Dynamic load testing

Dynamic load testing, also known as high-strain dynamic testing, is a method used to evaluate the , structural integrity, and performance of elements such as driven or cast-in-place piles by applying a sudden axial load and measuring the resulting dynamic response. This technique induces high strain in the pile through an impact from a pile-driving or drop weight, capturing data on and to estimate the ultimate axial static , provided sufficient pile movement (at least 2 mm net penetration per blow) occurs. Standardized under ASTM D4945, it applies to both vertical and inclined s and serves as a primary tool for during foundation . The procedure involves attaching strain transducers and accelerometers to the pile head to record the impact-induced waves, from which force-time and velocity-time histories are derived. These measurements are analyzed using signal-matching software, such as the Case Pile Wave Analysis Program (), which simulates -pile interaction by adjusting parameters like resistance, quake, and damping to match observed data with a one-dimensional model. Testing can occur at the end of initial driving () or during restrikes (beginning of restrike, ) after a setup period, allowing assessment of capacity changes due to or relaxation. This approach also evaluates driving stresses, hammer efficiency, and pile integrity, identifying potential damage from excessive forces. Compared to static load testing, which applies a sustained load until or a specified (per ASTM D1143), dynamic load testing is faster, more economical, and enables testing of numerous piles with minimal and setup time, often during routine . While static tests provide direct load- curves for precise deflection analysis, dynamic methods typically yield conservative capacity estimates—such as a 35% increase from to in some projects—and are particularly valuable for large-scale installations where full static testing is impractical. Dynamic testing correlates well with static results when properly executed, supporting its use for verifying design assumptions and optimizing driving criteria. The origins of dynamic load testing trace back to 19th-century dynamic formulas based on hammer energy, but modern high-strain methods emerged in the mid-20th century, with significant advancements in the 1960s through research at institutions like Case Western Reserve University. The Pile Driving Analyzer (PDA), introduced in 1972 and refined in the 1970s, revolutionized the field by enabling real-time data acquisition and analysis during pile driving. Over the past six decades, these techniques have evolved into a globally accepted standard, applied in diverse projects from bridges to offshore platforms, enhancing foundation reliability while reducing costs and construction risks.

Fundamentals

Definition and Scope

Dynamic load testing is a non-destructive method used in to assess the axial and structural integrity of deep foundations by applying a sudden, high-strain to the pile head, typically via a drop or pile driving , and measuring the resulting force and velocity responses. This approach derives data from strain gauges and accelerometers attached to the pile, enabling real-time evaluation without requiring extensive setup or full-scale loading to failure, distinguishing it from more invasive static load tests. The scope of dynamic load testing is primarily confined to deep foundations such as driven piles, piles, auger-cast piles, drilled shafts, and helical piles, where the simulates loading conditions to estimate ultimate compressive and tensile capacities along with . It excludes low-strain integrity tests, which focus solely on detecting defects without capacity assessment, and does not replicate full-scale static simulations that apply sustained loads. The technique is particularly suited for in-situ verification during or after installation, providing insights into soil-pile interaction without compromising the foundation's serviceability. Key concepts in dynamic load testing involve the generation of compressive and tensile stress waves from the high-strain impact, which propagate through the pile and interact with the to produce measurable and force signals for analysis (detailed principles in subsequent sections). Tests are commonly conducted at the (EOD) to evaluate immediate capacity or at the beginning-of-restrike (BOR) after a rest period to account for setup effects. This method is widely applied to a broad range of deep foundations, offering a practical alternative for in foundation projects.

Principles of Wave Propagation

Dynamic load testing of piles relies on the principles of one-dimensional stress wave propagation, treating the pile as an elastic rod subjected to axial impact loading. The governing equation is the one-dimensional wave equation for elastic rods: \frac{\partial^2 u}{\partial t^2} = c^2 \frac{\partial^2 u}{\partial x^2}, where u(x,t) represents the longitudinal displacement at position x along the pile and time t, and c = \sqrt{E/\rho} is the wave speed, with E as the modulus of elasticity and \rho as the mass density of the pile material. This equation describes how compression or tension waves propagate longitudinally through the pile at constant speed c, assuming no lateral deformation and uniform cross-section. When a impacts the pile head, it generates an initial that travels downward from the top toward the pile . Upon reaching the , the reflects: if the encounters low , it reflects as a tensile propagating upward; higher modifies this reflection, partially converting it back to . The upward-traveling reaches the pile head, where and are measured using transducers; these signals capture the 's arrival times and amplitudes, enabling inference of pile and response. The relationship between F and v at any point is given by the Z = A \sqrt{E \rho}, where A is the cross-sectional area, such that for a traveling , F = Z v in and F = -Z v in . Soil resistance during wave propagation is modeled as two primary components: shaft resistance, which arises from frictional interaction along the pile length, and toe resistance, which provides end-bearing capacity at the pile tip. These resistances absorb energy, causing partial reflections that distort the measured signals at the pile head. In the Smith model, soil behavior is idealized with a parameter, representing the elastic displacement threshold (typically 0.1 to 0.25 inches) beyond which plastic deformation occurs, and a J, which accounts for velocity-dependent viscous energy loss (e.g., J_s = 0.1 to $0.4 s/m for , higher for toe). introduces stiffness, while dissipates energy, influencing the magnitude and duration of reflected waves; for instance, higher damping reduces tension wave peaks, protecting the pile from damage. This interaction allows dynamic testing to estimate total capacity as the sum of static and toe resistances, adjusted for dynamic effects.

