Hywind Scotland

Hywind Scotland is the world's first floating offshore wind farm, consisting of five 6 MW turbines with a total installed capacity of 30 MW, located approximately 30 km off the coast of in , , at water depths of 95 to 120 meters. The project, developed by in partnership with , became operational in October 2017 and spans about 4 square kilometers, utilizing spar-type floating foundations with patented motion control technology to enable deployment in deeper waters unsuitable for fixed-bottom structures. As a pioneering pilot project, Hywind Scotland demonstrated the commercial viability of floating offshore wind technology, achieving the highest average among offshore wind farms and generating enough electricity to power approximately 35,000 homes annually while displacing around 63,000 tonnes of carbon emissions each year. The farm's inter-array and export cables connect the turbines to the grid, with an export cable of approximately 30 km, the project costing around 2 billion and representing a 60-70% compared to its predecessor, the single-turbine Hywind . In 2024, the farm underwent a major maintenance campaign, including towing all five turbines to for upgrades and temporary cable disconnections; it was fully reconnected in October and remains operational as of 2025, serving as a key reference for scaling up floating wind projects globally, including larger arrays up to ten times its size.

Background and Development

Project Origins

The Hywind Scotland project originated from Equinor's earlier Hywind Demo initiative, launched in by Statoil (Equinor's predecessor) off the coast of . This demonstration featured a single 2.3 MW , marking the world's first full-scale prototype to validate the feasibility of in deeper waters where fixed foundations are impractical. Building on the lessons from Hywind Demo, announced the development of Hywind Scotland in November 2015 as the world's first commercial-scale floating , targeting a 30 MW capacity with five turbines. The project aimed to demonstrate scalability and cost efficiency for floating wind in challenging offshore environments, positioning it as a pivotal step toward broader commercialization. To advance the initiative, formed the Hywind (Scotland) Limited, retaining 75% ownership while divesting 25% to in January 2017, sharing development risks and costs. The partners committed approximately 2 billion in total investment, achieving a 60-70% per MW compared to the Hywind Demo through optimized scaled production and accumulated expertise.

Planning and Approvals

The site selection process for Hywind Scotland focused on identifying a location in the Buchan Deep, approximately 25 km east of in , , where water depths range from 95 to 120 meters. This depth profile was ideal for demonstrating technology, as it exceeds the typical limits for fixed-bottom foundations (generally under 50 meters), while providing stable conditions for systems and access to strong from the west and southwest. Key criteria included proximity to existing infrastructure, such as Port for assembly and operations, and the Grange substation for grid connection, alongside minimal interference with shipping routes and low based on initial desk studies of distributions and marine habitats. Regulatory approvals were secured through a streamlined process, as the project's capacity of 30 MW and location beyond 12 nautical miles from the coast exempted it from requiring consent under Section 36 of the Electricity Act 1989. Instead, a marine licence was granted by the Scottish Ministers on November 2, 2015, under the Marine (Scotland) Act 2010 and the Marine and Coastal Access Act 2009, enabling activities. This followed the submission of an (EIA) in April 2015, which evaluated potential effects on key receptors including (e.g., collision risks for seabirds like guillemots and gannets, assessed via European Seabirds at Sea surveys), marine mammals (e.g., disturbance to harbour porpoises and minke whales from construction noise), and fisheries (e.g., temporary access restrictions for demersal in the 4 km² area). The EIA concluded negligible to minor impacts overall, with no significant effects on protected species or commercial stocks, supported by mitigation measures like 500-meter safety zones during installation. Stakeholder consultations played a central role in addressing potential conflicts, with early and ongoing engagement involving local fisheries organizations such as the Inshore Fishermen’s and the Scottish Fishermen’s Federation to mitigate displacement risks for vessels targeting species like and . Discussions with informed lease agreements and fisheries liaison protocols, while Marine Scotland provided guidance on scoping, cumulative impacts, and Habitats Regulations Appraisal requirements to ensure compliance with European protected sites. These interactions, conducted from 2013 through 2015, incorporated feedback on navigation safety and environmental monitoring, leading to the adoption of best-practice guidelines for offshore renewables. Development timeline milestones included the final investment decision by (then Statoil) in November 2015, immediately following the marine licence approval, committing approximately €214 million to the project. An Agreement for Lease was awarded by The Crown Estate in May 2016, securing seabed rights and enabling onshore preparations. The project is a between (75% stake) and (25% stake), with the partnership formalized in January 2017 to share development costs and risks.

Construction and Installation

Turbine and Platform Manufacturing

The Hywind Scotland project featured five SWT-6.0-154 direct-drive wind turbines, each with a rated capacity of 6 MW, a rotor diameter of 154 meters, and a hub height of 98 meters above . These turbines were produced at 's facilities in and as part of a aimed at leveraging established wind manufacturing expertise. The direct-drive design eliminated the need for a gearbox, enhancing reliability in the challenging environment. The floating platforms employed spar-buoy designs, comprising tall steel cylinders up to 100 meters in length, fabricated by Navantia in collaboration with Windar Renovables at the Fene shipyard in Spain. These cylindrical structures, with a draught of approximately 78 meters, were ballasted to provide stability and were constructed using welded steel blocks assembled onshore before transport. The platforms' design drew from proven spar technology, ensuring deep submergence for reduced wave excitation. Key manufacturing innovations focused on scaling production through standardized components adapted from the earlier Hywind Demo project, which enabled a 60-70% relative to the prototype. Final integration of the turbines onto the platforms occurred at the facility in , where the complete assemblies were prepared for subsequent deployment. This approach emphasized modular assembly to streamline processes and minimize risks. The project's total capacity reached 30 MW through these five units.

