ...
    Feb 28, 2022 · The Pebble Project could help the U.S. reduce its dependence on imports of copper metal as demand surges during the transition from an oil-based ...
  87. [87]
    [PDF] An Introduction to the Economy of Alaska
    The State of Alaska is extremely dependent on oil revenues, mostly from oil ... A major new potential mining project in Alaska is the proposed Pebble mine, which ...
  88. [88]
    [PDF] COPPER - USGS.gov
    Domestic Production and Use: In 2024, the recoverable copper content of U.S. mine production was an estimated 1.1 million tons, a decrease of 3% from that in ...
  89. [89]
    Copper Statistics and Information | U.S. Geological Survey - USGS.gov
    Statistics and information on the worldwide supply of, demand for, and flow of the mineral commodity copper
  90. [90]
    Rhenium discovery adds fresh intrigue to Alaska Pebble mine decision
    Aug 21, 2020 · Rhenium is a strategic metal with military applications, and Pebble mine owner says new find could increase US domestic reserves by 84%.Missing: reserves dependency
  91. [91]
    News Releases - Northern Dynasty Minerals Ltd.
    Oct 7, 2020 · This level of production could also reduce the percentage of US rhenium requirements sourced from offshore producers by 25% over 2019 levels.
  92. [92]
    Pebble Mine Could Reduce Dependence on China for Critical Metals
    Oct 22, 2020 · The Pebble Mine could be a valuable source of critical metals, which are needed for the construction of numerous technologies.
  93. [93]
  94. [94]
    [PDF] THE PEBBLE PROJECT - Northern Dynasty Minerals Ltd.
    Jan 15, 2024 · The Pebble Project is the world's largest undeveloped copper/gold deposit, a US-based resource with potential to help secure America's green ...
  95. [95]
    [PDF] Review of the Pebble Mine Project Preliminary Economic Assessment
    Dec 1, 2021 · The overall Net Present Value (NPV) of the 20-year starter-mine is almost certain to be less than. $700 million in value, which is less than a ...
  96. [96]
    Independent Review Rejects Pebble Mine Economic Analysis - NRDC
    Dec 7, 2021 · Citing major flaws in Pebble Mine's Preliminary Economic Assessment, Rio Tinto's former Environment Chief concludes destructive Bristol Bay ...<|separator|>
  97. [97]
    Preliminary Economic Assessment for Alaska's Pebble Project ...
    Sep 9, 2021 · At forecast long-term2 metal prices, Internal Rate of Return (“IRR”) of 15.8% and Net Present Value at 7% discount rate (“NPV7”) of $2.3 billion ...Missing: critiques opponent
  98. [98]
    [PDF] The Economic Potential of Alaska's Mining Industry
    Oct 4, 2023 · Including indirect employment, the mineral industry could be responsible for almost 17,000 jobs in the favorable scenario.
  99. [99]
    PEA reveals Pebble economics, benefits - North of 60 Mining News
    Sep 9, 2021 · At today's metal prices, the IRR for this operation would be 23.8%, and the NPV would more than double to US$4.8 billion. This operation is ...<|separator|>
  100. [100]
    [PDF] water resources near dillingham in the bristol bay area, alaska
    The area is underlain by a complex sequence of primarily fine-grained glacial, fluvial, and marine sediments that are several hundred feet thick. SURFACE WATER ...
  101. [101]
    Water resources near Dillingham in the Bristol Bay Area, Alaska
    Dillingham, the largest community in the Bristol Bay area of Alaska, lies near the confluence of the Wood and Nushagak Rivers.Falta(n): glacial feeds
  102. [102]
    [PDF] Investigations of Surface Water Quality in the Nushagak, Kvichak ...
    (Kvichak watershed) and the Koktuli River (Nushagak watershed), which form the headwaters of two of the five anadramous rivers feeding into Bristol Bay.
  103. [103]
    [PDF] Overview of Environmental and Hydrogeologic Conditions at ...
    HYDROLOGY. The hydrology of the Dillingham area is strongly influenced by the maritime conditions of. Bristol Bay. Streams in the area drain a broad lowland ...
