Fact-checked by Grok 2 weeks ago

Victorian Desalination Plant

The Victorian Desalination Plant is a seawater desalination facility situated near in southeastern , , capable of producing up to 150 gigalitres of per year, sufficient to meet approximately one-third of greater 's annual demand when operating at full capacity. Commissioned on 17 December 2012 following announcement in 2007 and construction commencing in 2009, the plant was developed through a public-private partnership with the Aquasure consortium to diversify water sources amid the Millennium Drought and anticipated , integrating with an 84-kilometre to deliver water to , , and surrounding regions. Employing energy-efficient technology powered in part by , it draws seawater from via intake tunnels and discharges brine through outlet structures designed to minimize marine impacts, while the site incorporates environmental mitigation measures including a 225-hectare ecological reserve, constructed wetlands, and Australia's largest living to support and reduce operational noise. The project, with a capital construction cost of $3.5 billion and a total net present cost of $5.7 billion, has delivered during dry periods—contributing 16 gigalitres in the first months of 2025 amid low rainfall—but has drawn scrutiny for fixed availability payments totaling hundreds of millions annually even during standby modes when catchment inflows suffice, resulting in nominal lifetime costs projected at $23.9 billion passed through to water users.

Background and Rationale

Historical Context of Water Scarcity

Victoria has a long history of driven by variable rainfall patterns, with significant droughts recurring in the 1990s and intensifying during the Millennium Drought from 1997 to 2009, a period of 13 consecutive years of below-average that severely reduced runoff across southeastern Australia. This event marked the most prolonged dry spell in instrumental records for the region, with cumulative rainfall deficits leading to critically low streamflows in key catchments supplying urban centers. Melbourne's water infrastructure historically relied on surface water harvested from rainfall-dependent, protected catchments, primarily in the basin and adjacent systems, which provide the bulk of supply for the city's population exceeding 4 million without significant contributions from or inter-basin transfers. These catchments exhibit high sensitivity to variability, where inflows to reservoirs can decline disproportionately—a 10% drop in rainfall often translates to 20-30% reductions in runoff due to increased , deficits, and reduced saturation excess overland flow. By mid-2007, total storage levels across Melbourne's reservoirs had fallen to around 25% of capacity, equivalent to less than one year's demand under normal usage. The 2006/07 water year exemplified this vulnerability, recording the lowest inflows to Victorian storages on record, underscoring the limitations of expanding dams or enhancing as short-term mitigations against multi-year dry sequences. Such empirical patterns demonstrated the causal risks of over-reliance on rainfall events, prompting recognition that diversified, climate-independent sources were essential to buffer against inherent hydrological intermittency rather than attempting to predict or adapt solely through .

Proposal and Initial Justification

The Victorian government announced its intention to develop a desalination plant near on 19 June 2007, as part of the Securing Our Water Future Together plan, to produce up to 150 gigalitres (GL) of annually and thereby augment Melbourne's supply by approximately 50 percent under average conditions. This decision came amid the Millennium Drought (2001–2009), recognized as the most severe on record for southeast , with Melbourne's storages at 29 percent capacity and reservoirs having declined significantly due to consecutive years of below-average rainfall and record-low inflows into catchments in 2006–07. The primary justification centered on the vulnerability of Victoria's rainfall-dependent catchments, which supply over 80 percent of Melbourne's and exhibited high to climatic variability, as evidenced by hydrological records showing inflows to storages at historic lows during the period. was positioned as a drought-proof alternative, drawing from to deliver a reliable baseline supply independent of weather patterns and catchment yields, thereby mitigating risks of shortages during prolonged dry spells that demand management measures alone could not fully address. assessments highlighted that traditional sources, reliant on variable southeast , had proven inadequate for sustaining urban demand amid the 's intensity, with storages approaching critically low levels that threatened for the region's approximately 3.6 million residents at the time. Alternative options, such as new , were constrained by limited suitable sites in Victoria's and stringent environmental protections, while programs and initiatives, though effective for baseline conservation, fell short in addressing peak summer demands or multi-year deficits observed in hydrological data from the affected catchments. The proposal emphasized long-term resilience for projected population growth, with Melbourne's urban area expected to expand substantially by mid-century, underscoring desalination's role in diversifying supply sources beyond weather-vulnerable reservoirs.

Planning and Approvals

Environmental Effects Studies

The Environment Effects Statement (EES) for the Victorian Desalination Project was prepared in 2008 by the Department of Sustainability and Environment's Capital Projects Division, evaluating potential environmental impacts under Victoria's Environment Effects Act 1978. This comprehensive assessment included technical appendices on structures, plant operations, routes, and infrastructure, focusing on verifiable risks such as discharge, alteration, and amenity effects. Public exhibition occurred from July to September 2008, followed by an independent inquiry report on December 4, 2008, which analyzed over 200 submissions and expert evidence. Marine studies emphasized brine concentrate discharge into Bass Strait, with hydrodynamic modeling using two-dimensional Bass Strait and Bays (BAS) models to simulate plumes and dispersion. Near-field and far-field plume analyses predicted rapid dilution of hypersaline effluent due to strong currents and wind-driven mixing, limiting increases to less than 1% beyond 500 meters from the outfall under operational scenarios of up to 200 gigalitres annual capacity. surveys of benthic , assemblages, and epibenthic communities in the intake and discharge zones indicated resilient ecosystems, with no endemic at risk of significant long-term population declines from or impingement, as supported by ecotoxicity testing showing primary effects attributable to rather than chemical additives. Terrestrial assessments documented habitat disruption at the Wonthaggi plant site, including surveys of native grasslands and coastal dunes hosting species like the hooded plover, predicting temporary clearance of 120 hectares but no irreversible loss to threatened communities through offset planning. Visual and impact studies modeled plant structures' visibility from coastal viewpoints and construction propagation, forecasting localized effects within 2 kilometers, mitigated by and design but acknowledged as unavoidable during peak building phases. An independent expert panel reviewed marine ecological risks in October 2008, highlighting discharge and intake as primary concerns but affirming model predictions of negligible far-field impacts given Bass Strait's high-energy environment. The EPA Victoria submitted concerns on brine toxicity and monitoring adequacy but concurred with the EES findings of no long-term irreversible damage, recommending conditions including real-time salinity controls and seasonal discharge restrictions to align with lower summer stratification risks. The Minister for Planning's assessment in January 2009 endorsed project feasibility, citing empirical modeling and surveys as evidence that effects were manageable without prohibiting approval.

