Line 5 Eglinton is a 19-kilometre light rail transit line spanning Eglinton Avenue in Toronto, Ontario, Canada, from Mount Dennis station in the west to Kennedy station in the east, with 25 stations and stops including over 10 kilometres of underground trackage. Designated as part of the Toronto Transit Commission's (TTC) subway network despite its light rail vehicles, the line is projected to reduce end-to-end travel times by up to 60% compared to existing bus routes through dedicated rights-of-way and signal priority systems. Initiated under the provincial MoveOntario 2020 plan and awarded to Crosslinx Transit Solutions in 2010, construction faced repeated setbacks from geotechnical challenges, contractor disputes, and integration issues with , resulting in ballooning costs exceeding $12 billion and postponing the original 2020 opening target. As of October , revenue service demonstration testing remains incomplete following a recent rail yard incident that halted operations, underscoring ongoing reliability concerns for the long-delayed project.

Historical Development

Pre-Planning Context and Initial Proposals

The corridor emerged as a focal point for proposals in during the early , driven by the need to accommodate urban expansion along this key midtown east-west artery. In 1910, Mayor Horatio Hocken proposed a loop under the "Tubes for the " plan, incorporating a line from Weston to via St. Clair and Eglinton to link growing suburbs, but voters rejected the required $5.4 million funding in a 1912 , prioritizing other infrastructure like the Yonge , which opened in 1954. Mid-century plans continued to eye Eglinton for high-capacity service amid rising automobile dependence, though fiscal and technical hurdles deferred action. The 1972 GO-Urban proposal by Premier envisioned a () crosstown route along Eglinton from Pearson Airport to Malvern for suburban connectivity, but engineering issues with curves, snow, and unproven technology led to its cancellation, yielding only the in 1985. By the 1980s, chronic bus overcrowding and traffic bottlenecks intensified calls for dedicated infrastructure. In 1985, Metro Toronto Council and the advanced a busway along Eglinton West for priority service. Local advocacy from , Etobicoke councillors, and Peel Region in 1986 secured inclusion of an Eglinton subway in the Network 2011 plan, targeting a route from Pearson Airport to . Premier Bob Rae's 1993 Rapid Transit Expansion Plan refined this to a shorter heavy-rail segment from to Black Creek Drive as economic stimulus, with tunneling starting in 1994; however, Premier Mike Harris's Progressive Conservatives axed it in 1995 citing prohibitive costs exceeding $1 billion, filling in the bored tunnels and reverting the corridor to buses. This pattern of ambitious subway initiatives thwarted by fiscal realism and political shifts underscored Eglinton's transit deficit, with 's 2003 Ridership Growth Strategy forecasting corridor overload by 2011 absent upgrades. Early 2000s reviews of "Higher Order Transit Corridors" and avenues like Eglinton shifted toward for its lower capital demands. The pivotal initial proposal materialized in 2007 via Mayor David Miller's plan, designating a 19-kilometer Eglinton Crosstown LRT from to Mount Dennis—tunneled from to for speed and reliability—prioritizing surface-running LRT over costlier s to enable broader network rollout amid constrained provincial support.

Approval and Early Design Under Provincial Funding

The committed $5.3 billion toward the capital costs of the Eglinton Crosstown LRT (Line 5 Eglinton) in 2010, positioning it as a priority project under as part of the regional transportation plan The Big Move, thereby securing provincial funding independent of municipal decisions. This funding commitment followed the completion of the Transit Project Assessment in November 2009 and preceded Mayor Rob Ford's election, ensuring the LRT configuration advanced despite his advocacy for a full subway conversion. Early design phases under this provincial framework commenced in early 2011, focusing on station architectures and alignments from Keele Street westward to Chaplin Crescent in the central tunnel segment, incorporating public consultations to refine at-grade and underground elements. On March 31, 2011, Ontario and Toronto formalized an agreement allocating $8.2 billion in provincial contributions toward the Eglinton line—primarily as LRT with a 10-kilometer central tunnel from Mount Dennis to Leaside—alongside related transit initiatives, solidifying the project's scope at approximately 19 kilometers with 17 stations. These efforts emphasized integration with existing TTC lines at Yonge-University and Kennedy, prioritizing cost efficiency and capacity for projected ridership of up to 14,600 passengers per hour per direction. Provincial oversight via facilitated preliminary engineering for right-of-way acquisitions and utility relocations, with environmental approvals leveraging prior assessments to accelerate progression toward procurement; this included specifying low-floor vehicles compatible with street-level operations on eastern segments. By mid-2011, the Board endorsed the LRT design parameters, aligning early concepts with provincial funding stipulations for completion by , though subsequent delays arose from contractual and construction challenges.

Political Redesigns During Rob Ford Administration

During 's mayoralty from 2010 to 2014, the Eglinton Crosstown LRT—initially part of the plan—faced cancellation threats but proceeded following a 2011 agreement between and the government, under which Premier pledged $8.4 billion in funding contingent on advancing the project as a primarily line rather than converting it to a full . , who campaigned on prioritizing over surface LRTs, initially sought to scrap the line entirely but relented due to provincial leverage, resulting in a revised scope that emphasized tunneling to align with his vision of reduced surface-level operations. This preserved approximately 10 km of alignment in the central corridor from Mount Dennis to , with at-grade sections on the western and eastern ends, though publicly advocated extending tunneling across the full 19 km route to eliminate above-ground segments and mitigate traffic interference. Ford's push for comprehensive aimed to enhance and reliability, positioning the line closer to standards despite using lighter rail vehicles, but it drew opposition for inflating expenses; estimates indicated full tunneling would raise project costs from $4.6 billion to $8.2 billion, primarily due to extended boring requirements under rivers like the and , as well as expanded footprints. In February 2012, overrode Ford's full-bury directive, voting to revert to a hybrid configuration that balanced cost with central tunneling, though subsequent design tweaks under his administration—such as enlarging platforms and incorporating -like infrastructure for potential future upgrades—persisted and contributed to and higher bids from contractors. These modifications, including beefier boxes and provisions for heavier loads, elevated the line's projected daily toward 100,000–120,000 riders initially but at the expense of efficiency compared to pure LRT or full alternatives. Planning professionals criticized Ford's strategy as misaligned with global precedents, where partial surface or elevated LRT segments in suburban areas often deliver adequate service at lower cost without full burial, arguing that the added $2–3 billion premium for concealment equated to multiple other transit initiatives. Despite council's rejection of total tunneling, Ford's shaped and choices, including a May 2012 TTC review that integrated heavier vehicles and signal systems for subway emulation, factors later linked to construction delays and overruns exceeding $1 billion by the mid-2010s. ceremonies on November 9, 2011, at Keelesdale Park symbolized the politically brokered revival, with Ford and McGuinty presiding, though Ford continued pressing for eastern extensions underground, vowing in August 2014 to bury the Scarborough at-grade portion if reelected to prioritize seamless operations over fiscal restraint. These redesign efforts reflected Ford's causal emphasis on subsurface to avert surface but yielded a critiqued for compromising on both LRT affordability and subway . In October 2024, the Save Eglinton Flats Coalition filed for an injunction in the against to stop construction on the western extension of Line 5 Eglinton, alleging the at-grade track alignment through Mount Dennis parkland constituted environmental racism. The group contended that the proposed route, which required clearing about 1,200 mature trees, would exacerbate environmental burdens—such as increased flooding, heat, and noise—disproportionately on a lower-income, racially diverse community in Mount Dennis, while eastern segments in wealthier areas had incorporated tunneling and consultations to mitigate impacts. They argued this reflected in route selection and inadequate and under the Environmental Assessment Act. Metrolinx defended the alignment as consistent with the project's approved environmental assessments, engineering feasibility along the corridor, and cost-effectiveness for connecting to Pearson Airport, noting that surface sections predominate across diverse neighborhoods without evidence of discriminatory intent. The agency emphasized prior public consultations and mitigation plans, including tree replacement and park enhancements. The court rejected the on October 25, 2024, ruling that the failed to demonstrate irreparable harm outweighing in completion, thereby permitting removal and trackwork to advance. No further appeals succeeded in halting the alignment, allowing the western extension to proceed in the existing right-of-way configuration. Earlier planning-phase concerns over in residential medians, such as near Mount Pleasant Road, were addressed through design revisions without escalating to litigation, prioritizing signal priority and right-of-way integration over alternative subsurface options deemed uneconomical.

Shift to Westward Extension Priorities

In February 2020, the enacted the Building Transit Faster Act, which transferred oversight of regional transit projects, including extensions to Line 5 Eglinton, from the City of Toronto to the province, enabling accelerated decision-making and funding allocation for westward infrastructure. This legislative change prioritized the Eglinton Crosstown West Extension (ECWE), a 9.2-kilometre addition from to Renforth Drive, featuring four underground stations, two elevated stations, and one at-grade station, with provisions for future linkage to . The province committed $4.7 billion to design, construct, and integrate rail, signalling, communications, and electrification systems, projecting completion before 2031 and generating over 4,500 construction jobs. The prioritization stemmed from 2019 provincial announcements identifying ECWE as one of four key transit initiatives for the , alongside the , Yonge North Subway Extension, and Subway Extension, to address congestion and boost economic connectivity westward into . This focus diverged from earlier plans emphasizing the unbuilt eastern segment to , which lacked comparable funding and remained deferred, later reconfigured as a distinct proposal spanning approximately 18 kilometres. By December 2023, contracts were awarded for the elevated guideway portion, with tunnelling on the western underground section completed by June 2024, advancing the project independently of central segment delays. The westward emphasis aligned with regional demands for airport access and integration with services at Mount Dennis, Scarlett Road, and Renforth, serving an estimated 37,500 additional residents and 23,600 jobs within while reducing travel times for commuters from and Peel Region. In May 2025, approved transferring four city-owned properties along the route to provincial control, facilitating land acquisition and utility relocations without altering the core alignment. This strategic pivot, under Premier Doug Ford's administration, reflected a causal focus on high-impact extensions over comprehensive east-west completion, prioritizing measurable reductions in dependency and support for 4,600 direct jobs during peak construction.