Historical Development

Early Research

While the conceptual roots of dynamic pile evaluation date back to 19th-century empirical formulas like the Engineering News Record (ENR) formula, which estimated capacity from hammer energy, modern high-strain dynamic load testing emerged from mid-20th-century advancements in one-dimensional wave equation theory, notably by E.A.L. Smith in the 1960s. The pivotal shift to practical high-strain methods began in the mid-1960s at Case Institute of Technology in Cleveland, Ohio (which merged to form Case Western Reserve University in 1967), where a multi-phase research project titled "Dynamic Studies on the Bearing Capacity of Piles" was initiated under the leadership of George G. Goble, with key contributions from Frank Rausche, J. J. Tomko, and others. This effort, sponsored by entities including the Ohio Department of Highways, focused on applying one-dimensional wave equation analysis to evaluate the bearing capacity of driven piles, addressing limitations in traditional static load testing by analyzing stress waves generated during pile driving. Phase II of the project, completed in July 1968, emphasized theoretical modeling and initial field validations of wave propagation in piles embedded in soil. In 1968, during the project's early phases, Frank Rausche, George G. Goble, and George E. Likins developed the foundational , adapting E.A.L. Smith's one-dimensional model to enable practical interpretation of dynamic measurements from pile driving impacts. This approach used and data at the pile head to estimate soil resistance and total , simplifying complex mechanics for field application without requiring extensive computational resources at the time. The method built on principles of elastic propagation, allowing separation of shaft and toe resistances to improve predictions over empirical static formulas. Initial studies from this research highlighted the inaccuracies of established static formulas, such as the (ENR) formula, which often overestimated or underestimated pile capacity due to unaccounted soil-pile interactions and driving variables. By comparing dynamic predictions with limited static load tests, the work demonstrated that wave equation-based dynamic methods provided significantly better correlation with static capacities, establishing a more reliable alternative for preliminary assessments. A pivotal development occurred in the early when Goble, Rausche, and Likins established a consulting practice at to apply these dynamic testing techniques, conducting early field trials on U.S. highway projects sponsored by the . This initiative, which formalized in 1976 as GRL Engineers, Inc., marked the transition from academic exploration to practical validation, with trials confirming the method's efficacy in diverse soil conditions.

Commercialization and Adoption

The commercialization of dynamic load testing began in the early 1970s, building on foundational research conducted at in the mid-1960s. In 1972, Pile Dynamics, Inc. (PDI) was founded by Frank Rausche and Garland Likins to commercialize the , a device that measures strain and acceleration in during pile driving to assess and . This instrument marked a pivotal shift from theoretical wave propagation studies to practical field application, enabling engineers to monitor pile stresses and estimate on-site without relying solely on empirical formulas. Goble, Rausche, and Likins further expanded services through Engineers, incorporated in 1976, which provided consulting based on PDA data. During the 1980s, dynamic load testing saw significant expansion internationally, particularly in demanding environments. It was introduced in in 1981 to support for foundations, where rapid assessment of pile performance in challenging proved essential. followed in , with into finite modeling to handle complex conditions in bridge and harbor projects. These developments facilitated broader use in , as the method's portability and cost-effectiveness compared to static testing encouraged its uptake in industrial applications. A key milestone was the refinement of signal matching software, such as (Case Pile Wave Analysis Program), conceived in the early 1970s alongside the for more accurate post-test capacity predictions. By the , dynamic testing had achieved routine global acceptance, with PDI's tools deployed in over 100 countries for verification in projects. In the United States, (FHWA) guidelines increasingly endorsed dynamic methods as a primary verification tool, contributing to their widespread integration into driven pile projects and reducing dependence on more expensive static tests.