Site Selection and Location

The Victorian Desalination Plant is situated near in the Bass Coast Shire of , , approximately 90 km southeast of and 3–5 km west of the town center, on cleared agricultural land adjacent to and east of the Powlett River estuary. The site's coordinates are approximately 38°35′17″S 145°31′34″E. Site selection occurred during the project's planning phase in 2007–2009, following Water's feasibility study and government tenders, with chosen over alternatives like sites near Kilcunda for its balance of logistical and environmental attributes. Primary factors included direct coastal access to Bass Strait's deep s (with structures 1–2 km at depths up to 33 m), enabling efficient sourcing and dispersal while minimizing of or larvae. The rural positioning, over 20 km from the Ramsar wetland and avoiding urban centers like Cardinia, reduced community disruption and preserved recreational coastal uses behind protective dunes. Geological suitability further supported selection, with flat coastal plains, stable dune systems resistant to storm surges, and sandy preferable to reefs for tunneling (15 m below seabed) and routing toward Melbourne's supply at Berwick, 84–85 km away. Proximity to existing power infrastructure, including the Woolamai Terminal Station and planned 66–220 kV lines, facilitated the plant's 133 MW annual needs without extensive new grid development. The site also circumvented high-biodiversity zones, maintaining 50 m buffers from sensitive / habitats and minimizing impacts on national parks like Bunurong. Post-construction integration emphasized landscape rehabilitation, including dune and restoration, low-profile structures with green roofs, and compatibility with public access areas near Williamsons Beach to blend the facility with natural surroundings.

Project Execution

Contracting and Consortium

The procurement for the Victorian Project followed the Partnerships Victoria framework, utilizing a competitive process to select a private capable of handling , construction, financing, and long-term operations while transferring significant risks—including cost overruns and performance failures—from the to private participants. This approach prioritized bidder proposals that demonstrated efficiency gains through innovative engineering and integrated . On 30 June 2009, the Victorian Government awarded the contract to the under a public-private partnership (PPP) structure. , comprising Degrémont (a Suez Environnement subsidiary, now associated with ), Thiess Pty Ltd, and financial backers, was selected from competing bids including BassWater (led by John Holland and ). The consortium's proposal highlighted advanced desalination techniques and commitments to procurement for offsetting plant operations, aligning with tender criteria for technological innovation and . The agreement adopted a design-build-finance-operate-maintain (DBFOM) model with a fixed-price commitment for capital delivery, enabling the to avoid direct upfront funding while securing performance guarantees. AquaSure fully financed the project and assumed operational risks, with contractual provisions allowing buy-back options during the term and mandatory handover of the assets—debt-free and fully operational—after the 30-year concession period ending in 2040. AquaSure subcontracted operations and maintenance to the Degrémont Thiess Services , leveraging specialized expertise in and .

Design and Construction Timeline

Construction of the Victorian Desalination Plant commenced on 30 September 2009, following financial close earlier that month and contract award to the AquaSure consortium in 2009. The initial phases focused on site preparation and early works, including the laying of the first section of the 84 km transfer pipeline at Clyde North on 4 2010. Major engineering milestones included the start of inlet tunnel boring on 27 July 2010 using tunnel boring machines to excavate the 1.2 km intake tunnel approximately 15 meters below the seabed. The outlet tunnel, measuring 1.5 km, was completed by 16 March 2011, demonstrating efficient progress in marine infrastructure despite challenging coastal geology. Pipeline installation advanced steadily, with the full 84 km transfer line to Cardinia Reservoir finalized on 24 October 2011, enabling connection to Melbourne's water grid. Power infrastructure, including a dedicated substation, was integrated concurrently to support the plant's high-energy demands. The plant produced its first samples of on 6 September 2012, marking successful testing of the process. began flowing into Cardinia on 26 September 2012, followed by commercial acceptance on 30 November 2012. Final commissioning was achieved on 17 December 2012, completing construction within the 36-month schedule and under the $3.5 billion budget cap, notwithstanding adverse weather and industrial conditions. No significant delays arose from regulatory approvals or geological issues beyond routine project challenges.

Technical Features

Desalination Process and Capacity


The Victorian Desalination Plant utilizes a two-pass reverse osmosis (RO) desalination process to convert seawater into potable water, leveraging semi-permeable membranes to separate salts and contaminants under high pressure. Seawater is extracted from Bass Strait via a 1.5 km intake tunnel positioned about 30 meters below the seabed to limit intake of fish eggs and larvae, with flow velocities maintained at approximately 3.5 km per hour for a transit time of around 20 minutes.
Pre-treatment of the intake involves chemical dosing, , , clarification, and dual-media to eliminate , organic matter, and microorganisms, thereby safeguarding membrane integrity and optimizing performance. The treated then undergoes the first pass to remove the majority of dissolved salts, followed by a second pass for further purification to meet stringent standards. This configuration achieves a water recovery rate of roughly 50%, minimizing volume relative to output. At full operational capacity, the plant produces 444 megalitres of desalinated water per day, equating to 150 gigalitres annually, with provisions for expansion to 200 gigalitres per year through additional trains and . Concentrated reject is returned to the via a dedicated 1.2 outlet terminating in a multi-port diffuser array, engineered to rapidly dilute and disperse the discharge plume over a broad area to reduce ecological stress on benthic habitats. This rainfall-independent process enables flexible, demand-driven production, scaling output to address conditions without reliance on variable catchment inflows.

Pipeline and Power Infrastructure

The Victorian Desalination Plant delivers desalinated water to 's supply system via an 84-kilometer underground extending from the facility to the Cardinia Reservoir. The features a of 1.93 and incorporates a transfer pump station at the plant site, a booster pump station along the route, and surge protection facilities to handle pressure variations and maintain flow stability up to a peak design rate of 444 megalitres per day. A dedicated 87-kilometer underground high-voltage , co-located with the pipeline , provides the plant with approximately 90 megawatts of through a 220 kV connection, ensuring operational reliability independent of broader grid fluctuations. Upon reaching the Cardinia Reservoir, the desalinated water integrates into the Melbourne Water grid, enabling blending with conventional sources to meet regional demands while preserving system redundancy.