Deployment Process

The deployment of Hywind Scotland began with the tow-out phase in summer 2017, when the five fully assembled spar-buoy platforms, each supporting a 6 MW , were transported from the assembly site in , , across the to the project location approximately 30 km off the coast of , . The first platform set sail on July 17, 2017, and arrived in Scottish waters on July 24, 2017, with the remaining four following by the end of July to capitalize on favorable seasonal weather conditions. This multi-vessel towing operation marked a key logistical step in positioning the floating units at the Buchan Deep site in water depths of 95 to 120 meters. Installation proceeded in a sequenced manner starting with preparation in spring 2017. TechnipFMC's Deep Explorer installed 15 suction anchors—three per platform, each 16 meters tall and weighing about 300 tonnes—between April and June 2017, followed by the attachment of mooring lines to secure the platforms upon arrival. Once towed to site, the platforms were ballasted and connected to their s, after which the turbines were verified for operational readiness; the full array of five units was anchored and positioned by mid-August 2017. Turbine erection relied on floating heavy-lift s, such as the S7000, due to the deep-water conditions precluding jack-up use. Cabling installation occurred concurrently in September 2017, with deploying approximately 7.5 km of 33 kV dynamic inter-array cables to interconnect the five turbines and a single 30 km cable to transmit power onshore. The inter-array system formed a linking the floating units, while the cable was laid along a corridor from the array to a landfall near , connecting to an onshore substation at for integration into the electricity grid. This setup achieved the world's first multi-turbine floating wind array grid connection in October 2017. Key challenges during deployment included navigating limited weather windows in the harsh environment, where unpredictable storms and high waves necessitated scheduling tow-outs and installations during the calmer summer period to ensure safe operations. The project's success in overcoming these conditions demonstrated the viability of coordinated multi-vessel for floating wind, culminating in full operational readiness by October 2017.

Technical Design

Wind Turbines

Hywind Scotland utilizes five Siemens Gamesa SWT-6.0-154 wind turbines, each with a rated capacity of 6 MW and a rotor diameter of 154 meters, contributing to the project's total installed capacity of 30 MW. These direct-drive turbines, featuring permanent magnet generators without gearboxes, were selected for their reliability in environments and adapted through specialized control systems to suit floating operations. Key adaptations for floating conditions include the Hywind Motion Controller, a layer developed by that integrates with the turbine's standard to enhance dynamic stability. This controller employs individual blade adjustments—known as Active Yaw Individual Pitch Control (AYIPC)—to counteract platform motions, limiting yaw deviations to approximately 3 degrees and reducing mooring line tensions. Dozens of onboard sensors monitor real-time parameters such as yaw angle, blade thrust forces, and platform sway, feeding data directly into the control algorithms to enable proactive and yaw corrections that minimize rocking and heeling effects. The turbines' power curve is characterized by a cut-in of 4 m/s, reaching rated power at 13 m/s, and a cut-out speed of 25 m/s to protect against extreme conditions. In floating applications, the and yaw systems incorporate floating-specific adjustments, such as reduced during high winds via blade feathering, to further stabilize the structure without compromising energy capture. For integration with the spar-type floating base, each turbine features a weighing 360 tons, with the total structure extending approximately 253 meters from to tip.

Floating Foundation Technology

The floating foundation technology employed in Hywind Scotland utilizes a spar-buoy design, consisting of a slender, vertical steel cylinder that serves as a ballast-stabilized to support offshore wind turbines in deep-water environments. This concept, developed by , enables deployment where fixed-bottom foundations are impractical due to water depths exceeding 50 meters, with the Hywind Scotland site specifically featuring depths of 95–120 meters. Unlike shallower-water monopile or structures, the spar-buoy's deep draft and distributed mass provide inherent stability against environmental loads, allowing access to high-wind resource areas farther from shore. The spar-buoy structure has a maximum base diameter of approximately 14.5 meters, tapering to 9–10 meters at the , with an overall of around 90 meters and a total of about 3,500 tonnes per unit. , comprising high-density ( 4.05 t/m³) and loose MagnaDense (submerged weight 2,000–3,100 kg/m³), totals roughly 5,100 tonnes of loose material and 1,100 tonnes of per , ensuring over 70% submersion to lower the center of and generate a strong restoring moment against wave and wind-induced tilts. This configuration suits water depths of 100–300 meters, as the deep minimizes hydrodynamic excitation while the counteracts and roll motions. Stability is further enhanced by tuning the spar-buoy's natural periods—typically 20–30 seconds for heave and motions—to avoid with dominant sea states, which have periods of 8–12 seconds in the . The design draws from the Hywind Demo project, operational since 2009 with a single 2.3 MW unit on a similar 100-meter spar, but scales up for Hywind Scotland's five units by optimizing distribution and structural proportions to improve yaw stability under larger turbine loads and array interactions. Wind turbines are mounted atop these foundations via a transition piece, integrating the floating base with the above-water and rotor assembly.