Construction Execution

Central Segment Progress and Contractor Involvement

The central segment of Line 5 Eglinton, comprising the 19-kilometre route from Mount Dennis to stations with approximately 10 kilometres of tunnelling along , is delivered by Crosslinx Transit Solutions (CTS), a consortium led by SNC-Lavalin (now ) and including , , and others, under a design-build-finance-operate-maintain contract awarded by in July 2015. CTS bears responsibility for constructing 25 stations (13 ), installing track and systems, and maintaining the line for 30 years post-opening, with funding capital costs exceeding $5 billion amid delays and overruns. Tunnelling for the central segment's twin bored tunnels, each 6.4 metres in diameter and totalling over 6 kilometres, concluded in June 2017 using two tunnel boring machines, followed by track installation reaching 10 kilometres of double track by December 2018. excavations and structural work advanced concurrently, with concrete segments for guideway beams cast off-site and erected for surface sections, though integration of signalling, overhead , and systems lagged due to CTS schedule shortfalls reported as early as 2022. By mid-2025, CTS completed major elements including platform edging, surfacing, and power rail installation across the central segment, enabling non-revenue vehicle testing to commence in phases from 2023 onward. The (TTC) has supported CTS in operational readiness, including staff training on vehicles and interface testing for fare gates and elevators at stations like Yonge-Eglinton and Eglinton West. In October 2025, the segment achieved the demonstration milestone, initiating a 30-day trial of end-to-end operations simulating passenger loads to validate reliability, with CTS coordinating defect resolutions under oversight; this phase positions the line for potential commissioning by late 2025, despite historical contractor delays pushing the original 2020 target by over five years.

Timeline of Key Milestones and Interruptions

Construction of the central segment of Line 5 Eglinton commenced in the summer of 2011 following the award of the primary public-private partnership contract to Crosslinx Transit Solutions in December 2010. Tunnelling operations began on June 12, 2013, with two tunnel boring machines excavating the 10-kilometre underground portion over the subsequent years, completing the bores by 2017. The project faced its initial major delay announcement in 2016, pushing the original 2020 opening to due to complexities in systems integration and testing requirements. Further postponements occurred amid the , which disrupted supply chains and on-site work starting in 2020, extending the timeline to 2022. In July 2018, Crosslinx Transit Solutions initiated legal action against , seeking compensation for delays attributed to changes in design and approvals imposed by the agency, marking a significant contractual interruption. This dispute contributed to ongoing timeline slippage, with projected openings revised to 2023 and later. In May 2023, the consortium petitioned the court for permission to halt non-essential construction amid unresolved demands for design modifications, exacerbating progress halts. Testing phases intensified in 2023, but persistent issues with signalling, ventilation, and integration delayed revenue service. By September 2025, the targeted opening was conceded as unachievable, with Metrolinx citing unresolved technical deficiencies. The 30-day revenue service demonstration commenced on October 7, 2025, simulating passenger operations to validate systems. However, this phase was paused later in October 2025 following a collision between two test trains, prompting safety reviews and further postponing public opening potentially into 2026.

Western Extension Infrastructure Builds

The Eglinton Crosstown West Extension adds 9.2 kilometres to , running westward from to Renforth Drive primarily underground before transitioning to an elevated guideway west of Scarlett Road. This configuration includes approximately 6.4 kilometres of twin-bore tunnels with a 5.75-metre , designed to connect with the central segment's at . Tunnelling commenced in spring 2024 using two tunnel boring machines, named Renny and a second unnamed machine, excavating from launch sites near Renforth Drive eastward toward Scarlett Road. By mid-2024, Renny had advanced 6 kilometres, with the final tunnelling leg starting in 2025 to link to Mount Dennis. The Advance , the initial phase encompassing these bores, reached substantial completion on June 30, 2025, enabling subsequent rail and systems installation. The elevated guideway spans from west of Road to Renforth Drive, featuring viaducts that cross the Humber River, Highway 427, and other roadways to maintain and operational speeds. This structure supports two elevated stations and integrates with one at-grade station, while four underground stations are built within portals and excavated boxes along the route. The seven new stations—anticipated to include , York-Eglinton, Islington-Eglinton, Kipling-Eglinton, Grove, Renforth, and an additional stop between Mount Dennis and —will feature platform-edge doors, accessibility-compliant designs, and intermodal connections to , UP Express, and bus services. Infrastructure procurement is structured across four major contracts: Advance Tunnel 1, Advance Tunnel 2, , and . The contract, covering builds, laying, overhead , and signalling systems, issued a request for proposals on September 27, 2024, with progressive design-build awarded to Alberici and design subcontracted to WSP by September 2025. Major site preparation and utility relocations preceded these phases, with full-route construction mobilization reported expanding by mid-2025.

Integration of Stations, Systems, and Testing Phases

The integration of stations, systems, and testing phases for Line 5 Eglinton represents the culmination of construction efforts, ensuring seamless operation across the 19 km light rail transit corridor with 25 stations. This process, managed by Crosslinx Transit Solutions under a public-private partnership with Metrolinx, involves verifying the interoperability of civil infrastructure—including underground and surface stations—with electrical and mechanical systems such as overhead catenary, traction power substations, communications-based train control (CBTC) signaling, ventilation, and fire safety systems. Station integration focuses on equipping facilities with elevators, escalators, platform edge protections, and passenger information systems, while confirming their alignment with vehicle operations and emergency protocols. System integration testing verifies the exchange of data and functionality between subsystems, such as fire alarms interfacing with escalators and tunnel ventilation responding to movements. Integrated system testing then assesses the absence of conflicts across the network, including mechanisms for safety-critical elements like signaling and power redundancy. By December 2023, for individual subsystems was nearly complete, enabling progression to these integration stages, which incorporate the 25 low-floor vehicles tested for compatibility with tracks and stations. Testing phases follow a structured sequence adhering to industry standards. Post-installation checkout, verifying equipment setup, reached approximately 90% completion by October 2023. Site acceptance testing of powered subsystems exceeded 66% by the same date, paving the way for recovery and reliability tests simulating service disruptions, such as towing disabled vehicles or to backup communications. The final demonstration (), a 30-day under full operational conditions including timetables and functions, commenced on October 7, 2025, to validate end-to-end performance before handover to the (). However, this phase was paused following an unspecified incident in mid-October 2025, pending resolution by and provincial oversight.

Technical and Operational Features

Route Alignment and Right-of-Way Configuration

Line 5 Eglinton follows eastward from its western terminus at to in the east, covering 19 km with 25 stations and stops. The alignment consists of a central 10 km twin-bore segment between approximately Keele Street and Laird Drive, flanked by at-grade sections to the west and east. The western at-grade portion extends from Mount Dennis, located near and , to the tunnel portal west of Street, utilizing a dedicated right-of-way (ROW) along the avenue's or adjacent corridor, separated from general traffic lanes. This configuration includes double tracks to support bidirectional service, with provisions for minimal street-level crossings to prioritize transit flow over vehicular interference. The central tunnel alignment runs subsurface beneath , avoiding surface disruptions in dense urban areas and enabling higher speeds up to 80 km/h in straight sections, with cross passages and ventilation shafts integrated for operational safety. East of the Leaside portal near Laird Drive, the line transitions to an 8 km at-grade segment in a semi-exclusive ROW within East's median, featuring double tracks buffered from adjacent roadways and sidewalks. This setup incorporates grade-separated elements where feasible, such as bridges over ravines, but includes signalized intersections with limited priority for LRT vehicles to balance transit reliability against existing traffic demands. The overall ROW design emphasizes segregation from automobiles, drawing on engineering assessments to minimize conflicts while accommodating utilities and pedestrian access. The planned 9.2 km westward extension from Mount Dennis to Renforth Drive maintains an at-grade alignment along West in a dedicated ROW for much of its length, before shifting to tunneled and elevated segments approaching Pearson Airport, with double tracks throughout to integrate seamlessly with the main line. This extension's configuration includes one at-grade terminus, two elevated stations, and four underground stations, reflecting adaptations to terrain and connectivity needs.

Station Designs and Accessibility Standards

The stations of Line 5 Eglinton incorporate a mix of , at-grade, and elevated configurations to align with the route's and urban density, with 15 stations featuring mined or cut-and-cover and 10 surface-level stops designed for seamless street integration. stations emphasize natural daylight penetration through skylights, large windows, and open atrium layouts extending to platform levels, as demonstrated in full-scale replicas used for pre-construction testing to optimize spatial flow and . Surface stations adopt streamlined, boxy architectural forms with marquee-style entrances accented by angled structural columns, prioritizing minimal visual obstruction and pedestrian connectivity via secondary entries and plazas. Accessibility standards adhere to Ontario's Accessibility for Ontarians with Disabilities Act (AODA) and incorporate universal design principles, including low-floor light rail vehicles for level boarding, elevators at all main entrances, wide platform edges, tactile warning strips, and barrier-free pathways at interchange points with existing TTC subway lines. Metrolinx has stated that all 25 stations and stops will be fully accessible upon opening, with features such as integrated wayfinding, passenger assistance intercoms, and audible signals for visually impaired users. However, disability advocates, including the AODA Alliance, have criticized the center-platform design in underground stations for reducing edge detectability and increasing disorientation risks for those with vision loss, arguing that side-platform alternatives would better mitigate these hazards without compromising capacity. For the westward extension, station designs mirror the central segment's approach, with four , two elevated, and one at-grade featuring open concourses, integrated , and elements like mini-platforms for level bus transfers where applicable, though construction as of 2025 emphasizes progressive design-build collaboration to refine these features. Empirical testing of mockups has informed adjustments for ergonomic circulation, ensuring platforms accommodate peak-hour crowds while maintaining clear sightlines and emergency egress paths compliant with fire safety codes.

Rolling Stock Specifications and Procurement

The for Line 5 Eglinton consists of low-floor light rail vehicles (LRVs) procured by from , which was subsequently acquired by in 2021. awarded Bombardier a C$770 million for the vehicles as part of preparations for the line's operations, with deliveries commencing after resolution of supply disputes. Due to Bombardier's delivery delays on prior LRV contracts, Metrolinx issued a notice of intention to cancel the Eglinton agreement in November 2016 and pursued an alternative supplier. In May 2017, Metrolinx signed a C$528 million contract with Alstom for 61 Citadis Spirit LRVs, including 44 allocated as contingency for Eglinton should Bombardier fail to deliver; 17 were designated for the Finch West LRT. However, Metrolinx reached a settlement with Bombardier in December 2017, retaining the Flexity Freedom vehicles for Line 5 while reassigning the Alstom order primarily to other projects. The Flexity Freedom LRVs are bi-directional, 100% low-floor articulated units designed for street-running and dedicated rights-of-way, with an operational maximum speed of 80 km/h. Vehicles operate in married pairs or triples, providing a train capacity of nearly 500 passengers including standing room. Full-vehicle testing of coupled units began in 2022 on surface sections east of Sunnybrook Park, validating integration with the line's signalling and track systems prior to revenue service. The fleet supports peak-hour frequencies of every 3-5 minutes, with maintenance handled under a separate contract at the Hillcrest facility shared with TTC operations.