Economic Aspects

Capital and Operating Costs

The of the Victorian Desalination Project was fixed at $3.5 billion in 2009 Australian dollars under the public-private partnership contract, encompassing the design, construction, and commissioning of the plant, the 84-kilometer transfer pipeline to Melbourne's water grid, and supporting power infrastructure including a dedicated . This amount was fully financed by the private-sector AquaSure consortium, with the bearing no upfront but committing to long-term payments. Early estimates placed the at approximately $2.9 billion, but revised assessments by the Victorian Auditor-General in 2010 indicated potential overruns exceeding $2 billion due to scope expansions and market conditions, though the allocated construction risk to the private partner and incorporated penalties such as $419 million withheld for commissioning delays. Operating and standby costs form part of the project's total net present cost (NPC) of $5.7 billion (2009 dollars), which spans 30 years and 1 month and includes , , and facility readiness irrespective of water production levels. These are funded through fixed monthly payments to AquaSure, ensuring the plant remains operational in standby mode even during periods of low demand, with nominal payments escalating to $23.9 billion over the contract term due to and financing charges. Audits, including those by the Victorian Auditor-General, have noted incremental nominal cost increases—such as $993 million higher in 2012–13 projections—attributable to financing and operational variables, yet the PPP model's independent expert verification and performance-based incentives mitigated taxpayer exposure to private-sector inefficiencies. Savings of $1.2 billion in nominal terms were realized through measures like debt refinancing ($187 million) and power supply renegotiations ($625 million). The fixed payment structure provides contractual safeguards against usage variability, as standby obligations persist to guarantee drought resilience, contrasting with potential economic disruptions from unmitigated water shortages; for instance, prior restrictions during the Millennium Drought imposed compliance costs on households and agriculture estimated in the hundreds of millions annually based on reduced productivity and enforcement.

Financing Model and Long-Term Value

The Victorian Desalination Plant operates under a model, with the financing, designing, constructing, and maintaining the facility for a 30-year period starting from award in 2009. This structure shifted the upfront of approximately AUD 3.5 billion from the to private investors, who raised and to fund development, thereby avoiding immediate taxpayer outlay while spreading payments over the term. Risk allocation favored the bearing design, construction, and operational performance s, with penalties for non-availability, while the assumed volume risk through contracted payments. Contract payments to AquaSure comprise two elements: a fixed "" component to guarantee plant availability and readiness to produce up to 150 gigalitres annually, and a variable component scaled to actual volumes ordered by . The security payment persists regardless of usage, ensuring the asset remains operational as a hedge, with total annual payments averaging around AUD 600 million in early years, funded via tariffs and government allocations. This output-contingent variable element aligns incentives for efficiency but does not eliminate fixed costs, as the must maintain standby capability; critiques frame these as an " premium" against rainfall deficits, given Victoria's historical catchment variability, where even modest rainfall declines can halve inflows. In terms of long-term value, the has delivered by a portion of Melbourne's from rainfall-dependent reservoirs, enabling flexible augmentation during low-storage periods, such as the 50 gigalitres ordered for 2025-26 amid below-average inflows. By 2025, the plant's cumulative output, including intermittent operations since commissioning in 2017, has exceeded 300 gigalitres, averting potential restrictions that could disrupt economic activity in a reliant on stable for and . underscores net benefits: 's climate-independent yield mitigates GDP losses from shortages—estimated in prior droughts at billions in forgone productivity—outweighing standby expenditures by providing scalable capacity without equivalent delays. This hedging against patterns, where runoff sensitivity amplifies dry spells, positions the investment as a prudent for long-term , despite opportunity costs in alternative uses of funds.

Energy and Resource Use

Power Consumption Details

The Victorian Desalination Plant requires an average power input of 90 MW to operate at full capacity of 150 gigalitres per year. This demand is met through a dedicated 220 kV high-voltage underground connected to . At peak output, daily energy consumption reaches approximately 2,160 MWh, reflecting continuous operation of processes including pretreatment, high-pressure pumping, and energy recovery systems. Specific energy consumption for the plant's seawater reverse osmosis technology typically falls in the range of 3-5 kWh per of , higher than traditional methods like pumping (often under 1 kWh/m³) due to the thermodynamic challenges of salt- separation, though modern devices mitigate this to levels competitive with large-scale alternatives. Annual energy use at full capacity would approximate 788 GWh, calculated from continuous 90 MW draw over 8,760 hours, though actual figures vary with production scaling. Power demand exhibits variability tied directly to output levels, as the plant operates in a load-following mode: partial production (e.g., % ) reduces proportionally, with pretreatment and adjustments enabling flexible without fixed baseload penalties. Empirical data from similar facilities confirm that energy efficiency improves marginally at higher loads due to optimized , but overall remains elevated compared to non-desalinated sources, underscoring the for drought-independent supply reliability.

Renewable Energy Offset and Efficiency

The Victorian Desalination Plant offsets 100% of its operational electricity consumption through the purchase and surrender of renewable energy certificates (RECs), primarily sourced from wind and solar generation via contracts with AGL Energy. This arrangement covers up to 860 GWh annually, equivalent to the plant's and pipeline's full-capacity demand of approximately 90 MW for producing 150 gigalitres of water per year. To enhance , the plant employs advanced pressure exchanger devices from Energy Recovery, Inc., such as the series, which recover energy from high-pressure streams during with efficiencies reaching up to 98%. These devices minimize power requirements by transferring hydraulic energy from the concentrate to incoming , reducing overall consumption compared to traditional turbine-based recovery systems. However, REC offsets function as a financial to support renewable generation elsewhere on rather than directly supplying the plant's energy needs or altering its physical draw from Victoria's network, which historically relies heavily on coal-fired sources. This offset approach enables a claim for the plant's operations but does not mitigate the real-time grid impacts or the process's inherent , which remains higher than alternatives like or in non-drought scenarios. In contrast, powering the facility without offsets would result in emissions aligned with the state's average grid intensity of around 0.8-1.0 kg CO2 per kWh during peak periods, underscoring that offsets shift rather than eliminate environmental costs.

Environmental Considerations

Impacts on Marine and Terrestrial Ecosystems

The discharge of brine from the Victorian Desalination Plant results in a salinity increase of ≤1 PSU above ambient levels within the designated mixing zone (180 m radius), achieved through a minimum initial dilution factor of 30:1 via multi-port diffusers, with 95% compliance during operational monitoring periods such as SP9-SP11 post-2012 commissioning. Quarterly ecological surveys at 20 inshore and offshore sites, using methods like photoquadrats and settlement plates, have detected no substantial changes in reef community composition, benthic , or larval recruitment beyond the mixing zone, indicating no significant adverse impacts on . Seawater intake operations, designed with screens and velocity caps to minimize , have shown negligible effects on and larval stages, as evidenced by baseline and ongoing inshore monitoring of assemblages with no detectable operational perturbations outside expected variability. Terrestrial ecosystems experienced disturbance during construction, including vegetation clearing and soil disruption across the plant site and immediate access areas, affecting native coastal scrub and woodland habitats within the Bass Coast region; the project footprint necessitated planning for approximately 225 hectares to address these impacts. No long-term terrestrial ecological has been reported from post-construction assessments tied to plant operations. The Operational Marine Monitoring Program, aligned with EPA Victoria operating licence conditions (e.g., OL_G2, OL_DW3), has confirmed ongoing compliance through in-plant tracking, diffuser performance verification, and ecological endpoints from 2012 onward, with no Tier 2 or 3 environmental warnings triggered.

