Intercity Express Programme

The Intercity Express Programme (IEP) is a government procurement initiative led by the to design, finance, manufacture, and maintain a fleet of new intercity trains for the and , replacing ageing high-speed diesel fleets such as the InterCity 125. Initiated in 2005 with contracts awarded in 2012 to a Hitachi-led under a public-private partnership model, the programme encompasses a 27.5-year agreement valued at approximately £5.7 billion, delivering over 200 bi-mode and electric multiple units classified as Class 800 and Class 801 series from Hitachi's family. Key features of the IEP trains include bi-mode capability allowing seamless operation on both electrified and non-electrified routes via onboard generators, increased capacity by 16% over predecessors, lighter construction for improved (18% less energy per seat-kilometer), and modern interiors enhancing comfort and . The first arrived in the UK in 2015, with passenger services commencing on the Great Western route in 2017 and the East Coast in 2018, enabling faster journey times and higher frequencies between and cities such as , , , and Newcastle. The programme has driven significant economic impacts, including the creation of over 900 direct jobs and thousands more in the , alongside upgrades like depots and route enhancements to support the new . While delivering on expansion and reliability improvements amid growing , the IEP has faced over initial estimates and integration with delayed projects, though empirical performance data post-deployment indicates enhanced and passenger satisfaction.

Overview and Objectives

Programme Rationale and Scope

The Intercity Express Programme was launched by the in June 2005 to replace the aging fleet, which dated from the 1970s and faced rising maintenance costs and reliability risks by the mid-2000s due to structural fatigue, component wear, and the practical limits of extending overhauls beyond original design lives of around 30 years. These High Speed Trains, while operationally successful in their era, incurred disproportionate upkeep expenses relative to their residual value, with projections indicating unsustainable expenditures without modernization, particularly as passenger volumes grew and safety regulations tightened. The rationale emphasized sustaining high-speed intercity connectivity on key routes without compromising service frequency or punctuality, prioritizing fleet renewal over incremental refurbishments that would yield diminishing returns. In scope, the programme targeted the —from Paddington to destinations in the , , and —and the —from King's Cross to , with intermediate stops—encompassing the replacement of approximately 200 High Speed Trains and associated Mark 3 coaching stock or InterCity 225 swallow sets. It involved procuring bi-mode trains operable under diesel power or 25 kV AC overhead electrification, a configuration selected amid limited committed wiring plans in 2005–2007, to enable seamless through-services on mixed infrastructure without diesel-only constraints or full diesel dependency. The initiative was divided into two parallel but interdependent lots for these corridors, with initial contracts for 112 five- or nine-car sets (expandable to 225 via options), focusing on outputs like maximum speeds of 125 mph under diesel and 140 mph under electric traction, alongside depot upgrades and signaling compatibility. Core design goals integrated expansion—aiming for 20–30% more seats per train through efficient layouts and wider use of standing areas during peaks—with reliability exceeding % fleet availability, reduced journey times via lighter structures and traction improvements, and enhanced passenger facilities including step-free , onboard , and systems to address documented shortcomings in legacy stock. Environmental considerations, such as lower emissions per passenger-km through electric mode efficiency on wired sections, were secondary to operational imperatives, though the programme aligned with broader network demands for decarbonization potential without mandating it upfront. emphasized value for money via a public-private , with risk transfer to suppliers for , , and financing over a 27.5-year term.

Key Specifications and Design Goals

The Intercity Express Programme (IEP) sought to deliver trains capable of operating at a maximum service speed of 125 mph (201 km/h) on the (ECML) and (GWML), with design provisions for future upgrades to higher speeds up to 140 mph (225 km/h). Primary objectives included boosting network capacity to handle rising passenger demand, estimated to require up to 2,000 vehicles in the long term, while replacing aging High Speed Trains (HSTs) and sets nearing the end of their service life. Emphasis was placed on bi-mode capability, allowing seamless switching between electric (25 kV AC overhead) and diesel self-power modes at any speed to support routes with incomplete electrification, thereby minimizing diesel dependency as infrastructure upgrades progressed. Design goals prioritized , targeting specific consumption limits such as no more than 4,600 kWh for a 130 m electric unit on the Kings Cross to Newcastle route, alongside and metering for precise billing. Reliability targets mandated full functionality under diverse conditions, with rapid embarkation/disembarkation—up to 240 passengers per minute for a 208 m unit—and short dwell times of around 2 minutes at stations to optimize throughput. Passenger-focused enhancements included flexible interior layouts with at least 144 m of furnishable space per 208 m unit, HVAC systems compliant with BS EN 13129-1:2002 for air quality under crush loads, and provisions for , per-seat power sockets, and real-time information displays. Safety features incorporated (AWS), Train Protection and Warning System (TPWS), and compatibility with (ETCS) Level 2, alongside selective door operation integrated with GPS and systems. Train configurations ranged from 5-car (130 m) to 10-car (260 m) sets, with nominal vehicle lengths of 24–26 m and maximum of 0.75 m/s² to enable efficient utilization on congested lines. Overall, the programme emphasized whole-system , environmental through reduced emissions via bi-mode efficiency, and adaptability for future , while maintaining under a 27.5-year public-private .

Historical Development

Initiation and Early Planning (2007–2009)

![Hitachi Super Express mockup](./assets/Hitachi_Super_Express_mockup_$1 The Department for Transport (DfT) formally initiated the procurement process for the Intercity Express Programme (IEP) in March 2007, marking the UK's largest investment in new rolling stock in over three decades. The programme aimed to replace ageing InterCity 125 high-speed diesel trains built between 1976 and 1982, which were facing escalating maintenance costs and capacity constraints amid projected passenger growth of up to 50% by 2015-16 on key routes including the Great Western Main Line (GWML) and East Coast Main Line (ECML). Initial planning emphasized bi-mode trains capable of operating under diesel, electric, or hybrid power to accommodate partial electrification, while prioritizing increased seating capacity, improved passenger comfort, enhanced safety features, and lifecycle cost reductions through a 35-year public-private partnership structure. On 16 August 2007, the DfT announced a shortlist of bidders following expressions of interest, narrowing the field to qualified consortia for further evaluation. By 16 November 2007, three preferred bidders— with Rail, the Express Rail Alliance (comprising , , , and ), and Europe—were invited to submit detailed tender proposals for designing and supplying up to 2,000 carriages across six routes. This phase involved collaborative development of initial specifications, including lighter-weight designs for energy efficiency and sustainability, with bidders tasked to propose innovative solutions balancing performance and whole-life costs. In February 2008, Alstom-Barclays withdrew from the competition, citing commercial risks amid rising material costs and economic uncertainty, leaving two consortia to refine bids due by May 2008. Early planning progressed amid the global , prompting DfT assessments of bidder financing capabilities. By May 2009, the DfT's updated projected a benefit-cost ratio of 1.2 for the programme, justifying continuation despite delays, while a strategic shift toward full GWML reduced reliance on diesel-only units and influenced evolving design requirements. These adjustments reflected causal pressures from infrastructure upgrades and fiscal constraints, ensuring alignment with broader rail network sustainability goals without compromising core capacity and reliability objectives.

Tender Process and Bidding (2008–2010)

The Department for Transport issued the Invitation to Tender for the Intercity Express Programme on 16 November 2007 to three pre-qualified consortia shortlisted in August 2007: Alstom-Barclays Rail Group, Express Rail Alliance (Bombardier Transportation, Siemens Mobility, and Angel Trains), and Hitachi Europe Ltd. The ITT sought bids for manufacturing, financing, and maintaining up to 2,000 bi-modal train carriages capable of 140 mph operation on electrified lines and diesel fallback on non-electrified sections, with submissions due by May 2008. Alstom-Barclays withdrew in February , stating a strategic focus on enhancing existing technology rather than pursuing the IEP's novel hybrid requirements. This reduced competition to two primary bids: Express Rail Alliance, proposing a consortium-led conventional design, and Agility Trains, a newly formed entity with Ltd. holding a 40% stake alongside investors like John Laing, emphasizing Shinkansen-derived modular construction for cost efficiency and adaptability. Bidders refined proposals through 2008, incorporating feedback on specifications such as gangwayed end cars for flexibility and all-electric traction systems to minimize emissions. In September 2008, Agility Trains unveiled preliminary mock-up designs highlighting distributed traction, lightweight aluminum bodies, and rapid reconfiguration capabilities between nine- and five-car formations. On 12 February 2009, Agility Trains was designated the preferred bidder, based on evaluations favoring its lower lifecycle costs, domestic manufacturing commitments at a proposed plant, and alignment with programme goals for across routes. Negotiations extended into 2010 amid escalating estimates—initial bids projected £5.5 billion but faced upward pressure from commodity prices and scope refinements—delaying contract finalization and prompting interim fiscal reviews by July 2010. The process highlighted tensions between innovation demands and budget constraints, with Agility's bid scrutinized for risks in unproven bi-mode technology despite its competitive financing model.

