Merowe Dam


The Merowe Dam is a concrete-faced rock-fill gravity dam spanning the Nile River in northern Sudan, approximately 350 kilometers north of Khartoum, constructed between 2003 and 2009 at a cost of $2.4 billion. With a crest height of 67 meters and a length of 9 kilometers, it forms a reservoir of 8.3 billion cubic meters, capable of storing about 20 percent of the Nile's annual flow. The dam's primary function is hydroelectric power generation, featuring ten Francis turbines with a total installed capacity of 1,250 megawatts, nearly doubling Sudan's national electricity output to around 2,250 megawatts upon completion.
Financed through a including the and constructed largely by Chinese firm , the project aimed to provide , expand irrigated from 10,000 to 207,000 acres, mitigate floods, and reduce sedimentation downstream at the Aswan High Dam. It generates over 6,500 gigawatt-hours annually, powering 90 percent of the region via extensive 500 kV and 220 kV transmission lines totaling 1,500 kilometers. These developments have supported for up to 3 million people through enhanced power supply and water management for 400,000 hectares of farmland. However, the reservoir inundated around 900 villages in the Fourth Cataract region, displacing 50,000 to 70,000 individuals primarily from the Manasir, Hamdab, and Amri communities. Government-led resettlement efforts, including new villages like New Hamdab and New Amri, involved compensation and housing but faced criticism for inadequate livelihoods, forced evictions via rapid flooding, and violent suppression of protests, such as the 2006 Amri incident where security forces killed at least three demonstrators. While some affected groups initially accepted relocation packages and a subset reported partial satisfaction, widespread dissatisfaction persisted over service delivery and economic viability, leading to ongoing local resistance including legal challenges and self-reliant adaptations like terrace farming.

Project Overview

Geographical and Strategic Location

The Merowe Dam is located on the River at the fourth in northern , approximately 350 kilometers northwest of the capital , within the Northern State near the town of Merowe. Its precise coordinates are 18.6689° N, 32.0503° E, positioning it in the region where the river flows through rugged granite formations characteristic of the cataract. This site lies downstream from the confluence of the White and Blue Niles but upstream of Egypt's major reservoirs, integrating it into the broader . Strategically, the dam's placement at the fourth cataract exploits the 's natural and elevation drop, optimizing hydroelectric potential in an arid environment with limited alternative energy sources. By controlling flow in this segment of the main , it enhances Sudan's capacity for —doubling national output upon completion—and expansion, supporting agricultural development in water-scarce areas. The location also underscores its role in national , reducing reliance on fossil fuels and imports, while situating as a key player in upstream amid regional tensions over water allocation.

Primary Objectives and Design Capacity

The Merowe Dam was constructed primarily to generate hydroelectric power, addressing Sudan's chronic electricity shortages and supporting national energy needs. With an installed capacity of 1,250 megawatts from ten turbine-generator units, the facility is engineered to produce approximately 5,600 gigawatt-hours of annually under optimal hydrological conditions. This output, derived from the Nile's flow regulated by the dam's 12.5 cubic kilometer reservoir, effectively doubled Sudan's total capacity upon completion, reducing dependence on costlier sources. Additional design objectives encompass water supply to expand in northern , where traditional flood-based farming predominates, and to protect downstream communities from the Nile's seasonal inundations. The project's multipurpose framework allows for controlled reservoir releases to irrigate over 1 million feddans (approximately 420,000 hectares) via associated canals, fostering agricultural intensification and . mitigation is achieved through the dam's capacity of up to 10,000 cubic meters per second, enabling storage of excess floodwaters for later use in power and . These capacities align with broader goals of regional , including job creation in construction and operations, as well as enhanced fisheries and in the Merowe area, though realization has been constrained by ongoing hydrological variability and grid challenges. Actual annual energy yields have averaged around 6,465 gigawatt-hours in baseline scenarios, influenced by upstream flows and .

Technical Specifications

Dam Infrastructure

The Merowe Dam is primarily a concrete-faced rockfill dam (CFRD) structure, supplemented by earthfill and rockfill sections to span the Nile River at the Fourth Cataract. The main CFRD on the right bank measures approximately 4,400 meters in length, while the left bank features a roughly 4,000-meter-long rock and earthfill embankment, and a 311-meter homogeneous earth dyke completes the barrier. The dam's total crest length reaches 9,280 , with a maximum structural height of 67 above the and a crest elevation designed to withstand regional . Construction utilized for the facing of the rockfill sections, enabling efficient placement and impermeability, while the core materials were sourced from local quarries to minimize transport costs and environmental impact. Waterproofing measures included polyurethane injections into core bores to seal potential seepage paths under hydrostatic pressure. Engineering design prioritized stability against seismic activity and flood events, incorporating zoned fill with impervious cores in earthfill portions to control seepage. The structure supports a impoundment while integrating and outlet works for regulated flow management, though specific spillway capacity details remain tied to reports.

Power Generation Facilities

The Merowe Dam's power generation facilities consist of a hydroelectric power plant with a total installed capacity of 1,250 MW, achieved through ten Francis-type turbines, each rated at 125 MW. The turbines are housed in an open-air powerhouse designed to handle high-volume water flow from the , with each unit capable of discharging approximately 300 cubic meters per second. The plant operates under a net head of 43 meters, enabling efficient conversion of hydraulic energy into via synchronous generators coupled to the turbines. Annual output is estimated at 5,600 to 6,000 GWh, varying with River inflows and reservoir levels, which directly influence turbine performance and grid supply reliability. These facilities were engineered by Chinese contractors, including Corporation, utilizing vertical technology optimized for the site's sediment-laden waters to minimize erosion and maintenance issues. The design prioritizes phased commissioning, with initial units becoming operational in 2009 to progressively ramp up to full capacity by 2010, supporting Sudan's national needs.

Reservoir Characteristics and Hydrology

The Merowe Reservoir, impounded by the Merowe Dam at the Fourth Cataract of the River in northern , has a total storage capacity of 12.5 billion cubic meters (12.5 km³) at its full supply level of 300 meters above mean . This volume represents approximately 15-20 percent of the 's average annual flow at that location, enabling significant regulation of river discharge for , , and mitigation. At full supply, the attains a maximum surface area of 800 km² and extends upstream for roughly 170 km, with a maximum depth of 57 meters. Observed post-impoundment data indicate a typical operational surface area of around 476 km², reflecting variations in levels managed for operational efficiency. Hydrologically, the receives an average annual inflow of 84 km³ from the upstream , dominated by seasonal floods from the and contributions, with peak discharges occurring during the July-October flood season averaging over 2,500 m³/s. directly on the contributes negligibly to inflows, while evaporation losses average 1.75 km³ annually under full surface conditions in the arid regional . The dam's operations prioritize generation, releasing an average of 31.5 km³ per year through turbines for controlled downstream flow, which mitigates flood peaks and stabilizes base flows for downstream users including the Hamdab Dam and High Dam. As a major trap, the captures significant upstream loads, with projected rates potentially reducing dead storage capacity over decades, though designs incorporate flushing mechanisms to maintain long-term viability.

Historical Development

Pre-Construction Planning and Feasibility

The planning for the Merowe Dam originated in the Sudanese government's efforts to develop large-scale following the 1989 military coup that brought to power, with initial reconnaissance surveys at the Fourth Cataract site conducted in 1989 and 1990 by national and international teams. These early assessments, partially financed by the , evaluated the site's geological and hydrological potential for a major dam, marking the project's transition from conceptual to practical evaluation amid Sudan's push for energy self-sufficiency. Subsequent feasibility studies in the 1990s, culminating in detailed technical evaluations by 1999, confirmed the viability of constructing a rock-fill with a 1,250 MW installed , designed to harness the 's flow for equivalent to addressing national shortages estimated at over 500 MW by the early , alongside expansion for up to 1 million hectares of . Sudanese authorities prioritized the Merowe location over alternatives due to its favorable , minimal risks compared to downstream sites, and to store approximately 12.5 billion cubic meters of in the , based on hydrologic modeling of average annual inflows exceeding 80 billion cubic meters at that reach. An (EIA) was prepared prior to construction approval, outlining hydraulic, geologic, and baseline ecological data, including projected inundation of 170 square kilometers and impacts on downstream flow regimes, though independent reviews later highlighted gaps in comprehensive social analysis and public disclosure, with no full made publicly available despite anticipated of 50,000 to 70,000 residents from upstream communities. The Sudanese government, through the Dam Implementation Unit established in 1999, endorsed proceeding without major international lender involvement after initial reconnaissance, citing self-financed viability via domestic revenues and Arab fund allocations, and dismissing opposition from affected Valley tribes as localized rather than prohibitive to national developmental imperatives.