Mitigation and Restoration Efforts

The Victorian Desalination Project incorporated extensive terrestrial as part of its environmental offset program, rehabilitating 225 hectares of surrounding land—one of the largest such initiatives in Victoria's history. This involved planting over 3.5 million native plants, including 150,000 advanced tube stock specimens, to restore coastal dunes, wetlands, and degraded habitats, thereby enhancing and screening the facility from the landscape. A 26,000 m² extensive , the largest in upon completion in 2012, covers the main plant building with indigenous coastal vegetation selected for and ecological compatibility, supporting pollinators and species while aiding regulation and management. Public access was integrated via 6-8 km of walking and cycling trails through the ecological reserve, featuring interpretive signage, viewing decks, and restored vantage points that promote habitat connectivity and community appreciation of the rehabilitated ecosystems without compromising operational security. Marine mitigation relies on the outfall's multi-port diffuser system, engineered for high-velocity discharge and rapid initial mixing, achieving dilution of brine concentrate at ratios of 1:120 within 50 meters via specialized nozzles, which disperses hypersaline effluent and reduces risks of benthic habitat alteration in the receiving waters. Physical modeling validated this configuration to optimize near-field dilution under varying currents, minimizing plume footprint and localized salinity gradients that could affect biota. Ongoing operational monitoring of discharge plumes and receptor sites assesses long-term efficacy, with adjustments mandated if thresholds for ecological integrity are exceeded.

Operational History

Commissioning and Early Performance

The Victorian Desalination Plant achieved commissioning in December 2012, following the production of its first samples of on 6 September 2012, which met the required standards under the 30A Commissioning Approval. Construction and reliability testing were finalized on 19 December 2012, marking the completion of contractual milestones and confirming the plant's operational readiness to produce up to 150 gigalitres of desalinated water annually. During initial operations, the plant demonstrated technical reliability through successful testing phases, with early water production aligning with design specifications for processes that ensured low salinity and compliance with guidelines. However, Melbourne's reservoirs reached 81% capacity by late due to post-Millennium Drought rainfall recovery, prompting immediate transition to standby mode without a full production ramp-up for public supply. From 2015 to 2017, the facility operated in preservation or care-and-maintenance mode amid sustained wet conditions that further replenished levels, maintaining integrity while minimizing use in the absence of orders. This period underscored the plant's design flexibility for intermittent activation, with no reported early operational failures despite limited runtime.

Usage Patterns and Reliability

The Victorian Desalination Plant operates on an intermittent basis, activated primarily during periods of low rainfall and declining water storages to supplement Melbourne's supply system. In March 2020, amid forecasts of below-average inflows, the Victorian Government placed a 125 gigalitre (GL) order for the 2020-21 supply year to bolster security for the region's growing population. Similar orders were issued in prior years, including initial production starting in 2016 and continued activations through to March 2022, reflecting targeted deployment rather than continuous operation. By April 2025, cumulative production reached 455 GL, representing a fraction of the plant's 150 GL annual capacity but aligned with episodic drought-response needs. The plant has demonstrated high reliability in delivery, with no recorded failures in meeting ordered volumes during activation periods. Initial reliability testing in 2012 confirmed sustained full-capacity output of over 400 megalitres per day for 30 consecutive days, producing high- compliant with standards. Subsequent operations, including the 2020-21 order and 2022 production, integrated seamlessly into the broader grid via the transfer , blending desalinated without disrupting supply or requiring special . This performance underscores the facility's role as a dependable , independent of rainfall variability, which mitigates risks of by providing scalable —up to one-third of Melbourne's annual demand—precisely when catchment yields falter.

Controversies and Debates

Public and Political Opposition

Public opposition to the Victorian Desalination Plant centered on local impacts in the area, including concerns over visual alterations to the landscape, increased heavy vehicle traffic on rural roads, and the perceived extravagance of a $3.1 billion expenditure during the 2008 global . Residents formed groups such as Your Water Your Say, which organized public meetings drawing 500 attendees on June 24, 2008, following a prior gathering of 700 people, to voice fears of and community disruption from construction activities. Protests escalated with rallies of about 100 people in on September 3, 2008, and direct actions like fence-jumping at the site in August 2009, reflecting resistance rooted in not-in-my-backyard sentiments and grievances over consultation processes. Political criticism emanated primarily from the Australian Greens and elements within Labor circles, emphasizing opposition to the public-private partnership model and escalating costs, while downplaying the variability of southeastern Australia's amid recurring droughts. The Greens, through affiliated environmental organizations like Watershed Victoria, argued that should serve as a rather than a priority, prioritizing and sustainable alternatives over energy-intensive . Victorian Labor had rejected calls for the plant prior to the 2006 state election, deeming it unnecessary, but proceeded under Premier amid the millennium drought, drawing intra-party and opposition scrutiny for risks and fiscal burdens passed to consumers via bills. These critiques often overlooked of rainfall unreliability, as Victoria's catchments had experienced severe drawdowns, with storage levels dropping below 30% in the mid-2000s. Counterarguments highlight that such opposition, while delaying approvals, failed to negate the plant's underlying rationale, as subsequent dry spells necessitated its operation to buffer reliance—water was first ordered in 2016 during post-millennium concerns and again in April 2025 amid easing dry conditions, supplying up to one-third of Melbourne's demand and demonstrating resilience against hydrological volatility independent of short-term rainfall patterns. In 2008, the community group Your Water Your Say Inc. initiated legal proceedings in the against the Minister for the Environment, Heritage and the Arts, challenging the adequacy of the referral submitted under the Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act) for the Victorian Desalination Plant project. The challenge centered on procedural grounds, alleging insufficient detail in the referral regarding potential environmental impacts, including and effects from the plant's construction and operation, which the group argued undermined in the approval mechanism. Justice Heerey dismissed the application on 16 May 2008, ruling that the referral contained adequate information for the Minister to assess whether the project constituted a controlled action under the EPBC Act and that relevant impacts, including cumulative climate risks, had been appropriately considered without breaching statutory requirements. The court emphasized the scientific basis of the environmental assessments, prioritizing empirical evaluations over unsubstantiated objections, thereby affirming the validity of the integrated Victorian Environment Effects Statement (EES) process accredited for federal purposes. Subsequent costs orders against Your Water Your Say in June 2008 contributed to the group's financial ruin and dissolution, highlighting the procedural risks and resource disparities in judicial challenges to major approvals. No further successful legal impediments arose from opposition tactics targeting the EES or EPBC processes, with courts consistently upholding the project's progression based on verified environmental data rather than procedural nitpicking or subjective claims. Privacy concerns emerged in December 2009 amid allegations that Victoria Police had shared personal information on desalination plant protesters—gathered during demonstrations—with the private AquaSure consortium tasked with building the facility. Victoria's Privacy Commissioner, Helen Versey, investigated following complaints and received assurances from police that no such protester details had been disclosed to the consortium, deeming the matter resolved without evidence of breach under privacy laws. Despite the official clearance, the episode amplified distrust in the project's transparency, as opponents viewed it as potential undue influence by private interests on public security data handling. Additional privacy issues surfaced in November 2010 with revelations of a covert monitoring operation at the site, where a private consultant was engaged to surveil workers' , recruitment, and subcontracting activities on behalf of and stakeholders. Unions, including the ACTU, condemned the initiative as an unwarranted of employee and a betrayal of , prompting calls for formal inquiries, though no rulings invalidated project operations on these grounds. These incidents, while not derailing approvals, underscored tensions between project imperatives and individual , with regulatory assurances prioritizing operational continuity over expansive reinterpretations of obligations.