Testing Procedures

Equipment Used

The primary equipment for dynamic load testing of piles is the system, a specialized suite designed to measure force and velocity responses during high-strain impacts. Developed by Pile Dynamics, Inc., the is the most widely used system for this purpose, compliant with ASTM D4945 standards for high-strain dynamic testing. Central to the are transducers, typically piezoelectric gauges that convert compressive and tensile forces into electrical signals. These transducers are mounted in pairs, diametrically opposed around the pile's , with gauge points spaced 50-100 mm apart to capture axial accurately. Placement occurs 1-2 pile diameters below the pile top to minimize boundary effects from wave reflections at the pile head, ensuring reliable wave propagation data. Accelerometers, often piezoelectric or piezoresistive, complement the transducers by measuring pile-top , which is digitally integrated to derive ; they must withstand high accelerations up to 1000 g for piles and feature resonant frequencies exceeding 10,000 Hz for fidelity. The impact source generates the axial compressive wave essential for testing, commonly a drop hammer with a ram mass of 1-5 tons dropped from heights of 2-5 meters to deliver controlled energy levels sufficient to mobilize the pile's without exceeding material limits. Alternatively, a provides more precise energy control for larger or during . For restrike tests conducted after setup time to assess soil relaxation, smaller ram masses are often adequate to achieve the required without excessive disturbance. Data acquisition is handled by portable PDA units or connected computers, featuring high-speed analog-to-digital converters sampling at 100-500 kHz to capture transient signals with at least 12-bit resolution and record durations of 100 ms or more post-impact. These systems include amplifiers to boost outputs, anti-aliasing filters to prevent signal distortion, and software for waveform display and basic processing. Sensors are calibrated to ASTM D4945 specifications, achieving ±5% accuracy for force measurements and ±2% for velocity, with built-in self-check functions verifying performance before and during testing. Modern PDA configurations increasingly incorporate GPS modules to log precise pile locations, facilitating geospatial correlation in large-scale projects.

Step-by-Step Procedure

The step-by-step procedure for dynamic load testing of deep foundations follows standardized protocols to ensure accurate measurement of pile capacity and integrity under high-strain impacts. Preparation involves selecting a representative subset of test piles, typically 1-5% of the total production piles, to evaluate overall foundation performance without excessive cost. For cast-in-place concrete piles, strain and acceleration transducers are installed after sufficient curing (typically 24-48 hours); for precast driven piles, they are attached directly to the pile head. The hammer or drop weight is calibrated to deliver impact energy equivalent to 120-150% of the anticipated design capacity, ensuring mobilization of full soil resistance without pile damage; this often requires adjusting drop heights progressively based on preliminary blows. Execution occurs either at the end of initial driving () or beginning of restrike (), using the selected device aligned vertically above the pile. At least ten hammer blows for or 1-2 for are applied, with each generating compressive that propagate through the pile; and traces are recorded simultaneously using the transducers at a high sampling (e.g., 10,000 Hz for or ). The pile-top F is calculated from the measured v via the relation F = Z v, where Z is the pile impedance (product of cross-sectional area, , and wave speed inverse). Throughout the blows, penetration per blow (set) is monitored for consistency, typically aiming for less than 2-3 mm net set to confirm stable resistance mobilization. Post-test activities include immediate removal of transducers to resume production driving and visual inspection of the pile head for cracks, spalling, or deformation caused by excessive stresses. Data from the force and velocity traces are uploaded to analysis software for preliminary evaluation of capacity and driving stresses, often providing on-site feedback within minutes. Restrike tests are conducted 3-21 days after EOD to quantify soil setup, the time-dependent increase in shaft and toe resistance due to pore pressure dissipation and soil consolidation. Energy levels during restrikes are adjusted conservatively, typically using fewer blows and lower drop heights than initial driving, to limit tensile stresses to prestress plus 3√f'_c (with f'_c in psi), in accordance with AASHTO specifications, for concrete piles and prevent cracking.

Data Analysis Methods

Case Method

The is a foundational analysis technique in dynamic load testing of piles, providing an immediate estimate of total ultimate based on measured force and during pile driving. Developed in the late 1960s at as a practical simplification of principles, it enables on-site evaluation without extensive computation, drawing from E.A.L. Smith's 1960 model for pile- interaction. The method estimates the total static resistance R_s using the formula R_s = (1 - J) \cdot W_{d1} + (1 + J) \cdot W_{u2}, where W_{d1} = \frac{F_1 + Z v_1}{2} is the downward-traveling stress wave, W_{u2} = \frac{F_2 - Z v_2}{2} is the upward-traveling stress wave (with F as force, v as , Z as pile impedance, and times t_1 and t_2 = t_1 + 2L/c, L pile length, c wave speed), and J is the accounting for dynamic effects. The procedure begins with data acquisition from the testing setup, where strain gauges and accelerometers capture and traces at the pile head during hammer impacts. From these traces, the peak compressive F_{\max} and corresponding particle velocity v_p are identified at the time of maximum , typically when the downward reflects from the pile toe. The J is selected based on —typically 0.0 to 1.0, with lower values (0.1-0.3) for dense sands and higher (0.4-0.8) for cohesive clays—to adjust for . These parameters are then substituted into the model equations to compute R_s instantaneously using a simplified closed-form that assumes uniform propagation and concentrated resistance. In practice, the Case Method serves as a quick field tool for go/no-go decisions during pile installation, allowing engineers to verify if the driven pile meets design capacity criteria without halting construction for static tests. It relies on Smith's underlying soil model, which idealizes resistance as elasto-plastic with velocity-proportional damping, facilitating rapid assessments of driving stresses and integrity. For cohesionless soils, the method achieves accuracy within ±15-20% of static load test results, though performance varies with soil layering and hammer efficiency.