Construction Timeline and Milestones

The Merowe Dam's construction phase spanned from 2003 to 2009, marking a significant effort led by Sudanese authorities in partnership with contractors including China's Corporation and Germany's Lahmeyer International. Initial site preparation and groundwork began on July 8, 2003, following feasibility approvals and funding commitments. Main construction activities, including foundation works and riverbed preparations, commenced in early December 2003. Key early milestones focused on river management to enable safe progression. The first phase of river diversion was executed in December 2003, involving the closure of the right river channel through upstream and downstream cofferdams, which facilitated dry construction conditions in the diversion channel. A second diversion phase followed in , fully redirecting flows to bypass the dam site via engineered tunnels and channels. These steps minimized flood risks during the core rockfill dam's embankment and concrete-faced slab installation, with the structure reaching its designed height of 110 meters by mid-2008.
MilestoneDateDescription
Project groundbreakingJuly 8, 2003Initiation of site clearance and preparatory works.
Main construction startEarly December 2003Launch of foundation and activities.
First river diversion phaseDecember 2003Closure of right with for diversion tunnel construction.
Full river diversion2004Completion of flow bypass to allow main body construction.
Core concrete completionMid-2008Finishing of mud-core elements in the earth-core rockfill structure.
First generators onlineMarch 3, 2009Connection of initial two 85 MW turbines to the national grid, initiating power generation.
Full operational capacityMarch 2009Inauguration of all ten turbines, achieving 1,250 MW total output.
The accelerated timeline, completed ahead of some initial projections despite logistical challenges in the remote northern Sudanese terrain, reflected efficient coordination among contractors and Sudanese oversight via the Dams Implementation Unit. Reservoir impoundment proceeded post-diversion, filling to support and objectives by late 2009.

Inauguration and Initial Operations

The Merowe Dam was formally inaugurated on March 3, 2009, by Sudanese President , who described the project as the "project of the century" during the ceremony attended by national officials and participants transported from various regions. The event highlighted the government's emphasis on infrastructure as a symbol of national progress, coinciding closely with international legal pressures on Bashir, including an impending indictment issued the following day, which some observers attributed to political motivations for the timing. Initial operations commenced immediately following the inauguration, with the first two of the dam's ten 125-MW Francis turbine-generators connected to Sudan's national grid on the same date, marking the onset of hydroelectric power production from the 1,250 MW facility. The project, designed to nearly double the country's electricity capacity at the time, began contributing to the grid progressively, though full operational capacity of all turbines was targeted for later in 2009, with reports indicating substantial power output achieved by 2010 as additional units came online. Early performance focused on hydropower generation to alleviate chronic shortages, integrating output via high-voltage transmission lines to northern and central Sudan, while reservoir filling and hydrological stabilization proceeded to support both electricity and ancillary irrigation functions.

Financing and Partnerships

Funding Mechanisms and Sources

The Merowe Dam project was primarily financed through concessional loans from export credit agencies and Arab development funds, with the Sudanese government providing supplementary domestic funding to cover equity and any shortfalls. The total project cost was estimated at $2.4 billion, reflecting escalations from initial projections of around $1.2 billion due to construction delays, supplementary works, and inflation. These loans were often tied to procurement from contractors in the lending countries, such as Chinese firms for the China Eximbank portion, aligning financing with technology transfer and export promotion objectives. China's Export-Import Bank extended a $608 million specifically for the 1,250 MW hydroelectric power plant, representing a core pillar of the funding structure and enabling rapid construction by state-owned enterprises like . This was complemented by a $250 million contribution from the Arab Fund for Economic and Social Development, including supplementary loans for overflow canals and related . Gulf-based funds played a key role in bridging gaps, with the providing $200 million in 2002 for dam construction, while the and Fund for Arab Economic Development offered additional loans totaling around $52.5 million for phase 2 expansions and ancillary features like the Hamdab . The Sudanese government allocated budget resources equivalent to roughly 20-30% of the total, drawn from oil revenues during the mid-2000s boom, though exact figures remain opaque due to limited public disclosure. No grants were predominant; the structure emphasized debt instruments with repayment terms linked to future revenues projected at $100-150 million annually post-commissioning.

International Contractors and Technology

The construction of the Merowe Dam involved a of primarily Chinese state-owned enterprises as the main international contractors, reflecting Sudan's partnerships with for large-scale infrastructure projects. China International Water & Electric Corporation (CWE) served as the lead contractor for civil works, including the dam's concrete gravity and earthfill sections, while Corporation Limited handled key implementation phases such as preparation and core structure erection. Harbin Power Engineering Company contributed to engineering design, particularly for the powerhouse and associated hydroelectric components, ensuring integration of the 1,250 MW capacity with six 208 MW Francis-type turbines. European firms provided specialized technical expertise and equipment, supplementing the Chinese-led effort. Germany's Lahmeyer International acted as the independent engineering consultant, overseeing planning, feasibility studies, and construction supervision to align with international standards for hydraulic and structural integrity. France's Power was awarded the €260 million mechanical and electrical (M&E) package in 2004, supplying turbines, generators, and control systems critical for power generation efficiency and grid synchronization. Additional contributions included Switzerland's ABB for a $16 million and substation upgrade contract, facilitating the extension of high-voltage lines from the dam site. The technology deployed emphasized robust, scalable hydroelectric systems suited to the Nile's flow regime, with (RCC) techniques accelerating dam wall construction to minimize curing times and costs. Advanced (SCADA) systems from and ABB enabled remote monitoring of operations, water levels, and management, reducing downtime and enhancing output reliability to an average of 5.5 billion kWh annually. These integrations prioritized durability against seismic activity and flash floods, drawing on proven designs from similar Chinese projects like the , though adapted for the Fourth Cataract's geological constraints.

Economic and Developmental Benefits

Electricity Supply and National Grid Integration

The Merowe Dam's hydropower plant features an installed of 1,250 megawatts (MW), generated by ten turbines each rated at 125 MW. This enables an annual electricity output of approximately 5,600 gigawatt-hours (GWh), primarily serving periods through controllable generation. At the time of its inauguration in 2009, the dam nearly doubled Sudan's total installed electricity from around 1,000 MW, positioning it as the country's largest single power source and a cornerstone for addressing chronic shortages in urban centers like . Integration into Sudan's national involved the construction of high-voltage transmission lines totaling 1,776 kilometers, linking the dam's 1,400 megavolt-ampere (MVA) substation directly to key load centers and interconnecting with existing infrastructure. This setup facilitates efficient power evacuation, with the dam's output synchronized to the 's 50 Hz frequency for stable delivery, marking a technical advancement in Sudan's energy infrastructure by enabling remote to support northern and central regions. Post-2009 operations have seen Merowe contribute roughly 50% of Sudan's total production, enhancing reliability despite seasonal flow variations that influence actual output below . The dam's role extends to cross-border potential, with provisions for exporting surplus , though domestic prioritization has focused on reducing load-shedding in and residential sectors; by 2020, it accounted for a significant share of the national total of 1,907 MW. Challenges in include grid losses from long-distance and vulnerability to or , as evidenced by disruptions during Sudan's civil unrest, yet empirical data affirm its outsized impact on electrifying remote areas previously reliant on generators.

Irrigation Expansion and Agricultural Productivity

The Merowe Dam's , with a capacity of 12.5 billion cubic meters, enables regulated water releases that support year-round in northern , extending beyond seasonal floods. This infrastructure facilitates the development of irrigation schemes, including the Hamdab extension, which draws from the dam to cultivate arid lands along the . Pre-dam planning targeted of approximately 120,000 hectares on both riverbanks through gravity-fed canals and systems, transforming rainfed or flood-dependent farming into operations. Empirical assessments indicate that the dam has expanded irrigated areas in the Northern State, enabling larger farm holdings and a transition from subsistence to commercial agriculture. Local perceptions, drawn from surveys of affected communities, highlight increased land access and adoption of mechanized techniques, such as electrified pumps powered by the dam's grid integration, which have boosted crop yields for staples like wheat and cash crops including fruits and vegetables. Productivity gains stem from reliable water supply mitigating drought risks, with respondents reporting higher incomes from diversified outputs, though realization varies by scheme efficiency and soil quality.
Key Agricultural ImpactsDescriptionSource
Irrigated Area ExpansionEnabled perennial for planned 120,000 via storage and canals
Farming ShiftFrom small-scale family farms to commercial operations with
Yield and Income EffectsIncreased via electrified and modern systems; perceived rises
These developments contribute to Sudan's broader agro-economic framework, though sustained productivity requires complementary investments in and extension services to address variability in outcomes.