Critiques of Cost-Effectiveness and Necessity

Critics have labeled the Victorian Desalination Plant a "" due to its idling from 2013 to 2019 following the end of the Millennium Drought, during which it produced no water despite annual standby costs exceeding $600 million, equivalent to approximately $1.8 million per day. These payments, mandated under the public-private partnership () structure, continued irrespective of usage, with total project costs projected to reach $20 billion over the 30-year contract term. Opponents argue this underutilization reflects overinvestment in capacity unnecessary for Melbourne's diversified water portfolio, which relies primarily on rainfall-dependent catchments and has benefited from subsequent wetter periods. The model, however, transferred construction and financing risks to the private consortium AquaSure, capping government exposure at fixed availability payments and avoiding the cost overruns common in publicly managed megaprojects, as evidenced by comparative experiences in where state-led desalination efforts incurred delays and budget escalations before privatization. Proponents contend that the plant's standby costs function as a hedge against recurrence, providing drought-proof supply up to 150 gigalitres annually—about 50% of Melbourne's demand—without the economic disruptions of water restrictions, which previously strained agriculture, industry, and household use during the 1997–2009 . Underuse during wet years underscores the success of supply diversification rather than project failure, as the facility enables flexible reservoir management and averts reliance on unpredictable rainfall, mirroring patterns at Sydney's desalination plant, which has also operated intermittently since 2010 to supplement storages during dry spells despite similar idle-period critiques. Empirical assessments indicate that early activation of such plants minimizes overall system costs by stabilizing supply reliability, with desalination's fixed expenses offset by avoided losses from emergency measures or infrastructure deficits in prolonged dry conditions.

Recent Developments

Production Milestones Post-2020

The Victorian Desalination Plant produced 125 gigalitres (GL) of in the 2020-21 supply year and another 125 GL in 2021-22, representing significant activations during periods of low inflows and heightened urban demand influenced by and hygiene measures. These outputs, equivalent to over 80% of the plant's annual capacity each year, helped maintain reservoir levels amid drier-than-average conditions in Victoria's catchments. Production scaled back to 15 GL in 2022-23 as inflows improved, with the plant entering long-term preservation mode in subsequent years due to sufficient rainfall and storage recoveries, incurring no operational orders in 2023-24 or 2024-25. On April 4, 2025, the Victorian Government placed a 50 GL order for the 2025-26 supply year, prompting reactivation starting July 1, 2025, to bolster storages amid persistent dry spells and below-median catchment inflows. Daily outputs in late 2025 ranged from 276 to 453 megalitres, demonstrating efficient ramp-up without reported water quality deviations. By mid-2025, cumulative production since commissioning reached 455 GL, with ongoing 2025-26 deliveries projected to surpass 500 billion litres by year-end, underscoring the plant's role in climate-resilient supply diversification. No major operational disruptions or efficiency shortfalls were documented in these periods, aligning with the facility's design for reliable, high-purity output.

Expansion and Future Supply Plans

The Victorian Water Security Plan, released in September 2025, outlines potential expansions to desalination capacity as part of a diversified strategy to meet rising demand in Greater , , and connected towns, driven by projected to over 8 million by 2050 and observed declines in natural inflows from rainfall and runoff variability. Empirical data from stream gauges indicate a long-term reduction in average annual runoff, with inflows to Melbourne's storages averaging 20-30% below historical norms in recent decades due to climatic shifts, necessitating non-rain-dependent sources like to buffer against variability without reverting to the severe restrictions experienced during the 2000s Millennium Drought. Key options under consideration include upgrading the existing Victorian Desalination Plant at from its current 150 gigalitres per year (GL/y) maximum to 200 GL/y, leveraging built-in design capacity, or developing a second desalination facility on Victoria's western coast to enhance redundancy and supply security. These measures would integrate with hybrid approaches, such as expanded purified recycled water schemes and , analyzed through a taskforce review set to consult communities and report recommendations by , prioritizing cost-benefit assessments grounded in demand forecasts and hydrological modeling rather than short-term projections. While expansion entails elevated capital and operational costs—potentially exceeding billions in upfront investment due to energy-intensive processes and infrastructure scaling—these are deemed essential to maintain supply reliability amid of reduced catchment yields, avoiding economic disruptions from water shortages as seen in prior low-storage periods below 30% capacity. The plan emphasizes pragmatic scaling, with interim reliance on the plant's proven output, including a 50 GL order for the 2025-26 supply year to bolster storages currently at secure levels but vulnerable to prolonged dry sequences.