  104. [104]
    [PDF] %STIMATING AND 3TREAMS - USGS Publications Warehouse
    Methods for estimating daily mean flow- duration statistics for seven regions in Alaska and low-flow frequencies for one region, southeastern.
  105. [105]
    [PDF] 7. SURFACE WATER HYDROLOGY - 7.1 Regional Study Area
    The hydrological studies were designed to gather a general understanding of the regional hydrology for the Bristol Bay drainage basin along with more detailed ...
  106. [106]
  107. [107]
    [PDF] Geochemical Characterization - Pebble Science
    The main objective of the geochemical characterization studies is to assess the potential for acid rock drainage (ARD) and the related phenomenon of metal ...
  108. [108]
    Acid Rock Drainage and Metal Leaching at the Proposed Pebble Mine
    As little as 0.2 percent sulfide in rocks may trigger acid drainage, depending on site conditions. Lab tests estimate how much acid will be made and neutralized ...
  109. [109]
  110. [110]
    [PDF] An Assessment of Potential Mining Impacts on Salmon ... - EPA
    This assessment reviews, analyzes, and synthesizes information relevant to potential impacts of large-scale mine development on Bristol Bay fisheries and.Missing: fragmentation | Show results with:fragmentation
  111. [111]
    [PDF] An assessment of potential mining impacts on salmon ecosystems of ...
    Preferred citation: USEPA (U.S. Environmental Protection Agency). 2014. An Assessment of Potential. Mining Impacts on Salmon Ecosystems of Bristol Bay, Alaska.
  112. [112]
    Hydrologic and Water Quality Modeling of the Pebble Mine Project ...
    The Environmental Impact Statement (EIS) proposes a 20-year open-pit extraction, sulfide flotation, and deposition of separated pyritic tailings and potentially ...
  113. [113]
    Earthquake Risk at Pebble | Ground Truth Alaska
    The most serious earthquake-related dangers at Pebble Mine would be a major collapse in the pit or underground mine and a dam breach at the giant tailings ...
  114. [114]
    [PDF] The Costs of Climate Change on the Pebble Mine - Cook Inletkeeper
    USACE predicts that the mine would generate millions of dollars in state and local taxes during construction and operational phases. Total tax revenue ...
  115. [115]
    [PDF] memorandum-pebble-mine-20210503.pdf - NRDC
    May 3, 2021 · this task, the mine would have two water treatment plants (“WTP”) during operations ... 376 Earthworks, Pebble Mine: Unprecedented Waste Water ...
  116. [116]
    Pebble Tailings Storage Facility designed to protect the fishery
    Sep 19, 2022 · The tailings storage and management plan for Pebble includes an investment of approximately $500 million in modern water treatment facilities.Missing: technologies dry- stack synthetic
  117. [117]
    [PDF] EPA Comments to U.S. Army Corps of Engineers on Draft EIS for ...
    Jul 1, 2019 · To ensure disclosure of practicable means to mitigate the direct, indirect, and cumulative impacts of the Pebble Project, the EPA recommends the ...
  118. [118]
    A Comprehensive Review on Reasons for Tailings Dam Failures ...
    Jun 20, 2019 · In the reported 18,000 mines around the world, the failure rate in the past 100 years is estimated at 1.2%. The failure rate of the traditional ...
  119. [119]
    Dry Stacking of Filtered Tailings for Large-Scale Production Rates ...
    Nov 16, 2023 · This article presents a new paradigm in managing mine tailings, with disruptive and futuristic characteristics, considering the dry stacking of filtered mine ...1.1. Mine Tailings... · 2. Dewatering Process Plant... · 6. Smart Mining Technologies...
  120. [120]
    CEI Challenges Federal Rejection of Alaska's Pebble Mine
    Nov 15, 2018 · Because the EPA had no specific mine application to review, it simply made up several hypothetical mine scenarios and rejected them all.Missing: criticism | Show results with:criticism
  121. [121]
  122. [122]
    CEI Again Asks EPA to Withdraw or Correct Bristol Bay Watershed ...
    Aug 29, 2019 · Although the Proposed Determination has been withdrawn, the flawed BBWA still represents EPA's position on the Pebble Mine and is still being ...Missing: criticism | Show results with:criticism
  123. [123]
    Senators: EPA Moving Forward on Preemptive Veto of Pebble Mine ...