Independent Review and Restructuring (2010)

In March 2010, the (DfT) commissioned Sir Andrew Foster, former chief executive of the Audit Commission, to undertake an independent review of the Intercity Express Programme (IEP) amid concerns over its affordability following receipt of bids that exceeded initial projections by approximately 25-30%. The review was prompted by the post-2008 , which had constricted debt markets essential for the programme's planned private finance structure, alongside rising procurement costs estimated at £5.9 billion for 1,300 new vehicles. Foster's report, delivered in June 2010 and published on 6 July 2010, affirmed the strategic necessity of replacing the ageing fleet—whose maintenance costs were projected to rise sharply beyond 2010—due to capacity constraints on the East Coast and Great Western main lines. However, it highlighted that the Agility Trains consortium's bid (led by ) did not demonstrate clear value for money at prevailing prices, attributing overruns to optimistic initial assumptions, limited competition, and market disruptions rather than programme mismanagement. Foster noted technical feasibility for alternatives, such as re-engineering existing high-speed trains () for service until 2025-2030 at lower short-term cost, but cautioned against indefinite deferral given long-term reliability risks. Key recommendations included proceeding with Agility Trains as preferred bidder while aggressively renegotiating terms to reduce , scrutinizing the viability of bi-mode (dual electric/diesel) trains for unelectrified sections of the Great Western route due to potential efficiency penalties, and exploring financing to mitigate reliance on impaired private debt markets. Foster urged the DfT to enhance risk-sharing with suppliers and conduct sensitivity analyses on fleet sizing (e.g., reducing from 1,300 to fewer units if timelines accelerated). He emphasized that cancellation risked higher future expenses from fleet life extensions exceeding £1 billion cumulatively. The incoming , post-May 2010 election, integrated Foster's findings into its October , deferring a final IEP decision pending fiscal reassessment. On 25 November 2010, announced programme continuation with restructuring: abandonment of the original public-private partnership leveraging private finance (which had inflated costs via higher borrowing spreads), replaced by direct DfT funding of £4.7 billion in —enabling cheaper sovereign borrowing rates—and a simplified lease-back arrangement with Agility Trains. This shift aimed to deliver savings of around £2 billion over the lifecycle compared to pre-review bids, while retaining bi-mode capability pending electrification decisions, though it exposed to greater upfront risk. The restructured path paved the way for contract award in 2011, prioritizing delivery timelines over expansive involvement.

Contract Awards and Finalization (2011–2012)

In March 2011, following the government's restructuring of the Intercity Express Programme after its 2010 pause due to escalating costs, the confirmed its intent to proceed with the Agility Trains consortium's revised bid, retaining them as the preferred supplier despite earlier financial liquidity challenges. The revised proposal incorporated cost reductions, including a shift toward bi-mode (electric and ) trains to accommodate incomplete timelines, and commitments to UK-based manufacturing to stimulate domestic jobs and supply chains. The programme's first major contract award occurred on July 25, 2012, when financial close was reached for the phase with Agility Trains West Coast Limited, a special-purpose formed by Europe (responsible for train design and manufacture) and John Laing (handling financing and investment). This £4.5 billion public-private partnership agreement, spanning 27.5 years, encompassed the of 57 Class 800 and Class 802 bi-mode sets totaling 378 carriages, the of new maintenance depots at Stoke Gifford and , and the refurbishment of the existing . The deal required to establish a train assembly facility in , , creating over 700 direct jobs and supporting long-term maintenance obligations. Finalization of the contract marked a pivotal shift from the original all-electric train specification under the cancelled Siemens-led deal, prioritizing fiscal prudence and operational flexibility amid budgetary constraints post-2008 . The phase remained pending, with its separate financial close achieved in April 2014 under Agility Trains East Coast Limited for an additional 65 trainsets. This phased approach allowed the government to mitigate risks while securing private financing for 60% of the capital costs, with the remainder funded through public borrowing.

Procurement and Financial Framework

Agility Trains Consortium and Hitachi Involvement

Agility Trains Ltd. was formed as a special-purpose consortium to bid for the UK's Intercity Express Programme (IEP), with the primary objective of supplying, financing, and maintaining a new fleet of high-speed bi-mode trains. Established in 2008, the consortium was led by Japanese manufacturer Hitachi Ltd., which held a 40% stake at the time of its selection as preferred bidder. Other initial shareholders included UK-based investors focused on infrastructure financing. On 12 February 2009, the announced Agility Trains as the preferred bidder for the IEP contract, following a competitive process initiated in 2008. Hitachi's proposed Super Express train design, based on its platform, featured electro-diesel bi-mode capability to operate on both electrified and non-electrified sections of the and . The bid emphasized fixed-price delivery over approximately 30 years, with Agility Trains responsible for train availability and performance. The programme faced delays after the 2009 announcement due to an independent review prompted by the and fiscal austerity measures, which restructured the to separate train supply from infrastructure upgrades. Despite this, Agility Trains retained its position, and financial close was achieved in July 2012 with a £4.5 billion contract awarded to the consortium, now comprising Hitachi Rail Europe and John Laing Investments. Hitachi's stake in Agility Trains increased to 70% by 2011, underscoring its dominant role in execution. Hitachi's core involvement encompassed the design, manufacturing, and initial testing of the Class 800 and Class 801 units, with starting at its Kasado Works in before transferring to a new facility in , , to support domestic content requirements. The consortium's public-private partnership model shifted financial risk from the to private investors, with Agility Trains owning the 122-train fleet (596 vehicles) and providing lifecycle through dedicated depots. This structure facilitated entry into service from 2015 on the Great Western route and 2016 on the East Coast, totaling over 5,800 vehicles in operation by 2020.

Public-Private Partnership Structure

The Intercity Express Programme (IEP) employed a framework to deliver new intercity train fleets, marking the first such model for mainline in the . The UK (DfT) acted as the procuring authority, awarding to two special purpose vehicles—Agility Trains West Ltd for the services and Agility Trains East Ltd for the services. These entities, owned 70% by Ltd and 30% by John Laing plc, were responsible for the , finance, and maintain (DBFM) elements of approximately 122 trainsets over a 27.5-year period. The PPP structure integrated private sector financing and risk management to address the programme's scale, estimated at a £5.7 billion capital value. Financial close was achieved for the Great Western phase on 26 July 2012 and for the East Coast phase on 16 April , following selection of the Agility Trains as preferred bidder in February 2009 and contract confirmation in March 2011. Funding comprised commercial loans, with up to £2.2 billion in co-financing, including approximately £1 billion from the (JBIC) and contributions from the (EIB) alongside private lenders such as The Bank of Tokyo-Mitsubishi UFJ Ltd, Bank plc, and Mizuho Corporate Bank Ltd. A 2014 refinancing effort yielded £60 million in savings for the project companies. Under the Master Availability and Reliability Agreement, the DfT guaranteed monthly availability payments to train operating companies, with deductions applied for failures in train availability, reliability, or performance metrics. Risk allocation transferred , , and responsibilities to the private partners, while the DfT retained exposure to exogenous factors such as delays from or electrification shortfalls on the Great Western route. Innovations included provisions for "contemplated variations" to handle foreseeable changes, such as the shift to bi-mode (electric/diesel) s amid electrification delays, and a unified overseeing both project phases to optimize efficiencies.

Cost Breakdown and Funding Mechanisms

The Intercity Express Programme (IEP) was structured as a (PPP), whereby the UK (DfT) contracted Agility Trains—a comprising , John Laing, and others—to , finance, and maintain 122 bi-mode and electric trainsets, along with associated depots and upgrades. The contracts, finalised in 2012, had a headline value of £5.7 billion, encompassing initial for and depot estimated at around £4.5 billion, with the remainder allocated to 27.5-year maintenance and performance obligations. This whole-life costing approach shifted financing and operational risks to the , including delays and performance shortfalls, in exchange for DfT's fixed monthly availability payments tied to train reliability metrics. Capital expenditure breakdown included approximately £2.7 billion for the (ECML) fleet phase (57 trainsets, depots at and ), and a similar scale for the (GWML) phase (65 trainsets, depots at and Stoke Gifford), with additional provisions for route enhancements like . Manufacturing costs were influenced by Hitachi's supply chain efficiencies, though UK assembly at added localisation premiums; per-unit estimates for Class 800/801 sets hovered around £40 million, reflecting bi-mode technology premiums over conventional electric trains. A 2010 independent review identified cost pressures from rising debt financing and exchange rates, prompting restructuring that capped DfT exposure at affordability limits, with future payments projected at £7.65 billion in 2014 prices to cover lifecycle support. Funding mechanisms relied on private capital, with Agility Trains securing debt from commercial banks, a £1 billion loan from the European Investment Bank (EIB), and support from Japanese export credit agencies to mitigate currency risks for Hitachi's involvement. No upfront DfT equity was provided; instead, revenue streams commenced post-service entry in 2015–2017, via performance-indexed payments averaging £25–£30 per unit mile operated, incentivising uptime above 90% to avoid penalties. This model drew scrutiny in National Audit Office assessments for potentially inflating long-term costs compared to outright purchase, as private financing margins exceeded public borrowing rates by 2–3%, though it aligned with fiscal rules limiting immediate public spending. Contingency provisions absorbed variances, such as £120 million in infrastructure adaptations, without derailing the programme's value-for-money ratio of approximately 1.4.