References

  1. [1]
    Desalination plant - Water and catchments
    May 29, 2024 · The Victorian Desalination Project includes the largest desalination plant in Australia and is one of the greenest in the world.
  2. [2]
    Victorian Desalination Project | dtf.vic.gov.au
    Nov 27, 2024 · The Victorian Desalination Project (Project), located in the Wonthaggi region, achieved final commissioning completion on 17 December 2012 and ...Missing: capacity date
  3. [3]
    [PDF] Victorian Desalination Project
    The total maximum cost of the VDP is $5.7 billion (NPC), with a $3.5 billion capital cost. The nominal cost is $23.9 billion. Payments are made in two ...
  4. [4]
    Melbourne's Winter Water Storage Report: Desal steps in as rain ...
    Sep 9, 2025 · The Victorian Desalination Plant has contributed 16 GL (billion litres) since 1 July, enough to meet the city's water needs for roughly 20 days.Missing: utilization | Show results with:utilization
  5. [5]
    [PDF] Managing extreme water shortage in Victoria
    These 13 consecutive years of drought, including the lowest annual inflows to storages recorded (2006/07), resulted in conditions well outside the boundaries ...
  6. [6]
    [PDF] Melbourne's response to the Millennium Drought in Southeast ...
    The Millennium Drought in Southeast Australia forced greater Melbourne, a city of 4.3 million people, to find innovative ways of increasing water supply and.
  7. [7]
    Melbourne - International Water Association
    Actual storage levels dropped to around 25% of total volume in June of 2007, 2008 and 2009. This equates to 1 year of supply. Without the major water ...Missing: reservoir | Show results with:reservoir
  8. [8]
    [PDF] VICTORIAN DESALINATION PROJECT ENVIRONMENT EFFECTS ...
    Appearances at Hearing. 2. Key Elements of Reference Project, Variations and Options. 3. Approximate Capacity of Marine Structures.
  9. [9]
    Victorian desalination project background - Water and catchments
    Sep 8, 2023 · AquaSure funded the cost of building the plant, pipeline, and power supply, with the capital cost to build the project being $3.5 billion. They ...Missing: total | Show results with:total
  10. [10]
    The Millennium Drought in southeast Australia (2001–2009): Natural ...
    Feb 6, 2013 · Electricity prices were also driven up by the drought, particularly in 2007 ... reservoir storage, and groundwater levels varied by months to ...<|separator|>
  11. [11]
    [PDF] Partnerships Victoria Project Summary - dtf.vic.
    The date on which the Desalination Plant and associated infrastructure satisfies the required commissioning tests to demonstrate an output capacity of 50 GL per ...
  12. [12]
    [PDF] Environmental effects
    summary of the Victorian Desalination Project Environment Effects Statement, the environment of the region, the potential effects associated with the.
  13. [13]
    [PDF] Advice on the Desalination Project Environment Effects Statement ...
    Oct 10, 2008 · DPCD has sought comment on the adequacy of the assessment of likely marine ecological impacts arising from the construction and operation of the ...Missing: 2008-2009 | Show results with:2008-2009
  14. [14]
    Victorian Desalination Project (ecology) - Biosis
    Biosis was engaged to provide objective assessments of the potential impact of the Victorian Desalination Project upon the natural and constructed environment.Missing: achievements | Show results with:achievements
  15. [15]
    EPA raises concerns on desalination plant
    Oct 15, 2008 · Disposal of the "brine" back into the ocean is one of the most environmentally contentious aspects of desalination. In a written submission, the ...<|separator|>
  16. [16]
    [PDF] VICTORIAN DESALINATION PROJECT ASSESSMENT
    The proposed VDP works comprise a desalination plant with the capacity to produce 150 to 200 gigalitres (GL) of drinking water per year, marine structures for ...
  17. [17]
    [PDF] epa-works-approval-application-victorian-desalination-project.pdf
    The proposed Site for the Desalination Plant is located near the town of Wonthaggi ... environmental (and other) considerations associated with desalination ...
  18. [18]
    Desalination Plant for Victoria, Australia | Public Private Partnership
    Jan 1, 2009 · The state has contracted with the consortium AquaSure to deliver all aspects of the project. AquaSure has engaged other contractors to ...
  19. [19]
    [PDF] Victorian Desalination Project - SUEZ
    Mar 20, 2025 · It includes 221 strict environmental performance requirements across 38 areas, from wetlands and waterways to air quality and visual amenity.Missing: achievements | Show results with:achievements
  20. [20]
    Profile | Aquasure
    AquaSure was contracted by the Victorian State Government to finance, design, build, operate and maintain the Victorian Desalination Plant.
  21. [21]
    Desalination timeline - Water and catchments
    Sep 8, 2023 · The project was announced in 2007, construction began in 2009, and commissioning was completed in 2012. The plant started producing first ...Missing: date | Show results with:date
  22. [22]
    History - Aquasure
    On 19 June 2007, the Victorian Government announced plans to construct a desalination plant as part of the next stage of its Water Plan.Missing: commissioning | Show results with:commissioning
  23. [23]
    Victorian Desalination Plant - Herrenknecht AG
    Two Herrenknecht Mixshields drove two 1.5 and 1.2-kilometer-long tunnels starting from the coast: one tunnel to extract water from the sea (inlet tunnel) and ...Missing: intake | Show results with:intake
  24. [24]
    [PDF] victorian desalination project - fact sheet - Aquasure
    The Victorian Desalination Project uses a two pass reverse osmosis process to remove minerals and salts and produce a product that meets strict water quality.
  25. [25]
  26. [26]
    [PDF] VICTORIAN DESALINATION PROJECT
    The $3.5 billion Victorian Desalination Project will have an initial production capacity of up to 150 billion litres of water a year (444 million litres per ...<|separator|>
  27. [27]
    Pipeline & Powerline - Aquasure
    Desalinated water from the plant at Wonthaggi is piped to Melbourne via an 84 kilometre underground pipeline. The pipe is made up of more than 6200 lengths ...
  28. [28]
    Preparing for pipeline completion at the Victorian Desalination Project
    Mar 16, 2016 · Pipeline statistics Length: 83,400 m Diameter: 1.93 m Pipeline volume: 243 ML/d Peak design flow-rate: 444 ML/d initial pumping capacity.
  29. [29]
    The Victorian desalination plant's water transfer system - Informit
    ... pipeline over an 84km length with a capacity of 200 GL per annum; transfer pump station to convey up to 150 GL per annum; booster pump station; surge ...
  30. [30]
    Pipelines and power supply - Water and catchments
    Sep 8, 2023 · The desalination plant has a series of pipelines and tunnels that connect with a power supply, Victoria's water grid and Bass Strait.Missing: laying | Show results with:laying
  31. [31]
    The water energy nexus in Australia – The outcome of two crises
    Jun 29, 2018 · The 150 GL (150,000,000 m3) annual capacity Victorian Desalination Plant requires 90 MW of power supplied underground through a 220 kV High ...