CAPWAP Analysis

The Case Pile Wave Analysis Program () is a computer-based signal matching technique developed at and introduced in 1981 for interpreting dynamic load test data from driven piles. It employs a one-dimensional solution to the wave equation, modeling the pile as a series of lumped masses and springs to simulate stress propagation. The program imports force-time and velocity-time records obtained from Pile Driving Analyzer (PDA) measurements during hammer impact—building on basic force-velocity data from the —and iteratively adjusts the soil-pile interaction model to achieve the best match between computed and measured signals. This process refines the distribution of soil resistance along the pile and at the , accounting for wave reflections and damping effects. CAPWAP solves for key soil parameters through least-squares optimization, including static shaft and toe resistances, quake (pile-soil displacement at resistance onset), and Smith-type damping factors (J_c for side resistance and J_q for toe resistance). It incorporates the measured pile impedance (EA/L, where E is modulus of elasticity, A is cross-sectional area, and L is length) to handle mismatches between the pile and , ensuring realistic simulation of propagation and dissipation. The iterative typically converges in 10-20 cycles, starting with an initial model derived from pre-analysis, and uses the downward-traveling as input to predict the upward-traveling response. The primary outputs include a detailed load-settlement curve derived from the simulated pile-soil system , as well as the of static and dynamic resistances along the pile . When calibrated against static load tests, CAPWAP capacities correlate closely, with an average ratio of 0.98 and a around 17%, indicating typical accuracy within approximately ±10% for well-instrumented tests. Analysis requires importing data into dedicated software, often paired with GRLWEAP for pre-test simulations to establish initial quake and damping values.

Applications and Case Studies

Primary Applications

Dynamic load testing, particularly high-strain dynamic testing, serves as a primary method for in the of driven piles, including , , and timber types, commonly employed in the foundations of , bridges, and offshore platforms. This technique applies a controlled load to the pile head, enabling engineers to verify the pile's design and detect installation anomalies such as necking, cracking, or plug issues that could compromise structural integrity. It is routinely applied to projects involving 10 to 1,000 piles, such as U.S. highway and bridge constructions overseen by the Federal Highway Administration (FHWA), where it facilitates efficient verification across large-scale sites without the need for extensive static testing. Often integrated with Pile Driving Analyzer (PDA) systems, dynamic testing allows real-time monitoring and adjustments during pile driving, optimizing hammer energy and driving stresses to ensure compliance with design specifications. Key variations include end-of-driving tests for immediate feedback on initial capacity and restrike tests after a set period, which account for time-dependent strength gain, particularly in cohesive clays where setup effects can increase resistance by 50-200% over days. In seismic zones, dynamic load testing is widely utilized to evaluate pile dynamic and characteristics, providing essential data for assessing performance under earthquake-induced vibrations and informing seismic design parameters.

Notable Case Studies

One notable early application of dynamic load testing occurred during the 1970s Ohio Turnpike project, where the Pile Driving Analyzer (PDA) was employed for the first time on a large scale to assess 74 piles of various types, including steel pipe piles. The testing revealed that traditional static formulas overpredicted bearing capacities, with dynamic methods providing predictions within approximately 20% of static load test results. This case demonstrated the reliability of PDA in providing real-time data for capacity verification, influencing subsequent geotechnical practices in highway construction.

Advantages and Limitations

Advantages

Dynamic load testing provides substantial benefits in terms of speed and efficiency, particularly when compared to static load testing. Tests are conducted during pile driving, yielding immediate preliminary results that facilitate real-time adjustments to driving criteria and hammer energy, thereby enhancing productivity. This approach allows for 2–6 tests per day, in contrast to the single test often limited by the multi-day setup and execution required for static methods, enabling up to 10–20 tests daily in high-volume operations under optimal conditions. The method is highly cost-effective, less expensive than static load testing due to the absence of a reaction loading system, extensive site preparation, or heavy counterweights. By optimizing pile lengths and driving parameters based on rapid feedback, dynamic testing can reduce overall foundation costs through minimized material use and fewer redrives. Dynamic load testing excels in versatility, simultaneously evaluating both axial capacity and structural integrity in a single procedure using and measurements. It is well-suited for challenging environments, including installations where space is constrained and sites with limited access, as it requires no additional heavy machinery beyond standard driving equipment.

Limitations

Dynamic load testing exhibits accuracy limitations, particularly in cohesive soils where rapid loading induces rate effects that increase measured , leading to overestimations of static by up to 50%. These errors, often ranging from 10% to 50%, arise because viscous in clays amplifies dynamic shaft and toe compared to slow static loading. The method is less reliable for assessing tension , as single-blow estimates are inherently approximate and conservative, especially for piles with embedded lengths under 10 meters. Additionally, in conditions with soft soil at the pile toe, dynamic testing can overestimate due to incomplete mobilization of static during the brief impact duration. A key risk involves potential structural damage to the pile from high tensile stresses generated during impacts, which can reach magnitudes comparable to compressive stresses and up to twice the incident compression wave in reflected phases, potentially cracking from excessive forces. To mitigate this, impacts must be controlled to keep stresses below 85% of the 's or the material's yield point, though excessive energy can still cause undetected fractures. Analysis of dynamic test data introduces subjectivity, as interpretations—such as in signal matching—depend on the engineer's judgment in selecting ratios and values, which can vary results significantly based on experience and assumptions about -pile interaction. The method is not ideal for bored piles without specialized modifications, like additional , due to their irregular and lack of initial driving stresses. Furthermore, dynamic testing is unsuitable for very short piles under 10 feet, where wave propagation is insufficient for accurate measurements, or in extremely dense gravels, where high complicates force-velocity . ASTM D4945 recommends for on critical structures to verify dynamic results and ensure reliability.