Mooring and Cabling

The mooring system for Hywind Scotland consists of three lines per , each connected to the spar-buoy at attachment points near the base and anchored to the using piles. Each line employs a chain--chain configuration, with the polyester segments providing and reducing overall weight while the chains ensure durability against abrasion and high loads. The total length of each mooring line extends up to approximately 850 meters from the to the touchdown point. The piles, numbering 15 in total across the five , measure 5 meters in diameter and 16 meters in length, with each weighing about 300 tonnes and installed into the clay-dominated at depths of 100 to 120 meters. This design is engineered to maintain stability in the North Sea's harsh , capable of withstanding extreme conditions including 50-year storms with significant wave heights up to 15.5 meters and wind speeds exceeding 40 meters per second. The configuration allows the lines to form a natural curve under their own weight, distributing loads dynamically and minimizing vertical on the anchors while preventing excessive offset of the floating structures. Integrated systems, including sensors for line , tracking, and motion , enable real-time assessment of system integrity, helping to detect potential and ensure precise alignment of turbines with . The electrical infrastructure features dynamic inter-array cables operating at 33 kV, totaling approximately 6 kilometers, which connect the five turbines in a configuration that transmits generated to a central substation on one of the platforms. These cables are designed to accommodate the motion of the floating foundations, using flexible armoring to resist bending and fatigue from wave-induced movements. A single static cable, also at 33 kV, runs from the offshore substation to the onshore connection at Power Station, covering about 20 kilometers and buried 1 to 2 meters beneath the to protect against gear, anchors, and environmental . This setup ensures reliable while integrating with the local network, supporting the farm's operational capacity of 30 MW.

Location and Site Characteristics

Geographical Position

Hywind Scotland is located in the Buchan Deep area of the northern , approximately 25 kilometers east of in , , placing it within waters managed under lease by the Crown Estate. The pilot park's central position is at roughly 57.49°N 1.36°W, encompassing a deployment area of about 13 square kilometers buffered by safety zones. This site selection leverages 's offshore wind potential in deeper waters unsuitable for fixed-bottom foundations, while benefiting from proximity to the Port of for logistical support. The five wind turbines are arranged in a compact layout spanning approximately 4 square kilometers on the sea surface, with inter-turbine spacing of 800 to 1,600 meters in a roughly linear north-south to optimize and cabling efficiency. Anchor points for the three-point systems extend the footprint to up to 15 square kilometers, positioned to avoid interference with nearby oil and gas like the Forties pipelines. This configuration facilitates shared use of existing subsea routes and enhances operational by drawing on the region's established energy supply chain. Bathymetry at the site features water depths ranging from 95 to 120 meters, suitable for spar-type floating platforms, over a of mega-rippled silty sand and gravel with scattered boulders and occasional rocky outcrops. The sandy-gravel composition supports suction installation for stability in this part of the continental shelf. At this distance from shore, the installation remains accessible for routine surface-based monitoring, reducing reliance on specialized deep-water interventions while aligning with environmental protocols for the area.

Environmental Conditions

The Hywind Scotland site, located in the Buchan Deep area of the , experiences a wind regime characterized by average speeds of approximately 10.2 m/s at hub height (100 m) based on data from 1980 to 2010. Winds predominantly originate from the south and west, with southerly directions (180°–210°) being most common, contributing to the site's suitability for offshore energy generation. During storms, gusts can reach up to 50 m/s, reflecting the extreme conditions for which the project was engineered, with operational shutdowns programmed above 25 m/s to ensure safety. Wave and current patterns at the site are influenced by its exposure to swells, with significant wave heights typically below 4 m but peaking in winter months, such as January. Extreme events include significant wave heights up to 10.9 m for a 100-year , accompanied by wave periods of 4–8 seconds dominantly and up to 13.1 seconds in extremes. Tidal currents exhibit mean speeds of 0.32–0.40 m/s (0.6–0.8 knots), with maximum spring speeds reaching 1.3 m/s (2.5 knots), and the site's position at water depths of 95–120 m amplifies exposure to long-period swells from the . The marine environment surrounding Hywind Scotland features circalittoral fine sands with sparse benthic , indicating a low impact area suitable for floating installations. populations include such as guillemots, gannets, and puffins, with high seasonal concentrations near nearby headlands during breeding periods, based on European Seabirds at Sea (ESAS) surveys from 2013–2014. Fish stocks comprise pelagic like and , demersal fish including sandeels and , and such as and scallops, supporting regional fisheries. Marine mammals, including harbour porpoises (most frequent sightings), and harbour , and occasional minke whales, are present but in low densities, with no anticipated significant population-level effects from the project. Project design adaptations address these conditions through turbines rated for winds exceeding 25 m/s and waves up to 20 m, as demonstrated in prior Hywind demonstrations, ensuring structural integrity in harsh environments. The floating spar-buoy foundations, with ballast stabilization and a 70–82 m operational draught, minimize disturbance and reduce scour risks compared to fixed-bottom structures, while the three-point system with anchors provides redundancy against extreme loads. These features align with standards for structures, enabling reliable operation in the site's dynamic metocean regime.