    Jun 11, 2013 · ... faulty analyses. Yet the Assessment in its current form remains flawed, as it relies on six biased reports authored by Pebble Mine opponents.<|separator|>
  124. [124]
    [PDF] State of Alaska Technical Comments
    ... Pebble proponents in 2011. The Assessment relies heavily on concepts developed by Northern Dynasty who are party to the Pebble Limited Partnership but do ...
  125. [125]
    The EPA's Pebble Mine Assessment Puts Politics Above Sound ...
    Jan 1, 2013 · The EPA's draft assessment is too flawed a document to be allowed to pass judgment on a project as important as the Pebble Mine. By ...
  126. [126]
    [PDF] The Economic and Employment Contributions of a Conceptual ...
    IHS Global Insight offers an independent assessment of the potential contribution of a “conceptual”. Pebble Mine to Alaska and the Lower 48 economies. This ...
  127. [127]
    Study finds Pebble Project's impact could be huge
    Jun 1, 2013 · The report found that the potential economic impact could include an estimated $136 to $180 million in annual taxes and royalties.Missing: fiscal | Show results with:fiscal
  128. [128]
    Economic Benefits | Northern Dynasty Minerals Ltd.
    The project would create jobs, contribute almost $2 billion in taxes, provide dividends to residents, and reduce US reliance on copper imports.
  129. [129]
    [PDF] Alaska Industrial Development and Export Authority - Supreme Court
    Sep 25, 2023 · Because Alaska validly selected the Pebble land here and obtained the rights over mineral deposits on that land, the federal government cannot ...
  130. [130]
    The Pebble Mine: US EPA Bristol Bay Watershed Assessment Key ...
    May 24, 2012 · The direct loss of 55– 87 miles of streams used for spawning and rearing habitat for coho salmon, sockeye salmon, and Chinook salmon.
  131. [131]
    [PDF] Direct loss of salmon streams, tributaries, and wetlands under the ...
    Jun 1, 2019 · SUMMARY: This study compares the loss of salmon streams, tributaries and wetlands under the 2018 proposed Pebble Mine to thresholds ...Missing: burial | Show results with:burial
  132. [132]
    EPA's Bristol Bay Assessment | US EPA
    Apr 4, 2025 · EPA's assessment found that mining the headwaters of these river systems could cause harm to the valuable fishery in Bristol Bay.
  133. [133]
    Environmental Disaster of Giant Mine in Yellowknife - Facebook
    Mar 29, 2025 · CASE STUDY: The Giant Mine in Canada left behind 237,000 tonnes of arsenic trioxide that must be frozen in place FOREVER at a cost of over $1 ...
  134. [134]
    Victims in Brazil's worst environmental disaster take mining giant ...
    Oct 21, 2024 · The class-action lawsuit at the High Court in London seeks an estimated 36 billion pounds ($64.6 billion Cdn) in damages from the global mining giant BHP.
  135. [135]
    In the Pan Amazon, environmental liabilities of old mining have ...
    Jun 5, 2024 · The 'legacy' of older mines translates into environmental liabilities, as failures can cause leakages of toxic sludge or fuel into river systems.Missing: international | Show results with:international
  136. [136]
    Pebble Mine - Bristol Bay Native Corporation
    Since 2009, Bristol Bay Native Corporation has opposed the proposed Pebble mine near the headwaters of Bristol Bay's Nushagak and Kvichak watersheds.
  137. [137]
    Poll Finds Overwhelming Local Opposition to the Pebble Mine - NRDC
    Jul 20, 2018 · The poll reveals that an overwhelming majority (80%) think that the Pebble Mine would pose a serious threat to fishing in Bristol Bay. A vast ...Missing: reliance quantified
  138. [138]
    [PDF] Bristol Bay's Wild Salmon Ecosystems and the Pebble Mine
    Small stream near the Pebble Mine site (photo by Steve Baird). Page 11. 3. Executive Summary. Executive Summary. Located in southwestern Alaska, the Bristol Bay.