Maintenance Facilities and Operational Logistics

The Eglinton Maintenance and Storage Facility (EMSF), situated at 85 Industry Street adjacent to , functions as the dedicated rail yard and vehicle service centre for Line 5 Eglinton's fleet. Spanning 23 hectares, it includes multiple storage tracks, maintenance bays, and workshops designed to handle routine inspections, repairs, wheel truing, and cleaning of vehicles. The facility supports the line's 76 low-floor vehicles, providing overnight stabling, heavy and capabilities, and space for component storage to ensure operational readiness. Crosslinx Transit Solutions (CTS), the under the public-private partnership, is contractually obligated to perform all non-lifecycle for a 30-year term, adhering to standards outlined in the project agreement with . Day-to-day operations fall under the , which manages train dispatch, scheduling, and integration with connecting TTC subway lines and bus routes, as well as services at key interchanges. A central Operations Control Centre, supplemented by a backup facility, enables real-time monitoring of vehicle locations, speeds, and braking via systems, facilitating automated operations and rapid incident response. Logistics emphasize efficient vehicle turnaround, with EMSF handling pre-service preparations to support projected peak frequencies of up to 7-10 minute headways across the 19-kilometre corridor.

Financial and Performance Challenges

Original Budget Projections Versus Actual Expenditures

The Eglinton Crosstown LRT project, formally Line 5 Eglinton, was initially projected with a capital construction of $5.3 billion upon its revival and funding commitment in 2009–2010 under the provincial government's MoveOntario 2020 plan. This figure covered the core design, engineering, and building of the 19-kilometer central segment, including tunnels, stations, and trackwork, but excluded long-term operational elements. The full alternative financing and (AFP) contract awarded in December 2010 to Crosslinx Transit Solutions expanded the scope to include vehicle , systems integration, and 30-year obligations, elevating the total projected cost to $8.25 billion, with $5.3 billion allocated to capital works and the remainder to lifecycle financing and upkeep. By 2018, amid emerging delays and scope adjustments, the budgeted had risen to $9.1 billion under the terms, while the overall project envelope reached $11.3 billion plus a $672 million , as documented in provincial audits reflecting payments for design-build phases and change orders. Actual expenditures continued to escalate due to unresolved technical issues and contractual disputes, with reporting cumulative spending exceeding initial projections by billions through 2023. As of 2024–2025 updates preceding testing, the total projected expenditures for the central segment stand at approximately $12.8 billion, representing an overrun of roughly $4.5 billion from the original full-contract projection and over $7.5 billion from the initial capital estimate alone. This escalation is evidenced in financial disclosures and independent audits, which highlight unabsorbed contingencies and supplemental payments outside the fixed-price structure.
Cost ComponentOriginal Projection (2010)Latest Projection (2024–2025)Overrun
Capital Construction$5.3 billion~$9.1 billion$3.8 billion
Full Project (incl. Maintenance & Financing)$8.25 billion$12.8 billion$4.55 billion
These figures exclude the separate $4.7 billion westward extension, which remains in early and unaffected by central segment overruns to date. The Auditor General's assessments underscore that while the AFP model aimed to cap risks through fixed pricing, actual payouts via amendments and performance incentives deviated substantially from baseline forecasts.

Causes of Cost Overruns and Empirical

The Eglinton Crosstown LRT (Line 5) experienced significant , with the project budget rising from an initial estimate of $5.3 billion in 2010 to approximately $11.8 billion by 2018 and $12.8 billion by 2024, representing a more than doubling in nominal terms before adjusting for and financing costs under the public-private partnership (P3) model. This overrun equates to roughly $674 million per kilometer for the 19-kilometer line, far exceeding comparable projects in less dense urban environments. Primary causes trace to deficiencies in early and scoping, as identified in Ontario's reports, which highlighted Metrolinx's limited mandate for integrated transit , leading to $436 million in sunk costs from uncoordinated decisions and repeated revisions to and designs. Frequent changes requested by municipal and provincial authorities—such as adjustments to right-of-way configurations and utility relocations in Toronto's densely built midtown corridor—exacerbated these issues, compounding delays in and construction sequencing. The P3 delivery model, involving a $9.1 billion alternative financing and signed in 2015 with Crosslinx Transit Solutions (CTS), introduced additional frictions through risk allocation disputes, including legal battles over responsibilities and failure to secure timely operating agreements with the , which stalled progress and inflated contingency claims. Empirical analysis reveals that these overruns were not isolated but symptomatic of systemic factors in Canadian transit megaprojects, including governance silos that hindered collaborative decision-making and fostered adversarial contractor relations under P3 structures. Quantitative breakdowns from audits indicate that planning shortfalls accounted for over 30% of avoidable costs, with the remainder driven by execution risks amplified by urban site constraints, such as geotechnical challenges in tunneling sections and inflationary pressures on materials post-2015. Comparative data from Metrolinx's portfolio shows similar patterns in other LRT lines, where initial underestimation of lifecycle financing—embedded in P3 bids—masked true capital risks, leading to taxpayer exposure via change orders exceeding $500 million. While external factors like supply chain disruptions were cited by contractors, agency assessments downplayed their role relative to endogenous managerial lapses, underscoring the need for upfront risk modeling grounded in historical overrun rates of 50-100% for urban rail in North America.

Delay Factors: Technical, Managerial, and External

The Eglinton Crosstown LRT, designated as Line 5, has experienced repeated delays since its original projected opening in 2020, with the latest estimates pushing to no earlier than mid-2025 due to unresolved performance issues. Technical challenges have been a primary driver, including approximately 260 deficiencies identified across the project's , encompassing defects in trackwork, signaling systems, and station integrations that required extensive remediation. More recently, train reliability and performance problems, such as software bugs and propulsion system failures, have necessitated prolonged testing phases, with an incident during dynamic testing in October 2025 halting final demonstrations. These hurdles stem from complex underground tunneling and elevated guideway integrations in a densely urban corridor, where unforeseen utility conflicts and material specifications amplified rework demands. Managerial factors have compounded these technical setbacks, particularly within the public-private partnership (P3) framework involving the , which handled , , and maintenance responsibilities. Disputes between and Crosslinx escalated into by May 2023, with the consortium alleging barriers to completion imposed by the public authority, while characterized the claims as delay tactics to avoid accountability for subpar deliverables. Inadequate upfront and oversight in processes contributed to cascading delays, as evidenced by repeated misses on internal milestones for and , reflecting broader institutional challenges in coordinating multi-stakeholder contracts. leadership acknowledged in 2023 the absence of a credible amid these issues, attributing prolonged holdups to insufficient allocation and incentives in the P3 model. External influences, notably the , imposed logistical disruptions starting in 2020, including workforce reductions, supply chain interruptions for specialized components like signaling equipment, and halted on-site activities that extended construction timelines by months. Regulatory and environmental approvals, combined with urban constraints during peak construction, further impeded progress, though these were secondary to endogenous project flaws. Independent analyses highlight that while external shocks amplified delays, pre-pandemic managerial and technical deficiencies—such as optimistic scheduling without buffers for urban complexity—formed the causal foundation, rendering the project vulnerable to exogenous pressures.

Public-Private Partnership Model Evaluation

The Eglinton Crosstown LRT project employed 's Alternative Financing and Procurement () model, a form of public-private partnership (P3) under which and Infrastructure Ontario contracted Crosslinx Transit Solutions—a including SNC-Lavalin, Dragados, and —to , finance, and maintain the line for 30 years following substantial completion. The contract value stood at approximately $8.4 billion for these core elements, with the retaining responsibility for acquisition, relocations, and certain third-party interfaces. Proponents argued this structure would transfer risks such as construction delays and cost overruns to the private partner, incentivizing efficiency through fixed-price commitments and performance penalties. A pre-procurement value-for-money (VfM) analysis by Infrastructure Ontario projected 22% net savings—equivalent to $2.18 billion in —over a traditional design-bid-build approach, attributing benefits to competitive , lifecycle costing, and allocation. However, empirical outcomes diverged sharply: by 2023, total costs exceeded initial estimates by over $4 billion, reaching approximately $12.8 billion, while the opening date slipped from 2020 to ongoing testing phases in 2025 amid unresolved signaling and integration issues. issued acceleration payments totaling $237 million to Crosslinx in 2018 to mitigate delays, and subsequent negotiations addressed further claims, indicating incomplete risk transfer where public funds absorbed private shortfalls. Ontario's highlighted deficiencies in the model's execution, noting that not all construction risks were fully allocated to Crosslinx, leading to protracted disputes over scope changes, subcontractor performance, and external factors like utility coordination. Private financing embedded in the P3 structure incurred higher interest rates—typically 1-2% above public borrowing—extending repayment over decades and inflating lifecycle costs, contrary to VfM assumptions that overlooked such premiums in volatile economic conditions. Legal confrontations ensued, with Crosslinx suing in 2023 for alleged breaches including failure to secure an operator, while withheld payments for non-performance, underscoring adversarial dynamics that eroded projected efficiencies. Critics, including transit advocates and fiscal watchdogs, contend the P3 framework prioritized profit margins over accountability, fostering opacity in tracking and incentivizing conservative that masked underlying complexities in urban tunneling and integration with existing . Comparative analyses of Ontario's 74 prior P3s, as reviewed by the , found no consistent of superior outcomes, with Eglinton exemplifying how bundled financing and obligations complicated without delivering on-time, on-budget results. Despite these shortfalls, defenders note that private involvement accelerated initial mobilization post-2013 award, though causal factors like revisions and supply chain disruptions—exacerbated by the —reveal limits in any model's ability to insulate against exogenous shocks absent robust contingency planning. Overall, the Eglinton experience empirically challenges the P3's purported advantages for complex megaprojects, with public exposure to overruns undermining the risk-transfer rationale central to its adoption.

