Fact-checked by Grok 2 weeks ago

Canada Line

The Canada Line is a fully automated line forming part of the network in Metro , , . It spans 19 kilometres and serves 17 stations, connecting Waterfront Station in to Richmond–Brighouse in the suburb of , with a branch extending to (YVR). Opened on 17 August 2009 ahead of the , the line provides a direct 25-minute journey from downtown to the airport, enhancing regional connectivity and accommodating high volumes of passengers. Constructed via a public-private partnership (P3) model to expedite delivery, the Canada Line achieved completion on time and within budget, but design choices prioritizing cost efficiency resulted in shorter trains and platforms compared to other lines, leading to capacity constraints amid unexpectedly strong ridership growth. The project's elevated and tunneled minimized surface disruption in parts, yet along Cambie Street severely impacted local businesses, with many reporting significant revenue losses and some closures due to prolonged traffic blockages. Despite these challenges, the line has become integral to Metro Vancouver's transit system, supporting economic activity around stations like the recently added in 2024, which includes retail and to foster community integration.

Route and Geography

Vancouver Section

The Vancouver section of the Canada Line originates at Vancouver City Centre station in downtown , adjacent to the Expo Line's Waterfront station for interline transfers, and proceeds southward to Marine Drive station near the city's southern boundary. This segment primarily follows the Cambie Corridor, a north-south arterial route through dense urban development characterized by mixed residential, commercial, and institutional land uses. The path navigates the flat to gently sloping terrain of Vancouver's peninsula, crossing inlet and paralleling Cambie Street, a major six-lane thoroughfare. Initial infrastructure consists of underground tunnels serving the initial stations. Vancouver City Centre station connects to office towers and retail in the . Yaletown–Roundhouse station provides access to the historic neighborhood, known for its converted industrial buildings and proximity to entertainment venues. The route then traverses a subaqueous beneath to Olympic Village station, located on the southeast inlet shore amid post-2010 Winter Olympics developments including residential high-rises and parks. South of , the line emerges onto an elevated guideway aligned parallel to Cambie Street, minimizing surface disruption in the Fairview and Oakridge areas. Broadway–City Hall station lies at the intersection of Cambie and , linking to City Hall and nearby educational institutions. King Edward station serves the west side of General Hospital's campus and surrounding healthcare facilities. Oakridge–41st Avenue station adjoins the Oakridge Centre shopping mall and residential zones at West 41st Avenue. The section concludes at Marine Drive station, positioned near the North Arm of the , facilitating the transition to the municipality via elevated structure.
StationLocation and Key Connections
Vancouver City CentreDowntown core; transfers to Expo Line at adjacent Waterfront station; access to offices and shopping.
Yaletown district; near Roundhouse Community Arts and Recreation Centre.
Southeast ; residential and Olympic legacy sites.
Broadway–City HallCambie and Broadway intersection; Vancouver City Hall, commercial hubs.
King EdwardNear ; medical precinct.
Oakridge–41st AvenueOakridge Centre mall; West 41st Avenue and residences.
Marine DriveNear North Arm; industrial and residential fringe.

Richmond and YVR Section

The Canada Line enters at Bridgeport station, a major interchange hub connecting to the Expo Line and situated near Highway 99 and the approaches. Southbound service along the mainline proceeds on an elevated guideway through commercial and mixed-use zones, serving Aberdeen station adjacent to the mall and surrounding retail developments. The route then reaches Capstan station, which opened on December 20, 2024, in the Capstan Village neighborhood to support high-density residential growth and local amenities. Continuing south, trains stop at Lansdowne station near and community facilities before terminating at Richmond–Brighouse station in the city's at No. 3 Road and Brighouse Street, a key node for shopping, libraries, and civic buildings. This segment, spanning flat delta land reclaimed from the floodplain, integrates with Richmond's grid of arterial roads and high-density urban form, where over 200,000 residents—predominantly of Asian descent—rely on it for intra-city mobility amid limited . Travel times within average 5-7 minutes between Bridgeport and Richmond–Brighouse, with frequencies up to every 3-6 minutes during peak hours. At Bridgeport, trains diverge onto a dedicated spur to Vancouver International Airport (YVR), routing southeast across industrial zones and the Middle Arm of the . The branch serves Templeton station near the airport's north entrance and local schools, then Sea Island Centre station in the Sea Island community of single-family homes and parks, before terminating at YVR–Airport station, directly linked to the airport's terminals via pedestrian walkways. This extension, operational since August 17, 2009, reduces airport trips to 18 minutes from Richmond–Brighouse and under 30 minutes from , alleviating road congestion on Highway 99. The spur navigates Sea Island's low-elevation terrain, incorporating environmental mitigations for nearby wildlife corridors and dikes.

Stations and Infrastructure

Station List and Design Features

The Canada Line serves 17 stations across , , and (YVR), with the line splitting at Bridgeport Station into branches to Richmond–Brighouse and YVR–Airport. The stations from to Langara–49th Avenue are underground, while , Marine Drive, and all stations in and toward YVR are elevated or at-grade. Most stations opened on August 17, 2009, except , which opened on December 20, 2024. Stations on the main line from to Bridgeport include: The Richmond branch from Bridgeport continues to: The YVR branch from Bridgeport serves:
  • Templeton (Richmond)
  • Sea Island Centre (Richmond)
  • YVR–Airport (Vancouver International Airport)
Canada Line stations emphasize openness and security through extensive frameless glazing, providing line-of-sight visibility across platforms and entrances. Designs incorporate modern materials like steel superstructures with wood elements—such as prefabricated Douglas-fir panels and arched roofs at stations like Aberdeen and Lansdowne—for aesthetic warmth and acoustic benefits. Architectural firms including Perkins&Will, DIALOG, and Fast + Epp contributed to specific stations, adapting to urban contexts with features like captured roof water channels and integrated plazas. The elevated sections use concrete platforms and steel frameworks, while underground stations employ bored tunneling for minimal surface disruption. Capstan Station uniquely features the Canada Line's longest platforms (80 meters) and expanded circulation areas to accommodate growing ridership in Capstan Village. All stations support the line's automated operation, with no crew cabins on platforms.

Accessibility and Amenities

All Canada Line stations provide barrier-free access through elevators and escalators connecting street level, mezzanine areas, and platforms, enabling users and those with mobility aids to navigate independently. Escalators are available at all stations, though some operate in a single direction only, with real-time status updates accessible via TransLink alerts. The line's automated trains include dedicated multi-use areas at each end for s, scooters, strollers, and bicycles, facilitating secure boarding with level platform alignment. Priority seating, marked with icons for users and those with mobility canes, is located near doors to accommodate passengers with disabilities, elderly individuals, or those temporarily needing support. Amenities vary by station but include provisions for station assistance, available by calling 604-520-5518 at least 10 minutes prior to arrival for guidance on or boarding. Newer stations, such as Capstan opened in December 2024, feature enhanced designs with two elevators per platform, dual escalator sets, expanded public circulation space, secure bike parking, bright LED lighting, and space for future retail kiosks to support passenger convenience. Older stations emphasize core accessibility without extensive commercial integration, prioritizing efficient flow to nearby urban amenities like shopping districts at City Centre.