  139. [139]
    New Poll Finds Bristol Bay Fishermen Overwhelmingly Opposed to ...
    Aug 25, 2011 · 85% of Bristol Bay commercial fishers oppose Pebble Mine, including 80% who oppose it strongly. 86% agree that Pebble Mine would jeopardize the ...Missing: statistics | Show results with:statistics
  140. [140]
    Pebble Mine Resources - Commercial Fishermen for Bristol Bay
    The Pebble Limited Partnership is pushing to develop the deposit and build the Pebble Mine despite public and political opposition and peer-reviewed scientific ...Missing: statistics | Show results with:statistics
  141. [141]
    [PDF] SURVEY RESULTS - Bristol Bay Native Corporation
    What we learned was conclusive and clear: BBNC shareholders, in Bristol Bay and beyond, continue to oppose the proposed Pebble mine. Nearly 80% of shareholders ...Missing: 2024 | Show results with:2024
  142. [142]
    Iliamna Natives Limited, et al. v. EPA - Pacific Legal Foundation
    Jun 24, 2024 · The veto crushed hopes of Alaska Native shareholders of APC and Iliamna, undercutting their ability to provide jobs and social services and ...
  143. [143]
    Subsistence Fisheries - Pebble Science
    Subsistence harvests and uses of wild resources in Iliamna, Newhalen, Nondalton, Pedro Bay, and Port Alsworth, Alaska, 2004. Alaska Department of Fish and ...
  144. [144]
    [PDF] EPA's Recommended Determination for Bristol Bay
    Jan 24, 2023 · Stream and river fishes depend on the interconnected suite of watershed processes that shape physical habitat, structure the flow of energy ...
  145. [145]
    [PDF] Pebbles of Gold or Salmon of Time: Pebble Mine and the Cultural and
    In addition Alaska will provide economic opportunities that necessarily depend upon responsible resource development, such as mining projects (ADNR, 2013).
  146. [146]
    Pebble Mine Permit Denied by Army Corps of Engineers
    Nov 30, 2020 · The US Army Corps of Engineers denied a key permit for the proposed Pebble mine. This is a huge win for the largest sockeye salmon run in the world.
  147. [147]
    US Environmental Protection Agency Withdraws Proposed ...
    Jul 30, 2019 · In December 2017, Pebble submitted a permit application to the Corps for a project with a substantially smaller development footprint and ...
  148. [148]
    Bristol Bay 404(c) Timeline | US EPA
    On August 24, 2020, the Corps issued a determination that the Pebble Mine project, as proposed, could not be permitted under section 404 of the Clean Water Act.
  149. [149]
    Final Determination for Pebble Deposit Area | US EPA
    On January 30, 2023, EPA issued a Final Determination under its Clean Water Act Section 404(c) authority to limit the use of certain waters in ...
  150. [150]
    Bristol Bay and the Pebble Mine
    Jul 17, 2025 · On Jan. 30, 2023, EPA issued a final determination under Section 404(c) of the Clean Water Act that effectively blocked the Pebble Mine.
  151. [151]
    Northern Dynasty extends losses as it seeks court resolution on ...
    Jul 18, 2025 · In a bid to overturn the EPA's decision, the Vancouver-headquartered miner filed in March 2025 two separate actions in federal courts. Two ...
  152. [152]
    Conservation Groups Defend EPA Decision on Proposed Pebble Mine
    May 17, 2024 · “The EPA rightly decided that the devastating risks Pebble Mine poses to Alaska's Bristol Bay watershed are far too great,” said Cooper Freeman, ...
  153. [153]
    [PDF] 24-397 L - Alaska Beacon
    Mar 14, 2024 · Northern Dynasty began investing in the Pebble Deposit in 2001, by purchasing the mineral rights from Cominco. Northern Dynasty then ...Missing: handover | Show results with:handover
  154. [154]
    Motion for Summary Judgement Filed in Federal District Court in ...
    Jul 17, 2025 · In addition, the likelihood of future mining at the Pebble Project is subject to a large number of risks and will require achievement of a ...Missing: major | Show results with:major
  155. [155]
    No EPA settlement; court case likely to drag on - Pebble Watch
    Aug 4, 2025 · Meanwhile we are confident that the court will agree with our assessment that the issuance of the veto by the Biden administration was unlawful.