Manufacturing and Production

Facilities and Supply Chain

The assembly of Intercity Express Programme (IEP) trains primarily occurred at Rail's dedicated manufacturing facility in , , , which was constructed as part of the programme to localize production and stimulate regional employment. Opened in September 2015 following an £82 million investment, the plant handled the final assembly and outfitting of the bulk of the fleet, including bi-mode Class 800 and electric Class 801 units, with production spanning from 2016 onward. This facility created approximately 730 direct jobs in the local area and incorporated advanced processes such as , , and systems integration tailored for high-speed . Initial prototype and early production units were manufactured at Hitachi's established Kasado Works in Kudamatsu, , prior to the full transition to UK-based assembly; for instance, the first Class 800 trainset departed Kasado in January 2015 for testing and delivery. This Japanese facility provided engineering expertise and component pre-assembly, leveraging Hitachi's global experience from projects like Japan's , before the programme emphasized domestic capabilities to meet requirements for industrial revival in the North East. The IEP supply chain encompassed over 1,400 suppliers, with a strategic focus on -based firms to maximize economic benefits, including more than 130 companies in the region alone. Key components such as precision-engineered parts from firms like Hydram Engineering in were sourced locally, supporting sectors like hydraulics and fabrication, while coordinated global inputs for specialized elements including traction systems and bogies. This structure, managed through the Agility Trains consortium, aimed to distribute approximately 70% of contract value within the , fostering a resilient network that delivered 596 carriages while mitigating risks through diversified sourcing and quality assurance protocols.

Assembly and Quality Control Processes

Assembly of Intercity Express Programme (IEP) trains began with pre-series units at Hitachi's Kasado Works in Kudamatsu City, Yamaguchi Prefecture, Japan, where the first Class 800 train was completed and unveiled in November 2014 before shipment in January 2015. Car bodies featured lightweight aluminum alloy double-skin structures joined by friction stir welding to achieve high strength with minimal distortion. Bogies employed a bolsterless design, with trailer variants using inner frame structures to reduce unsprung mass. The majority of the 122-train fleet underwent final assembly at Hitachi's Newton Aycliffe facility in , , which opened in 2015 and employed around 730 workers for integrating bodyshells shipped from with propulsion systems, interiors, and bi-mode capabilities. Modular allowed configurations of 5, 9, or up to 12 cars via standardized intermediate units and automatic couplers enabling in under 2 minutes. The first UK-assembled train was unveiled in December 2016. Quality control integrated progressive design assurance processes for train control systems and overall safety, ensuring compliance with Technical Specifications for Interoperability (TSI), Railway Group Standards, and EN 15227 for . Full-scale interior mockups underwent inspections to verify specifications, while numerical simulations validated collision with deformation predictions accurate to within 1%. Post-assembly testing at sites included equipping units with measurement devices for network trials starting April 2015, alongside ride comfort (Ride Index below 1.6), noise (below 57 dB at maximum speed), and reliability assessments under BS EN standards. Independent risk assessments by covered impacts and safety-critical areas.

Testing, Deployment, and Operations

Pre-Introduction Testing Phases

Three pre-series Class 800 bi-mode multiple units were constructed by at its Kasado Works in as part of the Intercity Express Programme to validate design and performance prior to full production. These units underwent initial low-speed running trials in starting in September 2014 to assess basic functionality and systems integration. systems, supplied from the , were installed on these trains for early evaluation of compatibility. The first pre-series five-car set, designated 800-001, departed the Kasado factory on January 7, 2015, and arrived in the UK in March 2015 for further evaluation. Upon arrival, it was fitted with measurement devices to support comprehensive testing managed by Europe. Post-delivery trials commenced at the near in April 2015, focusing on dynamic performance, braking, and bi-mode propulsion switching between diesel and electric modes. This phase included closed-circuit runs to simulate operational conditions and verify structural integrity under UK loading gauges and track geometries. Subsequent testing expanded to route-specific validation, including night-time operations on a Signal Protected Zone along the to evaluate signaling interactions and higher speeds. By , pre-series units underwent (ETCS) certification trials, with unit 800-002 tested on the Hertford Loop between and to ensure compliance with in-cab signaling requirements. Network-wide acceptance testing, including runs to in , confirmed reliability across diverse terrains and confirmed the trains' readiness for passenger service without major deviations from specifications. These phases culminated in regulatory approvals, enabling entry into on the in October 2017.

Rollout Timeline and Initial Services

The rollout of Intercity Express Programme trains began with Great Western Railway (GWR) introducing Class 800 bi-mode units into passenger service on 16 October 2017. The inaugural revenue run departed Bristol Temple Meads at 6:00 AM bound for London Paddington, marking the entry of the first production trains under the programme. Initial operations concentrated on high-demand routes including London Paddington to Bristol Temple Meads and , replacing select High Speed Train sets while providing increased capacity of up to 40% more seats per train. Deployment expanded progressively through 2018, with additional units entering service to support services extending to , , and , ahead of full electrification completion in 2019. On the , () initiated Azuma-branded services using Class 800 and 801 trains on 15 May 2019, starting with routes from London King's Cross to . The introduction proceeded incrementally, adding approximately one train per week to the timetable, with extensions to Newcastle and achieved by 30 May 2019 via the 05:40 Edinburgh to London King's Cross service. Further rollout included Glasgow-London services from 23 September 2019, enabling bi-mode operation on non-electrified sections and supporting timetable enhancements for improved frequency and reliability. Across both main lines, the programme aimed for full fleet integration of 122 trainsets by , though actual operational ramp-up varied by operator and route due to , crew training, and dependencies. Early services emphasized bi-mode flexibility to gaps in progress, with GWR units operating predominantly in diesel mode initially on the .

Maintenance Depots and Lifecycle Support

The Intercity Express Programme (IEP) incorporated dedicated maintenance facilities to service the AT300 fleet, including Class 800 bi-mode units, with several new depots constructed or upgraded under the public-private partnership framework led by Agility Trains (a -led ). These facilities support routine inspections, heavy maintenance, stabling, and ancillary functions such as fuelling and washing, tailored to the trains' bi-mode design requiring both electric and diesel capabilities. Key depots include the Stoke Gifford facility near , which features a purpose-built ten-car maintenance shed, carriage wash, and storage sidings primarily serving Great Western Railway (GWR) services on the . Additional GWR-supporting sites encompass Acton in for lighter servicing and Laira in , where contracts sustain over 500 skilled jobs focused on IEP . For the East Coast Main Line, the Doncaster Carr depot provides comprehensive overhaul and stabling for (LNER) fleets, integrated with Hitachi's manufacturing operations in the area. The in London's underwent reconfiguration to accommodate IEP train servicing, enhancing capacity for intercity routes.
Depot LocationPrimary Operator ServedKey Facilities
Stoke Gifford (Filton Triangle), BristolGWRTen-car maintenance shed, carriage wash, storage sidings
Acton, West LondonGWRTrain care and light servicing
Laira, PlymouthGWRHeavy maintenance, job-sustaining operations
Doncaster CarrOverhaul, stabling, integration with manufacturing
North Pole, IEP fleets (multi-operator)Refurbished servicing bays
Lifecycle support under the IEP contract extends for 27.5 years from award, with Agility Trains obligated to , maintain, and ensure train availability through an Interface Agreement specifying performance standards, defect rectification, and modifications. provides ongoing technical support, including component supply chains like braking systems from partners such as , to address wear from high-speed bi-mode operations and mitigate reliability issues observed in early service. This structure aims to optimize whole-life costs but has faced scrutiny for dependencies on operator adherence and progress.

Technical Features and Performance

Propulsion Systems and Bi-Mode Capability

The Class 800 bi-mode trains of the Intercity Express Programme feature a distributed that integrates electric traction with generation for operation on both electrified and non-electrified routes. In electric mode, is supplied via pantographs from 25 50 Hz overhead lines, processed through transformers and IGBT-based inverters to drive asynchronous AC traction motors on each , delivering a maximum operating speed of 125 (201 km/h) and of 0.70 m/s². Diesel propulsion relies on underfloor Generator Units (GUs), each powered by an MTU 12V 1600 R 80 L V12 engine with 21.0 L displacement, rated at 700 kW output at 1,900 rpm maximum speed, coupled to alternators that feed the common traction and auxiliary power systems. These engines incorporate urea selective catalytic reduction (SCR) exhaust systems to meet EU Stage IIIB emissions standards, with each main traction motor rated for 226 kW continuous power and four motors per supply converter. Bi-mode capability enables automatic, seamless switching between electric and modes at any speed or while stationary, using onboard controls that select sources based on availability detected via trackside balises or sensors, eliminating the need for mode changes at terminals. A five-car set typically includes three GUs for , while nine-car sets have five, providing sufficient for intercity services on partially electrified lines like the . This approach, unique to the IEP's AT300 , supports transitional strategies without full dependency. In contrast, the electric-only Class 801 variant omits primary diesel GUs, relying on power with auxiliary GUs for emergencies or limited non-electrified running in locomotive-hauled configuration. The unified traction across modes optimizes by reusing inverters and motors, though diesel output is lower than full electric capacity, reflecting compromises in bi-mode design for UK network constraints.