Technology and Operations

Vehicles and Fleet Specifications

The Canada Line utilizes a fleet of 32 two-car (EMU) trains built by of . Initial deliveries occurred between 2007 and 2009, with 12 additional trainsets entering service starting in late 2019 to expand capacity. These trains operate exclusively on the line in fixed two-car configurations, comprising 64 cars total. Each car measures approximately 20 meters in length, resulting in a trainset length of 41 meters, aligned with station platform dimensions. Cars feature three doors per side, brushed stainless steel bodies, and Mitsubishi Electric AC traction motors powered by third-rail electrification at standard gauge (1,435 mm). The trains support a maximum operating speed of 80 km/h. Seating capacity stands at 44 per car (88 per trainset), with a comfortable total capacity of 334 passengers and up to 400 at per trainset. The design emphasizes compatibility, lacking operator cabs in traditional form, and includes features like for . No further fleet expansions are planned for the Canada Line as of 2025, unlike the and lines.

Automation, Signaling, and Maintenance

The Canada Line operates as a fully automated system without onboard train operators, relying on a Thales SelTrac (CBTC) system for unattended train operations. This technology, implemented since the line's opening on August 17, 2009, integrates automatic train protection (ATP) to enforce speed limits and prevent collisions, (ATO) for precise movement control, and automatic train supervision (ATS) for centralized monitoring and scheduling adjustments. The CBTC employs a moving-block signaling approach, using continuous communication between trains and trackside equipment to dynamically adjust train spacing, enabling peak-hour headways as low as 2 minutes and supporting a maximum throughput of up to 20,000 passengers per hour per direction. All train movements are overseen from the Canada Line Operations and Maintenance Centre (OMC) located at 9851 Van Horne Way in , adjacent to Bridgeport station. This facility houses control rooms for real-time system supervision, fault detection, and remote diagnostics, with contingency protocols for manual overrides in rare disruptions, such as signal failures or track obstructions. Signaling infrastructure includes zone controllers, balises for train positioning, and onboard transponders, ensuring operations compliant with Canadian rail standards. Maintenance responsibilities fall under ProTrans BC, a led by (formerly SNC-Lavalin), operating via a 35-year public-private concession agreement signed in 2005. Routine tasks encompass daily inspections of the 20-train fleet of EMU-3000 vehicles, track and power rail servicing, and automated cleaning, performed primarily at the OMC during off-peak hours to minimize service interruptions. leverages a model of the entire 19.1 km guideway, incorporating sensor data from tracks, trains, and substations to forecast component failures—such as rail wear or door malfunctions—and optimize replacement schedules, reportedly reducing overall maintenance costs by 15% since implementation around 2022. This data-driven approach contrasts with more reactive methods on older lines, prioritizing asset longevity amid annual ridership exceeding 20 million passengers.

History and Development

Planning and Naming Origins

The corridor linking , , and had been studied for transportation improvements for over three decades prior to the project's formal advancement. In 1999, during public consultations for the Livable Region Strategic Plan, the Richmond/Airport/Vancouver (RAV) line emerged as a designated priority to address growing demand along the route, projected to carry up to 100,000 daily passengers by accommodating , urban commuting, and regional connectivity. These early assessments emphasized automated light technology to minimize operational costs and maximize capacity, drawing from precedents like existing lines while adapting to the corridor's mix of elevated, at-grade, and tunneled segments necessitated by and airport constraints. Project planning accelerated in 2000, with Transit (predecessor to aspects of TransLink's oversight) initiating detailed feasibility studies and development. Municipal endorsements followed, including City Council's approval of a management plan for the RAV project on September 25, 2000, which outlined environmental assessments, route alignments, and preliminary cost estimates ranging from CAD $1.2 to $1.8 billion. reviewed integration with local bus networks in April 2003, prioritizing seamless transfers at key hubs like Vancouver City Centre station. The provincial government committed funding in 2004, structuring it as a public-private to expedite delivery ahead of the , with SNC-Lavalin selected to lead design-build-finance-operate-maintain phases. Originally designated the RAV Line to reflect its endpoints, the project was rebranded as the Canada Line in November 2005 to signify its role as a national gateway via the airport and to unify it under the branding. This naming shift occurred amid final route approvals and procurement, emphasizing automated operations compatible with but distinct from the and Lines' fleet.

Timeline of Key Events

  • December 2004: The TransLink board provided final approval for the Canada Line project, following agreements among provincial, regional, and authorities to proceed with .
  • November 2005: Construction commenced on the 19-kilometer line, including elevated guideways, tunnels, and stations connecting to and .
  • March 2, 2008: Bored tunnel segments under were completed ahead of schedule, marking a major underground infrastructure milestone.
  • November 12, 2008: Initial passenger testing began, with the first groups riding prototype trains to validate operations prior to full .
  • March 27, 2009: Provincial and federal officials celebrated near-completion of construction, confirming the line would open by early September, three months ahead of the original November target.
  • August 17, 2009: The Canada Line officially opened to the public, providing automated service with 16 stations and integrating with the existing .
  • December 20, 2024: opened between Bridgeport and Aberdeen stations in , adding capacity to serve growing residential development in the area.

Construction Processes and Milestones

The Canada Line's construction adopted a hybrid approach tailored to urban constraints and timelines, primarily using cut-and-cover methods along the 9 km corridor on Cambie Street, where trenches were excavated, reinforced with anchored systems, fitted with tunnel segments, and backfilled to minimize long-term disruption while enabling seismic resilience. A supplemented this for select underground sections, starting operations in June 2006 from the future station site and advancing southward. In and to , elevated guideways and at-grade segments were built using beams and piers, facilitating faster assembly over less dense terrain. The 19 km line, spanning 16 stations, was executed under a public-private by the InTransitBC , which assumed primary risks to accelerate delivery ahead of the . Key milestones included the project's formal commencement on November 1, 2005, shortly after contract award. Tunnel boring achieved a significant breakthrough on April 7, 2007, completing the initial TBM drive. By March , the line neared operational readiness, with trackwork, electrification, and systems integration substantially complete. launched on August 17, 2009—three months ahead of the revised target and four months early against the initial plan—following intensive testing and a fare-free inaugural day that drew tens of thousands of riders. The $1.9 billion project finished on budget, earning recognition for innovation in delivery.