Controversies and Stakeholder Perspectives

Political Interference and Decision-Making Critiques

The Eglinton Crosstown LRT project originated as part of Toronto's plan, approved by city council in 2009 under Mayor David Miller, which prioritized over extensions for cost efficiency across multiple corridors, including . Upon Ford's election as mayor in 2010, the incoming administration canceled , favoring expansions, though preliminary work on Eglinton continued amid legal and funding disputes; a 2013 compromise under interim mayor Karen Stintz retained the LRT alignment, with provincial funding secured in 2014 by the Liberal government under Premier . Critics, including transit advocates and former officials, have attributed initial planning delays—spanning from 2009 approval to 2011 groundbreaking—to this political oscillation, arguing that repeated mode and scope revisions eroded momentum and increased pre-construction costs without advancing core infrastructure. Decision-making critiques have centered on the choice of low-floor vehicles over higher-capacity or technology, despite the line's 10-kilometer mostly designed for grade-separated , which elevated costs to subway-like levels (approximately $8.4 billion by 2023) while limiting throughput to around 10,000 passengers per hour per direction. Proponents of alternatives, such as urban planners and commentators, contend that municipal and provincial leaders prioritized short-term fiscal constraints over long-term demand projections—Eglinton's corridor serving over 100,000 daily boardings via buses—resulting in a system ill-suited for projected ridership growth and requiring future upgrades or parallel investments. This choice, reaffirmed by council against Ford's 2010 subway proposal, has been faulted for reflecting electoral posturing rather than empirical ridership modeling, with some analyses highlighting how surface LRT constraints elsewhere in informed the underground pivot yet failed to justify the hybrid's inefficiencies. Under the Doug Ford-led Progressive Conservative government since 2018, accusations of direct political interference intensified, particularly regarding , the provincial agency overseeing construction. Emails revealed in 2024 showed Ford's office directing to withhold the Crosstown's opening date from public disclosure, citing economic sensitivities, a move criticized by opposition figures and transit advocates as undermining the agency's arm's-length mandate established to insulate projects from electoral cycles. The government resisted freedom-of-information requests for related documents until court-ordered in July 2025, prompting claims of opacity that exacerbated public distrust amid repeated delays from the original 2020 target to indefinite postponements in 2025. Toronto City Council voted on October 10, 2024, to request a provincial public inquiry into the project's mismanagement, citing chronic delays, cost overruns exceeding $1 billion, and unresolved signal and integration issues as symptoms of flawed oversight, with councillors attributing accountability lapses to intergovernmental tensions between the city and province. Ontario NDP Leader Marit Stiles echoed this in October 2024, pressing for an inquiry to examine decision-making chains, including potential favoritism in public-private partnerships and evasion of scrutiny during testing halts, such as the October 2025 train collision at Mount Dennis yard. Broader analyses link these episodes to systemic political involvement in transit governance, where provincial appointees to Metrolinx boards and policy shifts—such as integrating the line with GO Transit—have been seen as prioritizing political narratives over operational rigor, contributing to empirical failures like unintegrated signaling that persist into late-stage testing.

Community and Environmental Impact Disputes

The proposed elevated guideway for the Eglinton Crosstown West Extension (ECWE), a planned westward continuation of Line 5 Eglinton, has sparked significant opposition from community groups and organizations over and loss of . In January 2023, an -led coalition including the ENAGB Indigenous Youth Agency, Stop the Trains in Our Parks, and the Mount Dennis Community Association protested the 1.5-kilometer elevated structure between Scarlett Road and Jane Street, arguing it would necessitate the removal of thousands of trees in the Eglinton Flats parkland within the Humber River floodplain. Opponents cited threats to wildlife habitats, , noise buffering, and community programs for youth and vulnerable populations, with calls to bury the segment underground to preserve the area. Protests included a sustained sacred blockade lasting nearly five months by June 2023, though construction proceeded as planned. In October 2024, the Save Eglinton Flats Coalition filed for an injunction in the to halt the clearing of approximately 1,200 trees—about half classified as —in Mount Dennis parkland for the ECWE elevated line. The group alleged "environmental racism," claiming inadequate consultation in the lower-income, racialized Mount Dennis area compared to tunnelled segments elsewhere, and emphasized the trees' role in flood mitigation and . defended the design citing flood risks from historical events like in 1954 and the 2013 Toronto floods, asserting that elevation avoids submersion while committing to replant at least three trees per removed one, totaling over 8,500 new trees including 3,500 in Mount Dennis. The court denied the injunction, enabling tree removal to begin in mid-October 2024, which transformed parts of Eglinton Flats into a cleared wasteland despite prior environmental assessments. Construction of the main Line 5 Eglinton corridor has also generated community complaints regarding localized disruptions, particularly in dense neighborhoods like , where ongoing work since 2011 has altered streetscapes, impeded pedestrian access, and strained local businesses through prolonged and . A 2012 engineering report highlighted the project's potential to displace 1.5 million cubic meters of and fill, raising concerns over , groundwater , and long-term urban fabric changes, though these were addressed in the 2010 environmental assessment with mitigation measures like sediment controls. Unlike the ECWE, mainline disputes have not escalated to widespread legal challenges, but residents have reported persistent quality-of-life issues, including and air quality degradation during tunneling and station builds. maintains that such impacts are temporary and outweighed by reduced emissions from future operations.

Labor and Contractor Performance Issues

has imposed financial penalties on Crosslinx Transit Solutions (CTS), the consortium contracted for the design, construction, financing, and 30-year maintenance of Line 5 Eglinton, citing poor performance as a primary factor in project delays. In May 2023, confirmed it was withholding substantial payments from CTS to enforce accountability for substandard work and failure to meet contractual milestones. Quality control deficiencies have been a recurring issue under CTS oversight. As of April 2023, auditors documented roughly 260 unresolved quality problems across stations, tracks, and systems, ranging from structural defects to integration failures, which attributed to inadequate contractor supervision and execution. These lapses delayed system handover and necessitated extensive remediation, with no firm completion schedule emerging until late 2023. Contractor disputes escalated into litigation in May 2023, when CTS filed claims against and Infrastructure Ontario, arguing that changes to the project's operating model—particularly TTC integration—breached the public-private partnership agreement and justified extensions. CTS threatened to halt collaboration with the TTC, prompting to label the action a "delay tactic" while affirming its intent to pursue all contractual remedies, including further penalties. A prior settlement in December 2021 resolved CTS claims related to disruptions and technical challenges, awarding $325 million to cover verified impacts without admitting fault. Labor-specific challenges appear limited compared to technical and managerial shortcomings, with no documented major strikes or union actions disrupting the project. Broader Canadian sector labor shortages, estimated at nearly 1 million unfilled positions as of , have strained timelines industry-wide, but public reports do not isolate deficits as a dominant factor for Line 5. CTS's performance evaluations, including ongoing 2025 testing phases, continue to highlight reliability gaps requiring joint TTC-CTS-Metrolinx interventions, underscoring persistent execution flaws over acute labor unrest.

Comparative Efficacy Against Alternative Transit Models

The Eglinton Crosstown LRT (Line 5) was selected over (BRT) alternatives primarily due to its higher projected capacity and potential to attract greater ridership in a corridor forecasted to require 10,000–13,000 passengers per hour per direction (pphpd) by 2031. BRT systems, such as enhanced bus lanes with signal priority, typically achieve capacities of 5,000–8,000 pphpd under optimal conditions, limited by vehicle size (around 55–80 passengers per bus) and operational constraints like bunching and road sharing. In contrast, the LRT's design supports up to 13,040 pphpd using two- or three-car trainsets, each accommodating approximately 163–489 passengers depending on configuration, enabling more efficient peak-hour service with fewer vehicles. analyses indicate the LRT would generate 143 million annual boardings by 2031, compared to lower estimates for BRT-like options under the concept (117 million boardings), attributed to rail's perceived reliability and permanency inducing mode shifts from automobiles. However, BRT offers lower —potentially 20–50% less per kilometer for surface implementations—and faster deployment, avoiding the LRT's tunneling and relocation expenses that have driven actual costs to over CA$12.8 billion for the 19-kilometer line.
MetricEglinton LRT (Line 5)BRT Alternative (e.g., Enhanced Bus Lanes)
Capacity (pphpd, 2031)13,0405,000–8,000
Avg. Speed (kph)3520–30
Capital Cost (CA$B, initial est.)6.9~3–5 (inferred from surface options)
Annual Boardings (millions, 2031)143~117 ( proxy)
Operating costs for LRT benefit from potential and lower requirements per compared to BRT, which incurs higher labor expenses due to more frequent vehicles; rail modes can reduce staffing by 30–50% for equivalent throughput. Empirical data from similar corridors, such as Ottawa's BRT-to-LRT , show LRT increasing ridership by 20–40% through capacity and comfort gains, though Toronto's at-grade segments risk delays from traffic interference, potentially eroding speed advantages over BRT. Independent critiques, including from the Neptis Foundation, highlight that even LRT's incremental ridership gains yield high costs per new rider (over CA$40,000), questioning efficacy if projections overestimate amid stagnant regional transit funding. Against subway alternatives, the LRT demonstrates superior cost-effectiveness in initial assessments, with estimated at $6.9 billion versus $8.3 billion for a full subway extension, a differential of roughly 20% despite comparable average speeds (35 kph for LRT vs. 36 kph for ). Subways offer higher ultimate (15,000+ pphpd) and immunity to surface disruptions, outperforming LRT in metrics like fewer transfers and longer platforms for efficiency, as detailed in City of evaluations. However, 's benefit-cost ratio (BCR) favored LRT at 0.52 (benefits exceeding costs by 52% in , including user time savings of $2.3 billion), against subway's 0.33, due to lower upfront enabling broader network expansion under fiscal constraints. Projected ridership slightly favors LRT (143 million vs. 126 million annual boardings), though subway might capture more long-term growth through faster end-to-end times (minimal at-grade exposure). Actual overruns have narrowed this gap, pushing LRT costs toward subway levels without matching grade-separated reliability, prompting debates on whether subway's durability justifies 3–4 times the per-kilometer expense ($300–400 million vs. $100–200 million for LRT). Critics argue the LRT's efficacy is compromised by design choices, such as low-floor vehicles limiting lengths and signal systems prone to street-level bottlenecks, potentially capping real-world below pphpd amid Toronto's dense traffic—evident in pre-opening tests revealing reliability issues. advocates, citing Vancouver's Expo Line ( 20,000+ pphpd at similar costs adjusted for scale), contend that LRT's semi-exclusive right-of-way fails causal tests for transformative impact, as lower speeds (under 30 kph in mixed sections) deter ridership shifts comparable to ' 40–50 kph averages. Benefit analyses, while privileging LRT for BCR, reveal net losses (BCR <1 across options), suggesting neither mode fully justifies expenditures without complementary measures like ; empirical parallels in Calgary's LRT expansions show strains at 12,000 pphpd without upgrades. Ultimately, the LRT's selection reflects fiscal realism over peak-demand optimization, delivering moderate efficacy for mid-tier corridors but underperforming in speed and resilience, and BRT in deployability.