Energy Efficiency and Capacity Enhancements

The Class 800 bi-mode trains under the Intercity Express Programme incorporate advanced propulsion and lightweight construction to enhance energy efficiency, particularly in electric mode where overhead lines are available. The electric-only Class 801 variant consumes 17% less energy per passenger kilometer than the diesel-powered Intercity 125 High Speed Train (HST) and 12% less than the electric Intercity 225, while emitting over 40% less CO₂ per passenger kilometer than the HST and nearly 10% less than the Intercity 225. In comparison to existing electric rolling stock, the Class 800 series achieves a 12% reduction in energy and carbon emissions per person per journey. These gains stem from features such as aluminum alloy car bodies using double-skin structures and friction stir welding for reduced weight, regenerative braking via electrically actuated pneumatic systems with brake choppers, and a Driver Advisory System that optimizes power usage based on timetables and route profiles. The MTU V12 diesel generator units in bi-mode operation offer thermal efficiencies exceeding 40%, surpassing older diesel locomotives, though self-powered (diesel) mode lacks a mandated efficiency target in the programme specification. Bi-mode capability further bolsters efficiency by prioritizing electric traction on electrified sections—such as the post-2018 upgrades—minimizing reliance on less efficient generators and enabling seamless transitions without performance loss on mixed routes. This approach avoids the energy penalties of -electric conversion in traditional locomotive-hauled sets, with urea selective catalytic reduction systems on generators meeting EU Stage IIIB emissions standards to curb output. Overall, these elements support projected lifecycle reductions in fuel and use, though real-world mode efficiency remains constrained by the inherent thermodynamic limits of engines compared to full electric operation. Capacity enhancements address peak-hour demand on routes like the East Coast and Great Western Main Lines, with fixed-formation multiple units allowing denser seating without space. A 200-meter equivalent configuration provides over 30% more seated capacity than the . Specific configurations include 315 seats in a 5-car set (45 , 270 ) and 627 seats in a 9-car set (101 , 526 ), enabling up to 12-car formations by units. A 9-car train adds 131 seats over the and 188 over a comparable off-the-shelf 9-car unit, incorporating wider aisles and 50 mm extra legroom in airline-style seats without reducing overall . By 2030, the programme was projected to increase morning peak seats by 40% into London Paddington and 28% into King's Cross relative to 2011 levels, yielding over 10,000 additional daily seats on Great Western services alone upon full rollout. These improvements facilitate higher frequency and load factors, though bi-mode weight from underfloor generators slightly offsets potential gains versus pure electric designs.

Speed, Reliability, and Operational Metrics

The Intercity Express Programme (IEP) trains, primarily the Class 800 bi-mode units and Class 801 electric units, operate at a maximum service speed of 125 mph (201 km/h) across electrified and non-electrified sections of the and . These trains were designed with a higher capability of up to 140 mph (225 km/h), though limits, including signaling and , restrict routine operations to 125 mph in electric mode and equivalent performance. Acceleration rates meet requirements for diagrams specifying up to 0.75 m/s² under laden conditions, enabling efficient adherence to timetabled journey profiles. Reliability targets for IEP fleets specify 27,000 miles mean time in need (MTIN) for Class 800 bi-mode trains and 54,000 miles MTIN for Class 801 electric trains, reflecting contractual expectations for fault intervals in operational service. Early deployment phases encountered higher failure rates consistent with the "bathtub curve" of new , but by 2024, reported its fleet, dominated by IEP units, achieving reliability rates three times the national industry average, attributed to matured protocols and refinements. Operational metrics for operators deploying IEP trains show mixed but improving performance. In the April to June 2025 quarter, Great Britain's overall Public Performance Measure (PPM)—the percentage of trains arriving within 10 minutes of schedule—stood at 87.1%, with Great Western Railway (GWR) recording a 0.7 improvement in on-time arrivals compared to the prior year. (LNER), reliant on Class 800/801 Azuma trains for most intercity services, saw train cancellations fall by 1.7 s year-over-year, contributing to network-wide reliability gains amid post-pandemic recovery. Capacity metrics include up to 108 seated passengers per intermediate vehicle under standard loads, supporting peak-hour demands with dwell times limited to 1-2 minutes for efficient station throughput.

Criticisms, Challenges, and Controversies

Delays, Cost Overruns, and Budgetary Realities

The process for the Intercity Express Programme (IEP) was delayed by over three years, with the awarded to in July 2012 instead of the originally planned April 2009. This stemmed from a 2010 government review that cancelled the initial Agility Trains bid due to inadequate value for money, prompting a re-tender that prioritized domestic and reduced upfront capital costs. The revised approach lowered estimated costs from around £7.5 billion to £4.5 billion for the core fleet, though total lifecycle payments, including finance and maintenance over 27.5 years, reached £7.65 billion in present value terms by 2014. Train rollout faced further postponements, with entry into service shifting to June 2017—a 2.5-year delay from initial projections—and full fleet deployment extending to 2020. For the (GWML), electrification delays of 18 to 36 months, driven by underestimated engineering challenges such as bridge reinforcements and geotechnical issues, prompted the (DfT) to modify the IEP order in 2016, substituting seven electric-only sets with bi-mode equivalents at higher unit costs (£2.93 million per bi-mode vehicle versus £2.43 million per electric). These infrastructure setbacks added up to £330 million in direct costs to the DfT, exacerbating the programme's exposure to diesel-dependent operations and reduced efficiency. Budgetary pressures were compounded by the absence of a comprehensive until 2015, more than two years after contract award, which the National Audit Office (NAO) attributed to and fragmented planning between trains and . The overall GWML modernisation ballooned to £5.58 billion by 2016, a £2.1 billion increase from 2013 baselines, with alone overrunning by £1.2 billion (70%). NAO assessments highlighted how commencing IEP without committed widened benefit-cost ratios from initial forecasts, as bi-mode adaptations incurred premiums for hybrid propulsion while yielding lower long-term energy savings. These realities reflected systemic underestimation of integration risks in DfT-led initiatives, prioritizing interim solutions over aligned infrastructure timelines.

Electrification Dependencies and Strategic Missteps

The Intercity Express Programme (IEP) incorporated bi-mode trains, such as the Class 800 series, to enable operations on both electrified and non-electrified sections, predicated on the timely completion of projects like the (GWML). Initial plans in anticipated a fleet mix including pure electric units for fully wired routes, with bi-mode capability serving as a transitional measure until reached destinations like , Newbury, and eventually and by 2017–2018. However, GWML delays—stemming from technical challenges in overhead line equipment installation, signalling upgrades, and maintaining concurrent freight and passenger services—pushed full completion beyond 2018, with segments like to deferred indefinitely. In response, the (DfT) amended the IEP contract in July 2016 to convert the entire 171-train fleet to bi-mode configuration, forgoing pure electric options and incurring variant costs of approximately £200 million, plus up to £330 million in total delay-related expenses for infrastructure adaptations and extended diesel usage. This dependency exposed the programme to electrification risks, as bi-mode trains in diesel mode operate at reduced speeds (up to 140 km/h versus 200 km/h electric), lower energy efficiency (with fuel consumption 20–30% higher than equivalent electric traction), and elevated maintenance needs for dual power systems. Strategic missteps arose from inadequate integration of with infrastructure timelines, as the DfT proceeded with IEP awards in 2012 without resolved electrification feasibility, leading to post-contract modifications that inflated the programme's £5.7 billion baseline cost. The National Audit Office critiqued this as a of holistic , noting that earlier alignment of train specifications with realistic infrastructure delivery could have avoided reactive shifts and preserved options for cost-effective pure electric fleets on core electrified corridors. Industry analyses further highlight that bi-mode adoption, while pragmatically bridging gaps, locked in higher lifecycle costs—estimated at 15–25% premiums over electric-only equivalents due to duplicated components and expenses—exacerbating fiscal pressures amid stalled wiring progress. These decisions reflected in electrification projections, underestimating complexities on legacy , and contributed to prolonged reliance on , undermining decarbonisation goals with bi-mode emissions profiles approximating those of older sets in non-electric operation.