  156. [156]
    Alaska asks US Supreme Court to undo EPA Pebble mine veto
    Jul 26, 2023 · The state of Alaska on Wednesday asked the U.S. Supreme Court to vacate a Biden administration veto blocking Northern Dynasty Minerals' ...<|control11|><|separator|>
  157. [157]
    [PDF] Pebble Limited Partnership - Supreme Court of the United States
    Sep 26, 2023 · But EPA vetoed the issuance of any such permit for essentially any mining activities across a 309-square-mile area, with the 25-square-mile ...
  158. [158]
    Supreme Court rejects Pebble mine, climate and water cases
    Jan 8, 2024 · The Supreme Court has rebuffed a plea by the state of Alaska to revisit a federal veto of a massive mine, an attempt by oil companies to extract themselves ...
  159. [159]
    [PDF] Nunamta Aulukestai, et al., vs. State of Alaska Findings of Fact and ...
    Court's Findings of Fact and Conclusions of Law. Nunamta Aulukestai vs. State OfAlaska. DNR and Pebble Limited Partnership. Case No. 3AN ·09-9173 C! Page 124 ...
  160. [160]
    [PDF] Bristol Bay Residents Likely to Appeal Pebble ... - Trustees for Alaska
    ... Pebble. Project area to what they were before mining exploration started,” said Nondalton resident Ricky Delkittie, a plaintiff in the case. “People in the ...
  161. [161]
    Minor Setback in Bristol Bay Case | MidCurrent
    The legal fight against the massive Pebble Mine hit a minor snag earlier this week. On Tuesday, in the case State v. Non Dalton Tribal Council, et al,.
  162. [162]
    Alaska's Pebble Mine: Fish Versus Gold - Yale E360
    Sep 8, 2008 · ... contains 67 billion pounds of extractable copper, 82 million ounces of gold, and 4 billion pounds of molybdenum. At current prices, the ...
  163. [163]
    Ballot Measure 4 poses threat to Alaska - Anchorage Daily News
    Aug 18, 2008 · The proponents of Ballot Measure 4 want you to believe the measure is all about the Pebble Mine. They've spent millions upon millions of ...
  164. [164]
    Alaska's Pebble Mine Vote the Same Old Catch-22 - Shelterforce
    Sep 2, 2008 · Much attention has been on Alaska politics lately thanks to John McCain's choice of Gov. Sarah Palin as his vice presidential running mate, ...
  165. [165]
    Rpt-Voters in Alaska pass anti-Pebble ballot initiative | Reuters
    Oct 18, 2011 · Voters in a sparsely populated district of rural Alaska have narrowly passed a ballot initiative that could block development of the ...
  166. [166]
    Alaska Bristol Bay Mining Ban, Ballot Measure 4 (2014) - Ballotpedia
    This bill would require the legislature to approve future large-scale metallic sulfide mines in the Bristol Bay Fisheries Reserve (BBFR) by passing a law.Text of measure · Background · Opposition · Media editorial positionsMissing: interventions | Show results with:interventions
  167. [167]
    Alaska votes to restrict large mine - The Hill
    Nov 5, 2014 · Alaska voters approved a ballot measure aimed at adding a hurdle to the potential development of a major copper and gold mine.Missing: interventions | Show results with:interventions
  168. [168]
    Frequent questions about the Bristol Bay Clean Water Act 404c ...
    Apr 4, 2025 · EPA Region 10 proposes to restrict the discharge of dredged or fill material related to mining the Pebble deposit into waters within the mine ...Missing: pathway | Show results with:pathway
  169. [169]
    Reversing Obama, Trump EPA reaches deal with Pebble mine ...
    May 12, 2017 · The Trump administration and the mine company have agreed to drop the legal fight and allow Pebble to apply for a federal permit.Missing: shifts | Show results with:shifts
  170. [170]
    As Trump administration removes federal roadblocks, Pebble Mine ...
    Oct 11, 2017 · In 2014, the Obama administration effectively halted the project after hearing concerns that the mine could harm the Bristol Bay salmon fishery.