Operation and Performance

Commissioning and Grid Connection

The commissioning process for Hywind Scotland began following the installation of its five 6 MW turbines in August 2017, with all units positioned and moored at the Buchan Deep site approximately 25 km east of , . Individual turbine testing, conducted in collaboration with , focused on verifying electrical systems, control mechanisms, and structural integrity under operational loads, ensuring each unit could generate and transmit power independently before array integration. By early September 2017, the first turbine achieved grid connection, exporting initial power to the National Grid on September 8, marking the project's inaugural electricity production from floating offshore wind. Array-level followed in the subsequent weeks, involving coordinated testing of inter-turbine cabling, power export systems, and grid stability features to enable full 30 MW output. Minor weather-related challenges, including high winds and swells in the , caused brief pauses in offshore testing activities during this phase, though they did not significantly extend the overall timeline. The wind farm's grid integration connected the 30 MW array to the onshore substation at via a subsea export cable route landing on the coast, feeding into the Scottish and National Grid network operated by . Commissioning simulations had targeted a of 50-60%, aligned with expectations for fixed-bottom wind in the region, to validate the floating platform's performance under variable conditions. Full operational synchronization was completed by mid-October 2017, with the project officially opened on October 18, 2017, by Scotland's , , confirming its readiness for commercial energy delivery.

Energy Production and Efficiency

Hywind Scotland, with its 30 MW installed capacity from five 6 MW turbines, generates an annual electricity output of approximately 135 GWh, sufficient to power around 20,000 to 35,000 households depending on updated consumption estimates. In its first year of operation starting October 2017, the farm exceeded performance expectations, achieving production substantially higher than the projected P50 baseline through strong wind conditions and high system uptime. The farm's capacity factor has averaged 56% over its initial years of operation (2017-2019), outperforming the UK offshore wind average of around 40% for fixed-bottom installations due to access to consistent deep-water winds. This metric peaked at 65% during the farm's first three full months of production in late 2017 and early 2018, and reached 57.1% for the 12-month period ending March 2020, setting a record for UK offshore wind farms at the time. Over the subsequent years through 2024, the average stabilized at 54%, reflecting robust performance amid varying weather, including a planned maintenance outage in 2024. Key efficiency factors include minimized wake losses from the turbines' 1 km spacing, which allows greater recovery compared to denser fixed-bottom arrays, and the floating spar platforms' motion, which has shown no adverse impact on or output in operational . Supervisory control and (SCADA) systems have supported , enabling real-time monitoring that contributes to consistent operation in optimal conditions. Post-2018 optimizations, including advanced software, have further enhanced load management and energy capture by reducing structural fatigue and adapting to platform dynamics.

Maintenance and Reliability

Hywind Scotland employs a combination of vessel-based and remote methods for access and maintenance. Routine checks and technician transfers are primarily conducted using a dedicated crew transfer vessel (CTV) based in , , operating up to 12 hours per day year-round to facilitate efficient onsite interventions. For subsea surveys, major component exchanges, and inspections of moorings and cables, ad hoc vessels equipped with remotely operated vehicles (ROVs) are deployed on a campaign basis, typically bi-annually to assess structural integrity. Additionally, unmanned aerial vehicles (UAVs) are utilized for blade inspections during suitable weather conditions, minimizing the need for physical access. The wind farm has demonstrated strong reliability since its commissioning in 2017, achieving technical availability consistently above 95% through , with only brief outages associated with scheduled and subsea inspections. No major structural failures have been reported, underscoring the robustness of the floating spar foundations and systems in harsh conditions, including waves up to 10 meters. This high uptime has been supported by extensive sensor networks monitoring , lines, and structural strains in , enabling proactive issue detection and contributing to the farm's status as the UK's best-performing offshore wind project over multiple years. The heavy maintenance campaign in 2024, involving towing turbines to for component exchanges, was successfully completed in October 2024, with all units reconnected and the farm returning to full operation, maintaining high reliability as of 2025. Maintenance strategies incorporate derived from sensor data and specialized monitoring systems, such as those for subsea cables that use physics-based models to forecast performance and preempt faults. has leveraged data from Hywind Scotland's operations, including open datasets shared for research, to refine these tools and optimize scheduling via enterprise systems like , achieving over seven years of operation (with a planned full shutdown in 2024 only). These innovations, including a long-term service agreement with for turbine upkeep extended to 2027, have enhanced operational efficiency. Key challenges include managing , or marine growth, on moorings and substructures, which is addressed through ROV inspections and controlled deballasting procedures to maintain system performance without environmental discharge risks. Through optimized maintenance scheduling and lessons from predictive monitoring, operational costs have been reduced, contributing to industry-wide LCOE reductions for scaled-up floating wind projects, with targets approaching €50-60 per MWh in the , compared to Hywind Scotland's initial projections of around €180/MWh.