Reliability Issues and Diesel Mode Limitations

The Intercity Express Programme's Class 800 series trains have encountered several reliability challenges since entering service, including structural defects and propulsion system constraints. In May 2021, cracks were discovered in the bodyshell structures of certain Class 800 units operated by Great Western Railway, prompting a precautionary withdrawal of affected trains and an investigation by the Office of Rail and Road (ORR). The ORR's review assessed potential safety risks to passengers and infrastructure, leading Hitachi Rail to implement inspections and repairs across the fleet, with no immediate derailment threats identified but highlighting manufacturing quality concerns in the aluminum bodyshells. Additionally, early operational teething issues, such as software glitches and engine faults, were reported during initial testing and inaugural runs, including a failure to engage diesel power on a test unit in 2015 and disruptions on the first passenger service in October 2017. Propulsion reliability has been particularly affected by the compact packaging required for bi-mode functionality, which squeezes MTU 12V 1600 R80L engines into underfloor spaces originally designed with more generous allowances from predecessor power cars. This design compromise has contributed to overheating risks and maintenance difficulties under high loads, exacerbated during prolonged diesel-only operations on unelectrified sections. By 2024, while overall fleet reliability had improved to levels comparable with legacy on certain routes, persistent issues with engine oil consumption and traction system faults necessitated ongoing upgrades, including enhanced cooling and software refinements. Diesel mode operations reveal inherent limitations in , output, and compared to electric mode, stemming from the bi-mode architecture's distributed traction design. In diesel configuration, the Class 800 achieves approximately 70% of the rate possible under electric , with power-to-weight ratios dropping significantly—yielding around 2,250 horsepower for a five-car set versus higher effective electric equivalents—resulting in slower recovery from intermediate stops on mixed-traffic routes. This performance gap, compounded by the need for five modules per five-car unit, limits top speeds to 125 under ideal conditions but often requires on gradients or during fuel-efficient throttling, unlike pure diesel HSTs with centralized cars. consumption in diesel mode is markedly higher, estimated at 20-30% above electric equivalents per passenger-kilometer on non-electrified legs, contributing to elevated operational costs and emissions where delays persist, such as on the Great Western Main Line's unelectrified branches. These constraints underscore the bi-mode's role as a transitional solution, with diesel reliability further strained by the engines' exposure to variable loads without the buffering of dedicated cars.

Broader Critiques of Government Oversight

The (DfT) faced criticism for its inexperience in leading major like the Intercity Express Programme (IEP), relying heavily on external consultants while its internal teams were overstretched, which compromised effective oversight and decision-making. This lack of prior expertise contributed to a process described as poorly managed from the outset, with unclear initial specifications for numbers and configurations, heightening risks to public funds. A 2010 independent by Sir Foster highlighted flaws in the DfT's approach, including excessive emphasis on commercial confidentiality that stifled industry engagement and bred disenchantment among stakeholders, alongside unproven technical choices like bi-mode capability without precedents for high-speed applications. The noted risks from the novel funding structure—where trains are paid for only upon availability, shifting downtime liability to the supplier but exposing the to broader affordability issues amid economic pressures and deteriorating benefit-cost ratios due to rising costs and subdued demand forecasts. The National Audit Office (NAO) further critiqued the DfT for mishandling bidder relationships, such as communicating changes via media rather than direct channels, which elevated legal challenge risks and eroded trust; it also accepted a revised bid from the Agility Trains consortium without fresh competition after other bidders withdrew, undermining value-for-money assessments. Contractual arrangements granted the DfT extensive oversight powers, potentially delaying operations and inflating compliance costs if not executed adeptly, while strategic shifts—like committing to bi-mode trains before confirming timelines—left taxpayers vulnerable to daily losses of up to £0.4 million from delayed benefits and dependencies. The () in 2014 condemned the DfT's direct procurement model for IEP and related fleets totaling £10.5 billion, arguing it transferred all financial risks to taxpayers under inexperienced officials, without adequate safeguards or competitive pressures to optimize outcomes. These lapses exemplified broader governmental shortcomings in rail project governance, including insufficient contingency planning for technical uncertainties and a failure to balance innovation ambitions against proven alternatives, resulting in prolonged delays and escalated public expenditure without commensurate accountability mechanisms.

Economic and Societal Impacts

Job Creation and Industrial Benefits

The Intercity Express Programme (IEP) directly generated 730 skilled manufacturing jobs at Rail's purpose-built £82 million factory in , , opened in 2015 to produce the 122 bi-mode Class 800 and 801 trainsets for the and franchises. An additional 200 jobs were created during the factory's construction phase, contributing to a total of around 900 direct employment opportunities announced in the £4.5 billion contract award in July 2012. This marked the UK's largest investment in three decades and revived domestic high-speed train assembly, which had lapsed since the early 2000s. Beyond direct factory roles, the IEP bolstered an extensive , with 70% of train components procured from and suppliers, sustaining thousands of indirect jobs in , fabrication, and sectors. Hitachi's commitment included leveraging UK-Japan technical expertise to enhance local skills in advanced , while contracts—such as a extension for Great Western Railway fleets—secured ongoing annual spending of £70 million. These investments positioned the programme as a catalyst for industrial regeneration in , with the site exporting expertise and components internationally. The initiative's economic ripple effects extended to regional development, injecting capital into deprived areas like and fostering apprenticeships in precision engineering and digital rail technologies. Government assessments highlighted the IEP's role in securing long-term competitiveness for the rail sector against global competitors, though sustained benefits depended on follow-on orders to offset post-IEP production slowdowns that later threatened up to 250 factory positions by 2020. Official sources from the and emphasize verifiable job metrics tied to contract milestones, underscoring the programme's tangible contributions despite procurement delays.

Passenger Experience: Achievements vs. Shortcomings

The Intercity Express Programme (IEP) trains, primarily Class 800/801 bi-mode units deployed by Great Western Railway (GWR) and (LNER), have delivered measurable improvements in passenger capacity and amenities. These trains offer up to 20% more seating than predecessors like High Speed Trains (), with configurations providing 649 seats in electric mode for services, enabling reduced overcrowding on high-demand routes. Modern interiors include air-conditioned carriages, free , power sockets at seats, and enhanced luggage space, contributing to faster journey times through improved and top speeds of 125 mph. Passenger satisfaction surveys reflect these gains, particularly for LNER's Azuma fleet (Class 800 series), which achieved 89% overall journey satisfaction in Transport Focus assessments, ranking it as the top UK train operator and marking a 2% year-on-year improvement. GWR reported a 9% rise in customer satisfaction following IET (Intercity Express Train) introduction in 2017-2019, attributed to the new fleet's role in service upgrades. These outcomes stem from design priorities emphasizing legroom comparable to some operators' first-class offerings and electronic reservations for better space allocation. However, shortcomings in physical comfort have tempered these advances, with widespread and reports highlighting inadequate padding and ergonomic design in standard class. Seats are often described as hard and unsupportive, with metal frames causing discomfort on longer journeys, a regression from HST cushions despite meeting standards. Ride quality issues, including excessive and instability at speed—exacerbated by lighter bi-mode construction and underfloor diesel engines—have drawn criticism, contrasting unfavorably with smoother HST performance on legacy tracks. Additional grievances include the removal of full buffets on GWR IETs, replaced by trolley services, which staff surveys indicate negatively impacts passenger experience by limiting hot food options. Early deployments faced problems like air-conditioning leaks and IT failures, contributing to initial dissatisfaction dips, such as GWR's overall score falling to 78% in late 2018 amid integration challenges. While capacity and digital features represent objective progress, these comfort deficits underscore causal trade-offs in prioritizing lightweight efficiency and cost over proven ergonomic standards from prior generations.

Long-Term Fiscal and Infrastructure Implications

The Intercity Express Programme (IEP) imposes enduring fiscal commitments on the UK government, with contracts totaling approximately £4.5 billion covering train procurement, depot construction, maintenance, and select route enhancements, structured as fixed-price service agreements spanning up to 30 years. Under these arrangements, the Department for Transport (DfT) assumes primary financial responsibility, disbursing payments to the Agility Trains consortium (led by Hitachi) for train availability and upkeep, which are then leased to operators via availability-based charges ultimately underwritten by a combination of fare income and public subsidies. This model shifts some risk to the private sector but exposes taxpayers to residual liabilities, particularly amid fluctuating rail subsidies that reached £11.3 billion annually across the network by 2020, partly attributable to legacy investments like IEP. Bi-modal train configurations, adopted to mitigate electrification delays, amplify long-term costs, with maintenance expenses for diesel-electric hybrids projected at £4 million per coach higher over 27 years relative to pure electric units, driven by dual-system complexity, fuel dependency, and emissions compliance burdens. shortfalls, such as on the where full wiring remains incomplete as of 2023, have sustained diesel usage, inflating operational expenditures by an estimated 20-30% in non-electrified segments and deferring efficiency gains. The National Audit Office has critiqued the DfT's for insufficient emphasis on whole-system lifecycle , noting that operators prioritized short-term availability over holistic cost minimization, potentially locking in suboptimal fiscal outcomes through 2040s. Infrastructure-wise, IEP deployment has necessitated targeted upgrades, including track strengthening for 125 speeds, enhanced signalling for denser services, and depot modernizations at sites like Pензance and , yielding measurable capacity expansions—up to 20% more seats per train—and reliability improvements documented at 2.3 times prior levels on deployed routes. These enhancements support sustained network throughput amid rising demand, projected to grow 40% by 2040 on core intercity corridors, but hinge on complementary investments in and digital systems like ETCS to avert bottlenecks. Persistent under- perpetuates hybrid inefficiencies, complicating net-zero transitions and risking stranded assets if phases out without retrofits, while supplier-specific designs may elevate future costs and hinder competitive tendering for expansions. Overall, the programme exemplifies causal trade-offs in phased modernization: upfront fiscal outlays secure fleet renewal but amplify dependencies on unresolved dependencies, with net returns contingent on accelerated public investment in electrification and maintenance optimization.