Standards and Comparisons

Relevant Standards

Dynamic load testing of deep foundations is governed by several international and national standards that outline procedures, equipment requirements, , and acceptance criteria to ensure reliable assessment of pile capacity and integrity. The American Society for Testing and Materials (ASTM) D4945-17 provides the primary standard for high-strain dynamic testing of piles, applicable to driven piles, drilled shafts, and other elements. This standard specifies the application of an axial impact using a pile driving hammer or drop weight to induce compressive forces, with measurements of and velocity at the pile head to evaluate and structural integrity. It requires such as strain gauges and accelerometers placed no less than 1.5 times the pile from the top, ensuring alignment with the pile axis, and mandates reporting of test data including force-velocity traces, estimated capacities, and analyses. Restrike testing typically involves recording data from multiple blows after the setup period to assess capacity changes, ensuring sufficient penetration to validate measurements, with data considered valid when force and times impedance are proportional during the impact phase. In , Eurocode 7 (EN 1997-1:2004, updated in the second generation EN 1997-1:2024) integrates dynamic load testing into geotechnical design for pile foundations, particularly under Section 7 for axially loaded piles. It permits dynamic impact tests to estimate compressive resistance when calibrated against static load tests on comparable piles in similar soil conditions, emphasizing measurement of and per methods like ASTM D4945. The standard requires verification of pile acceptance by ensuring the design resistance exceeds applied loads, adjusted by correlation factors such as model factors ranging from 1.1 to 1.5 for signal matching analysis in dynamic impact tests (depending on soil type: e.g., 1.5 for shaft bearing in fine soils, 1.1 in coarse soils) to higher values for dynamic formulas without displacement measurement, with values specified in national annexes based on the number of tests performed. The second generation maintains core dynamic testing provisions but updates these model factors for enhanced reliability. For U.S. highway applications, the Federal Highway Administration's (FHWA) reference manual NHI-05-042 (published 2006, with updates in FHWA-NHI-16-009 and -010 in 2016) details dynamic testing procedures for driven pile foundations in bridge and highway projects. It recommends high-strain dynamic testing using systems compliant with ASTM D4945 to monitor driving stresses, capacity, and integrity during installation, including initial driving and restrikes timed based on (e.g., 1-14 days). The manual specifies allowable stresses, such as 0.9 times yield strength for piles, and integrates dynamic data with analysis for construction control. In , IS 2911 (Part 4): 2013 from the covers of piles, including dynamic methods to determine safe working loads and structural capacity. It outlines procedures for impact-driven tests using hammers, with instrumentation to measure force, velocity, and , analyzed via dynamic formulas like the wave equation or to compute soil resistance components. The standard applies to various pile types in , , and lateral loading, requiring at least preliminary tests on trial piles for correlation with design assumptions.

Comparison with Static Load Testing

Dynamic load testing employs a transient impact from a hammer or drop weight, lasting approximately 0.1 to 1 second, to generate stress waves that are measured and analyzed using methods like the Pile Driving Analyzer (PDA) and signal matching software such as , providing an indirect estimate of pile capacity based on wave propagation and soil resistance. In contrast, static load testing applies a sustained, incrementally increasing load over hours to days using kentledge (dead weights) or a reaction frame with hydraulic jacks, directly measuring the pile's settlement and load-settlement curve to determine ultimate capacity. This fundamental difference in loading duration and mechanism—transient versus quasi-static—means dynamic testing simulates driving conditions more closely for driven piles, while static testing replicates long-term service loads. Static load testing offers direct measurement of with high accuracy, typically within ±5%, and provides the complete load- behavior essential for validating settlement predictions, but it is significantly more expensive, often 3 to 5 times the cost of dynamic testing, due to extensive setup, equipment, and time requirements that limit it to 1 or 2 piles per site. Dynamic load testing, being indirect and reliant on analysis, achieves comparable results when calibrated but may introduce variability from or hammer efficiency; however, its scalability allows testing of multiple piles economically, making it suitable for routine (QA) during of driven piles. Dynamic testing is particularly ideal for routine QA in standard driven pile projects, where rapid results during or shortly after enable on-site adjustments and cost savings, whereas static testing is preferable for validating designs in high-risk or unusual , such as those in seismic zones or variable soils, to ensure precise and data under controlled conditions. A approach, using dynamic testing for initial screening of most piles and static testing for on a subset (e.g., 1-2% of production piles), is widely recommended to balance efficiency and reliability, as supported by standards like Eurocode 7, which allows reduced partial safety factors when dynamic results are calibrated against static tests.