Impact and Legacy

Technological Advancements

Hywind Scotland served as a critical for the commercial viability of spar-buoy floating wind turbines deployed in arrays, marking the world's first such installation with five 6 MW turbines totaling 30 MW capacity operational since 2017. This pilot demonstrated reliable performance in harsh conditions, achieving capacity factors exceeding 57% and validating the scalability of the technology for utility-scale applications ten times larger. The success directly informed subsequent developments, including the 88 MW Hywind Tampen project commissioned in 2022, which expanded on the spar-buoy design to power offshore oil and gas platforms. Key operational from Hywind Scotland advanced understanding of motion-response coupling between the floating , , and environmental loads, enabling refinements to hydrodynamic models used in and . Full-scale measurements revealed interactions such as and yaw influencing loads, which informed aero-hydro-servo-elastic modeling tools like those validated against Hywind for predicting responses in irregular waves. Additionally, the confirmed substantial cost reductions, with per MW dropping 60-70% compared to the earlier Hywind Demo, supporting economic feasibility for 10x scaling to 300 MW farms through optimized and installation processes. Innovations from Hywind Scotland, particularly the simple three-line system using anchors, have been exported to international projects, influencing designs in the (e.g., Equinor's floating wind initiative) and (e.g., adaptations in deep-water pilots by partners like Sumitomo). The seamless integration of standard bottom-fixed turbines with spar platforms established benchmarks for load transfer and stability, contributing to the formulation of IEC 61400-3-2, the international standard for design released in 2019. This standard incorporates coupled dynamic analysis requirements derived from early array data like Hywind's to ensure fatigue resistance and operational safety. The project has driven significant research contributions, yielding over 50 peer-reviewed publications on hydrodynamics, wake effects, and platform motions, often leveraging shared operational datasets. Partnerships with institutions such as the Offshore Renewable Energy Catapult and universities including the have focused on fatigue analysis, using Hywind measurements to develop probabilistic models for long-term structural integrity under combined wind-wave loading. These efforts have enhanced predictive tools for mooring fatigue and endurance, informing global R&D for next-generation floating arrays.

Economic and Social Contributions

Hywind Scotland has generated significant economic benefits for Scotland, particularly in the northeast region. During the construction and installation phase, the project supported 370 full-time equivalent (FTE) jobs across direct, indirect, and induced categories over two years, with 78 direct jobs focused on onshore activities in Peterhead. In the operational phase, it sustains approximately 33 FTE jobs annually, including 21 direct and indirect roles in operations and maintenance, primarily based in Peterhead. Overall, the project is projected to contribute £68 million in gross value added (GVA) to the Scottish economy over its lifetime from 2015 to 2038, with £26 million benefiting the local area around Peterhead. The project has bolstered the Scottish offshore wind supply chain by engaging 788 companies nationwide, 25% of which are located within 50 miles of , fostering local procurement and expertise in floating wind technologies. Scottish content accounted for 19.9% of the total spend, with key contributions from local firms such as Isleburn for suction anchors and in for installation services; in optimistic scenarios, local content could reach up to 90% if all feasible work is retained in . This involvement has supported £8 million in direct spending in the area during construction and enhanced skills development, including training programs at institutions like for floating offshore technologies. Additionally, the project contributed around £10-15 million to the broader supply chain through indirect expenditures on services and materials. On the social front, Hywind Scotland has delivered community benefits through localized economic activity and engagement initiatives. It has provided minor positive impacts to Peterhead's businesses via increased demand for services during construction and operations, alongside potential boosts to from opportunities like to view the turbines. Fisheries compensation agreements were established to mitigate any disruptions to local operations, ensuring ongoing with affected communities. The project also enhances energy by contributing to net-zero goals, powering approximately 36,000 homes annually with clean energy and displacing substantial CO₂ emissions. In 2024, the project experienced a temporary export cable disconnection requiring turbines to be towed to for maintenance, but was fully reconnected by October 2024 with no long-term impact on operations. As a pioneering , Hywind Scotland has left a lasting legacy by attracting follow-on investments for floating offshore wind in , including the 50 MW Kincardine project and contributions to Scotwind leasing rounds that have spurred further development in the sector. This has positioned as a global leader in floating wind, driving national economic growth and innovation in supply chains.