Funding and Delivery Model

Project Costs and Budgeting

The Canada Line project was initially estimated in the early at approximately $1.6 billion CAD for a connection from to and , encompassing design, construction, and operations under a proposed public-private partnership (P3). By financial close on July 29, 2005, the approved budget stood at $2.05 billion CAD in nominal terms (or $1.889 billion in 2003 dollars), reflecting refined scope including 19 kilometers of guideway, 16 stations, and a 35-year design-build-finance-operate agreement with the private consortium InTransitBC. Funding was secured through a mix of public contributions totaling $1.331 billion CAD and $720 million in private equity from InTransitBC, which assumed responsibility for cost overruns during via the structure. The public portion included direct without exposure to private-side risks, aided by a $41 million held by the (CLCO) for defined public liabilities such as acquisition.
Funding SourceContribution (CAD million, nominal)
Government of Canada450
Province of British Columbia252
Greater Vancouver Transportation Authority (TransLink)333
259
30
Private (InTransitBC )720
The project concluded construction within the $2.05 billion envelope, with total costs reported at $2.054 billion, avoiding taxpayer-funded overruns due to the P3 model's risk allocation to the private partner. This outcome contrasted with broader Canadian transit trends of escalation, as the fixed-price mechanism incentivized efficient delivery despite early planning revisions from initial lower estimates driven by preliminary scoping.

Public-Private Partnership Structure

The Canada Line was developed through North America's inaugural public-private partnership (PPP) for rapid transit infrastructure, structured as a design-build-finance-operate-maintain (DBFOM) concession agreement with a 35-year term, achieving financial close in July 2005. The model allocated design, construction, partial upfront financing, operations, and maintenance to the private sector while enabling public oversight via Canada Line Rapid Transit Inc. (CLCO), a special-purpose vehicle co-owned by the South Coast British Columbia Transportation Authority (TransLink), the Province of British Columbia, the Vancouver International Airport Authority (YVR), and Transport Canada. InTransitBC, the selected private consortium comprising Infrastructure Partners LP (formerly SNC-Lavalin), Plenary Americas as equity investor, and (bcIMC), bore primary responsibility for delivering the 19.5 km automated guideway, 16 stations, 20-train fleet, and an operations and maintenance facility in . InTransitBC assumed most risks, including overruns and delays, as well as operational risks such as performance shortfalls, in exchange for monthly availability payments from CLCO totaling the project's approximately CAD$2 billion value. These payments were calibrated at 70% for (measured by trains per hour), 20% for metrics, and 10% tied to ridership volume to incentivize efficiency and demand generation. Public contributions, drawn from TransLink, provincial, federal, and YVR funds, covered the majority of estimated at CAD$1.76 billion upon approval in December 2004, with and bridging the remainder and repaid progressively through the concession. TransLink retained authority over fare policy, system integration with the broader network, and overall scheduling, ensuring alignment with regional transit goals while mitigating full control over revenue streams. This risk-transfer mechanism aimed to harness private-sector and , though evaluations noted the private operator's incentives influenced choices like shorter lengths to optimize under initial low ridership projections.

Performance Metrics

The Canada Line, which opened on August 17, 2009, recorded initial average daily boardings of approximately 83,000 in September 2009, rising to 105,000 by March 2010 amid strong post-opening demand connected to and . Ridership continued to expand rapidly, surpassing pre-construction projections of 120,000 daily boardings—originally forecasted for 2025—by around 2011 or 2012, driven by population growth in and airport traffic. Pre-pandemic ridership peaked with over 50 million annual boardings in 2019, reflecting sustained growth from urban development and transit-oriented connectivity. The caused a sharp decline, with fall 2022 boardings recovering to only 74% of fall 2019 levels amid reduced air travel and office . Post-pandemic recovery accelerated, with 2023 boardings increasing 21% over 2022, aligning with broader trends. In 2024, Canada Line boardings grew 5% year-over-year, reaching average weekday levels of 132,307 (Monday-Friday), 102,561 on Saturdays, and 86,454 on Sundays/holidays, approaching or exceeding pre-2019 peaks due to regional population expansion and service enhancements. These trends indicate robust demand along the corridor, though capacity constraints persist during peak hours.

Capacity Utilization and Upgrades

The Canada Line's current peak directional stands at approximately 8,600 passengers per hour under its standard operating parameters with two-car automated trains and minimum headways of around two minutes. This configuration supports up to 75% utilization based on recent assessments, though projections indicate potential overloads exceeding 112% of within horizons due to sustained ridership growth outpacing initial forecasts. Physical counts and service data confirm peak-period crowding, particularly on segments serving and Richmond, where boardings have consistently surpassed early targets, reaching over 50 million annually by 2019 before pandemic disruptions. To address escalating demand, TransLink augmented capacity through fleet and scheduling enhancements in –2020, introducing additional 300 train cars and denser peak frequencies, which collectively raised service capacity by 35% relative to 2019 baselines. These measures included the addition of four cars in early 2020 alone, accommodating roughly 800 more riders per peak hour and enabling an 11% weekday capacity uplift via extended peak operations. Post-implementation monitoring in TransLink's annual performance reviews has shown ridership rebounding to 74–80% of pre-2020 levels by 2023–2024, underscoring the upgrades' role in maintaining service reliability amid recovery. Prospective upgrades focus on extensions to support three-car , potentially elevating ultimate to 15,000 passengers per hour per direction through compatible 50-meter trainsets and optimized signaling, though realization hinges on renegotiating the line's public-private with ProTrans BC. Constraints from the original design—stations built for 40–50 meter envelopes—limit immediate scalability without structural modifications, as evidenced by ongoing SkyTrain-wide infrastructure reviews prioritizing and lines but identifying Canada Line bottlenecks. No major lengthening projects were funded or underway as of 2025, with emphasis instead on operational tweaks like frequency adjustments to defer capital-intensive overhauls.

Economic and Regional Impacts

Positive Outcomes and Achievements

The phase of the Canada Line created 7,000 job-years of direct , averaging 1,400 jobs annually over the five-year build period from 2005 to 2009, while disbursing $415 million in worker wages. This activity stimulated local supply chains and supported ancillary economic multipliers in materials and services procurement. Operational since August 17, 2009—two months ahead of its contractual deadline—the line enabled seamless mass transit during the , transporting 3.9 million passengers across 17 days with peak daily volumes reaching 112,000 riders. Its integration with (YVR) established North America's first direct automated rail link to a major international gateway, serving as a boon for airport operations and facilitating efficient access for and travelers. Post-opening, the Canada Line has unlocked land value along its corridor by easing access constraints, promoting and higher-density uses near stations in , , and YVR environs. Enhanced regional mobility has supported patterns, reducing reliance on automobiles for airport-bound trips and fostering between urban core, suburbs, and trade hubs.