Job Creation and Infrastructure Spillovers

The construction and operation of the Merowe Dam generated direct for over 400 individuals, with approximately 350 locals hired in roles such as accountants, engineers, , electricians, drivers, and laborers. Complementary agricultural and industrial projects associated with the dam further expanded job opportunities, including around 400 positions at the Al Nile Poultry Company in New Amri—many held by women—and 120-130 roles in the Al Makabrab scheme, where 80% of the 145 staff comprised displaced persons. Additional arose in sectors like farming factories, artisanal , and labor on Dam Implementation Unit (DIU)-owned commercial farms, contributing to a shift from subsistence to commercial that indirectly supported livelihoods for communities reliant on the sector, which employs about 60% of Sudan's workforce. Local and displaced communities reported varied perceptions of these employment gains, with 52% noting positive economic impacts including job creation, though upstream-relocated groups expressed lower satisfaction due to inadequate support limiting sustained agricultural jobs. The dam's supportive projects fostered skill development in , , and services, enhancing long-term amid Sudan's agriculture-dominated . Infrastructure spillovers extended beyond the dam itself, including the 42 km Merowe Dam Road built to facilitate equipment transport, alongside tarmac connections to the Northern lifeline Highway from Khartoum, which reduced travel time to Merowe from four days to three to four hours via improved bus services. Bridges such as the Merowe Karimah Bridge and three additional major spans enhanced regional connectivity, while an airport and paved roads supported broader access to previously isolated areas. Health facilities proliferated with the construction of Merowe New Hospital (also known as Chinese Hospital) and a well-equipped hospital plus four medical centers in New Amri, staffed by midwives and specialists, improving access in resettlement zones equipped with electricity, schools, and marketplaces. Educational infrastructure saw expansion through establishments like and Merowe University of Technology Abdulatif Alhamad, alongside six regional colleges benefiting from reliable , which enabled vocational training aligned with emerging economic needs. Transmission lines integrated the dam's 1,250 MW output into Sudan's national grid, spurring that supported ancillary developments like modern housing and commercial hubs, though these benefits were unevenly distributed, with downstream communities reporting higher gains than upstream ones. Overall, these spillovers catalyzed non-agricultural diversification into services, small , and , correlating with perceived rises in income sources and .

Social and Demographic Impacts

Displacement Scale and Resettlement Programs

The Merowe Dam's reservoir flooded approximately 174 kilometers of the River valley, displacing an estimated 50,000 to 70,000 people primarily from the Manasir, Hamdab, and Amri communities between 2003 and 2008. These populations, reliant on riverside and , inhabited around 30 villages in fertile areas that were inundated, with the Manasir tribe bearing the largest impact as semi-nomadic herders and farmers. The Sudanese Dam Implementation Unit oversaw resettlement, relocating over 4,700 families from Hamdab and Amri to pre-designated desert sites such as and Kehaila East, where sandy soils and scarce groundwater hindered farming viability compared to original Nile-adjacent lands. Compensation packages included cash payments, housing construction, and transplantation of date palms, but lacked comprehensive provisions for or livelihood restoration, leading to documented reliance on food aid in new settlements. International financing supplemented domestic efforts, with a $37.7 million from the Chinese government funding infrastructure at Kehaila East to support displaced Manasir households. Programs emphasized rapid relocation to meet timelines, yet faced allegations of inadequate consultation, exemplified by the unannounced flooding of Amri properties in August 2006, which submerged homes and assets for about 3,000 families without evacuation. Despite government assertions of equitable compensation based on property valuations, independent assessments highlighted disparities, with pastoralists receiving less tailored support than sedentary farmers.

Nomadic Livelihood Disruptions

The Merowe Dam's , formed between 2006 and 2009, flooded approximately 170 kilometers of the River valley in northern , submerging traditional lands and watering points essential to nomadic pastoralists, particularly nomadic segments of the Manasir tribe who inhabited fringes adjacent to the river. These groups, numbering in the thousands within the broader 30,000–50,000 displaced households from Manasir, Amri, and Hamdab communities, depended on seasonal for , with , camels, and sheep on flood-recession pastures and accessing riverine sources. The inundation severed established corridors, compelling herders to detour through arid, non-traditional paths or confine movements to shrinking peripheral zones around the , thereby increasing vulnerability to and reducing herd viability. Post-displacement resettlement schemes relocated many to remote sites such as Al-Makabrab and Kehila, where and lack of sources rendered sustained untenable, forcing a shift toward sedentary or marginal farming with limited success. Livestock-dependent incomes reportedly declined by around 50% for affected households due to lost access to fertile floodplains and groves that supplemented economies, with surveys indicating a drop in livestock farming prevalence from pre-dam levels to 24–40% among relocated groups. Nomads faced additional barriers, including occupation of pre-existing wells by authorities in areas like Sani in 2005, exacerbating for animals and prompting herd reductions or sales at undervalued prices. Approximately 60% of Manasir households rejected official resettlement by 2009, opting instead to cluster on islands or embankments, where periodic flooding risks persisted and access to veterinary services or markets diminished, leading to heightened economic marginalization and fragmentation. These disruptions compounded broader impoverishment, as —key to risk diversification in Sudan's variable climate—proved incompatible with the dam-induced landscape alterations, with no verified evidence of compensatory provisions restoring pre-project patterns. Empirical assessments highlight ongoing reliance on improvised wells and reduced herd sizes, underscoring causal links between formation and eroded without adaptive .

Empirical Outcomes on Affected Populations

Resettled communities from the Amri and Manasir regions experienced significant disruptions following , with rates in affected areas rising from approximately 10% in 2003 to 65% by 2005 due to loss of fertile Valley farmland and relocation to arid sites unsuitable for traditional . Compensation for submerged assets, such as date palm groves, was deemed inadequate by displaced households, often based on outdated valuations that undervalued long-term productivity and excluded non-traditional landowners like migrant laborers, leading to a reported 40% loss of s and up to 50% reduction in agricultural income for upstream-resettled groups. A survey of 300 households across upstream, downstream, and resettled sites found that 64% of upstream residents held negative views of the dam's impacts, citing deficiencies and unequal benefit distribution, though 111 out of 150 respondents with expanded allocations post-resettlement reported income gains linked to increased plot sizes. Health outcomes were mixed, with a 2014 entomological study documenting the dam's role in interrupting (river blindness) transmission in the Hamed focus by 2011, as flooding submerged key blackfly sites, reducing adult densities from monthly biting rates of 651–59,514 per person pre-dam (2007–2008) to near zero post-impoundment (2010–2011). However, the same survey revealed 66% of respondents experiencing , attributed to reliance on shallow underground wells in resettlement areas lacking reliable access, while a pre-construction projected exacerbation of vector-borne illnesses including , , and due to stagnant waters and altered hydrology. Socially, resettlement yielded some improvements in living standards, with 77% of upstream-relocated households expressing with larger home sizes compared to pre-displacement structures, and enhanced to for children rated positively (mean of 3.18 for upstream-relocated). opportunities arose in ancillary sectors like services and small , though these were unevenly distributed and ranked lower in perceived economic value ( 2.36). Negative effects included heightened social fragmentation, with 48% of surveyed households reporting increased community conflicts, particularly among Manasir nomads facing livelihood erosion from flooded grazing lands and cultural disruptions. Overall, 55.6% of respondents perceived net positive social changes, but downstream and host communities benefited more from infrastructure spillovers like (90% approval) than directly affected groups.

Environmental Assessments

Water Resource Management and Evaporation Losses

The Merowe Dam facilitates water resource management primarily through its , which stores Nile River inflows to support hydroelectric generation, seasonal flow regulation, and supplementary downstream. Completed in 2009, the dam's has a live of approximately 12.5 billion cubic meters, enabling controlled releases that stabilize water availability during dry periods and attenuate flood peaks from upstream catchments. This regulation addresses historical variability in Nile flows, where annual discharges at the site average around 35-40 billion cubic meters, by prioritizing power production—turbining up to 31.5 billion cubic meters annually—while reserving portions for agricultural use in the and other schemes via canal diversions. Evaporation constitutes a primary inefficiency in this system, driven by the reservoir's expansive surface area of roughly 700-800 square kilometers in Sudan's arid northern , where exceeds 2,000 millimeters annually. Estimates indicate annual losses of 1.5 to 1.75 billion cubic meters, representing 8-10% of Sudan's 18.5 billion cubic meter allocation under the 1959 Waters Agreement. These losses arise from the reservoir's , which increased the 's local surface area by about 270 square miles, amplifying to high solar radiation and low humidity; studies confirm as a dominant outflow component, validated against measured inflows and releases by Sudan's Hydraulic Research Center. Management strategies to mitigate such losses include operational rules that minimize drawdown during peak months ( to October) and integrate seepage estimates—typically under 0.5 billion cubic meters yearly—into balance computations for accurate forecasting. However, the dam's upstream position relative to downstream reservoirs like Roseires limits cascading benefits for control, and projections under variability suggest potential increases in losses if inflows decline or temperatures rise, underscoring trade-offs between storage benefits and unrecoverable volumetric waste. Empirical monitoring post-impoundment in 2006 has informed adaptive releases, though independent assessments note that without advanced covers or recirculation technologies—rare in large tropical s—these losses remain inherent to the design.