References

  1. [1]
    D4945 Standard Test Method for High-Strain Dynamic ... - ASTM
    Dec 12, 2017 · This test method obtains the force and velocity induced in a pile during an axial impact event (see Figs. 1 and 2).
  2. [2]
    Chapter 4. Dynamic and Static Pile Load Test Data - Design and ...
    This chapter presents the methodology and results of dynamic and static pile load test data for the selected contracts.
  3. [3]
    Dynamic Load Testing for Foundation Bearing Capacity
    Dynamic Load Tests are standardized by ASTM D4945 Standard Test Method for High-Strain Dynamic Testing of Piles. The test may also be configured to meet the ...
  4. [4]
    About Us - Pile Dynamics, Inc.
    CAPWAP is the only dynamic testing tool with an extensive published correlation study comparing its results favorably with static load tests; as a result CAPWAP ...
  5. [5]
    [PDF] Dynamic Monitoring of Piles
    Feb 7, 2020 · Example Dynamic Load Testing Result. 25. Page 26. Winter ... ▫ Dynamic testing methods provide an accurate and non-destructive capacity.
  6. [6]
    [PDF] Pile Setup and Restrike Procedures - ROSA P
    High-strain dynamic load test data from end of driving (EOD) and beginning of restrike (BOR) were compiled from sites in Northern Missouri and Southeast ...
  7. [7]
    [PDF] Pile-Driving Analysis by One-Dimensional Wave Theory
    One-dimensional wave theory uses the wave equation to analyze pile-driving, predicting impact stresses and estimating soil resistance. It uses a discrete ...
  8. [8]
    Isaacs and Glanville: The Beginnings of the Wave Equation for Piles
    Sep 18, 2017 · ... wave propagation in piles. The classical one dimensional wave equation is given by the formula. u(x,t)tt = c2 u(x,t)xx. where. u(x,t) ...
  9. [9]
    [PDF] Dynamic Loading Tests - GRL Engineers
    Dynamic testing checks both bearing capacity and pile integrity, features which make them ... and Proper Use of PDI Low Strain Pile Integrity. Testing.
  10. [10]
    [PDF] Dynamic Testing Report - American Piledriving Equipment
    May 20, 2013 · Bearing capacity testing of either driven piles or drilled shafts applies the same basic measurement approach of dynamic pile monitoring.
  11. [11]
    Pile-Driving Analysis by the Wave Equation | Vol 86, No 4
    Feb 12, 2021 · Journal of the Soil Mechanics and Foundations DivisionArticle December 1960. Discussion of “Pile-Driving Analysis by the Wave Equation”.
  12. [12]
    [PDF] Static Pile Load-Movement from Dynamic Measurements
    As discussed, the shaft resistance is lumped into N, shaft resistance forces plus one toe resistance. With 3 unknowns of the basic Smith model for each soil.
  13. [13]
    [PDF] Dynamic Studies on the Bearing Capacity of Piles - GRL Engineers
    DYNAMIC STUDIES ON THE BEARING CAPACITY OF PILES. Volume I. Final Project Report of Phase II. July 1, 1968 by. G. G. Goble. J. J. Tomko. F. Rausche. P. M. Green.
  14. [14]
    About GRL Engineers
    Incorporated in 1976, GRL continues to expand its capabilities in the dynamic testing field servicing drilled shafts, driven piles, ACIP/CFA foundations, micro ...Missing: 1972 | Show results with:1972
  15. [15]
    [PDF] Bearing Capacity of Piles from Dynamic Measurements
    project "Dynamic Studies on the Bearing Capacity of Piles". This phase was the fifth and last in a series which was sponsored at Case Western. Reserve ...
  16. [16]
    Engineering Aspects in Evaluation of Pile Capacity by Dynamic ...
    Apr 30, 2015 · Engineering research is needed to ascertain the accuracy and the area of application of high strain dynamic pile testing. ... errors about 10-15 % ...
  17. [17]
    GRL Engineers, Inc. - LinkedIn
    GRL Engineers services range from small or specialized testing jobs (such as investigating unknown foundations) to large-scale projects.
  18. [18]
    [PDF] Introducing the PDA-8G - Pile Dynamics completely revamps ... - NET
    Essentially, CAPWAP completes the dynamic load testing procedure and simulates a static load test. Pile Driving Analyzer. VT. FN. TS. Seven previous generations.
  19. [19]
    INTERVIEW: GRL Engineers - Pile Buck Magazine
    Jun 21, 2023 · In 1976, the founders, including Dr. George Goble, Dr. Frank Rausche, and Mr. Garland Likins, incorporated GRL to provide consulting services ...
  20. [20]
    [PDF] The Analysis of Pile Driving: A State of the Art - vulcanhammer.info
    Goble, G.G., Li kins, G.E., Jr. and Rausche, F., "Bearing Capacity of. Pi les from Dynamic Measurements," Final Report, Department of Civil. Engineering, Case ...
  21. [21]
    PDA Test Results - Africa, Asia, Australia & Europe
    This document lists PDA test results for Africa, Asia, Australia & Europe. Red indicates expired validity. Contact proficiencytest@pile.com to retake.
  22. [22]
    Design and Construction of Driven Pile Foundations