Adverse Effects on Local Economies

The construction of the Canada Line between 2007 and 2009, employing cut-and-cover tunneling along much of Cambie Street in , imposed significant short-term economic burdens on adjacent small businesses through prolonged street closures, noise, dust, vibrations, and barriers that impeded customer access and reduced foot traffic. These disruptions led to substantial revenue losses, with fencing and excavation works blocking visibility and entry to storefronts for over three years in some segments. In the Cambie Village area, from 2nd Avenue to 25th Avenue, the impacts forced the closure of 39 businesses unable to sustain lease payments amid the interference. Dozens of affected merchants pursued compensation via class-action lawsuits against Canada Line Rapid Transit Inc. and ProTrans BC, alleging unreasonable interference with their operations. In a 2018 test case (Gautam v. Canada Line Inc., 2018 BCSC 1515), three Cambie Street businesses—a , a , and a outlet—were awarded a total of over $180,000 in damages for proven financial hardships, including lost sales directly attributable to the construction methods selected under the public-private partnership (P3) model. The court recognized the cumulative effects of the works as intolerable, though subsequent appeals by TransLink in 2020 overturned the damages awards on calculation grounds while affirming the interference's severity. Overall, more than 80 property owners and business operators claimed hundreds of thousands in collective losses, highlighting how the P3's emphasis on accelerated timelines and cost efficiencies contributed to inadequate mitigation measures despite community opposition to the chosen techniques. In , the elevated guideway along No. 3 Road necessitated post-construction street restorations to address aesthetic and access issues, but documented business-specific economic harms were less pronounced than in , with impacts varying by location and primarily involving temporary traffic rerouting rather than widespread closures. Critics of the P3 structure, including labor unions, argued that profit-driven decisions exacerbated community-level costs by favoring disruptive methods over less invasive alternatives, eroding local economic vitality during the build phase without sufficient compensatory funding or consultation. These effects underscore the trade-offs in rapid delivery, where upfront private efficiencies can amplify localized fiscal strains on small enterprises reliant on stable and vehicular patronage.

Controversies and Debates

Ridership Forecasting Accuracy

The Canada Line's pre-opening ridership forecasts, developed as part of the project's , projected approximately 100,000 weekday boardings by fall 2010. In practice, the line achieved this threshold ahead of schedule, with post-opening data showing average daily boardings of 83,000 in September 2009—shortly after launch—and rising to 105,000 by March 2010. By 2014, weekday ridership had surpassed 120,000, exceeding the near-term forecast. Annual boardings in the first full year of operation (to August 2010) totaled 36 million, reflecting strong initial demand driven by airport connectivity and . Growth persisted, with average weekday boardings reaching 150,000 in 2019, consistently outperforming original projections according to TransLink assessments. This pattern held into the early 2020s, though pandemic-related disruptions temporarily reduced volumes before a rebound; for instance, 2018 annual boardings stood at 48.7 million prior to impacts. The forecasting approach, informed by regional travel demand models, proved conservative relative to actual utilization, particularly for airport-bound traffic and Vancouver-Richmond corridors. While short-term targets were met or exceeded without significant shortfalls, the underestimation of long-term growth contributed to earlier-than-anticipated pressures, including and overcrowding. TransLink's contractual metrics with the private operator (InTransit BC) were fulfilled, as ridership thresholds tied to revenue-sharing and incentives were achieved promptly post-opening.

Design Choices and Capacity Constraints

The Canada Line features automated, driverless using two-car consists on a dedicated guideway combining tunnels in central and elevated sections toward and . Platforms were built predominantly at 40 meters long to match these lengths, with knock-out panels allowing extension to 50 meters at certain stations, reflecting a prioritized for swift under the 2009 opening deadline ahead of the . This configuration stemmed from the public-private partnership model, which allocated design-build-finance-operate responsibilities to InTransit BC to minimize public risk and expedite delivery amid tight timelines and budgets. Each two-car trainset accommodates approximately 334 passengers, including 41 seated per car, emphasizing standing for short trips. Minimum headways of two minutes enable up to 30 trains per hour per direction, supporting a of roughly 10,000 passengers per hour per direction (pphpd) under optimal conditions. Post-2020 fleet expansions raised effective service to about 8,000 pphpd with 24 trains per hour, but actual utilization often exceeds load factors during rush hours due to surging demand from links and suburban growth. Capacity constraints arise primarily from the inability to deploy longer without , which at many stations have reached their 50-meter maximum or face spatial limitations from adjacent . Extending to three-car consists could elevate to 15,000 pphpd, but this necessitates breaching end walls, lengthening, and contractual amendments with the operator, entailing billions in costs and years of disruption. manifests in passengers beyond seated limits, prompting modifications like seat removals in some cars to improve flow and standing room. Initial ridership forecasts underestimated post-opening growth, which exceeded projections by 2010 and continued rising, exposing the line's underbuilt nature relative to comparable extensions. Design emphasis on cost efficiency—yielding construction at about $167 million per kilometer—locked in lighter infrastructure unsuitable for unchecked demand expansion, fueling debates over whether parallel lines or rebuilds represent viable long-term remedies.

Hiring Practices and Labor Issues

The construction of the Canada Line involved the use of temporary foreign workers (TFWs) for tunneling operations, primarily through a subcontract with Italy-based SELI Overseas and Canadian partner SNC-Lavalin. In June 2006, construction unions alleged exploitation of dozens of these workers from , claiming they faced substandard wages, excessive hours, and poor living conditions compared to local standards. These claims led to legal action, culminating in a 2008 BC Tribunal ruling that found based on , as the TFWs were paid approximately 30-50% less than equivalently skilled Canadian workers for similar tasks. The tribunal ordered back pay, , and ; by April 2013, about 40 affected workers received settlements totaling tens of thousands of dollars each from the involved companies. In a related case, determined in August 2016 that SNC-Lavalin and SELI Canada wrongfully dismissed a who reported safety violations on the tunnel project, ruling it retaliatory under occupational health regulations. During operations, managed by ProTrans BC under the InTransit public-private partnership, labor tensions arose with maintenance and service staff represented by the BC Building Trades Council. In October 2023, the council successfully organized TFWs employed on the line, securing union protections amid complaints of intimidation tactics by employers, including non-work-related contacts that violated labor rules. Additionally, in September 2018, a switch to a new cleaning contractor resulted in the loss of jobs, benefits, and negotiated improvements for previously unionized janitors, prompting union protests over subcontracting practices that prioritized cost savings. Operator and attendant staff, under the Local 1724, threatened in February 2021 over demands for wage parity with and workers (who earned about 3% more), increased sick days from four to match regional standards, and better benefits. A tentative agreement averted disruption, but the dispute highlighted ongoing inequities in compensation tied to the Canada Line's separate operational structure. Earlier, in 2006, the Construction and Specialized Workers' Union Local 1611 filed complaints against Canada Line contractors, alleging anti-union tactics during construction hiring.

Community and Environmental Concerns

Construction of the Canada Line, completed in 2009 ahead of the , faced opposition in over the decision to build elevated guideways along sections like No. 3 Road, with some city councillors in 2004 advocating for at-grade alternatives to minimize visual and property impacts. Residents and officials expressed concerns that elevated structures would disrupt neighborhood aesthetics and lower property values, though the elevated design was selected for cost and speed. The public-private partnership (P3) model employed for the project drew criticism for inadequate community consultation, leading to significant disruptions during the 2005–2009 phase, including , dust, and noise affecting nearby businesses and residents in and . A analysis highlighted business revenue losses and resident nuisances, attributing these to rushed timelines and over-simplified impact assessments that allegedly misled stakeholders on construction severity. Legal claims, such as those from Hazel & Co., alleged misrepresentation of disruption levels, potentially paving the way for class actions, though outcomes favored the project proponents. Post-opening, some community groups raised fears of increased along the line due to expanded access, but a 2015 study found no evidence of elevated crime rates attributable to the Canada Line, countering perceptions in affected neighborhoods. Environmental concerns centered on in urban and airport-adjacent areas, necessitating remediation of contaminated sites along the alignment to secure permits and mitigate soil and groundwater risks. A fisheries and aquatic resources assessment evaluated potential impacts from bridge and guideway work near water bodies, implementing measures to protect salmon habitats and aquatic life during crossings and shoreline proximity. Operational analyses later confirmed net reductions from mode shifts to the line, outweighing construction emissions, with no major long-term ecological disruptions reported.