Biodiversity and Ecosystem Alterations

The Merowe Dam's , with a storage capacity of 12.4 billion cubic meters, inundated approximately 55 square kilometers of irrigated land and 11 square kilometers of farmland upon filling in , submerging terrestrial habitats including riparian vegetation and contributing to the fragmentation of local . Independent reviews of the project's (EIA) have highlighted deficiencies in documenting affected , predicting significant loss for adapted to the pre-dam riverine . Seasonal fluctuations in reservoir levels, ranging from a maximum inundated area of around 800 square kilometers to 350 square kilometers, expose expansive drawdown zones to aeolian erosion, further degrading soil stability and vegetation cover in the arid surroundings. Aquatic biodiversity has been profoundly altered by the dam's barrier effect, which blocks upstream migration of potamodromous species such as Barbus bynni and Labeo niloticus, isolating populations between the Merowe and Dams over a 700-kilometer stretch of the and disrupting spawning and feeding cycles. The EIA underestimated these impacts by claiming negligible effects on fauna, whereas reviews criticize the lack of comprehensive inventories and plans, noting that reservoir during hot seasons induces hypoxic conditions that reduce suitable habitats for benthic and pelagic . Daily hydropeaking operations, causing fluctuations of 2.6 to 4.9 meters downstream, erode riverbanks, destroy spawning grounds, and fragment communities, leading to declines in native health, survival, and overall productivity. Downstream ecosystems face reduced sediment flux, with the dam trapping about 90% of incoming load—estimated at 130 million tons annually—diminishing delivery to benthic communities and potentially lowering long-term river productivity. These hydrological alterations, including regulated flows and temperature shifts, exacerbate for riparian and aquatic invertebrates, though empirical post-impoundment monitoring remains limited, with reviews attributing ongoing erosion to unaddressed EIA flaws rather than adaptive fisheries development. While the may support some lacustrine , the net outcome favors simplification, with migratory and river-dependent taxa experiencing the most severe declines.

Public Health Considerations

The Merowe Dam's has altered aquatic habitats in northern , potentially influencing the transmission of vector-borne diseases by providing new breeding sites for mosquitoes and snails while submerging others for blackflies. Pre-construction environmental impact assessments highlighted risks of exacerbating and due to stagnant water favoring Anopheles mosquitoes and Biomphalaria or Bulinus snails, respectively, though comprehensive post-impoundment monitoring has been limited. Contrary to expectations for river blindness (), the dam has had a beneficial effect by flooding blackfly (Simulium hamedense) breeding sites along rapids in the Abu Hamed focus, reducing density from 1,200 bites per person per month pre-dam to near zero post-2009 impoundment, contributing to verified interruption of transmission by 2013. For , post-dam surveys in Merowe Locality indicate low prevalence of among schoolchildren (0-5% in sampled foci as of 2022), with the area historically a low-endemic zone experiencing only sporadic cases tied to floods rather than reservoir-driven surges. Malaria transmission dynamics show mixed patterns near the dam, with studies noting potential for heightened arabiensis activity in irrigated perimeters and reservoir fringes, though no quantified post-dam spike has been documented specific to Merowe; general dam meta-analyses attribute 0.9-1.7 million annual cases continent-wide to s, underscoring the need for . Displacement of approximately 50,000-70,000 residents to resettlement sites has raised secondary concerns for sanitation-related illnesses, including risks of outbreaks in altered pastoral ecosystems, but empirical data on elevated morbidity remains sparse amid broader Sudanese health system strains.

Cultural and Archaeological Dimensions

Submerged Heritage Sites

The construction of the Merowe Dam, completed in 2009, created a 174-kilometer reservoir that inundated the Fourth Nile Cataract region, submerging more than 1,000 archaeological sites documented in the project's Environmental Impact Assessment. These sites encompassed a range of prehistoric to historic remains, reflecting continuous human occupation from the Middle Palaeolithic period onward, including lithic scatters, settlements, cemeteries, rock art, tombs, and monumental structures such as medieval fortresses and early Kushite pyramids. The flooding permanently buried these heritage elements under sediment-laden water, eliminating opportunities for further study without prior excavation, though salvage surveys recorded approximately 2,800 sites across the affected left bank, islands, and adjacent areas between Amri and Kirbekan. Archaeological evidence from the submerged zone highlights the Fourth Cataract's role as a corridor for Nile Valley cultures, with sites spanning Early habitations, Kerma-period burials (circa 2500–1500 BCE), Kushite settlements and cemeteries (including Meroitic phases from 300 BCE to 350 ), and Medieval Christian churches and graves. Rock drawings and inscriptions, often depicting , hunters, and motifs, were prevalent on cliff faces and boulders now underwater, providing insights into prehistoric and practices. Key examples include Site 4-F-6, an early Kushite structure indicative of burial practices, and Site 4-L-88, a Classique cemetery yielding pottery and skeletal remains that illuminate mortuary customs. These losses represent irrecoverable data on Sudan's rural historical sequences, as the reservoir's depth—up to 80 meters in places—precludes non-invasive recovery post-inundation. Prior to filling the reservoir in late 2008, the Merowe Dam Archaeological Salvage Project, initiated in 1999 by the Archaeological Research Society with support, conducted surveys and limited excavations, but coverage was constrained by the vast 170-kilometer impact zone and local opposition from affected Manasir communities, who prioritized displacement concerns over heritage work. In some instances, flooding occurred before full evacuation or archaeological clearance, as seen in 2008 inundations of surveyed islands, underscoring tensions between development imperatives and cultural preservation. Artifacts recovered, such as ceramics and burial goods, are housed in institutions including the Sudan National Museum and Merowe Museum, but the submerged corpus remains inaccessible, limiting causal understandings of environmental adaptations and cultural transitions in the region.

Salvage Operations and Preservation Data

The Merowe Dam's inundated the Fourth region, endangering over 1,000 archaeological sites documented in environmental assessments, prompting the Merowe Dam Archaeological Salvage Project (MDASP) as an international collaborative effort led by Sudan's National Corporation for Antiquities and Museums (NCAM). Operations commenced in the late and intensified from onward, with multiple foreign and domestic teams assigned concessions to conduct surveys, test excavations, and full digs before filling began following the dam's inauguration on , 2009. These efforts focused on recording and excavating sites threatened by submersion, prioritizing multiphase settlements, cemeteries, and from Palaeolithic to Islamic periods, though time limitations prevented comprehensive coverage of all identified locations. The Sudan Archaeological Research Society (SARS), a British-led team, surveyed and excavated a 40 km concession along the Nile's left bank and adjacent islands between Amri and Kirbekan from October 1999 to November 2007, registering over 670 sites including enclosures, tumuli, occupation scatters, and medieval Christian box graves. Key findings encompassed Middle Palaeolithic tools, pottery and lithics, Kerma-period tumuli (such as clusters of 50–80 burials at sites like 4-L-2), post-Meroitic bead-adorned graves, and Kushite remnants, with many structures showing evidence of ancient but preserved architectural features like circles. Complementary work by teams from the , Poland's Gdansk Archaeological Museum, and others on the right bank uncovered Kerma-era (1700–1500 B.C.) gold-processing sites at Hosh el-Guruf, featuring grinding stones and a yielding 101 gold beads alongside vessels, underscoring the region's role in ancient Kushite-Egyptian trade networks. Preservation outcomes included relocation of select artifacts to institutions such as the , Sudan National Museum, and the dedicated Merowe Museum, alongside production of draft reports, typological series for monuments, and ongoing multi-volume publications funded by entities like the Packard Humanities Institute. Despite these measures, substantial irrecoverable losses occurred, as hundreds of sites—particularly in resettlement zones like El Multaga, where 120 were noted—remained partially undocumented or unexcavated due to project delays and resource constraints, with submerged heritage now inaccessible without advanced underwater methods not employed at the time. Post-salvage analyses have informed Nubian chronology but highlight gaps in data from unprobed areas, emphasizing the salvage's partial success in empirical documentation amid logistical challenges.

Controversies and Stakeholder Perspectives

Compensation Disputes and Protest Movements

The Merowe Dam's reservoir inundated lands inhabited by the Hamdab, Amri, and Manasir tribes, displacing an estimated 50,000 to 70,000 people between 2003 and 2009. Sudanese government compensation included cash payments, replacement housing in designated villages, and irrigated farmland allocations, but affected communities reported these measures failed to replicate prior riverine , leading to economic marginalization and reliance on arid relocations unsuitable for traditional farming and . Disputes intensified over lack of meaningful consultation and perceived undervaluation of lost assets, such as groves and fertile floodplains, with Manasir representatives rejecting proposed sites in al-Muqaddam as ecologically barren and distant from access. Initial acceptance by some groups eroded as relocations proceeded without equitable land-for-land swaps, prompting organized resistance from tribal councils demanding veto rights or enhanced packages. Protest movements emerged in 2005 amid arrests of community leaders opposing opaque dam planning, escalating into mass demonstrations by 2006. On April 22, 2006, pro-government militia fired on Amri villagers protesting forced eviction, killing at least three and wounding over 50 in an attack involving machine guns and artillery. Clashes continued in June 2007, when dispersed Manasir protesters rejecting relocation, resulting in four deaths and at least 10 injuries from live . responses involved unannounced reservoir filling in August 2006, flooding over 100 Amri families on islands without prior evacuation, further fueling accusations of deliberate over . Post-dam completion, movements persisted with Manasir blockades of access roads in 2010-2011 to demand revisited compensation, culminating in mediated settlements by 2012 offering additional funds but leaving underlying grievances over livelihood restoration unresolved. Demands resurfaced in 2017 from displaced seeking fair reassessment of losses amid ongoing impoverishment.