Projected Impacts and Extensions

Anticipated Operational Benefits and Capacity

The Eglinton Crosstown LRT (Line 5) is designed to deliver operational efficiencies through dedicated rights-of-way, including a 10-kilometer underground section, enabling average speeds up to 60 percent higher than current along the corridor. This configuration minimizes delays from surface traffic and intersections, with projections indicating reduced journey time variability by 1 to 1.5 minutes in standard deviation compared to at-grade alternatives. across much of the 19-kilometer route will also lower maintenance and operational disruptions, contributing to higher service reliability and fewer bus-hour equivalents required for equivalent capacity—estimated at a reduction of over 793,000 bus hours annually by 2031 under optimized scenarios. Peak directional is forecasted at 15,000 passengers per hour, supported by longer platforms and low-floor vehicles optimized for high-volume boarding, exceeding projected peak demand of approximately 5,500 passengers per hour by 2031. This enables the line to absorb ridership growth, with annual boardings anticipated at 126 to 143 million by 2031, while integrating with three TTC subway lines, services, and over 50 bus routes at its 25 stations. Overall, these features are expected to yield substantial user benefits, including quantified travel time savings valued at $1.4 to $1.9 billion in present terms across design options, primarily from faster end-to-end trips and enhanced frequency without proportional increases in fleet size. The system's signal priority and centralized control will further optimize dwell times and headways, supporting seamless transfers and reducing system-wide congestion on parallel corridors like Line 1 Yonge-University.

Western Extension to Airport Connectivity

The Eglinton Crosstown West Extension comprises a 9.2-kilometre segment extending Line 5 Eglinton from westward to Renforth Drive, primarily underground with an elevated guideway over the Humber River, incorporating seven new stations to enhance regional transit integration. This phase, procured through public-private partnerships and with construction advancing since 2021—including tunnel boring completed by April 2025—facilitates indirect airport connectivity via Renforth station's linkage to the and existing bus routes to . Upon completion, expected to support up to 69,700 daily boardings, the extension will improve access for approximately 37,500 residents and reduce travel times to western and hubs by integrating with and services. A further 4.7-kilometre link from Renforth Drive directly to Pearson Airport terminals remains in exploratory planning stages, coordinated with the Greater Airports Authority, to provide seamless LRT access without transfers. has affirmed ongoing commitment to this connection, citing technical feasibility studies and potential for elevated or at-grade alignment, though full funding and environmental assessments are pending as of 2025. This direct extension aims to alleviate airport congestion by diverting an estimated 10-15% of ground access trips from roads and taxis to rail, based on initial projections for the full 14-kilometre westward route. Critics note risks of delays akin to the main Crosstown line, potentially pushing operational service beyond 2030, while proponents highlight from airport passenger growth exceeding 50 million annually. Enhanced connectivity via the western extension is projected to yield multimodal benefits, including synchronization with airport employee shuttles and long-term reductions in Highway 427 traffic volumes by up to 5% during peak hours, per regional transport models. The Renforth Gateway, as an interim hub, already supports to Pearson, but the LRT extension would elevate capacity to handle 20,000+ hourly passengers bidirectional, fostering economic ties between Toronto's urban core and airport-related employment zones employing over 50,000 workers. Recent design contracts awarded in September 2025 to firms like WSP for stations and systems underscore momentum, though fiscal constraints may prioritize the core 9.2-kilometre buildout before airport linkage.

Eastern LRT Proposals and Network Integration

The Eglinton East Transit (EELRT) represents the primary for development east of Line 5 Eglinton's terminus at , spanning 18.6 kilometres from Kennedy to Malvern Town Centre with 27 stops along East and Sheppard Avenue East. This project, revived in following the cancellation of earlier Scarborough-Malvern LRT plans in 2010, aims to deliver electric-powered vehicles on dedicated guideways, each accommodating up to 292 passengers, to serve historically underserved areas in , including eight Neighbourhood Improvement Areas. The initiative includes five interchange points with major transit corridors and features such as traction power substations and a maintenance facility near Conlins Road and Sheppard Avenue East. At , the EELRT is designed to provide a direct and seamless interface with Line 5 Eglinton, facilitating passenger transfers alongside connections to subway and services. This integration enhances the eastern endpoint of Line 5, which serves as a key hub linking to 54 bus routes and regional rail, enabling efficient east-west connectivity across and into Scarborough's growth areas like the campus. The project's environmental assessment review concluded prior to 2025, with ongoing public consultations and approval of 10% functional design advancing planning toward higher-order transit in the corridor. Broader network integration for Line 5's eastern operations incorporates surface bus adjustments, such as the proposed 34 Eglinton route serving stations east of Mount Dennis while aligning with Line 5 operations at for feeder services. The EELRT's alignment supports connectivity to complementary systems, including the proposed Sheppard extension, Durham-Scarborough , and Line 3 busway, promoting modal shifts from automobiles in high-density corridors without designating it as a direct extension of Line 5 per 2022 city council directives. Public realm enhancements, such as widened sidewalks and bikeways, accompany the transit build to foster urban development tied to improved accessibility.

Long-Term Fiscal and Urban Development Implications

The Eglinton Crosstown LRT's capital expenditure has escalated to approximately $13 billion as of 2025, substantially exceeding the original 2010 estimate of $5.3 billion, primarily due to construction delays, design changes, and procurement issues under the public-private partnership model. Long-term fiscal burdens include lifecycle maintenance costs embedded in annual service payments to the private consortium, spanning a 30-year period from 2021 to 2051, with the alternative financing and procurement approach yielding an estimated present-value savings of $2.18 billion (22%) compared to traditional public delivery, though actual overruns have eroded much of this advantage. Benefit-cost ratios from pre-construction analyses ranged from 0.33:1 to 0.87:1 (including reliability benefits), indicating that user and societal transport benefits may not fully offset capital and operating expenditures over the 30-year horizon, with net present values as low as -$3.488 billion. Projected ridership of 176,000 to 220,000 daily boardings could generate incremental fare revenues with a net present value of $607 million to $1.214 billion, but persistent funding gaps—exacerbated by negative operating cost savings of up to $715 million in present value—suggest ongoing subsidies from provincial and municipal taxpayers. Urban development along the corridor is anticipated to benefit from transit-oriented intensification, with land value uplifts estimated at $770 million to $2.06 billion in present value (2011 dollars), concentrated in areas like Yonge-Eglinton, promoting densification in designated urban growth centers. Property values for condominiums and single-family homes proximate to stations have risen significantly, with some segments experiencing increases of up to 135% over five years preceding full operations, driven by enhanced accessibility and reduced commute times across . This appreciation is expected to expand the municipal base, supporting fiscal recovery through higher assessments, while fostering economic activity via 490 to 1,070 construction-related jobs and contributions of $52 million to $114 million by 2031. However, uneven impacts may include accelerated and displacement pressures on rental housing stocks, as investor activity targets older apartment buildings along the line, potentially straining affordability in lower-income neighborhoods without targeted mitigation. Overall, while the project enhances regional connectivity—projected to reduce by $4.3 million to $7.1 million in and enable wider economic benefits of $175 million to $350 million—the low benefit-cost ratios underscore causal risks in large-scale delivery, where overruns and suboptimal design (e.g., surface-level conflicts) could limit net urban productivity gains relative to alternatives like . Extensions, such as the westward link adding 69,700 daily riders and access to 23,600 jobs, may amplify these effects but introduce additional fiscal commitments estimated at $4.7 billion.