References

  1. [1]
    New state-of-the-art InterCity Express train arrives in the UK - GOV.UK
    Mar 12, 2015 · The new IEP trains will bring faster services and additional capacity between London and major UK cities including Reading, Bristol, Cardiff and Swansea.
  2. [2]
    Intercity Express Programme - PPP Contract Management
    The Procuring Authority, the UK Department for Transport, awarded two contracts to supply, finance and maintain a fleet of new trains.
  3. [3]
    UK: Intercity Express Programme | Hitachi Rail
    Over 200 intercity trains in service, delivering more capacity, modern interiors and faster journey times for millions of passengers. Pioneering bi-mode ...
  4. [4]
    £4.5 billion investment in new trains creates new jobs - GOV.UK
    Jul 25, 2012 · More than 900 jobs will be created and thousands more secured after Transport Secretary Justine Greening approved a £4.5 billion contract to supply Britain.Missing: timeline key facts
  5. [5]
    Class 800 Series (800-810) - Hitachi Rail
    Projects Delivered: Hitachi is proud to be delivering the Government-funded £5.7bn Intercity Express Programme, delivering pioneering intercity trains for ...
  6. [6]
    [PDF] Intercity Rail Travel - GOV.UK
    The intercity rail program includes 100 new trains, a 27.5 year contract, 16% more seats, 11% lighter trains, and 18% less energy per seat-km.Missing: facts | Show results with:facts
  7. [7]
    [PDF] A Review of the Intercity Express Programme - Railhub
    “The Intercity Express Programme is intended to deliver the rolling stock needed to ensure that the passenger train franchises on the principal. Intercity ...
  8. [8]
    [PDF] Procuring new trains - National Audit Office
    Jul 9, 2014 · 1.6 In the case of Intercity Express, there was a need to replace existing intercity trains that were reaching the end of their expected time in ...
  9. [9]
    [PDF] Intercity Express Programme - Global Infrastructure Hub
    The government was required to play a key role in managing the interests of various stakeholders. The UK rail network is operated by private Train Operators who.
  10. [10]
    Intercity Express Programme - Railway Technology
    Dec 17, 2007 · IEP objectives include increased network carrying capacity, an enhanced passenger environment, improved safety, being environmentally ...Missing: rationale | Show results with:rationale
  11. [11]
    [PDF] Intercity Express Programme (IEP) Train technical specification
    This document is the final Train Technical Specification (TTS) for the IEP, part of the MARA contract, and must not be read in isolation.Missing: timeline facts
  12. [12]
  13. [13]
    Intercity Express Programme - Invitation to Tender
    This Invitation to Tender (ITT) seeks proposals from Bidders that will provide IE Services for the Contract Life of the IEP.Missing: process | Show results with:process
  14. [14]
    Alstom withdraws from IEP | News | Railway Gazette International
    Feb 12, 2008 · The remaining bidders on the shortlist announced on August 16 2007 are Hitachi Europe Ltd and the Express Rail Alliance of Bombardier, Siemens, ...
  15. [15]
    [PDF] Agility Trains Announced as Preferred Bidder for Intercity Express ...
    Feb 12, 2009 · For the Intercity Express Programme, Agility Trains will provide a new fleet of Hitachi Super. Express Trains that will provide more seats and ...
  16. [16]
    [PDF] Intercity Express Programme, UK
    Sep 21, 2012 · Spread over two phases, the total £4.5 billion IEP comprises trains, maintenance depots, and route upgrades, with the UK's. Network Rail ...
  17. [17]
    Intercity Express design unveiled | News - Railway Gazette
    Sep 11, 2008 · A consortium of Alstom and Barclays Private Equity decided not to bid, Alstom preferring to concentrate on further development of it existing ...
  18. [18]
    High-speed train funding decision delayed until October
    Jul 6, 2010 · Decision on whether to fund the replacement of Britain's ageing fleet of intercity trains will now be made in October.Missing: 2008-2010 | Show results with:2008-2010
  19. [19]
    Rolling stock: 6 July 2010 - GOV.UK
    Jul 6, 2010 · IEP is a complex programme which has interdependencies with several other major rail projects, and as expenditure on rail projects will be re- ...
  20. [20]
    A Review of the Intercity Express Programme :: The Railways Archive
    The report by Sir Andrew Foster into the value for money provided by the DfT's Intercity Express Programme. This document was published on 6th July 2010 by ...Missing: independent | Show results with:independent
  21. [21]
    None
    ### Summary of Key Findings and Critiques of the Intercity Express Programme (IEP) Review
  22. [22]
    Rail investment: 25 November 2010 - GOV.UK
    Nov 25, 2010 · In February 2009 the Intercity Express Programme, launched by the previous government, identified the Agility Trains consortium as preferred ...Missing: restructuring | Show results with:restructuring
  23. [23]
    Inter-city Express Programme - Hansard - UK Parliament
    Sep 15, 2010 · Hansard record of the item : 'Inter-city Express Programme' on Wednesday 15 September 2010.
  24. [24]
    Intercity Express and rail electrification - GOV.UK
    Mar 1, 2011 · Both the government and Agility Trains as preferred bidder recognised this. Over the last few months we have worked together on these issues and ...
  25. [25]
    Agility Trains Confirm Intercity Express Programme Contract - Hitachi
    Mar 1, 2011 · Agility Trains Ltd. is a bidding consortium formed to bid for the UK Intercity Express Programme. The company shareholders are Hitachi Ltd ...Missing: process 2008-2010
  26. [26]
    News Releases : July 25, 2012 - Hitachi
    Jul 25, 2012 · INTERCITY EXPRESS PROGRAMME FINANCIAL CLOSE PAVES WAY FOR HITACHI INVESTMENT IN RAIL MANUFACTURING AND ASSEMBLY PLANT. London and Tokyo, July 25 ...Missing: signing | Show results with:signing
  27. [27]
    Agility Trains signs Intercity Express Programme contract
    Jul 25, 2012 · The Agility Trains consortium of Hitachi Rail Europe and John Laing Investments was named preferred bidder for the IEP contract in February 2009 ...
  28. [28]
    Loan for the Intercity Express Programme in the UK | JBIC Japan ...
    Jul 25, 2012 · Loan for the Intercity Express Programme in the UK the First Project Finance Loan toward the Railway Sector for JBIC NR/2012-27 July 25, 2012
  29. [29]
    [PDF] Agility Trains Confirm Intercity Express Programme Contract - Hitachi
    Mar 1, 2011 · Agility Trains Confirm Intercity Express Programme Contract ... Agility Trains is now looking forward to finalising the commercial details and ...<|control11|><|separator|>
  30. [30]
    Minister sees the future of Britain's train fleet - GOV.UK
    Oct 15, 2014 · Rail Minister Claire Perry toured a mock-up of Hitachi's new train, part of the government's £5.7 billion Intercity Express Programme.Missing: cost | Show results with:cost
  31. [31]
    InterCity 125 v Hitachi: What are the UK's new trains like? - BBC News
    Mar 12, 2015 · Under the Intercity Express Programme (IEP), the Department for Transport in 2011 awarded a £5.7bn contract to Agility Trains, a consortium of ...
  32. [32]
    [PDF] Short-term Intercity East Coast train operator 2018 options report
    The Intercity Express Programme is worth in the region of £2.7bn for the. East Coast Mainline fleet3, comprising rolling stock, maintenance depots, and a full.
  33. [33]
    Rolling stock: IEP casts costly shadow - Modern Railways
    Feb 24, 2025 · From the start of the Department for Transport's Intercity Express Programme (IEP), this column was a consistent critic.
  34. [34]
    IEP - Intercity Express Programme - European Investment Bank
    Jan 21, 2008 · Total cost (Approximate amount). Approximately GBP 2.5 billion. (EUR 3.3 billion). Environmental aspects. The supply of rolling stock does not ...Missing: breakdown | Show results with:breakdown
  35. [35]
    Newton Aycliffe's Hitachi train plant opens - BBC News
    Sep 3, 2015 · An £82m factory for manufacturing high-speed Intercity trains is officially opened in County Durham.<|separator|>
  36. [36]
    Hitachi unveils first UK-assembled IEP train - Rail Magazine
    The bi-mode train has been assembled at HRE's Newton Aycliffe facility in County Durham, and is the first of 110 IEPs to come off the production line.
  37. [37]
    [PDF] Hitachi unveils first UK built Intercity Express Train
    Dec 9, 2016 · Intercity Express (IEP) train to be built in the UK at its manufacturing facility in Newton Aycliffe,. County Durham. Hitachi will be joined ...
  38. [38]
    Hydram and Hitachi Rail – Main Line to Success!