Human Rights Claims Versus Government Responses

Human rights advocates and displaced communities have alleged that the construction of the Merowe Dam involved forced evictions without adequate consultation, affecting an estimated 60,000 Nubian residents through loss of ancestral farmlands, homes, and traditional livelihoods dependent on the . In August 2006, approximately 2,200 families, primarily women and children, were compelled to abandon their homes as the reservoir flooded the area, with reports of minimal or no compensation for lost fruit trees and structures. Protests against these displacements, such as those in April 2006 at Amri village, were met with lethal force; , including armed in the presence of , fired live , killing at least three demonstrators and injuring over 40 others. Additional incidents included the , , and of organizers in Hamadab, where families were relocated to arid sites unsuitable for agriculture. The Sudanese government has countered these allegations by emphasizing the dam's role in national development, asserting that it generates 1,250 megawatts of to address chronic shortages and foster across . Officials claimed to have provided compensation packages including cash payments for lost assets, new housing, resettlement land plots, and free for ten years to affected families. In response to protests, the government deployed army units and local , framing unrest as instigated by political opponents rather than legitimate grievances, and denied systematic abuses while upholding project implementation as a priority. Disputes over compensation persisted, with resettled communities reporting sandy, infertile soils at sites like New Amri and that rendered farming unviable, exacerbating and food insecurity. A 2015 court ruling rejected further claims for damages by displaced persons, prompting protests in ad-Damir where hundreds demanded reconsideration of losses from seven years prior. The government's position aligns with invoking the under international norms, prioritizing infrastructure benefits over individual relocation challenges, though independent assessments, such as those urged by UN experts in 2007, highlighted unaddressed violations amid opposition. In 2016, the African Commission on Human and Peoples' Rights declared admissible a complaint against for mass forced evictions and suppression of related to the Merowe and other dams, signaling ongoing contention without resolution.

NGO Critiques and Alternative Viewpoints

Non-governmental organizations, including International Rivers and the Corner House, have criticized the Merowe Dam for displacing approximately 50,000 to 60,000 Manasir Nubian residents from fertile Nile Valley lands to arid desert resettlement sites lacking water and agricultural viability, in violation of international standards such as those from the World Commission on Dams. These groups documented inadequate consultation, with affected communities excluded from planning and represented only by government-appointed agents. An independent review commissioned by NGOs highlighted flaws in the project's , including unaddressed sedimentation risks—up to 130 million tons annually, potentially reducing capacity by 34% within 50 years—and downstream ecological disruptions like 4-5 meter daily water level fluctuations eroding banks and blocking . Human rights-focused NGOs reported violent suppression of protests, such as the April 2006 clashes where Sudanese killed three civilians and injured over 50 using live against peaceful demonstrators opposing forced relocation. Additional incidents included arbitrary arrests, of activists, and deliberate flooding of villages to coerce compliance, prompting a 2007 UN Special Rapporteur to urge a halt to due to forced evictions and rights abuses. Critics from these organizations argue the project exemplifies broader patterns of repression under Sudan's authoritarian regime, prioritizing state control over . Alternative viewpoints, advanced by Sudanese government officials and the Dam Implementation Unit, emphasize the project's national benefits, including 1,250 megawatts of hydroelectric power—enough to electrify rural areas and support industrial growth—and expanded for , positioning the dam as a of economic modernization. The government maintained that compensation packages, comprising cash payments, new housing, and allocated farmland, addressed resettlement needs, with a 2006 Nile State agreement purportedly securing consensual relocation terms despite subsequent rejections by project authorities. Proponents contend that such infrastructure is essential for in a resource-scarce , outweighing localized disruptions, and have dismissed NGO as exaggerated by anti-development activists lacking appreciation for Sudan's sovereignty in .

Political and Geopolitical Ramifications

Domestic Policy Debates and Implementation

The Merowe Dam was advanced as a initiative under Sudan's autocratic regime led by President , forming part of the Al-Ingaz government's post-1999 oil-era economic policy to foster energy self-sufficiency, double national capacity, and enable infrastructure-led industrialization through hydroelectric projects. The project aligned with nationalist discourses that blended Islamist with , portraying dams as symbols of and unity amid ethnic diversity, as propagated in like the Sad Merowe magazine series. Implementation was centralized under the Dam Implementation Unit (DIU), later integrated into the Ministry of , , and , with construction commencing in 2003 by the China International Water and Electric Corporation and completion of the 1250 MW facility by 2009, at a cost exceeding $1.8 billion primarily funded by Chinese and Sudanese sources alongside Middle Eastern loans. Domestic debates were constrained by the regime's undemocratic structure, where the State Minister for acted as the primary decision-maker, issuing Presidential Decree No. 217 in 2005 to authorize the project without broad parliamentary consultation or public access to environmental impact assessments. Opposition from affected Nile Valley communities, including the Manasir and Amri tribes, centered on inadequate resettlement planning—such as the rejection of upstream sites like Al-Multaga due to risks—and violations of the 2005 Interim Constitution's provisions for and property rights, though legal frameworks like the 1930 Land Acquisition Act were invoked to justify expropriations. Pro-dam arguments emphasized economic imperatives, including the dam's role in supplying approximately 50% of Sudan's needs and supporting for agricultural modernization, contrasting with critics' focus on unequal decision-making participation and long-term livelihood disruptions for 30,000–50,000 displaced individuals between 2006 and 2009. Implementation proceeded amid repression of , with the DIU employing deliberate flooding strategies from 2006 to coerce relocations to downstream "model villages" lacking and promised services, contravening World Commission on Dams guidelines on voluntary resettlement. Compensation policies offered three hectares of replacement land per hectare lost, plus an additional three hectares for displaced families, but payments were often delayed or unfulfilled, exacerbating conflicts documented in UN reports and leading to violent clashes, such as the 2003 protest dispersal by live . The government's handling prioritized rapid execution over consensus, reflecting a hegemonic approach that marginalized local input in favor of top-down , though post-construction evaluations noted persistent shortfalls and delays undermining projected agricultural gains.

International Diplomacy and Aid Dynamics

The Merowe Dam project, estimated at $2.4 billion, was predominantly financed through a concessional loan from the Export-Import Bank, which acted as the primary lender and enabled construction despite Sudan's economic isolation from Western donors following conflicts such as . The contributed $200 million, with additional support from other Arab financial institutions and the Sudanese government, reflecting a model that bypassed conditional Western tied to and environmental standards. This funding structure underscored 's non-interference policy in recipient countries' internal affairs, contrasting with multilateral institutions' reluctance to engage due to concerns. Chinese development assistance to , where and projects like Merowe accounted for approximately 70% of total commitments—including the Khartoum refinery—filled a gap left by declining aid from traditional donors post-2005 pledges of $4.5 billion from international sources that prioritized over . AidData indicates that such investments supported Sudan's political survival strategies by bolstering regime-aligned , with Merowe's completion in 2009 doubling national capacity and enhancing . This dynamic shifted Sudan's foreign relations toward , fostering resource-backed loans and technology transfers without governance preconditions. Diplomatically, the project exemplified China's global expansion in , involving Corporation alongside German and French engineering firms for turbine and expertise, which facilitated technical but drew limited scrutiny compared to downstream disputes. Bilateral ties were reinforced through high-level engagements, positioning Merowe as a of Sudan-China cooperation amid broader initiatives, though it elicited critiques from environmental NGOs for prioritizing economic outputs over social impacts.