References

  1. [1]
    SkyTrain Schedules | TransLink
    Our three automated rapid transit SkyTrain lines take you all around Metro Vancouver. Find Schedule Quickly look up scheduled times for a specific bus stop, ...
  2. [2]
    Canada Line on track to meet Olympic deadline - TunnelTalk.com
    Mar 1, 2007 · The critical path on Vancouver's 19km long Canada Line rapid transit construction program is excavation of the 2.45km long twin bored TBM ...
  3. [3]
    Capstan Station - TransLink
    The newest Canada Line station is now open between Bridgeport and Aberdeen stations. Capstan Station features public art, retail space, and more.
  4. [4]
    It's official: the Canada Line opens Monday, August 17
    Aug 4, 2009 · The Canada Line has an opening date: Monday, August 17! We're already planning a huge celebration for the day, where you'll be able ride the Canada Line for ...
  5. [5]
    Visiting Vancouver | TransLink
    The Canada Line connects YVR airport and Waterfront Station in Downtown Vancouver. The total trip takes approximately 25 minutes. The Canada Line also offers ...<|separator|>
  6. [6]
    How Vancouver's Olympic Legacy Is Shaping the Future of Transit
    Mar 7, 2014 · The decision to build the Canada Line in this way was controversial. Critics—especially unions—said it was a form of privatization that ...<|control11|><|separator|>
  7. [7]
    Canada Line impacts still felt one year later | CBC News
    Aug 17, 2010 · The construction of the tunnel blocked traffic through the Cambie Village shopping area, forcing many business to relocate or face bankruptcy.
  8. [8]
    Canada Line Southbound - TransLink
    Get the latest timetable and real-time schedules for the Canada Line.
  9. [9]
    Cambie Street - AARoads Wiki
    Jul 27, 2025 · South of False Creek, the street is a major six-lane arterial road, and runs as a two-way north–south thoroughfare according to the street grid ...
  10. [10]
    Vancouver celebrates as Canada Line tunnel completed | CBC News
    Mar 2, 2008 · It will have 16 stations, two bridges, and approximately 19 kilometres of tunnel. The line is expected to be in operation in 2009. The tunnel ...
  11. [11]
    Broadway - City Hall Station Guide - The Canada Line
    Head north along Cambie Street for a great view of downtown Vancouver and to visit one of the many large chain stores, such as Home Depot, Canadian Tire or ...Missing: route | Show results with:route
  12. [12]
    Canada Line Skytrain | Tourism Richmond, BC
    Richmond's seven Canada Line stations are: YVR-Airport, Sea Island Centre, Templeton, Bridgeport, Lansdowne, Aberdeen and Richmond-Brighouse. Trips from YVR to ...<|separator|>
  13. [13]
    9 features to know about SkyTrain's newly opened Capstan Station
    Dec 20, 2024 · Capstan Station's platforms span a length of 52.5 metres, which is slightly longer than the Canada Line's previous longest platforms of 50 ...
  14. [14]
    The Buzzer rides the Canada Line!
    Jul 10, 2009 · The end of the Canada Line at Richmond-Brighouse. We got out at Richmond-Brighouse to get a feel for the station.
  15. [15]
    YVR-Airport Station - Vancouver - TransLink
    Get the latest timetable and real-time schedules for YVR-Airport Station.
  16. [16]
    Public Transportation - YVR
    The Canada Line is Vancouver's rapid transit rail connecting YVR to downtown Vancouver in under 30 minutes and to downtown Richmond in 18 minutes.
  17. [17]
    SkyTrain's Canada Line marks 15th anniversary - The Buzzer blog
    Aug 16, 2024 · The SkyTrain's Canada Line marks its 15th anniversary in 2024. While we celebrate 15 years of scenic connection between Richmond and downtown Vancouver.
  18. [18]
    British Columbia Rapid Transit Company | TransLink
    The Millennium Line joined the service starting in January 2002 with two stations (Sapperton and Braid). ... Canada Line Rapid Transit Project's Board of ...
  19. [19]
    Capstan Station opens on Canada Line in Richmond - TransLink
    Dec 20, 2024 · TransLink and the City of Richmond are announcing the newly completed Capstan SkyTrain Station on the Canada Line is now open to customers.<|control11|><|separator|>
  20. [20]
    Canada Line Skytrain Stations - Pro-Bel
    The Canada Line is a rapid transit line in the Metro Vancouver region of British Columbia, Canada, comprising of 19.2 kilometres (11.8 miles) of track.
  21. [21]
    Canada Line Stations - Perkins&Will
    We designed three stations along the Richmond segment of the new line: Aberdeen Station, Lansdowne Station, and Richmond-Brighouse Station.
  22. [22]
    Aberdeen Canada Line Station - Naturally Wood
    The Aberdeen Canada Line station has an economical concrete platform slab, and a steel superstructure above which wood is used to bring warmth and character.
  23. [23]
    Lansdowne Canada Line Station - Naturally Wood
    The station features a swooping arched wood roof, prefabricated wood panels, and a steel structure with wood for warmth, using Douglas-fir lumber.<|separator|>
  24. [24]
    Canada Line Stations - DIALOG
    Captured roof water spills down a concrete channel adjacent to the entry. Extensive frameless glazing allows clear sight lines to the plaza beyond, and spills ...
  25. [25]
    Canada Line Skytrain Stations - Fast + Epp
    The Canada Line Skytrain Stations was a collaboration with three architectural firms to design two at-grade and four elevated stations.
  26. [26]
    Canada Line Rapid Transit System - Architecture49
    The Canada Line spans two municipal authorities and travels through widely differing urban and suburban contexts. Construction included bored tunneling as well ...
  27. [27]
    Canada Line | Plenary
    Design features. The Canada Line features a mix of underground, elevated, and at-grade stations and track sections, connecting downtown Vancouver, Richmond ...
  28. [28]
    [PDF] Accessible Transit in Metro Vancouver - TransLink
    5420. Elevators and Escalators. • Elevators and escalators are at all SkyTrain stations, providing full access between the station entrance and platforms ...
  29. [29]
    Vancouver City Centre Station Guide - The Canada Line
    Vancouver City Centre Station offers easy access to offices, shopping, transit connections and everything downtown has to offer.
  30. [30]
    Hyundai Rotem Canada Line EMU
    Dec 28, 2023 · Fleet numbers ... SkyTrain Canada Line cars 101/201-132/232 are Hyundai Rotem EMU units that run exclusively on the Canada Line in 2 car sets.
  31. [31]
    First of 12 new trains for the Canada Line now in service (PHOTOS)
    Nov 4, 2019 · By early 2020, a total of 12 new additional two-car trains will enter service, increasing the Canada Line's train fleet size to 32 two-car ...
  32. [32]
    SkyTrain - CPTDB Wiki (Canadian Public Transit Discussion Board)