    This study focused on an evaluation of static and dynamic load test data and a case study of significant movement of an adjacent building during pile driving.Missing: adoption | Show results with:adoption
  23. [23]
    Pile Driving Analyzer® (PDA) for High Strain Testing
    High strain dynamic load testing and pile driving monitoring system. Perform dynamic load testing on most types of deep foundations.Missing: definition | Show results with:definition
  24. [24]
    D4945 Standard Test Method for High-Strain Dynamic Testing of Piles
    Mar 2, 2021 · This test method obtains the force and velocity induced in a pile during an axial impact event (see Figs. 1 and 2).
  25. [25]
    [PDF] Helpful Hints for Field Testing and Data Interpretation Using the Pile ...
    USING THE PILE DRIVING ANALYZER ... The transducers also should (if at all possible) be attached at least 2 and preferably 3 or more diameters below the pile top ...
  26. [26]
    [PDF] High-Strain Dynamic Testing of Deep Foundations1
    Scope. 1.1 This dynamic test method covers the procedure for applying an axial impact force with a pile driving hammer or.
  27. [27]
    High Strain Dynamic Load Testing (Drop Hammer)
    High Strain Dynamic Load Testing (Drop Hammer) · Test capacities up to 2,000 tons (higher loads available upon special request) · Ram weights from 8 kips to 60 ...Missing: definition | Show results with:definition
  28. [28]
    ASTM D4945 Compliance - Piletest.com
    ASTM D4945: Standard Test Method for High-Strain Dynamic Testing of Deep Foundations ; 5.23. Transducers shall be calibrated to an accuracy of 3%. 2% ; 5.2.4.1.Missing: 2025 placement
  29. [29]
    [DOC] Dynamic Pile Testing
    Scope of work shall include furnishing all labor, equipment and analysis associated with dynamic testing of driven piles as specified in this special provision.
  30. [30]
    Dynamic Load Test (DLT) On Pile - Civil practical knowledge
    Dec 20, 2024 · Dynamic Load Testing (DLT) evaluates pile load capacity using a high-strain impact, often with a hammer, to simulate load conditions.Missing: definition | Show results with:definition
  31. [31]
    [PDF] Dynamic Load Testing of Augered Cast-In-Place Piles
    Figure 1 shows a conventional hammer or large drop weight is used to dynamically impact piles installed by continuous flight augers.Missing: typical | Show results with:typical
  32. [32]
  33. [33]
    [PDF] Untitled - NET
    project "Dynamic Studies on the Bearing Capacity of Piles". This phase was the fifth and last in a series which was sponsored at Case Western. Reserve ...
  34. [34]
    [PDF] Dynamic Determination of Pile Capacity | GRL Engineers
    The purpose of this paper is to present the derivation of the Case. Method, and to discuss the assumptions contained in the governing equations. Sources of ...
  35. [35]
    [PDF] An Experience with Dynamically Tested Piles
    The results of the. CAPWAP analysis are thus the magnitude and location along the pile of both static and dynamic resistance forces. Static computations can be ...
  36. [36]
    CAPWAP® (Case Pile Wave Analysis Program)
    CAPWAP (Case Pile Wave Analysis Program) is a software program that estimates total bearing capacity of a pile or shaft, as well as resistance distribution.
  37. [37]
    [PDF] Static and Dynamic Models for CAPWAP Signal Matching
    The goal of CAPWAP is the determination of dynamic and static soil resistance parameters of the generally accepted Smith-type pile-soil interface model. ...
  38. [38]
    [PDF] CORRELATION OF CAPWAP WITH STATIC LOAD TESTS
    CORRELATION OF CAPWAP WITH STATIC LOAD TESTS. Garland Likins1 and Frank Rausche2. ABSTRACT. Signal matching analysis such as CAPWAP is considered a standard ...
  39. [39]
    High Strain Dynamic Pile Load Testing | Foundation Integrity
    This advanced, non-destructive testing method ensures the integrity and capacity of deep foundations, providing real-time insights to optimise construction and ...<|control11|><|separator|>
  40. [40]
    Deep Foundation Load Test Database (DFLTD) - Version 2.0 | FHWA
    Jun 2, 2025 · Load test types include axial static, rapid (Statnamic), and dynamic load tests. Foundation types include open- and closed-end steel pipe ...Missing: scope | Show results with:scope
  41. [41]
    [PDF] High strain dynamic pile testing, equipment and practice - G. Likins
    High strain PDA testing verifies pile capacity, hammer efficiency, and driving stresses. It uses a Pile Driving Analyzer (PDA) to measure strain and ...
  42. [42]
    [PDF] Guidelines for successful High Strain Dynamic Load Tests - NET
    High Strain Dynamic Pile Testing with the Pile Driving Analyzer® (PDA) was first offered by Pile. Dynamics in 1972 following a decade of pioneering research ...
  43. [43]
    [PDF] Analysis and Design of Piles for Dynamic Loading - CFMS