References

  1. [1]
    Hywind Scotland - the world's first floating wind farm - Equinor
    The world's first floating offshore wind farm, with 5 turbines · Pilot park covering around 4 square kilometres · Installed capacity: 30 MW · Diameter 154 m ...
  2. [2]
    Hywind Scotland Pilot Park | Tethys
    Sep 24, 2025 · Hywind Scotland Pilot Park is the world's first floating offshore wind farm and is the first project to connect multiple floating turbines in an array.Missing: facts | Show results with:facts
  3. [3]
    Hywind Scotland - Masdar
    Hywind is the world's first floating offshore windfarm, located off the coast of Aberdeenshire in Scotland. Masdar has a 25 per cent stake in the 30MW project, ...
  4. [4]
    Hywind project: first floating wind farm - Nexans
    The Hywind Scotland Pilot Park, located 30 km off the coast of Aberdeenshire, consists of five wind turbine generators connected through an inter-array cable ...Missing: facts | Show results with:facts
  5. [5]
    Hywind Scotland export cable reconnected, power restored - reNews
    Aug 16, 2024 · Global Maritime has announced that Hywind Scotland's export cable has been reconnected and is ready to supply power back to Scotland.<|control11|><|separator|>
  6. [6]
    Floating wind projects in Scotland
    Scotland is a world leader in the deployment of floating wind with two of the world's largest operational floating wind farms, Hywind Scotland and Kincardine.Floating Wind In Scotland · An Advantageous History · Floating Wind - The Big...Missing: facts | Show results with:facts<|control11|><|separator|>
  7. [7]
    [PDF] Hywind Demo - Equinor
    May 22, 2008 · full scale floating wind turbine. • StatoilHydro invests approximately 400 MNOK. • Start up in 2009. • Chosen vendors: – Siemens. – Technip.
  8. [8]
    World's first floating wind farm: the key to broadening wind power's ...
    Mar 13, 2016 · In 2009, Statoil built the world's first floating, full-scale wind turbine offshore Norway, the Hywind Demo. Statoil says it expects a 60 ...
  9. [9]
    Statoil to build the world's first floating wind farm: Hywind Scotland
    Nov 3, 2015 · The decision triggers investments of around NOK 2 billion, realizing a 60-70 percent cost reduction per MW from the Hywind demo project in ...
  10. [10]
    Statoil Sets Aside EUR 214 Million for Hywind Scotland Pilot Park
    Nov 3, 2015 · The decision triggers investments of around NOK 2 billion (EUR 214 million), realizing a 60-70 percent cost reduction per MW from the Hywind ...
  11. [11]
    Statoil introduces partner in Hywind Scotland - equinor.com
    Jan 17, 2017 · Statoil has agreed to divest 25% of its assets in Hywind Scotland pilot park, the world's first floating wind farm, to Masdar.Missing: 2015 | Show results with:2015
  12. [12]
    [PDF] Hywind Scotland Pilot Park Project - EIA Scoping Report
    Oct 1, 2013 · Under these Acts the Scottish Government is required to prepare a National Marine Plan for Scottish Territorial. Waters and the offshore zone ...
  13. [13]
    [PDF] Hywind Scotland Pilot Park
    4.1 Introduction. 4-1. 4.2 Project timescale. 4-1. 4.3 Hywind Scotland Pilot Park Project components included in this EIA – offshore.
  14. [14]
    Hywind Scotland receives final consent - updated
    Nov 2, 2015 · As a result of the government approval, Statoil has made the final investment decision for the project to be built. The Hywind floating ...Missing: joint 2016
  15. [15]
    Scottish Government approves Statoil's Hywind project - Energy Voice
    Nov 2, 2015 · The Scottish Government has today granted the firm a marine licence, allowing construction work on the huge structures to begin. It will become ...
  16. [16]
    Statoil Sets Aside EUR 214 Million for Hywind Scotland Pilot Park
    Nov 3, 2015 · The decision triggers investments of around NOK 2 billion (EUR 214 million), realizing a 60-70 percent cost reduction per MW from the Hywind ...
  17. [17]
    The Crown Estate Okays Hywind Scotland Seabed Lease
    May 16, 2016 · The project secured consent from Marine Scotland last October and Statoil has taken the final investment decision to construct the project.Missing: joint | Show results with:joint
  18. [18]
    Innovation in world´s largest floating wind farm by Siemens Gamesa ...
    Jun 26, 2017 · Five Siemens Gamesa turbines of Six-Megawatt-class have now been installed on floating foundations in Stord, Norway, at the 30 MW “Hywind ...Missing: specifications | Show results with:specifications
  19. [19]
    The case of Hywind farm wind turbines - Windtech International
    Sep 10, 2024 · The five 6 MW Siemens SWT-6.0-154 in the first floating wind farm have a rotor diameter of 154 metres, they do not have a gearbox and use a permanent magnet ...
  20. [20]
    NAVANTIA and WINDAR award supply of SPAR type floating ...
    Jun 25, 2018 · The joint venture Navantia-Windar has been awarded by Statoil's subsidiary Hywind Scotland Ltd, the supply of 5 spar-type floating foundations for 6 MW ...
  21. [21]
    Navantia shapes Hywind Scotland - reNews
    Feb 22, 2017 · The work is being carried out at Navantia's Fene shipyard in Spain. The demo project will be located 30km off the coast of northeast Scotland.
  22. [22]
    [PDF] HYWIND SCOTLAND - Equinor
    • Hywind Scotland is owned by Statoil (75%) and Masdar. (25%). • Hywind is the world's first commercial floating wind farm. • Located at Buchan Deep, 25 km off ...