    SkyTrain ; Fleet, 406 cars 342 - Expo and Millennium lines 64 - Canada Line ; Technical. Line length, 79.5 km (49.4 mi). Track gauge, 1,435 mm (4 ft 8 1⁄2 in).British Columbia Rapid Transit... · Commercial–Broadway Station · Granville Station
  33. [33]
    SkyTrain Canada Line - Canadian Public Transit Discussion Board
    Dec 21, 2024 · SkyTrain Canada Line ; Number of stations, 17 ; Cities serviced, Vancouver, Richmond ; Termini, Waterfront · Richmond–Brighouse · YVR–Airport.
  34. [34]
    SkyTrain Fleet Expansion - TransLink
    Our new Mark V-model trains are longer than current trains with five interconnected cars and room for 25 per cent more customers. These trains allow us to ...
  35. [35]
    SkyTrain Evergreen extension opened with Thales' SelTrac control ...
    Dec 6, 2016 · Currently, SelTrac™ rail signalling equips 100 per cent of the SkyTrain network, including the Canada Line. The USD 1.431 billion project ...<|separator|>
  36. [36]
    SNC – Lavalin (Canada Line) - Vancouver - Alianz
    The Canada Line is an 18-km fully automated and grade-separated rail ... Need to learn fast all intricacies of Thales's SelTrac® Automatic Train ...
  37. [37]
    How digital twinning is making Canada's trains run on time
    Dec 16, 2022 · SNC-Lavalin operates and maintains the fully automated Canada Line rapid transit system under a Public-Private Partnership and concession ...
  38. [38]
    TransLink SkyTrain Canada Line Operations and Maintenance Centre
    Mar 14, 2023 · The SkyTrain Canada Line Operations and Maintenance Centre is located at 9851 Van Horne Way, Richmond, British Columbia, directly under the ...
  39. [39]
    CanadaLine
    Under a 31-year operations and maintenance contract, PROTRANS BC operates and maintains the award-winning Canada Line. A fleet of 20 trains provide a 26 ...
  40. [40]
    The Canada Line – AtkinsRéalis
    The Canada Line is North America's most efficient commuter rail line. It is a 19 km, fully automated commuter rail line and part of Vancouver's SkyTrain network ...
  41. [41]
    Virtual Canada Line improves maintenance - Business in Vancouver
    Jun 28, 2023 · The company estimates the use of this virtual Canada Line has helped reduce maintenance costs by 15 per cent. The Canada Line's digital twin ...
  42. [42]
    [PDF] Canada Line Final Project Report | Infrastructure BC
    Apr 12, 2006 · Canada Line is a 19km rail rapid transit system connecting downtown Vancouver, the. Vancouver International Airport and Central. Richmond. It ...<|separator|>
  43. [43]
    [PDF] Project Definition Report Summary - Environmental Assessment Office
    This is a summary of the Project Definition Report for the proposed rail rapid transit connection between Richmond, the Airport and. Vancouver (RAV). The report ...
  44. [44]
    A brief history of RAV - TheThunderbird.ca
    Oct 25, 2007 · Timeline: 1995: B.C Transit begins to discuss plans to commence a rapid transit project connecting Richmond Airport with Vancouver. 2003 ...
  45. [45]
    [PDF] City Council Records - City of Richmond
    Apr 18, 2001 · At its regular meeting on September 25, 2000, Council approved the Management Plan for the. Richmond/Airport-Vancouver Rapid Transit Project and ...
  46. [46]
    Richmond/Airport-Vancouver Rapid Transit Project report
    Apr 22, 2003 · The bus integration plan for the project shall be reviewed as part of the Vancouver Area Transit Plan process, due to start late this year. The ...
  47. [47]
    CANADA LINE BY THE NUMBERS - News
    2009 – Construction began in November 2005 and the Canada Line is scheduled to be operational in November 2009. The project is on budget and ahead of schedule.Missing: milestones | Show results with:milestones
  48. [48]
    Canada Line Project - Infrastructure BC
    The Canada Line is a rail rapid transit line connecting Richmond, the Vancouver International Airport and Vancouver, completed in August 2009, costing $1.9 ...
  49. [49]
    First Passengers Mark Canada Line Milestone
    Dec 15, 2016 · When finished in 2009, the Canada Line will carry people between the centre of Richmond, YVR and Vancouver's Waterfront Centre in 25 minutes or ...
  50. [50]
    CANADA, B.C. CELEBRATE NEAR COMPLETION OF CANADA LINE
    Mar 27, 2009 · VANCOUVER – The Canada Line is on track and will open by the Labour Day 2009 weekend, about three months earlier than originally scheduled.
  51. [51]
    SkyTrain's Canada Line celebrates 13th anniversary - The Buzzer blog
    Aug 17, 2022 · SkyTrain's Canada Line officially opened on August 17, 2009 celebrating 13 years of operation and transformation within our region.Missing: began | Show results with:began
  52. [52]
    TransLink adds new Canada Line SkyTrain station in Richmond - CBC
    Dec 20, 2024 · Capstan Station, located between the Bridgeport and Abderdeen Canada Line SkyTrain stations on No. 3 Road, opened on Friday.
  53. [53]
    [PDF] Canada Line Cut and Cover Tunnel Shotcrete Shoring
    Construction began in December 2005 using the anchored shoring method commonly used in. Vancouver. This system differs from the soil nailing system more ...
  54. [54]
    [PDF] The 14 - SEISMIC DESIGN OF THE CUT AND COVER TUNNEL OF ...
    The seismic design and construction of the cut and cover tunnel of the Canada Line Rapid Transit project have been presented in this paper. The design for ...
  55. [55]
    TUNNEL BORING BEGINS ON CANADA LINE IN VANCOUVER
    In total, the tunnel boring machine measures 86 metres in length, and 6.1 metres in diameter and weighs 440 tonnes (weight excludes backup). Electrically ...
  56. [56]
    Canada Line Rapid Transit Project Documents - World Bank PPP
    InTransitBC commits to design, build, partially finance, maintain and operate the Canada Line. InTransitBC is to assume most construction and operations risks.
  57. [57]
    Canada Line Construction - OKthePK
    The Canada Line is an urban transit rail line under construction in greater Vancouver, British Columbia, that was commenced on 1 Nov 2005.
  58. [58]
    CANADA LINE REACHES LANDMARK BREAKTHROUGH ...
    No. H 059/07. For release April 7, 2007. VANCOUVER -- Canada Line's tunnel boring machine (TBM) achieved a milestone today when it broke through the ground ...
  59. [59]
    [PDF] Evaluating the Canada Line 10 Years After Vancouver 2010
    The initially $1.6 billion RAV line was intended as a PPP to be jointly funded by the federal and provincial governments, the regional transit authority ( ...Missing: total | Show results with:total
  60. [60]
    Why is there an extra $5 fare on the Canada Line from Vancouver ...
    May 26, 2025 · The total cost to build the Canada Line came to $2.054 billion, including $720 million contributed by the private consortium led by AtkinsRealis ...
  61. [61]
    Canada Line | Plenary Americas
    The Canada Line is an automated light metro system, providing a high-capacity rail link between downtown Vancouver, YVR, and downtown Richmond.<|separator|>