Strategic Role in the 2023–Present Sudanese Civil War

The Merowe Dam, Sudan's primary hydroelectric facility generating approximately 1,250 megawatts and supplying up to 70% of the nation's electricity, has emerged as a critical strategic asset in the ongoing civil war between the and the , which began on April 15, 2023. Located in Northern State about 350 kilometers north of , the dam underpins power distribution to SAF-controlled regions, including the capital and eastern ports, making its disruption a means to erode the SAF's logistical and governance capabilities. RSF forces deployed near Merowe as early as April 11, 2023, signaling its perceived value, though ground control has remained with the SAF, which stations the 19th Infantry Division headquarters there. RSF strategy has emphasized aerial assaults on the dam to sever electricity and water supplies, aiming to induce civilian hardship and undermine SAF authority without committing to costly ground offensives. Between October 2024 and March 2025, the RSF conducted approximately 50 drone strikes targeting the Merowe Dam alongside Dongola and Atbara airports, with roughly half focused on the dam itself to overload defenses and inflict cumulative damage. A notable escalation occurred on January 13, 2025, when RSF drones struck the dam's power station and transformer, igniting a fire that caused widespread blackouts in Khartoum, Northern, and River Nile states, exacerbating water shortages in areas like Omdurman. The Arab League condemned this attack on Africa's largest hydropower project, highlighting its role in regional power stability. SAF air defenses have intercepted multiple subsequent drone incursions, including several on June 19, 2025, preserving operational continuity but revealing the dam's vulnerability to asymmetric RSF tactics reliant on imported drones. Control of Merowe bolsters SAF's and military mobility in northern theaters, while RSF targeting reflects a broader to fragment SAF-held , as seen in parallel strikes on eastern grids and ports. These operations have not yielded territorial gains for the RSF but have intensified humanitarian strains, with power disruptions hindering , hospitals, and urban economies in SAF zones, thereby pressuring the military government's . The dam's defense underscores SAF prioritization of vital nodes over peripheral fronts, yet persistent RSF campaigns—potentially sourced from external backers—pose risks of long-term degradation, potentially shifting the war's momentum if repairs lag amid sanctions and supply constraints.