  171. [171]
    EPA Settles Lawsuit: Puts Pebble Mine First, America Last - NRDC
    May 12, 2017 · Today EPA settled a lawsuit with Northern Dynasty Minerals—the Canadian junior mining company behind the proposed Pebble Mine in Bristol Bay, ...Missing: shifts | Show results with:shifts
  172. [172]
    [PDF] Pebble Deposit Area, Southwest Alaska
    Dec 2, 2022 · The streams, wetlands, and other aquatic resources of the Bristol Bay watershed also provide the foundation for world-class, economically ...
  173. [173]
    Alaska's Bristol Bay & The Pebble Mine - Earthjustice
    May 17, 2024 · As proposed, the Pebble Mine project would entail mining a pit over a mile long, a mile wide and 200 meters deep, destroying nearly 3,500 acres ...Missing: methods | Show results with:methods
  174. [174]
    Alaska District > Media > News Releases
    17 Apr 2024. USACE completes appeal process for proposed Pebble mine. The U.S. Army Corps of Engineers – Alaska District finalized the appeal remand ...
  175. [175]
    Army Corps of Engineers affirms denial of permit for Pebble Mine
    Apr 16, 2024 · The U.S. Army Corps of Engineers has upheld its denial of a permit for the proposed Pebble Mine, upstream from Bristol Bay.
  176. [176]
    Trump stands opposed to Pebble mine - The Cordova Times
    Jul 25, 2025 · The Justice Department confirmed on July 17 that it would defend a 2020 USACE decision rejecting a key permit needed for the mine and the EPA's ...<|separator|>
  177. [177]
    Mine developer and EPA fail to reach agreement over Pebble ...
    Jul 21, 2025 · A possible settlement agreement between the Trump administration and the Pebble copper and gold prospect in Southwest Alaska did not pan out ...Missing: hiring | Show results with:hiring
  178. [178]
    Pebble legal battle rages with EPA agreement elusive - POLITICO Pro
    Jul 18, 2025 · Court documents show EPA and developers of the Alaska mine haven't reached agreement on the 2023 Clean Water Act veto. Avatar of Hannah ...
  179. [179]
    Pebble, EPA talks end; litigation resumes - North of 60 Mining News
    Jul 18, 2025 · No settlement reached, Northern Dynasty resumes fight over veto. What appeared to be progress toward a settlement between Northern Dynasty ...
  180. [180]
    Northern Dynasty gets Pebble court dates - MINING.COM
    Aug 8, 2025 · The mine would cost around $10 billion to develop, according to analysts at IHS Markit in February 2022. The site would produce 6.4 billion lb.<|separator|>
  181. [181]
  182. [182]
  183. [183]
    Trump's EPA reaffirms Biden-era Pebble Mine veto - KDLG
    Jul 18, 2025 · The Environmental Protection Agency is sticking with its veto of the proposed Pebble Mine project in southwest Alaska.
  184. [184]
    Seismic Risk at the Pebble Mine
    The Castle Mountain fault can experience a major earthquake. Earthquake effects on tailings dams at Pebble depend on their proximity to the fault.Missing: climate | Show results with:climate
  185. [185]
    New analysis shows seismic risks related to Pebble mine
    Jul 5, 2020 · The report by Lynker's team of scientists and engineers, released on Monday, June 29, found numerous problems with the seismic work conducted ...Missing: climate | Show results with:climate
  186. [186]
    Mine Plan - Pebble Watch
    In response, PLP stated that, “An updated estimate to complete the project cannot be provided at this time due to National Instrument 43-101 reporting ...
  187. [187]
    EPA open to idea of Pebble settlement - North of 60 Mining News
    Jul 9, 2025 · A PEA of Pebble outlines plans for an average annual production of approximately 320 million pounds of copper, 15 million pounds of molybdenum, ...Missing: future prospects<|separator|>
  188. [188]
    Pebble Mine Fails Financial Feasibility Analysis - NRDC
    Mar 28, 2019 · Former Rio Tinto permitting expert concludes that proposed mine is “almost certainly not economically feasible,” with an estimated strongly negative net ...