    Hitachi Rail's success with the Intercity Express Programme (IEP) ... supply chain of over 1,400 individual suppliers. This includes over 130 suppliers ...
  39. [39]
    UK: Investing in the North East and UK Supply Chain – Hydram ...
    Nov 24, 2020 · Thanks to the successful contract win and delivery of the Intercity Express Programme (IEP) ... supply chain of over 9,000 individual suppliers.
  40. [40]
    [PDF] INTERCITY EXPRESS PROGRAMME FINANCIAL CLOSE PAVES ...
    Jul 25, 2012 · As part of the IEP, Agility Trains' main supplier Hitachi will provide, service and maintain a total of 596 rail carriages destined to run ...
  41. [41]
    [PDF] Hitachi Begins Shipment of Trains from Kasado Works for the UK ...
    Jan 7, 2015 · Hitachi Begins Shipment of Trains from Kasado Works for the UK Intercity Express Programme. A Class 800 train is being loaded for shipment.Missing: assembly | Show results with:assembly
  42. [42]
    [PDF] Development of Class 800/801 High-speed Rolling Stock for UK ...
    HITACHI developed the Class 800/801 rolling stock for the Intercity Express Programme (IEP) to run between London and other major cities in the UK (see. Fig. 1) ...
  43. [43]
    Hitachi Intercity Express | Projects - Ricardo
    The Intercity Express Programme (IEP) was commissioned by the UK's Department for Transport to provide more capacity and faster journey times.
  44. [44]
    [PDF] Hitachi Unveils Train for the UK Intercity Express Programme
    Nov 13, 2014 · Of the total 122 trains ordered, twelve, including the one recently unveiled, are being manufactured at Kasado Works.Missing: assembly process
  45. [45]
    Hitachi Class 800 trainsets begin testing in Japan - Railway Gazette
    Sep 12, 2014 · Three Class 800 trainsets are now undergoing testing at Hitachi's Japanese factory in Kasado. UK: The first of three pre-series Class 800 ...
  46. [46]
    First Pantographs for New Class 800 Series IEP Trains Leave UK for ...
    Feb 28, 2014 · The first pantograph systems will be shipped from the UK to Japan for installation and testing on the first three pre-series Class 800 series trains.
  47. [47]
    News Releases : January 7, 2015 - Hitachi
    Jan 7, 2015 · The running tests are to be carried out on the UK Rail Network by Hitachi Rail Europe, to enable acceptance by Agility Trains, the special- ...
  48. [48]
    Class 800 begins journey to the UK - Global Railway Review
    Jan 7, 2015 · The train being shipped will arrive in the UK in March 2015, after which it will be equipped with various measurement devices for testing. This ...Missing: phases | Show results with:phases
  49. [49]
    Hitachi ships first IEP train to Britain - International Railway Journal
    Trials are due to begin on the Old Dalby test track near Nottingham in April and the test programme will be managed by Hitachi Rail Europe. Three pre-series ...
  50. [50]
    News Releases : March 12, 2015 : Hitachi Global
    Mar 12, 2015 · Train 800-001 is the first five-car pre-series train to be shipped to the UK from Japan, with 110 trains for the £5.7bn Department for Transport ...
  51. [51]
    Hitachi unveils first five-car IEP for DfT's £6bn order - Rail Magazine
    Jan 8, 2015 · There it will undergo daytime testing, with night-time testing carried out on a Signal Protected Zone (SPZ) on the East Coast Main Line. When ...
  52. [52]
    Hitachi Class 800s pass ETCS tests - The Railway Magazine
    Sep 20, 2017 · Class 800 No. 800002 was tested on the ETCS national integration facility test track on the Hertford loop between Stevenage and Watton-at-Stone.Missing: phases | Show results with:phases
  53. [53]
    Testing takes IEP train to Scotland for the first time - Rail Magazine
    Aug 18, 2017 · Intercity Express Programme trains reached Scotland for the first time on August 16, when the first IEP ran to Dunbar for testing.Missing: timeline | Show results with:timeline
  54. [54]
    Hitachi begins test run of Class 800 trains for UK's Intercity Express ...
    Sep 15, 2014 · Low-speed running trials of three pre-series Class 800 intercity train sets have started as part of the UK's Intercity Express Programme (IEP).
  55. [55]
    First new trains in a generation launched by GWR - FirstGroup plc
    Oct 16, 2017 · These trains are being built to cope with the more demanding geography of Devon and Cornwall and are due in passenger service next summer. In ...Missing: date | Show results with:date
  56. [56]
    aboard the new Intercity Express trains that will transform journeys ...
    Oct 16, 2017 · The new trains are a renewal of the ageing Intercity 125 fleet, which was first introduced in 1976, and they will go on to replace fleets across ...Missing: key | Show results with:key
  57. [57]
    UK's GWR Launches Brand New Intercity Express Train
    Oct 16, 2017 · The first services of the 57 new Class 800 Hitachi trains are being introduced from now into 2018 and will mark the start of the biggest ...Missing: initial | Show results with:initial
  58. [58]
    LNER announces new Azuma trains will enter service in May
    Mar 18, 2019 · London North Eastern Railway (LNER) has announced new Azuma trains will enter service on 15 May 2019.Missing: rollout timeline
  59. [59]
    Azuma trains going to Edinburgh - LNER
    May 30, 2019 · Azuma roll-out accelerates to the north east and Scotland · The first Azuma southbound weekday train will be the 05:40 Edinburgh to London King's ...Missing: timeline | Show results with:timeline
  60. [60]
    LNER launches new Azuma service on Flying Scotsman route
    Aug 2, 2019 · Azuma services will also become available between Glasgow and London from Monday 23 September. David Horne, LNER Managing Director said, “This ...
  61. [61]
    First Hitachi InterCity Express train has arrived in the UK
    Mar 19, 2015 · All 122 trains will be in service by 2020. The new IEP trains will bring faster services and additional capacity between London and major UK ...
  62. [62]
    aboard the new Intercity Express trains that will transform journeys ...
    Oct 16, 2017 · A new timetable will be introduced once Network Rail's electrification programme has been completed in early 2019, adding 40% more seats than ...Missing: timeline key facts
  63. [63]
    Great Western Intercity Express Programme - Arup
    ... Intercity Express trains manufactured by Hitachi Rail Europe in good running order. The depots were constructed by VolkerFitzpatrick with Arup as lead ...
  64. [64]
    Stoke Gifford Intercity Express Depot Rail Construction - JBA Corp
    The Stoke Gifford depot provides a new purpose built, state of the art facility, incorporating a ten car storage maintenance depot and carriage wash building.
  65. [65]
    News Releases : April 20, 2023 - Hitachi Global
    Apr 20, 2023 · ... Railway's 36 Class 802 Intercity Express Trains for the next five years; The maintenance programme will improve train availability and ...<|separator|>
  66. [66]
    North Pole intercity express depot | VolkerFitzpatrick
    VolkerFitzpatrick was appointed to undertake the reconfiguration and refurbishment of the North Pole train servicing and maintenance depot in Old Oak Common.
  67. [67]
    Rail investment: Intercity Express Programme - GOV.UK
    Apr 28, 2014 · The value of the contract is £2.7 billion. I would like to thank Agility and its constituent entities, Hitachi and John Lang, for their support.Missing: awards 2011
  68. [68]
    Supporting high-speed train operations: Knorr-Bremse and Hitachi ...
    Jan 13, 2021 · Knorr-Bremse will start supplying a new generation of brake pads and discs for Hitachi intercity Class 800/801/802 trains serving UK intercity routes.
  69. [69]
    Hitachi Super Express Trains - Railway Technology
    Oct 30, 2013 · The Class 800 are Bi-mode (diesel-electric) trains ,whereas the Class 801 are electric trains. “The £5.8bn ($9.37bn) IEP programme was initiated ...Missing: propulsion capability
  70. [70]
    Government gives green light for more state-of-the-art intercity trains
    Jul 18, 2013 · ... overall £5.8 billion Intercity Express Programme ( IEP ). The latest order for the trains, called the class 800 series, will be operational ...Missing: cost | Show results with:cost
  71. [71]
    News Releases : July 18, 2013 : Hitachi Global
    Jul 18, 2013 · Hitachi Class 800 series train selected by DfT to provide more seats and greater comfort for passengers as part of capacity improvements on East Coast Main ...
  72. [72]
    Huge increase in capacity on GWR as final Class 800 enters traffic
    Dec 28, 2018 · More than 10,000 extra seats will be available to Great Western Railway passengers on January 2, compared with the same number last year.
  73. [73]
    INFORMED SOURCES: Bathtub curve descent slow
    Apr 23, 2020 · The reliability levels for IEPs are 27,000 MTIN for Class 800 bi-mode and 54,000 for Class 801 electric trains. This level of reliability is ...