References

  1. [1]
    Merowe Dam | Success Stories | Our Impact | Abu Dhabi Fund for...
    Recognized as one of the largest hydropower projects in Africa, the Merowe Dam constituted the government's most ambitious initiative to boost economic activity ...
  2. [2]
    Power plant profile: Merowe (Hamdab), Sudan - Power Technology
    Oct 21, 2024 · The hydro reservoir capacity is 8,300 million cubic meter. The net head of the project is 43m. The project generated 6,000 GWh of electricity.Missing: specifications | Show results with:specifications
  3. [3]
    [PDF] Displacement and resistance induced by the Merowe Dam - UEA
    Many of the displaced voluntarily initially accepted the Government of Sudan's compensation and resettlement plan, and a large fraction remains satisfied ...
  4. [4]
    Merowe Dam hydroelectric plant - Global Energy Monitor
    Apr 24, 2025 · Location, Coordinates (WGS 84). Merowe, Nile River Basin, Ash Shalal ar Rabia, Northern State, Sudan, 18.6689, 32.0503 (exact) ...Missing: geographical | Show results with:geographical
  5. [5]
    Astronaut Photo ISS025-E-6160 SUDAN
    Oct 5, 2010 · The Merowe Dam is located near the 4th cataract of the Nile River, in the Nubian Desert of the Republic of the Sudan (also known as Sudan). The ...Missing: coordinates | Show results with:coordinates
  6. [6]
    Merowe Dam, Sudan | The Corner House
    The Merowe/Hamadab hydroelectric and irrigation Dam on the River Nile in Sudan, the largest hydro project in Africa, was completed in 2009.
  7. [7]
    Why Sudan's RSF Militia Aim to Control 'Merowe' and Destroy Its ...
    Apr 8, 2025 · The dam was specifically designed to generate electricity and supply water, playing a crucial role in meeting Sudan's renewable energy needs.
  8. [8]
    [PDF] THE MEROWE DAM IN THE SUDAN
    May 3, 2005 · The purpose of the project is electric power generation (about 5,600 GWh/year), supply of water for irrigation and flood control.Missing: objectives | Show results with:objectives
  9. [9]
    The Merowe Dam and its Hydropower Plant in Sudan - ResearchGate
    Aug 6, 2025 · This project has been designed to serve several purposes, namely: the generation of electricity by the ten generating units of its 1250 MW ...Missing: primary | Show results with:primary
  10. [10]
    The Merowe Dam inauguration - ENRUC
    May 12, 2025 · The dam has an installed capacity of 1,250 MW and has doubled the country's electrical output, considerably reducing reliance on thermal power ...
  11. [11]
    [PDF] A Case Study of Merowe Dam, Sudan - PEARL
    Jun 12, 2020 · The main aims of the Merowe Dam and its supplementary projects were to support agricultural and non-agricultural economic development through ...Missing: specifications | Show results with:specifications
  12. [12]
    Merowe Dam (Supplementary Loan)
    Objectives: The project aims at meeting part of the increasing demand for electricity in Sudan as well as developing the northern regions of the country, ...Missing: primary | Show results with:primary
  13. [13]
    [PDF] A Case Study of Merowe Dam, Sudan - CentAUR
    Jun 12, 2020 · In the case of Merowe Dam, it can be argued that its main purpose was to generate electricity, provide irrigation, and stimulate other ...Missing: objectives | Show results with:objectives
  14. [14]
    [PDF] Hydropower Generation in Merowe Dam in response to Grand ...
    GERD reservoir capacity is estimated to be 74 Km3, with installed capacity of about 6000 Megawatts, while the installed capacity of MD is 1250 Megawatts; the ...Missing: primary | Show results with:primary
  15. [15]
    Merowe Dam (Merowe, 2009) - Structurae
    Merowe Dam is a rockfill dam and irrigation & industrial water dam that was built from 2004 until 2009. The project is located in Merowe, Sudan.
  16. [16]
    [PDF] Dams Merowe Sudan - Business & Human Rights Resource Centre
    The powerhouse is an open-air type with 10 Francis turbines of 125 MW capacity each with a discharge capacity of about 300 m3/s each.Missing: specifications | Show results with:specifications
  17. [17]
    [PPT] Merowe Dam: Setting of System & Engineering Design - MIT
    Dam of ~65 m height consist of: Concrete faced rockfill dam (right bank), ~4,800 m long; Rock and earthfill dam (left bank), ~4,000 m long ...
  18. [18]
    Merowe Dam Project - WEBAC-Chemie GmbH
    In 2000, the construction of the gigantic structure started which has a crest length of 9,280 m and a crest height of 67 m.Missing: specifications | Show results with:specifications<|separator|>
  19. [19]
    Merowe Dam Project - Züblin
    The Merowe Dam project involved waterproofing the dam by making core bores and injecting polyurethane resin and foam through them, while under water pressure.
  20. [20]
    [PDF] Simulation of River Bed Changes Upstream Merowe Dam
    Merowe Dam reservoir has a volume of 12.45 billion m3 at full supply level of 300.00 a.m.s.L. It worth mentioning that River Nile Basin has an area of 2.87.Missing: characteristics outflow
  21. [21]
    (PDF) Independent Review of the Environmental Impact Assessment ...
    The Environmental Impact Assessment Report (EIAR) for the Merowe Dam Project provided a detailed overview of the technical, hydraulic and hydrologic framework.
  22. [22]
    Water Levels in the Major Reservoirs of the Nile River Basin ... - MDPI
    Sep 19, 2022 · Since the dam operation started in 2009, the Merowe Reservoir has expanded to cover approximately 476 km2 surface area, and it can now hold up ...
  23. [23]
    (PDF) Case study Merowe/Hamdab Dam Project - Academia.edu
    Sedimentation rates in the reservoir may reach 10.5 cm/year, potentially losing dead storage capacity within 50 years according to evaluations. Figures (17).
  24. [24]
    political and ethical dimensions of the Merowe Dam Archaeological ...
    Behind this massive dam with a length of 9.3 km and a height of 67 m ... Merowe Dam, Sudan' (A. Askouri, andrn=1>. 13 September 2007) (available at ...Missing: specifications type
  25. [25]
    [PDF] Pre-feasibility Studies of Hydropower Projects - Nile Basin Initiative
    However, the construction of the Merowe dam, described in the following section, will reduce the sediment discharge in to High Aswan reservoir and slow the ...
  26. [26]
    Independent Review of the Environmental Impact Assessment for ...
    In summary, the Environmental Impact Assessment Report (EIAR) for the Merowe Dam Project provided a detailed overview of the technical, hydraulic and hydrologic ...
  27. [27]
    [PDF] The case of Merowe Dam - The Corner House
    The Merowe Dam will displace an estimated 50,000-78,000 people. The majority of the affected communities are from the Manasir tribe, including two sub-clans ...
  28. [28]
    [PDF] Merowe dam in northern Sudan: a case of populatin displacement ...
    May 6, 2013 · It uses the example of Merowe Dam; a large scale, multi-purpose dam built at the Fourth Cataract of the River Nile in Northern Sudan. The Dam is ...
  29. [29]
    China Eximbank provides $608 million loan for 1250 MW Merowe ...
    The 1250 MW Merowe Hydroelectric Power Plant Project was co-financed with: (1) $250 million from Arab Fund for Social and Economic Development (and possibly an ...
  30. [30]
    Merowe Dam: Pearl of Nile in Sudan
    Dec 24, 2007 · Despite a variety of formidable challenges encountered, the project was formally commenced by the end of November 2003. The construction of main ...Missing: initiation decisions
  31. [31]
    Marwi Dam | Projects - Abu Dhabi Fund for Development
    The Merowe Dam Project is one of the most important multi-purpose hydroelectric projects in Sudan. It has played a vital role in bridging the growing deficit ...
  32. [32]
    Merowe Dam - Daily Overview
    Merowe Dam. The Merowe Dam - built along the Nile River in Sudan - is ... surface area of the Nile increased roughly 270 square miles (699 square kilometers) ...
  33. [33]
    Merowe Dam, Sudan - Ej Atlas
    The capacity of the reservoir is 12.5 cubic kilometers, around 20 percent of the annual flow of the Nile. It produces 1.25 million kilowatts. The aerial ...Missing: installed production control
  34. [34]
    Sudan inaugurates 1,250-MW Merowe Dam
    Mar 4, 2009 · Sudan President Omar Hassan al-Bashir formally opened 1,250-MW Merowe Dam on the Nile River March 3, calling it the project of the century ...
  35. [35]
    The Inauguration of the Merowe Dam (Prologue) - Water, Civilisation ...
    On 30 June 1989, soldiers commanded by Brigadier Omar Al-Bashir suspended all civilian government activities and, in the subsequent hours and days, they ...
  36. [36]
    More power blackouts in Sudan starting Monday
    Oct 12, 2009 · Some observers have contended that Merowe dam was prematurely inaugurated for political reasons a day before the indictment of Sudanese ...
  37. [37]
    Sudanese development - International Water Power
    Sep 20, 2010 · However, in May 2010, Sudanese President, Omer Al-Bashir, inaugurated a fifth project. The Merowe hydropower station had swung into operation ...
  38. [38]
    Sudan: The Merowe/Hamadab Dam Project - SUDAN WATCH
    May 2, 2005 · The purpose of the Merowe Dam is to generate hydropower with an installed capacity of 1,250 megawatts. The project is expected to be ...
  39. [39]
    Kuwaiti fund extends $52.5 mln loan to finance phase 2 of Merowe ...
    The project is funded by the Kuwaiti Fund for Arab Development, the Arab Economic and Development Fund, the Saudi Development Fund, Abu Dhabi Fund for ...Missing: sources | Show results with:sources
  40. [40]
    The Merowe Dam: controversy and displacement in Sudan
    The idea of constructing a dam on the Fourth Cataract of the Nile, 350 km upstream from Khartoum, was first proposed by British authorities in the early 20th ...
  41. [41]
  42. [42]
    Damning indictment – DW – 05/19/2010
    May 19, 2010 · The area around the Merowe Dam is now cordoned off and Sudan's government has allegedly barred journalists from accessing the site.<|separator|>
  43. [43]
    Alstom selected for Merowe M&E package - MEED
    Paris-based Alstom Powerhas been selected for the estimated Eur 260 million ($299 million) mechanical and electrical (M&E) package on the Merowe hydroelectric ...
  44. [44]
    ABB Awarded Merowe Dam Power Contract By China's Harbin | MEES
    ABB signed a contract worth $16mn for a power transmission project relating to Sudans Merowe Dam hydroelectric scheme. The company won the contract from Chinas ...Missing: contractors | Show results with:contractors
  45. [45]
    ABB strengthens Sudan's power grid - ScienceDirect.com
    The company won the order from the main contractor Harbin Power Engineering Co Ltd of China. The Ministry of Irrigation and Water Resources Merowe Dam Project ...
  46. [46]
    Renewable Energy in Sudan: Current Status and Future Prospects
    Jan 21, 2025 · The construction of Merowe Dam has fulfilled several significant objectives, summarized as follows [83]: Generating 1250 MW of electricity. ...
  47. [47]
    Der Merowe-Staudamm und dessen Wasserkraftwerk im Sudan
    The successful grid-integration of the Merowe scheme marks a new era for Sudan's energy supply infrastructure. The 1 400 MVA hydropower plant forms the ...
  48. [48]
    Economic Contributions of Mega-Dam Infrastructure as Perceived by ...
    The main aims of the Merowe Dam and its supplementary projects were to support agricultural and non-agricultural economic development through electricity ...
  49. [49]
    The electricity crisis in Sudan | Transnational Institute
    Oct 14, 2022 · The initiative first targeted 100 users with a capacity of 100 watts per user (the aim is to reach a total capacity of 110 megawatts by 2031).
  50. [50]
    [PDF] A case study of Merowe Dam in Sudan - NAP Readiness Project
    Aug 10, 2025 · examines influences on agricultural production, specifically on increased productivity and agricultural infrastructure. Sections 5.4 ...
  51. [51]
    (PDF) Social Impacts of a Mega-Dam Project as Perceived by Local ...
    May 23, 2025 · Results show that Merowe Dam exerted positive as well as adverse social impacts on local communities. Increase in home sizes, opportunities for ...
  52. [52]
    Merowe Dam and Development in Northern Sudan | Pachodo.org
    It is obvious that the project is benefiting the Northern Sudanese only in term of well paid jobs and trade dividends. Does it mean there are no Southern ...Missing: employment | Show results with:employment
  53. [53]
    [PDF] ECCHR European Center for Constitutional and Human Rights
    In the criminal complaint, the defendants are charged with displacing over 4,700 families and destroying their livelihoods. 1.The Merowe Dam project and its ...