  32. [32]
    Desalination | Melbourne Water
    Jul 8, 2025 · The Victorian Desalination Plant at Wonthaggi, in Victoria's south east. Warmer temperatures and growing demand are putting increased pressure ...
  33. [33]
    Victorian desal plant to cost extra $2b - ABC News
    Oct 7, 2010 · Cost blowout. The Victorian auditor-general says a proposed desalination plant will cost $2 billion more than State Government estimates.Missing: overruns | Show results with:overruns
  34. [34]
    Auditor-General's Report on the Annual Financial Report of the State ...
    Nov 26, 2013 · This report informs Parliament about the results of the audit of the Annual Financial Report of the State of Victoria for 2012–13 (the AFR).
  35. [35]
    [PDF] Paying for the Victorian desalination plant: A case study in ...
    The price impact on end-use customers would have been about $10 per year for an average household. Alternatively, Melbourne Water suggested that if the ...Missing: utilization | Show results with:utilization
  36. [36]
    [PDF] AUSTRALIAN DESALINATION PROJECTS, PAST, PRESENT AND ...
    Jun 11, 2025 · Significant reductions in runoff across major city catchments, with even small decreases in rainfall causing significant declines in runoff.Missing: achievements | Show results with:achievements
  37. [37]
    Desalination - Water and catchments
    The Victorian Desalination Plant can deliver up to one-third of Melbourne's annual water needs. On this page: Desalination essentials; Water orders ...Missing: rate | Show results with:rate
  38. [38]
    Desalination data - Melbourne Water
    The Victorian Desalination Plant can deliver up to 150 billion litres of high-quality drinking water a year. That's one-third of Melbourne's needs.
  39. [39]
    Why we need to use water desalination plants early - Pursuit
    Mar 21, 2019 · In response the Victorian government has made the largest-ever water order from the desalination plant at Wonthaggi. This is a good decision ...
  40. [40]
    Water Security Plan - Water and catchments
    Oct 3, 2025 · The Victorian Desalination Plant will continue to support the South-Central Water Grid with a secure source of water that does not rely on rain ...
  41. [41]
    Victorian desalination plant - Appropedia
    Plans to build a desalination plant at Wonthaggi in Victoria, Australia, were announced by the Bracks Labor government in June 2007.
  42. [42]
    [PDF] Melbourne A ugmentation Program Seawater Desalination
    Jun 7, 2007 · Recovery through entire plant. 42.5%. 42.5%. Figure 16 –Reverse osmosis racks inside a large seawater desalination plant (under construction) ...
  43. [43]
  44. [44]
    Climate Change Statement - Aquasure
    ... Plant, and to produce desalinated water, has been 100% offset by the purchase and surrender of Renewable Energy Certificates (REC's). AquaSure has ...Missing: LGCs | Show results with:LGCs
  45. [45]
    Energy Recovery, Inc. to Deliver Unmatched Power Efficiency at ...
    Feb 2, 2010 · Energy Recovery's PX devices operate at up to 98 percent efficiency and reduce the energy consumption of seawater reverse osmosis (SWRO) systems ...Missing: Victorian | Show results with:Victorian
  46. [46]
    Energy Recovery, Inc. PX Devices Contracted for Largest ...
    Dec 15, 2009 · Energy Recovery's PX devices reduce the energy consumption of SWRO systems by up to 60 percent, making desalination a cost-effective solution ...Missing: pass | Show results with:pass
  47. [47]
    Energy Efficiency | Aquasure
    Reverse osmosis is the most energy efficient method of desalination. AquaSure has introduced a number of innovative systems to minimise power consumption within ...
  48. [48]
    [PDF] Victorian Desalination Project - Aquasure
    A number of Direct Toxicity Assessments have been undertaken firstly for the Environment Effects. Statement in 2008 (Department of Sustainability and ...
  49. [49]
    [PDF] VICTORIAN DESALINATION PROJECT - FACT SHEET the design
    The restoration will include over 3.5 million new plants and 150,000 trees, a constructed dune system and the creation of wetlands, coastal and swampy woodlands.
  50. [50]
    Victorian Desalination Project and Ecological Reserve - AnArt4Life
    Jan 22, 2022 · The roof garden project commenced in 2011 and finished early 2012. The 26,000m2 size of the roof garden, makes it the largest green roof in the ...
  51. [51]
    Victorian Desalination & Ecological Reserve | ASPECT Studios
    The project includes a desalination plant delivering 150 billion liters of water, a 225-hectare ecological reserve, a 26,000m² green roof, and aims to minimize ...Missing: terrestrial construction
  52. [52]
    [PDF] Ecological Reserve Fact Sheet - Aquasure
    The walking and cycling trails include a number of vantage points and viewing decks from which visitors can get a good look at the Desalination Plant buildings ...
  53. [53]
    Wonthaggi - Victorian Desalination Project Ecological Reserve Trails
    There are a number of walks (6-8km / 2-3 hours) in the 225 hectare ecological reserve surrounding the Desalination Plant. The walks cover natural and ...
  54. [54]
    [PDF] Outfalls Capabilities - UNSW Sydney
    WRL physically modelled diffuser arrangements to refine the design for the Victorian Desalination Plant. A non-dimensional analysis technique was used ...
  55. [55]
    [PDF] Assessment of the Values of Victoria;s Marine Environment - Tethys
    May 21, 2019 · This report of the assessment together with a companion atlas is based on evidence from data and analysis, supported by expert judgement and.
  56. [56]
    Desalination Plant Produces First Samples Of Drinking Water
    Sep 6, 2012 · The production of drinking water has recently commenced at the Victorian Desalination Plant near Wonthaggi.Missing: groundbreaking date
  57. [57]
    Desal plant passes final tests | The Australian
    12:00AMDecember 19, 2012. TheAustralian. CONSTRUCTION at the Victorian Desalination Plant has finished, marking the final contractual milestone for Leighton ...
  58. [58]
    Victorian desalination plant complete - Engineers Australia
    Dec 19, 2012 · Construction of the 84km, 1.9m diameter transfer pipeline that will provide water to communities throughout Melbourne, South Gippsland and ...
  59. [59]
    Producing high-quality water
    Jul 4, 2025 · In 2023, water from the Victorian Desalination Plant was named Victoria's best tasting tap water by the Water Industry Operators Association.Missing: uptime | Show results with:uptime
  60. [60]
    Desalination Plant Victoria - WSP
    The Victorian Desalination Project provides a drought-proof water supply for the growing areas of Melbourne and Geelong.Missing: MW | Show results with:MW
  61. [61]
    Victoria's Water Storages Currently Secure | Premier
    Accordingly, the Government will not be ordering water from the Victorian Desalination Project for 2015-16. ... The plant will remain in standby ... The ...
  62. [62]
    AquaSure's Victorian Desalination Plant secures its first water order
    Oct 12, 2016 · The payment in 2016-17 was $607 million, not including the amount due for the water, which was reportedly $27 million. AquaSure subcontracted ...
  63. [63]