  62. [62]
    [PDF] FTA/NCPPP Implementation of PPPs for Transit, Canada Line Case ...
    May 20, 2009 · Project is governed and managed by Canada Line Rapid Transit Co. (CLCO) and involves several equity partners and lending institutions.<|separator|>
  63. [63]
    PPP Profiles: Canada Line - Metropolitan Planning Council
    May 9, 2011 · Location: · Project Sponsor: · Private Partner: · Project Delivery: · Cost: · Funding Sources: Government of Canada: C$450 Million. Funding Program: ...
  64. [64]
    [DOC] FLORIDA I-595
    The Canada Line is a C$2 billion 12.1 mile (19.5 km) rail transit line that will connect downtown Vancouver, the City of Richmond and the Vancouver ...Missing: length | Show results with:length
  65. [65]
    [PDF] Public Private Partnership Foreign Case Studies Report
    Foreign PPP Case Study Analysis Report. FINAL. Page 42. Figure 20: Canada Line Governance Structure. The CLCO is a separate independently governed subsidiary of ...
  66. [66]
    Canada Line continues to break records: TransLink
    Feb 14, 2020 · Originally projected to reach just 120,000 daily boardings by 2025, it surpassed that number around 2011 or 2012, according to a TransLink ...
  67. [67]
    [PDF] TransLink 2022 Transit Service Performance Review
    Apr 26, 2023 · Canada Line ridership increased to 74% of fall 2019 levels. ... Average weekday daily boardings during fall 2022 were around 1.1 million boardings ...
  68. [68]
    [PDF] Transit Service Performance Review 2023 - Vancouver - TransLink
    Apr 29, 2024 · Ridership on the Expo and Millennium lines increased by 21% in 2023 compared to 2022, exceeding 100 million total boardings. The Canada Line ...
  69. [69]
    [PDF] TransLink 2024 Transit Service Performance Review
    May 21, 2025 · Boardings on the Expo and Millennium Lines grew by 6% in 2024, nearly double the system-wide rate, and Canada Line and SeaBus boardings grew by ...
  70. [70]
    [PDF] Transport 2050 Phase 2 Engagement Backgrounder - Action 2
    We'll also keep up with new technologies such as electrification and automation to make sure that transit remains a competitive and affordable travel choice ...
  71. [71]
    [PDF] 2018 Transit Service Performance Review - Vancouver - TransLink
    9%) and the Canada Line had 48 .7 million annual boardings. (+5 .3%) . Expo Line: Metrotown Station now has the second highest annual boardings ...
  72. [72]
    TransLink increases capacity on Canada Line rail service
    Jan 23, 2020 · After more trains are added to the service later this year, capacity will have been increased by 35 percent compared with 2019 service levels, ...<|separator|>
  73. [73]
    [PDF] 2017 Transit Service Performance Review - TransLink
    weekend passenger capacity increase. • Canada Line: increased weekday peak frequency and extended peak service, an. 11% weekday passenger capacity increase.
  74. [74]
    Reality Check: Has TransLink Again Mislead The Public?
    Apr 21, 2022 · The Canada Line can reach an ultimate capacity of 15,000 pphpd, with higher frequencies and longer trains accommodated by adopting a 50-metre ...Missing: utilization | Show results with:utilization
  75. [75]
    SkyTrain Expansion Program | TransLink
    From February 2024, for approximately 2 years, customers can expect major service pattern changes on the Expo Line when traveling from Columbia station toward ...
  76. [76]
    [PDF] 2025 Financial and Performance Report (as at June. 30, 2025)
    Sep 4, 2025 · Canada Line's service results were 2.7 per cent lower than the budget due to the deferral of a peak service increase that was planned to start ...Missing: load | Show results with:load
  77. [77]
    Canada Line Celebrates 200 Millionth Passenger
    Nov 21, 2014 · During the Vancouver 2010 Olympic Winter Games, 3.9 million passengers traveled on the Canada line during the 17-day Games. Highest single-day ...
  78. [78]
    How an Olympics P3 Transformed Vancouver's Public Transit
    Dec 26, 2019 · During the Olympics, the rail accommodated about 112,000 passengers daily and nearly 40 million annually.Missing: contribution | Show results with:contribution
  79. [79]
    Path to 2010 Olympics built from asphalt, steel - Vancouver Is ...
    Feb 11, 2020 · The transit line has been a boon for YVR, which contributed $300 million towards the $2 billion capital costs.
  80. [80]
    Evaluating the Canada Line 10 Years After Vancouver 2010
    Mar 26, 2021 · This article evaluates one such rapid rail transit investment linked to the Vancouver 2010 Olympics, the Canada Line.
  81. [81]
    As Canada Line turns 10, TransLink looks to future while avoiding ...
    Aug 17, 2019 · The opening of the Canada Line on Aug. 17, 2009, came after years of squabbles over rising costs, shrinking timelines, lost business revenue and traffic ...
  82. [82]
    TransLink wins appeal in long-running court battle over Canada ...
    May 14, 2020 · Speaking Thursday, he said the construction forced closures of 39 businesses from 2nd Avenue to 25th Avenue that couldn't pay their leases.<|control11|><|separator|>
  83. [83]
    Court rules Canada Line construction harmed Cambie Street business
    Sep 7, 2018 · A B.C. Supreme Court justice has awarded three Cambie Street merchants more than $180,000 as compensation for financial hardship experienced ...Missing: displacement | Show results with:displacement
  84. [84]
    1st group of Cambie Street business owners win damages in ... - CBC
    Sep 6, 2018 · Three Vancouver merchants have been awarded thousands of dollars as compensation for disruption to their businesses during construction of the Canada Line ...Missing: displacement | Show results with:displacement
  85. [85]
    Appeal forces Cambie merchants to wait for compensation in ...
    Oct 5, 2018 · More than 80 owners of properties and small businesses who suffered through noise, dust and fencing that impeded customer access while the ...
  86. [86]
    [PDF] taken for a ride: - the community impact of the canada line p3
    The Canadian Union of Public Employees has looked into the community costs and consequences of privatization of a transit project through a public private.
  87. [87]
    Canada Line Celebrates 200 Millionth Passenger - TransLink
    Nov 21, 2014 · The Canada Line has an approximate weekday ridership in excess of 120,000, exceeding the original forecast of 100,000 by fall 2010; During the ...Missing: projected | Show results with:projected
  88. [88]
    CANADA LINE CELEBRATES FIRST YEAR OF SERVICE - News
    Aug 17, 2010 · In one year Canada Line has recorded 36 million passenger boardings. On Aug. 6, 2010, TransLink released figures that show average daily ...
  89. [89]
    Canada Line continues to break records: TransLink - Richmond News