  54. [54]
    [PDF] Lethal Partnership - Wilson Center
    In August 2006, the houses and properties of 3000 families in Amri were flooded without warning. – The dam authority cordoned the area preventing the media and ...<|control11|><|separator|>
  55. [55]
    Social Impacts of a Mega-Dam Project as Perceived by Local ... - MDPI
    The paper assesses social impacts of a mega-dam project (Merowe Dam in Sudan) as perceived by host and affected communities (ie, upstream, downstream, and ...
  56. [56]
    The impact of Merowe Dam on Simulium hamedense vector of ...
    Apr 4, 2014 · Some of the negative impacts of hydropower include loss of vegetation, changes in riverine flow patterns and regimes, involuntary resettlement, ...
  57. [57]
    Water Balance Study and Validation of Reservoir ... - HRC-Sudan
    The objective of this study is to verify the accuracy of water balance components: inflows, evaporation losses,seepage into ground water, and outflow releases ...
  58. [58]
    The water balance for the Merowe Reservoir - ResearchGate
    Sudan has one large dam on the main stem Nile – the 1250 MW capacity, 67 m high Merowe Dam, located 800 km north of Khartoum near the fourth cataracts ...Missing: specifications | Show results with:specifications
  59. [59]
    Estimation of evaporation losses from water bodies in the Sudan ...
    Aug 8, 2025 · It is estimated that higher annual evaporation losses shall significantly occur, an increase from 4.80 to 9.13 Billion m³ (more than doubled); ...
  60. [60]
    [PDF] Review of the 2002 Environmental Impact Assessment ... - DORA 4RI
    Mar 23, 2006 · The main purpose of the 67 m high Merowe Dam is hydropower production. The capacity of 1'250 MW will be almost twice the current hydropower ...
  61. [61]
    Independent Review Reveals Serious Flaws in Sudan's Merowe Dam
    Mar 22, 2006 · The project violates Sudan's Environmental Protection Act and all internationally accepted environmental standards. The Merowe Dam could not be ...Missing: Hamdan | Show results with:Hamdan
  62. [62]
    SUDAN: No Clear Studies on Impacts of Merowe Dam - Global Issues
    Jan 2, 2012 · The Merowe Dam, which was completed in 2010, will affect the aquatic ecology of the Nile River in Sudan by blocking fish migration and degrading ...Missing: ecosystem | Show results with:ecosystem
  63. [63]
    [PDF] Health issues involving water can be broken into three categories
    Mar 8, 2004 · Health Impact of Merowe Dam. According to a health impact analysis ... Malaria Infosheet, Geneva: Roll Back Malaria, World Health.
  64. [64]
    The impact of Merowe Dam on Simulium hamedense vector of ...
    Apr 4, 2014 · The overall impact of Merowe Dam on Abu Hamed focus of onchocerciasis has been positive. The artificial reservoir of the Dam has submerged and ...
  65. [65]
    [PDF] Prevalence of Schistosoma haematobium among Schoolchildren in ...
    Merowe Locality free zone of schistosomiasis expect sporadic case after Nile rivers flood, so all the inhibitors have no awareness about the diseases and it is ...
  66. [66]
    Prevalence of Schistosoma haematobium among Schoolchildren in ...
    Apr 25, 2022 · After built up of Merowe Dams,. many areas, according to our results,. did not report positive cases. Table 1: Prevalence of S. haematobium ...
  67. [67]
    Journal of Science Medicine www.journalofscience.net MOSQUITO ...
    The dam is a hydroelectric and irrigation scheme that may probably develop climatic and environmental changes which might have profound impact on the vectors ...Missing: outbreak | Show results with:outbreak
  68. [68]
    The impact of large and small dams on malaria transmission in four ...
    Jun 25, 2021 · The annual number of malaria cases attributable to dams of either size across the four basins was 0.9–1.7 million depending on the year, of ...
  69. [69]
    [PDF] ARCHAEOLOGY BY THE FOURTH NILE CATARACT - Archaeopress
    From an archaeological perspective the building of this dam required surveys and rescue excava- tions over vast regions: • The construction area itself at the ...Missing: submerged | Show results with:submerged
  70. [70]
    Merowe Dam Archaeological Salvage Project
    A substantial collection of material is housed in the Sudan National Museum in Khartoum, with smaller collections in the Merowe Land Museum and in the Jebel ...Missing: submerged | Show results with:submerged
  71. [71]
    [PDF] The Merowe Dam Archaeological Salvage Project
    As elsewhere in the concession there is a vast number of sites spanning from the Palaeolithic up until the recent past across the whole area surveyed. Before ...
  72. [72]
    Letter from Sudan: The Gold of Kush - Archaeology Magazine Archive
    The construction of the Merowe Dam, some 25 miles downstream from where we were to work, was about to flood the Fourth Cataract, a 100-mile-long stretch of the ...
  73. [73]
    Three killed in Sudan protest over Nile dam
    Apr 23, 2006 · Three civilians were killed in violent clashes between Sudanese police and residents protesting the construction of a dam on the Nile river ...
  74. [74]
    Sudan Government Massacres Merowe Dam Affected People
    Apr 22, 2006 · On April 22, 2006, the militia of the Merowe Dam authorities, armed with machine guns and heavy artillery, attacked the affected people of Amri village.Missing: protests 2010
  75. [75]
    Dam protest leaves four dead in Sudan - Mongabay
    Jun 14, 2007 · June 14, 2007. Four people were killed and at least 10 wounded when police dispersed a group of dam protesters in Sudan, reports Sapa-AFP.Missing: 2006 | Show results with:2006
  76. [76]
    [PDF] sdn 301107.escr sudan - World Organisation Against Torture | OMCT
    Nov 30, 2007 · • 7 August 2006: the authorities closed the gates of the Merowe Dam without warning and more than 100 Amri families from the island of Kouk ...Missing: 2010 | Show results with:2010
  77. [77]
    Sudan's ex-PM hails government efforts in resolving Manasir standoff
    Jan 18, 2012 · ... compensation for their displacement that resulted from the construction of the Merowe dam. ... communities, Al Hamdab, Amri and Al-Manasir.
  78. [78]
    Northern Sudanese youth call for Merowe dam compensation
    Jun 30, 2017 · It doubled Sudan's electricity generation capacity but displaced more than 50,000 people, most of them of the El Manaseer tribe, from the Nile ...Missing: Amri Hamdab
  79. [79]
    Sudanese displaced by Merowe Dam demand compensation
    The displaced, most of them Manaseer tribesmen, have repeatedly submitted their claims to the authorities. Their main demand concerns the reconsideration of the ...Missing: Hamdab | Show results with:Hamdab
  80. [80]
    Becoming indigenous or being overcome ... - Taylor & Francis Online
    In the case of the Merowe Dam, it is estimated that around 60,000 people have been affected by the government's hydropower programmes, including loss of land, ...
  81. [81]
    Norms, Mobilization and Conflict: The Merowe Dam as a Case Study
    Jul 18, 2019 · The article uses the Merowe Dam in North Sudan as a case study. In addition to widespread displacement, the case presents an ongoing conflict ...
  82. [82]
    Controversy surrounds new dam that will displace 50,000
    Sep 8, 2006 · The Sudanese government has offered the affected families cash compensation for lost assets, a new house, land at resettlement sites and free ...
  83. [83]
    Court ruling angers those displaced by River Nile dam - ReliefWeb
    Jan 17, 2015 · Hundreds of people who were displaced by the building of the Merowe dam in River Nile state years ago protested a Court's decision to deny any compensation to ...
  84. [84]
    UN rights expert urges suspension to dam projects in northern Sudan
    Aug 28, 2007 · Mr. Kothari said work on the dams in the Merowe and Kajbar areas of the northern Nile Valley should be suspended until an independent assessment ...Missing: response | Show results with:response
  85. [85]
    UN expert urges Sudan to respect human rights of communities ...
    Aug 27, 2007 · Moreover, as opposition by the communities to the dams has grown, I have received numerous reports of violations of civil and political rights ...
  86. [86]
    Dam up the Nile to benefit poverty-stricken Sudanese - Sudan Tribune
    Jan 30, 2006 · The Merowe Dam will produce some 1,250 megawatts of electricity, and eight transmission lines with a combined length of 1,760 km will ...Missing: perspective | Show results with:perspective<|separator|>
  87. [87]
    [PDF] Dams, Islamist Modernity and Nationalist Politics in Sudan
    Jun 2, 2016 · At the inauguration of the Merowe Dam in March. 2009, the DIU ... Interview with DIU Director of Information, Khaled Othman, in Khartoum, June ...
  88. [88]
    [PDF] The New Great Walls | International Rivers
    The Merowe Dam only went ahead because Chinese and. Middle Eastern financial institutions agreed to finance it. China Exim. Bank was the project's main funder.
  89. [89]
    [PDF] The Impact of China-Africa Aid Relations: The Case of Sudan
    This brief examines the effectiveness of China-Africa aid relations, focusing on Sudan, where China became a key aid source after a drop in aid from ...<|separator|>
  90. [90]
    [PDF] Sudan and the Merowe/Hamadab Dam Project
    Apr 12, 2005 · The largest project under construction is the Merowe/Hamadab dam with a planned capacity of 1,250 megawatts. The government is currently ...
  91. [91]
    Chinese Development Finance and Strategies of Political ... - AidData
    May 8, 2013 · Instead, a substantial majority has been invested in power generation (such as the Merowe hydroelectric dam that was financed with a huge loan ...Missing: international | Show results with:international
  92. [92]
    Exporting dams: China's hydropower industry goes global
    But evidence from project sites such as the Merowe Dam in Sudan demonstrates that these dams have unrecognized social and environmental costs for host ...
  93. [93]
    Merowe Dam, Sudan - International Rivers Network
    The Merowe Dam is being financed by funders from China and Arabic countries. Chinese, Sudanese, German and French companies are participating in the project ...Missing: mechanisms | Show results with:mechanisms
  94. [94]
    China and the Sudans - MERIP
    The epitome of this cooperation was the controversial Merowe dam, even if that was never solely a Chinese project. First conflict in Darfur and then the ...<|separator|>
  95. [95]
    The environmental costs of the war in Sudan - CEOBS
    May 21, 2025 · Impacts include increased deforestation, agricultural decline, pollution from damaged industrial and energy infrastructure, de-energisation ...Missing: public | Show results with:public
  96. [96]
    Water Crisis in Omdurman Worsens Following Attack on Sudan's ...
    Jan 19, 2025 · The Merowe Dam, located 350 kilometers north of Khartoum, is a vital source of hydroelectric power for the region, and its incapacitation has ...
  97. [97]
    Sudan: Closed Consultations - Security Council Report
    Jan 30, 2025 · Recently, an attack on the Merowe Dam, Sudan's largest dam, severely disrupted water and electricity supply in Khartoum, Northern, and River ...<|separator|>
  98. [98]
    RSF drone attacks cause power outage in Sudan's Merowe
    Mar 1, 2025 · Merowe, a strategically important city that hosts a major dam and the 19th Infantry Division headquarters, has been repeatedly targeted by RSF ...
  99. [99]
    Africa File, April 10, 2025: The Rsf's Northern Sudan Campaign
    Apr 10, 2025 · [1] Roughly half of these attacks targeted the SAF-controlled Merowe Dam, Dongola Airport, and Atbara Airport.[2]. Figure 1. RSF Drone Attacks ...Missing: importance | Show results with:importance
  100. [100]
    Risk of continued drone strikes on Port Sudan - ReliefWeb
    May 23, 2025 · Between October 2024 and March 2025, meanwhile, the RSF launched 50 drone strikes on Merowe Dam, Dongola Airport, and Atbara Airport in SAF- ...
  101. [101]
    Arab League condemns attack in Sudan on Africa's largest ...
    The attack on the dam, the largest hydropower project in Africa, in the early hours of Monday morning caused power outages in several Sudanese cities, ...
  102. [102]
    SAF intercepts drones over strategic Merowe Dam - Sudans Post
    Jun 19, 2025 · The Sudanese Armed Forces (SAF) reported on Thursday morning that the strategic Merowe Dam in Northern State came under attack by several suicide drones.
  103. [103]
    Drone Warfare Over Sudan: The “Siege from the Air”
    Oct 14, 2025 · In January of this year, a series of drone attacks crippled Sudan's electricity grid, knocking out power in major army-held regions after drones ...