  23. [23]
    Works on Hywind Scotland Foundations in Full Swing
    Nov 24, 2016 · Navantia started welding together the first blocks for the first Hywind Scotland floating foundation at the assembly area of its Fene yard ...
  24. [24]
    First Hywind Scotland Towers Head to Norway | Offshore Wind
    Mar 6, 2017 · The turbine towers have a height of 83 metres with a diameter of 7.5 metres at the base and 4.2 metres at the top, where the turbines will be ...Missing: hub | Show results with:hub
  25. [25]
    Turbines return to world's first commercial floating wind farm after ...
    Aug 20, 2024 · Hywind Scotland consists of five Siemens Gamesa SWT-6.0-154 turbines ... power production during the fall,” the spokesperson said. Floating ...Missing: specifications | Show results with:specifications
  26. [26]
    Meet the brains behind the brain of Hywind - Equinor
    Oct 13, 2024 · The Hywind Demo captivated people's imaginations with its gravity-defying design. It was simple, elegant, and it borrowed the floating spar ...Missing: origins | Show results with:origins
  27. [27]
    Siemens SWT-6.0-154 - Manufacturers and turbines - The Wind Power
    The Siemens SWT-6.0-154 has a rated power of 6,000 kW, a 154m rotor diameter, 3 blades, 360 ton nacelle, 4 m/s cut-in wind speed, and 13 m/s rated wind speed.
  28. [28]
    [PDF] Intec Formal Report Template - Energy NL
    Figure 7-3: Installation of Hywind Scotland Turbine by Floating Semisubmersible Crane Vessel. Saipem S7000 (Credit: Saipem). Most floating offshore wind ...
  29. [29]
    [PDF] SeaShare: Hywind Static Fishing Gear Trials - Equinor
    Consideration of weather and sea conditions played a major role in the safety of the trial and influenced the decision to enter the wind farm area and deploy ...<|control11|><|separator|>
  30. [30]
    [PDF] Geotechnical Support Services - Hywind Scotland Offshore Pilot Park
    The export cable corridor will be 25 to 30 km in length connecting to a landfall in the Peterhead area. ... > Hywind Scotland Export Cable Route– nominal 1000m ...
  31. [31]
    [PDF] Design of Mooring Systems for Large Floating Wind Turbines in ...
    The natural periods of the Hywind Scotland mooring system is found in table 8. ... Table 9.3 shows the results from the polyester mooring analysis for ...
  32. [32]
    Mooring design for floating wind turbines: A review - ScienceDirect
    This paper reviews state-of-the-art mooring designs for floating wind turbines, addressing key aspects such as floater-mooring interactions, material and ...Missing: standardized | Show results with:standardized
  33. [33]
    Equinor and ORE Catapult collaborating to share Hywind Scotland ...
    Nov 28, 2019 · The data shared will include environmental data, motions of the floating wind turbine and loads in the mooring system. POD was enabled through ...Missing: details | Show results with:details
  34. [34]
    [PDF] Hywind Scotland Pilot Park Project Plan for Construction Activities ...
    Dec 31, 2017 · The turbines will have a hub (centre) height of 97,8 m above sea level and a height to tip of rotor blade of 175 m, with a draught of 78 m.
  35. [35]
    Hywind Pilot Park, Aberdeenshire - Power Technology
    Jun 29, 2018 · ... Peterhead in Aberdeenshire, Scotland. ... The Hywind Pilot Park wind farm extends over 4km² area in water depths between 95m and 120m.Missing: selection | Show results with:selection
  36. [36]
    [PDF] Hywind Scotland Pilot Park Decommissioning programme - Equinor
    May 3, 2022 · - 5 floating Hywind units that consist of a 6 MW turbine on a floating spar buoy. - 15 mooring lines and 15 anchors (three per turbine). - 4 ...
  37. [37]
    [PDF] Hywind Scotland Pilot Park
    ... buoy (SPAR2) concept, the Hywind Scotland WTG Units consist of a steel tower ... height. 80 – 104 m above MSL. Rotor diameter. 154 m. Height to tip of ...
  38. [38]
    [PDF] Hywind Buchan Deep Metocean Design Basis RE2014-002
    Dec 5, 2013 · Design wave heights for selected return periods. ... Figure 4.2 shows estimates of 50-year return period depth-averaged hourly-mean storm surge.
  39. [39]
    All Hywind Scotland Floating Turbines Now In Place | Offshore Wind
    Aug 16, 2017 · The first electricity from the world's first floating wind farm is expected to be produced in October. The 30MW Hywind Scotland Pilot Park ...Missing: multi- array
  40. [40]
    Statoil Testing Hywind Scotland Floating Turbines | Offshore Wind
    Sep 18, 2017 · The testing is being carried out prior to the floating wind farm's full commissioning, scheduled for October.
  41. [41]
    World's first floating wind farm has started production - equinor.com
    Oct 18, 2017 · Linked to the Hywind Scotland project Statoil and partner Masdar will also install Batwind, a 1MWh Lithium battery storage solution for offshore ...Missing: 2015 | Show results with:2015
  42. [42]
    [PDF] Hywind Scotland Pilot Park
    Final Investment Decision: 2015. Onshore Construction: 2015/2016. Offshore Construction: 2016/2017. Final commissioning: 2017. About Statoil. Statoil is an ...
  43. [43]
    Q&A: How viable are floating offshore windfarms? - Carbon Brief
    Jul 27, 2017 · For comparison, the typical capacity factor for a typical offshore wind farm during the winter is 45-60%, according to Statoil. Statoil and its ...
  44. [44]