    Feb 12, 2020 · On an average weekday last year, the Canada Line had an average of 150,000 boardings, continuing to “outperform projections,” according to ...Missing: actual | Show results with:actual
  90. [90]
    SkyTrain's Canada Line ridership projected to soar this decade
    up from 48.7 million during 2018's full set of data, according to ...
  91. [91]
    Despite Extraordinary Ridership, Vancouver's New Canada Line is ...
    Nov 17, 2009 · The Canada Line's problems are representative of many areas of infrastructure investment across Canada. TransLink is under-funded, and some ...
  92. [92]
    Short platforms and trains: Is the Canada Line under-built and near ...
    May 13, 2016 · Most Canada Line platforms are only 40 metres long and expandable to 50 metres, though there are exceptions to a small number of stations that ...
  93. [93]
    New Canada Line trains increase service for customers
    Jan 21, 2020 · The maximum headway with all 32 trains is 2 minutes, or 30 trains per hour per direction, or 10000 pphpd. I don't think this will happen in 2020 ...Missing: length | Show results with:length
  94. [94]
    We need to rethink, reimagine, and rebuild SkyTrain Canada Line
    beyond 50 metres. This will allow for the Canada Line's two-car trains to be ...
  95. [95]
    Is the Canada Line at maximum capacity? No. Will it be in a decade ...
    – The current line has a capacity for 6,100 people per hour per direction. – At the latest count (yes, they go in and do physical counts), the line is carrying ...
  96. [96]
    Seating capacity reduced on overcrowded Canada Line trains in ...
    Aug 16, 2016 · Some Canada Line trains have had 10 seats removed from the interior in an effort to boost overall capacity, improve passenger circulation, ...Missing: constraints | Show results with:constraints
  97. [97]
    Canada Line is a model example of a poorly-designed, under-built ...
    Jul 9, 2019 · Currently, the Canada Line has a peak hour capacity of 6,100 pphpd, and this will increase to just over 8,000 pphpd when 12 new two-car trains ...<|separator|>
  98. [98]
    Friends Don't Let Friends Build PPPs - Pedestrian Observations
    Jan 15, 2021 · PPP-built lines do not have to have high construction costs. The Canada Line was cheap to build – it was Canada's last reasonable-cost ...
  99. [99]
    Canada Line tunnel workers exploited, say unions | CBC News
    Jun 1, 2006 · B.C.'s construction unions say dozens of foreign workers at the Canada Line rapid transit tunnel are the victims of exploitation, ...
  100. [100]
    Canada Line workers get money five years after Human Rights ...
    Apr 1, 2013 · The tribunal ordered the companies to pay the workers the difference between the salary paid to them and the salary paid to others, as well as ...
  101. [101]
    Canada Line foreign workers win wage settlement | CBC News
    Apr 3, 2013 · About 40 temporary foreign workers from Latin America have finally been paid the tens-of-thousands-of-dollars they were each owed for building the Canada Line ...Missing: issues | Show results with:issues
  102. [102]
    Employers dismissed mechanic after he had reported safety issues ...
    Sep 13, 2016 · In the 28-page decision, dated Aug. 26, WorkSafeBC ruled that SNC-Lavalin and SELI Canada had discriminated against David Britton in terminating ...Missing: controversies | Show results with:controversies
  103. [103]
    BCBT makes history by organizing Canada Line TFWs
    Oct 12, 2023 · Those included an order for the company to stop contacting workers for anything but work-related issues, finding it had intimidated them.
  104. [104]
    Canada Line's unionized janitors lose jobs to new cleaning company
    Sep 18, 2018 · As a result, the workers have lost their jobs, health and dental benefits, and other improvements secured in negotiations that concluded in ...
  105. [105]
    Transit strike averted as Canada Line workers reach tentative deal ...
    Feb 2, 2021 · The concerns from the workers included wage parity and sick leave issues. A strike and shutdown of the Canada Line would have come more than ...<|separator|>
  106. [106]
    Canada Line workers prepared to strike in Metro Vancouver
    Feb 2, 2021 · The union representing Canada Line employees continues to negotiate with Protrans BC but is holding off on job action while talks continue.Missing: practices | Show results with:practices
  107. [107]
    British Columbia Supreme Court finds Labour Relations Board ...
    Jun 15, 2009 · In 2006, the Construction and Specialized Workers' Union Local 1611 launched a series of unfair labour practices complaints against Canada Line ...
  108. [108]
    Letter: Do our leaders know what they're doing? - Richmond News
    Jul 19, 2017 · In 2004, a number of city councillors vehemently opposed elevated tracks for the Canada Line. They wanted an at-grade line running down No. 3 ...
  109. [109]
    Canada Line - Wikipedia
    It opened on August 17, 2009, ahead of the 2010 Winter Olympics. Canada Line.
  110. [110]
    The Canada Line Controversy - reVerb Communications
    Mar 6, 2025 · However, the final construction plan included extensive cut-and-cover tunneling along Cambie Street. This decision led to prolonged street ...
  111. [111]
    Case study: The community impact of the Canada Line P3
    Nov 24, 2016 · The construction of the Canada Line had significant negative impacts on the communities near the line, particularly due to a flawed consultation ...Missing: controversies | Show results with:controversies
  112. [112]
    [PDF] Taken for a ride: The community impact of the Canada Line P3
    Feb 22, 2011 · In addition to ballooning costs, secrecy that undermined the public interest, lack of compatible technology, and SNC-Lavalin's questionable ...
  113. [113]
    Canada Line Nuisance - Canadian Consulting Engineer
    Canada Line Nuisance · “Gross over-simplification” of construction impacts · Could lead to class actions · “Hazel & Co. claimed it was misled by representations ...
  114. [114]
    Dismantling fears and concerns of crime along Vancouver ...
    Aug 10, 2025 · The expansion of mass public transportation systems has often been resisted due to fears and concerns over an increased level of crime.
  115. [115]
    Transportation & Logistics: Canada Line - Next Environmental Inc
    This case study shows investigations and remediations of several contaminated sites for Canada Line to obtain necessary permits. Call 604-419-3800.
  116. [116]
    Canada Line Richmond, Vancouver International Airport
    The Fisheries and Aquatic Assessment examines impacts to fisheries and aquatic resources prospectively associated with the conceptual design, construction and ...
  117. [117]
    [PDF] ASSESSING THE GHG EMISSIONS EFFECTS OF THE CANADA ...
    In this paper, we compare two recent additions to urban public transportation networks in different countries to assess their potential in reducing GHG.