  74. [74]
    Hitachi delivers 300th train, marking a milestone in UK rail ...
    Sep 16, 2024 · Hitachi's trains have set new standards for reliability, with the company's fleet achieving reliability rates three times higher than the ...Missing: IEP MTIN MTBF 2023
  75. [75]
    [PDF] Passenger rail performance, April to June 2025 - ORR Data Portal
    Sep 11, 2025 · There have been improvements in reliability, but punctuality has worsened compared with the same quarter in the previous year.Missing: LNER IEP
  76. [76]
    Modernising the Great Western railway - NAO report
    Nov 9, 2016 · The cost of modernising the Great Western railway is estimated to be £5.58 billion, an increase of £2.1 billion since 2013, and there are delays to the ...
  77. [77]
    Agility finally secures £4.5bn deal to build IEP trains - Rail Magazine
    With Agility set to receive £4.5bn over the life of the contract for supplying 502 26-metre vehicles every weekday (from the fleet of 596), the rate per vehicle ...
  78. [78]
    [PDF] Modernising the Great Western railway - National Audit Office
    Nov 9, 2016 · 13 Delays to the electrification programme will cost the Department up to £330 million. The Department intends to vary its order of Intercity ...
  79. [79]
    Great Western electrification: Intercity line work 'deferred' - BBC News
    Nov 8, 2016 · Part of a £2.8bn project to electrify the Great Western route has been deferred. The plan was to fully electrify the route from Cardiff to London by 2018.Missing: dependencies strategic
  80. [80]
    Issue 157 - Good news and bad news - Rail Engineer
    Oct 27, 2017 · Bi-modes are also much more expensive to run and maintain. Diesel fuel is significantly more costly than electric traction. The higher ...Missing: assumptions missteps<|separator|>
  81. [81]
    [PDF] RIA Electrification Cost Challenge - NSAR
    Whilst bi-modes have a role in providing through services beyond 'the end of the wires', they are more expensive to buy and operate than an electric train and ...
  82. [82]
    Responding to ORR's Class 800 safety report - RSSB
    Apr 8, 2022 · In May 2021, cracks were found in the bodyshell of some Class 800 series trains manufactured by Hitachi Rail. As a precaution, some GWR and ...
  83. [83]
    Learning the lessons: ORR review into Hitachi Class 800 series and ...
    ORR immediately launched a review of both the passenger and safety impact following Hitachi Rail Class 800 series trains withdrawn from service for safety ...
  84. [84]
    Hitachi apologises for IEP problems - Rail Magazine
    Oct 17, 2017 · Hitachi Rail Europe apologised for the problems that affected the first passenger-carrying Intercity Express Programme train on October 16.
  85. [85]
    Software sinks performance hopes - Modern Railways
    Mar 26, 2020 · According to informed sources, among their various teething troubles the Class 755 bi-modes have suffered with engine problems, including oil ...
  86. [86]
    IEP – engine packaging hits the limit? - Modern Railways
    May 30, 2024 · The Intercity Express Programme (IEP) was a bit of a bodge-up. What began as an IC125 replacement, with two diesel driving power cars, morphed into a bi-mode.
  87. [87]
    Reliability Review 2024 - Modern Railways
    Jan 22, 2025 · The overall reliability of the national passenger rolling stock fleets improved in the year to Period 6 2024-25 (Table 1). While mileage increased by 6%, 701D ...Missing: IEP MTIN MTBF
  88. [88]
    Bi-mode trains: Unlocking opportunity? - Rail Engineer
    Oct 24, 2017 · This article will show that bi-mode trains in self-powered mode will struggle to deliver anything like the performance possible in electric mode.
  89. [89]
    Audit criticises British train procurement - International Railway Journal
    The procurement of IEP is criticised as "poorly managed from the outset" and the PAC says the DfT started out with no clear idea of how many trains it would ...
  90. [90]
    Train contracts: Ministers criticised by MPs' committee - BBC News
    Dec 17, 2014 · The Public Accounts Committee criticised the Department for Transport (DfT) for buying stock itself for the Intercity Express programme and the ...Missing: critiques | Show results with:critiques
  91. [91]
    Taxpayers bore all risk when DfT procured IEP and Thameslink fleets
    Taxpayers bore all risk when DfT procured IEP and Thameslink fleets - Public Accounts Committee. By Richard Clinnick; |; 17 December 2014; News.
  92. [92]
    Intercity express £4.5bn train deal to create 900 jobs - The Guardian
    Jul 25, 2012 · The government has finally announced the much-delayed deal for new intercity express trains, with the £4.5bn contract helping to create 900 new jobs.
  93. [93]
    Consortium Acquires 30% stake in Intercity Express Programme West
    Nov 1, 2018 · ATW was established in 2012 to finance, own and maintain 57 Hitachi class 800 trains that form the first phase of the Intercity Express ...
  94. [94]
    [PDF] Intercity Express Program (IEP)
    Jun 9, 2023 · The IEP project was to deliver highly reliable and efficient train fleets to run on the. - Great Western Main Line – London to Reading,.Missing: public- | Show results with:public-
  95. [95]
    Strengthening Britain's train-building industry - GOV.UK
    Nov 1, 2013 · The Intercity Express Programme is part of the government's commitment to investing in our nation's infrastructure. Once they are on the network ...
  96. [96]
    Hitachi plan to axe 250 jobs at Newton Aycliffe rail plant
    Jan 10, 2020 · Up to 250 jobs are set to be axed at a factory making trains in County Durham. The Newton Aycliffe site opened in 2015 and has a workforce of 900.
  97. [97]
    Sustained success for LNER passenger satisfaction
    LNER secured 89% for overall passenger satisfaction as part of the independent survey by Transport Focus. This represents a year on year improvement by two ...Missing: Azuma | Show results with:Azuma
  98. [98]
    New IETs drive record satisfaction levels for GWR - RailAdvent
    Jul 14, 2019 · New figures show a 9% improvement in customer satisfaction with regional train company Great Western Railway.
  99. [99]
    Next generation of trains for the Intercity Express Programme
    Jul 20, 2014 · The Intercity Express Programme represents a step change in intercity services on the Great Western and East Coast Main Lines. This next ...Missing: objectives | Show results with:objectives
  100. [100]
    FROM THE ARCHIVES: Are you sitting comfortably? - Rail Magazine
    New fleets have been criticised for having uncomfortable seats. Is a lack of padding due to the need to meet fire safety and crashworthiness standards?Missing: shortcomings | Show results with:shortcomings
  101. [101]
    Are passengers getting a good ride? - Rail Engineer
    Feb 23, 2023 · ... class 8XX Inter City Express Trains (IET). Critics compare them unfavourably with older trains which, they say, deliver a superior ride ...
  102. [102]
    Ride revelations raise more questions - Modern Railways
    Oct 25, 2024 · As we know, complaints about the ride of the LNER Hitachi Class 80x Azuma trains have been widespread. Often this has been accompanied by ...
  103. [103]
    New GWR IETs under fire over lack of buffets - Railnews
    May 13, 2019 · A survey of GWR staff revealed that 19 out of 20 staff think the lack of buffets is a mistake, and has had a negative impact on passengers. More ...Missing: satisfaction | Show results with:satisfaction
  104. [104]
    GWR takes intercity express trains out of service after PR fiasco
    Oct 19, 2017 · Technical issues plagued new trains in £5.7bn fleet envisaged as replacements after electrification projects are scrapped.
  105. [105]
    [PDF] Great Western Rail delays and performance across the network
    Feb 5, 2019 · It stated that while the IEP was “designed to be flexible enough to accommodate this change of direction”, it recommended that “the.
  106. [106]
    [PDF] A financial overview of the rail system in England
    Apr 26, 2021 · The arrangements for delivering rail services in England involve complex cash flows and contractual obligations and accountabilities between a ...
  107. [107]
    TFF0012 - Evidence on Trains fit for the future?
    Electric trains are approximately 30% cheaper to maintain than a diesel train and approximately 50% cheaper than a diesel bi-mode train. For example, on Great ...Missing: energy | Show results with:energy
  108. [108]
    [PDF] Procuring new trains (executive summary)
    Jul 9, 2014 · Because the Department began the Intercity Express programme when it considered that there was not a case for a major electrification programme ...