References

  1. [1]
    Eglinton Crosstown LRT - Metrolinx
    25 stations and stops along Eglinton Avenue · 19 kilometres, with more than 10 kilometres running underground · Up to 60% faster than current travel times · Link ...
  2. [2]
  3. [3]
  4. [4]
  5. [5]
    The tortured history of Toronto's discarded subway plans
    Apr 15, 2019 · The first would have run along Sheppard, from Downsview Station to Victoria Park. The second would have run along Eglinton, from Pearson Airport ...<|control11|><|separator|>
  6. [6]
    TIMELINE: A brief history of Toronto's Eglinton Crosstown LRT project
    Metro Council and the Toronto Transit Commission propose a busway along Eglinton West. · 1986 — A coalition of City of York and Etobicoke ...
  7. [7]
    Eglinton Crosstown LRT Chronology (Updated) - Steve Munro
    Feb 19, 2020 · TTC placed the order for the Eglinton TBMs in June 2010, but only a month later Metrolinx announced that it had ordered them. Any Toronto ...
  8. [8]
    Eglinton Crosstown LRT - Infrastructure Ontario
    The Eglinton Crosstown LRT is part of Metrolinx's regional transportation plan, The Big Move, and is one of the first large-scale transit projects for the ...
  9. [9]
    Ontario to launch green bonds to fund Eglinton LRT project - InfraPPP
    Sep 25, 2014 · The Eglinton Crosstown LTR represents a CAD$5.3 billion (2010) transit improvement investment. The Eglinton Crosstown LRT will provide ...
  10. [10]
    Toronto Transit Commission Line 5 Eglinton - CPTDB Wiki ...
    In total, there would have been 26 stations. The combined Eglinton Line and Scarborough RT was named the Eglinton-Scarborough Crosstown Line.
  11. [11]
    Toronto mayor's transit plan gets Ont. support | CBC News
    Mar 31, 2011 · Ontario Premier Dalton McGuinty announced the province will contribute $8.2 billion to put an Eglinton light rail line underground, ...
  12. [12]
    Agreement Reached Between Toronto and Ontario on City's Transit ...
    Mar 31, 2011 · ... crosstown light rail subway underneath Eglinton Avenue for a total cost of C$8.2 billion, both to be completed by 2020 as a unified line.
  13. [13]
    LORINC: Ford's mistake of historic proportions - Spacing Toronto
    Nov 14, 2011 · Mayor Rob Ford's plan to bury the 19-km Eglinton Crosstown LRT from end to end, instead of just through the crowded core of the city, ...
  14. [14]
    Cost of digging a tunnel for the Eglinton crosstown ... - Toronto Life
    Nov 7, 2011 · The Globe and Mail reports that the cost of the Eglinton crosstown LRT has jumped from $4.6 billion to $8.2 billion due to Mayor Rob Ford's ...
  15. [15]
    Planning experts blast Ford's Eglinton Crosstown strategy
    Feb 5, 2012 · Dismissing Mayor Rob Ford's pledge to bury the entire Eglinton Crosstown LRT as "radically out of sync" with design in leading cities around ...
  16. [16]
    Route 5 - The Eglinton-Crosstown LRT - Transit Toronto - Content
    Sep 17, 2025 · In December 2010, when newly-elected Toronto mayor Rob Ford vetoed the proposal to operate LRT lines on street, the EGLINTON-CROSSTOWN LRT ...
  17. [17]
    Toronto's Eglinton Crosstown LRT, Well Sort Of LRT
    Jun 21, 2025 · The soon to open 19-kilometre Eglinton Crosstown LRT, (Line 5) includes a 10 km subway, which in my book, makes this project a light metro and not LRT.
  18. [18]
    Rob Ford vows to build entire Eglinton line underground - Toronto Sun
    Aug 8, 2014 · Mayor Rob Ford is pledging to bury the above-ground portion of the Eglinton Crosstown if he's re-elected.
  19. [19]
    toronto: earth to mayor: subways are expensive! - Human Transit
    Jan 23, 2012 · Ford's preferred plan for underground light rail on Eglinton Avenue “delivers greater benefit” than the Transit City version a coalition of ...
  20. [20]
    Eglinton LRT injunction sought over 'environmental racism'
    Oct 7, 2024 · A community group is taking Metrolinx to court Tuesday to halt Eglinton LRT construction on the grounds that it is discriminatory. The Save ...
  21. [21]
    Coalition fails to derail Metrolinx plan to cut down trees for ECWE ...
    Oct 25, 2024 · A coalition of groups representing the Mount Dennis community in Toronto has failed in court to derail plans by Metrolinx to cut down mature trees in parkland.Missing: lawsuit | Show results with:lawsuit
  22. [22]
    [PDF] Appendix B2: Project Correspondence Tracking Log - Metrolinx
    Oct 4, 2023 · More specifically, this EPR Addendum assesses the changes to the track alignment including impacts to bridges and culverts, new ... Eglinton ...
  23. [23]
    The Building Transit Faster Act | Ontario Newsroom
    Feb 18, 2020 · The western extension of the Eglinton Crosstown LRT (future Line 5) will increase connectivity along Eglinton Avenue from the future Mount ...
  24. [24]
    Eglinton Crosstown West Extension – Stations, Rail and Systems
    Request for Qualifications: March 25, 2024 · Pre-qualified Teams Selected: September 27, 2024 · Request for Proposals: September 27, 2024 · Request for Proposals ...Missing: funding | Show results with:funding
  25. [25]
    [PDF] Eglinton Crosstown West Extension Initial Business Case - Metrolinx
    The Eglinton Crosstown. West Extension would extend Line 5 (Eglinton Crosstown LRT) 14 kilometres west from Mount Dennis Station to the proposed Regional ...<|separator|>
  26. [26]
    Government of Ontario breaks ground on final tunnel segment of ...
    Apr 9, 2025 · In June 2024, the province completed tunnelling on the western underground portion of the Eglinton Crosstown West Extension from Renforth Drive ...
  27. [27]
    The Evolution of Transit-oriented Development in Canada - NAIOP
    These include the 19-kilometer Eglinton Crosstown Light Rail Transit (LRT) line ... A future 18-kilometer line (Eglinton East LRT) has also been proposed.
  28. [28]
    Ontario Takes Next Step to Build the Eglinton Crosstown West ...
    Dec 15, 2023 · The Ontario government is awarding a contract to construct the elevated portion of the Eglinton Crosstown West Extension, marking a major milestone in the ...
  29. [29]
    Ontario Celebrating Major Milestone for Eglinton Crosstown West ...
    Jun 24, 2024 · The Eglinton Crosstown West Extension will support as many as 4,600 good-paying jobs during construction. The Extension will bring 37,500 more ...
  30. [30]
    Eglinton Crosstown West Extension - Metrolinx
    Key facts ; Route length. Up to 13.9 km. 9.2 km between Mount Dennis and Renforth Drive; 4.7km for the potential link between Renforth Drive and Pearson ...
  31. [31]
    Eglinton Crosstown West Extension - City of Toronto
    In May 2025, Toronto City Council approved the transfer of four City-owned properties along the route of the Eglinton Crosstown West Extension to the Province ...
  32. [32]
    Crosslinx Transit Solutions Consortium awarded contract for ...
    Jul 24, 2015 · Crosslinx Transit Solutions Joint Venture has been awarded a contract for the Eglinton Crosstown Light Rail Transit project in Toronto, ON, Canada.Missing: contractor involvement
  33. [33]
    Crosslinx Transit Solutions | Eglinton Crosstown Light Rail Transit ...
    Crosslinx Transit Solutions (CTS) is a design and construction consortium established to deliver and maintain the Eglinton Crosstown LRT.Job Opportunities · Who We Are · Contact Us · Our Parent Companies
  34. [34]
    Eglinton Crosstown on track for major milestone - Metrolinx
    By December 2018, crews are expected to reach the milestone of 10 kilometres of underground track installed. Track will need to be doubled along the entire 19- ...
  35. [35]
    Eglinton Crosstown LRT will be delayed by about a year, source says
    Sep 23, 2022 · "Unfortunately, while progress has been made, Crosslinx Transit Solutions have fallen behind schedule, are unable to finalize construction ...Missing: contractor | Show results with:contractor
  36. [36]
    [PDF] Provincial LRT Program – Line 5 Eglinton Update - City of Toronto
    Jun 23, 2025 · This Agreement provides provincial funding support for a three-year term commencing in Q1 2024 through to Q1 2027. Future funding for transit ...
  37. [37]
    Eglinton Crosstown LRT starts final testing phase, could open next ...
    Oct 7, 2025 · The Eglinton Crosstown LRT today embarked on its final testing phase, a timeline which could see the years-delayed line open by early November.
  38. [38]
    Eglinton Crosstown LRT crosses major milestone - CTV News
    Oct 8, 2025 · Eglinton Crosstown LRT crosses major milestone, but opening date still unclear. The Eglinton Crosstown LRT's revenue service demonstration has ...
  39. [39]
    Eglinton Crosstown LRT crosses major milestone - CP24
    Oct 8, 2025 · The project is at least $1 billion over budget and was scheduled to open in 2020.Missing: central | Show results with:central
  40. [40]
    TTC - Eglinton-Scarborough Crosstown Transit Project - LRT - subway
    Construction of The Crosstown began in the summer of 2011 and has a projected completion date of 2020. Key facts about the Eglinton-Scarborough Crosstown Plan:.Missing: milestones | Show results with:milestones
  41. [41]
    Metrolinx hopes to start 30-day revenue service demonstration for ...
    Sep 29, 2025 · It was supposed to open in 2020, but it has been repeatedly pushed back due to various legal, construction and testing issues along with COVID- ...Missing: interruptions | Show results with:interruptions<|control11|><|separator|>
  42. [42]
    Company building Eglinton Crosstown sues Metrolinx over delays ...
    Jul 12, 2018 · The company that is building the Eglinton Crosstown LRT line has filed a lawsuit against Metrolinx to compensate it for delays in the $5.3-billion project.
  43. [43]
    Eglinton Crosstown LRT consortium seeks legal work stoppage
    May 16, 2023 · The consortium building the Eglinton Crosstown LRT is asking a court for permission to stop construction, accusing Metrolinx and ...
  44. [44]
    Eglinton Crosstown LRT misses another deadline. Metrolinx has ...
    Sep 5, 2025 · The years-delayed Eglinton Crosstown LRT will miss its most recent target of opening to the public in September, Metrolinx has conceded, ...
  45. [45]
    Eglinton Crosstown LRT 30-day revenue service demonstration ...
    Oct 7, 2025 · The earliest opening date, barring any major issues, would be in November. However, potential timeframes have shifted many times. Aside from ...Missing: approval | Show results with:approval
  46. [46]
  47. [47]
    Eglinton Crosstown West Extension - Advance Tunnel
    The Eglinton West Extension Advance Tunnel project consists of a 5.75m diameter twin bore tunnel for the 6.4km extension of the under-construction Eglinton ...
  48. [48]
    Construction update on the Eglinton Crosstown West Extension
    When these two tunnel boring machines are finished, they will have dug more than 6 km of tunnel between Renforth Drive and just west of Scarlett Road – a ...
  49. [49]
    Tracking Eglinton Crosstown West Extension tunnelling progress
    Tunnelling for the Eglinton Crosstown West Extension began earlier this spring with Renny, the first of two tunnel boring machines (TBMs) leading the way.
  50. [50]
    Crews Begin Final Leg of Tunneling for Eglinton Crosstown West ...
    Apr 17, 2025 · Crews have begun digging the tunnels to connect the Eglinton Crosstown West Extension to the Eglinton Crosstown LRT at Mount Dennis Station.
  51. [51]
    Renny, the last TBM on Eglinton Crosstown West Extension project ...
    May 15, 2024 · Renny, the last TBM on Eglinton Crosstown West Extension project has reached 6 kilometres of tunnelling! The extension will bring the Eglinton ...<|control11|><|separator|>
  52. [52]
    Tunnelling work starts on final section of Ontario's Eglinton ...
    May 15, 2025 · Tunnelling work starts on final section of Ontario's Eglinton Crosstown West Extension. 15 May, 2025 By Nia Kajastie. Final leg of tunnelling ...