    Desalination order to secure our water supply for 2021
    The Victorian Government has ordered 125 gigalitres from the Victorian Desalination Plant in Wonthaggi to secure Melbourne's water supply for our growing ...
  64. [64]
    Wonthaggi Desalination Plant to be switched on to ease dry conditions
    Apr 4, 2025 · The desalination plant can supply up to 150 billion litres of water a year to Melbourne, Geelong, South Gippsland and Western Port townships, ...Missing: daily ML/<|control11|><|separator|>
  65. [65]
    Desalinated water to boost storages - South East Water
    Apr 4, 2025 · To date, the Victorian Desalination Plant has produced 455 billion litres of fresh drinking water for Greater Melbourne and regional towns. In ...
  66. [66]
    Victoria desalination plant in Melbourne, Australia - SUEZ
    The award-winning Victorian Desalination Plant is the largest desalination ... The plant was commissioned in record time in 2012, meeting 100 per cent of ...Missing: date | Show results with:date
  67. [67]
    Opposition to desal plant grows - Green Left
    Jul 5, 2008 · A public meeting on June 24 against the proposed desalination plant drew 500 people. The gathering, 12 months after a 700-strong public meeting ...
  68. [68]
    Protesters march against desal plant - ABC News
    Sep 3, 2008 · About 100 people are rallying in Wonthaggi to protest against the $3-billion desalination plant to be built at nearby Powlett River. They ...
  69. [69]
    Protesters to renew campaign against desal plant
    Aug 3, 2009 · Anti-desalination protesters jump fence and invade property of Wonthaggi desalination plant in first major protest since Government ...
  70. [70]
    "Desalination must be a last resort, not a first resort" - Green Left
    Dec 9, 2008 · Watershed Victoria is an environmental organisation dedicated to the campaign against the proposed desalination plant at Wonthaggi in Victoria,
  71. [71]
    Australia: Victorian government covers up desalination plant costs
    Oct 27, 2010 · With the Victorian state election looming on November 27, the Labor government of Premier John Brumby is deliberately hiding the huge costs ...Missing: 2007 | Show results with:2007
  72. [72]
    Victorian Desalination Project Management Case Study - IvyPanda
    Jun 30, 2022 · According to the project's outlay, the feasibility study was commissioned in late 2006. The feasibility study was followed by a number of ...
  73. [73]
    Melbourne's desalination plant is just one part of drought-proofing ...
    Mar 10, 2016 · Water has now been ordered from the Victorian desalination plant. The plant was built at the end of the millennium drought to provide security against drought.Missing: activation | Show results with:activation
  74. [74]
    [PDF] [2008] FCA 670
    May 16, 2008 · 1 The Victorian Government proposes the con- struction of a desalination plant (the Project) on the. Gippsland Coast near Wonthaggi. Seawater ...
  75. [75]
    What To Include In Referrals Under The EPBC Act, Minister for the ...
    The Federal Court decision in Your Water Your Say v Minister for the ... Victorian desalination plant raises a number of interesting issues. First, the ...Missing: challenges | Show results with:challenges
  76. [76]
    Your Water Your Say Inc v Minister for the Environment, Heritage ...
    Heerey J, in approving the proposed desalination plant, held that the agency had adequately considered the impact of greenhouse gas emissions on protected ...Missing: approvals | Show results with:approvals
  77. [77]
    Costs ruling sinks protesters - AFR
    Jun 14, 2008 · The Federal Court on Friday ruled that Your Water Your Say, having lost its case against the plant, should have to pay costs incurred by state ...
  78. [78]
    Desalination plant gets green light - The Sydney Morning Herald
    May 16, 2008 · ... court dismissed a claim from a community group to stop it from being built. A bid by Your Water Your Say (YWYS) to stop work beginning on ...
  79. [79]
    Privacy chief meets police over desalination plant - ABC News
    Dec 10, 2009 · Victoria's Privacy Commissioner, Helen Versey, says police have assured her no details about protesters have been passed onto the consortium ...
  80. [80]
    Unions demand talks on desal plant spying - ABC News
    Nov 19, 2010 · A private consultant was hired to monitor the security, recruitment and subcontracting processes at the desal plant near Wonthaggi, south-east of Melbourne.
  81. [81]
    Spying operation at Victorian desal project is a breach of workers ...
    Nov 18, 2010 · The ACTU said the covert operation spying on workers was an invasion of privacy and a breach of trust of the highest order. The spying operation ...
  82. [82]
    Victoria's unused $4bn desalination plant may be dusted off to ease ...
    Oct 7, 2015 · The facility cost $4bn but was immediately put on standby as the drought broke. It costs Victoria $620m a year to keep it online, even though ...Missing: annual | Show results with:annual
  83. [83]
    Victoria's desalination plant at Wonthaggi sits idle at cost of $1.8m a ...
    Apr 1, 2015 · Victoria's $6.1 billion desalination plant will remain idle for another financial year at a cost of $1.8 million a day to taxpayers.
  84. [84]
    Costly, idle desal plant adds to cost of living pain - Liberal Victoria
    Jan 14, 2024 · Initiated in 2009, the Victorian Desalination Project will cost the state at least $20 billion in nominal terms over its 30-year contract. It is ...
  85. [85]
    Victorians stuck with 'white elephant' - ABC listen
    Mar 1, 2011 · In the first year of operation the plant will cost $654 million even if it doesn't produce a drop of water. The costs will be borne entirely by ...Missing: idling | Show results with:idling
  86. [86]
    [PDF] PPPs and economic regulation: substitute or complement? - ACCC
    ○ Victoria built desalination plant as a PPP. ○ NSW built as a government project, then privatised the lease. ○ NSW allowed for the state regulator to have ...<|control11|><|separator|>
  87. [87]
    Desalinated water to boost storages
    Apr 4, 2025 · Using desalinated water will reduce the need for water restrictions, which have social impacts and economic cost. To date, the Victorian ...
  88. [88]
    Why Sydney residents use 30% more water per day than Melburnians
    May 24, 2019 · Sydney's desalination plant is relatively small, as it currently is capable of supplying 15 percent of the daily water demand. In comparison ...
  89. [89]
    [PDF] Water Security Plan for Greater Melbourne, Geelong and connected ...
    By the end of 2025 the desalination plant will have delivered half a trillion litres of drinking water, or 28% of Melbourne's total water storage capacity.Missing: mitigation restoration
  90. [90]
    Securing Victoria's Water Supply for the Future - Melbourne Water
    Sep 25, 2025 · “By the end of 2025, the existing desalination plant will have delivered half a trillion litres of drinking water to many of our communities and ...
  91. [91]
    Securing Victoria's Water Supply For The Future | Premier
    However, modelling estimates that over the next decade, Victoria will need an extra 95 billion litres of water per year on top of the Victorian ...