    This paper describes some of the ongoing efforts to use sophisticated analysis and testing in “code-based” design practice. 2 BRIEF REVIEW OF RESEARCH. Seismic ...
  44. [44]
    Nonlinear dynamic analysis of pile foundation using finite element ...
    Oct 24, 2025 · Nonlinear dynamic response analysis of pile foundations is essential in seismic regions, where soil–pile–structure interaction governs safety ...Missing: zones | Show results with:zones
  45. [45]
    Use of the dynamic load test to obtain the pile capacity - ResearchGate
    The objective of this paper is to compare the expected geotechnical load capacity through empirical and semi-empirical Brazilian methods with the ultimate pile ...Missing: offshore | Show results with:offshore<|separator|>
  46. [46]
    [PDF] Micropile Foundations in Karst: Static and Dynamic Testing Variability
    Although PDA testing had been used in some cases to predict capacity of drilled shafts in soils, the geotechnical consultant could find no records on the use of.
  47. [47]
    [PDF] FHWA Geotechnical Engineering Circular 015 - vulcanhammer.net
    Alternative performance tests may include rapid load tests, high-strain dynamic tests, or even pile restrike tests to assess pile setup. Load testing of all ...<|control11|><|separator|>
  48. [48]
    (PDF) Axial capacity of impact-driven monopiles: the case study at ...
    Aug 2, 2019 · Axial capacity of impact-driven monopiles: the case study at Cuxhaven, Germany. February 2019. Conference: Pfahl-Symposium 2019; At: Germany.Missing: farm | Show results with:farm
  49. [49]
    [PDF] University of Dundee Pile capacity testing Brown, Michael; Ball ...
    device, for example the Pile Driving Analyser (PDA) produced by Pile Dynamics Inc. ... such as CAPWAP (Case pile wave analysis program), TNOWAVE and SIMBAT ...
  50. [50]
    [PDF] Pile Testing - NET
    "The advantages of dynamic load testing is that it's a faster test, and it's often less costly than a static load test," said Beim. "After post-processing ...
  51. [51]
    [PDF] Dynamic and Static Load Testing: A Cost Savings Approach | GRL ...
    A correlation of the static and dynamic load test results was established to develop a driving criteria for the piling across the two kilometer project. The.
  52. [52]
    [PDF] COMPARISON OF STATIC AND DYNAMIC LOAD TESTING
    Jul 1, 2024 · When conducting CAPWAP analysis for all blows of the same test, confirming a better fit between the tests when comparing the DLT and the SLT ( ...
  53. [53]
    [PDF] High Strain Dynamic Pile Testing and Static Load Test
    The HSDPT also offers the following advantages: ▫ piles can be ... Dynamic Load Testing of Drilled Shafts at National. Geotechnical Experimentation Sites.
  54. [54]
    [PDF] Load Testing Handbook (Including Pile Testing Datasheets)
    Typically a dynamic test will take about 15 minutes to perform on a precast concrete pile using the piling rig hammer to 30 minutes on a bored cast in place ...
  55. [55]
    (PDF) Comparison of static and dynamic load testing: A review
    Oct 3, 2024 · The literature review recommends comparing SLT capacities to the DLT's field capacities and those obtained using CAPWAP analysis.<|separator|>
  56. [56]
    None
    ### Summary of Tensile Stresses in Concrete Piles During Dynamic Testing
  57. [57]
    [PDF] Accuracy and Limitations of Full-Scale Dynamic Shaft Testing
    This paper has the following aims: to create an awareness of the potential cumulative errors that are inherent in dynamic load testing, to highlight the ...Missing: ENR 10-15%
  58. [58]
    What is the shortest foundation length for Dynamic Load Testing?
    The guidelines below are the recommended minimum lengths. It is also recommended that the number of pile and soil elements in CAPWAP is increased to at least 4.Missing: unsuitable dense gravels
  59. [59]
    Comparing Static vs Dynamic Load Tests - G-Octopus
    Nov 30, 2020 · While dynamic load tests can be used to estimate pile capacity and pile integrity on test and production piles, according to main international ...
  60. [60]
    Chapter 8 - Static Pile Load Testing and Pile Dynamic Analysis
    ... pile load test systems of varying maximum load capacity: 1,000,000-pound Load Test System; 2,000,000-pound Load Test System; 4,000,000-pound Load Test System ...
  61. [61]
    [PDF] The Economics of Pile Testing - GRL Engineers
    As a supplement to or replacement for static tests. dynamic testing takes far less time to perform and thus reduces the costs. The time required on site for a ...Missing: comparison | Show results with:comparison
  62. [62]
    Benefits of Dynamically Testing Driven Piles
    Mar 28, 2023 · Dynamic testing is an efficient and cost-effective way to evaluate driven steel, timber, or concrete pile foundations during installation.