  53. [53]
    Eglinton Crosstown West Extension – Advance Tunnel Project
    The Eglinton Crosstown West Extension (ECWE) Advance Tunnel Project is the first phase of work for the 9.2 kilometre extension of the Eglinton Crosstown LRT.Missing: early | Show results with:early
  54. [54]
    Elevated guideway - Metrolinx
    The Eglinton Crosstown West Extension will operate underground from Renforth Drive to just west of Scarlett Road, where it will then transition to a ...Elevated Guideway · Renderings · Frequently Asked Questions
  55. [55]
    Eglinton Crosstown West Extension - Arup
    almost 5,000 of whom are considered low-income. With improved access ...
  56. [56]
    Three Teams Shortlisted for Eglinton Crosstown West Extension ...
    Sep 30, 2024 · Renforth Station · Martin Grove Station · Kipling-Eglinton Station · Islington-Eglinton Station · Royal York-Eglinton Station · Scarlett Station ...
  57. [57]
    Perkins&Will Helps Drive Transit Expansion Across Canada with ...
    Oct 6, 2025 · The extension will connect five major transit services, including UP Express, Kitchener GO Train, TTC, MiWay, and GO Transit buses, which will ...
  58. [58]
    RFP issued for Eglinton Crosstown West Extension stations - Metrolinx
    Sep 27, 2024 · A request for proposals (RFP) has been issued for the Stations, Rail and Systems (SRS) contract for the Eglinton Crosstown West Extension.
  59. [59]
    Alberici Secures Progressive Design-Build Contract for Eglinton ...
    The project will improve connectivity across Toronto and the Greater Toronto Area by extending Line 5 Eglinton 9.2 kilometres west from Mount Dennis Station to ...
  60. [60]
    WSP to design Eglinton Crosstown West Extension Stations, rails ...
    Sep 10, 2025 · The contract includes the construction of one at-grade, two elevated and four underground stations, track construction, electrification, ...
  61. [61]
    Eglinton Crosstown West Extension - Latest updates - Metrolinx
    Recent news and in-depth stories about the Eglinton Crosstown West Extension. ... Major construction expands across entire route of 9.2-kilometre extension.
  62. [62]
    [PDF] Eglinton Crosstown LRT - Progress Update - Metrolinx
    Dec 8, 2023 · Acceptance testing work is almost complete. • System Integration Testing will ensure train control systems, fire alarms, tunnel fans and ...
  63. [63]
    Dig deeper into Eglinton Crosstown testing & commissioning
    Testing & commissioning is ongoing for the Eglinton Crosstown LRT project. Nov 1, 2023. Testing and commissioning (T&C) is an important phase that every ...<|separator|>
  64. [64]
    Crosstown LRT testing & commissioning explained - Metrolinx
    Oct 16, 2023 · In the case of the Eglinton Crosstown LRT, more than 66 per cent of the site acceptance testing has been completed.
  65. [65]
    Eglinton Cross Town - WSP
    Running through the heart of Toronto, the 19 km rapid transit line features 15 underground stations, 10 at-grade stops and a 10 km section tunneled underground.
  66. [66]
    Eglinton Crosstown LRT - Design - Dr. Sauer & Partners
    The project provides a 19km corridor across Eglinton Avenue, connecting ten stops at grade and 15 underground stations with a 10km twin-bored tunnel.
  67. [67]
    Eglinton Crosstown Light Rail Transit - Hatch
    Metrolinx needed to pay critical attention during construction, due to the tunnel alignment's proximity to buried and surface utilities, two operational ...
  68. [68]
    Full-scale replica shows off Eglinton Crosstown station design
    A replica of one of the stations has been built at an off-site location to allow construction and design teams to see their work up close in advance.
  69. [69]
    The Big Move: A Preview of Toronto's Eglinton Crosstown LRT
    Nov 21, 2024 · The stations are now functionally complete, and they offer an alluring preview of a sensitive and streamlined design that prioritizes an airy ...
  70. [70]
    Eglinton Crosstown LRT Project Overview - Infrastructure Ontario
    Nov 3, 2015 · Eglinton Crosstown LRT Project Overview ... standards and principles of Universal Design to maximize accessibility for users with a disability.
  71. [71]
    [PDF] Eglinton Crosstown LRT Interchange Stations - Final Designs - TTC
    Mar 20, 2018 · The public passageways between the LRT and subway concourses are barrier free. The current accessibility features of the subway station remain ...
  72. [72]
    [PDF] Metrolinx 2021 Accessibility Status Report
    All stations and stops will be accessible when the Eglinton. Crosstown goes into service. 2.2.3.2. Construction for the Finch West LRT is underway, and ...
  73. [73]
    Toronto Star Reports that Metrolinx Designed Underground Eglinton ...
    Toronto Star Reports that Metrolinx Designed Underground Eglinton LRT Stations with Troubling and Preventable Barriers to Disability Accessibility and ...
  74. [74]
    AODA Alliance Chair Resorts to Freedom of Information Application ...
    Lepofsky emphasizes that the centre platform design is less accessible and safe for people with certain disabilities, such as those with vision loss. In a ...<|separator|>
  75. [75]
    [PDF] Royal York- Eglinton Station - Metrolinx
    Its design allows for an open plaza, a concourse and a platform, with integrated lighting, wayfinding and passenger assistance intercoms. Jane-. Eglinton.
  76. [76]
    The differences between trains, light rail vehicles and subways
    Jun 30, 2025 · ... line stretching from Exhibition Place to a new interchange with Line 5 Eglinton at Don Valley Station.
  77. [77]
    Eglinton Crosstown Light Rail Transit, Toronto - Railway Technology
    Jul 22, 2021 · The twin tunnels are being constructed under two separate sections, which were awarded to two different contractors. The first section covering ...Missing: configuration | Show results with:configuration<|separator|>
  78. [78]
    Metrolinx inks deal with Alstom as LRT spat with Bombardier continues
    May 12, 2017 · Metrolinx has reached a deal to purchase light rail vehicles from French manufacturer Alstom for future transit builds in the Greater Toronto ...
  79. [79]
    Alstom receives order for 61 Citadis Spirit light rail vehicles for ...
    May 12, 2017 · Alstom has been awarded a firm order for the supply of 61 Citadis Spirit light rail vehicles for the Greater Toronto and Hamilton area (GTHA) by Metrolinx.
  80. [80]
    Metrolinx selects Alstom as alternative light rail vehicle supplier
    May 12, 2017 · Should Bombardier deliver the Eglinton Crosstown LRVs on time, the 44 Alstom LRVs would be reassigned to the Hurontario LRT project. 'We are ...Missing: rolling stock
  81. [81]
    Metrolinx, Bombardier come to terms - Railway Age
    Dec 21, 2017 · As a results, in May 2017, Metrolinx placed an order with Alstom for 61 Citadis LRVs, at $528 million as, in effect, an insurance policy for the ...
  82. [82]
    Flexity Freedom - Wikipedia
    The Flexity Freedom is a low-floor, articulated light rail vehicle developed by Bombardier Transportation (and later Alstom) for the North American market.Design · Orders · Toronto · Waterloo Region
  83. [83]
    Full vehicle testing for Eglinton Crosstown – plus other updates
    Jul 21, 2022 · Look out – full-length vehicles for the Eglinton Crosstown LRT are hitting the streets. That means three cars, and a capacity of almost 500 ...<|control11|><|separator|>
  84. [84]
    [PDF] Transit Network Expansion - Board Report July 17, 2024 - TTC
    Jul 17, 2024 · The Province on June 14, 2024, advised they would only fund the portion necessary to facilitate the construction of the SSE. Further information ...
  85. [85]
    Eglinton Maintenance and Storage Facility - Transit Toronto - Content
    Sep 17, 2025 · The Eglinton Maintenance and Storage facility is being built by Metrolinx to store and maintain the line's 76 Flexity Freedom LRT vehicles.
  86. [86]
    You're invited inside the Crosstown's Maintenance Facility - Metrolinx
    May 23, 2019 · The Eglinton Crosstown LRT Maintenance and Storage Facility, located at 85 Industry Street in Toronto, will be open on May 25 from 10 am. to 5 pm.Missing: yard details
  87. [87]
    [PDF] line 5 – eglinton operating and funding: term sheet - City of Toronto
    Term Sheet Schedule B will form the foundation of the commercial terms to be included in a detailed Train Operating and Funding Agreement for Line 5 - Eglinton, ...
  88. [88]
  89. [89]
    New technology means faster trips for Eglinton Crosstown LRT
    Nov 23, 2023 · Inside the control centre, operators know the location of each train and can authorize train movements, speed, and braking based on the data ...
  90. [90]
    Metrolinx--Regional Transportation Planning
    Apr 5, 2025 · The Eglinton Crosstown project has a capital construction budget of $5.3 billion, growing to $9.1 billion when maintenance and lifecycle costs ...
  91. [91]
    [PDF] 3.07 Metrolinx—LRT Construction and Infrastructure Planning
    Manage Risks in the Eglinton. Crosstown LRT Project. The total budget for the Eglinton Crosstown LRT is about $11.3 billion, plus a contingency fund budget of ...<|separator|>
  92. [92]
    [PDF] STANDING COMMITTEE ON PUBLIC ACCOUNTS
    As part of the Eglinton Crosstown LRT project, for example, the agency procured rolling stock from Bombardier, while signing a contract with a consortium to ...
  93. [93]
    [PDF] THE PRICE OF PROGRESS - NET
    Aug 9, 2024 · Look no further than the oft-maligned Eglinton Crosstown. LRT project – now almost 4 years overdue and. $4 billion over budget.4 These delays ...Missing: details | Show results with:details
  94. [94]
    [PDF] 1.07 Metrolinx—LRT Construction and Infrastructure Planning
    on the project's cost or schedule; and alignment between the TTC, as future ... for the Eglinton Crosstown and 17 for Finch West. If Bombardier met the ...
  95. [95]
    Poor Planning Results in High-Cost Project Delays
    The Eglinton Crosstown LRT is the only light rail transit project currently under construction. ... LRT project cost $125 million: Scarborough Rapid ...
  96. [96]
    Completing the Eglinton Crosstown LRT has now become a legal fight
    May 22, 2023 · Completing the Eglinton Crosstown LRT has now become a legal fight. Metrolinx calls the court filing by Crosslinx Transit Solutions a delay ...Missing: track | Show results with:track
  97. [97]
    Eglinton Crosstown builder says agency does not believe COVID-19 ...
    Oct 9, 2020 · Eglinton Crosstown builder CTS believes COVID-19 has created cost overruns and delays, and is taking its and Metrolinx to court.
  98. [98]
    Why does it cost so much to build transportation in Canada? - ppgr
    Feb 7, 2023 · While P3 should be continuously analyzed to prevent the kinds of delays and cost overruns seen in the Eglinton Crosstown, they are an important ...
  99. [99]
    Eglinton Crosstown will open no earlier than mid-2025, TTC chair says
    Dec 4, 2024 · The chair of the TTC says the long-delayed and over-budget Eglinton Crosstown will not open for service before mid-2025.Missing: causes | Show results with:causes
  100. [100]
    Eglinton Crosstown plagued by 260 quality control issues, including ...
    Apr 27, 2023 · The repeatedly delayed and over-budget Eglinton Crosstown LRT is being held up by some 260 quality control issues and there is still no credible timeline for ...
  101. [101]
    Eglinton Crosstown light rail project in Toronto delayed again
    Sep 5, 2025 · Eglinton Crosstown light rail project in Toronto delayed again. The Canadian Press September 5, 2025 ... RFQ issued for stations, rail and systems ...
  102. [102]
    Eglinton Crosstown trains latest source of delay as LRT line inches ...
    Aug 6, 2025 · Instead, it's been plagued by construction flaws, procurement issues, lawsuits, software bugs and pandemic-related slowdowns. Major construction ...<|separator|>
  103. [103]
  104. [104]