    Floating wind farms just became a serious business - Quartz
    Hywind even beat out the average capacity of fossil fuel plants. Over the course of a year, it's capable of generating 135 GWh of clean electricity, sufficient ...Missing: annual | Show results with:annual
  45. [45]
    World's biggest floating wind farm to be built in Scotland
    Hywind Pilot Park, which will be constructed by energy company Statoil ... annual generating capacity of 135 GWh of electricity. 4134. The North Sea has ...
  46. [46]
    Heavy maintenance completed on Hywind Scotland floating offshore ...
    Oct 9, 2024 · It supplies power to approximately 35,000 UK homes and operates with a capacity factor of 54%.
  47. [47]
    World's First Floating Wind Farm Outdelivers - offshoreWIND.biz
    Feb 15, 2018 · The 30MW Hywind Scotland, the world's first commercial-scale floating wind farm, performed better than expected in its first three full months in production.
  48. [48]
    The world's first floating wind farm is already exceeding expectations
    Mar 2, 2018 · Hywind Scotland's high availability has ensured that the volume of electricity generated is substantially higher than expected." Offshore wind ...
  49. [49]
    Equinor and ORE Catapult collaborating to share Hywind Scotland ...
    Nov 28, 2019 · Five floating wind turbines, total installed capacity of 30 MW; Average capacity factor of 56% over the first two years of operation. About ...
  50. [50]
    World's First Floating Wind Farm Exceeds Expectations
    A typical capacity factor for a bottom fixed wind farm is 45-60%. By comparison, the Hywind Scotland achieved an average of 65% during November, December, and ...
  51. [51]
    Hywind Scotland remains the UK's best performing offshore wind farm
    Mar 23, 2021 · With an average capacity factor of 57.1% in the twelve month period to March 2020, the floating offshore wind farm set a new record in the UK.Missing: annual GWh
  52. [52]
    How Miros data supports the world's first floating offshore wind farm
    It is operated by Hywind (Scotland) Limited, a joint venture of Equinor (75%) and Masdar (25%). The farm, which has been in operation since 2017, has five ...
  53. [53]
    Revealing inflow and wake conditions of a 6 MW floating turbine
    Oct 12, 2023 · We investigate the characteristics of the inflow and the wake of a 6 MW floating wind turbine from the Hywind Scotland offshore wind farm.
  54. [54]
    Floating offshore wind emerges on the horizon - DNV
    Operating since Autumn 2017, Hywind Scotland has shown promising results with a capacity factor well over 50%. This indicates floating motions do not have a ...Missing: 50-60% | Show results with:50-60%<|separator|>
  55. [55]
    SCADA system for floating offshore wind farms - Origo Solutions
    Origo Solutions commissioned, designed, produced and tested the supervisory control and data acquisition (SCADA) system for Hywind Scotland Pilot Park.
  56. [56]
    The world's largest floating offshore wind farm officially opened
    Aug 23, 2023 · Adjusted for price developments since 2016/2017, the investment cost for Hywind Tampen is about 35 percent lower per installed MW.<|control11|><|separator|>
  57. [57]
    Technology legitimation and strategic coupling: A cross-national ...
    Regarding Hywind Scotland, Equinor utilized its existing networks with most of the suppliers also involved in supplying the Hywind Demo (see Authors 2019b).
  58. [58]
    Equinor Funding Shallow-Water Floating Wind Mooring Project in US
    May 14, 2021 · The Genesis scope focuses on floating platform and mooring system design in water depths ranging from 60 to 100 metres. The company will develop ...Missing: adopted | Show results with:adopted
  59. [59]
    Influence of wakes and atmospheric stability on the floater ...
    Aug 25, 2020 · In this paper, we have presented measurements of floater responses from the Hywind Scotland wind farm, both for turbines in free wind and in wake and for ...
  60. [60]
    Floating wind turbines structural details fatigue life assessment
    Sep 28, 2023 · Novel deconvolution extrapolation method has been introduced in this study, and it was shown to be able to accurately predict long-term fatigue damage.
  61. [61]
    [PDF] Hywind Scotland Pilot Park Project – Assessment of socio-economic ...
    A breakdown of the indirect impact potential on capital spend in and jobs creation in the supply chain during the construction and installation phase of the ...
  62. [62]
    4. As-is analysis - Scenario mapping for offshore renewable energy ...
    Nov 3, 2022 · Hywind Scotland will generate £68 million direct, indirect and induced GVA in Scotland over the lifetime of the wind farm, of which £26 million ...
  63. [63]
    [PDF] Hywind Scotland - Masdar
    Masdar has a 25 per cent stake in the project, along with lead operator Equinor, which owns 75 per cent. The facility consists of five 6MW floating Siemens wind.
  64. [64]
    Accelerating Scotland's leadership in floating offshore wind | The ...
    Scotland is a leading market for floating offshore wind, home to the world's first floating wind pilot park, Hywind Scotland and soon to host the world's ...
  65. [65]
    [PDF] Floating Offshore Wind Manufacturing
    Established by the ORE Catapult to develop an internationally recognised initiative to reduce the cost of energy from floating wind. The. Centre will accelerate ...