    Why experts say work on these 5 fronts is needed to tackle Toronto's ...
    Jan 28, 2025 · Overwhelmingly, experts told CBC Toronto the city needs to improve its oversight and management of construction projects. Image | Roger Browne, ...Missing: managerial | Show results with:managerial
  105. [105]
    [PDF] Value for Money Assessment – Eglinton Crosstown Light Rail Transit
    The VFM assessment shows an estimated $2.18 billion (22%) cost savings using the AFP approach for the Eglinton Crosstown LRT compared to traditional delivery.
  106. [106]
    Why private-public infrastructure projects haven't always lived up to ...
    Nov 21, 2023 · The Crosstown, which is being built by a consortium of globe-trotting engineering giants, is more than $4 billion over budget and has blown ...<|separator|>
  107. [107]
    Delay-plagued Eglinton Crosstown LRT delayed again
    Sep 28, 2022 · In 2018, Metrolinx paid Crosslinx an extra $237 million to keep the project on track and in February 2020 a delay was blamed on the consortium's ...Missing: evaluation | Show results with:evaluation
  108. [108]
    [PDF] Public-Private Partnerships and Light Rail Transit
    Apr 17, 2024 · Under the Eglinton Crosstown LRT AFP contract, the responsibility for some risks was not fully transferred to the AFP consortium, and Metrolinx ...
  109. [109]
    Metrolinx prepares for legal battle over Eglinton LRT project
    May 18, 2023 · The consortium is suing Metrolinx because they failed to retain an operator, causing delays and costs. Metrolinx calls it a "delay tactic".
  110. [110]
    [PDF] A CASE STUDY OF THE EGLINTON CROSSTOWN By Joseph To
    What causes cost overrun in transport infrastructure projects? Transport ... Decision-making on mega-projects: Cost-benefit analysis, planning and innovation.
  111. [111]
    Toronto's history of transit woes and why there's hope on the horizon
    Aug 26, 2024 · The plan for an Eglinton Crosstown LRT was born in 2007, and the project began construction in 2011. The budget for the design, construction and ...
  112. [112]
    A Controversial Project Nears Completion
    Toronto council dismissed Ford's concept and voted to forge ahead with a less expensive Light Rapid Transit system (as opposed to a subway) on Eglinton. The ...Missing: administration | Show results with:administration<|separator|>
  113. [113]
    Toronto - Eno Transit Project Delivery Initiative
    Nov 3, 2021 · Fraught transit governance that is subject to significant political interference can result in expensive low priority projects and significant ...Missing: critiques | Show results with:critiques<|separator|>
  114. [114]
    The real failure of the Eglinton Crosstown isn't the delays - TVO Today
    Dec 1, 2023 · “Out of Service” signs are shown on the Eglinton Crosstown LRT in Toronto on May 5. ... track alignment in one area that required significant work ...
  115. [115]
    The Problems with the Eglinton Crosstown are just getting started.
    which, as usual for Toronto, likely won't be reported ...
  116. [116]
    Ford government forced to release Eglinton LRT, Ontario Line emails
    Jul 17, 2025 · The Ford government has been ordered to release seemingly innocuous emails containing an outdated schedule for the Eglinton Crosstown LRT ...
  117. [117]
    Many Torontonians outraged about Ford's office ordering Metrolinx ...
    Aug 2, 2024 · Canadians are reacting to emails showing Doug Ford's office directing Metrolinx to keep the Eglinton Crosstown LRT opening date kept secret.Missing: critiques | Show results with:critiques
  118. [118]
    Toronto city council to ask province for public inquiry into Eglinton ...
    Oct 10, 2024 · Toronto city council will ask the Ontario government to hold a public inquiry into the repeatedly delayed Eglinton Crosstown light rail transit line.
  119. [119]
    Toronto City Council calls for public inquiry into much-maligned ...
    Oct 10, 2024 · The City of Toronto is calling on the Ford government to hold a public inquiry into what has gone wrong with the construction of the Eglinton Crosstown LRT.
  120. [120]
    New Democrats put pressure for public inquiry into Eglinton LRT fiasco
    Oct 15, 2024 · Ontario NDP is renewing the calls for a public inquiry into the Eglinton-Crosstown LRT delay after City Hall passed a motion for a provincial
  121. [121]
  122. [122]
    Indigenous-led coalition says it will stop construction to keep ... - CBC
    Jan 7, 2023 · An Indigenous-led coalition is resurfacing calls to bury a 1.5 kilometre stretch of the long-anticipated Eglinton Crosstown West Extension (ECWE) to protect ...
  123. [123]
    Indigenous-led protest not backing down to save trees from ...
    Jun 17, 2023 · A sacred fire and protest is approaching five months as an Indigenous-led coalition is not backing down in their fight to save an urban forest from LRT ...
  124. [124]
    Toronto park completely devastated as Metrolinx begins clearing ...
    Oct 23, 2024 · A Toronto park looks like a total wasteland this week as Metrolinx proceeds with the controversial clearcutting of over 1,200 trees.
  125. [125]
    [PDF] Investigating the Eglinton LRT Crosstown: Understanding the Impact ...
    In this research paper, I outline Flemingdon Park's development to understand the community's history and what it looks like currently with the construction of ...
  126. [126]
    [PDF] Eglinton LRT Project: - RCCAO
    The Metrolinx Eglinton Crosstown Light Rail. Transit Project in Toronto will result in the displacement of approximately 1,500,000 cubic metres of soil and fill ...
  127. [127]
    Eglinton Crosstown LRT - Resources - Metrolinx
    These studies include a business case, which presents evidence and analysis to explain why a project should be built, and an environmental assessment.
  128. [128]
    Metrolinx statement on Eglinton Crosstown LRT
    May 16, 2023 · Metrolinx is already withholding significant payments for poor performance. We will continue to hold CTS to account and examine every remedy ...
  129. [129]
    UPDATE: Legal battle brewing between Crosslinx Transit Solutions ...
    May 16, 2023 · Metrolinx is already withholding significant payments for poor performance. We will continue to hold CTS to account and examine every remedy ...
  130. [130]
    Eglinton Crosstown builder taking legal action against Metrolinx ...
    May 16, 2023 · A consortium of four companies building Toronto's Eglinton Crosstown project says it is taking legal action against Metrolinx over changes to the transit line ...Missing: alignment resolutions
  131. [131]
    Media Statement: Metrolinx, Infrastructure Ontario and Crosslinx ...
    Dec 22, 2021 · Metrolinx and Infrastructure Ontario are pleased to have reached a claims settlement agreement with Crosslinx Transit Solutions (CTS) worth $325 million.
  132. [132]
    Canada's construction industry urging governments to rebuild ...
    “Canada is facing its most severe labour shortage in over 50 years – nearly 1 million jobs are unfilled,” said Mary Van Buren, CCA president. “The situation is ...
  133. [133]
    Metrolinx begins final test of Eglinton Crosstown as councillor calls ...
    Oct 7, 2025 · A series of technical problems and associated cost overruns, however, have plagued the project and repeatedly delayed its completion.Missing: reports | Show results with:reports
  134. [134]
    [PDF] Eglinton Crosstown Rapid Transit Benefits Case - Metrolinx
    Options 1 and 2: Eglinton Scarborough Crosstown ... Don Mills and Eglinton-Yonge, effectively where the Eglinton Rapid Transit line.
  135. [135]
    Subway vs LRT vs BRT - CodeRedTO
    Unfortunately, building subways is very expensive—about three times the price of LRT—and it takes a lot longer. Above-ground rapid transit is also smart in many ...
  136. [136]
    Line 5 Eglinton - Wikipedia
    Surface stops would be spaced on average 500 metres (550 yd) apart and the underground stations would be 850 m (930 yd) apart on average, as constructing ...Eglinton East LRT · Jane LRT · Flexity Freedom · Mount Dennis station
  137. [137]
    What is wrong with the schemes? | Neptis Foundation
    Cost per new transit rider is high: $40,000 or more. At this rate, Metrolinx would need $50 billion to achieve its 2033 ridership objectives, not the $36 ...
  138. [138]
    [PDF] Subway Versus LRT in Median - City of Toronto
    Mar 16, 2012 · The Subway Plan outperforms the LRT plan in terms of speed, fewer transfers, station length to accommodate transit users waiting to board, ...
  139. [139]
    Comparing LRT and Subway Construction Costs
    Jan 24, 2012 · The construction cost of LRT is so significantly lower than Subway construction that in some cases it is possible build TWO, or even THREE parallel lines for a ...
  140. [140]
    Ontario Reaches Major Milestone on Eglinton Crosstown LRT ...
    Aug 9, 2017 · Ontario is fully funding the Eglinton Crosstown LRT to expand transit in the City of Toronto, with an investment of $5.3 billion. The Eglinton ...
  141. [141]
    Eglinton Crosstown West Extension.What We're Building - Metrolinx
    The Eglinton Crosstown West Extension will bring the Eglinton Crosstown LRT another 9.2 kilometres farther west, creating a continous rapid transit line.
  142. [142]
    Eglinton Crosstown West Extension.FAQs - Metrolinx
    As each major contract is awarded, the cost will be posted publicly. Procurement. Why is the project divided into multiple contracts? Dividing the project ...
  143. [143]
    WSP wins design contract for Eglinton Crosstown West Extension in ...
    Sep 2, 2025 · Plans are also being explored to extend the line another five kilometers to Pearson airport. The extension project broke ground in 2022 and has ...
  144. [144]
    Eglinton East Light Rail Transit
    ### Summary of Eglinton East LRT Project
  145. [145]
    Eglinton East LRT: Project Background - City of Toronto
    The Eglinton East LRT (EELRT) will bring higher order transit to historically underserved areas of Scarborough including eight Neighbourhood Improvement Areas.
  146. [146]
    [PDF] Advancing Eglinton East Light Rail Transit - City of Toronto
    Jan 14, 2025 · City Council approve the 10% functional design for the Eglinton East Light Rail. Transit (EELRT), as described in Attachment 1 – Environmental ...
  147. [147]
  148. [148]
    Light at the end of the tunnel for one of Canada's most expensive ...
    Jun 18, 2025 · The cost ballooned from $5 billion to $13 billion, and dozens of businesses have shut down, blaming the impact from the years of construction.
  149. [149]
    Eglinton Crosstown Line | Neptis Foundation
    Total daily riders 2023. 176,000. 220,000 ; New daily riders 2023. 44,000. 88,000 ; Incremental revenues $m NPV. $ 607. $ 1,214 ; NET FUNDING GAP $m NPV. $ -5,680.Missing: projections | Show results with:projections
  150. [150]
  151. [151]
    The Average Price of Single-family Detached Homes in Different ...
    Dec 7, 2022 · Generally, average housing prices were higher during the construction phase ($1.08 million) as compared to the announcement phase ($805k) across ...
  152. [152]
    Transit and Investment: How the Eglinton Crosstown LRT Is ...
    Sep 3, 2025 · Discover how Toronto's new Line 5 Eglinton Crosstown is reshaping condo demand and real estate values. Learn which neighbourhoods are best ...Missing: urban implications
  153. [153]
    After making Toronto home, PhD candidate explores potential ...
    Apr 2, 2024 · Arku's research explores how transportation and land use decisions affect people in urban areas, especially regarding housing, gentrification, and displacement.Missing: values | Show results with:values
  154. [154]
    Eglinton Crosstown West Extension - Arup
    The 9.2km extension will connect with the Mississauga Transitway and other local and regional transit, including the Union Pearson (UP) Express, Kitchener GO ...